JPH07301089A - Launching method of shield machine - Google Patents

Launching method of shield machine

Info

Publication number
JPH07301089A
JPH07301089A JP11475094A JP11475094A JPH07301089A JP H07301089 A JPH07301089 A JP H07301089A JP 11475094 A JP11475094 A JP 11475094A JP 11475094 A JP11475094 A JP 11475094A JP H07301089 A JPH07301089 A JP H07301089A
Authority
JP
Japan
Prior art keywords
starting
shield excavator
ring
bag
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11475094A
Other languages
Japanese (ja)
Other versions
JP3177908B2 (en
Inventor
Tadashi Okamoto
正 岡本
Shiyuuji Tsujigami
修士 辻上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP11475094A priority Critical patent/JP3177908B2/en
Publication of JPH07301089A publication Critical patent/JPH07301089A/en
Application granted granted Critical
Publication of JP3177908B2 publication Critical patent/JP3177908B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE:To prevent the flow out of underground water, sand and earth into a launching shaft surely and very easily, without prolonging a construction period and increasing the cost, and launch a shield machine to a satisfactory manner. CONSTITUTION:Before the front end 4a of a shield machine 4 passes through an improved soil area 3 and arrives at an unimproved soil area, a bag-attached ring 22 is installed in a launching shaft 2 where the end of the bag-attached ring 22 and an opening of a launching entrance are closed with an entrance packing 7 while a back-filling material is filled up in a shielding bag 21 installed the outer peripheral part of the bag-attached ring 22, thereby expanding the bag so as to join with the internal surface of the launching entrance and forming a ring-shaped space on the outer peripheral side of the bag-attached ring 22. Then, excavation work is started again by driving the shield machine 4.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、例えば、下水道トン
ネル、自動車用トンネル、鉄道用トンネル等を掘削する
シールド掘削機の発進方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for starting a shield excavator for excavating a sewer tunnel, an automobile tunnel, a railway tunnel, etc.

【0002】[0002]

【従来の技術】周知のように、シールド工法は、外形円
筒状のスキンプレートを有するシールド掘削機の前端部
に設けられたカッタ装置を回転させることにより地山を
掘削しつつ、スキンプレート内で円筒分割体たるセグメ
ントを組み立ててなるリングを連結し、さらにリングの
前端に反力をとってシールド掘削機内部の推進ジャッキ
を伸長させることで地中にトンネルを掘削構築する工法
である。上記シールド工法において、シールド掘削機を
発進させる場合、図7に示すように、コンクリートによ
って構築した発進立坑1の側方へ形成した発進坑口2の
近傍に、例えば、凍結あるいは薬液注入等によって地盤
を硬化させてなる地盤改良部3を形成しておき、この状
態にて、発進坑口2からシールド掘削機4による掘削を
開始させ、仮リング5及び本設リング6を連結してい
た。
2. Description of the Related Art As is well known, in the shield construction method, a cutter device provided at a front end portion of a shield excavator having an outer cylindrical skin plate is rotated to excavate the natural ground while the skin plate is being excavated. This is a method of excavating and constructing a tunnel in the ground by connecting rings formed by assembling segments that are cylindrical divided bodies, and further taking a reaction force at the front end of the rings to extend the propulsion jack inside the shield excavator. In the above shield construction method, when the shield excavator is started, as shown in FIG. 7, the ground is formed near the start shaft 2 formed on the side of the start shaft 1 constructed by concrete, for example, by freezing or chemical solution injection. The ground improvement portion 3 formed by hardening was formed, and in this state, the excavation by the shield excavator 4 was started from the starting hole 2 and the temporary ring 5 and the permanent ring 6 were connected.

