Prior art keywords
rail
guide
vehicle
track
attached
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7974488A
Other languages
Japanese (ja)
Other versions
JPH01250502A (en
Inventor
紘郎 神崎
陽三 福本
勝郎 福元
昌二 尾之内
徹 藤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Sharyo Ltd
Kobe Steel Ltd
Mitsubishi Heavy Industries Ltd
Kumagai Gumi Co Ltd
Tokyu Construction Co Ltd
Original Assignee
Nippon Sharyo Ltd
Kobe Steel Ltd
Mitsubishi Heavy Industries Ltd
Kumagai Gumi Co Ltd
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Sharyo Ltd, Kobe Steel Ltd, Mitsubishi Heavy Industries Ltd, Kumagai Gumi Co Ltd, Tokyu Construction Co Ltd filed Critical Nippon Sharyo Ltd
Priority to JP7974488A priority Critical patent/JPH0759802B2/en
Publication of JPH01250502A publication Critical patent/JPH01250502A/en
Publication of JPH0759802B2 publication Critical patent/JPH0759802B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Railway Tracks (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は一般にガイドウェイバスと称されるエンジン駆
動車両、またはゴムタイヤ付き電気車両を誘導する軌道
を、車両の転換を考慮して建設する工法に関するもので
ある。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention is a method for constructing a track for guiding an engine-driven vehicle generally called a guideway bus or an electric vehicle with rubber tires in consideration of conversion of the vehicle. It is about.

(従来技術) 上記ガイドウェイバスは、一般道路をも走行可能なとこ
ろからデュアルモード車両とも別称され、車体の左右両
側に張出したガイドローラと、軌道側方に設けられたガ
イドレールとによる誘導作用によって軌道上を走行する
ようになっている。このような輸送システムは、一般に
ガイドウェイバスシステムに称される。
(Prior Art) The guideway bus is also referred to as a dual mode vehicle because it can travel on a general road, and is guided by guide rollers extending to the left and right sides of the vehicle body and guide rails provided on the side of the track. It is designed to run on orbit. Such a transportation system is generally referred to as a guideway bus system.

一方、上記ゴムタイヤ付き電気車両は、一般に新交通シ
ステムと称される輸送システムに使用され、電気(モー
タ)駆動されながら、上記ガイドウェイバス同様、ガイ
ドローラとガイドレールとによる誘導作用によって軌道
上を走行する。
On the other hand, the electric vehicle with rubber tires is generally used in a transportation system called a new transportation system, and is driven by an electric (motor) while being guided by guide rollers and guide rails in the same way as the guideway bus. To run.

このように、両システムとも、軌道側のガイドレールと
車両側のガイドローラとによって車両を誘導する点で共
通するため、システム転換時に軌道を転用することは、
理論上可能である。また、新交通システムは、全線に亘
って電気設備や通信設備を必要とすること等から建設コ
ストが高く、しかも現状では早期の投資回収は望めない
ことから、当初は設備コストが安いガイドウェイバスシ
ステム用軌道として活用することにより初期投資の軽減
を図り、将来、需要の増加に応じて新交通システム用軌
道へ転換したいという要請がある。
In this way, both systems are common in that the vehicle is guided by the guide rails on the track side and the guide rollers on the vehicle side.
Theoretically possible. In addition, the new transportation system has high construction costs due to the need for electrical and communication facilities over the entire line, and at the present time it is not possible to expect an early return on investment. There is a demand to reduce the initial investment by using it as a system track and switch to a new transportation system track in the future as demand increases.

しかしこの場合、ガイドウェイバスにおいては、ガイド
ローラを、一般道路走行時には走行障害とならないよう
に車体下方に格納する必要から、このガイドローラの位
置が低く設定されているのに対し、ゴムタイヤ付き電気
車両(以下、新交通車両という)においては、ガイドロ
ーラの下方に分岐部案内用の分岐輪が設けられること等
から、ガイドローラが上記ガイドウェイバスの場合より
高位置に設けられているため、ガイドフェイバス用軌道
として使用するか新交通車両用軌道として使用するかに
よって軌道のガイドレールの高さ位置を変える必要があ
る。
However, in this case, in the guideway bus, the guide roller needs to be stored under the vehicle body so that it does not hinder traveling when traveling on general roads. In a vehicle (hereinafter referred to as a new transportation vehicle), since a branch wheel for guiding a branch portion is provided below the guide roller, the guide roller is provided at a higher position than that of the guideway bus, It is necessary to change the height position of the guide rail of the track depending on whether it will be used as a guide fabus track or a new traffic vehicle track.

