JPH0742222A - Liquid tank made of concrete and repair lining work of sewer pipe and repair lining structure - Google Patents

Liquid tank made of concrete and repair lining work of sewer pipe and repair lining structure

Info

Publication number
JPH0742222A
JPH0742222A JP5185821A JP18582193A JPH0742222A JP H0742222 A JPH0742222 A JP H0742222A JP 5185821 A JP5185821 A JP 5185821A JP 18582193 A JP18582193 A JP 18582193A JP H0742222 A JPH0742222 A JP H0742222A
Authority
JP
Japan
Prior art keywords
lining
concrete
panel
metal frame
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5185821A
Other languages
Japanese (ja)
Other versions
JP2637356B2 (en
Inventor
Toshiyuki Noda
利幸 野田
Kazuhiko Tanaka
和彦 田中
Takatoshi Imafuku
崇敏 今福
Tsuneji Mito
常次 三戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsutsunaka Plastic Industry Co Ltd
Showa Sangyo Co Ltd
Original Assignee
Tsutsunaka Plastic Industry Co Ltd
Showa Sangyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsutsunaka Plastic Industry Co Ltd, Showa Sangyo Co Ltd filed Critical Tsutsunaka Plastic Industry Co Ltd
Priority to JP5185821A priority Critical patent/JP2637356B2/en
Publication of JPH0742222A publication Critical patent/JPH0742222A/en
Application granted granted Critical
Publication of JP2637356B2 publication Critical patent/JP2637356B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/20Controlling water pollution; Waste water treatment
    • Y02A20/208Off-grid powered water treatment

Abstract

PURPOSE:To facilitate a repair work and securely prevent corrosion after the repair work, by removing corroded faults on the wall face of a concrete body and charging a backing material into the clearance between the concrete wall face and a lining panel arranged at the external face of a metallic frame. CONSTITUTION:The corroded faults on the wall face 1a of a concrete body 1 are removed and the surface is conditioned as the base material and many anchor bolts 2 are buried in the wall face 1a. A female screw cylinder 5 of the fitting plate 4 of a frame body is fixed with the bolts 2. The fitting plate 4 is attached so as to be adjustable in the height. Next, stud bolts 6 are welded at the external face of fitting plate 4 and inserted in fitting holes 8 at the four corners of a rigid metallic frame 7 to fix the frame 7. A number of lining panels 12 made of hard vinyl chloride are fixed at the external face of the frame 7 by use of stud bolts 11. Preventive sash bars 18, 19 are arranged on the external face of the panel 12 to form a lattice and fixed thereon. A backing material 25 like concrete is charged in the space between the wall face la and the panel 12.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、例えば下水の集積処
理槽、汚泥処理槽等のコンクリート製液槽及び管渠等の
改修ライニング工法及び改修ライニング構造に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a repair lining construction method and a repair lining structure for concrete liquid tanks such as sewage integrated treatment tanks and sludge treatment tanks and pipes.

【0002】[0002]

【従来の技術】大容量の下水処理槽等の液槽や管渠等
は、一般に鉄筋コンクリート製のものとして地中に埋没
状態に建造設置されている。かかる液槽等は、その内部
に貯留される下水等からの揮発成分、とくに細菌によっ
て発生する硫酸その他の酸化物成分等の影響で、予測を
こえる短かい期間のうちに内面腐食を生じ、周囲の壁面
や天井面がぼろぼろになって構造強度が損われる事態を
生じ、近時この腐食の問題が大きくクローズアップされ
ている。
2. Description of the Related Art Liquid tanks such as large-capacity sewage treatment tanks and pipes are generally constructed and installed in the ground as reinforced concrete. Such liquid tanks are subject to internal corrosion within a short and unexpected period due to the influence of volatile components from sewage and the like stored inside, especially sulfuric acid and other oxide components generated by bacteria, and the surrounding environment. The wall surface and the ceiling surface of the building become worn out and the structural strength is impaired, and the problem of this corrosion has recently been greatly highlighted.

【0003】而して、上記のような腐食を発生したコン
クリート製液槽等は、安全性のためにも、爾後的に補修
を施し、望ましくは以降の腐食防止をはかり得るものと
することが強く求められている。
Therefore, for the sake of safety, the concrete liquid tank etc. in which the above-mentioned corrosion has occurred should be repaired after that, and preferably, the subsequent corrosion can be prevented. There is a strong demand.

【0004】従来、このような腐食したコンクリート液
槽等の改修のための工法としては、次のような方法が試
みられている。即ち、コンクリート躯体壁面(天井面を
含む意味において用いられる。)の腐食部分を取り除い
た後、当該壁面の内側に木材とか合板パネル等で型枠を
組み、型枠内にコンクリートを注入して養生硬化せしめ
た後、型枠を取り外して新規なコンクリート壁を構成
し、そしてこの新しいコンクリート壁面に例えばタール
系塗料等の耐薬品性の防食塗料を塗布して仕上げをした
り、あるいは耐薬品性の合成樹脂板を貼着固定して壁面
をライニングする工法が採られている。
Conventionally, the following method has been attempted as a method for repairing such a corroded concrete liquid tank. That is, after removing the corroded part of the concrete skeleton wall surface (used to include the ceiling surface), form a mold with wood or plywood panels on the inside of the wall surface and inject concrete into the mold to cure. After curing, remove the formwork to construct a new concrete wall, and then apply a chemical resistant anticorrosive paint such as tar paint to the new concrete wall for finishing or A construction method is used in which a synthetic resin plate is attached and fixed and the wall surface is lined.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、従来の
上記のような工法によるときは、第1に、新たなコンク
リート壁の築造工程と、コンクリート壁面の仕上げ処理
工程との二つの工程を必要とし、特に前者の工程に多く
の手間と時間がかかり、工期、工費のいずれの点でも好
ましいものではなかった。
However, when the conventional construction method as described above is used, firstly, two steps are required: a new concrete wall building step and a concrete wall finishing step, In particular, the former process requires a lot of labor and time, which is not preferable in terms of construction period and construction cost.

【0006】のみならず、コンクリート壁面に樹脂板等
でライニング被覆した場合においても、躯体強度はコン
クリート壁の強度のみに依存するものであるため、地震
等の外的な振動に対して不十分であり、耐久性に問題を
残すものであった。
Not only when the concrete wall is lined with a resin plate or the like but also the skeleton strength depends only on the strength of the concrete wall, it is not sufficient for external vibration such as an earthquake. There was a problem with durability.

【0007】一方、防食塗料で塗装仕上げした場合にお
いては、該塗料の塗層自体の耐薬品性、耐久性に問題が
あり、比較的短期間のうちに再び下地のコンクリート壁
面に腐食を生じやすく、恒久的なものになし得なかっ
た。
[0007] On the other hand, when the coating is finished with an anticorrosion paint, there is a problem in the chemical resistance and durability of the coating layer itself of the paint, and corrosion is likely to occur again on the concrete wall surface of the base in a relatively short period of time. , Couldn't be permanent.