【0003】ところで、このシールド掘削機4の発進
は、工事全体の中でも最もトラブルが多い施工段階であ
り、今後増加すると予想される高水圧下でのシールド掘
削機4の発進では、発進坑口2に作用する水圧に対して
安全かつ経済的な対策が必要とされている。このため、
従来では、シールド掘削機4の前端部4aが地盤の未改
良部分に達する前に、テールボイドTの立坑1側の開口
箇所を、鉄板及びゴム等からなるエントランスパッキン
7によって封鎖し、その後、テールボイドT内に裏込注
入ポンプ8によって裏込材9を充填していた。
By the way, the start of the shield excavator 4 is the most troublesome construction stage in the entire construction, and when the shield excavator 4 is started under high water pressure, which is expected to increase in the future, the start pit 2 is opened. Safe and economical measures against the acting water pressure are needed. For this reason,
Conventionally, before the front end portion 4a of the shield excavator 4 reaches the unimproved portion of the ground, the opening portion of the tail void T on the shaft 1 side is closed by an entrance packing 7 made of an iron plate and rubber, and then the tail void T The backfill material 9 was filled in the inside by the backfill injection pump 8.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記発
進方法にあっては、テールボイドT内に充填した裏込材
9が重力によって下方へ流れてしまうため、テールボイ
ドの上方側へ裏込材9が十分に行き渡らず、これによ
り、裏込材9によるシールが不十分となってしまう。つ
まり、この状態にて、シールド掘削機4の掘削を開始さ
せた場合、シールド掘削機4の前端部4aが未改良部分
に達してテールボイドT内に地下水、砂、土砂等が流入
した際に、裏込材9によるシールが弱い上方側にて、エ
ントランスパッキン7に高圧力が作用し、さらに、エン
トランスパッキン7のシールの弱い箇所から地下水、
砂、土砂等が、発進立坑1内に流出してしまい、掘削作
業を中断させなければならなかったり、また、掘削現場
の上部で地盤沈下が生じる恐れがあった。
However, in the starting method described above, the backfill material 9 filled in the tail void T flows downward due to gravity, so that the backfill material 9 is sufficiently above the tail void. Therefore, the sealing by the backing material 9 becomes insufficient. That is, when the excavation of the shield excavator 4 is started in this state, when the front end portion 4a of the shield excavator 4 reaches the unimproved portion and groundwater, sand, earth and sand, etc., flow into the tail void T, High pressure acts on the entrance packing 7 on the upper side where the sealing by the backing material 9 is weak, and further, from the weak sealing part of the entrance packing 7 to groundwater,
There is a risk that sand, earth and sand, etc. will flow into the starting shaft 1 and interrupt the excavation work, or that ground subsidence may occur at the upper part of the excavation site.

【0005】このため、図8に示すように、発進立坑1
に、発進坑口2を軸線方向へ延長させてなるエントラン
スルーム11を構築し、このエントランスルーム11に
シールド掘削機4を設置した状態にて、リング6及びシ
ールド掘削機4とエントランスルーム11との間に裏込
材9を充填して止水ゾーンを形成し、水圧に対処する方
法があるが、この方法にあっても、シールド掘削機4の
掘削を再開した際に、シールド掘削機4と裏込材9との
間に空隙が生じてしまい、その空隙内に地下水、砂、土
砂が流れ込んで、エントランスパッキン7に高圧力が作
用して、発進立坑1内へ地下水、砂、土砂等が流出する
恐れがあり、また、裏込材9によってシールド掘削機4
がエントランスルーム11に付着してしまい、シールド
掘削機4の再発進が不能となってしまうことがある。ま
た、この方法の場合、発進立坑1にエントランスルーム
11を構築する作業に多大な手間を要するとともに、コ
ストアップを招いてしまい、さらには、このエントラン
スルーム11を構築することにより工期が長期化してし
まうという問題があった。また、このエントランスルー
ム11を構築するためには、大口径の発進立坑1の構築
が必要であり、このため、さらなる構築作業の煩雑化及
び工期の長期化が生じてしまい、また、大口径の発進立
坑1を構築することが可能な場所にしか適応することが
できず、建築物の過密化が進む現在においては、好まし
い発進方法ではなかった。
Therefore, as shown in FIG. 8, the starting shaft 1
In this state, an entrance room 11 is constructed by extending the start pit entrance 2 in the axial direction, and with the shield excavator 4 installed in the entrance room 11, the ring 6 and the shield excavator 4 are separated from the entrance room 11. There is a method of coping with the water pressure by filling the backfill material 9 with the backfill material 9 and even in this method, when the excavation of the shield excavator 4 is restarted, A void is created between the filler material 9 and groundwater, sand, or earth and sand flows into the void, and high pressure acts on the entrance packing 7, causing groundwater, sand, or earth and the like to flow into the starting shaft 1. In addition, the backing material 9 causes the shield excavator 4 to
May adhere to the entrance room 11 and the shield excavator 4 may be unable to restart. Further, in the case of this method, it takes a lot of time and labor to construct the entrance room 11 in the starting shaft 1 and leads to an increase in cost. Furthermore, the construction of the entrance room 11 prolongs the construction period. There was a problem of being lost. Further, in order to construct the entrance room 11, it is necessary to construct a large-diameter starting shaft 1, which further complicates the construction work and prolongs the construction period. Since it can be applied only to a place where the starting shaft 1 can be constructed, it is not a preferable starting method at the present time when the density of buildings is increasing.