この場合、従来の車両誘導軌道においては、ガイドレー
ルを、車両に応じた高さをもった固定設備として床版に
設置しているため、上記したようにガイドウェイバスシ
ステムから新交通システムへ転換するにあたって、ガイ
ドレールをレール支柱等の付属設備を含めて全線に亘っ
て一新しなければならず、このレール改装ために軌道改
造工事がきわめて大がかりとなる。このため、工期が長
く、工費が高くなり、この点がシステム転換の大きな障
害となる。
In this case, in the conventional vehicle guidance track, since the guide rail is installed on the floor slab as fixed equipment with a height corresponding to the vehicle, the guideway bus system is switched to the new transportation system as described above. In doing so, the guide rail must be renewed over the entire line including the supporting equipment such as rail stanchions, and the track remodeling work will be extremely large for this rail remodeling. Therefore, the construction period is long and the construction cost is high, which is a major obstacle to system conversion.

(発明の目的) そこで本発明は、ガイドレールの改装を最小限の手間と
労力によって能率良く行なうことができ、システム転換
に伴う軌道改造工事の工期短縮、工費節減を実現するこ
とができる車両誘導軌道の段階建設工法を提供するもの
である。
(Object of the Invention) Therefore, the present invention is a vehicle guidance system that can efficiently perform guide rail remodeling with a minimum of labor and labor, and can shorten the period of track remodeling work associated with system conversion and reduce construction costs. It provides a track construction method.

(発明の構成) 本発明は、車両走行路盤を備えた床版に、車両の左右両
側に張出されたガイドローラに接触して車両の誘導する
左右両側ガイドレールが設けられて構成される車両誘導
軌道を、上記ガイドローラの高さ位置が異なる二種類の
車両に対応して上記ガイドレールの高さ位置を可変とし
うるように建設する車両誘導軌道の段階建設工法であっ
て、上記床版における一方のガイドレールが取付けられ
る部分に、上記二種類の車両に対応する高位置用および
低下位置用両レール取付具を設けるとともに、他方のガ
イドレールが取付けられる部分に支柱取付具を設け、初
期建設段階において、上記一方のガイドレールは、上記
低位置用レール取付具に取外し可能に取付けたレール支
持部材に、他方のガイドレールは、上記支柱取付具に取
外し可能に取付けたレール支柱にそれぞれ取付け、車両
転換時において、上記一方のガイドレールは、上記低位
置用レール取付具から取外して上記高位置用レール取付
具にレール支持部材を介して取付け、他方のガイドレー
ルは、上記レール支柱と床版との間に支柱受け台を挿入
することによって高位置に位置替えするものである。
(Structure of the Invention) The present invention is a vehicle in which a floor slab equipped with a vehicle running roadbed is provided with left and right guide rails that guide the vehicle by contacting guide rollers that are extended on both the left and right sides of the vehicle. A step construction method of a vehicle guide track for constructing a guide track so that the height position of the guide rail can be made variable so as to correspond to two types of vehicles having different height positions of the guide rollers. In the part where one of the guide rails is attached, both the high position and low position rail mounts corresponding to the above two types of vehicles are provided, and the column mount is provided in the part where the other guide rail is mounted. At the construction stage, one of the guide rails is detachably attached to the rail support member that is detachably attached to the low-position rail mount, and the other guide rail is detached to the column mount. Each of the guide rails is detachably attached to the high-position rail mount via a rail support member, and the other guide rail is removed from the low-position rail mount at the time of vehicle conversion. The guide rail of (1) is to be moved to a high position by inserting a support pedestal between the rail support and the floor slab.

この構成により、ガイドウェイバスシステムから新交通
システムへの移行に伴う軌道改造時に、一方のガイドレ
ールについては低位置用レール取付具から高位置用レー
ル取付具への移設により、また他方のガイドレールにつ
いてはレール支柱下に支柱受け台を挿入することによ
り、それぞれ新車両に対応する位置に簡単に位置替えす
ることができる。このため、ガイドレールの改装を最小
限の手間と労力で簡単に行なうことができ、軌道改造工
事を短時間で能率良く行なうことができる。
With this configuration, when the track is modified due to the transition from the guideway bus system to the new transportation system, one guide rail is moved from the low position rail fixture to the high position rail fixture, and the other guide rail is moved. With regard to, by inserting the support pedestal under the rail support, it is possible to easily change the position to the position corresponding to the new vehicle. For this reason, the guide rail can be easily refurbished with a minimum of labor and labor, and the track remodeling work can be performed efficiently in a short time.

(実施例) 第1図(イ)(ロ)に発明の第1実施例、第2図(イ)
(ロ)に同第2実施例、第3図(イ)(ロ)に同第3実
施例をそれぞれ示している。また、この各実施例では複
線軌道の場合を例にとっている。
(Embodiment) FIG. 1 (a) and (b) show a first embodiment of the invention, and FIG. 2 (a).
The second embodiment is shown in (B), and the third embodiment is shown in FIGS. Further, in each of the embodiments, the case of a double track is taken as an example.

まず、各実施例共通部分について説明すると、1はコン
クリート床版で、この床版1には、左右両側壁2,2と、
車両が走行する左右の走行路盤3,3とが設けられ、この
両走行路盤3,3を挟んで両側ガイドレール4,5が設けられ
る。このガイドレール4,4は、この軌道がガイドウェイ
バスシステムに使用される場合には、第1〜第3各図の
(イ)に示すようにガイドウェイバスBのガイドローラ
B1,B1に対応して低位置に、新交通システムに使用され
る場合には、各図(ロ)に示すように新交通車両Mのガ
イドローラM1,M1に対応して高位置にそれぞれ設置され
る。また、第1、第2両実施例は、両車両のガイドロー
ラ間隔が異なる場合に対応してガイドレール間隔(以
下、ガイド幅という)をも変更するケース、第3実施例
は、ガイドローラ間隔が等しい場合に対応してレール高
さ位置のみを変更するケースをそれぞれ示している。以
下、各実施例について詳述する。なお、各実施例におい
て、複線軌道の両線の構成は全く同じであるため、以下
には一方の線のみについて説明する。
First, the parts common to each embodiment will be described. 1 is a concrete floor slab, and the floor slab 1 includes both left and right side walls 2, 2.
Left and right traveling roadbeds 3, 3 on which the vehicle travels are provided, and both side guide rails 4, 5 are provided so as to sandwich the both traveling roadbeds 3, 3. When the track is used in a guideway bus system, the guide rails 4 and 4 are guide rollers of the guideway bus B as shown in (a) of each of FIGS. 1 to 3.
When it is used in a new transportation system in a low position corresponding to B 1 and B 1 , it is high corresponding to the guide rollers M 1 and M 1 of the new transportation vehicle M as shown in each figure (b). It is installed in each position. Further, in both the first and second embodiments, the guide rail spacing (hereinafter referred to as the guide width) is also changed corresponding to the case where the guide roller spacings of the two vehicles are different. In the third embodiment, the guide roller spacing is changed. Cases in which only the rail height position is changed corresponding to the case where are equal are shown. Hereinafter, each example will be described in detail. In addition, in each embodiment, since both lines of the double track are exactly the same, only one line will be described below.

第1実施例 軌道の初期建設段階において、床版1における走行路盤
(以下、単に路盤という)3の左右両側部のうち、軌道
中心側に支柱取付具としてのアンカーボルト6、側壁2
側に低位値用レール取付具としてのアンカーボルト7が
それぞれ一組ずつ植設され、第4図(イ)に拡大して示
すようにこれらアンカーボルト6,7にそれぞれレール支
柱8,9がナット10…により取外し可能に取付けられると
ともに、この両レール支柱8,9の上面にガイドレール4,5
がねじ止め等によって着脱可能に取付けられる。また、
システム転換に備えて、予め、側壁2の内面に、高位置
用レール取付具としての一組のアンカーボルト11が水平
に植設される。H1はこの軌道状態でのレール高さ、W1
同ガイド幅を示し、この軌道状態でガイドウェイバスB
の両側ガイドロー等B1,B1が両側ガイドレール4,5に接
触し、これらによる誘導作用によってガイドウェイバス
Bが路盤3上を走行する。
First Embodiment At the initial stage of construction of the track, anchor bolts 6 and side walls 2 as pillar support members on the track center side of the left and right sides of the traveling roadbed (hereinafter simply referred to as roadbed) 3 in the floor slab 1 are provided.
One set of anchor bolts 7 as rail attachments for low value are planted on the side, and rail posts 8 and 9 are nuts on these anchor bolts 6 and 7, respectively, as shown in enlarged view in FIG. It is removably attached with 10… and guide rails 4,5
Is detachably attached by screwing or the like. Also,
In preparation for the system conversion, a set of anchor bolts 11 as high-position rail mounts are horizontally installed in advance on the inner surface of the side wall 2. H 1 indicates the rail height in this track condition, W 1 indicates the guide width, and guideway bus B in this track condition
The guideways B 1 and B 1 on both sides of the guideway contact the guide rails 4 and 5 on both sides, and the guideway bus B travels on the roadbed 3 by the guiding action of these.

つぎに、ガイドウェイバスシステムから新交通システム
へのシステム転換にあたって軌道を改造する場合は、第
1図(ロ)に示すように、両ガイドレール4,5のうち、
路盤中心側のガイドレール(以下、内側ガイドレールと
いう)4については軌道幅方向同一位置において高さ位
置のみ変えられ、もう一方のガイドレール(以下、外側
ガイドレールという)5については軌道幅方向位置およ
び高さ位置ともに変えられる。
Next, when modifying the track for system conversion from the guideway bus system to the new transportation system, as shown in Fig. 1 (b),
Only the height position of the guide rail (hereinafter referred to as the inner guide rail) 4 on the center side of the roadbed can be changed at the same position in the track width direction, and the position of the other guide rail (hereinafter referred to as the outer guide rail) 5 in the track width direction. And height can be changed.

すなわち、このとき内側ガイドレール4用のレール支柱
(以下、ガイドレールにあわせて内側レール支柱とい
う)8をアンカーボルト6から取外し、第4図(ロ)に
拡大し示すように代わりにこのアンカーボルト6に支柱
受け台12をナット10によって取付けた後、この支柱受け
台12上にレール支柱8をボルト13a,13bにて取付ける。
一方、外側レール支柱9もアンカーボルト7から取外
し、さらにこの外側レール支柱9から取外した外側ガイ
ドレール5を、側壁2のアンカーボルト11に支持プレー
ト13を介して取付ける。この支持プレート13は、第5図
に拡大して示すようにアンカーボルト11にナット14…に
よって取付け、この支持プレート13に外側ガイドレール
5をレール止め具15,16によって止めつける。
That is, at this time, the rail support 8 for the inner guide rail 4 (hereinafter referred to as the inner rail support along with the guide rail) 8 is removed from the anchor bolt 6, and the anchor bolt is used instead as shown in FIG. After mounting the column support 12 on 6 with the nut 10, the rail column 8 is mounted on the column support 12 with bolts 13a and 13b.
On the other hand, the outer rail support 9 is also removed from the anchor bolt 7, and the outer guide rail 5 removed from the outer rail support 9 is attached to the anchor bolt 11 of the side wall 2 via the support plate 13. The support plate 13 is attached to the anchor bolt 11 by nuts 14 ... As enlargedly shown in FIG. 5, and the outer guide rail 5 is fixed to the support plate 13 by rail stoppers 15 and 16.

H2はこのときレール高さ、W2は同ガイド幅をそれぞれ示
し、この軌道状態で新交通車両MのガイドローラM1,M1
が両側ガイドレール4,5に接触して車両誘導機能が果さ
れる。
At this time, H 2 indicates the rail height and W 2 indicates the guide width, and in this track state, the guide rollers M 1 , M 1 of the new transportation vehicle M
Contacts the guide rails 4 and 5 on both sides to perform the vehicle guidance function.

このように、ガイドウェイバスシステムから新交通シス
テムへのシステム転換に際して、内側ガイドレール4に
ついては内側レール支柱8とを床版1との間に支柱受け
台12を挿入して嵩上げし、外側ガイドレール5について
は側壁2に予め植設しておいたアンカーボルト11に移設
するという最小限の手間と労力によって、ガイドレール
4,5の位置変更作業を簡単、迅速に行なうことができ
る。このため、このレール改装が大きなウエイトを占め
る軌道転換工事を短期間で能率良く行なうことできる。
In this way, when the system is changed from the guideway bus system to the new transportation system, for the inner guide rails 4, the inner rail struts 8 and the floor slab 1 are inserted into the pedestal pedestals 12 to raise the outer guides. As for the rail 5, the guide rail can be installed with the minimum effort and labor of moving it to the anchor bolts 11 that are previously planted on the side wall 2.
The position change work of 4 and 5 can be performed easily and quickly. For this reason, it is possible to efficiently perform the track conversion work in which the rail remodeling occupies a large weight in a short period of time.

第2実施例 第2実施例においては、上記第1実施例の場合とは逆
に、外側ガイドレール5については高さ位置のみを変
え、内側ガイドレール4については高さおよび軌道幅方
向両位置を変えるようにしている。
Second Embodiment In the second embodiment, contrary to the case of the first embodiment, only the height position of the outer guide rail 5 is changed, and both the height and the track width direction positions of the inner guide rail 4 are changed. I am trying to change.

すなわち初期建設段階において、床版1における軌道中
心側の部分に左右三組のレール支柱取付用のアンカーボ
ルト(以下、支柱用アンカーボルトという)17,18,19を
側壁2に上下三組の支持プレート取付用のアンカーボル
ト(以下、プレート用アンカーボルトという)20,21,22
をそれぞれ等間隔置きに取付ける。そして、ガイドウェ
イバス用軌道としての初期使用時には、レール支柱8を
内側二組の支柱用アンカーボルト17,18に、支持プレー
ト13を下側二組のプレート用アンカーボルト20,21にそ
れぞれ第1実施例の場合と同様に取付け、レール支柱8
に内側ガイドレール4、支持プレート13に外側ガイドレ
ール5をそれぞれ取付ける。
That is, in the initial construction stage, three pairs of left and right anchor bolts (hereinafter referred to as column anchor bolts) 17,18,19 for mounting the rail post on the side wall of the floor slab 1 are supported on the side wall 2 in the upper and lower three sets. Anchor bolts for plate mounting (hereinafter referred to as plate anchor bolts) 20,21,22
Install at equal intervals. When initially used as a guideway bus track, the rail support 8 is first set to the inner two sets of anchor bolts 17 and 18, and the support plate 13 is first set to the lower two sets of plate anchor bolts 20 and 21, respectively. The rail support 8 is attached in the same manner as in the embodiment.
The inner guide rail 4 and the outer guide rail 5 are attached to the support plate 13 and the support plate 13, respectively.

一方、新交通システムへの転換時には、第2図(ロ)に
示すように、内側ガイドレール4については支柱受け台
12によって嵩上げした状態で内側二組の支柱用アンカー
ボルト18,19に移設し、外側ガイドレール5については
支持プレート13ごと上側二組のプレート用アンカーボル
ト21,22に移設することにより、両ガイドレール4,5を新
交通車両Mに対応する高位置に位置変更する。
On the other hand, at the time of conversion to the new transportation system, as shown in FIG.
The two guides are moved to the two anchor bolts for pillars 18 and 19 on the inner side in a state of being raised by 12 and the guide rails 5 for the outer guide rail 5 are moved to the two anchor bolts for plates 21 and 22 on the upper side so that both guides are supported. Relocate the rails 4,5 to a high position corresponding to the new transportation vehicle M.

第3実施例 第3実施例においては、ガイド幅は両システム共通とし
て、軌道改造時にレール高さ位置のみを変更するケース
として、初期建設時に、内側ガイドレール4は前記第1
実施例同様アンカーボルト6に、外側ガイドレール5は
前記第2実施例同様側壁2の下側二組のプレート用アン
カーボルト20,21にそれぞれレール支柱8、支持プレー
ト13を介して取付け、軌道改造時に、内側ガイドレール
4は支柱受け台12の加入による嵩上げによって、また外
側ガイドレール5は上側二組のプレート用アンカーボル
ト21,22に支持プレート13ごと移設することによって、
それぞれ同一軸方向位置において高さ位置を変更するよ
うにしている。
Third Embodiment In the third embodiment, the guide width is common to both systems, and only the rail height position is changed when the track is modified.
Similar to the second embodiment, the outer guide rail 5 is attached to the lower two sets of plate anchor bolts 20 and 21 of the side wall 2 via the rail support 8 and the support plate 13 as in the second embodiment, and the track is modified. At some times, the inner guide rail 4 is raised by adding the support pedestal 12, and the outer guide rail 5 is transferred to the upper two sets of plate anchor bolts 21 and 22 together with the support plate 13,
The height position is changed at the same axial position.

ところで、上記実施例ではレール取付具および支柱取付
具としてアンカーボルトを例に上げたが、これら取付具
は、レール支柱またはレール支持部材の形状、構造等に
応じて適宜変更可能である。また、本発明は上記した複
線軌道に限らず単線軌道にも適用しうることはいうまで
もない。
By the way, although the anchor bolts have been taken as an example of the rail attachment and the column attachment in the above-mentioned embodiment, these attachments can be appropriately changed depending on the shape, structure, etc. of the rail column or the rail support member. Further, it goes without saying that the present invention is applicable not only to the above-mentioned double track but also to a single track.

(発明の効果) 以上述べたように本発明によるときは、ガイドウェイバ
スシステムから新交通システムへのシステム転換に伴う
ガイドレールの高さ位置の変更作業を、一方のガイドレ
ールの嵩上げ、および他方のガイドレールの移設とうい
最小限の手間と労力によって簡単、迅速に行なうことが
でき、これによりシステム転換のための軌道改造工事の
工期短縮、工費節減を実現しうるものである。
(Effects of the Invention) As described above, according to the present invention, the work of changing the height position of the guide rails accompanying the system conversion from the guideway bus system to the new transportation system is performed by raising one of the guide rails and the other. The guide rails can be relocated easily and quickly with minimum effort and labor, which can shorten the construction period of track remodeling work for system conversion and reduce the construction cost.

【図面の簡単な説明】 第1図(イ)(ロ)は本発明の第1実施例、第2図
(イ)(ロ)は同第2実施例、第3図(イ)(ロ)は同
第3実施例をそれぞれ示すシステム転換前後の軌道の断
面図、第4図(イ)(ロ)は各実施例におけるシステム
転換前後のレール支柱およびガイドレールの取付状態を
示す拡大断面図、第5図は各実施例におけるレール支持
部材およびガイドレールの取付状態を示す拡大断面図で
ある。 1……床版、2……床版の側壁、3……走行路盤、4,5
……ガイドレール、B……ガイドウェイバス、M……新
交通車両、B1,M1……ガイドローラ、6,17,18,19……支
柱取付具としてのアンカーボルト、7,20……低位置用レ
ール取付具としてのアンカーボルト、11,22……高位置
用レール取付具としてのアンカーボルト、21……高位置
用および低位置用兼用レール取付具としてのアンカーボ
ルト、8……レール支柱、9……レール支持部材として
のレール支柱、12……支柱受け台、13……レール支持部
材としての支持プレート。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 (a) (b) is the first embodiment of the present invention, FIG. 2 (a) (b) is the same second embodiment, and FIG. 3 (a) (b). Is a cross-sectional view of the track before and after the system conversion showing the third embodiment, and FIGS. 4 (a) and (b) are enlarged cross-sectional views showing the mounting states of the rail support and the guide rail before and after the system conversion in each embodiment, FIG. 5 is an enlarged cross-sectional view showing a mounting state of the rail support member and the guide rail in each embodiment. 1 ... Floor slab, 2 ... Side wall of floor slab, 3 ... Roadbed, 4,5
…… Guide rails, B …… Guideway buses, M …… New transportation vehicles, B 1 , M 1 …… Guide rollers, 6,17,18,19 …… Anchor bolts for supporting columns, 7,20… … Anchor bolts for low position rail mounts, 11,22 …… Anchor bolts for high position rail mounts, 21 …… Anchor bolts for high position and low position combined rail mounts, 8 …… Rail stanchions, 9 ...... rail stanchions as rail support members, 12 ...... post pedestals, 13 ...... support plates as rail support members.

───────────────────────────────────────────────────── フロントページの続き (71)出願人 999999999 株式会社新潟鐵工所 東京都千代田区霞が関1丁目4番1号 (71)出願人 999999999 株式会社熊谷組 福井県福井市中央2丁目6番8号 (71)出願人 999999999 西武建設株式会社 東京都豊島区南池袋1丁目16番15号 (71)出願人 999999999 東急建設株式会社 東京都渋谷区渋谷1丁目16番14号 (72)発明者 神崎 紘郎 茨城県つくば市大字旭1番地 建設省土木 研究所内 (72)発明者 福本 陽三 兵庫県神戸市北区泉台2丁目7―2 (72)発明者 福元 勝郎 広島県三原市沼田東町末広315番地の31 (72)発明者 尾之内 昌二 愛知県名古屋市熱田区三本松町1番1号 (72)発明者 藤田 徹 埼玉県浦和市三室3747―7 ─────────────────────────────────────────────────── ─── Continuation of the front page (71) Applicant 999999999 Niigata Ironworks Co., Ltd. 1-4-1, Kasumigaseki, Chiyoda-ku, Tokyo (71) Applicant 999999999 Kumagai Gumi Co., Ltd. 2--6, Chuo, Fukui City, Fukui Prefecture No. (71) Applicant 999999999 Seibu Construction Co., Ltd. 1-16-15 Minamiikebukuro, Toshima-ku, Tokyo (71) Applicant 999999999 Tokyu Construction Co., Ltd. 1-16-14 Shibuya, Shibuya-ku, Tokyo (72) Inventor Kanzaki Hiroo, Asahi 1 Tsukuba, Ibaraki Prefectural Civil Engineering Research Institute, Ministry of Construction (72) Inventor Yozo Fukumoto 2-7-2 Izumidai, Kita-ku, Kobe, Hyogo (72) Inventor Katsuo Fukumoto 315 Suehiro, Numata Higashi-machi, Mihara-shi, Hiroshima 31 (72) Inventor Shoji Onouchi 1-1, Sanbonmatsu-cho, Atsuta-ku, Nagoya-shi, Aichi (72) Inventor Toru Fujita 3747-7 Muromuro, Urawa-shi, Saitama

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】車両走行路盤を備えた床版に、車両の左右
両側に張出されたガイドローラに接触して車両を誘導す
る左右両側ガイドレールが設けられて構成される車両誘
導軌道を、上記ガイドローラの高さ位置が異なる二種類
の車両に対応して上記ガイドレールの高さ位置を可変と
しうるように建設する車両誘導軌道の段階建設工法であ
って、上記床版における一方のガイドレールが取付けら
れる部分に、上記二種類の車両に対応する高位置用およ
び低位置用両レール取付具を設けるとともに、他方のガ
イドレールが取付けられる部分に支柱取付具を設け、初
期建設段階において、上記一方のガイドレールは、上記
低位置用レール取付具に取外し可能に取付けたレール支
持部材に、他方のガイドレールは、上記支柱取付具に取
外し可能に取付けたレール支柱にぞれぞれ取付け、車両
転換時において、上記一方のガイドレールは、上記低位
置用レール取付具から取外して上記高位置用レール取付
具にレール支持部材を介して取付け、他方のガイドレー
ルは、上記レール支柱と床版との間に支柱受け台を挿入
することによって高位置に位置替えすることを特徴とす
る車両誘導軌道の段階建設工法。
1. A vehicle guide track comprising a floor slab equipped with a vehicle running roadbed, and left and right guide rails for contacting guide rollers extending to the left and right sides of the vehicle to guide the vehicle. A step construction method of a vehicle guide track for constructing the guide rail so that the height position of the guide rail can be changed corresponding to two types of vehicles having different height positions of the guide rollers, and one guide in the floor slab In the portion where the rail is attached, both high position and low position rail attachments corresponding to the above two types of vehicles are provided, and the column attachment is provided in the portion where the other guide rail is attached, in the initial construction stage, One of the guide rails is detachably attached to the rail support member that is detachably attached to the low-position rail mount, and the other guide rail is detachably attached to the column mount. Each of them is attached to a rail post, and when the vehicle is converted, one of the guide rails is removed from the low-position rail mount and attached to the high-position rail mount via a rail support member, and the other guide is attached. A step construction method for a vehicle-guided track, characterized in that the rail is repositioned to a high position by inserting a support pedestal between the rail support and the floor slab.
JP7974488A 1988-03-30 1988-03-30 Stage construction method for vehicle guided track Expired - Lifetime JPH0759802B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7974488A JPH0759802B2 (en) 1988-03-30 1988-03-30 Stage construction method for vehicle guided track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7974488A JPH0759802B2 (en) 1988-03-30 1988-03-30 Stage construction method for vehicle guided track

Publications (2)

Publication Number Publication Date
JPH01250502A JPH01250502A (en) 1989-10-05
JPH0759802B2 true JPH0759802B2 (en) 1995-06-28

Family

ID=13698731

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7974488A Expired - Lifetime JPH0759802B2 (en) 1988-03-30 1988-03-30 Stage construction method for vehicle guided track

Country Status (1)

Country Link
JP (1) JPH0759802B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010044514A1 (en) * 2008-10-17 2010-04-22 Nam Hun Kang Method and apparatus for constructing railway for rubber-wheeled automated guideway transit system
JP2013035666A (en) * 2011-08-09 2013-02-21 Taihei Dengyo Kaisha Ltd Portal traveling crane

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4836709B2 (en) * 2006-08-22 2011-12-14 野地テック株式会社 Guide rail adjuster
KR100906684B1 (en) * 2007-08-27 2009-07-07 삼표이앤씨 주식회사 Guide rail fixing system of rubber wheel AGT
KR100906685B1 (en) * 2007-08-27 2009-07-07 삼표이앤씨 주식회사 Expansion joint of using the divering wheel of rubber wheel AGT
KR100910912B1 (en) * 2009-01-16 2009-08-05 강남훈 Guideway way construction method of automated guideway transit type light weight railway and thereof construction machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010044514A1 (en) * 2008-10-17 2010-04-22 Nam Hun Kang Method and apparatus for constructing railway for rubber-wheeled automated guideway transit system
JP2013035666A (en) * 2011-08-09 2013-02-21 Taihei Dengyo Kaisha Ltd Portal traveling crane

Also Published As

Publication number Publication date
JPH01250502A (en) 1989-10-05

Similar Documents

Publication Publication Date Title
KR890017438A (en) Vehicle parking system
JPH0759802B2 (en) Stage construction method for vehicle guided track
JPH01304294A (en) Underground railway of shielded tunnel as two-layer double track
CN210140770U (en) Cast-in-place bridge formwork support system device
CN210507089U (en) Simple bridge
JP2707881B2 (en) Floor side structure for moving objects
CN210886779U (en) Support upright post and monorail beam structure capable of being used for single-double rail transformation
DE19619867A1 (en) Method of manufacturing magnetic travel track
CN112681844B (en) Multi-layer three-dimensional parking system
JP2972287B2 (en) Track girder structure of branching device
RU2098301C1 (en) Monorail with air cushion cars
JP2613490B2 (en) Rail laying structure
KR102456420B1 (en) function expandable platform
GB2384223A (en) Trackway for personal rapid transport systems
JP2630579B2 (en) Connecting structure of lining plate
JP2004346735A (en) Structural system equipped with track for magnetic levitation transportation system supplied with power by linear electric motor
JP2000345517A (en) Connecting type movable form device
JPH1144187A (en) Constructing method for bulkhead inside shielded tunnel
JPH0949216A (en) Media strip protection fence
CN1837477A (en) Method and apparatus for quickly changing road traffic situation by employing module design
JP2002105912A (en) Temporary support device for bridge on road
JPH049901B2 (en)
KR200262651Y1 (en) Beam structure for supporting mobile bracket
JPH0734775Y2 (en) Liveline gauge land vehicle
JPS6133082B2 (en)

Legal Events

Date Code Title Description
S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term