【0008】この発明は、上記のような従来の問題点に
鑑み、腐食を生じた鉄筋コンクリート製の液槽等につ
き、改修を施すことによってもとの構造物にも増して強
度的に一段と優れたものとすることができ、かつ改修後
においては腐食の発生のおそれのないものとし、しかも
比較的簡易な作業で改修工事を完了することができるよ
うな改修ライニング工法及びそれによって構築される改
修ライニング構造を提供することを目的とする。
In view of the above-mentioned conventional problems, the present invention is superior in strength to the original structure by repairing a corroded liquid tank made of reinforced concrete, etc. The repair lining method and the repair lining constructed by the repair lining method that can be completed without any risk of corrosion after the repair, and can complete the repair work with relatively simple work. It is intended to provide a structure.

【0009】[0009]

【課題を解決するための手段】上記の目的において、本
願第1の発明は、下水処理槽等の液槽あるいは管渠等の
改修ライニング工法に係るものであって、上記液槽等の
コンクリート躯体壁面の腐食欠陥部を除去したのち素地
調整し、該壁面に所定配置に多数個のアンカーボルトを
固植し、上記躯体壁面との間に所定間隔を隔てゝ剛性金
属枠体を配置しかつ上記アンカーボルトを利用して該金
属枠体を直接または間接に固定し、次いで上記金属枠体
の外面側に硬質合成樹脂製の多数個のライニングパネル
を並べて配設し、かつ該各ライニングパネルを上記金属
枠体に ボルト・ナットで締結固定すると共に、次い
で、更に該ライニングパネル群の外面側に棒状抑止棧を
格子状配置等に配列してこれをライニングパネル面上に
固定金具で固定し、しかる後前記躯体壁面とライニング
パネルとの間の空間部内にコンクリート等の裏込材を注
入充填し、そして、上記裏込材の養生硬化後、前記抑止
棧及びその固定金具を除去することを特徴とする液槽等
の改修ライニング工法を要旨とするものである。
For the above object, the first invention of the present application relates to a repair lining construction method for a liquid tank such as a sewage treatment tank or a pipe, and a concrete frame for the liquid tank. After removing the corrosion defect portion of the wall surface, the base material is adjusted, a large number of anchor bolts are fixedly planted on the wall surface in a predetermined arrangement, and a rigid metal frame body is arranged at a predetermined distance from the body wall surface and The metal frame body is directly or indirectly fixed using an anchor bolt, and then a plurality of hard synthetic resin lining panels are arranged side by side on the outer surface side of the metal frame body, and each of the lining panels is arranged as described above. Fasten and fix it to the metal frame with bolts and nuts, and then arrange rod-like restraining ties on the outer surface side of the lining panel group in a grid arrangement, etc., and fix it on the lining panel surface with fixing metal fittings. After curing, a backing material such as concrete is injected and filled into the space between the wall surface of the body and the lining panel, and after the curing of the backing material, the restraint shaft and its fixing metal fittings are removed. The lining method is a repair lining method for liquid tanks.

【0010】好ましくは、上記のライニングパネルして
は、硬質合成樹脂製のパネル本体の周側面に緩衝用の弾
性薄板を貼着一体化したものが用いられ、パネルの熱伸
縮あるいは地震時振動等によって隣接パネル間に加わる
応力を上記弾性薄板で吸収して、ライニング被覆の破損
や目地部分のシール不良の発生を防止するものとなされ
る。
[0010] Preferably, the lining panel is a panel body made of a hard synthetic resin, and an elastic thin plate for cushioning is integrally attached to the peripheral side surface of the panel body. Thus, the stress applied between the adjacent panels is absorbed by the elastic thin plate to prevent the damage of the lining coating and the occurrence of the sealing failure at the joint portion.

【0011】また、金属枠体の取付固定を簡単かつ確実
に行いうるものとするために、次のような工程を採用す
るのが有利である。即ち、コンクリート躯体壁面に固植
されたアンカーボルトの先端に、所定大の金属板からな
る枠体取付板を、その背面に有する雌ねじ筒部を上記ボ
ルトに螺合して高さ調節自在に装着し、該枠体取付板の
レベル調整を行った後、前記金属枠体を該取付板にボル
ト・ナットで締結固定するものとするのが有利である。
Further, it is advantageous to adopt the following steps so that the metal frame can be attached and fixed easily and surely. That is, a frame body mounting plate made of a metal plate of a predetermined size is attached to the tip of an anchor bolt that is fixedly planted on the wall surface of a concrete frame, and a female threaded cylinder portion on the back surface of the frame body mounting plate is screwed onto the bolt so that the height can be adjusted freely. After adjusting the level of the frame mounting plate, it is advantageous to fasten and fix the metal frame to the mounting plate with bolts and nuts.

【0012】更にまた、ライニングパネル面上に配設さ
れる抑止棧の取付固定は、次のようにして行うのが有利
である。即ち、金属枠体に固着するライニングパネル取
付用のスタッドボルトとして、その長さ方向の中間部に
括れ部を有して、該括れ部より先端側をノックオフ部と
したものを用い、ライニングパネルの取付固定後におい
て該パネル面上からスタッドボルトの上記ノックオフ部
を突出せしめるものとし、このノックオフ部に前記固定
金具を取付けて前記抑止棧を固定するものとするのが好
ましい。
Furthermore, it is advantageous to mount and fix the restraint board arranged on the surface of the lining panel as follows. That is, as a stud bolt for attaching a lining panel that is fixed to a metal frame, a stud bolt that has a constricted portion at the middle portion in the length direction and has a knock-off portion on the tip side from the constricted portion is used. It is preferable that the knock-off portion of the stud bolt is made to project from the panel surface after the attachment and fixation, and the fixing metal fitting is attached to the knock-off portion to fix the restraining rod.

【0013】本願第2の発明は、上記ライニング工法に
よって得られる液槽等のライニング構造に関し、液槽等
のコンクリート躯体壁面に所定配置に多数個のアンカー
・ボルトが固植され、前記躯体壁面との間に所定間隔を
隔てゝ剛性金属枠体が配置され、該金属枠体が前記アン
カーボルトの先端部に直接または間接に固定されるとと
もに、前記金属枠体の外面側に多数個の硬質合成樹脂板
からなるライニングパネルが敷き並べ状態に配置され、
該ライニングパネルが前記金属枠体にボルト・ナットで
締結固定されるとともに、前記躯体壁面とライニングパ
ネルとの間の空間部内にコンクリート等の裏込材が注入
充填されかつ固化されてなることを特徴とするものであ
る。
The second invention of the present application relates to a lining structure for a liquid tank or the like obtained by the above-mentioned lining construction method, wherein a large number of anchor bolts are fixedly planted in a predetermined arrangement on the wall surface of a concrete frame of the liquid tank or the like, and A rigid metal frame body is arranged at a predetermined interval between the metal frame body and the metal frame body is directly or indirectly fixed to the tip end portion of the anchor bolt, and a large number of hard composites are formed on the outer surface side of the metal frame body. Lining panels made of resin plates are laid out in a line,
The lining panel is fastened and fixed to the metal frame body with bolts and nuts, and a backing material such as concrete is injected and solidified in a space between the wall surface of the body and the lining panel. It is what

【0014】ライニングパネルは、最も一般的には耐薬
品性、コスト等の面での有利性から、塩化ビニル樹脂か
らなるものが好適に用いられる。
The lining panel is most preferably made of vinyl chloride resin because of its advantages in terms of chemical resistance and cost.

【0015】また、ライニングパネルは、隣接するパネ
ルとの間の目地部分のシ−ル性を完全なものとするべ
く、好ましくは周縁部外面に浅い段部を有し、隣接する
パネル間にまたがって上記段部に対応断面形状の帯状目
地被覆材が嵌め込まれ、接着固定されたものとなされ
る。
Further, the lining panel preferably has a shallow step portion on the outer surface of the peripheral portion so as to complete the sealing property of the joint portion between the adjacent panels, and extends over the adjacent panels. Then, the band-shaped joint covering material having a corresponding cross-sectional shape is fitted into the step portion and is fixed by adhesion.

【0016】なお、この発明に用いられる裏込材として
は、一般的な普通コンクリートのほか、水性ディスパー
ジョンセメント系、水溶性ポリマーセメント系等のポリ
マーセメント系コンクリートやモルタル、更にはエポキ
シ樹脂等の合成樹脂組成物等を使用可能なものとして挙
示することができる。
The backing material used in the present invention includes, in addition to general ordinary concrete, polymer cement concrete such as water-based dispersion cement and water-soluble polymer cement, mortar, and epoxy resin. The synthetic resin composition and the like can be mentioned as usable.

【0017】[0017]

【実施例】次に、この発明の好適な実施例を添付図面に
基いて説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT A preferred embodiment of the present invention will now be described with reference to the accompanying drawings.

【0018】図1ないし図8に示す実施例は、腐食した
下水処理槽等の液槽の改修施工例を示すものである。か
かる液槽の腐食したコンクリート躯体(1)の壁面(1
a)は、多くの場合ぼろぼろの状態であるので、その腐
食欠陥部を適宜の掻取り工具等を用いて除去したのち、
その表面の素地調整を施す。
The embodiment shown in FIGS. 1 to 8 shows an example of repair work of a liquid tank such as a corroded sewage treatment tank. The wall surface (1) of the corroded concrete frame (1) of the liquid tank
In the case of a), in most cases, it is in a tattered state, so after removing the corrosion defect portion with an appropriate scraping tool,
The base material of the surface is adjusted.

【0019】そして、図1、2に示すように、該壁面
(1a)に所定の配列ピッチに多数本のアンカーボルト
(2)を固植する。例えばコンクリート躯体(1)に壁
面側から孔(3)を穿設し、これにアンカー部(2a)
を挿入してその裾部を強制拡開することにより、アンカ
ーボルト(2)を強固に立設固定する。
Then, as shown in FIGS. 1 and 2, a large number of anchor bolts (2) are fixedly planted on the wall surface (1a) at a predetermined arrangement pitch. For example, a hole (3) is made in the concrete frame (1) from the wall surface side, and an anchor portion (2a) is provided in this hole.
The anchor bolt (2) is firmly erected and fixed by inserting and forcibly expanding the hem.

【0020】次に、このアンカーボルト(2)の先端に
Tプレートと称されるような枠体取付板(4)を取付け
る。この枠体取付板(4)は、例えば10cm角程度の
鋼板からなるもので、その背面中央部に雌ねじ筒(5)
を有し、図3に示すように該雌ねじ筒(5)をボルト
(2)に螺合することにより、高さ調節可能に装着せし
めるものする。
Next, a frame mounting plate (4) called a T plate is attached to the tip of the anchor bolt (2). The frame mounting plate (4) is made of, for example, a steel plate of about 10 cm square, and has a female screw cylinder (5) at the center of its back surface.
The height is adjustable by screwing the female screw cylinder (5) onto the bolt (2) as shown in FIG.

【0021】次に、上記枠体取付板(4)の外面、即ち
槽内面側の適宜位置に、スタッドボルト(6)を溶接固
着して立設する。もとより、これは予め枠体取付板
(4)に取り付けておくものとしても良い。なお、スタ
ッドボルト(6)は、次工程の金属枠体(7)の取り付
けの便宜のために、図1に示すように長さの中間部に切
断用の括れ部(6b)を有し、それより先端側をノック
オフ部(6a)としたものを用いるのが好ましい。そし
て、上記枠体取付板(4)をアンカーボルト(2)の軸
線周りに回転して、全ての枠体取付板(4)が同一平面
内に位置するように、その高さ調節を行う。
Next, a stud bolt (6) is welded and fixedly erected on the outer surface of the frame mounting plate (4), that is, at an appropriate position on the inner surface of the tank. Of course, this may be attached to the frame attachment plate (4) in advance. The stud bolt (6) has a constriction portion (6b) for cutting at an intermediate portion of its length as shown in FIG. 1 for the convenience of attaching the metal frame body (7) in the next step. It is preferable to use a knock-off portion (6a) on the tip side. Then, the frame mounting plate (4) is rotated around the axis of the anchor bolt (2), and the height of the frame mounting plate (4) is adjusted so that all the frame mounting plates (4) are located in the same plane.

【0022】続いて、槽壁の強度部材となる剛性金属枠
体(7)の取付けを行う。該枠体(7)は、図1ないし
図3の参照によって理解し得るように、鋼製アングル材
をもって1辺の長さを500mm程度とする額縁状の周枠
部(7a)と、その中央部に1つの縦枠部(7b)とを
有する正方形の枠体からなり、その四隅部に内方に向い
て突出した取付け用ブラケット部(7c)が設けられて
いる。(8)は該ブラケット部(7c)に設けられた取
付孔である。而して、金属枠体(7)は、その四隅部の
任意の1つの取付孔(8)に前記スタッドボルト(6)
を適合させて挿通し、ワッシャ(9)を介してナット
(10)をかけて締結固定する。また、これだけでは取
付強度に不十分であるので、更に隣接する金属枠体
(7)(7)同士を、図3に示すように連結孔(16
a)を通じてボルト・ナット(16)で締結固定して連
結する。そして、かかる作業を繰り返し、多数個の金属
枠体(7)を隣接するものどうしで相互に密接する状態
に縦横に配列し、該枠体群をもって前記コンクリート壁
面(1a)から所定間隔(S)を隔てた位置に補強枠組
みを形成する。なお、前記スタッドボルト(6)のノッ
クオフ部(6a)は、上記枠体取付け後に切断用括れ部
(6b)で折って除去する。
Subsequently, the rigid metal frame body (7) which is a strength member for the tank wall is attached. As can be understood by referring to FIGS. 1 to 3, the frame body (7) includes a frame-shaped peripheral frame portion (7a) having a steel angle member with a side length of about 500 mm, and a central portion thereof. It is composed of a square frame body having one vertical frame portion (7b), and mounting bracket portions (7c) protruding inward are provided at four corners thereof. (8) is a mounting hole provided in the bracket portion (7c). Then, the metal frame body (7) has the stud bolts (6) in any one of the mounting holes (8) at its four corners.
Are fitted and inserted, and a nut (10) is applied through a washer (9) to fasten and fix them. Further, since this alone is not sufficient for the mounting strength, the adjacent metal frame bodies (7) and (7) are connected to each other by connecting holes (16) as shown in FIG.
Fasten and connect with bolts and nuts (16) through a). Then, by repeating such work, a large number of metal frame bodies (7) are arranged vertically and horizontally in a state in which adjacent metal bodies are in close contact with each other, and the frame body group is arranged at a predetermined interval (S) from the concrete wall surface (1a). A reinforcing frame is formed at positions separated from each other. The knock-off portion (6a) of the stud bolt (6) is folded and removed by the cutting constriction portion (6b) after the frame is attached.

【0023】次に、上記各金属枠体(7)について、そ
の周枠部(7a)の四隅部と、縦枠部(7b)の中央部
との5個所に、図2に示すようにそれぞれスタッドボル
ト(11)を溶接固定して立設する。もとより、このス
タッドボルト(11)は予め金属枠体(7)に取付けて
おくものとしても良い。またこのスタッドボルト(1
1)には、長さの中間部に切断用の括れ部(11b)を
有して、それより先端側を部分をノックオフ部(11
a)としたもの用いるものとする。
Next, with respect to each of the metal frame bodies (7), as shown in FIG. 2, the four corner portions of the peripheral frame portion (7a) and the central portion of the vertical frame portion (7b) are respectively arranged at five points as shown in FIG. The stud bolt (11) is welded and fixed to stand. Of course, the stud bolt (11) may be attached to the metal frame body (7) in advance. Also, this stud bolt (1
1) has a constricting part (11b) for cutting in the middle part of the length, and the part on the tip side from that has a knock-off part (11b).
The one described in a) shall be used.

【0024】そして、次に上記金属枠体(7)の外面側
に、対応大の方形に形成した多数個のライニングパネル
(12)を当接配置し、前記スタッドボルト(11)を
利用してこれを固定する。
Next, a large number of square lining panels (12) formed in a corresponding size are arranged in contact with the outer surface of the metal frame (7), and the stud bolts (11) are used. Fix this.

【0025】ライニングパネル(12)は、硬質合成樹
脂製のものであり、その樹脂材質は特に限定されるもの
ではなく、耐薬品性、機械的強度に優れたものであれば
何でも使用可能出あるが、特にコスト面を考慮した場合
硬質塩化ビニル樹脂板を好適に用い得る。
The lining panel (12) is made of a hard synthetic resin, and the resin material is not particularly limited, and any material having excellent chemical resistance and mechanical strength can be used. However, in consideration of cost, a hard vinyl chloride resin plate can be preferably used.

【0026】図示実施例において、ライニングパネル
(12)は、図4、5に示すように、厚さ20mm程度
の硬質塩化ビニル樹脂板からなるパネル本体(12a)
と、その四周側面に貼着一体化された軟質塩化ビニル樹
脂製の緩衝用弾性薄板(12b)とで構成されている。
上記弾性薄板(12b)は、施工後隣接して配置される
ライニングパネル(12)(12)間に介在して緩衝作
用を果し、パネルの伸縮、地震時の振動等によって加わ
る応力を吸収して、ライニング被覆に損壊を生じるのを
防ぐのに役立つものである。従って、弾性材料からなる
ものであれば他の任意の材料に置換しても良い。
In the illustrated embodiment, the lining panel (12) is a panel body (12a) made of a hard vinyl chloride resin plate having a thickness of about 20 mm, as shown in FIGS.
And a cushioning elastic thin plate (12b) made of a soft vinyl chloride resin, which is attached and integrated on the four side surfaces thereof.
The elastic thin plate (12b) is interposed between the lining panels (12) (12) arranged adjacent to each other after the construction so as to perform a cushioning function and absorb stress applied by expansion and contraction of the panel, vibration during an earthquake, or the like. And helps prevent damage to the lining coating. Therefore, another material may be substituted as long as it is made of an elastic material.

【0027】また、ライニングパネル(12)は、周縁
部外側面に、幅20mm、高さ3mm程度の浅い切欠段部
(13)が形成され、施工後に隣接パネル間にまたがる
態様に対応断面形状の目地被覆材(14)を嵌合しうる
ものとなされている。また、パネル本体(12a)部分
の四隅部と中央部に合計5個の取付用孔(15)が穿設
されている。この取付用孔(15)は、図5に示すよう
に、パネルの背面側から、順次径大としたボルト挿通孔
部(15a)、ナット嵌合孔部(15b)、及び封鎖片
嵌合孔部(15c)が階段状に形成されたものとなされ
ている。
Further, the lining panel (12) has a shallow notch step portion (13) having a width of 20 mm and a height of 3 mm formed on the outer surface of the peripheral edge portion, and has a cross-sectional shape corresponding to a mode in which it extends between adjacent panels after construction. The joint covering material (14) can be fitted therein. Further, a total of five mounting holes (15) are formed at the four corners and the center of the panel body (12a). As shown in FIG. 5, the mounting hole (15) has a bolt insertion hole portion (15a), a nut fitting hole portion (15b), and a blocking piece fitting hole, which are sequentially increased in diameter from the rear surface side of the panel. The part (15c) is formed stepwise.

【0028】而して、ライニングパネル(12)の取付
けは、その5個の取付孔(15)に金属枠体(7)から
突設されたスタッドボルト(11)を適合させて挿通
し、外面側から円形ナット(17)をかけて締結固定す
ることによって行う。この固定後において、ナット(1
7)は取付孔(15)のナット嵌合孔部(15b)内に
納まり、スタッドボルト(11)のノックオフ部(11
a)は、パネル(12)を貫通してその外面側に大きく
突出したものとなされる。
In order to mount the lining panel (12), the stud bolts (11) projecting from the metal frame (7) are fitted into the five mounting holes (15) and inserted, and the outer surface It is done by fastening a circular nut (17) from the side and fastening. After this fixing, the nut (1
7) is housed in the nut fitting hole portion (15b) of the mounting hole (15), and the knock-off portion (11) of the stud bolt (11).
The a) is formed by penetrating the panel (12) and largely protruding to the outer surface side thereof.

【0029】上記の如くして、多数個のライニングパネ
ル(12)を縦横配列に面状配置して固定した後、隣接
パネル相互間に残ることのある隙間部分、及び取付用ナ
ット(17)の周辺部分にシーリング剤を充填して止水
処理を施す。これによって実質的に液槽のコンクリート
壁の内側に、その壁面(1a)と略平行する形に止水効
果をもった一体のライニング壁を完成する。
As described above, after fixing a large number of lining panels (12) arranged in a plane in a vertical and horizontal arrangement, the gaps that may remain between the adjacent panels and the mounting nut (17). The peripheral part is filled with a sealing agent and a waterproof treatment is applied. As a result, an integral lining wall having a water blocking effect is completed inside the concrete wall of the liquid tank substantially parallel to the wall surface (1a).

【0030】そこで、次に上記コンクリート壁面(1
a)とライニング壁との間の空間部にコンクリート等の
裏込材を注入充填してライニング構成部材の全体を一体
化するが、ライニング壁を補強しないままに裏込材の注
入充填を行うと、ライニングパネル(12)が裏込材の
注入充填圧で撓曲変形し、あるいはライニング壁の損壊
を生じるおそれがある。
Then, next, the concrete wall surface (1
The space between a) and the lining wall is filled with a backing material such as concrete to integrate the entire lining component, but if the backing material is poured and filled without reinforcing the lining wall, The lining panel (12) may be flexibly deformed by the injection filling pressure of the backing material, or the lining wall may be damaged.

【0031】このため、裏込材注入を行う前に、予めラ
イニング壁の外面側に抑止用の補強枠組みを施工する。
この補強枠組みの好ましい施工例を図6、7に示す。同
図に示すように、ライニング壁の外面に沿わせて多数本
の鋼管等からなる水平抑止棧(18)を平行状に配置
し、固定金具(20)でこれらを固定すると共に、更に
上記水平抑止棧(18)上に同様の鋼管等からなる垂直
抑止棧(19)を所定ピッチに配列固定して格子状の補
強枠組を構成する。
Therefore, before the backfill material is injected, a reinforcement frame for restraint is previously constructed on the outer surface side of the lining wall.
A preferred construction example of this reinforcing frame is shown in FIGS. As shown in the figure, along the outer surface of the lining wall, a plurality of horizontal pipes (18) composed of steel pipes are arranged in parallel and fixed with a fixing metal fitting (20), and further, the above horizontal Vertical restraining rods (19) made of the same steel pipe or the like are arranged and fixed at a predetermined pitch on the restraining rods (18) to form a lattice-shaped reinforcing frame.

【0032】ここに、抑止棧(18)(19)の固定金
具(20)は、図1、6に示すように、ライニングパネ
ル(12)面上に突出したスタッドボルト(11)のノ
ックオフ部(11a)にセンタースピンドル(21)の
一端の雌ねじ部(21a)を螺合してこれに取付けるも
のとし、該スピンル(21)に昇降自在に組付けられた
押え翼部材(22)を抑止棧(18)(19)の外面に
押圧せしめた後、スピンドル(21)の後部の雄ねじ部
(21b)に具備するナット(23)を締め付けること
により、上記押え翼部材(22)で抑止棧(18)(1
9)を抑圧固定しうるようになされたものである。
As shown in FIGS. 1 and 6, the fixing metal fitting (20) of the restraining rods (18) and (19) has a knock-off portion () of the stud bolt (11) protruding above the surface of the lining panel (12). The female screw portion (21a) at one end of the center spindle (21) is screwed to the center spindle (21a) and attached thereto, and the presser blade member (22) assembled to the spinle (21) so as to be able to move up and down is restrained. 18) After being pressed against the outer surface of (19), by tightening the nut (23) provided on the male screw portion (21b) at the rear of the spindle (21), the restraining blade (18) is held by the pressing blade member (22). (1
It is designed to suppress and fix 9).

【0033】上記の抑止棧(18)(19)による補強
枠組を施工した後、前述したようにコンクリート躯体壁
面(1a)とライニングパネル(12)によるライニン
グ壁との間の空間部内に、裏込材(25)(図8参照)
の注入充填を行う。
After constructing the reinforcing frame by the above-mentioned restraining shafts (18), (19), as described above, backfilling is performed in the space between the concrete skeleton wall surface (1a) and the lining wall by the lining panel (12). Material (25) (see FIG. 8)
Injection filling.

【0034】そして、上記注入裏込材(25)の養生硬
化後、固定金具(20)の押え翼部材(22)を緩めて
抑止棧(18)(19)を撤去し、更にスタッドボルト
(11)を切断用括れ部(11b)で折ってノックオフ
部(11a)を切り離し、固定金具(20)とともに除
去する。
After the injection backing material (25) is cured and hardened, the holding blade members (22) of the fixing fittings (20) are loosened to remove the restraining rods (18) and (19), and further the stud bolts (11). ) Is folded at the cutting constriction portion (11b) to separate the knock-off portion (11a), and is removed together with the fixing metal fitting (20).

【0035】最後に、隣接するライニングパネル(1
2)(12)間の目地部分に形成される浅い溝部分、即
ち前記切欠段部(13)(13)によって形成される凹
部内に、対応断面形状の硬質合成樹脂製の帯状目地被覆
材(14)(図5、8参照)を嵌め込み、かつ接着固定
すると共に、取付け孔(15)の封鎖片嵌合孔部(15
c)に、対応形状の硬質合成樹脂製封鎖片(24)(図
3、8参照)を嵌め込んで接着固定する。そして、更に
要すれば、上記目地被覆材(14)及び封鎖片(24)
の周辺部分をシーリング剤で止水処理し、改修工事のす
べてを完了する。
Finally, the adjacent lining panel (1
2) In the shallow groove portion formed in the joint portion between (12), that is, in the concave portion formed by the notch step portions (13) and (13), a strip-shaped joint covering material (corresponding to a cross-sectional shape) made of hard synthetic resin ( 14) (see FIGS. 5 and 8) is fitted and adhesively fixed, and the sealing piece fitting hole portion (15) of the mounting hole (15) is attached.
A hard synthetic resin sealing piece (24) of a corresponding shape (see FIGS. 3 and 8) is fitted into c) and fixed by adhesion. Then, if necessary, the joint covering material (14) and the blocking piece (24).
Complete the repair work by waterproofing the surrounding area with a sealant.

【0036】したがって、上記によって施工されたライ
ニング構造は、図8に示すような構成を有する。即ち、
液槽のコンクリート躯体(1)の壁面(1a)に所定配
置に多数個のアンカーボルト(2)が固植され、前記躯
体壁面(1a)との間に所定間隔を隔てゝ剛性金属枠体
(7)が配置され、該金属枠体が前記アンカーボルト
(9)の先端部に直接または間接に固定されるととも
に、前記金属枠体(7)の外面側に多数個の硬質合成樹
脂板からなるライニングパネル(12)が敷き並べ状態
に配置され、該ライニングパネル(12)が前記金属枠
体(7)にボルト・ナット(11)(17)で締結固定
されると共に、前記躯体壁面(1a)とライニングパネ
ル(12)との間の空間部内に裏込材(25)が注入充
填されかつ固化されてなる構成を有する。
Therefore, the lining structure constructed as described above has a structure as shown in FIG. That is,
A large number of anchor bolts (2) are fixedly planted on a wall surface (1a) of the concrete body (1) of the liquid tank in a predetermined arrangement, and a rigid metal frame ( 7) is arranged, the metal frame body is fixed directly or indirectly to the tip of the anchor bolt (9), and a large number of hard synthetic resin plates are formed on the outer surface side of the metal frame body (7). The lining panels (12) are arranged side by side, and the lining panels (12) are fastened and fixed to the metal frame body (7) with bolts and nuts (11) and (17), and the body wall surface (1a) is also fixed. The backing material (25) is injected and filled and solidified in the space between the lining panel (12) and the lining panel (12).

【0037】図9及び図10は、この発明をコンクリー
ト製管渠の改修施工例を示すものである。
FIG. 9 and FIG. 10 show an example of repair work for a concrete pipe according to the present invention.

【0038】この場合、金属枠体(37)及びライニン
グパネル(42)は、管渠のコンクリート躯体(31)
の径に対応して、同方向に複数個のセグメント単位に分
割された弯曲状のものを用いるものとする。また、コン
クリート躯体壁面(31a)とライニングパネル(4
2)との間の空間部内への裏込材(55)の注入充填
は、例えば、環状の上記空間部の両端を閉鎖したのち、
この端面閉鎖部材の少なくとも一方または両方に設けた
注入口から裏込材を圧力注入することによって支障なく
行いうる。また、この裏込材(55)の注入充填に先立
ってパネル面上に組付けられる抑止用の補強枠組は、図
9に鎖線で示すように、鋼管等の抑止棧(48)を各ラ
イニングパネル(42)の中央部上において、管渠の軸
線方向に水平状に所要本数を平行状に配置するものとす
るのが一般的である。
In this case, the metal frame (37) and the lining panel (42) are the concrete frame (31) of the pipe ditch.
According to the diameter of, the curved shape divided into a plurality of segment units in the same direction is used. In addition, the concrete wall surface (31a) and the lining panel (4
Injecting and filling the backing material (55) into the space portion between 2) and, for example, after closing both ends of the annular space portion,
This can be done without trouble by pressure-injecting the backing material from the injection port provided in at least one or both of the end face closing members. Further, the reinforcing frame for restraint which is assembled on the panel surface prior to the filling and filling of the backing material (55) has a restraint shaft (48) such as a steel pipe as shown in a chain line in FIG. On the central part of (42), it is general to arrange the required number in parallel horizontally in the axial direction of the pipe.

【0039】その他の事項は、図1ないし図8に示した
実施例の施工例の場合と同様であり、相互に対応部分を
同一の符号で示して重複説明を省略する。
Other matters are the same as in the case of the construction example of the embodiment shown in FIGS. 1 to 8, and the corresponding portions are designated by the same reference numerals, and the duplicated description will be omitted.

【0040】以上、この発明の好ましい実施例について
説明したが、この発明は特許請求の範囲に記載した構成
を逸脱しない範囲で任意の設計的変更が許容されるもの
であり、図示実施例の具体的構成に何ら限定されるもの
ではない。
The preferred embodiment of the present invention has been described above. However, the present invention allows any design change without departing from the configuration described in the claims, and the embodiment of the embodiment shown in the drawings. It is not limited to the physical composition.

【0041】[0041]

【発明の効果】この発明の改修ライニング工法によれ
ば、コンクリート躯体壁面(1a)(31a)との間に
所定間隔を隔てて予めライニングパネル(12)(4
2)によるライニング壁を施工し、該ライニング壁を裏
込材の型枠に利用してコンクリート等の裏込材(25)
(55)の注入充填を行うものであるから、別途型枠を
組んで裏込材注入を行う場合に較べて資材の節減、工期
の短縮、労務の軽減をはかり得る。
According to the repair lining construction method of the present invention, the lining panels (12) (4) are preliminarily spaced from the concrete skeleton wall surfaces (1a) (31a) by a predetermined distance.
The lining wall according to 2) is constructed, and the lining wall is used as a formwork for the backing material and the backing material such as concrete (25)
Since the injection filling of (55) is performed, the material can be saved, the construction period can be shortened, and the labor can be reduced as compared with the case where the backing material is injected by forming a separate mold.

【0042】かつ、裏込材(25)の注入によって新た
に形成される裏込材壁体内に、液槽等のコンクリート躯
体(1)側とアンカーボルト(2)で連結一体化された
金属枠体(7)(37)が埋設されたものとなり、液槽
や管渠の全体の強度の顕著な増大をはかり得る。
In addition, a metal frame integrally connected to the concrete skeleton (1) side such as a liquid tank by an anchor bolt (2) in the backfill material wall body newly formed by injecting the backfill material (25). Since the bodies (7) and (37) are buried, the strength of the whole of the liquid tank and the pipe can be significantly increased.

【0043】また、液槽等の躯体内面は、硬質合成樹脂
からなるライニングパネルによるライニング壁で被覆さ
れるので、恒久的に優れた耐蝕性を有する液槽や管渠に
改修することができるとともに、ライニング壁は表面平
滑性に優れたものとなし得るので、下水等の槽内貯留
液、流動液の滞留のない流下特性に優れたものとなしう
る。
Further, since the inner surface of the body such as the liquid tank is covered with the lining wall of the lining panel made of hard synthetic resin, it can be repaired into a liquid tank or a pipe having a permanently excellent corrosion resistance. Since the lining wall can be made to have excellent surface smoothness, it can be made to have excellent flow-down characteristics without retention of the stored liquid in the tank such as sewage or the flowing liquid.

【0044】この発明のライニング工法によって施工さ
れる請求項5のライニング構造においても、実質的に上
記同様の効果を実現しうるものであり、またその他の請
求項に記載された限定事項に基ずく作用効果は、実施例
の説明に記述されたとおりである。
Also in the lining structure of claim 5 which is constructed by the lining method of the present invention, substantially the same effect as described above can be realized, and based on the restrictions described in other claims. The function and effect are as described in the description of the embodiment.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明に係るコンクリート製液槽の改修ライ
ニング工法に用いられる構成部材を分離状態にして示し
た斜視図である。
FIG. 1 is a perspective view showing constituent members used in a repair lining method of a concrete liquid tank according to the present invention in a separated state.

【図2】金属枠体の取付施工状態を示す斜視図である。FIG. 2 is a perspective view showing a mounting state of a metal frame body.

【図3】ライニングパネルの取付前の状態を、図2のII
−II線に沿う部分において示した断面図である。
FIG. 3 shows the state before mounting the lining panel, II in FIG.
It is sectional drawing shown in the part along the II line.

【図4】ライニングパネルの正面図である。FIG. 4 is a front view of a lining panel.

【図5】図4のV−V線の断面図である。5 is a cross-sectional view taken along line VV of FIG.

【図6】ライニング壁の施工後、その外面に補強枠組を
施工した状態を示す斜視図である。
FIG. 6 is a perspective view showing a state in which a reinforcing frame is applied to the outer surface of the lining wall after the construction.

【図7】補強枠組の構成例を示す正面図である。FIG. 7 is a front view showing a configuration example of a reinforcing frame.

【図8】改修ライニング構造の完成後の状態を示す縦断
面図である。
FIG. 8 is a vertical cross-sectional view showing a state after completion of the repair lining structure.

【図9】コンクリート製管渠の改修ライニング工法に用
いられる構成部材を分離状態にして示した斜視図であ
る。
FIG. 9 is a perspective view showing constituent members used in a repair lining method for a concrete pipe under a separated state.

【図10】コンクリート製管渠の改修ライニング構造の
完成後の状態を示す横断面図である。
FIG. 10 is a transverse cross-sectional view showing a state after completion of the repair lining structure of the concrete pipe.

【符号の説明】[Explanation of symbols]

1、31…コンクリート躯体 1a、31a…コンクリート躯体壁面 2…アンカーボルト 4…枠体取付板 6…スタッドボルト 7、37…金属枠体 10…ナット 11…スタッドボルト 11a…ノックオフ部 11b…切断用括れ部 12…ライニングパネル 12a…パネル本体 12b…弾性薄板 13…切欠段部 14…目地被覆材 16…ボルト・ナット 18、19、48…抑止棧 20…固定金具 25、55…裏込材 1, 31 ... Concrete skeleton 1a, 31a ... Concrete skeleton wall surface 2 ... Anchor bolt 4 ... Frame body mounting plate 6 ... Stud bolt 7, 37 ... Metal frame body 10 ... Nut 11 ... Stud bolt 11a ... Knock-off part 11b ... Tightening for cutting Part 12 ... Lining panel 12a ... Panel body 12b ... Elastic thin plate 13 ... Notch step part 14 ... Joint covering material 16 ... Bolts / nuts 18, 19, 48 ... Restraining rod 20 ... Fixing metal fittings 25, 55 ... Backing material

───────────────────────────────────────────────────── フロントページの続き (72)発明者 三戸 常次 千葉県市原市荻作590ー13 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Tsuneji Minohe 590-13 Ogisaku, Ichihara City, Chiba Prefecture

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 液槽等のコンクリート躯体壁面の腐食欠
陥部を除去したのち素地調整し、該壁面に所定配置に多
数個のアンカーボルトを固植し、上記躯体壁面との間に
所定間隔を隔てゝ剛性金属枠体を配置しかつ上記アンカ
ーボルトを利用して該金属枠体を直接または間接に固定
し、 次いで上記金属枠体の外面側に硬質合成樹脂製の多数個
のライニングパネルを並べて配設し、かつ該各ライニン
グパネルを上記金属枠体にボルト・ナットで締結固定す
ると共に、 次いで、更に該ライニングパネル群の外面側に棒状抑止
棧を格子状配置等に配列してこれをライニングパネル面
上に固定金具で固定し、 しかる後前記躯体壁面とライニングパネルとの間の空間
部内にコンクリート等の裏込材を注入充填し、 そして、上記裏込材の養生硬化後、前記抑止棧及びその
固定金具を除去することを特徴とするコンクリート製液
槽及び管渠等の改修ライニング工法。
1. After removing a corrosion defect portion of a concrete skeleton wall surface of a liquid tank or the like, the substrate is adjusted, and a large number of anchor bolts are fixedly planted on the wall surface in a predetermined arrangement, and a predetermined interval is provided between the skeleton wall surface. A rigid metal frame body is arranged at a distance, and the metal frame body is directly or indirectly fixed using the anchor bolts, and then a large number of hard synthetic resin lining panels are arranged on the outer surface side of the metal frame body. The respective lining panels are arranged and fastened and fixed to the metal frame body with bolts and nuts, and then rod-like restraint boards are arranged on the outer surface side of the lining panel group in a grid-like arrangement or the like to lining them. After fixing with a fixing bracket on the panel surface, injecting and filling a backing material such as concrete into the space between the body wall surface and the lining panel, and after curing and curing the backing material, Tome棧 and renovation lining method concrete tank and Kanmizo like and removing the fixing bracket.
【請求項2】 ライニングパネルは、硬質合成樹脂製の
パネル本体の周側面に、緩衝用の弾性薄板を貼着一体化
したものを用いる請求項1記載のコンクリート製液槽及
び管渠等の改修ライニング工法。
2. The concrete liquid tank, pipe ditch, etc. according to claim 1, wherein the lining panel is made of a hard synthetic resin panel main body and a cushioning elastic thin plate attached to the peripheral side surface of the panel main body. Lining method.
【請求項3】 コンクリート躯体壁面に固植されたアン
カーボルトの先端に、所定大の金属板からなる枠体取付
板を、その背面に有する雌ねじ筒部を上記ボルトに螺合
して高さ調節自在に装着し、 該枠体取付板のレベル調整を行った後、前記金属枠体を
該取付板にボルト・ナットで締結固定する請求項1また
は2に記載のコンクリート製液槽及び管渠等の改修ライ
ニング工法。
3. The height is adjusted by screwing an internal threaded cylinder portion having a frame mounting plate made of a metal plate of a predetermined size to the tip of the anchor bolt fixedly planted on the wall surface of the concrete skeleton to the bolt. 3. The concrete liquid tank and the pipe, etc. according to claim 1 or 2, wherein the metal frame body is freely attached and the level of the frame mounting plate is adjusted, and then the metal frame body is fastened and fixed to the mounting plate with bolts and nuts. Repair lining method.
【請求項4】 金属枠体に固着するライニングパネル取
付用のスタッドボルトは、その長さ方向の中間部に括れ
部を有して、該括れ部より先端側をノックオフ部とした
ものを用い、 ライニングパネルの取付固定後において該パネル面上か
らスタッドボルトの上記ノックオフ部を突出せしめるも
のとし、このノックオフ部に前記固定金具を取付けて前
記抑止棧を固定するものとした請求項1ないし3のいず
れか1に記載のコンクリート製液槽及び管渠等の改修ラ
イニング工法。
4. A stud bolt for attaching a lining panel, which is fixed to a metal frame, has a constricted portion at an intermediate portion in the length direction, and a knock-off portion is provided on the tip side from the constricted portion. 4. The knurled part of the stud bolt is projected from above the panel surface after the lining panel is mounted and fixed, and the fixing metal fitting is mounted on the knockoff part to fix the restraint shaft. The relining lining method for concrete liquid tanks and pipes as described in 1 above.
【請求項5】 貯液槽のコンクリート躯体壁面に所定配
置に多数個のアンカー・ボルトが固植され、 前記躯体壁面との間に所定間隔を隔てゝ剛性金属枠体が
配置され、該金属枠体が前記アンカーボルトの先端部に
直接または間接に固定されるとともに、 前記金属枠体の外面側に多数個の硬質合成樹脂板からな
るライニングパネルが敷き並べ状態に配置され、該ライ
ニングパネルが前記金属枠体にボルト・ナットで締結固
定されると共に、 前記躯体壁面とライニングパネルとの間の空間部内にコ
ンクリート等の裏込材が注入充填されかつ硬化されてな
ることを特徴とするコンクリート製液槽及び管渠等の改
修ライニング構造。
5. A large number of anchor bolts are fixedly planted in a predetermined arrangement on a concrete wall surface of the liquid storage tank, and a rigid metal frame body is arranged at a predetermined distance from the wall surface of the body, and the metal frame is formed. The body is fixed directly or indirectly to the tip end portion of the anchor bolt, and a lining panel made of a large number of hard synthetic resin plates is arranged on the outer surface side of the metal frame body in a lined state, and the lining panel is A concrete liquid, which is fastened and fixed to a metal frame with bolts and nuts, and in which a backing material such as concrete is injected and filled and cured in the space between the body wall surface and the lining panel. Relining structure for tanks and pipes.
【請求項6】 ライニングパネルは、硬質塩化ビニル樹
脂からなる請求項5記載のコンクリート製液槽及び管渠
等の改修ライニング構造。
6. The relining lining structure for a concrete liquid tank, a pipe or the like according to claim 5, wherein the lining panel is made of a hard vinyl chloride resin.
【請求項7】 ライニングパネルは、周縁部外面に浅い
段部を有し、隣接するパネル間にまたがって上記段部に
対応断面形状の帯状目地被覆材が嵌め込まれ、接着固定
されてなる請求項6記載のコンクリート製液槽及び管渠
等の改修ライニング構造。
7. The lining panel has a shallow step portion on the outer surface of the peripheral edge portion, and a band-like joint covering material having a corresponding cross-sectional shape is fitted over the adjacent step portions of the panel and is fixed by adhesion. Refurbished lining structure of concrete liquid tank and pipe as described in 6.
JP5185821A 1993-07-28 1993-07-28 Renovation lining method and concrete lining structure for concrete liquid tanks and pipes Expired - Fee Related JP2637356B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5185821A JP2637356B2 (en) 1993-07-28 1993-07-28 Renovation lining method and concrete lining structure for concrete liquid tanks and pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5185821A JP2637356B2 (en) 1993-07-28 1993-07-28 Renovation lining method and concrete lining structure for concrete liquid tanks and pipes

Publications (2)

Publication Number Publication Date
JPH0742222A true JPH0742222A (en) 1995-02-10
JP2637356B2 JP2637356B2 (en) 1997-08-06

Family

ID=16177473

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5185821A Expired - Fee Related JP2637356B2 (en) 1993-07-28 1993-07-28 Renovation lining method and concrete lining structure for concrete liquid tanks and pipes

Country Status (1)

Country Link
JP (1) JP2637356B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007100446A (en) * 2005-10-06 2007-04-19 Kansai Electric Power Co Inc:The Reinforcement structure of concrete wall, and reinforcement method for concrete wall
KR100949071B1 (en) * 2010-01-25 2010-03-19 주식회사 복주 Pannel unit for lining and water tank using the same
KR100978244B1 (en) * 2010-03-29 2010-08-26 주식회사 복주 Water tank for union type pannel
CN107558602A (en) * 2017-09-30 2018-01-09 武汉圣禹排水系统有限公司 Weir gate stopping means, the Vatch basin and weir gate for being provided with the stopping means
KR102369645B1 (en) * 2021-08-13 2022-03-03 (주)에코인프라 Concrete Conduit Repair and Reinforcement Method Using Composite Cement Panel

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102490760B1 (en) * 2022-10-19 2023-01-20 주식회사 디에이치오토 Construction method of vehicle interior structure that is strong against vibration

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007100446A (en) * 2005-10-06 2007-04-19 Kansai Electric Power Co Inc:The Reinforcement structure of concrete wall, and reinforcement method for concrete wall
JP4551304B2 (en) * 2005-10-06 2010-09-29 関西電力株式会社 Concrete wall reinforcing structure and concrete wall reinforcing method
KR100949071B1 (en) * 2010-01-25 2010-03-19 주식회사 복주 Pannel unit for lining and water tank using the same
KR100978244B1 (en) * 2010-03-29 2010-08-26 주식회사 복주 Water tank for union type pannel
CN107558602A (en) * 2017-09-30 2018-01-09 武汉圣禹排水系统有限公司 Weir gate stopping means, the Vatch basin and weir gate for being provided with the stopping means
KR102369645B1 (en) * 2021-08-13 2022-03-03 (주)에코인프라 Concrete Conduit Repair and Reinforcement Method Using Composite Cement Panel

Also Published As

Publication number Publication date
JP2637356B2 (en) 1997-08-06

Similar Documents

Publication Publication Date Title
US5537794A (en) Shear bolt connected structural units
US6904636B2 (en) Deck-to-girder connections for precast or prefabricated bridge decks
JP2018178396A (en) Reinforcing and fixing method and reinforcing and fixing structure
JPH0742222A (en) Liquid tank made of concrete and repair lining work of sewer pipe and repair lining structure
JP2806267B2 (en) Rehabilitation lining method and rehabilitation lining structure of concrete frame wall
KR101879277B1 (en) An reinforcement method for repair of underground structures
JPH09221760A (en) Temporary coffering structure and method of construction thereof
JP2920851B2 (en) Repair method of concrete wall
JPH083200B2 (en) Repair structure and repair method for inner wall surface of concrete tank
JP2893490B2 (en) Waterway repair method
KR20050034978A (en) Waterproof, repair and reinforcement of flat, curved and rectangular structures
JPH11190135A (en) Improvement lining construction method for concrete building frame wall face and improvement lining structure
JP2010106534A (en) Method of repairing and replacing flexible joint of closed conduit, and repair and replacement structure therefor
KR20020023018A (en) Connection method between composite or precast deck and girders
JP4574778B2 (en) Method for repairing concrete structure and surface coating formwork
JPH09209582A (en) Reinforcing structural body and reinforcing method for structure with it
JPH11256839A (en) Reinforcing and repairing method of concrete structure
JP2019108729A (en) Reinforcing structure and reinforcing method of pile support structure
CN218148937U (en) Embedded part fixing device
JP2003082994A (en) Tunnel repairing structural material and tunnel repairing construction method
KR20210078155A (en) Prefabricated steel frame for composite member of steel and concrete with ferrocement form and construction method of composite member using the same
KR200253540Y1 (en) elastic connecter of railroad bridge
JP2578356Y2 (en) Repair structure of concrete pipe joint
JP4153611B2 (en) Pipe laying structure and laying method
JP2003314065A (en) Permanent seismic reinforcing method for reinforced concrete column

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080425

Year of fee payment: 11

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080425

Year of fee payment: 11

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080425

Year of fee payment: 11

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080425

Year of fee payment: 11

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees