JPH0769585A - Crane boom assembly - Google Patents

Crane boom assembly

Info

Publication number
JPH0769585A
JPH0769585A JP24368493A JP24368493A JPH0769585A JP H0769585 A JPH0769585 A JP H0769585A JP 24368493 A JP24368493 A JP 24368493A JP 24368493 A JP24368493 A JP 24368493A JP H0769585 A JPH0769585 A JP H0769585A
Authority
JP
Japan
Prior art keywords
boom
rope
stay
intermediate boom
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24368493A
Other languages
Japanese (ja)
Inventor
Takayuki Eguchi
隆幸 江口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Construction Machinery Co Ltd
Original Assignee
Hitachi Construction Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Construction Machinery Co Ltd filed Critical Hitachi Construction Machinery Co Ltd
Priority to JP24368493A priority Critical patent/JPH0769585A/en
Publication of JPH0769585A publication Critical patent/JPH0769585A/en
Pending legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

PURPOSE:To improve workability by easily projecting each stay for a main rope from an intermediate boom. CONSTITUTION:The tension fitting 31A of each bracket 31 is fixed to front and rear pipes 17 and 17 laid above an intermediate boom 8, and an intermediate reinforcement pipe 18, using a nut 32 or the like. Also, the holder 31B of each bracket 31 is provided with each stay 33 in such a way as vertically slidable. A main rope 25 is connected to the upper end of each stay 33, and a rope 38 is led along the lower end thereof. One end of the rope 38 is hooked to a fastener 34 and the other end thereof is pulled in an arrow B direction, thereby keeping each stay 33 at a projected position.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、例えばクローラ式クレ
ーンやタワークレーン等に好適に用いられるクレーンブ
ーム組立体に関し、特に、上ブームと下ブームとの間に
中間ブームを現場作業等で分解・組立できるようにした
クレーンブーム組立体に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a crane boom assembly suitably used in, for example, a crawler type crane, a tower crane, etc. The present invention relates to a crane boom assembly that can be assembled.

【0002】[0002]

【従来の技術】図3ないし図8に従来技術のクレーンブ
ーム組立体が設けられたクローラ式クレーンを示す。
2. Description of the Related Art FIGS. 3 to 8 show a crawler type crane provided with a prior art crane boom assembly.

【0003】図において、1は下部走行体、2は該下部
走行体1上に旋回可能に設けられたクレーン本体を構成
する上部旋回体を示し、該上部旋回体2にはA型フレー
ム3およびカウンタウェイト4等が設けられると共に、
巻上用ドラム5およびブーム俯仰動用ドラム(図示せ
ず)等が設けられている。
In the drawing, 1 is a lower traveling body, 2 is an upper revolving body which constitutes a crane main body provided on the lower traveling body 1 so as to be rotatable, and the upper revolving body 2 has an A-shaped frame 3 and With the counter weight 4 etc.,
A hoisting drum 5 and a boom / elevation drum (not shown) are provided.

【0004】6は上部旋回体2の前部に俯仰動可能に設
けられたクレーンブーム組立体を示し、該クレーンブー
ム組立体6は、上部旋回体2の前部に回動可能に取付け
られた下ブーム7と、該下ブーム7の先端側に連結ピン
(図示せず)等を介して一体的に連結された例えば3個
の中間ブーム8,8,…と、該各中間ブーム8のうち先
端側の中間ブーム8に連結ピン等を介して連結された上
ブーム9とから構成され、該上ブーム9の先端側には巻
上ロープ10用のシーブ11が取付けられている。そし
て、巻上ロープ10は巻上用ドラム5によって巻上げ、
巻下げられ、シーブ11の下側からフック12を昇降さ
せるようになっている。
Reference numeral 6 denotes a crane boom assembly which is provided on the front part of the upper swing body 2 so as to be able to move up and down. The crane boom assembly 6 is rotatably attached to the front part of the upper swing body 2. Of the intermediate booms 8, the lower boom 7 and, for example, three intermediate booms 8, 8, ... Which are integrally connected to the tip end side of the lower boom 7 via connecting pins (not shown) or the like. The upper boom 9 is connected to the intermediate boom 8 on the front end side via a connecting pin or the like, and the sheave 11 for the hoisting rope 10 is attached to the front end side of the upper boom 9. Then, the hoisting rope 10 is hoisted by the hoisting drum 5,
The hook 12 is wound down, and the hook 12 is moved up and down from the lower side of the sheave 11.

【0005】13は上部旋回体2のブーム俯仰動用ドラ
ムからA型フレーム3を介して繰出,入される俯仰動用
ロープを示し、該俯仰動用ロープ13は先端側がブライ
ドル14を介してペンダントロープ15に接続され、該
ペンダントロープ15の先端側は上ブーム9の先端側に
連結されている。そして、前記ブーム俯仰動用ドラムに
より俯仰動用ロープ13を繰入れるときには、クレーン
ブーム組立体6がペンダントロープ15を介して上向き
に仰動され、俯仰動用ロープ13を繰出すときにはクレ
ーンブーム組立体6が下向きに俯動される。なお、ペン
ダントロープ15はクレーンブーム組立体6を図4、図
5に示す如く分解した状態では、複数本のペンダントロ
ープ15,15,…に分割され、該各ペンダントロープ
15は組立時に金具(図示せず)等を用いて互いに連結
される。
Denoted at 13 is a depression / elevation rope which is fed out from the boom depression / elevation drum of the upper revolving structure 2 via the A-shaped frame 3 and is inserted into the pendant rope 15 via the bridle 14. The front end side of the pendant rope 15 is connected to the front end side of the upper boom 9. The crane boom assembly 6 is lifted upward via the pendant rope 15 when the boom raising / lowering rope 13 is fed by the boom raising / lowering drum. Be moved to. The pendant rope 15 is divided into a plurality of pendant ropes 15, 15, ... When the crane boom assembly 6 is disassembled as shown in FIG. 4 and FIG. (Not shown) or the like.

【0006】次に、図6ないし図8を参照してクレーン
ブーム組立体6の中間ブーム8について詳述する。
Next, the intermediate boom 8 of the crane boom assembly 6 will be described in detail with reference to FIGS. 6 to 8.

【0007】図中、16,16,…は上,下、左,右に
離間して前後方向に伸長した長尺の枠パイプ、17,1
7,…は該各枠パイプ16の両端側で該各枠パイプ16
間を連結した連結パイプを示し、該各連結パイプ17は
各枠パイプ16と共に四角形状の枠構造をなし、中間ブ
ーム8の枠体を構成している。
In the figure, 16, 16, ... Are long frame pipes 17, 17 which are spaced apart from each other at the top, bottom, left and right and extend in the front-rear direction.
7, ... Are provided at both ends of each frame pipe 16
The connecting pipes connecting the two are shown, and each connecting pipe 17 forms a quadrangular frame structure together with each frame pipe 16 and constitutes a frame body of the intermediate boom 8.

【0008】18,18,…は各枠パイプ16間に斜め
に接合された補強パイプを示し、該各補強パイプ18は
前,後の各連結パイプ17と共に各枠パイプ16間で略
三角形のトラス構造をなし、各枠パイプ16および各連
結パイプ17の曲げ強度や捩り強度等を高めるようにな
っている。また、各枠パイプ16の両端側には上,下の
枠パイプ16,16間を斜めに連結する他の補強パイプ
19,19が設けられ、該各補強パイプ19は前,後の
各連結パイプ17の対角線方向に延びている。
Reference numerals 18 and 18 denote reinforcing pipes obliquely joined between the frame pipes 16. The reinforcing pipes 18 together with the front and rear connecting pipes 17 are substantially triangular trusses between the frame pipes 16. The frame pipes 16 and the connecting pipes 17 have a structure to increase the bending strength and the torsional strength. Further, other reinforcing pipes 19, 19 for obliquely connecting the upper and lower frame pipes 16, 16 are provided on both ends of each frame pipe 16, and each reinforcing pipe 19 is a front and rear connecting pipe. 17 extend in a diagonal direction.

【0009】20,21は枠パイプ16の前,後両端に
接合された連結金具を示し、該各連結金具20,21は
各枠パイプ16の両端にそれぞれ設けられ、各中間ブー
ム8を互いに連結するとき、連結金具20を二又状の連
結金具21内に挿入して両者を連結ピン等で結合するも
のである。また、下ブーム7の先端側および上ブーム9
の基端側にも図5に示す如く同様の連結金具20(2
1)が接合して設けられている。
Reference numerals 20 and 21 denote connecting fittings joined to the front and rear ends of the frame pipe 16. The connecting fittings 20 and 21 are provided at both ends of the frame pipe 16, respectively, and connect the intermediate booms 8 to each other. At this time, the connecting fitting 20 is inserted into the bifurcated connecting fitting 21 and the two are joined by a connecting pin or the like. In addition, the tip side of the lower boom 7 and the upper boom 9
As shown in FIG. 5, a similar connecting fitting 20 (2
1) is provided by being joined.

【0010】22,22,…は上側の連結パイプ17,
17および補強パイプ18に取付けられたブラケットを
示し、該各ブラケット22は緊締金具22Aおよびホル
ダ22B等からなり、緊締金具22Aを連結パイプ17
または補強パイプ18の長さ方向中間部にナット23等
を介して締着することにより取付けられている。そし
て、該各ブラケット22のホルダ22Bは後述の各ステ
ー24を上,下にスライド可能に保持し、これらの各ス
テー24が図7,図8に示す如く中間ブーム8から昇降
するのを許すようになっている。
22 are connected to the upper connecting pipe 17,
17 and a bracket attached to the reinforcing pipe 18, each bracket 22 is composed of a tightening metal fitting 22A, a holder 22B and the like.
Alternatively, the reinforcing pipe 18 is attached by being fastened to the middle portion in the longitudinal direction via a nut 23 or the like. The holder 22B of each bracket 22 holds each stay 24, which will be described later, slidably up and down, and allows each stay 24 to move up and down from the intermediate boom 8 as shown in FIGS. It has become.

【0011】24,24,…は各ブラケット22のホル
ダ22Bにスライド可能に保持されたステーを示し、該
ステー24は小径のパイプ材から所定長さをもって形成
され、その先端側となる上端側には親綱25を繋留する
ための繋留リング24Aが設けられている。また、該各
ステー24には上下方向に所定間隔をもって一対のピン
穴24B,24Cがそれぞれ形成され、該各ピン穴24
B,24Cには各位置決めピン26が選択的に装着され
る。そして、該各位置決めピン26は、図7に示す如く
各ステー24を中間ブーム8から上向きに突出させると
きには、下側のピン穴24Cに装着され、各ステー24
を図7に示す張出位置で各ホルダ22Bに位置決めす
る。
Reference numerals 24, 24, ... Show stays slidably held by the holders 22B of the brackets 22. The stays 24 are formed from a small-diameter pipe material with a predetermined length and are provided on the upper end side which is the tip end side. An anchoring ring 24A for anchoring the master rope 25 is provided. Further, each stay 24 is formed with a pair of pin holes 24B and 24C at predetermined intervals in the vertical direction.
Positioning pins 26 are selectively attached to B and 24C. The positioning pins 26 are mounted in the lower pin holes 24C when the stays 24 are projected upward from the intermediate boom 8 as shown in FIG.
Is positioned on each holder 22B at the projecting position shown in FIG.

【0012】また、各ステー24を図8に示す収納位置
へと降下させるときには、各位置決めピン26を各ピン
穴24Cから抜取り、各ステー24を自重によって中間
ブーム8内に降下させた状態で、各ピン穴24Bに各位
置決めピン26を装着する。そして、このときには各位
置決めピン26が各ホルダ22Bの下端側に係合するこ
とにより、各ステー24を収納位置に保持するようにな
っている。一方、親綱25は図7、図8に示す各ステー
24のうち中間のステー24の繋留リング24Aに挿通
され、その両端側が両側のステー24の繋留リングに止
め具25A,25Aを介して繋着(掛止め)されてい
る。
Further, when lowering each stay 24 to the storage position shown in FIG. 8, each positioning pin 26 is pulled out from each pin hole 24C, and each stay 24 is lowered into the intermediate boom 8 by its own weight. Each positioning pin 26 is mounted in each pin hole 24B. Then, at this time, each positioning pin 26 is engaged with the lower end side of each holder 22B to hold each stay 24 at the storage position. On the other hand, the master rope 25 is inserted into the mooring ring 24A of the intermediate stay 24 among the stays 24 shown in FIGS. 7 and 8, and both ends thereof are connected to the mooring rings of the stays 24 on both sides via the fasteners 25A and 25A. It is worn (hanged).

【0013】27は中間ブーム8の上側で、前,後の連
結パイプ17,17間に架け渡された渡し板を示し、該
渡し板27は作業者が中間ブーム8上を歩くために着脱
可能に設けられ、後述の如くクレーンブーム組立体6の
分解・組立作業を行うときの便宜を図るものである。こ
こで、中間ブーム8は図4に示す如くその高さ寸法Hが
2〜3mに及び、渡し板27上での作業は高所作業とな
る。そこで、作業者は渡し板27上に登ったときには命
綱(図示せず)を親綱25に引掛けておき、高所作業で
の安全性を確保するようにしている。
Reference numeral 27 denotes an upper plate of the intermediate boom 8 which is a bridge plate bridged between the front and rear connecting pipes 17, 17. The bridge plate 27 is detachable for an operator to walk on the intermediate boom 8. It is provided for the convenience of disassembling and assembling the crane boom assembly 6 as described later. Here, as shown in FIG. 4, the intermediate boom 8 has a height dimension H of 2 to 3 m, and the work on the bridge plate 27 is a work at a high place. Therefore, the worker hooks a lifeline (not shown) on the master line 25 when climbing on the bridge 27 so as to ensure safety in high-place work.

【0014】このように構成される従来技術では、クレ
ーンブーム組立体6の全長が10m以上となるから、作
業現場に運搬するときには各中間ブーム8および上ブー
ム9等を互いに分解した状態で運搬するようにしてい
る。そして、作業現場ではクレーン作業に先立って図
4,図5に示す如く各中間ブーム8および上ブーム9を
組立てるようにしている。
In the prior art thus constructed, the crane boom assembly 6 has a total length of 10 m or more, and therefore, when the crane boom assembly 6 is transported to the work site, the intermediate boom 8 and the upper boom 9 are transported in a disassembled state. I am trying. At the work site, the intermediate boom 8 and the upper boom 9 are assembled before the crane work as shown in FIGS.

【0015】この場合、まず各中間ブーム8に設けた各
ステー24を図8に示す収納位置に収納した状態で、各
中間ブーム8上に図4に示すようにそれぞれペンダント
ロープ15を載置しておく。そして、この状態で小型の
補助クレーン(図示せず)によりフック28およびワイ
ヤ29等を介して中間ブーム8を吊上げ、所望位置に配
置する。
In this case, first, with each stay 24 provided on each intermediate boom 8 stored in the storage position shown in FIG. 8, the pendant ropes 15 are placed on each intermediate boom 8 as shown in FIG. Keep it. Then, in this state, the intermediate boom 8 is lifted by a small auxiliary crane (not shown) via the hook 28, the wire 29, etc., and is placed at a desired position.

【0016】次に、中間ブーム8を現場に接地させた状
態では各ステー24を図7に示す張出位置に上昇させ、
図6に示す如く各ステー24を中間ブーム8上に所定高
さをもって突出させると共に、この中間ブーム8上には
渡し板27を架け渡すようにし、この渡し板27に登っ
た作業者が命綱を親綱25に引掛けて、その後の組立て
作業を安全に行いうるようにする。そして、この状態で
図4に示すように次なる中間ブーム8を補助クレーンの
フック28およびワイヤ29等を介して吊上げ、先に接
地させた中間ブーム8の位置へと移送する。このとき
に、次なる中間ブーム8の連結金具21を先の中間ブー
ム8の連結金具20に矢示A方向から差込むようにし、
差込んだ状態で両者を連結ピンで一体的に結合する。
Next, in a state where the intermediate boom 8 is grounded on the site, each stay 24 is raised to the extended position shown in FIG.
As shown in FIG. 6, each stay 24 is projected onto the intermediate boom 8 at a predetermined height, and a bridge 27 is bridged over the intermediate boom 8. An operator who climbs the bridge 27 attaches a lifeline. It is hooked on the main rope 25 so that the subsequent assembling work can be performed safely. Then, in this state, as shown in FIG. 4, the next intermediate boom 8 is hoisted via the hook 28 and the wire 29 of the auxiliary crane, and is transferred to the position of the intermediate boom 8 which was previously grounded. At this time, the connecting fitting 21 of the next intermediate boom 8 is inserted into the connecting fitting 20 of the previous intermediate boom 8 from the direction of arrow A,
In the inserted state, both are integrally connected with a connecting pin.

【0017】この場合、図4中で下側に位置する連結金
具20,21をピン結合するのは地面からの作業で行う
ことが可能である。しかし、上側の連結金具20,21
の結合作業は、先に接地した中間ブーム8(渡し板2
7)上に作業者が登り、前記親綱25に命綱を引掛けた
状態で連結金具20,21を確実に連結ピンにより結合
する必要がある。そして、2個の中間ブーム8,8を連
結した状態でも、それぞれの各ステー24を図6、図7
に示す如く張出位置におき、親綱25に命綱を掛止めで
きるようにし、その後に次なる中間ブーム8を前記と同
様に連結してゆく。
In this case, the connecting fittings 20 and 21 located on the lower side in FIG. 4 can be pin-joined by working from the ground. However, the upper coupling fittings 20, 21
The connecting work of the intermediate boom 8 (the bridge 2
7) It is necessary for the worker to climb up and hook the life rope on the master rope 25 so that the connecting fittings 20 and 21 are securely joined by the connecting pins. Even in a state in which the two intermediate booms 8 and 8 are connected, each stay 24 is attached to each stay 24 as shown in FIG.
As shown in FIG. 3, the main rope 25 is set to the extended position so that the life rope can be hooked, and then the next intermediate boom 8 is connected in the same manner as described above.

【0018】次に、図5に示すように中間ブーム8の先
端側に上ブーム9を連結した状態で、これらの組立体を
補助クレーンのフック28等で吊上げ、上部旋回体2に
予めに取付けた下ブーム7の先端側へと移送し、中間ブ
ーム8の基端側に設けた連結金具21(20)を下ブー
ム7の連結金具20(21)に差込むようにして両者を
連結ピンで結合する。また、各中間ブーム8上に載置し
た各ペンダントロープ15を金具等で互いに連結してゆ
くようにする。そして、このときの作業も中間ブーム8
上で各ステー24を介して突出させた親綱25に命綱を
引掛けて行い、組立作業の安全性を確保する。また、ク
レーン作業を終了した後にクレーンブーム組立体6を再
び分解するときにも、前述の組立て時とほぼ同様に行
い、これらの分解・組立作業が終わると、中間ブーム8
の各ステー24を図8に例示した収納位置へと収納する
ようにしている。
Next, as shown in FIG. 5, with the upper boom 9 connected to the tip side of the intermediate boom 8, these assemblies are hoisted by the hooks 28 of the auxiliary crane and attached to the upper swing body 2 in advance. It is transferred to the tip side of the lower boom 7, and the connecting metal fittings 21 (20) provided on the base end side of the intermediate boom 8 are inserted into the connecting metal fittings 20 (21) of the lower boom 7 to connect them with a connecting pin. . Also, the pendant ropes 15 placed on the respective intermediate booms 8 are connected to each other by metal fittings or the like. And the work at this time is also the middle boom 8
The safety rope of the assembling work is secured by hooking the life rope on the master rope 25 protruding above each stay 24. Also, when the crane boom assembly 6 is disassembled again after the crane work is completed, the procedure is similar to that at the time of assembling described above. When the disassembling / assembling work is completed, the intermediate boom 8
Each stay 24 is stored in the storage position illustrated in FIG.

【0019】[0019]

【発明が解決しようとする課題】ところで、上述した従
来技術では、各中間ブーム8上に親綱25を張り出すた
めに、上端側の繋留リング24Aにそれぞれ親綱25を
繋着させた各ステー24を中間ブーム8に各ブラケット
22を介してスライド可能に設け、該各ステー24には
上,下に所定間隔をもってピン穴24B,24Cを形成
すると共に、該各ピン穴24B,24Cに各位置決めピ
ン26を選択的に装着することにより、各ステー24を
図7に示す張出位置と図8に示す収納位置とに手作業で
スライドさせつつ、位置決めするようにしている。
By the way, in the above-mentioned prior art, in order to project the master rope 25 on each intermediate boom 8, each stay in which the master rope 25 is connected to the mooring ring 24A on the upper end side is connected. 24 is slidably provided on the intermediate boom 8 via the brackets 22. The stays 24 are formed with pin holes 24B and 24C at predetermined intervals on the upper and lower sides thereof, and the pin holes 24B and 24C are respectively positioned. By selectively mounting the pins 26, the stays 24 are positioned by manually sliding them to the extended position shown in FIG. 7 and the storage position shown in FIG.

【0020】このため、従来技術では、クレーンブーム
組立体6の分解・組立作業を現場において行うときに、
作業者は中間ブーム8上に登って例えば図8の収納位置
にある各ステー24から位置決めピン26を抜取り、各
ステー24をそれぞれ上向きに引上げるようにして中間
ブーム8から突出させつつ、各ステー24を図7に示す
張出位置に位置決めすべく、各ステー24のピン穴24
Cに各位置決めピン26を装着する必要があり、各ステ
ー24を中間ブーム8から張出したり、収納したりする
作業に多大な労力と時間を費すことになり、作業性が非
常に悪いという問題がある。
Therefore, in the prior art, when disassembling and assembling the crane boom assembly 6 at the site,
The worker climbs on the intermediate boom 8 and pulls out the positioning pins 26 from the stays 24 at the storage position shown in FIG. 8, for example, and pulls the stays 24 upward so as to project from the intermediate boom 8. The pin holes 24 of each stay 24 are positioned to position the stay 24 in the projecting position shown in FIG.
Since it is necessary to attach each positioning pin 26 to C, a great amount of labor and time are required for the work of overhanging and storing each stay 24 from the intermediate boom 8, and the workability is very poor. There is.

【0021】本発明は上述した従来技術の問題に鑑みな
されたもので、本発明は親綱を中間ブームから張出すた
めの各ステーを収納位置と張出位置とに簡単にスライド
させることができ、分解・組立時の作業性を大幅に向上
できるようにしたクレーンブーム組立体を提供すること
を目的としている。
The present invention has been made in view of the above-mentioned problems of the prior art. The present invention allows each stay for extending the master rope from the intermediate boom to be easily slid between the storage position and the extension position. The purpose of the present invention is to provide a crane boom assembly capable of greatly improving workability during disassembly and assembly.

【0022】[0022]

【課題を解決するための手段】上述した課題を解決する
ために本発明は、クレーン本体に取付けられる下ブーム
と、先端側に巻上ロープ用のシーブが取付けられる上ブ
ームと、該上ブームと下ブームとの間に着脱可能に設け
られる中間ブームとからなるクレーンブーム組立体にお
いて、前記中間ブームには、該中間ブームの長さ方向に
離間し、それぞれブラケットを介して長さ方向とは直交
する方向にスライド可能に保持された複数のステーと、
該各ステーの先端側に設けられ、該各ステー間に配設さ
れた親綱と、前記各ステーの基端側に挿通され、一端側
が前記中間ブームに固定される固定端となり、他端側が
自由端となった索条とを設け、該索条の自由端を引張る
ことにより、前記各ステーを中間ブーム内から外向きに
突出させるようにしたことを特徴としてなる構成を採用
している。
SUMMARY OF THE INVENTION In order to solve the above problems, the present invention relates to a lower boom attached to a crane body, an upper boom to which a sheave for a hoisting rope is attached on the tip side, and an upper boom. In a crane boom assembly comprising an intermediate boom detachably provided between the lower boom and the lower boom, the intermediate boom is separated from the intermediate boom in the length direction of the intermediate boom, and is orthogonal to the length direction via brackets. A plurality of stays slidably held in the direction
The main rope provided on the tip side of each stay and inserted between the stays and the base end side of each stay, one end side being a fixed end fixed to the intermediate boom, the other end side A cord is formed as a free end, and by pulling the free end of the cord, the stays are projected outward from the inside of the intermediate boom.

【0023】[0023]

【作用】上記構成により、当該クレーンブーム組立体の
分解・組立作業に先立って中間ブーム上に親綱を張出さ
せる場合には、索条の自由端側を引張るようにすれば、
このときの索条の張力によって各ステーは各ブラケット
を介して外向きにスライドし、中間ブーム内から外向き
に突出して親綱を中間ブーム上に張出すことができる。
また、前記索条の引張力を解除すれば、各ステーは自重
によって中間ブーム内へと降下し、各ステーを中間ブー
ム内に簡単に収納することができる。
With the above construction, when the master rope is to be extended onto the intermediate boom prior to the disassembling / assembling work of the crane boom assembly, if the free end side of the rope is pulled,
By the tension of the rope at this time, the stays slide outward through the brackets and project outward from the inside of the intermediate boom so that the master rope can be extended onto the intermediate boom.
Further, when the tensile force of the rope is released, each stay descends into the intermediate boom by its own weight, and each stay can be easily stored in the intermediate boom.

【0024】[0024]

【実施例】以下、本発明の実施例を図1および図2に基
づき説明する。なお、実施例では前述した図3ないし図
8に示す従来技術と同一の構成要素に同一の符号を付
し、その説明を省略するものとする。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to FIGS. In the embodiments, the same components as those of the conventional technique shown in FIGS. 3 to 8 are designated by the same reference numerals, and the description thereof will be omitted.

【0025】図中、31,31,…は上側の連結パイプ
17,17および補強パイプ18に取付けられたブラケ
ットを示し、該各ブラケット31は従来技術で述べた各
ブラケット22と同様に緊締金具31Aおよびホルダ3
1Bからなり、各金締金具31Aはナット32等によっ
て連結パイプ17または補強パイプ18の長さ方向中間
部に締着されている。
In the figure, 31, 31, ... Show brackets attached to the upper connecting pipes 17, 17 and the reinforcing pipes 18, and each of the brackets 31 is the same as the brackets 22 described in the prior art. And holder 3
1B, and each metal fitting 31A is fastened to the middle portion in the length direction of the connecting pipe 17 or the reinforcing pipe 18 by a nut 32 or the like.

【0026】33,33,…は各ブラケット31のホル
ダ31Bに上,下にスライド可能に保持されたステーを
示し、該各ステー33は従来技術で述べた各ステー24
とほぼ同様に上端側の繋留リング33Aに親綱25が繋
着されているものの、該各ステー33にはその下端に後
述のロープ38を挿通するためのロープ挿通リング33
Bが溶接等で固着されている。また、該各ステー33に
はロープ挿通リング33Bから所定寸法離間した位置に
ピン穴33Cが形成され、該各ピン穴33Cには従来技
術と同様に各位置決めピン26が着脱可能に装着され
る。
Reference numerals 33, 33, ... Show stays slidably held up and down by the holder 31B of each bracket 31, and each stay 33 is a stay 24 described in the prior art.
Although the master rope 25 is connected to the anchoring ring 33A on the upper end side in substantially the same manner as the above, the rope insertion ring 33 for inserting the rope 38 described later at the lower end of each stay 33 is provided.
B is fixed by welding or the like. Further, each stay 33 is formed with a pin hole 33C at a position separated from the rope insertion ring 33B by a predetermined dimension, and each positioning pin 26 is detachably attached to each pin hole 33C as in the prior art.

【0027】34はロープ38の一端側が掛止めして固
定される止め金を示し、該止め金34は図中左側に位置
する連結パイプ17の下面側に溶接等の手段で固着さ
れ、ブラケット31から離間した位置に配接されてい
る。35はロープの他端側が掛止めされる他の止め金を
示し、該止め金35は、例えば連結金具21に近い位置
で枠パイプ16の端部下面側に溶接等の手段で固着され
ている。
Reference numeral 34 denotes a stopper plate to which one end side of the rope 38 is hooked and fixed. The stopper plate 34 is fixed to the lower surface side of the connecting pipe 17 located on the left side in the figure by means such as welding and the bracket 31. It is installed at a position away from. Reference numeral 35 indicates another stopper plate to which the other end side of the rope is hooked. The stopper plate 35 is fixed to the lower surface side of the end portion of the frame pipe 16 at a position close to the connecting fitting 21 by means such as welding. .

【0028】36はロープ38の途中部分が巻回される
ガイドローラを示し、該ガイドローラ36は、例えば図
中右側に位置する連結パイプ17の下面側に取付ブラケ
ット37等を介して取付けられ、各ステー33を図1に
示す張出位置と図2に示す収納位置とに移動させるとき
に、ロープ38を円滑に繰出,入できるようになってい
る。
Reference numeral 36 denotes a guide roller around which an intermediate portion of the rope 38 is wound. The guide roller 36 is attached to the lower surface side of the connecting pipe 17 located on the right side in the drawing via a mounting bracket 37 or the like, When each stay 33 is moved to the extended position shown in FIG. 1 and the storage position shown in FIG. 2, the rope 38 can be smoothly drawn out and put in.

【0029】38は各ステー33のロープ挿通リング3
3Bに挿通して設けられた索条としてのロープを示し、
該ロープ38は小径のワイヤまたは綱等によって形成さ
れ、その両端側には掛け具38A,38Bが設けられて
いる。そして、該ロープ38は一端側の掛け具38Aが
図中左側の止め金34に掛止めされて固定端となり、他
端側の掛け具38Bは自由端となって上部旋回体2側の
引張りロープ(図示せず)または図中左側の止め金35
に選択的に掛止めされる。また、該ロープ38の途中部
分はガイドローラ36に1巻き程度巻回された後に図1
または図2に示す如く引回されている。
38 is a rope insertion ring 3 of each stay 33.
3B shows a rope as a rope provided by being inserted into 3B,
The rope 38 is formed of a wire having a small diameter, a rope, or the like, and hanging parts 38A and 38B are provided on both ends thereof. The rope 38 has a hook 38A on one end hooked on a clasp 34 on the left side in the figure to become a fixed end, and a hook 38B on the other end becomes a free end, which is a pull rope on the upper swing body 2 side. (Not shown) or clasp 35 on the left side in the figure
Selectively hooked to. In addition, the midway portion of the rope 38 is wound around the guide roller 36 about one turn and then
Alternatively, it is routed as shown in FIG.

【0030】本実施例によるクレーンブーム組立体は上
述の如き構成を有するもので、その基本的な作動につい
ては従来技術によるものと格別差異はない。
The crane boom assembly according to this embodiment has the above-mentioned structure, and its basic operation is not different from that of the prior art.

【0031】そこで、本実施例の特徴である親綱25の
張出操作および収納操作について説明する。
Therefore, the operation of projecting and storing the master rope 25, which is a feature of this embodiment, will be described.

【0032】まず、中間ブーム8等の分解・組立時に親
綱25および各ステー33を中間ブーム8上に図1に示
す如く張出すときには、ロープ38の自由端側に設けた
掛け具38Bを前記引張りロープの先端側に接続する。
そして、この引張りロープの基端側を上部旋回体2(図
3参照)の巻上用ドラム5または補助ドラム(図示せ
ず)によって駆動し、ロープ38の掛け具38B側を図
1中の矢示B方向に引張ることによってロープ38の張
力を増大させる。これにより、各ステー33は各ブラケ
ット31のホルダ31B内を上向きにスライドし、図1
に示す張出位置となって中間ブーム8上に突出し、親綱
25を所定の高さ位置に張出すようになる。
First, when the master rope 25 and each stay 33 are extended on the intermediate boom 8 as shown in FIG. 1 at the time of disassembling and assembling the intermediate boom 8, etc., the hanging tool 38B provided on the free end side of the rope 38 is used. Connect to the end of the pull rope.
Then, the base end side of this pulling rope is driven by the hoisting drum 5 of the upper swing body 2 (see FIG. 3) or an auxiliary drum (not shown), and the hanging tool 38B side of the rope 38 is indicated by the arrow in FIG. The tension of the rope 38 is increased by pulling in the direction B shown. As a result, each stay 33 slides upward in the holder 31B of each bracket 31.
The projecting position shown in (3) is projected onto the intermediate boom 8 and the master rope 25 is projected to a predetermined height position.

【0033】次に、この状態で各ステー33のピン穴3
3C内に各位置決めピン26を装着し、各ステー33を
図1に示す張出位置に位置決めする。これにより、ロー
プ38への前記張力を解除した後にも各ステー33が自
重等で中間ブーム8内へと不用意に降下してしまうのを
確実に防止できる。そして、この状態で図4、図5に例
示した中間ブーム8等の分解・組立作業を行えば、この
作業時に命綱を所定高さ位置の親綱25に確実に掛止め
でき、高所作業での安全性を確保できる。
Next, in this state, the pin hole 3 of each stay 33 is formed.
Each positioning pin 26 is mounted in 3C, and each stay 33 is positioned at the projecting position shown in FIG. As a result, even after the tension on the rope 38 is released, it is possible to reliably prevent the stays 33 from inadvertently dropping into the intermediate boom 8 due to their own weight or the like. In this state, if the disassembling and assembling work of the intermediate boom 8 and the like illustrated in FIGS. 4 and 5 is performed, the lifeline can be securely hooked to the master rope 25 at a predetermined height position during this work, and the lifeline work can be performed. The safety of can be secured.

【0034】また、中間ブーム8等の分解・組立作業が
完了したときには、各ステー33のピン穴33Cから各
位置決めピン26を抜取り、前記ロープ38への張力を
解除した状態とすれば、各ステー33が自重によって各
ブラケット31のホルダ31B内へと下向きに降下し、
各ステー33を図2に示す収納位置に配置して中間ブー
ム8内に収納することができる。そして、このときには
ロープ38の掛け具38Bを図2中の右側に位置する止
め金35に掛止めしておけば、中間ブーム8を運搬する
とき等に、ロープ38が各ステー33のロープ挿通リン
グ33Bから外れたり、ロープ38を紛失したりするの
を確実に防止できる。
Further, when the disassembling and assembling work of the intermediate boom 8 and the like is completed, each positioning pin 26 is pulled out from the pin hole 33C of each stay 33 and the tension on the rope 38 is released. 33 descends into the holder 31B of each bracket 31 by its own weight,
Each stay 33 can be placed in the storage position shown in FIG. 2 and stored in the intermediate boom 8. Then, at this time, if the hook 38B of the rope 38 is hooked on the stopper 35 located on the right side in FIG. 2, the rope 38 can be used for the rope insertion ring of each stay 33 when the intermediate boom 8 is transported. It is possible to reliably prevent the rope 38 from being disengaged and the rope 38 from being lost.

【0035】かくして、本実施例によれば、各ステー3
3の下端側にそれぞれロープ挿通リング33Bを設け、
該各ロープ挿通リング33Bに挿通したロープ38の一
端側を中間ブーム8の止め金34に掛止めし、他端側を
上部旋回体2の巻上用ドラム5または補助ドラム等で引
張る構成としたから、ロープ38の他端側を図1中の矢
示B方向に張力を加えて引張るだけで、各ステー33を
図2に示す収納位置から図1に示す張出位置へと自動的
に張出すことができ、各ステー33および親綱25の張
出、収納作業を簡単に行うことができる。
Thus, according to this embodiment, each stay 3
Provide the rope insertion ring 33B on the lower end side of 3, respectively,
One end side of the rope 38 inserted through each rope insertion ring 33B is hooked on the stopper 34 of the intermediate boom 8, and the other end side is pulled by the hoisting drum 5 of the upper swing body 2 or an auxiliary drum. From the above, each stay 33 is automatically stretched from the retracted position shown in FIG. 2 to the extended position shown in FIG. 1 only by applying tension to the other end of the rope 38 in the direction of arrow B in FIG. The stay 33 and the main rope 25 can be easily extended and stored.

【0036】従って、本実施例では、各ステー33およ
び親綱25を中間ブーム8から張出したり、収納したり
する作業をロープ38に張力を加えることにより簡単に
実行することができ、従来技術の如く親綱25の張出作
業に余分な労力や時間を費やすことなく、全体の作業性
を大幅に向上させることができる。
Therefore, in the present embodiment, the work of overhanging each stay 33 and the main rope 25 from the intermediate boom 8 and storing them can be easily performed by applying tension to the rope 38, which is a conventional technique. As described above, it is possible to significantly improve the overall workability without spending extra labor and time for the work of projecting the master rope 25.

【0037】なお、前記実施例では、止め金34,35
を連結パイプ17,枠パイプ16の下面側に設け、ガイ
ドローラ36を他の連結パイプ17の下面側に取付ブラ
ケット37を介して取付けるものとして述べたが、これ
に替えて、止め金34,35を各ブラケット31の緊締
金具31A等に取付けたり、または中間ブーム8の適所
に取付けるようにしてもよい。また、ガイドローラ36
についても中間ブーム8の適所に取付けるようにすれば
よい。
In the above embodiment, the stoppers 34, 35 are used.
It has been described that the guide roller 36 is provided on the lower surface side of the connecting pipe 17 and the frame pipe 16 and the guide roller 36 is attached to the lower surface side of the other connecting pipe 17 via the mounting bracket 37. May be attached to the tightening metal fittings 31A of each bracket 31 or the like, or may be attached to an appropriate position of the intermediate boom 8. In addition, the guide roller 36
As for the above, the intermediate boom 8 may be attached at a proper position.

【0038】また、前記実施例では、各ステー33にピ
ン穴33Cを形成し、該各ピン穴33Cに各位置決めピ
ン26を装着することによって、各ステー33を張出位
置に位置決めするものとして述べたが、本発明はこれに
限らず、例えばロープ38の掛け具38Bを中間ブーム
8の所定部位に掛止めすることにより、各ステー33を
図1に示す張出位置に保持するようにしてもよい。
Further, in the above-described embodiment, the pin holes 33C are formed in the stays 33, and the positioning pins 26 are mounted in the pin holes 33C to position the stays 33 at the projecting position. However, the present invention is not limited to this, and each stay 33 may be held at the extended position shown in FIG. 1 by, for example, hooking the hook 38B of the rope 38 to a predetermined portion of the intermediate boom 8. Good.

【0039】さらに、前記実施例では、クローラ式クレ
ーンを例に挙げて説明したが、本発明はこれに限らず、
例えばタワークレーン等にも適用できる。
Further, in the above-mentioned embodiment, the crawler type crane has been described as an example, but the present invention is not limited to this,
For example, it can be applied to a tower crane or the like.

【0040】[0040]

【発明の効果】以上詳述した通り本発明によれば、中間
ブーム上に親綱を張出させるための複数のステーを中間
ブームにそれぞれブラケットを介してスライド可能に設
け、該各ステーの基端側に挿通した索条の一端側を中間
ブームに固定し、他端側の自由端を引張ることにより、
各ステーを中間ブームから突出させる構成としたから、
索条の自由端に張力を加えるだけで、各ステーおよび親
綱を中間ブーム内から簡単に張出させることができ、全
体の作業性を大幅に向上できると共に、作業時の安全性
を確保でき、当該クレーンブーム組立体の分解・組立作
業の省力化を図ることが可能となる。
As described in detail above, according to the present invention, a plurality of stays for extending the master rope are provided slidably on the intermediate boom via the brackets, and the bases of the stays are provided. By fixing one end side of the rope inserted through the end side to the intermediate boom and pulling the free end on the other end side,
Since each stay is configured to project from the intermediate boom,
By simply applying tension to the free ends of the ropes, each stay and main rope can be easily extended from the middle boom, greatly improving the overall workability and ensuring safety during work. It is possible to save labor in disassembling and assembling the crane boom assembly.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例による中間ブームおよび親綱用
の各ステー等を示す縦断面図である。
FIG. 1 is a longitudinal sectional view showing an intermediate boom and stays for a main rope according to an embodiment of the present invention.

【図2】各ステーを中間ブーム内に収納した状態を示す
図1とほぼ同様の縦断面図である。
FIG. 2 is a vertical sectional view similar to FIG. 1, showing a state in which each stay is stored in an intermediate boom.

【図3】従来技術によるクローラ式クレーンを示す全体
図である。
FIG. 3 is an overall view showing a crawler type crane according to the related art.

【図4】図3に示す各中間ブームの組立状態を示す説明
図である。
4 is an explanatory view showing an assembled state of each intermediate boom shown in FIG. 3. FIG.

【図5】上ブームを組付けた中間ブームを下ブームに組
付ける状態を示す説明図である。
FIG. 5 is an explanatory view showing a state where an intermediate boom having an upper boom attached thereto is attached to a lower boom.

【図6】中間ブームの斜視図である。FIG. 6 is a perspective view of an intermediate boom.

【図7】図6中の矢示VII −VII 方向拡大断面図であ
る。
7 is an enlarged cross-sectional view taken along line VII-VII in FIG.

【図8】各ステーを中間ブーム内に収納した状態を示す
図7とほぼ同様の断面図である。
FIG. 8 is a cross-sectional view similar to FIG. 7, showing a state in which each stay is stored in the intermediate boom.

【符号の説明】[Explanation of symbols]

1 下部走行体 2 上部旋回体(クレーン本体) 6 クレーンブーム組立体 7 下ブーム 8 中間ブーム 9 上ブーム 10 巻上ロープ 11 シーブ 13 俯仰動用ロープ 15 ペンダントロープ 16 枠パイプ 17 連結パイプ 18 補強パイプ 25 親綱 31 ブラケット 33 ステー 34,35 止め金 36 ガイドローラ 38 ロープ(索条) 38A,38B 掛け具 1 Lower Traveling Body 2 Upper Revolving Body (Crane Main Body) 6 Crane Boom Assembly 7 Lower Boom 8 Middle Boom 9 Upper Boom 10 Hoisting Rope 11 Sheave 13 Depression Rope 15 Pendant Rope 16 Frame Pipe 17 Connecting Pipe 18 Reinforcement Pipe 25 Parent Rope 31 Bracket 33 Stay 34, 35 Clasp 36 Guide roller 38 Rope (cord) 38A, 38B Hanger

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 クレーン本体に取付けられる下ブーム
と、先端側に巻上ロープ用のシーブが取付けられる上ブ
ームと、該上ブームと下ブームとの間に着脱可能に設け
られる中間ブームとからなるクレーンブーム組立体にお
いて、前記中間ブームには、該中間ブームの長さ方向に
離間し、それぞれブラケットを介して長さ方向とは直交
する方向にスライド可能に保持された複数のステーと、
該各ステーの先端側に設けられ、該各ステー間に配設さ
れた親綱と、前記各ステーの基端側に挿通され、一端側
が前記中間ブームに固定される固定端となり、他端側が
自由端となった索条とを設け、該索条の自由端を引張る
ことにより、前記各ステーを中間ブーム内から外向きに
突出させる構成としたことを特徴とするクレーンブーム
組立体。
1. A lower boom attached to a crane main body, an upper boom to which a sheave for a hoisting rope is attached at a tip side, and an intermediate boom detachably provided between the upper boom and the lower boom. In the crane boom assembly, the intermediate boom is provided with a plurality of stays spaced apart in the longitudinal direction of the intermediate boom and slidably held via brackets in a direction orthogonal to the longitudinal direction.
The main rope provided on the tip side of each stay and inserted between the stays and the base end side of each stay, one end side being a fixed end fixed to the intermediate boom, the other end side A crane boom assembly, characterized in that a rope which is a free end is provided, and each stay is projected outward from the inside of the intermediate boom by pulling the free end of the rope.
JP24368493A 1993-09-03 1993-09-03 Crane boom assembly Pending JPH0769585A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24368493A JPH0769585A (en) 1993-09-03 1993-09-03 Crane boom assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24368493A JPH0769585A (en) 1993-09-03 1993-09-03 Crane boom assembly

Publications (1)

Publication Number Publication Date
JPH0769585A true JPH0769585A (en) 1995-03-14

Family

ID=17107453

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24368493A Pending JPH0769585A (en) 1993-09-03 1993-09-03 Crane boom assembly

Country Status (1)

Country Link
JP (1) JPH0769585A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007302433A (en) * 2006-05-12 2007-11-22 Kobelco Cranes Co Ltd Boom of crane
JP2012116606A (en) * 2010-11-30 2012-06-21 Hitachi Sumitomo Heavy Industries Construction Crane Co Ltd Mobile crane and method for assembling the mobile crane
JP2012140233A (en) * 2011-01-05 2012-07-26 Kato Works Co Ltd Fall-prevention work for crane truck
CN102897677A (en) * 2012-09-24 2013-01-30 三一重工股份有限公司 Crane fly jib self-assembly and disassembly device and method, as well as crane
JP2017516730A (en) * 2014-06-03 2017-06-22 シャーデ・ラーガーテヒニク・ゲゼルシャフト・ミト・ベシュレンクテル・ハフツング Portal scraper with carrier structure based on truss structure
WO2019220881A1 (en) * 2018-05-18 2019-11-21 コベルコ建機株式会社 Lattice structure, lattice structure coupling body, work machine, and connector
DE102009061819B4 (en) * 2008-05-10 2020-03-05 Terex Global Gmbh Cantilever element for a hoist
CN112105578A (en) * 2018-05-18 2020-12-18 神钢建机株式会社 Truss structure, truss structure connection body, construction machine, and connector
WO2021053863A1 (en) * 2018-09-28 2021-03-25 コベルコ建機株式会社 Handrail device and work machine comprising same

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007302433A (en) * 2006-05-12 2007-11-22 Kobelco Cranes Co Ltd Boom of crane
DE102009061819B4 (en) * 2008-05-10 2020-03-05 Terex Global Gmbh Cantilever element for a hoist
JP2012116606A (en) * 2010-11-30 2012-06-21 Hitachi Sumitomo Heavy Industries Construction Crane Co Ltd Mobile crane and method for assembling the mobile crane
JP2012140233A (en) * 2011-01-05 2012-07-26 Kato Works Co Ltd Fall-prevention work for crane truck
CN102897677A (en) * 2012-09-24 2013-01-30 三一重工股份有限公司 Crane fly jib self-assembly and disassembly device and method, as well as crane
JP2017516730A (en) * 2014-06-03 2017-06-22 シャーデ・ラーガーテヒニク・ゲゼルシャフト・ミト・ベシュレンクテル・ハフツング Portal scraper with carrier structure based on truss structure
WO2019220881A1 (en) * 2018-05-18 2019-11-21 コベルコ建機株式会社 Lattice structure, lattice structure coupling body, work machine, and connector
CN112105578A (en) * 2018-05-18 2020-12-18 神钢建机株式会社 Truss structure, truss structure connection body, construction machine, and connector
AU2019268668B2 (en) * 2018-05-18 2022-04-07 Kobelco Construction Machinery Co., Ltd. Lattice structure, lattice structure coupling body, work machine, and connector
US11787672B2 (en) 2018-05-18 2023-10-17 Kobelco Construction Machinery Co., Ltd. Lattice structure, lattice structure coupling body, work machine, and connector
WO2021053863A1 (en) * 2018-09-28 2021-03-25 コベルコ建機株式会社 Handrail device and work machine comprising same

Similar Documents

Publication Publication Date Title
KR101405010B1 (en) Lifting Gantry for Girder Erection Works of Suspension Bridges
JPH0769585A (en) Crane boom assembly
CN108149928A (en) The tower end installation method of suspension cable
JP2016047985A (en) Installation method of work sheet and device used for this method
JPH10218563A (en) Installing method of tie rod of tower jig crane and device thereof
JP6321938B2 (en) Installation method of construction sheet and equipment used for this method
JP6003556B2 (en) Jib fixing method for mobile tower crane
JP7136143B2 (en) Crane upper spreader retraction method and crane upper spreader retraction device
JP3069315B2 (en) Work method and device for leaderless auger
JP2002013294A (en) Safety halter for building work
JP6969281B2 (en) Crane and crane disassembly method
CN209114718U (en) A kind of building-supporting steel beam structure
JP2018162125A (en) Tower crane
JP3889521B2 (en) Pile driver and its work floor mounting method
JP6923014B2 (en) Work machine connecting device, connecting pin, connecting pin mounting device and disconnection method of connecting pin
JP2003128367A (en) Rope extension method at climbing of lifting device and its auxiliary device
JP3237258U (en) Bracket for loading and unloading
JPH0932351A (en) Pole for erecting column
JPH10129985A (en) Catwalk device of crane boom
JPH07291587A (en) Tower crane
JP6579172B2 (en) Crane and crane strut raising method
KR200294095Y1 (en) a connection structure of crane hook
JPH07291586A (en) Crane
JP2000219483A (en) Overhead crane installation structure
JP6103461B1 (en) Simple crane, suspension load suspension method with simple crane