【0006】この発明は、上記事情に鑑みてなされたも
ので、工期の長期化、コストアップ等を招くことなく、
極めて容易にかつ確実に、地下水、砂、土砂等の発進立
坑内への流出を防止することが可能なシールド掘削機の
発進方法を提供することを目的としている。
The present invention has been made in view of the above circumstances, and does not lead to a longer construction period, higher costs, etc.
It is an object of the present invention to provide a method for starting a shield excavator that can very easily and reliably prevent outflow of groundwater, sand, earth and sand, etc. into the starting shaft.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
に、請求項1記載のシールド掘削機の発進方法は、立坑
内にて側方に形成した発進坑口から、シールド掘削機に
よって掘削孔の掘削を開始させるシールド掘削機の発進
方法であって、前記発進坑口近傍の地盤を硬化させてな
る地盤改良部を前記シールド掘削機によって掘削させ、
前記シールド掘削機が前記地盤改良部を通過する前に、
前記発進坑口内にリングを設置するとともに該リングと
前記発進坑口との空間を、掘削方向前方側及び掘削方向
後方側にて封鎖して環状の空間部を形成し、該空間部内
に充填材を充填して硬化させることを特徴としている。
In order to achieve the above-mentioned object, a method for starting a shield excavator according to claim 1 is such that a shield excavator is used to form an excavation hole from a start hole formed laterally in a shaft. A method of starting a shield excavator for starting excavation, in which the ground improvement portion obtained by hardening the ground in the vicinity of the starting hole is excavated by the shield excavator,
Before the shield excavator passes through the ground improvement section,
A ring is installed in the starting hole and the space between the ring and the starting hole is closed at the front side in the excavation direction and the rear side in the excavation direction to form an annular space part, and a filler is filled in the space part. It is characterized by filling and curing.

【0008】また、請求項2記載のシールド掘削機の発
進方法は、請求項1記載のシールド掘削機の発進方法に
おいて、前記リングの掘削方向後方側の端部と前記発進
坑口の開口部とをパッキンによって閉鎖するとともに、
前記リングの掘削方向前方側における外周側に遮蔽袋を
設け、この遮蔽袋に充填材を充填して前記発進坑口の内
面に密着させることにより前記リングと前記発進坑口と
の空間を封鎖して環状の空間部を形成することを特徴と
している。
A starting method of the shield excavator according to a second aspect is the starting method of the shield excavator according to the first aspect, wherein the end of the ring on the rear side in the excavating direction and the opening of the starting wellhead are formed. While closing with packing,
A shield bag is provided on the outer peripheral side of the ring on the front side in the excavation direction, and the shield bag is filled with a filler to be closely attached to the inner surface of the start hole, thereby closing the space between the ring and the start hole and forming an annular shape. It is characterized by forming a space part of.

【0009】[0009]

【作用】そして、請求項1記載のシールド掘削機の発進
方法によれば、発進坑口近傍の地盤改良部をシールド掘
削機が通過する前に、発進坑口内にリングを設置すると
ともに、このリングと発進坑口との空間の掘削方向前方
側及び掘削方向後方側を封鎖して環状の空間部を形成
し、この環状の空間部内に充填材を充填して硬化させる
ことにより、充填材によって環状のシール部が形成され
る。その後、シールド掘削機の掘削を再開させ、シール
ド掘削機の前端が地盤改良部を通過し、地盤の未改良部
分へ達すると、未改良部分から地下水、砂、土砂等が、
シールド掘削機のテールボイド内に流入する。このと
き、リングと発進坑口との間に、硬化した環状の充填材
からなるシール部が形成されているので、テールボイド
内に流入した地下水、砂、土砂等の立坑への流出が確実
に防止される。
According to the starting method of the shield excavator according to the first aspect, the ring is installed in the starting hole of the starting hole before the shield excavator passes through the ground improvement section near the starting hole of the starting hole. An annular space is formed by blocking the front side and the rear side in the excavation direction of the space with the starting hole, and the annular space is filled with a filling material and cured to form an annular seal. Parts are formed. After that, the excavation of the shield excavator is restarted, and when the front end of the shield excavator passes through the ground improvement part and reaches the unimproved part of the ground, groundwater, sand, earth and sand, etc. from the unimproved part,
It flows into the tail void of the shield excavator. At this time, since a seal part made of a hardened annular filler is formed between the ring and the starting hole, the outflow of groundwater, sand, earth and sand, etc., flowing into the tail void to the vertical shaft is reliably prevented. It

【0010】また、請求項2記載のシールド掘削機の発
進方法によれば、リングの外周側に設けられた遮蔽袋内
に充填材を充填させることにより、遮蔽袋が膨張して発
進坑口の内面と密着する。即ち、リングの掘削方向後方
側の端部と発進坑口の開口部とを閉鎖するパッキンと、
充填材の充填により膨張した遮蔽袋とによって、リング
と発進坑口の内面との空間が封鎖され、環状の空間部が
形成される。この状態にて、環状の空間部内に充填材を
充填させて硬化させることにより、この充填材が充填さ
れた空間部がシール部とされる。
Further, according to the starting method of the shield excavator of the second aspect, by filling the inside of the shielding bag provided on the outer peripheral side of the ring with the filler, the shielding bag expands and the inner surface of the starting pit mouth is expanded. In close contact with. That is, a packing that closes the end on the rear side in the excavation direction of the ring and the opening of the starting shaft entrance,
The space between the ring and the inner surface of the starting hole is closed by the shielding bag expanded by the filling with the filling material, and an annular space is formed. In this state, the filling material is filled into the annular space portion and cured, so that the space portion filled with the filling material serves as a seal portion.

【0011】[0011]

【実施例】以下、本発明のシールド掘削機の発進方法の
実施例を図によって説明する。なお、従来例と同一構造
部分には、同一符号を付して説明を省略する。まず、予
め発進坑口2近傍における地盤を凍結あるいは薬液注入
等によって硬化させた地盤改良部3としておき、発進坑
口2内にシールド掘削機4を設置し、このシールド掘削
機4の後方側に仮のセグメントからなる仮リング5を設
置する。次いで、このシールド掘削機4の前端部4a側
に設けられたカッタ装置(図示略)によって前端部4a
側の地盤改良部3を掘削しながら、シールド掘削機4の
後方側にさらに仮リング5を連結していく(図1参
照)。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT An embodiment of a starting method for a shield excavator according to the present invention will be described below with reference to the drawings. The same parts as those of the conventional example are designated by the same reference numerals and the description thereof will be omitted. First, the ground in the vicinity of the starting pit mouth 2 is set beforehand as the ground improvement section 3 which is hardened by freezing or injecting a chemical solution, and the shield excavator 4 is installed in the starting pit mouth 2 and the temporary side is provided behind the shield excavator 4. A temporary ring 5 consisting of segments is installed. Next, a front end portion 4a is cut by a cutter device (not shown) provided on the front end portion 4a side of the shield excavator 4.
While excavating the ground improvement section 3 on the side, a temporary ring 5 is further connected to the rear side of the shield excavator 4 (see FIG. 1).

【0012】さらに、シールド掘削機4による掘削を進
め、シールド掘削機4のテール4bが、発進坑口2の開
口部を通過したら、この発進坑口2内に、スチールセグ
メントからなりかつその外周側に環状の遮蔽袋21が設
けられた袋付きリング22を設置し、この袋付きリング
22と発進坑口2の開口部をエントランスパッキン7に
よって閉鎖する。シールド掘削機4の前端部4aが地盤
改良部3内にある状態にて、そのテール4bが、袋付き
リング22より所定寸法(約300mm程度)過ぎたら
シールド掘削機4による掘削を停止させ、袋付きリング
22の前記遮蔽袋21内に、裏込注入ポンプ8によって
例えば、瞬結エアーモルタル等の裏込材を注入し、この
遮蔽袋21を膨らませ、その外周側を、発進坑口2の内
周側に密着させる。このようにすると、袋付きリング2
2の外周側に、この袋付きリング22、発進坑口2、遮
蔽袋21及びエントラスパッキン7によって区画された
環状の空間部Kが形成される(図2参照)。
Further, when the excavation by the shield excavator 4 is advanced and the tail 4b of the shield excavator 4 passes through the opening of the starting wellhead 2, a steel segment is formed inside the starting wellhead 2 and an annular shape is formed on the outer peripheral side thereof. The bag-equipped ring 22 provided with the shielding bag 21 is installed, and the bag-equipped ring 22 and the opening of the starting hole 2 are closed by the entrance packing 7. With the front end 4a of the shield excavator 4 inside the ground improvement section 3, when the tail 4b of the shield excavator 4 exceeds a predetermined size (about 300 mm) from the bag ring 22, the excavation by the shield excavator 4 is stopped, and the bag is closed. A back-filling material such as instant-setting air mortar is injected into the shielding bag 21 of the attached ring 22 by the back-filling injection pump 8 to inflate the shielding bag 21, and its outer peripheral side is the inner circumference of the starting hole 2 Stick it to the side. In this way, the ring with bag 2
An annular space K defined by the bag ring 22, the starting hole 2, the shielding bag 21, and the entras packing 7 is formed on the outer peripheral side of 2 (see FIG. 2).

【0013】次いで、袋付きリング22に形成されたグ
ラウトホール(図示略)から、裏込注入ポンプ8によっ
て、前記空間部K内に例えば、瞬結エアーモルタル等の
裏込材9を充填し、この裏込材9を硬化させる。このよ
うにすると、環状の空間部K内に裏込材9が充填されて
なるシール部Sが形成される(図3参照)。この状態に
おいて、シールド掘削機4による掘削を再開させ、前記
袋付きリング22に、調整リング23を連結して軸方向
の長さを調整し、その後、コンクリートセグメントから
なる本設リング6を連結させながら掘削を続ける。そし
て、本設リング6の外周側のテールボイドTには、裏込
注入ポンプ8によって裏込材9を注入する(図4参
照)。さらに、シールド掘削機4の掘削を続けながら、
本設リング6を連結させ、これら本設リング6の外周側
のテールボイドTへ裏込材9を充填しつつ、トンネルを
構築する(図5参照)。
Then, from the grout hole (not shown) formed in the bag ring 22, a backfilling pump 8 is used to fill the space K with a backfilling material 9 such as instant-setting air mortar, The backing material 9 is cured. By doing so, the seal portion S formed by filling the backing material 9 in the annular space portion K is formed (see FIG. 3). In this state, the excavation by the shield excavator 4 is restarted, the adjustment ring 23 is connected to the bag ring 22 to adjust the axial length, and then the permanent ring 6 made of a concrete segment is connected. While continuing the excavation. Then, the back void material 9 is injected into the tail void T on the outer peripheral side of the main ring 6 by the back void injection pump 8 (see FIG. 4). Furthermore, while continuing to excavate the shield excavator 4,
A tunnel is constructed while connecting the main rings 6 and filling the tail voids T on the outer peripheral side of the main rings 6 with the backing material 9 (see FIG. 5).

【0014】ここで、シールド掘削機4の前端部4a
が、地盤改良部3から未改良部分、つまり、軟弱な地盤
へ到達した際に、この軟弱な地盤から地下水、砂、土砂
等がテールボイドT内に流れ込み、この流れ込んだ地下
水、砂、土砂等がテールボイドT内に充填した裏込材9
の弱い部分、つまり、テールボイドTの上方側における
裏込材9の充填が不十分な部分から、発進坑口2の開口
部方向へ流れ込もうとするが、発進坑口2の開口部近傍
に、袋付きリング22、発進坑口2、遮蔽袋21及びエ
ントラスパッキン7によって区画された環状の空間部K
へ裏込材9を充填して硬化させてなる環状のシール部S
が形成されているので、テールボイドT内に流れ込んだ
地下水、砂、土砂等の発進坑口2の開口部への流れ込み
を確実に防止することができる。これにより、この地下
水、砂、土砂等の発進立坑1内への流れ込みによる掘削
作業の中断、掘削現場の上方における地盤沈下の発生を
確実に防止することができる。
Here, the front end portion 4a of the shield excavator 4
However, when the ground improvement part 3 reaches the unmodified part, that is, the soft ground, groundwater, sand, earth and sand flow into the tail void T from the soft ground, and the inflowing groundwater, sand, earth and sand, etc. Backing material 9 filled in the tail void T
From a portion where the backfill material 9 is insufficiently filled on the upper side of the tail void T, toward the opening portion of the starting wellhead 2, but a bag is formed near the opening of the starting wellhead 2. An annular space K defined by the attached ring 22, the starting hole 2, the shielding bag 21, and the entras packing 7.
An annular seal portion S formed by filling the backing material 9 and hardening it
As a result, the groundwater, sand, earth and sand flowing into the tail void T can be reliably prevented from flowing into the opening of the starting hole 2. As a result, it is possible to reliably prevent the interruption of the excavation work and the occurrence of ground subsidence above the excavation site due to the inflow of groundwater, sand, earth and sand, etc. into the starting shaft 1.

【0015】その後、発進立坑1内の仮リング5を撤去
し、エントランスパッキン7と袋付きリング22とを、
プレート(図示略)を溶接することにより完全に閉鎖し
て止水処理を施し、次いで、プレートを溶接して閉鎖し
た止水箇所に化粧コンクリート24を打設する(図6参
照)。
After that, the temporary ring 5 in the starting shaft 1 is removed, and the entrance packing 7 and the bag ring 22 are
A plate (not shown) is completely closed by welding to perform a water-stop treatment, and then a decorative concrete 24 is placed at the water-stop location where the plate is welded and closed (see FIG. 6).

【0016】このように、上記実施例のシールド掘削機
の発進方法によれば、エントランスルーム11を構築す
るような大掛かりな作業を行なうことなく、発進立坑1
内への地下水、砂、土砂等の流出を確実に防止すること
ができ、この地下水、砂、土砂等の発進立坑1内への流
出による不具合をなくし、極めて良好にシールド掘削機
4を発進させることができる。
As described above, according to the starting method of the shield excavator of the above-described embodiment, the starting shaft 1 can be carried out without performing a large-scale work such as constructing the entrance room 11.
It is possible to reliably prevent outflow of groundwater, sand, earth and sand, etc. into the interior, eliminate problems due to the outflow of groundwater, sand, earth, sand, etc. into the vertical shaft 1 and start the shield excavator 4 extremely well. be able to.

【0017】[0017]

【発明の効果】以上、説明したように、本発明のシール
ド掘削機の発進方法によれば、下記の効果を得ることが
できる。請求項1記載のシールド掘削機の発進方法によ
れば、発進坑口近傍の地盤改良部をシールド掘削機が通
過する前に、発進坑口内に設置したリングと発進坑口と
の空間の掘削方向前方側及び掘削方向後方側を封鎖して
環状の空間部を形成し、さらに、この環状の空間部内に
充填材を充填して硬化させることにより、環状のシール
部を形成することができるので、シールド掘削機が地盤
改良部を通過して未改良部分へ到達した際に、未改良部
分から地下水、砂、土砂等がテールボイド内に流入した
としても、シール部によって地下水、砂、土砂等の、発
進坑口の開口部から立坑への流出を確実に防止すること
ができる。これにより、この地下水、砂、土砂等の立坑
内への流れ込みによる掘削作業の中断、掘削現場の上方
における地盤沈下の発生を確実に防止することができ
る。即ち、エントランスルームを構築する大掛かりな方
法と比較して、工期の長期化を招くことなくかつ低コス
トにて、立坑内への地下水、砂、土砂等の流出を確実に
防止することができ、極めて良好にシールド掘削機を発
進させることができる。
As described above, according to the starting method of the shield excavator of the present invention, the following effects can be obtained. According to the starting method of the shield excavator according to claim 1, before the shield excavator passes through the ground improvement portion near the start hole, the space between the ring installed in the start hole and the start hole is in the front in the excavating direction. And the rear side in the excavation direction is closed to form an annular space, and the annular seal can be formed by filling the interior of the annular space with a filler and curing it. When the machine passes through the ground improvement section and reaches the unimproved section, even if groundwater, sand, earth and sand, etc., flow into the tail void from the unimproved section, the seal section allows the starting pit opening for groundwater, sand, earth and sand, etc. It is possible to reliably prevent the outflow from the opening of the to the vertical shaft. As a result, it is possible to reliably prevent interruption of excavation work due to inflow of groundwater, sand, earth and sand, etc. into the shaft, and occurrence of ground subsidence above the excavation site. That is, as compared with a large-scale method of constructing an entrance room, it is possible to reliably prevent the outflow of groundwater, sand, earth and sand, etc. into the shaft at a low cost without prolonging the construction period, The shield excavator can be launched extremely well.

【0018】請求項2記載のシールド掘削機の発進方法
によれば、リングの掘削方向後方側の端部と発進坑口の
開口部とをパッキンによって閉鎖するとともに、リング
の外周側に設けた遮蔽袋内に充填材を充填させることに
より、シール部となる環状の空間部を極めて容易に形成
することができる。
According to the starting method of the shield excavator according to the second aspect, the end of the ring on the rear side in the excavating direction and the opening of the starting hole are closed by packing, and the shielding bag provided on the outer peripheral side of the ring. By filling the inside with the filling material, it is possible to extremely easily form the annular space portion serving as the seal portion.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明のシールド掘削機の発進方法の実施例を
説明する発進坑口の断面図である。
FIG. 1 is a cross-sectional view of a starting hole for explaining an embodiment of a starting method for a shield excavator according to the present invention.

【図2】本発明のシールド掘削機の発進方法の実施例を
説明する発進坑口の断面図である。
FIG. 2 is a cross-sectional view of a starting hole for explaining an example of a starting method for a shield excavator according to the present invention.

【図3】本発明のシールド掘削機の発進方法の実施例を
説明する発進坑口の断面図である。
FIG. 3 is a cross-sectional view of a starting hole for explaining an example of a starting method for a shield excavator according to the present invention.

【図4】本発明のシールド掘削機の発進方法の実施例を
説明する発進坑口の断面図である。
FIG. 4 is a cross-sectional view of a start hole for explaining an embodiment of a start method for a shield excavator according to the present invention.

【図5】本発明のシールド掘削機の発進方法の実施例を
説明する発進坑口の断面図である。
FIG. 5 is a cross-sectional view of a starting hole for explaining an example of a starting method for a shield excavator according to the present invention.

【図6】本発明のシールド掘削機の発進方法の実施例を
説明する発進坑口の断面図である。
FIG. 6 is a cross-sectional view of a starting hole for explaining an example of a starting method for a shield excavator according to the present invention.

【図7】従来のシールド掘削機の発進方法を説明する発
進坑口の断面図である。
FIG. 7 is a cross-sectional view of a starting hole for explaining a starting method of a conventional shield excavator.

【図8】従来のシールド掘削機の発進方法を説明する発
進坑口の断面図である。
FIG. 8 is a cross-sectional view of a starting hole for explaining a starting method of a conventional shield excavator.

【符号の説明】[Explanation of symbols]

1 発進立坑(立坑) 2 発進坑口 3 地盤改良部 4 シールド掘削機 7 エントランスパッキン(パッキン) 9 裏込材(充填材) 21 遮蔽袋 22 袋付きリング(リング) K 空間部 1 Starting shaft (vertical shaft) 2 Starting shaft entrance 3 Ground improvement part 4 Shield excavator 7 Entrance packing (packing) 9 Backfill material (filling material) 21 Shielding bag 22 Ring with ring (K) Space section

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 立坑内にて側方に形成した発進坑口か
ら、シールド掘削機によって掘削孔の掘削を開始させる
シールド掘削機の発進方法であって、 前記発進坑口近傍の地盤を硬化させてなる地盤改良部を
前記シールド掘削機によって掘削させ、 前記シールド掘削機が前記地盤改良部を通過する前に、
前記発進坑口内にリングを設置するとともに該リングと
前記発進坑口との空間を、掘削方向前方側及び掘削方向
後方側にて封鎖して環状の空間部を形成し、該空間部内
に充填材を充填して硬化させることを特徴とするシール
ド掘削機の発進方法。
1. A method of starting a shield excavator, which starts excavation of an excavation hole by a shield excavator from a start hole formed laterally in a shaft, wherein the ground near the start hole is hardened. Excavate the ground improvement section by the shield excavator, before the shield excavator passes through the ground improvement section,
A ring is installed in the starting hole and the space between the ring and the starting hole is closed at the front side in the excavation direction and the rear side in the excavation direction to form an annular space part, and a filler is filled in the space part. A method for starting a shield excavator, which comprises filling and hardening.
【請求項2】 前記リングの掘削方向後方側の端部と前
記発進坑口の開口部とをパッキンによって閉鎖するとと
もに、前記リングの掘削方向前方側における外周側に遮
蔽袋を設け、この遮蔽袋に充填材を充填して前記発進坑
口の内面に密着させることにより前記リングと前記発進
坑口との空間を封鎖して環状の空間部を形成することを
特徴とする請求項1記載のシールド掘削機の発進方法。
2. An end of the ring on the rear side in the excavating direction and an opening of the starting hole are closed by a packing, and a shielding bag is provided on the outer peripheral side of the ring on the front side in the excavating direction. The shield excavator according to claim 1, wherein a space between the ring and the starting hole opening is closed by forming a ring-shaped space portion by filling a filling material and closely contacting the inner surface of the starting hole opening. How to start.
JP11475094A 1994-04-28 1994-04-28 Starting method of shield excavator Expired - Fee Related JP3177908B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11475094A JP3177908B2 (en) 1994-04-28 1994-04-28 Starting method of shield excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11475094A JP3177908B2 (en) 1994-04-28 1994-04-28 Starting method of shield excavator

Publications (2)

Publication Number Publication Date
JPH07301089A true JPH07301089A (en) 1995-11-14
JP3177908B2 JP3177908B2 (en) 2001-06-18

Family

ID=14645747

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11475094A Expired - Fee Related JP3177908B2 (en) 1994-04-28 1994-04-28 Starting method of shield excavator

Country Status (1)

Country Link
JP (1) JP3177908B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111271076A (en) * 2020-04-10 2020-06-12 中建八局轨道交通建设有限公司 Tunnel portal breaking construction method for underground excavation method transverse channel
CN113460125A (en) * 2021-05-26 2021-10-01 万朝栋 Automatic control system for safe running of battery car group in shield construction horizontal transportation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111271076A (en) * 2020-04-10 2020-06-12 中建八局轨道交通建设有限公司 Tunnel portal breaking construction method for underground excavation method transverse channel
CN113460125A (en) * 2021-05-26 2021-10-01 万朝栋 Automatic control system for safe running of battery car group in shield construction horizontal transportation
CN113460125B (en) * 2021-05-26 2022-08-23 万朝栋 Automatic control system for safe running of battery car group in shield construction horizontal transportation

Also Published As

Publication number Publication date
JP3177908B2 (en) 2001-06-18

Similar Documents

Publication Publication Date Title
JP2003206691A (en) Shield machine arrival construction method
JP4077341B2 (en) Shaft machine shaft construction method and pressure-resistant sealing device used for this
JPH07301089A (en) Launching method of shield machine
JP2002047881A (en) Pipeline construction method
JPH0821183A (en) Method for starting tunnel excavation
JP2022109072A (en) Shield method
JP2018003264A (en) Pipeline connection structure and construction method for the same
JP3184456B2 (en) How to receive shield machine into the arrival shaft
JP2976830B2 (en) Joining method of shield excavator and reaching shaft
JP4501311B2 (en) Grout filling method around buried pipe
JP2636139B2 (en) Wellhead sealing device
JPH10205280A (en) Tunnel construction method
JPH0437916B2 (en)
JP2002194988A (en) Receiving method of tunnel excavator to arrival shaft and facility for it
JPH1162466A (en) Receiving method of shield boring machine into arrival shaft, and structure of receiving part of shield boring machine in arrival shaft
JP2851520B2 (en) Shaft
JPH0641716B2 (en) A method for reaching a shield excavator into a vertical shaft, and a sealing device and an airtight tank used for the method.
JP2006152680A (en) Joining construction method for shield tunnel and structure of shield tunnel by its construction method
JPH04118497A (en) Application process for continuous wall of under ground reinforced concrete
JP3068396B2 (en) Shield excavator
JP2932957B2 (en) Underground joint structure of shield machine
JP3511429B2 (en) Replacement of existing buried pipes
JPH07180467A (en) Connecting method for vertical shaft and shield machine
JP4330929B2 (en) Water stop device and water stop method
JP2851521B2 (en) Shield excavator

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20010227

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080413

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090413

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100413

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees