JPH0776820A - Improving method for ground of tunnel excavation part and periphery thereof - Google Patents

Improving method for ground of tunnel excavation part and periphery thereof

Info

Publication number
JPH0776820A
JPH0776820A JP22194893A JP22194893A JPH0776820A JP H0776820 A JPH0776820 A JP H0776820A JP 22194893 A JP22194893 A JP 22194893A JP 22194893 A JP22194893 A JP 22194893A JP H0776820 A JPH0776820 A JP H0776820A
Authority
JP
Japan
Prior art keywords
tunnel
injection
ground
excavated
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP22194893A
Other languages
Japanese (ja)
Other versions
JP2566521B2 (en
Inventor
Isao Iwata
功 岩田
Akira Kamiide
明 神出
Iwao Sagimori
巌 鷺森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Osaka Bousui Construction Co Ltd
Original Assignee
Osaka Bousui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Osaka Bousui Construction Co Ltd filed Critical Osaka Bousui Construction Co Ltd
Priority to JP5221948A priority Critical patent/JP2566521B2/en
Publication of JPH0776820A publication Critical patent/JPH0776820A/en
Application granted granted Critical
Publication of JP2566521B2 publication Critical patent/JP2566521B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

PURPOSE:To improve the peripheral ground of a tunnel with a short term of works by a method wherein a chemical injection method and timbering based on a lock bolt method are simultaneously executed. CONSTITUTION:A heading 3 is previously excavated and built below a tunnel 2 to be excavated. Outer pipes 11 for injection are driven from the interior of the heading 3 in a manner that the outer pipe is driven over the cross section of the tunnel 2 to be excavated an down to a given depth in a ground at the peripheral part thereof. By using an inner pipe for injection with a double packer introduced in the outer pipe 11 for injection, chemicals are injected. A high strength part 11A of the outer pipe 11 for injection is caused to remain in a drive position. Further, the high strength part 11A is formed of a high strength member, such as a steel pipe and reinforced plastic. A multistage anchor part is built at the high strength part 11A to improve anchoring ability.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はトンネル掘削部及びその
周辺地盤の改良工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for improving a tunnel excavation part and the ground around it.

【0002】[0002]

【従来技術とその問題点】従来、自立性の低い例えば未
固結の軟弱地盤においてトンネルを構築するに際して
は、通常、トンネル掘削に先行してトンネル断面並びに
その周辺部の地盤を薬液注入により固結し、トンネル掘
削時に本抗や切羽部が崩壊せぬように強化している。
2. Description of the Related Art Conventionally, when constructing a tunnel in soft ground that has low self-sustainability, such as unconsolidated soft ground, the tunnel cross section and the ground around the tunnel are usually solidified by chemical injection prior to tunnel excavation. It is tied up and strengthened so that the main fence and the face part do not collapse during tunnel excavation.

【0003】またトンネル掘進中は、トンネルの掘削と
同時並行して掘削により新たに生じた坑壁を支保し、空
洞空間を確保している。従来、このような薬液注入工及
び支保工は個別作業によって行なわれているが、之等の
作業には多大の人手と時間を要し、工期延長,工費高騰
の原因になっていた。さらにトンネル掘進により新たに
生じた坑壁の周辺部の地盤は薬液注入により固結強化さ
れているとはいえ、薬液注入による地盤改良の効果には
限界があるので、坑壁の支保作業時に懸念される坑壁崩
壊防止対策としては万全なものでなく、より一層の改良
が望まれていた。
During the tunnel excavation, simultaneously with the excavation of the tunnel, a pit wall newly created by the excavation is supported to secure a hollow space. Conventionally, such chemical solution injecting work and supporting work have been performed by individual work, but these works require a great deal of manpower and time, which causes the extension of the work period and the rise of the construction cost. Furthermore, although the ground around the mine wall newly created by tunnel excavation has been consolidated and strengthened by chemical injection, there is a limit to the effect of ground improvement by chemical injection, so there is concern when supporting the pit wall. As a measure to prevent collapse of the mine wall, it is not perfect, and further improvement has been desired.

【0004】本発明はこのような従来の問題点を一掃す
ることを目的としてなされたものである。
The present invention has been made for the purpose of eliminating such conventional problems.

【0005】[0005]

【問題点を解決するための手段】本発明は、掘削すべき
トンネルと略々平行するように予め掘削形成された導坑
内よりトンネル掘削部及びその周辺地盤の改良を行なう
工法であって、上記導坑内から掘削すべきトンネルの断
面を超えてその周辺部の地盤内の所定深度に達するよう
に建込まれる注入用外管と、該外管内に挿入されるダブ
ルパッカー付注入用内管とを用いて薬液注入する工程を
含み、薬液注入後、建込み位置に残置される注入用外管
のうち、トンネル断面より外側の周辺地盤内に残置され
る部分は、鋼管,強化プラスチックなどのような高強度
材から構成され、高強度材構成部分には、残置位置での
定着性を高めるためのアンカー部が管軸方向に多段的に
形成されていることを特徴とするトンネル掘削部及びそ
の周辺地盤の改良工法に係る。
The present invention is a method for improving a tunnel excavation portion and the ground around it from the inside of a tunnel that has been excavated and formed substantially parallel to the tunnel to be excavated. An injection outer pipe built so as to reach a predetermined depth in the ground around the tunnel beyond the cross section of the tunnel to be excavated from the tunnel, and an injection inner pipe with a double packer inserted into the outer pipe. Including the step of injecting a chemical solution using the above, after injection of the chemical solution, the portion of the injection outer pipe left at the built-in position that is left in the surrounding ground outside the tunnel cross section is made of steel pipe, reinforced plastic, etc. A tunnel excavation part and its surroundings, which is composed of high-strength material, and in which the anchor part for enhancing the fixing property at the remaining position is formed in multiple stages in the pipe axis direction in the high-strength material constituent part. Ground improvement According to the law.

【0006】[0006]

【実施例】以下に本発明工法の実施例を添付図面にもと
づき説明すると、次の通りである。
Embodiments of the method of the present invention will be described below with reference to the accompanying drawings.

【0007】本発明工法の実施に際しては、図1に示す
ように先ず最初に自立性の低い例えば未固結の軟弱地盤
1内に、構築しようとする仮想トンネル2の下方近傍、
好ましくはその下辺中点の下方に、トンネルと平行に長
さ方向に延出する導坑3が掘削形成される。
In carrying out the method of the present invention, as shown in FIG. 1, first, in the vicinity of the lower part of the virtual tunnel 2 to be constructed, in the unconsolidated soft ground 1 having low self-sustainability,
Preferably, below the midpoint of the lower side thereof, a tunnel 3 extending in the longitudinal direction in parallel with the tunnel is excavated.

【0008】導坑3はトンネル掘削部の地盤改良を行な
うに際し作業坑として利用され、通常2〜5m程度の口
径を有している。図2に導坑3の掘削形成状況が示さ
れ、例えばシードル式掘削機4の掘進につれセグメント
5を順次継足して行くことにより、立坑6,6間に導坑
3を掘削形成できる。
The guide pit 3 is used as a working pit when performing ground improvement in a tunnel excavation portion, and usually has a diameter of about 2 to 5 m. FIG. 2 shows the excavation formation state of the guide shaft 3, and for example, the guide shaft 3 can be excavated and formed between the vertical shafts 6 and 6 by successively adding the segments 5 as the cider type excavator 4 advances.

【0009】図3は導坑3を作業坑として利用し、本発
明工法に従い地盤改良を行なった後の状況を示してい
る。参照符号aは本発明工法を適用して形成した1つの
地盤改良部を示し、地盤改良部aはトンネル断面方向と
トンネル長さ方向の全域を地盤改良するために、両方向
に適宜のピッチで繰返し形成される。
FIG. 3 shows a situation after the guide shaft 3 is used as a work shaft and the ground is improved according to the method of the present invention. Reference numeral a indicates one ground improvement portion formed by applying the method of the present invention. The ground improvement portion a is repeatedly formed in both directions at an appropriate pitch in order to improve the entire area in the tunnel cross-section direction and the tunnel length direction. It is formed.

【0010】地盤改良部aの形成状況を、図面を参照し
つつ工程順に説明すると、次の通りである。
The formation condition of the ground improvement portion a will be described in the order of steps with reference to the drawings as follows.

【0011】図4は削孔形成時の状況を示し、削孔形成
は、ケーシングチューブ7を用いて行なわれる。ケーシ
ングチューブ7は、導坑3内から口元止水ボックス8を
通じ地盤1中に、該チューブ7の先端から噴出される削
孔水の削孔案内のもとに挿入され、削孔により生ずる泥
水は上記ケーシング7の外側を通り、口元止水ボックス
8に備えた開閉バルブ9を経て導坑3内の適所に排出さ
れる。削孔形成のためのケーシングチューブ7の挿入は
導坑3内で継足しながら行なわれ、例えば図3に示すよ
うに仮想トンネル2の断面を超えて、その周辺部の地盤
1a内の所定深度に達した時点で終了する。
FIG. 4 shows a situation when forming a hole, and the hole is formed by using the casing tube 7. The casing tube 7 is inserted from the inside of the tunnel 3 into the ground 1 through the mouth water stop box 8 under the guide of the drilling water ejected from the tip of the tube 7, and the muddy water generated by the drilling is removed. It passes through the outside of the casing 7 and is discharged to an appropriate place in the tunnel 3 through the opening / closing valve 9 provided in the mouth water-stop box 8. The insertion of the casing tube 7 for forming the hole is performed while being added in the tunnel 3, and, for example, as shown in FIG. 3, the casing tube 7 is crossed over the cross section of the virtual tunnel 2 to a predetermined depth in the ground 1a in the peripheral portion. When it reaches the end.

【0012】削孔10の形成を終えた後は、図5に示す
ように削孔10内への注入用外管11の建込みが行なわ
れる。
After the formation of the drilled hole 10, the injection outer pipe 11 is built in the drilled hole 10 as shown in FIG.

【0013】注入用外管11は下記に述べるダブルパッ
カー付注入用内管と協同して薬液注入による地盤改良を
行なうためのものであり、管長さの方向に適宜の間隔を
存して多段的に多数の逆止弁環12付注入口13(図9
参照)を備えられいる。本発明工法において用いる外管
11は、これをロックボルトとして兼用するために、図
3において、トンネル断面を超えてその周辺部の地盤1
a内に挿入設置される部分1Aは、高強度材例えば鋼製
又は強化プラスチック製のパイプ材の継足しにより構成
されている。さらに高強度材構成部分1Aの外周部に
は、定着性を高めるために、管軸方向に多段的にアンカ
ー部15が設けられている。
The outer pipe 11 for injection is for improving the ground by injecting a chemical solution in cooperation with an inner pipe for injection with a double packer described below, and has a multi-stage structure with an appropriate interval in the direction of the pipe length. Inlet 13 with a large number of check valve rings 12 (see FIG. 9).
(See). Since the outer pipe 11 used in the method of the present invention also serves as a lock bolt, the outer pipe 11 in FIG.
The portion 1A inserted and installed in a is formed by adding a high-strength material such as a pipe material made of steel or reinforced plastic. Further, anchor portions 15 are provided on the outer peripheral portion of the high-strength material constituting portion 1A in multiple stages in the tube axis direction in order to enhance the fixing property.

【0014】図9にアンカー部15の詳細が示され、各
段のアンカー部15は上端の取付け固定部15aから下
方に向けて斜めに張出された線状又は板片状のバネ部材
から構成され、その張出し巾は、削孔10の孔径を少し
超えるような寸法に設定されている。アンカー部15は
各段において、管回りの方向に複数個所、例えば4個所
に90゜の間隔で設置されている。外管11の先端は閉
塞され、閉塞部の先端に復元バネ(図示せず)に抗し拡
縮自在な2枚の翼部材15a´,15a´からなる逆止
形状の補助アンカー部15´が備えられている。補助ア
ンカー部15´は主として外管11の落下防止部材とし
て機能する。
FIG. 9 shows the details of the anchor portion 15, and the anchor portions 15 at each step are composed of a linear or plate-shaped spring member that is obliquely extended downward from the attachment fixing portion 15a at the upper end. The overhang width is set to a dimension that slightly exceeds the hole diameter of the drilled hole 10. In each stage, the anchor portions 15 are installed at a plurality of positions, for example, four positions in the direction around the pipe, at intervals of 90 °. The tip of the outer tube 11 is closed, and the tip of the closed portion is provided with a non-return-shaped auxiliary anchor portion 15 'composed of two wing members 15a', 15a 'that can expand and contract against a restoring spring (not shown). Has been. The auxiliary anchor portion 15 ′ mainly functions as a fall prevention member for the outer tube 11.

【0015】上記構成の外管11は、導坑3(図3参
照)内で先端側のものから順次継ぎ足されながらケーシ
ングチューブ7内に基端側から先端に向け挿入されて行
き、ケーシング7内の通過中は、アンカー部材15及び
15´はチューブ内壁に拘束されて、保有バネ及び復元
バネに抗し縮小状態を保持し、通過できる。この挿入で
外管11の先端がケーシングチューブ7を通過すると、
図5に示すように補助アンカー部材15´はチューブ内
壁の拘束から解放され、復元バネの働きで当初の拡張状
態に自動復元し、削孔10の孔壁10aに係止し、外管
11を建込み位置に拘束し、落下を防止する。外管11
の建込みを終えた後は、図6に示すようにケーシングチ
ューブ7が削孔10の口元部近くまで抜き出される。こ
のチューブ7の抜き出しで外管11に備えられている各
段のアンカー部15は、ケーシングチューブ内壁の拘束
から解放され、保有バネの働きで当初の拡張状態に自動
復元し、それぞれ削孔10の孔壁10aに係止し、外管
11、特に高強度材構成部分11Aの定着性を高める。
ケーシングチューブ7の削孔口元部までの抜き出しを終
了した後は、該チューブ7と外管11間の隙間をプラグ
14により口元部で閉じた後に、例えば開閉バルブ9を
通じ、削孔10内にシールグラウト16が注入充填され
る。このシールグラウト16の充填は下記の注入用内管
を用いて行なってもよい。
The outer tube 11 having the above-described structure is inserted into the casing tube 7 from the base end side toward the tip end while being sequentially added from the tip end side inside the tunnel 3 (see FIG. 3). During the passage, the anchor members 15 and 15 'are constrained by the inner wall of the tube and can pass while retaining the contracted state against the retaining spring and the restoring spring. With this insertion, when the tip of the outer tube 11 passes through the casing tube 7,
As shown in FIG. 5, the auxiliary anchor member 15 ′ is released from the constraint on the inner wall of the tube, is automatically restored to the original expanded state by the action of the restoring spring, is locked to the hole wall 10 a of the drilled hole 10, and fixes the outer tube 11 to the outer tube 11. It is restrained at the built-in position to prevent it from falling. Outer tube 11
After the completion of the construction, the casing tube 7 is pulled out to near the mouth of the drilled hole 10 as shown in FIG. When the tube 7 is pulled out, the anchor portions 15 of each step provided on the outer tube 11 are released from the constraint on the inner wall of the casing tube, and the retained spring automatically restores the initial expanded state, and the holes 10 of the drilled holes 10 respectively. It is locked to the hole wall 10a to enhance the fixing property of the outer tube 11, particularly the high-strength material constituting portion 11A.
After the casing tube 7 has been extracted to the hole-drilling hole, the gap between the tube 7 and the outer tube 11 is closed by the plug 14 at the hole, and then sealed in the hole-drilling hole 10 through, for example, the opening / closing valve 9. The grout 16 is injected and filled. The filling of the seal grout 16 may be performed by using the following inner tube for injection.

【0016】削孔15内への外管11の建込み並びにシ
ールグラウト16の注入充填を終えた後は、シールグラ
ウト16の養生固化を持って、薬液注入による地盤改良
が行なわれる。薬液注入による地盤改良工程において
は、図7に示すようにダブルパッカー17,17と該パ
ッカー17,17間に射出口(図示ぜす)を備えた注入
用内管18が導坑3内で継ぎ出されながら外管11内に
挿入され、次いで常法に従いダブルパッカー17,17
と逆止弁環12付注入口13(図9参照)との協同のも
とに、各段の逆止弁環12付注入口13ごとに薬液注入
による地盤改良が行なわれる。
After the outer tube 11 has been built in the drilled hole 15 and the seal grout 16 has been injected and filled, the ground is improved by injecting a chemical solution while curing and solidifying the seal grout 16. In the ground improvement process by chemical injection, as shown in FIG. 7, double packers 17 and an injection inner pipe 18 having an injection port (shown in the figure) between the packers 17 and 17 are spliced in the tunnel 3. While being taken out, it is inserted into the outer pipe 11, and then double packers 17 and 17 are manufactured in accordance with a conventional method.
In cooperation with the injection port 13 with check valve ring 12 (see FIG. 9), ground improvement is performed by injecting a chemical solution for each injection port 13 with check valve ring 12 at each stage.

【0017】この状態が図7,8に示されている。This state is shown in FIGS.

【0018】図4〜8に示す工程を順次経ることにより
地盤改良工程の1サイクルが終了し、図3に示すように
1つの地盤改良部aが得られる。
One cycle of the ground improvement step is completed by sequentially passing through the steps shown in FIGS. 4 to 8, and one ground improvement portion a is obtained as shown in FIG.

【0019】而して、このような地盤改良工程の1サイ
クルをトンネル断面方向とトンネル長さ方向とに適宜の
ピッチで繰り返し行ない、両方向に連続されることによ
り、トンネル断面方向とトンネル長さ方向の全域を地盤
改良することができる。本発明工法において得られた地
盤改良部aは、図3に示すように薬液注入により補強さ
れた固結地盤部a1 と、該固結地盤部a1 の中心に貫入
する外管11とを含んでいる。
Thus, one cycle of such ground improvement process is repeated at an appropriate pitch in the tunnel cross-section direction and the tunnel length direction, and is continued in both directions, whereby the tunnel cross-section direction and the tunnel length direction are obtained. The whole area of can be improved. The ground improvement portion a obtained by the method of the present invention includes a solid ground portion a 1 reinforced by chemical injection as shown in FIG. 3, and an outer pipe 11 penetrating into the center of the solid ground portion a 1. Contains.

【0020】外管11のうち、高強度材から構成された
部分11Aは、図3に示すようにトンネル掘削後におい
て、その周辺部の地盤1a内に残る部分であり、この高
強度材構成部分1Aは、その外周部に多段的に形成れさ
たアンカー部15(図9参照)…により、基端方向への
引抜き抵抗が強化され、定着性が高められている。
A portion 11A made of a high-strength material in the outer pipe 11 is a portion which remains in the ground 1a around the periphery of the outer pipe 11 after excavation of the tunnel as shown in FIG. 1A has anchoring portions 15 (see FIG. 9) formed in multi-steps on the outer peripheral portion thereof, so that pullout resistance in the proximal direction is enhanced and fixing property is enhanced.

【0021】その結果、トンネル掘削後、その周辺部の
地盤1a内に残る外管11の高強度材構成部分11A
は、その高強度と、強化された引抜き抵抗力ひいては定
着性とにより、支保坑の1つとしてよく知られているロ
ックボルト工法におけるロックボルトと同じ働きをする
ことが可能になる。
As a result, after the tunnel is excavated, the high-strength material constituting portion 11A of the outer pipe 11 remaining in the ground 1a around the tunnel is excavated.
Due to its high strength and enhanced pull-out resistance and thus anchorage, it is possible to act like a lock bolt in the lock bolt construction method well known as one of the shafts.

【0022】よって本発明工法においては薬液注入工と
ロックボルト工法における支保工とを同時に施工するこ
とができる。
Therefore, in the method of the present invention, the chemical solution injecting process and the supporting work in the rock bolt process can be performed at the same time.

【0023】本発明工法に従いトンネル掘削部の地盤改
良を終えた後は、図3に示す仮想トンネル2の部分が常
法に従い掘削される。
After the ground improvement of the tunnel excavation portion is completed according to the method of the present invention, the portion of the virtual tunnel 2 shown in FIG. 3 is excavated according to the ordinary method.

【0024】トンネル掘削時の掘削性を考慮し、外管1
1のうち仮想トンネル2の領域を貫通する部分は塩化ビ
ニル樹脂などの実質的に掘削に障害となることのない材
質のものを用いることが好ましい。
Considering the excavability during tunnel excavation, the outer pipe 1
It is preferable to use a material such as vinyl chloride resin, which does not substantially hinder excavation, for the portion of the first portion which penetrates the region of the virtual tunnel 2.

【0025】従来一般にトンネルの掘進中は、トンネル
の掘進と同時並行して、掘削により新たに生じた坑壁の
崩壊を防止するために支保工が実施されるが、本発明工
法では、ロックボルト工による支保工を既に終えている
ので、新たな支保工は省略できるか又は少なくとも簡略
化することが可能になる。また支保工がトンネル掘進よ
りも先行しているので、トンネル掘削後に初めて支保工
を実施する場合に比べ、作業の安全性を向上し得る。
Generally, during the tunnel excavation, while the tunnel excavation is being carried out, in parallel with the tunnel excavation, support work is carried out in order to prevent collapse of the new pit wall caused by excavation. Since the support work has already been completed, new support work can be omitted or at least simplified. Further, since the support work precedes the tunnel excavation, the work safety can be improved as compared with the case where the support work is carried out only after the tunnel excavation.

【0026】図10に本発明工法の他の実施の一例が示
され、本実施例においては、高強度材構成部分11Aに
多段的備えられている各段の逆止弁環12には、外側方
へ突出する断面三角状のリング突部からなるアンカー部
151が一体に備えられている。上記アンカー部151
はシールグラウト16の層に喰い込みアンカー部として
機能し得るような構成になっている。アンカー部151
としてのリング突部を備える逆止弁環12は例えば硬質
ゴム製であって、上下巾の中間位置において左右巾方向
に延出する切目開口12aを備え、該切目開口12a
は、通常は閉状態を保持し、注入口13から注入圧を受
けると保有弾性に抗し開き、注入を可能する。
FIG. 10 shows an example of another embodiment of the method of the present invention. In this embodiment, the check valve ring 12 at each stage provided in the high-strength material component portion 11A in multiple stages has an outer side. An anchor portion 151 formed of a ring protrusion having a triangular cross-section protruding in one direction is integrally provided. The anchor 151
Has a structure capable of functioning as an anchor portion that bites into the layer of the seal grout 16. Anchor part 151
The check valve ring 12 including the ring protrusion is made of, for example, hard rubber, and has a cut opening 12a extending in the left-right width direction at an intermediate position of the vertical width.
Normally keeps the closed state, and when receiving the injection pressure from the injection port 13, opens against the retained elasticity and enables injection.

【0027】本実施例においては、逆止弁環12へのリ
ング突部ひいてはアンカー部151の形成で、アンカー
部151の外周部分では、シールグラウト16の層厚み
が小さくなる。従ってシールグラウト16として比較的
高強度のもの、例えばセメントの含有量の多いセメント
ベントナイト(混合重量比10〜50対1)を用いた場
合であっても薬液注入時の注入圧によりシールグラウト
層の割裂を行うことが可能になる。
In the present embodiment, the ring protrusion and the anchor 151 are formed on the check valve ring 12, and the layer thickness of the seal grout 16 is reduced at the outer peripheral portion of the anchor 151. Therefore, even when the seal grout 16 has relatively high strength, for example, cement bentonite having a high cement content (mixing weight ratio 10 to 50: 1), the seal grout layer is formed by the injection pressure at the time of injecting the chemical liquid. It becomes possible to split.

【0028】このようにシールグラウトとして高強度の
ものを用いると、高強度シールグラウト層へのアンカー
部151の係止が一層強固なものとなり、定着性をより
一層高めることができる。さらなる定着性の強化を計る
ために、高強度材構成部分11Aの外周面に突起物19
を設け、該突起物19をシールグラウト層に係止するよ
うな構成にしてもよい。
When a high-strength seal grout is used as described above, the anchor portion 151 is more firmly locked to the high-strength seal grout layer, and the fixing property can be further enhanced. In order to further enhance the fixing property, a protrusion 19 is formed on the outer peripheral surface of the high-strength material component portion 11A.
May be provided, and the protrusion 19 may be locked to the seal grout layer.

【0029】その他の構成は、先の実施例のもとの実質
的に異なる所がない。本発明工法に於ては、図11に示
すように薬液注入を終えた後、外管内に内管に代えロッ
クボルト20を挿入設置し、この挿入設置状態におい
て、ロックボルト20の周りの間隔21内に注入充填さ
れる高強度結合材22例えばセメントシルクを用いて結
合一体化することができる。このような構成にすること
により、スリーブパイプ11のうち、高強度材構成部分
11Aのより一層の強度の強化を計ることができる。こ
の場合、トンネル掘削時の掘削性を考慮し、仮想トンネ
ル2(図3参照)内を貫通する部分はプラスチック製と
することが好ましい。
Other configurations are substantially the same as those of the previous embodiment. In the method of the present invention, as shown in FIG. 11, after the injection of the chemical solution is completed, the lock bolt 20 is inserted and installed in the outer tube in place of the inner tube. A high strength bond 22, such as cement silk, can be used to bond and integrate. With such a configuration, the strength of the high-strength material constituting portion 11A of the sleeve pipe 11 can be further strengthened. In this case, it is preferable that the portion penetrating the inside of the virtual tunnel 2 (see FIG. 3) is made of plastic in consideration of excavation properties when excavating the tunnel.

【0030】本発明工法において、導坑3の形成位置
は、図3に示す仮想トンネル2の下方近傍加え、図12
〜14に示すようにトンネル2内であってもよい。
In the method of the present invention, the formation position of the tunnel 3 is in addition to the lower portion of the virtual tunnel 2 shown in FIG.
It may be in the tunnel 2 as shown in FIGS.

【0031】[0031]

【発明の効果】本発明工法によれば、トンネルの掘削に
先行して、薬液注入工とロックボルト工法にもとづく支
保工とを同時に施工できるので、之等を個別に行なう場
合に比べ、人手と時間を削減することができ、工期の短
縮と工費の節減を同時に計ることができる。さらにトン
ネルの掘削に先行して支保工が施工されるので、トンネ
ル掘削後に初めて支保工を実施する場合に比べ作業の安
定性を向上できる。
According to the method of the present invention, prior to excavation of the tunnel, the chemical solution injection work and the support work based on the rock bolt construction method can be carried out at the same time. The time can be reduced, and the construction period and the construction cost can be reduced at the same time. Further, since the support work is performed prior to the excavation of the tunnel, the stability of the work can be improved as compared with the case where the support work is performed for the first time after the tunnel excavation.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明工法における導坑の形成位置を概略的に
示す説明図である。
FIG. 1 is an explanatory view schematically showing the formation position of a tunnel in the method of the present invention.

【図2】同導坑の形成位置を概略的に示す説明図であ
る。
FIG. 2 is an explanatory view schematically showing a formation position of the tunnel.

【図3】本発明工法における地盤改良状況を概略的に示
す全体図である。
FIG. 3 is an overall view schematically showing a ground improvement situation in the method of the present invention.

【図4】本発明工法における削孔状況を概略的に示す説
明図である。
FIG. 4 is an explanatory view schematically showing a drilling situation in the method of the present invention.

【図5】同、注入用外管の建込み途中の状況を概略的に
示す説明図である。
FIG. 5 is an explanatory view schematically showing a situation in the process of building the outer injection pipe.

【図6】同、注入用外管の建込み後、シールグラウトの
注入充填を行なっている状況を概略的に示す説明図であ
る。
FIG. 6 is an explanatory view schematically showing a situation in which the seal grout is injected and filled after the outer tube for injection is built.

【図7】同、薬液注入開始時の状況を概略的に示す説明
図である。
FIG. 7 is an explanatory diagram schematically showing a situation at the start of injecting a chemical liquid.

【図8】同、終了時の状況を概略的に示す説明図であ
る。
FIG. 8 is an explanatory diagram schematically showing a situation at the end.

【図9】本発明工法に適用される注入用外管の高強度材
構成部分の拡大詳細図である。
FIG. 9 is an enlarged detailed view of a high-strength material constituting portion of the injection outer tube applied to the method of the present invention.

【図10】本発明工法の他の実施の一例を示す図9に対
応する図である。
FIG. 10 is a view corresponding to FIG. 9 showing another example of the method of the present invention.

【図11】本発明工法のさらに他の実施の一例を示す図
9に対応する図である。
FIG. 11 is a view corresponding to FIG. 9 showing still another embodiment of the method of the present invention.

【図12】本発明工法における、導坑の形成位置の変更
例を示す説明図である。
FIG. 12 is an explanatory diagram showing an example of changing the formation position of the tunnel in the method of the present invention.

【図13】さらに他の変更例を示す説明図である。FIG. 13 is an explanatory diagram showing still another modification example.

【図14】さらに他の変更例を示す説明図である。FIG. 14 is an explanatory diagram showing still another modification example.

【符号の説明】[Explanation of symbols]

1 軟弱地盤 2 仮想トンネル 3 導坑 4 シードル式掘削機 5 セグメント 6 立坑 7 ケーシングチューブ 8 口元止水ボックス 9 開閉バルブ 10 削孔 11 注入用外管 12 逆止弁環 13 注入口 14 プラグ 15 アンカー部 16 シールグラウト 17 ダブルパッカー 18 注入用内管 19 突起物 20 ロックボルト 21 隙間 22 高強度定着材 DESCRIPTION OF SYMBOLS 1 Soft ground 2 Virtual tunnel 3 Guide shaft 4 Cider type excavator 5 Segment 6 Vertical shaft 7 Casing tube 8 Port water stop box 9 Open / close valve 10 Drilling hole 11 Injection outer pipe 12 Check valve ring 13 Pouring port 14 Plug 15 Anchor part 16 Seal grout 17 Double packer 18 Inner tube for injection 19 Protrusion 20 Lock bolt 21 Gap 22 High strength fixing material

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 掘削すべきトンネルと略々平行するよう
に予め掘削形成された導坑内よりトンネル掘削部及びそ
の周辺地盤の改良を行なう工法であって、上記導坑内か
ら掘削すべきトンネルの断面を超えてその周辺部の地盤
内の所定深度に達するように建込まれる注入用外管と、
該外管内に挿入されるダブルパッカー付注入用内管とを
用いて薬液注入する工程を含み、薬液注入後、建込み位
置に残置される注入用外管のうち、トンネル断面より外
側の周辺地盤内に残置される部分は、鋼管,強化プラス
チックなどのような高強度材から構成され、高強度材構
成部分には、残置位置での定着性を高めるためのアンカ
ー部が管軸方向に多段的に形成されていることを特徴と
するトンネル掘削部及びその周辺地盤の改良工法。
1. A method for improving a tunnel excavation part and surrounding ground from a tunnel formed beforehand so as to be substantially parallel to a tunnel to be excavated, the cross section of the tunnel to be excavated from the tunnel. An outer pipe for injection that is built so as to reach a predetermined depth in the ground of the surrounding area,
Including a step of injecting a chemical solution using an inner tube for injection with a double packer inserted into the outer tube, of the outer tube for injection remaining at the built-in position after injecting the chemical solution, the surrounding ground outside the tunnel cross section. The part left inside is made of high-strength material such as steel pipe and reinforced plastic. The high-strength material part has multi-stage anchors to enhance the anchorage at the left position. The method for improving the tunnel excavation part and the ground around it is characterized by being formed on the ground.
JP5221948A 1993-09-07 1993-09-07 Tunnel excavation and surrounding ground improvement method Expired - Fee Related JP2566521B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5221948A JP2566521B2 (en) 1993-09-07 1993-09-07 Tunnel excavation and surrounding ground improvement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5221948A JP2566521B2 (en) 1993-09-07 1993-09-07 Tunnel excavation and surrounding ground improvement method

Publications (2)

Publication Number Publication Date
JPH0776820A true JPH0776820A (en) 1995-03-20
JP2566521B2 JP2566521B2 (en) 1996-12-25

Family

ID=16774670

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5221948A Expired - Fee Related JP2566521B2 (en) 1993-09-07 1993-09-07 Tunnel excavation and surrounding ground improvement method

Country Status (1)

Country Link
JP (1) JP2566521B2 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6215359U (en) * 1985-07-12 1987-01-29
JPS6241899A (en) * 1986-08-20 1987-02-23 鉄建建設株式会社 Method of fixing construction of tubular lock bolt
JPH01131715A (en) * 1987-11-16 1989-05-24 Osaka Bosui Constr Co Ltd Ground improving work by horizontal injection of chemical grout
JPH03267493A (en) * 1990-03-16 1991-11-28 Shimizu Corp Auxiliary method in tunnel construction
JP3011900U (en) * 1994-11-09 1995-06-06 好三 山野辺 Skipping rope
JP3021500U (en) * 1995-08-09 1996-02-20 株式会社桂 Door lock forget prevention device
JP3036024U (en) * 1995-09-12 1997-04-08 セキコン カング Shaft cell for golf bag

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6215359U (en) * 1985-07-12 1987-01-29
JPS6241899A (en) * 1986-08-20 1987-02-23 鉄建建設株式会社 Method of fixing construction of tubular lock bolt
JPH01131715A (en) * 1987-11-16 1989-05-24 Osaka Bosui Constr Co Ltd Ground improving work by horizontal injection of chemical grout
JPH03267493A (en) * 1990-03-16 1991-11-28 Shimizu Corp Auxiliary method in tunnel construction
JP3011900U (en) * 1994-11-09 1995-06-06 好三 山野辺 Skipping rope
JP3021500U (en) * 1995-08-09 1996-02-20 株式会社桂 Door lock forget prevention device
JP3036024U (en) * 1995-09-12 1997-04-08 セキコン カング Shaft cell for golf bag

Also Published As

Publication number Publication date
JP2566521B2 (en) 1996-12-25

Similar Documents

Publication Publication Date Title
KR101070072B1 (en) A multistaged equipment of pipe grouting by double packer system and its construction
KR100978006B1 (en) Soil nailing method
JP2004027813A (en) Packer for pressure type soil nailing and method of soil nailing using it
CN108678772A (en) A kind of multilevel hierarchy suspension device and its construction method for rich water sandy gravel stratum tunnel
KR100437910B1 (en) grouting apparatus for earth anchor using compound packer and earth anchor construction method using the same
KR200352267Y1 (en) Slope-reinforcing structure for soil nailing having function of drainage
KR100557010B1 (en) Earth anchor including a duplex grouting pipe and the earth anchor construction method using the same
KR100576053B1 (en) Soil nailing by extended packer grouting and construction method
KR101488721B1 (en) Construction method for extending bulb of the ground anchor by post grouting and bulb extending apparatus being used for the same
CN208502786U (en) Multilevel hierarchy suspension device for rich water sandy gravel stratum tunnel
KR100576789B1 (en) Multistage grouting apparatus and method using casing and packer
CN110144904A (en) It is a kind of to face upward inclined discharge structure and its construction method with anchoring function certainly
KR100823980B1 (en) Drain combination paker type pressurization grouting equipment and the upward method using the same
KR200381572Y1 (en) Paker can pressure with milk grouting
JPH08226119A (en) Packer and natural ground consolidation method using the packer
JP2002167746A (en) Ground reinforcing construction method and hole wall holding casing pipe used therefor
Bruce et al. The MPSP system: a new method of grouting difficult rock formations
JP2566521B2 (en) Tunnel excavation and surrounding ground improvement method
KR200337877Y1 (en) Pressure-type grouting apparatus for reinforcing the ground
KR100710866B1 (en) Pressure Grouting Method using Milk Grouting and Paker
JP2721950B2 (en) Ground improvement method for tunnel excavation and surrounding area
KR100556668B1 (en) Structure of a slop reinforced of carrying out by physical environment
JP3015858B2 (en) Construction structure of landslide prevention pile and its construction method.
KR200325653Y1 (en) Earth anchor including a duplex grouting pipe
JPH01131715A (en) Ground improving work by horizontal injection of chemical grout

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees