JPH07282140A - Production schedule system - Google Patents

Production schedule system

Info

Publication number
JPH07282140A
JPH07282140A JP7101894A JP7101894A JPH07282140A JP H07282140 A JPH07282140 A JP H07282140A JP 7101894 A JP7101894 A JP 7101894A JP 7101894 A JP7101894 A JP 7101894A JP H07282140 A JPH07282140 A JP H07282140A
Authority
JP
Japan
Prior art keywords
item
production
day
work
production plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7101894A
Other languages
Japanese (ja)
Other versions
JP3240237B2 (en
Inventor
Mitsuhiro Enomoto
充博 榎本
Hideaki Matoba
秀彰 的場
Tetsuji Segawa
哲司 瀬川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP7101894A priority Critical patent/JP3240237B2/en
Publication of JPH07282140A publication Critical patent/JPH07282140A/en
Application granted granted Critical
Publication of JP3240237B2 publication Critical patent/JP3240237B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To judge the planning possibility of a production schedule corresponding to received order contents. CONSTITUTION:The production plan is generated by bringing respective shop workloads required for the completion of an item to the earlier side from a completion request date based on the completion request of the item. When an order is received from a customer, the completion request for satisfying the received order contents is successively assigned. When the completion request to be assigned is not present, the completion request for satisfying the received order contents is added and the production schedule is regenerated. Then, the workloads before the present date of respective shops in the generated production schedule are compared with the workloads by the production schedule not assigned for the received order from the customer. When the overloads of the shops is not larger, the production schedule assigned for the received order from the customer is judged as executable by changing the production schedule not assigned for the received order from the customer for the shop.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、製造システムにおける
生産計画を生成する生産計画システムに関し、特に、必
要数の変更にも柔軟に対応することのできる生産計画シ
ステムに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production planning system for producing a production plan in a manufacturing system, and more particularly to a production planning system capable of flexibly coping with a change in a required number.

【0002】[0002]

【従来の技術】従来の、生産計画に関する技術として
は、特開昭63−306861号公報記載の、部品供給
ショップの供給能力と組立ショップの生産能力を相互に
比較検討し、資材または部品の消費量と供給量がバラン
スを保持するように製品生産量を調整し決定する技術が
知られている。
2. Description of the Related Art As a conventional technique relating to production planning, the supply capacity of a parts supply shop and the production capacity of an assembly shop, which are described in Japanese Patent Laid-Open No. 63-306861, are compared with each other and consumption of materials or parts is considered. There is known a technique for adjusting and determining a product production amount so that the supply amount and the supply amount are kept in balance.

【0003】また、特開平2−311250号公報記載
の、問題が発生している生産計画の調整を支援する技術
が知られている。
Further, there is known a technique described in Japanese Patent Application Laid-Open No. 2-311250 for supporting adjustment of a production plan in which a problem occurs.

【0004】また、特開平4−145573号公報記載
の、現在の生産計画では顧客の要求する納期に対応でき
ない場合に、その時点から、この要求に応じる製品の部
品、材料を調達するとして生産計画を変更し、この生産
計画で対応できる期日を、顧客への回答納期として検討
する技術が知られている。
Further, when the current production plan described in Japanese Patent Laid-Open No. 4-145573 cannot meet the delivery time required by the customer, it is assumed that the parts and materials of the product which meet the demand will be procured from that point onward. There is a known technology for changing the date and considering the deadline that can be met by this production plan as the delivery date to the customer.

【0005】[0005]

【発明が解決しようとする課題】ところで、一度、生産
計画を生成した後に、予定した必要数より実際の必要数
が増加してしまう場合がある。顧客よりの受注数が予定
数より多かった場合等である。このような場合には、生
産計画を見直し、極力、実際の必要数を満足する生産計
画を生成しなおすことが望ましい。この生産計画の再生
成は、一般的には、実際に必要となった必要数を満足す
るように生産計画を再生成することにより行なわれる
が、元の生産計画に余裕が無い場合、このようにして再
生成された生産計画には、作業の着手日が現在以前とな
ったり、在庫を超える材料、部品を必要としたりすると
いった問題が含まれていることが多い。したがい、この
ような場合には、問題を解決し、極力、実際の必要数を
満たすことのできるように生産計画を調整する必要が
る。
However, after the production plan is once generated, the actual required number may increase from the planned required number. This is the case when the number of orders from the customer is greater than the planned number. In such a case, it is desirable to review the production plan and regenerate a production plan that satisfies the actual required number as much as possible. Regeneration of the production plan is generally performed by regenerating the production plan so as to satisfy the required number actually required. However, when the original production plan has no margin, In many cases, the production plan regenerated in this way includes problems such as the start date of the work being before the current date and the need for materials and parts out of stock. Therefore, in such a case, it is necessary to solve the problem and adjust the production plan so as to meet the actual required number as much as possible.

【0006】しかし、特開昭63−306861号公報
記載の技術では、このような要求に対応することができ
ない。
However, the technique described in Japanese Patent Application Laid-Open No. 63-306861 cannot meet such requirements.

【0007】また、特開平2−311250号公報記載
の技術によれば、計画立案者の問題のある生産計画の生
産計画の調整作業を支援するが、問題個所の検出や、問
題発生の原因究明や、調整内容の決定等については支援
しないので、これらは、全て計画立案者が、独自に行な
わなければならない。
Further, according to the technique disclosed in Japanese Patent Laid-Open No. 2-311250, the planner assists the work of adjusting the production plan of the production plan having a problem, but the problem location is detected and the cause of the problem occurrence is investigated. Also, since it does not support the determination of the details of adjustment, the planner must do all of this independently.

【0008】また、特開平4−145573号公報記載
の技術によれば、現在の生産計画では顧客の要求する納
期に対応できない場合に、その時点から、この要求に応
じる製品の部品、材料を調達するとして生産計画を変更
し、この生産計画で対応できる期日を、顧客への回答納
期として検討する。しかし、顧客の要求納期以降に完成
予定の製品を、実際には必要としない場合もあり、この
場合は、製造システムの作業負荷や在庫量を考えれば、
この顧客の要求納期以降に完成予定の製品の生産計画を
変更すれば、その時点から、この要求に応じる製品の部
品、材料を調達する場合より早く(たとえば、顧客の要
求納期を満足するように要求製品を完成することのでき
る)、全体として問題のない生産計画を生成できる場合
もある。
Further, according to the technique described in Japanese Patent Laid-Open No. 145573/1992, if the current production plan cannot meet the delivery date requested by the customer, the parts and materials of the product complying with this request are procured from that point onward. Therefore, the production plan is changed, and the due date that can be handled by this production plan is considered as the reply delivery date to the customer. However, there are cases where a product that is scheduled to be completed after the customer's requested delivery date is not actually needed, and in this case, considering the workload of the manufacturing system and the inventory quantity,
If you change the production plan of the product that is scheduled to be completed after this customer's requested delivery date, from that point on, it will be faster than when you procure the parts and materials of the product that meets this requirement (for example, make sure that the customer's required delivery time is In some cases, the required product can be completed), and a production plan that is totally satisfactory can be generated.

【0009】そこで、本発明は、実際の必要数が予定数
より多かった場合にも、極力、実際の必要数を満足する
ように生産計画を、計画立案者が容易に変更することが
できるように支援することのできる生産計画システムを
提供することを目的とする。
Therefore, according to the present invention, even when the actual required number is larger than the planned number, the planner can easily change the production plan so as to satisfy the actual required number as much as possible. The purpose is to provide a production planning system that can support

【0010】[0010]

【課題を解決するための手段】前記目的達成達成のため
に、本発明は、たとえば、最終品目を製造するための製
造工程の一部の工程を担い、担った工程において最終品
目の部品として用いられる品目、もしくは、前記最終品
目を生産する複数のショップを有する製造システムの生
産計画を生成する生産計画システムであって、最終品目
を必要個数、必要時期に供給することを要求されたとき
に、最終品目の完成予定を規定する完成スケジュ−ルに
おいて完成予定の最終品目の中に、指定された必要時期
以前に完成予定の、他の要求に引き当てられていない、
前記必要個数以上の最終品目が存在する場合には、これ
を当該要求に引き当て、存在しない場合には、当該要求
を満足する最終品目の完成予定を完成スケジュ−ルに追
加する引当手段と、完成スケジュ−ルに基づいて、生産
計画により発生する各工程の各日の作業量が、各日の対
応するショップの能力を超えないように、各最終品目を
製造するための各工程の作業期間を、その完成予定日よ
り順次前倒ししていくことにより生産計画を生成する手
段と、生成された生産計画より、各工程について、各日
毎に、当該日に当該工程で完成予定の品目を全て製造す
るために要する作業量を累計した完成作業量を求め、各
工程について、各日に割り当てられる作業量が当該日の
ショップの能力を超えた場合に、超えた分の作業量を前
日に割り当て直すように、完成予定日の遅いものより順
次、各完成作業量に含まれる作業量を、対応する完成予
定日より過去に向かって順次、各日に割り当てる手段と
各工程について、現在日より前の日に、作業量が割り当
てられた場合に、前の日に作業量を割り当て直された日
が現在日より将来に向かって連続する期間中に、前記要
求に引き当てられていない最終品目および当該最終品目
に部品として用いられる品目を生産するための作業量の
累計が、現在日より前の日に割り当てられた作業量の累
計以上存在するか否かを判定し、存在する場合に、当該
工程については、前記要求に引き当てられていない最終
品目についての生産計画を変更することにより、前記要
求に引き当てられている最終品目の完成予定を満たす生
産計画の立案の可能性がある旨を判定する生産計画実行
判定手段とを有することを特徴とする生産計画システム
を提供する。
In order to achieve the above object, the present invention takes, for example, a part of a manufacturing process for manufacturing a final item, and is used as a part of the final item in the carried step. Or a production planning system for generating a production plan of a manufacturing system having a plurality of shops for producing the final item, when it is required to supply the required number of the final item at a necessary time, The final item to be completed in the completion schedule that specifies the final item's completion schedule is not allocated to other requirements to be completed before the specified required time,
If there is more than the required number of final items, this is allocated to the request, and if not, allocation means for adding the completion schedule of the final item satisfying the request to the completion schedule, and completion. Based on the schedule, set the work period of each process to manufacture each final item so that the amount of work of each process generated by the production plan on each day does not exceed the capacity of the corresponding shop on each day. , A means to generate a production plan by moving forward from the scheduled completion date, and for each process, from the generated production plan, manufacture all items scheduled to be completed in the process on that day on each day. If the amount of work allocated for each process exceeds the capacity of the shop on that day for each process, the completed work is calculated by totalizing the amount of work required for As described above, the amount of work included in each completed work amount is assigned in order from the latest scheduled completion date to the past from the corresponding expected completion date, and the means for allocating to each day and each process are dated before the current date. If the workload is allocated to the last item, the final item that has not been allocated to the request and the final item in question during the period in which the day when the workload is reassigned to the previous day continues from the present date toward the future. It is determined whether or not the total amount of work for producing the item used as a part of the item exists more than the total amount of work assigned to the day before the current date. , It is determined that there is a possibility of making a production plan that meets the completion schedule of the final item assigned to the requirement by changing the production plan for the final item not assigned to the requirement. It provides for the production planning system characterized by having a production plan execution determining means for.

【0011】[0011]

【作用】本発明に係る生産計画システムによれば、生成
された生産計画より、各工程について、各日毎に、当該
日に当該工程で完成予定の品目を全て製造するために要
する作業量を累計した完成作業量を求め、各工程につい
て、各日に割り当てられる作業量が当該日のショップの
能力を超えた場合に、超えた分の作業量を前日に割り当
て直すように、完成予定日の遅いものより順次、各完成
作業量に含まれる作業量を、対応する完成予定日より過
去に向かって順次、各日に割り当てる手段と各工程につ
いて、現在日より前の日に、作業量が割り当てられた場
合に、前の日に作業量を割り当て直された日が現在日よ
り将来に向かって連続する期間中に、前記要求に引き当
てられていない最終品目および当該最終品目に部品とし
て用いられる品目を生産するための作業量の累計が、現
在日より前の日に割り当てられた作業量の累計以上存在
するか否かを判定し、存在する場合に、当該工程につい
ては、前記要求に引き当てられていない最終品目につい
ての生産計画を変更することにより、前記要求に引き当
てられている最終品目の完成予定を満たす生産計画の立
案の可能性がある旨判定する。
According to the production planning system of the present invention, based on the produced production plan, for each process, the total amount of work required to manufacture all the items scheduled to be completed in the process on the day concerned is accumulated. If the amount of work allocated for each process exceeds the capacity of the shop on that day for each process, the amount of work that has been exceeded is reassigned to the previous day, so that the completed date is late. For each means and process that allocates the amount of work included in each completed work amount in order from the corresponding planned completion date to the past, the work amount is assigned to the day before the current date. In the case of the last day, the last item that has not been allocated to the requirement and the item that is used as a part of the last item during the period in which the amount of work is reassigned to the previous day is continuous from the present date toward the future. It is determined whether or not the cumulative amount of work for producing is greater than or equal to the cumulative amount of work assigned to the day before the current date, and if there is, the process is allocated to the request. It is determined that there is a possibility of drafting a production plan that meets the completion schedule of the final item allocated to the requirement by changing the production plan for the final item that does not exist.

【0012】したがい、この判定結果に基づいて、計画
立案者は、問題となっている工程毎に、要求に引き当て
られた、すなわち、実際に必要となっている完成予定を
満たす生産計画が、前記要求に引き当てられていない最
終品目についての生産計画を変更することにより立案可
能であるか否かを即座に認識することができる。したが
い、これに沿って、たとえば、前記要求に引き当てられ
ていない最終品目についての生産計画を変更することに
より立案可能である旨認識できた場合には、問題となっ
ている工程での作業を発生している前記要求に引き当て
られていない最終品目についての生産計画を取りやめる
ように生産計画を調整し、実際に必要となっている完成
予定を満たし、かつ、全体として問題の無い生成計画を
立案することができる。
Therefore, based on this judgment result, the planner determines that the production plan assigned to the requirement, that is, satisfying the actual completion schedule is required for each process in question. It is possible to immediately recognize whether or not it is possible to make a plan by changing the production plan for the final item that is not allocated to the requirement. Therefore, along with this, if it can be recognized that it is possible to make a plan by changing the production plan for the final item that is not allocated to the requirement, the work in the problematic process occurs. The production plan is adjusted so as to cancel the production plan for the final item that has not been allocated to the above requirements, and the production plan that meets the actual required completion schedule and is not problematic as a whole is prepared. be able to.

【0013】[0013]

【実施例】以下、本発明に係る生産計画システムの一実
施例について説明する。
EXAMPLE An example of the production planning system according to the present invention will be described below.

【0014】図1に、本実施例に係る生産計画システム
の構成を示す。
FIG. 1 shows the configuration of the production planning system according to this embodiment.

【0015】図中、1000は生産計画システム、11
00は受注システム、1200は製造システム、130
0は見込生産計画システムである。
In the figure, 1000 is a production planning system, 11
00 is an ordering system, 1200 is a manufacturing system, 130
0 is a forecast production planning system.

【0016】見込生産計画システム1300を用い、計
画立案者は、受注の見込量に基づいて、製品の完成スケ
−ジュ−ルを作成する。製品の完成スケ−ジュ−ルは、
製品名と製品の個数と完成日の組を指定する、それぞれ
注番を付された生産要求情報の集合として作成される。
作成された製品の完成スケ−ジュ−ルは、生産計画シス
テム1000に渡される。
Using the make-to-stock production planning system 1300, the planner creates a completed schedule of products based on the expected quantity of orders. The completed schedule of the product is
It is created as a set of production request information, each of which is assigned a note number, which specifies a product name, the number of products, and a completion date group.
The completed schedule of the created product is passed to the production planning system 1000.

【0017】生産計画システム1000は、製品の完成
スケ−ジュ−ルに基づいて、製造システム1200にお
ける製品の生産スケジュ−ルを作成する。
The production planning system 1000 creates a production schedule for a product in the manufacturing system 1200 based on the finished schedule for the product.

【0018】受注システムは、顧客よりの受注を処理
し、受注個数と要求納期を指定する受注情報を生産計画
システム1000に渡す。また、生産計画システム10
00より、生産スケジュ−ルに基づいた請負納期の回答
を得る。
The order-accepting system processes an order from a customer, and passes order-accepting information designating the number of orders and a requested delivery date to the production planning system 1000. In addition, the production planning system 10
From 00, the answer of the contract delivery date based on the production schedule is obtained.

【0019】製造システム1200は、生産計画システ
ム1000の立てた生産計画に従い、実際に製品を製造
するシステムである。
The manufacturing system 1200 is a system for actually manufacturing a product according to the production plan established by the production planning system 1000.

【0020】さて、生産計画システム1000は、製品
の完成スケ−ジュ−ルや受注情報や生産スケジュ−ルや
製造システム1200についての情報等を記憶するデー
タ記憶装置11と、計画立案者との間のユ−ザインタフ
ェ−スを提供するデータ入出力装置12とを有してい
る。
The production planning system 1000 includes a data storage device 11 for storing a product completion schedule, order information, a production schedule and information about the manufacturing system 1200, and a planner. And a data input / output device 12 for providing the user interface of the above.

【0021】また、MRP制御装置2、MRP展開装置
8、リードタイム計算装置1、作業量計算装置3、作業
量解析装置27、生産計画実行判定装置101を有して
いる。
Further, it has an MRP control device 2, an MRP development device 8, a lead time calculation device 1, a work amount calculation device 3, a work amount analysis device 27, and a production plan execution judgment device 101.

【0022】また、問題点解析装置7、生産能力調整装
置4、完成日調整装置5、代替ショップ調整装置6、作
業着手順序調整装置33、生産量調整装置104、計画
削除装置27を有している。
Further, it has a problem analysis device 7, a production capacity adjustment device 4, a completion date adjustment device 5, an alternative shop adjustment device 6, a work start sequence adjustment device 33, a production amount adjustment device 104, and a plan deletion device 27. There is.

【0023】さて、ここで、本実施例においては、製造
システム1200を次のようにモデル化する。
Now, in this embodiment, the manufacturing system 1200 is modeled as follows.

【0024】まず、各ショップをショップグル−プとし
てグル−プ化する。各シヨップグル−プは、作業を相互
に代替することのでき、かつ、担う工程に相互の前後関
係のないショップの集合であり、たとえば、組立を行う
ショップについてのショップグル−プ、塗装を行うショ
ップについてのショップグル−プ、加工を行うショップ
についてのショップグル−プ等が考えられる。
First, each shop is grouped into a shop group. Each shop group is a group of shops that can substitute for each other and do not have a mutual relationship in the processes to be carried out. For example, a shop group for a shop that assembles and a shop that performs painting. About the shop group and the shop group about the shop that performs the processing.

【0025】次に、各ショップグル−プをトポロジカル
ソ−トの手法によって並べる。
Next, the shop groups are arranged by the method of topological sort.

【0026】すなわち、いかなる製品の生産について、
より前の工程から生産工程順に各工程を担うショップ並
べ、並んだショップに対応して、各ショップの属するシ
ョップグル−プの番号を並べても、必ず、より小さい番
号が、より大きい番号より前になるように各ジョブグル
−プに番号を付す。これにより、いかなる製品の生産に
おいても、より前の工程を担うショップの属するショッ
プグル−プの番号は、より後の工程を担うショップの属
するショップグル−プの番号より小さいことになる。そ
こで、より小さい番号のショップグル−プを上流のショ
ップグル−プとし、より大きい番号のショップグル−プ
を下流のショップグル−プとする。
That is, regarding the production of any product,
Even if the shops that carry out each process are arranged in order from the earlier process to the production process, and the number of the shop group to which each shop belongs is arranged corresponding to the arranged shops, the smaller number always precedes the larger number. Number each job group so that As a result, in the production of any product, the number of the shop group to which the shop that carries the earlier process belongs is smaller than the number of the shop group to which the shop that carries the later process belongs. Therefore, a smaller-numbered shop group is set as an upstream shop group, and a larger-numbered shop group is set as a downstream shop group.

【0027】なお、各工程で製造された結果物を品目と
いい、各品目と当該品目を製造するショップとの関係は
あらかじめ、製造システムに関する情報としてデータ記
憶装置11に設定されているものとして説明する。ま
た、本実施例では、材料等、外部より調達する必要のあ
る品目を調達するシステムもショップとして扱う。本実
施例では、このショップを調達ショップと呼ぶ。調達シ
ョップは、品目の所要量より在庫量を減じた正味所要
量、品目を外部に発注し、調達するシステムである。
The products produced in each process are called items, and the relationship between each item and the shop that manufactures the item is preliminarily set in the data storage device 11 as information about the manufacturing system. To do. Further, in this embodiment, a system for procuring items such as materials that need to be procured from outside is also handled as a shop. In this embodiment, this shop is called a procurement shop. Procurement shop is a system for ordering and procuring net requirements and items, which are obtained by subtracting the inventory amount from the requirements of items.

【0028】また、製造システム1200は、各品目の
在庫量をも管理しており、現在の在庫状況を生産計画シ
ステム1000のデータ記憶装置11に送る。各ショッ
プで処理された品目、調達ショップで調達された品目
は、在庫に加えられる。
The manufacturing system 1200 also manages the inventory quantity of each item, and sends the current inventory status to the data storage device 11 of the production planning system 1000. Items processed at each shop and items procured at the procurement shop are added to the inventory.

【0029】以下、本実施例に係る生産計画システム1
000の動作について説明する。
Hereinafter, the production planning system 1 according to this embodiment
000 operation will be described.

【0030】本実施例に係る生産計画システム1000
は、まず、見込生産計画システム1100が作成した完
成スケジュ−ルに基づいた生産計画を作成する。
Production planning system 1000 according to the present embodiment
First creates a production plan based on the completed schedule created by the expected production planning system 1100.

【0031】図2に本実施例に係る生産計画システムの
生産計画生成の処理手順を示す。
FIG. 2 shows a processing procedure for production plan generation of the production planning system according to this embodiment.

【0032】まず、見込生産計画システム1100から
受け取った完成スケジュ−ルをデータ記憶装置11に記
憶した後に、データ入出力装置12より所要量展開指示
30を受けると、完成スケジュ−ル中の各注番に対応す
る生産要求情報中の製品(最終品目)名と、最終品目の
総所要量と完成日を、データ記憶装置11より読みだす
(201)。
First, after storing the completed schedule received from the expected production planning system 1100 in the data storage device 11, and receiving the required amount expansion instruction 30 from the data input / output device 12, each note in the completed schedule is received. The product (final item) name in the production request information corresponding to the number, the total required amount of the final item, and the completion date are read from the data storage device 11 (201).

【0033】次に、MRP制御装置2は、MRP展開装
置8の動作を制御して、最下流のショップグループに属
する各ショップについて(202)、順次、当該ショッ
プで製造する各品目毎に、総所要量より、データ記憶装
置11に記憶されている在庫量を減じ実際に当該ショッ
プで製造する必要のある数量を求め、当該ショップで製
造する各品目の正味所要量とする(203、204)。
次に、ショップ毎に、求めた各品目の正味所要量と完成
日をデータ3として、作業量計算装置40に渡す。ま
た、この際には、注番毎の所要量も求めておく。
Next, the MRP control device 2 controls the operation of the MRP expansion device 8 so that each shop belonging to the most downstream shop group (202) is sequentially processed for each item manufactured in the shop. The inventory quantity stored in the data storage device 11 is subtracted from the required quantity to find the quantity that actually needs to be manufactured in the shop, and set as the net required quantity of each item manufactured in the shop (203, 204).
Next, for each shop, the calculated net required amount and completion date of each item are passed to the work amount calculation device 40 as data 3. At this time, the required amount for each order number is also obtained.

【0034】作業量計算装置40は、ショップ毎に完成
作業量26を計算し(208)てリードタイム計算装置
1へ渡す。ここで完成作業量とは、各日毎に、当該日を
完成日としている全ての品目を製造するために必要なシ
ョップの作業量を求めたものをいう。
The work amount calculation device 40 calculates the completed work amount 26 for each shop (208) and transfers it to the lead time calculation device 1. Here, the completion work amount refers to the amount of work of the shop required for manufacturing all the items whose completion date is that day, for each day.

【0035】一方、リードタイム計算装置1ではショッ
プ毎に求めた完成作業量26と、あらかじめ設定されて
いるショップの生産能力13を基に、各品目のリードタ
イム14を求める(207、208、209)。リ−ド
タイムの計算方法の詳細については後述する。
On the other hand, in the lead time calculation device 1, the lead time 14 of each item is obtained based on the completed work amount 26 obtained for each shop and the preset production capacity 13 of the shop (207, 208, 209). ). The details of the calculation method of the lead time will be described later.

【0036】MRP展開装置8では、各品目を順次、展
開対象品目とし、リードタイム計算装置1が求めた展開
対象品目のリードタイム14を完成日から減じることに
より展開対象品目の製造着手日を決定し、展開対象品目
を製造するために必要な品目(子品目)を求め、決定し
た着手日を子品目の完成日とし、また、求めた各子品目
毎に総所要量についての所要量展開処理を行って、展開
対象品目を製造するために必要な各子品目の数量を求め
る(210〜113)。
In the MRP expansion device 8, each item is sequentially set as an expansion target item, and the lead time 14 of the expansion target item obtained by the lead time calculation device 1 is subtracted from the completion date to determine the manufacturing start date of the expansion target item. Then, the items (sub-items) necessary for manufacturing the expansion target items are obtained, the determined start date is set as the completion date of the sub-items, and the required amount expansion process for the total required amount is calculated for each sub-item. Then, the quantity of each child item required to manufacture the expansion target item is obtained (210 to 113).

【0037】以上、これで最下流のショップグル−プに
ついての生産計画が完了するので、MRP制御装置2
は、順次、上流のショップグル−プについて、図2符号
103以降の処理を繰り返す(214、215)。ただ
し、調達ショップについては、単純に、その品目の調達
に要する期間をリ−ドタイム(調達リ−ドタイム)と
し、リ−ドタイムより求まる着手日を、その品目を発注
する日とする。
As described above, since the production plan for the most downstream shop group is completed, the MRP controller 2
Sequentially repeats the processes after the reference numeral 103 in FIG. 2 for the upstream shop group (214, 215). However, for the procurement shop, the period required for the procurement of the item is simply set as the lead time (procurement lead time), and the start date obtained from the lead time is set as the date for ordering the item.

【0038】本実施例に係る生産計画システムは、この
ように生産計画の生成(MRPリジェネレーション)を
行なう。
The production planning system according to the present embodiment thus carries out the production planning (MRP regeneration).

【0039】次に、前述したリードタイム計算装置1の
行なうリードタイム計算について説明する。
Next, the lead time calculation performed by the lead time calculating device 1 described above will be described.

【0040】前述したように、リ−ドタイム計算装置1
は、各ショップの負荷を考慮して、各工程のリードタイ
ムを予測する。
As described above, the lead time calculation device 1
Predicts the lead time for each process, considering the load on each shop.

【0041】ところで、各ショップが工程フロ−上で固
定の作業を担うフローショップにおいてはライン固有の
タクトタイムがあり、最適な生産速度および1個あたり
のリードタイムが存在する。
By the way, in a flow shop in which each shop carries out a fixed work on the process flow, there is a tact time unique to the line, and there is an optimum production speed and a lead time per piece.

【0042】また、各ショップが投入されたジョブの作
業を担うジョブショップにおいては、平均のリードタイ
ムがショップ内仕掛りにほぼ比例して増大するのに対し
て、生産速度は仕掛りが増えてもあるレベルで飽和して
増加しなくなることが、待ち行列理論等を利用した過去
の研究により良く知られている。この事実は、最適な仕
掛りレベル、生産速度が存在し、ジョブを投入しても、
品目1個あたりのリードタイムが増大するばかりで生産
速度がほとんど増えくなる点が存在することを示してい
る。
Further, in the job shop which takes charge of the jobs submitted by each shop, the average lead time increases almost in proportion to the in-shop work in process, while the production speed increases in the work in progress. It is well known from past studies using queuing theory that the saturation is not reached and increases at a certain level. The fact is that there is an optimal work-in-progress level and production speed, and even if a job is submitted,
It indicates that there is a point that the lead time per item only increases and the production speed almost increases.

【0043】したがい、この最適な生産速度を保てるよ
うな生産計画を生成するようにリ−ドタイムを求める必
要がある。
Therefore, it is necessary to obtain the lead time so as to generate a production plan that can maintain the optimum production speed.

【0044】そこで、本実施例では、次のようにリ−ド
タイムを図3に示す方法で予測する。
Therefore, in this embodiment, the lead time is predicted by the method shown in FIG. 3 as follows.

【0045】図示するように、本実施例では、ショップ
毎に、当該ショップの担う各工程のリ−ドタイムを求め
る。いま、各ショップにおける最適な生産速度における
サイクルタイム(投入間隔=品目1個の産出間隔)と、
各品目1個あたりのリードタイムがショップごとに分か
っているものとする。
As shown in the figure, in the present embodiment, the lead time of each process carried out by each shop is obtained. Now, the cycle time (input interval = output interval of one item) at the optimum production speed at each shop,
It is assumed that the lead time for each item is known for each shop.

【0046】前述したように、まず、作業量計算装置4
0が、対象ショップの各日の完成作業量を求める。完成
作業量とは、当該日を完成日とする品目の作業量の総計
であり、図3aに示するように、完成作業量は、品目の
個数と当該品目を1個製造するのに要する標準時間ST
の積を、当該日を完成日とする全品目について総和した
ものとなる。なお、この際には、当該日を完成日とする
品目を用いる注番毎の、対象ショップにおける当該日
の、作業量も求めておく。
As described above, first, the work amount calculation device 4
0 determines the amount of completed work of the target shop each day. The completion work amount is the total work amount of the items whose completion date is the relevant date, and as shown in FIG. 3a, the completion work amount is the number of items and the standard required to manufacture one of the items. Time ST
The product of is the sum of all items whose completion date is the relevant date. At this time, the amount of work on the target shop for each order using the item whose completion date is the relevant day is also calculated.

【0047】次に、図3bに示すように、作業量分布と
投入時期を求める。
Next, as shown in FIG. 3b, the work amount distribution and the input timing are obtained.

【0048】すなわち、負荷を未来から過去の方向へ前
倒ししながら作業量分布を決めて行く。たとえばn日に
完成する品目群Aの作業量分布は次のように決める。ま
ず完成時刻(=最後の1個の産出時刻)を完成日の終わ
りと一致するように設定する。次に最初の1個の産出時
刻から最後の1個の産出時刻の間の幅を、当該日の正規
化完成作業量×標準サイクルタイムとして求め、最初の
1個の産出時刻を決定する。さらに当該品目1個あたり
のリードタイムを減じたものが、最初の1個の投入時
刻、すなわちAの着手時刻となる。ただし、品目群Bの
ように、次の日に完成する品目群Aの最初の1個の産出
時刻が、自身の完成日より前となった場合は、Bの完成
時刻をこれと一致させるように設定する。
That is, the work amount distribution is determined while the load is moved forward from the future to the past. For example, the work load distribution of the item group A completed on the nth day is determined as follows. First, set the completion time (= the production time of the last one) to coincide with the end of the completion date. Next, the width between the first one production time and the last one production time is obtained as the normalized completion work amount × standard cycle time of the day, and the first one production time is determined. Further, the lead time for each item is subtracted, and the first one is input time, that is, the start time of A. However, like the item group B, if the first production time of the item group A that will be completed on the next day is before the completion date of its own, make the completion time of B coincide with this. Set to.

【0049】ここで、正規化完成作業量とは、前記完成
作業量を標準ST(当該ショップで作業される品目のS
Tの、作業数量比による加重平均値をとったもの)で割
って正規化したものである。また標準サイクルタイムと
は当該ショップで作業される品目のサイクルタイムの、
作業数量比による加重平均値をとったものである。1個
あたりの標準リードタイムとしては、当該ショップで作
業される品目の1個あたりのリードタイムの、作業数量
比による加重平均値ををとったものである。
Here, the normalized completed work amount means the standard work amount (S of items to be worked in the shop concerned).
It is normalized by dividing the weighted average value of T by the work quantity ratio). Also, the standard cycle time is the cycle time of the items that are worked in the shop,
It is a weighted average value based on the work quantity ratio. The standard lead time per piece is the weighted average value of the lead time per piece of the item worked in the shop, which is based on the work quantity ratio.

【0050】次に、図3cに示すように、着手時刻と完
成時刻の間隔をリ−ドタイムとする。次の日以降に完成
する品目の作業が、完成日より前にずれ込んできている
ものについてはその分だけリードタイムが増大すること
となる。
Next, as shown in FIG. 3c, the interval between the start time and the completion time is set as the read time. If the work of the item completed after the next day is delayed before the completion date, the lead time will be increased accordingly.

【0051】ところで、本実施例では、後述するよう
に、生産計画の調整をショップの能力の設定を、日毎に
違うように変更することにより行なう。ここで、この場
合の動作について説明しておく。
By the way, in the present embodiment, as will be described later, the production plan is adjusted by changing the setting of the ability of the shop so that it is different for each day. Here, the operation in this case will be described.

【0052】この場合は、能力がα倍になったときは、
標準サイクルタイムと標準リ−ドタイムが1/α倍とな
るから、図3cの幅と、傾きを1/αすれば良い。しか
し、このようにすると、能力の変わり目では計算が複雑
になる。そこで、本実施例では、図4のbのようにす
る。すなわち、能力がα倍になったということは、時間
軸がα倍だけ伸びたと考え、この伸縮した時間軸上で、
図3と同じように幅と、傾きを設定し、リードタイムを
読み取るようにする。
In this case, when the ability becomes α times,
Since the standard cycle time and the standard read time are 1 / α times, the width and the inclination in FIG. 3c should be 1 / α. However, this makes the calculation complicated at the turning point of the ability. Therefore, in this embodiment, it is set as shown in FIG. That is, the ability increased α times means that the time axis has expanded by α times, and on this expanded / contracted time axis,
As in FIG. 3, the width and the inclination are set and the lead time is read.

【0053】以上のようにして、リードタイム計算装置
1は、ショップ毎に当該ショップの総合的な負荷を考慮
して各工程のリ−ドタイムを設定する。
As described above, the lead time calculating apparatus 1 sets the lead time of each process for each shop in consideration of the total load of the shop.

【0054】なお、以上のように、リードタイムの予測
を行うためには予測用パラメータが必要である。予測用
パラメータはSTおよびサイクルタイムおよび1個あた
りのリードタイムである。これらは、製造システム12
00についての情報として、データ記憶装置装置11
に、あらかじめ記憶しておく。ただし、製造システムか
ら生産実績の情報を得、これを基に正確な予測用パラメ
ータを計算し、リードタイム計算装置1に与えるように
してもよい。
As described above, the parameters for prediction are necessary to predict the lead time. The prediction parameters are ST, cycle time, and lead time per piece. These are the manufacturing system 12
00 as information about the data storage device 11
It is stored in advance. However, the production performance information may be obtained from the manufacturing system, an accurate prediction parameter may be calculated based on the production performance information, and may be provided to the lead time calculation device 1.

【0055】なお、リードタイム計算装置1は、パター
ン変換モデル、例えば、ニューラルネットワークを用い
て実現することもできる。ニューラルネットワークは、
入力データと出力データとの間のパターン変換能力およ
び、パターン学習能力を有するため、リードタイム計算
装置1、作業量計算装置3に関して、たとえば以下に示
すようなデータを用いて各々のニューラルネットワーク
を学習させておくことにより、新たな入力に対してリー
ドタイムをパターン変換により算出することが可能とな
る。
The lead time calculation device 1 can also be realized by using a pattern conversion model, for example, a neural network. The neural network is
Since it has a pattern conversion ability between the input data and the output data and a pattern learning ability, the lead time calculation device 1 and the work amount calculation device 3 learn each neural network by using the following data, for example. By doing so, the lead time for a new input can be calculated by pattern conversion.

【0056】入力:各ショップの能力、完成作業量 出力:リードタイム なお、ニュートラルネットワークの理論については、ル
メルハルト デー・イー、マクラレンド ジェー・エル
アンド ザ ピーデーピー リサーチグループ、19
86、パラレル ディストリビューティド プロセシン
グ:エムアイティー プレス (Remelhart D. E.、McC
lelland J. L. and The PDP Research group、 1986、
Parallel Destributed Processing : MIT Press)に詳
述されている。
Input: Ability of each shop, completed work output: Lead time In addition, regarding the theory of the neutral network, Rumelhardt Dee, McLarend JL and the PDP Research Group, 19
86, Parallel distributed processing: MI Press (Remelhart DE, McC
lelland JL and The PDP Research group, 1986,
Parallel Destributed Processing: MIT Press).

【0057】ニューラルネットワークをリードタイム計
算装置1として使用する時も、予測用パラメータが必要
である。予測用パラメータはニューラルネットワークの
細胞間の結合強度値の組である。これらは、製造システ
ムから得られた生産実績データを基にニューラルネット
ワークの学習を行うようにする。
Even when the neural network is used as the lead time calculation apparatus 1, a prediction parameter is necessary. The prediction parameter is a set of bond strength values between cells of the neural network. These perform learning of the neural network based on the production performance data obtained from the manufacturing system.

【0058】さて、このようにして、見込生産計画シス
テム1300が作成した完成スケジュ−ルに従った、注
番毎の生産、調達計画が、ショップ毎に生産計画システ
ム1000によって作成され、データ記憶装置11に記
憶される。いま、この時点で、生産、調達計画は完成ス
ケジュ−ルを満足できるように、すなわち、現在より以
前の着手日、発注日が設定されることなく作成できたも
のとする。
In this way, the production and procurement plan for each order number is created by the production planning system 1000 for each shop according to the completed schedule created by the expected production planning system 1300, and the data storage device is used. 11 is stored. Now, at this point, it is assumed that the production and procurement plan can be created so that the completed schedule can be satisfied, that is, the start date and order date before the present are not set.

【0059】さて、この後、受注システム1100よ
り、受注製品と要求個数と要求納期を指定する受注情報
がデータ記憶装置11に送られると、MPR制御装置は
2、要求納期より一定日数前の日を完成日として、生産
計画を作成した生産要求情報に付されている注番を、こ
れに引き当てる。そして、引き当てられた場合には、要
求納期を請負納期としてデータ記憶装置11を介して受
注システム1100に回答する。また、注番と、これを
引き当てた受注情報の対応をデータ記憶装置11に記憶
する。
After that, when the order receiving system 1100 sends the order receiving information designating the ordered products, the required number of products, and the required delivery date to the data storage device 11, the MPR control device receives 2, which is a certain number of days before the required delivery date. As the completion date, the order number attached to the production requirement information that created the production plan is assigned to this. When assigned, the requested delivery date is set as the contract delivery date, and the ordering system 1100 is answered via the data storage device 11. Further, the correspondence between the order number and the order information assigned thereto is stored in the data storage device 11.

【0060】しかし、見込生産計画システム1300が
作成した完成スケジュ−ルで予定した量を超える受注が
あった場合には、受注に引き当てることのできる注番
が、もはやないので、新たに、この受注情報が示す受注
内容を満足する、製品名と完成日と数量を指示する生産
要求情報を作成し、新たな注番を付して完成スケジュ−
ルに加え、この注番を受注情報に引き当てる。そして、
MRP展開装置8に生産計画の再生成を指示する。
However, if there is an order received that exceeds the planned quantity in the completed schedule created by the forecast production planning system 1300, there is no note number that can be assigned to the order anymore. Create production request information that indicates the product name, completion date, and quantity that satisfy the order received by the information, and add a new order number to complete the schedule.
In addition to this, assign this order number to order information. And
The MRP expansion device 8 is instructed to regenerate the production plan.

【0061】さて、生産計画の再生成を指示されたMR
P展開装置8、作業料計算装置3、リ−ドタイム計算装
置1は、現在の在庫量をデータ記録装置11より読み出
し、前述したように注番毎の生産、調達計画を、ショッ
プ毎に作成し、データ記憶装置11に記憶するが、この
際、作業量解析装置27と、生産計画判定装置101
は、作業量の面から、この新たな完成スケジュ−ルを満
足する実行可能な生産計画が立案されたか否か、立案さ
れなかった場合には、受注に引き当てられた全ての注番
の生産要求を満足する実行可能な生産計画が立案可能か
否かを判定する。また、MRP展開装置展開装置8と、
生産計画判定装置101は、外部より調達する品目につ
いての在庫量の面から、この新たな完成スケジュ−ルを
満足する実行可能な生産計画が立案されたか否か、立案
されなかった場合には、受注に引き当てられた全ての注
番の生産要求を満足する実行可能な生産計画が立案可能
か否かを判定する。
Now, the MR instructed to regenerate the production plan
The P expansion device 8, the work charge calculation device 3, and the lead time calculation device 1 read out the current stock amount from the data recording device 11 and prepare the production and procurement plan for each order number for each shop as described above. , The data storage device 11, but at this time, the work amount analysis device 27 and the production plan determination device 101.
In terms of the amount of work, whether or not a viable production plan that satisfies this new completed schedule has been drafted, and if not, the production requirements for all the orders assigned to the order, It is determined whether or not a viable production plan that satisfies the above can be drafted. In addition, the MRP expansion device expansion device 8,
The production plan determination device 101 determines whether or not a feasible production plan satisfying the new completed schedule has been drafted in terms of the inventory quantity of the items to be procured from the outside. It is determined whether or not a viable production plan that satisfies the production requirements of all the order numbers assigned to the orders can be drafted.

【0062】まず、作業量解析装置27と、生産計画判
定装置101が行なう、作業量の面からの判定動作につ
いて説明する。
First, the operation of judging the work amount performed by the work amount analyzing device 27 and the production plan judging device 101 will be described.

【0063】すなわち、リードタイム計算装置1では、
前述したように完成日単位の完成作業量データをショッ
プの生産能力(時間)にあわせて将来から現在へ向かっ
て前に倒すことで、実際に要するリ−ドタイムを計算す
る。したがい、図5aに示すように、現在日より作業を
行なう場合のショップの過負荷量の累計は、現在日より
前に存在する作業量の累計500となる。また、各日に
おいて、前日に倒す作業量を、その日の過負荷量とす
る。
That is, in the lead time calculation device 1,
As described above, the actual required lead time is calculated by moving the completed work amount data for each completed day unit forward from the future toward the present in accordance with the production capacity (time) of the shop. Therefore, as shown in FIG. 5A, the cumulative total of the overloads of the shops when the work is performed from the current date is the cumulative total of the workloads existing before the current date 500. In addition, on each day, the amount of work to be done the day before is the overload amount for that day.

【0064】作業量解析装置27は、リードタイム計算
装置1より、各ショップについての、各日の過負荷量を
得、現在日より前日に倒す完成作業量が無ければ、生産
計画判定装置101に、その旨通知し、作業量解析装置
27は、作業量の面から、このショップについて、新た
な完成スケジュ−ルを満足する実行可能な生産計画が立
案されたと判定し、データ記憶装置11に、その旨記憶
する。
The work amount analyzing device 27 obtains the overload amount for each shop from the lead time calculating device 1 on each day, and if there is no completed work amount to be defeated on the day before the present day, the work amount analyzing device 27 instructs the production plan judging device 101. Then, the work amount analysis device 27 determines that an executable production plan satisfying the new completed schedule has been drafted for this shop in terms of work amount, and the data storage device 11 Memorize that.

【0065】一方、作業量解析装置27は、現在日より
前日に倒す完成作業量があれば、現在日より将来に向い
連続して過負荷量が存在する各日の過負荷量(図5b参
照)を生産計画判定装置101に渡す。
On the other hand, if there is a completed work amount to be defeated on the day before the present day, the work amount analysis device 27 determines the overload amount on each day when the overload amount continuously exists in the future from the present day (see FIG. 5b). ) Is passed to the production plan determination device 101.

【0066】この場合、生産計画判定装置101は、次
のようにして、受注に引き当てられた注番の生産要求を
満足する実行可能な生産計画が立案可能か否かを判定す
る。
In this case, the production plan judging device 101 judges whether or not a viable production plan satisfying the production request of the order number assigned to the order can be made as follows.

【0067】すなわち、過負荷量が連続する期間を複数
の期間に区切り、受注に引き当てられていない注番の生
産を取りやめることにより、各期間の先頭日の過負荷量
が、その期間内に解消できるか否かを判定する。
That is, by dividing the period in which the overload amount is continuous into a plurality of periods and canceling the production of the order number that is not assigned to the order, the overload amount on the first day of each period is resolved within that period. Determine if it is possible.

【0068】たとえば、図5cの例では、(1)+
(2)の期間の先頭日以前の作業量a+b以上の作業量
が、受注に引き当てられていない注番に対応する作業量
として、(1)もしくは(1)+(2)の期間内に存在
する場合、もしくは、(2)の期間の先頭日の過負荷量
b以上の作業量が、受注に引き当てられていない注番に
対応する作業量として、(2)の期間内に存在し、か
つ、(1)の期間以前の作業量a+bから(2)の期間
の先頭日の過負荷量bを減じた過負荷量a以上の作業量
が、受注に引き当てられていない注番に対応する作業量
として、(1)の期間内に存在する場合には、このショ
ップについては、受注に引き当てられていない注番の生
産スケジュ−ルを変更することにより、受注に引き当て
られた注番の生産要求を満足する実行可能な生産計画が
立案可能と判定し、データ記憶装置11に、その旨記憶
する。また、この際には、現在日より将来に向い連続し
て過負荷量が存在する期間中に作業量を発生させる、受
注に引き当てられていない注番も、スケジュ−ル変更候
補注番として記憶しておくようにしてもよい。
For example, in the example of FIG. 5c, (1) +
The amount of work a + b or more before the first day of the period (2) exists within the period (1) or (1) + (2) as the amount of work corresponding to the order number not assigned to the order. Or the work amount equal to or larger than the overload amount b on the first day of the period (2) exists within the period (2) as the work amount corresponding to the order number not assigned to the order, and , The work corresponding to the order number which is not assigned to the order, the work amount of which is equal to or more than the overload amount a obtained by subtracting the overload amount b of the first day of the period (2) from the work amount a + b before the period (1) If the quantity exists within the period (1), for this shop, by changing the production schedule of the order number not assigned to the order, the production request of the order number assigned to the order is changed. It is determined that a viable production plan that satisfies The chromatography data storage device 11, to that effect storage. At this time, note numbers that are not assigned to orders and that generate work during a period in which there is a continuous overload from the present date to the future are also stored as schedule change candidate note numbers. You may keep it.

【0069】もし、この他の場合は、このショップにつ
いては、受注に引き当てられた注番の生産要求を満足す
る実行可能な生産計画が立案不可能と判定し、データ記
憶装置11に、その旨記憶する。
In other cases, it is determined that, for this shop, an executable production plan that satisfies the production request for the order number assigned to the order cannot be made, and the data storage device 11 is so notified. Remember.

【0070】そして、全てのショップについて、以上の
判定を行なったら、それぞれの注番の生産に携わる全て
のショップについて、新たな完成スケジュ−ルを満足す
る実行可能な生産計画が立案されたと判定されたか否か
を、受注に引き当てられている各注番について判定し、
全てのショップについて、新たな完成スケジュ−ルを満
足する実行可能な生産計画が立案されたと判定されてい
れば、当該注番に対応する生産要求を満足する生産計画
が立案されたと判定し、データ記憶装置11に記憶す
る。
When the above judgments have been made for all the shops, it is judged that a viable production plan satisfying the new completed schedule has been drafted for all the shops involved in the production of each order number. Whether or not it is determined for each order number assigned to the order,
If it is determined that a viable production plan that satisfies the new completed schedule has been drafted for all shops, it is determined that a production plan that satisfies the production requirements corresponding to the relevant order number has been drafted, and the data It is stored in the storage device 11.

【0071】また、それぞれの注番の生産に携わるいず
れかのショップについて、受注に引き当てられた注番の
生産要求を満足する実行可能な生産計画の立案が不可能
と判定された場合には、当該注番に対応する生産要求を
満足する生産計画が立案不可能な場合があると判定し、
その旨、データ記憶装置11に記憶する。
If it is determined that a viable production plan that satisfies the production requirement of the order number assigned to the order is not possible for any of the shops involved in the production of the respective order numbers, It is determined that it may not be possible to make a production plan that satisfies the production requirements corresponding to the order number,
The fact is stored in the data storage device 11.

【0072】これ以外の場合は、当該注番に対応する生
産要求を満足する実行可能な生産計画が、受注に引き当
てられていない注番の生産スケジュ−ルを変更すること
により、立案可能と判定し、データ記憶装置11に、そ
の旨記憶する。
In other cases, it is determined that a feasible production plan satisfying the production requirement corresponding to the order number can be planned by changing the production schedule of the order number not allocated to the order. Then, the fact is stored in the data storage device 11.

【0073】次に、MRP展開装置展開装置8と、生産
計画判定装置101とが、外部より調達する品目につい
ての在庫量の面から行なう判定について説明する。この
判定は、作業量の面より、新たな完成スケジュ−ルを満
足する実行可能な生産計画が立案されたとしても、外部
より調達する部品の不足により、立案された生産計画が
実行不可能な場合があることを考慮したものである。
Next, the judgment made by the MRP expanding device expanding device 8 and the production plan judging device 101 in terms of the inventory quantity of the items procured from the outside will be described. Even if a feasible production plan that satisfies the new completed schedule is drafted in terms of the amount of work, this decision makes it impossible to carry out the drafted production plan due to the lack of parts procured from outside. This is due to the fact that there are cases.

【0074】さて、外部よりの品目の調達には、一定の
期間(調達リ−ドタイム)を要する。したがい、現在日
において、現在日より、現在日に調達リ−ドタイム加算
した日までの在庫量(在庫予定量)は確定している。
Now, a certain period (procurement lead time) is required to procure an item from the outside. Therefore, at the current date, the inventory amount (planned inventory amount) from the current date to the date when the procurement lead time is added to the current date is fixed.

【0075】一方、作業量の面より、新たな完成スケジ
ュ−ルを満足する実行可能な生産計画が立案されたと仮
定すると、この生産計画においては、各作業の着手日は
現在日以降においてしか生じない。すなわち、MRP展
開装置8が前述したように求めた、外部より調達する品
目の、所要量は、現在日以降においてしか生じない。そ
こで、本判定では、現在日以降、現在日に調達リ−ドタ
イム加算した日までの、すなわち追加発注が間にあわな
い期間の所要量と在庫量(在庫予定量)を比較し、在庫
面からの生産計画の実行可能性を判定する。
On the other hand, assuming that a feasible production plan satisfying the new completed schedule is prepared from the viewpoint of the amount of work, in this production plan, the start date of each work occurs only after the current date. Absent. That is, the required amount of the item to be procured from the outside, which is obtained by the MRP expanding device 8 as described above, occurs only after the current date. Therefore, in this judgment, the required amount is compared with the inventory amount (planned inventory amount) from the current date to the date when the procurement lead time is added to the current date, that is, the period when the additional order is not in time, and the production from the inventory side is performed. Determine the feasibility of the plan.

【0076】生産計画判定装置101は、MRP展開装
置8が前述したように求めた、外部より調達する品目
の、各日の所要量と、確定している各日の在庫量(在庫
予定量)を、各品目について比較する。
The production plan determination device 101 determines the required amount for each day of the item to be procured from the outside, which has been determined by the MRP developing device 8 as described above, and the fixed inventory amount for each day (planned inventory amount). Are compared for each item.

【0077】そして、確定している各日の在庫量(在庫
予定量)が、各日の所要量を下回ることのない品目に関
して、新たな完成スケジュ−ルを満足する実行可能な生
産計画が立案されたと判定し、データ記憶装置11に、
その旨を記憶する。
Then, with respect to the items for which the confirmed inventory quantity (scheduled inventory quantity) of each day does not fall below the required quantity of each day, a feasible production plan satisfying the new completion schedule is drafted. Data storage device 11,
Memorize that.

【0078】一方、確定している各日の在庫量(在庫予
定量)が、各日の所要量を下回ることがある品目につい
ては、各日の所要量のうち、受注に引き当てられている
注番に対応する所要量を求め、これと、確定している各
日の在庫量(在庫予定量)を比較する。そして、確定し
ている各日の在庫量(在庫予定量)が、各日の受注に引
き当てられている注番に対応する所要量を所要量を下回
ることが無ければ、受注に引き当てられていない注番の
生産スケジュ−ルを変更することにより、この品目に関
して、受注に引き当てられた注番の生産要求を満足する
実行可能な生産計画が立案可能と判定し、データ記憶装
置11に、その旨記憶する。また、この際には、現在日
より、現在日に調達リ−ドタイム加算した日までの期間
に存在する所要量に対応する注番のうち、受注に引き当
てられていない注番もスケジュ−ル変更対象注番と記憶
しておくようにしてもよい。
On the other hand, for items for which the fixed inventory quantity (scheduled inventory quantity) for each day may fall below the required quantity for each day, the required quantity for each day is allocated to the order Note. The required quantity corresponding to the number is calculated, and this is compared with the confirmed inventory quantity (planned inventory quantity) for each day. If the confirmed inventory quantity (scheduled inventory quantity) for each day does not fall below the required quantity corresponding to the order number allocated for the order for each day, it is not allocated for the order. By changing the production schedule of the order number, it is determined that a feasible production plan that satisfies the production request of the order number assigned to the order can be drafted for this item, and the data storage device 11 is notified of that fact. Remember. In addition, at this time, of the order numbers corresponding to the required amount existing from the current date to the date when the procurement lead time is added to the current date, the order number not assigned to the order is also scheduled. You may make it memorize | store as a target note number.

【0079】図6には、一例として、リ−ドタイムが5
日の品目について、確定している各日の在庫量(在庫予
定量)が、各日の所要量を下回るが、各日の受注に引き
当てられている注番に対応する所要量の総計を下回らな
い場合について示した。
In FIG. 6, as an example, the lead time is 5
For the items of the day, the confirmed inventory quantity of each day (planned inventory quantity) is less than the requirement quantity of each day, but it is less than the total requirement quantity corresponding to the order number assigned to the order of each day. The case where there is no case is shown.

【0080】また、確定している各日の在庫量(在庫予
定量)が、各日の受注に引き当てられている注番に対応
する所要量の総計を下回ることがあれば、この品目に関
して、受注に引き当てられた注番の生産要求を満足する
実行可能な生産計画が立案不可能と判定し、データ記憶
装置11に、その旨記憶する。
Further, if the decided stock quantity of each day (planned stock quantity) may be less than the total quantity of the required quantity corresponding to the order number allocated to the received orders of each day, regarding this item, It is determined that a feasible production plan that satisfies the production request for the order number assigned to the order is unplanned, and the data storage device 11 stores that fact.

【0081】そして、全ての外部調達品目について、以
上の判定を行なったら、それぞれの注番の生産に必要と
なる外部調達品目に関して、新たな完成スケジュ−ルを
満足する実行可能な生産計画が立案されたと判定された
か否かを、受注に引き当てられている各注番について判
定し、全ての品目について、新たな完成スケジュ−ルを
満足する実行可能な生産計画が立案されたと判定されて
いれば、当該注番に対応する生産要求を満足する生産計
画が立案されたと判定し、データ記憶装置11に記憶す
る。
Then, after making the above determinations for all externally procured items, a feasible production plan satisfying the new completed schedule is drafted for the externally procured items required for the production of each order number. If it is determined that a viable production plan that satisfies the new completed schedule has been drafted for all items, it is determined whether or not it has been determined that it has been done. Then, it is determined that a production plan satisfying the production requirement corresponding to the order number has been drafted and stored in the data storage device 11.

【0082】また、それぞれの注番の生産に必要となる
いずれかの外部調達品目に関して、注番に対応する生産
要求を満足する実行可能な生産計画の立案が不可能と判
定されている場合には、当該注番に対応する生産要求を
満足する生産計画が立案不可能な場合があると判定し、
その旨、データ記憶装置11に記憶する。
When it is determined that it is not possible to formulate an executable production plan that satisfies the production requirement corresponding to the order number for any of the externally procured items required for the production of each order number. Determines that it may not be possible to make a production plan that satisfies the production requirements corresponding to the order number,
The fact is stored in the data storage device 11.

【0083】これ以外の場合は、当該注番に対応する生
産要求を満足する実行可能な生産計画が、受注に引き当
てられていない注番の生産スケジュ−ルを変更すること
により、立案可能と判定し、データ記憶装置11に、そ
の旨記憶する。
In other cases, it is determined that an executable production plan satisfying the production requirement corresponding to the order number can be planned by changing the production schedule of the order number not allocated to the order. Then, the fact is stored in the data storage device 11.

【0084】そして、生産計画判定装置101は、この
ようにして求めた、受注に引き当てられている各注番の
作業量の面と在庫の面からの判定に従い、作業量の面と
在庫の面の双方より、当該注番に対応する生産要求を満
足する実行可能な生産計画が、受注に引き当てられてい
ない注番の生産スケジュ−ルを変更することにより、立
案可能と判定されている場合は、当該注番に対応する生
産要求を満足する実行可能な生産計画が、受注に引き当
てられていない注番の生産スケジュ−ルを変更すること
により、立案可能と判定されている旨を最終判定として
データ記憶装置11に記憶し、少なくとも一方で、当該
注番に対応する生産要求を満足する生産計画が立案不可
能な場合があると判定されている場合には、当該注番に
対応する生産要求を満足する生産計画が立案不可能な場
合がある旨を最終判定としてデータ記憶装置11に記憶
し、それ以外の場合は、当該注番に対応する生産要求を
満足する実行可能な生産計画が、受注に引き当てられて
いない注番の生産スケジュ−ルを変更することにより、
立案可能である旨を最終判定としてデータ記憶装置11
に記憶する。
Then, the production plan judging apparatus 101 determines the amount of work and the amount of inventory according to the determination from the amount of work and the amount of stock of each order number allocated to the order thus obtained. If it is determined by both parties that a viable production plan that satisfies the production requirement corresponding to the order number can be planned by changing the production schedule of the order number that is not assigned to the order, The final judgment is that it is determined that a feasible production plan that satisfies the production requirements corresponding to the order number can be planned by changing the production schedule of the order number that is not assigned to the order. If it is determined that there is a case where it is impossible to make a production plan that is stored in the data storage device 11 and that satisfies the production request corresponding to the order number, at least one of the production requests corresponding to the order number is generated. It is stored in the data storage device 11 as a final judgment that a satisfying production plan may not be able to be drafted. In other cases, a viable production plan satisfying the production request corresponding to the order number is ordered. By changing the production schedule of the order number not assigned to
The data storage device 11 makes a final decision that planning is possible.
Remember.

【0085】ところで、以上説明してきたような生産計
画の生成や、生成された生産計画に問題がないかの確認
や、問題がある場合の生産計画の調整はデータ入出力装
置12が提供する物理的なユ−ザインタフェ−スを介し
て行なわれる。
By the way, the generation of the production plan as described above, the confirmation of whether there is a problem in the generated production plan, and the adjustment of the production plan when there is a problem are controlled by the physical data input / output device 12. Through a traditional user interface.

【0086】以下、このようなユ−ザインタフェ−スの
操作に対応させて、生産計画システムの、生成された生
産計画に問題がないかの確認や、問題がある場合の生産
計画の調整動作を説明する。
In the following, the operation of the user interface is checked to confirm whether or not there is a problem in the generated production plan of the production planning system, and the operation of adjusting the production plan when there is a problem. explain.

【0087】データ入出力装置12は、たとえば、ブラ
ウン管ディスプレイ装置等の表示装置と、キーボード、
マウス等の入力装置を有している。
The data input / output device 12 is, for example, a display device such as a cathode ray tube display device, a keyboard,
It has an input device such as a mouse.

【0088】まず、生産計画の生成指示を受付けるため
に、データ入出力装置12の表示装置に表示されるグラ
フィックユ−ザインタフェ−スを示す。
First, a graphic user interface displayed on the display unit of the data input / output unit 12 for receiving a production plan generation instruction will be described.

【0089】図6は、生産計画システムが起動された時
データ入出力装置12が初めに表示する初期画面であ
る。
FIG. 6 is an initial screen initially displayed by the data input / output device 12 when the production planning system is activated.

【0090】図7において、コマンドメニューのうち
「初期計画」コマンド41がマウスでピックされると、
データ入出力装置12はMRP制御装置2へMRP実行
を指示する。
In FIG. 7, when the "initial plan" command 41 in the command menu is picked with the mouse,
The data input / output device 12 instructs the MRP control device 2 to execute MRP.

【0091】そして、この指示により、前述したように
生産計画の生成が行なわれる。なお、受注システム11
00より、受け取った新たな受注情報を反映した生産計
画の生成も、「初期計画」コマンド41がマウスでピッ
クされることにより行なわれる。
Then, according to this instruction, the production plan is generated as described above. The ordering system 11
From 00, generation of a production plan that reflects the received new order information is also performed by picking the "initial plan" command 41 with the mouse.

【0092】一方、生産計画の生成後に、図7におい
て、コマンドメニューのうち「問題解析」コマンドメニ
ュー40がマウスでピックされると、図1の問題点解析
指示19が指令される。問題解析装置7は、この問題点
解析指示19を受けてデータ記憶装置11から、生成さ
れた生産計画を入力する。
On the other hand, after the production plan is generated, when the "problem analysis" command menu 40 of the command menus in FIG. 7 is picked with the mouse, the problem analysis instruction 19 of FIG. 1 is instructed. The problem analysis device 7 receives the problem analysis instruction 19 and inputs the produced production plan from the data storage device 11.

【0093】問題解析装置7は、生産計画内容をサーチ
して、その最先の工程の着手日が現在日より前(すなわ
ち、現在より前に製造開始を行なっていなければ、製品
の完成日を満足できない品目)となる品目の一覧を、注
番毎に作成し、その結果20をデータ入出力装置12へ
出力し、問題点解析結果をデータ入出力装置12の表示
装置に表示する。
The problem analysis device 7 searches the contents of the production plan, and the start date of the earliest process is before the present date (that is, if the production start is not performed before the present date, the completion date of the product is determined). A list of items that are not satisfied) is created for each order number, the result 20 is output to the data input / output device 12, and the problem analysis result is displayed on the display device of the data input / output device 12.

【0094】なお、この際、外部調達部品のうち、発注
日が現在日点より前(すなわち、現在より前に発注を行
なっていなければ、生産計画を満足できない品目)とな
る品目の一覧を作成し、その結果をも、データ入出力装
置12へ出力し表示するようにしてもよい。
At this time, among the externally procured parts, a list of items whose ordering date is before the current day point (that is, the item which cannot meet the production plan unless the order is placed before the present) is created. However, the result may be output to the data input / output device 12 and displayed.

【0095】図8に、問題点解析結果の出力画面を示
す。
FIG. 8 shows an output screen of the problem analysis result.

【0096】図8中、問題区間表示表42は、横軸に半
月単位の期間、縦軸に製品のカテゴリをとってある。
In FIG. 8, the problem section display table 42 has a horizontal axis indicating a period of a half month unit and a vertical axis indicating a product category.

【0097】縦横軸で区切られる各マトリクスは、横軸
でで表される範囲内に納期がある注番のうち、対応する
品目中に製造着手日もしくは外部調達部品の発注日が現
在より前にあるものがあって納期を守れないものがある
場合、濃色で表示される。またその際、問題発生状況を
示すための情報として、マトリクス内に含まれる件数、
数量、遅れ件数(最先の工程の着手日が現在日より前の
製品数)、最大遅れ(最先の着手日から現在までの日
数)等が表示される。
Each matrix divided by the vertical and horizontal axes has a delivery date within the range represented by the horizontal axis, and the production start date or the order date of the externally procured parts in the corresponding item is earlier than the present date. If there is something that cannot be delivered on time, it is displayed in dark color. At that time, the number of cases included in the matrix as information to show the problem occurrence status,
The quantity, the number of delays (the number of products whose start date of the earliest process is before the current date), the maximum delay (the number of days from the earliest start date to the present), etc. are displayed.

【0098】さて、計画立案者は、これら問題が発生し
ているマトリクスの詳細な情報は以下の手順により参照
することができる。
Now, the planner can refer to the detailed information of the matrix where these problems occur by the following procedure.

【0099】詳細情報参照マトリクスの決定 マウスによって詳細情報を参照しようとするマトリクス
をピックする。図8は、「期間 : 3月/上、カテゴ
リ : 2」のマトリクス部分がピックされていること
を示している。
Determination of Detailed Information Reference Matrix Pick a matrix for which detailed information is to be referred with the mouse. FIG. 8 shows that the matrix part of “period: March / upper, category: 2” is picked.

【0100】在庫不足/着手遅れ注文一覧の表示 コマンドメニューのうち「注文一覧」メニュー44をピ
ックする。「注文一覧」メニューをピックすることによ
り詳細情報として、着手遅れ注文一覧表43が表示され
る。着手遅れ注文一覧表43には、在庫不足(使用する
外部調達部品の発注日が現在より前である状態)もしく
は着手遅れ(製造着手日が現在より前である状態)を発
生している注番、その注番の製品に関して在庫不足、着
手遅れを発生している品目数(関係件数)、納期およ
び、遅れ/余裕が表示される(遅れ/余裕の詳細につい
ては後述する)。
Insufficient inventory / Launch start Order list display Pick the "Order list" menu 44 from the command menu. By picking the "order list" menu, the start-delay order list 43 is displayed as detailed information. In the delayed start table 43, there is a stock shortage (the order date of the externally procured parts to be used is before the present date) or the start delay (the production start date is before the present date). For the product of the order number, the inventory shortage, the number of items that are delayed in the start (number of related items), the delivery date, and the delay / margin are displayed (details of the delay / margin will be described later).

【0101】一方、図8において詳細情報参照マトリク
スを決定後、コマンドメニューのうち「選択」メニュー
45をピックすると、図9に示す注番/日付別問題発生
箇所表示表46が表示される。
On the other hand, when the "select" menu 45 of the command menu is picked after the detailed information reference matrix is determined in FIG. 8, the order number / date problem occurrence point display table 46 shown in FIG. 9 is displayed.

【0102】図9中、注番/日付別問題発生箇所表示表
46は、横軸に日付、縦軸に注番をとってある。
In FIG. 9, the note number / date-specific problem occurrence point display table 46 has the horizontal axis indicating the date and the vertical axis indicating the note number.

【0103】また、表示されている期間は図8に示した
「期間 : 3月/上、カテゴリ:2の範囲」に対応し
ている。
The displayed period corresponds to "period: March / upper, category: range of 2" shown in FIG.

【0104】注番/日付別問題発生問題発生箇所表示表
46で、濃色のマトリックス部分が問題発生箇所を示し
ており、発生問題状況を示すための情報として、最大遅
れとその注番の製品に関して着手遅れ、在庫不足を発生
している品目数が表示されている。
Problem occurrence by note number / date In the problem occurrence point display table 46, the dark matrix portion indicates the problem occurrence point. As information for indicating the occurrence problem situation, the maximum delay and the product of the order number Regarding the item, the number of items for which the start of work has been delayed and there is a shortage of inventory is displayed.

【0105】ここで、さらに、注番/日付別問題発生箇
所表示表46において問題が発生しているマトリクスの
詳細情報は以下の手順により参照することができる。
Here, the detailed information of the matrix in which the problem occurs in the note number / date-specific problem occurrence point display table 46 can be referred to by the following procedure.

【0106】詳細情報参照マトリクスの決定 マウスによって詳細情報を参照しようとするマトリクス
をピックする。図6には、「期間:3/4、注番:10
03」マトリクスがピックされていることを示してい
る。
Determination of Detailed Information Reference Matrix A matrix for which detailed information is to be referred is picked up by the mouse. In Figure 6, "Period: 3/4, note number: 10
The "03" matrix has been picked.

【0107】詳細情報指示 コマンドメニューのうち「詳細」メニュー48をピック
する。「詳細」メニューをピックすることにより詳細情
報一覧表47が表示される。詳細情報一覧表47には、
指定された注番の製品名、型式、数量、着手遅れ日数
(製造着手日より現在までの日数)等が表示される。
Detailed Information Instruction Pick the “Details” menu 48 from the command menu. A detailed information list 47 is displayed by picking the “details” menu. In the detailed information list 47,
The product name, model, quantity, number of days behind the start (number of days from the start of manufacturing to the present), etc. of the specified order number are displayed.

【0108】着手遅れ品目一覧表示 の「詳細」メニュー48の代わりに「品目一覧」メニ
ュー49をピックすることにより図7に示す着手遅れ品
目一覧表画面50に、指定された注番の製品に関して着
手遅れを発生している全品目の着手遅れ日数、数量等が
表示される。
By picking up the “item list” menu 49 instead of the “details” menu 48 for displaying the list of delayed items, the item list screen 50 shown in FIG. Displays the number of days late, the quantity, etc. of all the items that are late.

【0109】さて、以上の問題点解析装置7による問題
点のデータ入出力装置12への表示より、生産計画の問
題点が確認された場合、計画立案者は、生産計画を調整
しなければならない。
When the problem of the production plan is confirmed from the display of the problem point on the data input / output device 12 by the problem point analysis device 7 described above, the planner must adjust the production plan. .

【0110】生産計画の調整は、図11に示す表示上で
行なうことができる。
The production plan can be adjusted on the display shown in FIG.

【0111】図11は、問題経路表示部53、生産能力
表示部54、完成日変更メニュー55、代替ショップメ
ニュー56、能力調整メニュー57、MRP実行指示メ
ニュー58、作業着手手順序変更メニュ−150、生産
量調整メニュ−151、計画削除メニュ−156、調整
実行メニュ−157、対策プロポ−サルメニュ−93、
生産能力変更開始時点設定ダイアル59、生産能力変更
終了時点設定ダイアル60、生産能力設定ダイアル61
等から構成される。
FIG. 11 shows the problem route display section 53, the production capacity display section 54, the completion date change menu 55, the alternative shop menu 56, the capacity adjustment menu 57, the MRP execution instruction menu 58, the work start order change menu 150, Production adjustment menu-151, plan deletion menu-156, adjustment execution menu-157, countermeasure proposal menu-93,
Production capacity change start time setting dial 59, production capacity change end time setting dial 60, production capacity setting dial 61
Etc.

【0112】図11の表示は、以下の手順により呼び出
され、この呼び出された表示中の問題経路表示部53
は、問題経路を表示する。経路とは、品目の製造工程を
ショップとリ−ドタイムとの関連で示したものをいう。
問題経路とは、着手遅れを発生している品目のうち対策
品目として選択された品目の経路である。
The display of FIG. 11 is called by the following procedure, and the called problem route display portion 53 being displayed.
Displays the problem route. The route indicates the manufacturing process of the item in relation to the shop and the lead time.
The problem route is the route of the item selected as the countermeasure item among the items for which the start delay has occurred.

【0113】対策品目の選択 生産計画の調整を行なう上において、その対象となる品
目(在庫不足、着手遅れを発生している品目)を選択す
る。たとえば、図10の在庫不足/着手遅れ品目一覧表
50において「仕切り板」をマウスでピックした後、
「終了」ボタン52をマウスでピックすることにより対
象となる品目として「仕切り板」が選択される。
Selection of Countermeasure Item In adjusting the production plan, the target item (item in which inventory shortage, start delay has occurred) is selected. For example, in the inventory shortage / delayed item list 50 in FIG.
By picking the "end" button 52 with the mouse, the "partition plate" is selected as the target item.

【0114】生産計画調整指示 図8の出力画面のコマンドメニューのうち「調整」メニ
ュー51をピックする。
Production Plan Adjustment Instruction Pick the “adjustment” menu 51 from the command menu on the output screen of FIG.

【0115】問題点解析 これにより、データ入出力装置12から問題点解析指示
19が指令される。問題点解析装置7は、この問題点解
析指示19を受けてデータ記憶装置11から生産計画2
1を入力する。
Problem Analysis As a result, the data input / output device 12 issues a problem analysis instruction 19. The problem analysis device 7 receives the problem analysis instruction 19 and outputs the production plan 2 from the data storage device 11.
Enter 1.

【0116】また、問題解析装置7は、で選択された
対策品目を製造するために用いられる各ショップとその
負荷状況を求め、その結果20をデータ入出力装置へ出
力する。
Further, the problem analysis device 7 obtains each shop used for manufacturing the countermeasure item selected in and its load condition, and outputs the result 20 to the data input / output device.

【0117】問題経路表示 データ入出力装置12は、問題点解析結果20を問題経
路表示部53に所定のフォーマットで表示する。
Problem Route Display The data input / output device 12 displays the problem analysis result 20 on the problem route display section 53 in a predetermined format.

【0118】なお、この問題経路表示部53の表示フォ
−マットは以下のような特徴をもつ。
The display format of the problem route display section 53 has the following features.

【0119】対策品目の経路に関係するショップにつ
いてのみ表示する。
Only the shops related to the route of the countermeasure item are displayed.

【0120】各ショップの各期間の負荷状況(作業量
/生産能力)を、その大小によって色分け表示する。
The load status (work volume / production capacity) of each shop for each period is displayed in different colors according to its size.

【0121】各ショップの各期間の負荷状況の表示の
上に重ねて対策対象品目の経路を示す。図11中、太線
枠80で示したのが問題経路であり、順次ショップ9、
7、3、2、1により当該品目が製造されることを示し
ている。また、1つの太枠矩形は、一つのショプにおけ
る工程を示し、その横軸方向が、その工程のリ−ドタイ
ムを示す。
The route of the countermeasure target item is shown on the display of the load status of each shop for each period. In FIG. 11, the problem route is shown by a bold line frame 80, and the shop 9
7,3,2,1 indicates that the item is manufactured. Further, one thick frame rectangle indicates a process in one shop, and the horizontal axis direction indicates the lead time of the process.

【0122】問題経路表示部53をこのように構成する
ことにより、生産計画者は、問題経路が理解しやすくな
ると同時に、作業料の面の問題に関しては、混み具合の
大きな所から対策を打つといったような意思決定を容易
に行なうことが可能になる。
By configuring the problem route display section 53 in this way, the production planner can easily understand the problem route, and at the same time, regarding the problem of the work fee, the measure is taken from the place where the congestion degree is large. It becomes possible to easily make such a decision.

【0123】さて、この状態で、「対策プロポ−サル」
メニュ−93がピックされると、データ記憶装置11
に、対策品目を用いる注番について、最終判定として、
受注に引き当てられていない注番の生産スケジュ−ルを
変更することにより、立案可能な旨が記憶されている場
合には、領域95に、その旨表示する。また、この際、
図11に示すように、この注番について、データ記憶装
置11にスケジュ−ル変更対象注番として記憶されてい
る注番についての情報も合わせて表示するようにしても
よい。また、作業量、在庫量の面のいずれが問題である
かを合わせて表示するようにする。
Now, in this state, "countermeasure proposal"
When the menu 93 is picked up, the data storage device 11
For the order number using countermeasure items, as the final judgment,
If the fact that a plan can be planned is stored by changing the production schedule of the order number that has not been assigned to the order, that effect is displayed in the area 95. Also, at this time,
As shown in FIG. 11, information about the order number stored in the data storage device 11 as the schedule change target order number may be displayed together with this order number. In addition, whether the amount of work or the amount of inventory is a problem is displayed together.

【0124】また、最終判定として、注番に対応する生
産要求を満足する生産計画が立案不可能な場合がある旨
が記憶されている場合には、その旨を表示するようにす
る。
If it is stored as the final determination that there is a case where a production plan satisfying the production request corresponding to the order number cannot be drafted, that fact is displayed.

【0125】また、この場合も、作業量、在庫量の面の
いずれが問題であるかを合わせて表示するようにする。
Also in this case, which of the work amount and the stock amount is the problem is also displayed.

【0126】なお、前述したMRP展開装置8、作業料
解析装置27、生産計画実行判定装置101により行な
われる作業量、在庫量の面からの生産計画の判定は、生
産計画の生成の際に行なわずに、この対策プロポ−サル
メニュ−93がピックされた際にデータ記憶装置11に
記憶された詳細な生産計画に基づいて行なうようにして
もよい。
The determination of the production plan from the aspects of the amount of work and the amount of inventory performed by the MRP expansion device 8, the work charge analysis device 27, and the production plan execution determination device 101 described above is performed when the production plan is generated. Instead, it may be performed based on the detailed production plan stored in the data storage device 11 when the countermeasure proposal menu 93 is picked up.

【0127】これにより、生産計画立案者は、対策品目
についての対策の指針を得ることができたので、この指
針に基づいて対策を決定し、生産計画の調整を行なう。
As a result, the production planner can obtain the guideline for the countermeasure for the countermeasure item, so the countermeasure is decided based on the guideline and the production plan is adjusted.

【0128】さて、生産計画の調整は、完成日変更メニ
ュー55、代替ショップメニュー56、能力調整メニュ
ー57、MRP実行指示メニュー58、作業着手手順序
変更メニュ−150、生産量調整メニュ−151、計画
削除メニュ−156を用いて行なう。
Now, the adjustment of the production plan is carried out by the completion date change menu 55, the alternative shop menu 56, the capacity adjustment menu 57, the MRP execution instruction menu 58, the work start order change menu 150, the production amount adjustment menu 151, and the plan. Use Delete Menu-156.

【0129】まず、生産計画立案者が対策としてショッ
プの能力の変更を行なうことを決定した場合には、以下
の手順により、生産計画の調整を行なう。
First, when the production planner decides to change the capacity of the shop as a countermeasure, the production plan is adjusted by the following procedure.

【0130】生産能力変更工程の選択 問題経路表示部53の中の問題経路中で生産能力を変更
しようとする工程をマウスでピックした後に、能力調整
メニュー57をピックする。たとえば図11のshop
3の太線で囲まれた部分をマウスでピックする。
Selection of production capacity changing step After the step of changing the production capacity in the problem route in the problem route display portion 53 is picked with the mouse, the capacity adjustment menu 57 is picked. For example, shop in FIG.
Pick the part surrounded by the thick line in 3 with the mouse.

【0131】生産能力表示部54の表示 これに従いデータ入出力装置12は、図12に示すよう
に、上記で選択された工程の負荷状況、生産能力を生
産能力表示部54に示すフォーマットで表示する。生産
能力表示部54は、負荷状況62、生産能力線63、生
産能力変更開始点64、生産能力変更開終了点65、生
産能力変更対象区間枠66から構成される。
Display on the production capacity display section 54 Accordingly, the data input / output device 12 displays the load status and the production capacity of the process selected above in the format shown on the production capacity display section 54, as shown in FIG. . The production capacity display unit 54 includes a load status 62, a production capacity line 63, a production capacity change start point 64, a production capacity change open / close point 65, and a production capacity change target section frame 66.

【0132】生産能力変更開始/終了点の設定 生産能力変更開始時点設定ダイアル59、生産能力変更
開終了時点設定ダイアル60をマウスでピックすること
により生産能力変更開始点64、生産能力変更終了点6
5を左右に移動する。マウスでのピックにおいては、た
とえば2ボタン式のマウスの場合は、マウスの左ボタン
をピックした場合は生産能力変更開始/終了点を左へ、
右ボタンをピックした場合は右へ移動する。
Setting of production capacity change start / end point Production capacity change start point 64, production capacity change start point 6 and production capacity change end point 6 by picking the production capacity change start time setting dial 59 and the production capacity change end point setting dial 60 with the mouse.
Move 5 left and right. In the case of picking with a mouse, for example, in the case of a two-button mouse, when the left mouse button is picked, the production capacity change start / end point is moved to the left,
If you pick the right button, move to the right.

【0133】生産能力変更 生産能力設定ダイアル61をマウスでピックすることに
より、生産能力変更開始点64と生産能力変更開終了点
65の間の区間の生産能力を変更する。マウスでのピッ
クにおいては、例えば2ボタン式のマウスの場合は、マ
ウスの左ボタンをピックした場合は生産能力線63を下
(生産能力減少)へ、右ボタンをピックした場合は上
(生産能力増加)へ移動する。
Production Capacity Change By picking the production capacity setting dial 61 with the mouse, the production capacity in the section between the production capacity change start point 64 and the production capacity change opening end point 65 is changed. In the case of picking with a mouse, for example, in the case of a two-button type mouse, if the left mouse button is picked, the production capacity line 63 is moved downward (production capacity is decreased), and if the right button is picked, production capacity is increased (production capacity). Increase).

【0134】リードタイム変更/MRP計算実行 この後、調整実行メニュ−157がピックされたら、デ
ータ入出力装置12は、の生産能力変更結果に基づき
生産能力調整指示15を生産能力調整装置4へ出す。生
産能力調整装置4は、生産能力調整結果とMRP実行指
示22をMRP制御装置2へ送る。MRP制御装置2
は、生産能力調整結果に基づき、MRP展開装置と協調
して、選択された工程を含む問題経路により製造される
注番についての生産計画のみを生成しなおす。すなわ
ち、これ以外の注番に関する生産計画を前提条件として
生産計画のみを計算しなおし、生産計画を修正する。修
正された生産計画は、データ記憶装置11へ記憶され
る。ただし、生産能力調整結果を踏まえて、全ての注番
の生産計画を生成しなおすようにしてもよい。なお、こ
の生産計画の修正もしくは生成の際には、MRP展開装
置8、作業量解析装置27、生産計画事項判定装置10
1は、再度、前述した作業量、在庫量の面からの判定を
行ない、データ記憶装置11の判定の内容を更新する。
After changing lead time / execution of MRP calculation, when the adjustment execution menu-157 is picked, the data input / output device 12 issues the production capacity adjustment instruction 15 to the production capacity adjusting device 4 based on the result of the production capacity change. . The production capacity adjustment device 4 sends the production capacity adjustment result and the MRP execution instruction 22 to the MRP control device 2. MRP controller 2
Regenerates only the production plan for the order number manufactured by the problem route including the selected process based on the production capacity adjustment result in cooperation with the MRP expansion device. That is, only the production plan is recalculated on the basis of the production plans related to the other order numbers, and the production plan is corrected. The modified production plan is stored in the data storage device 11. However, the production plans of all the order numbers may be regenerated based on the production capacity adjustment result. When modifying or generating this production plan, the MRP expansion device 8, the work amount analysis device 27, the production plan item determination device 10
1 again performs the above-described determination of the work amount and the inventory amount, and updates the determination content of the data storage device 11.

【0135】問題経路表示部変更 データ入出力装置12は、データ記憶層と11からMR
P実行結果21を入力し、対策対象品目に関係する生産
計画を修正表示する。
Changing the problem route display section The data input / output device 12 includes the data storage layer 11 and the MR.
The P execution result 21 is input and the production plan related to the countermeasure target item is corrected and displayed.

【0136】〜ににより、生産計画者は、簡単な操
作で生産能力を変更できると同時に、生産能力の変更が
生産計画にどのような影響を余ぼすかをオンラインで確
認することが可能になる。
With the above, the production planner can change the production capacity by a simple operation, and at the same time, it is possible to confirm online how the change of the production capacity will affect the production plan. .

【0137】ところで、図12の生産能力表示部54の
表示は、図13のように構成してもよい。
By the way, the display of the production capacity display section 54 of FIG. 12 may be configured as shown in FIG.

【0138】図13のリードタイム表示部90と能力増
加ボタン91及び能力減少ボタン92を設けたことであ
る。この場合、前記の操作が異なるのでこれについ
て説明する。
The lead time display section 90, the capacity increase button 91 and the capacity decrease button 92 of FIG. 13 are provided. In this case, the above-mentioned operation is different, which will be described.

【0139】’生産能力変更開始/終了点の設定 負荷状況62の棒グラフをマウスの左ボタンでピックす
ることによりその日付に生産能力変更開始点64を、マ
ウスの右ボタンでピックすることによりその日付に生産
能力変更終了点65を設定する。
[Setting of production capacity change start / end point] By picking the bar graph of the load status 62 with the left mouse button, the date is selected by picking the production capacity change start point 64 with the right mouse button. The production capacity change end point 65 is set to.

【0140】’生産能力変更 能力増加ボタン91及び能力減少ボタン92をマウスで
ピックすることにより、生産能力変更開始点64と生産
能力変更開終了点65の間の区間の生産能力を変更す
る。
[Production Capacity Change] The production capacity in the section between the production capacity change start point 64 and the production capacity change end point 65 is changed by picking the capacity increase button 91 and the capacity decrease button 92 with the mouse.

【0141】次に、生産計画立案者が対策としてショッ
プの能力の変更を行なことを決定した場合には、以下の
手順により、生産計画の調整を行なう。
Next, when the production planner decides to change the capacity of the shop as a countermeasure, the production plan is adjusted by the following procedure.

【0142】図14に製品完成日変更用画面を示す。図
14の表示画面は、図11の完成日変更モード切り替え
メニュー55をマウスでピックすることにより呼びださ
れる。
FIG. 14 shows a screen for changing the product completion date. The display screen of FIG. 14 is called by picking the completion date change mode switching menu 55 of FIG. 11 with the mouse.

【0143】さて、この製品完成日変更用画面におい
て、遅れ/余裕表示部68は、注番表示75、余裕表示
76、遅れ表示78および、遅れ/余裕棒グラフ79に
より構成される。
On the screen for changing the product completion date, the delay / margin display section 68 is composed of a note number display 75, a margin display 76, a delay display 78, and a delay / margin bar graph 79.

【0144】遅れ/余裕棒グラフ79において、「現
在」と「着手」の間の黒色の部分が着手遅れ日数を、
「完成」と「納期」の間の白色の部分が、余裕日数を表
している。ここで、「納期」は顧客に回答した納期であ
り、「完成」は生産計画上の製品完成予定日である。前
述したように、生産計画を作成する場合、顧客納期にあ
る程度の余裕をもたせて製品完成予定日を設定するのが
一般的である。
In the delay / margin bar graph 79, the black portion between “current” and “start” indicates the number of days behind start,
The white part between "completion" and "delivery date" represents the number of spare days. Here, the "delivery date" is the delivery date answered by the customer, and the "completion" is the scheduled product completion date in the production plan. As described above, when a production plan is created, it is common to set a scheduled product completion date with a certain amount of customer delivery time.

【0145】したがい、今着手遅れを発生している製品
に対しては、この完成予定日を納期に近付けることによ
り、着手遅れを解消できる可能性がある。
Therefore, for a product which has a delay in starting work, it may be possible to eliminate the delay in starting work by bringing the scheduled completion date closer to the delivery date.

【0146】製品完成日の変更は、以下の手順により実
行される。
The change of the product completion date is executed by the following procedure.

【0147】完成日変更注番の選択 問題経路が複数個表示されている場合、どの注番の製品
を対象に完成日を変更するかを選択する。注番の選択の
ためには、注番変更ダイアル73をマウスでピックす
る。マウスでのピックにおいては、例えば2ボタン式の
マウスの場合は、マウスの左ボタンをピックした場合は
注番を増加し、右ボタンをピックした場合は注番を減少
する。図14においては問題経路が一つしか表示されて
いないので注番1003が完成日変更の対象となる。
Selection of completion date change order number When a plurality of problem routes are displayed, it is selected which order number product is to be changed in completion date. To select a note number, pick the note number change dial 73 with the mouse. In picking with a mouse, for example, in the case of a two-button mouse, when the left button of the mouse is picked, the note number is increased, and when the right button is picked, the note number is decreased. In FIG. 14, since only one problem route is displayed, the order number 1003 is the target for changing the completion date.

【0148】完成日変更 完成日変更ダイアル74をマウスでピックすることによ
り完成日を変更する。たとえば、2ボタン式のマウスの
場合は、マウスの左ボタンをピックした場合は完成日を
早く(「完成」表示を左へ動かす)し、右ボタンをピッ
クした場合は完成日を遅く(「完成」表示を右へ動か
す)する。
Change completion date Change the completion date by picking the change completion date dial 74 with the mouse. For example, in the case of a two-button mouse, if you pick the left button of the mouse, the completion date will be earlier (move the "Completion" display to the left), and if you select the right button, the completion date will be later ("Completion date". Move the display to the right).

【0149】なお、遅れ/余裕棒グラフ79をマウスで
ピックしたまま左右に動かす(ドラッグする)ことによ
って、完成日を変更するようにしてもよい。
The completion date may be changed by moving (dragging) the delay / margin bar graph 79 left and right while picking it up with the mouse.

【0150】MRP計算実行 調整実行メニュ−157がピックされると、データ入出
力装置12は、の完成日変更結果に基づき完成日調整
指示を完成日調整装置5へ指令する。完成日調整装置5
は、完成日調整結果とMRP実行指示23をMRP制御
装置2に指令する。MRP制御装置2は、完成日調整結
果に基づき、MRP展開装置と協調して、選択された工
程を含む問題経路により製造される注番の生産計画のみ
を生成しなおす。すなわち、これ以外の注番に関する生
産計画を前提条件として、選択された注番についての生
産計画のみを計算しなおし、生産計画を修正する。修正
された生産計画は、データ記憶装置11へ記憶される。
ただし、完成日調整結果に基づき完成スケジュ−ルを変
更し、全ての注番についての生産計画を生成しなおすよ
うにしてもよい。なお、この生産計画の修正もしくは生
成の際には、MRP展開装置8、作業量解析装置27、
生産計画事項判定装置101は、再度、前述した作業
量、在庫量の面からの判定を行ない、データ記憶装置1
1の判定の内容を更新する。
MRP Calculation Execution When the adjustment execution menu-157 is picked up, the data input / output device 12 issues a completion date adjustment instruction to the completion date adjustment device 5 based on the completion date change result. Completion date adjustment device 5
Gives the completion date adjustment result and the MRP execution instruction 23 to the MRP control device 2. Based on the completion date adjustment result, the MRP control device 2 cooperates with the MRP development device to regenerate only the production plan of the order number manufactured by the problem route including the selected process. That is, with the production plans for other order numbers as a precondition, only the production plans for the selected order numbers are recalculated and the production plan is revised. The modified production plan is stored in the data storage device 11.
However, the completion schedule may be changed based on the completion date adjustment result, and the production plans for all the order numbers may be regenerated. When modifying or generating this production plan, the MRP expansion device 8, the work amount analysis device 27,
The production plan item determination device 101 again performs the determination in terms of the work amount and the inventory amount described above, and the data storage device 1
The contents of the judgment of 1 are updated.

【0151】問題経路/遅れ/余裕表示部変更 データ入出力装置12は、データ記憶装置11から新た
な生産計画を入力し、問題経路/遅れ/余裕表示部を修
正表示する。
Change of problem route / delay / margin display unit The data input / output device 12 inputs a new production plan from the data storage device 11 and corrects and displays the problem route / delay / margin display unit.

【0152】以上〜ににより、生産計画者は、簡単
な操作で完成日を変更できると同時に、製品完成日の変
更が生産計画にどのような影響を及ぼすかをオンライン
で確認することが可能になる。
As described above, the production planner can change the completion date with a simple operation, and at the same time, can confirm online how the change of the product completion date affects the production plan. Become.

【0153】次に、生産計画立案者が対策としてショッ
プの変更を行なことを決定した場合には、以下の手順に
より、生産計画の調整を行なう。
Next, when the production planner decides to change the shop as a countermeasure, the production plan is adjusted by the following procedure.

【0154】図15に生産ショップ変更用画面を示す。
図15に示す生産ショップ変更用画面は、図11の代替
ショップモード切り替えメニュー56がピックされた場
合に呼びだされる。
FIG. 15 shows a screen for changing the production shop.
The production shop change screen shown in FIG. 15 is called when the alternative shop mode switching menu 56 of FIG. 11 is picked.

【0155】図中の、代替ショップ表示部81には、問
題経路のうちの任意の工程を選択した際に、その工程と
同等の作業を実行しうる代替ショップ群と、各代替ショ
ップにおけるリードタイムおよび、各代替ショップを採
用した際の改善日数すなわちリードタイム短縮日数が表
示される。
In the alternative shop display portion 81 in the figure, when an arbitrary process in the problem route is selected, a group of alternative shops which can execute the work equivalent to the process and the lead time in each alternative shop. In addition, the number of days for improvement when adopting each alternative shop, that is, the number of days for shortening lead time is displayed.

【0156】すなわち、問題経路のうちの任意の工程に
代替ショップが存在する場合、代替ショップを採用する
ことにより着手遅れを解消できる可能性がある。
That is, when an alternative shop exists in an arbitrary process of the problem route, there is a possibility that the delay in starting work can be resolved by adopting the alternative shop.

【0157】生産ショップを変更しながらの生産計画調
整は以下の手順により実行される。
The production plan adjustment while changing the production shop is executed by the following procedure.

【0158】生産ショップ変更工程の選択 問題経路表示部80の中で、生産ショップを変更しよう
とする工程をマウスでピックする。たとえば、図15の
shop3の太線で囲まれた部分をマウスでピックす
る。代替ショップが存在する場合、代替ショップ表示部
81が表示される。
Selection of production shop change process In the problem route display portion 80, a process for changing the production shop is picked with the mouse. For example, the portion surrounded by the thick line of shop3 in FIG. 15 is picked with the mouse. When there is an alternative shop, the alternative shop display section 81 is displayed.

【0159】また、問題経路表示部53にも代替ショッ
プが図15に示すようなフォーマットで表示される。
Further, the alternative shop is displayed in the problem route display portion 53 in the format as shown in FIG.

【0160】代替ショップ選択 代替ショップ表示部81の各ショップ名をマウスでピッ
クすることにより代替ショップを選択する。
Alternative shop selection The alternative shop is selected by picking each shop name in the alternative shop display area 81 with the mouse.

【0161】MRP計算実行 調整実行メニュ−157がピックされると、データ入出
力装置12が、の代替ショップ選択結果に基づき代替
ショップ調整指示17を代替ショップ調整装置6へ指令
する。代替ショップ調整装置6は、MRP制御装置2へ
代替ショップ調整結果とMRP実行指示24を出力す
る。MRP制御装置2は、代替ショップ調整結果に基づ
き、MRP展開装置と協調して、選択された工程を含む
問題経路により製造される注番についての生産計画のみ
を生成しなおす。すなわち、これ以外の注番に関する生
産計画を前提条件として対策品目についての生産計画の
みを計算しなおし、生産計画を修正する。修正された生
産計画は、データ記憶装置11へ記憶される。ただし、
代替ショップ調整結果を踏まえて、全ての注番の生産計
画を生成しなおすようにしてもよい。なお、この生産計
画の修正もしくは生成の際には、MRP展開装置8、作
業量解析装置27、生産計画事項判定装置101は、再
度、前述した作業量、在庫量の面からの判定を行ない、
データ記憶装置11の判定の内容を更新する。
MRP Calculation Execution When the adjustment execution menu-157 is picked, the data input / output device 12 issues an alternative shop adjustment instruction 17 to the alternative shop adjustment device 6 based on the alternative shop selection result. The alternative shop adjustment device 6 outputs the alternative shop adjustment result and the MRP execution instruction 24 to the MRP control device 2. Based on the alternative shop adjustment result, the MRP control device 2 cooperates with the MRP expansion device to regenerate only the production plan for the order number manufactured by the problem route including the selected process. That is, only the production plans for the countermeasure items are recalculated with the production plans for the other order numbers as a precondition, and the production plans are corrected. The modified production plan is stored in the data storage device 11. However,
The production plans of all the order numbers may be regenerated based on the alternative shop adjustment result. When the production plan is modified or generated, the MRP expansion device 8, the work amount analysis device 27, and the production plan item determination device 101 again perform the determination in terms of the work amount and the stock amount,
The contents of the judgment of the data storage device 11 are updated.

【0162】問題経路表示部変更 データ入出力装置12は、データ記憶装置11からMR
P実行結果21を入力し、代替ショップ採用後の問題経
路を修正表示する。
Change the problem route display section. The data input / output device 12 changes from the data storage device 11 to the MR.
The P execution result 21 is input, and the problem route after the alternative shop is adopted is corrected and displayed.

【0163】以上〜により、生産計画者は簡単な操
作で生産ショップを変更できると同時に、生産ショップ
の変更が生産計画にどのような影響を及ぼすかをオンラ
インで確認することが可能になる。
As described above, the production planner can change the production shop by a simple operation, and at the same time, can confirm online how the change of the production shop affects the production plan.

【0164】次に、生産計画立案者が対策として作業着
手順序の能力の変更を行なことを決定した場合には、以
下の手順により、生産計画の調整を行なう。
Next, when the production planner decides to change the capacity of the work start sequence as a countermeasure, the production plan is adjusted by the following procedure.

【0165】図16に作業着手順序変更用画面を示す。
作業着手順序変更用画面は、図11において、作業着手
手順変更メニュ−150がピックされた場合に呼びださ
れる。
FIG. 16 shows a screen for changing the work start order.
The work start order change screen is called when the work start procedure change menu 150 is picked in FIG.

【0166】図16中の着手順序変更表示部167に
は、問題経路のうちの任意の工程を選択した際に、その
工程と、その工程を含む期間内に作業すべき工程とに対
応する注番の作業着手順序、その注番の完成日日、更に
着手順序の設定を入力する項目が表示される。
The start order change display portion 167 shown in FIG. 16 indicates the process corresponding to the process and the process to be performed within the period including the process when an arbitrary process in the problem route is selected. The items for inputting the work start order of the number, the completion date of the order number, and the setting of the start order are displayed.

【0167】作業着手順序を変更しながらの生産計画調
整は以下の手順により実行される。
Production plan adjustment while changing the work start order is executed by the following procedure.

【0168】作業着手変更注番の選択 問題経路表示部53の中で、作業着手順序を変更しよう
とする工程をマウスでピックする。たとえば、shop
3の太線で囲まれた部分をマウスでピックする。その結
果、着手順序変更表示部167に示すフォ−マットで、
選択された工程を発生させている注番と、その工程を含
む期間内に作業すべき工程を発生させている注番の作業
着手順序、その注番の完成日日、更に着手順序の設定を
入力する項目が表示される。
Selection of work start change order number In the problem route display portion 53, a process for changing the work start order is picked with the mouse. For example, shop
Pick the part surrounded by the thick line in 3 with the mouse. As a result, in the format shown in the start order change display section 167,
Set the work order of the order number that generated the selected process, the work number that generated the process that should be performed within the period including the process, the completion date of the order, and the start sequence. Items to enter are displayed.

【0169】作業着手順序変更 着手順序変更表示部167に表示される製品の注番群の
中から着手順序を変更する注番に対し変更したい前後の
着手順序を変更順序入力項目へ入力する。たとえば、図
13では着手順序3の注番1005を着手順序2にする
ために、順序入力項目に着手順序2を入力する。
Change work start order The start order before and after the order for which the order is changed from the order number group of the products displayed on the change order display area 167 is input to the change order input item. For example, in FIG. 13, in order to set the order number 1005 of the starting order 3 to the starting order 2, the starting order 2 is input to the order input item.

【0170】MRP計算実行 データ入出力装置12が、の作業着手順序変更結果に
基づき、作業着手順序調整指示31を作業着手順序調整
装置33へ指令する。作業着手順序調整装置31は、M
RP制御装置2へ作業着手順序調整結果とMRP実行指
示23を指令する。MRP制御装置2は、作業着手順序
調整結果を満足するように、MRP制御装置2は、作業
着手順序調整結果に基づき、MRP展開装置と協調し
て、作業着手順序が変更された注番についての生産計画
のみを生成しなおす。すなわち、これ以外の注番に関す
る生産計画を前提条件として対策品目についての生産計
画のみを計算しなおし、生産計画を修正する。修正され
た生産計画は、データ記憶装置11へ記憶される。な
お、この生産計画の修正の際には、MRP展開装置8、
作業量解析装置27、生産計画事項判定装置101は、
再度、前述した作業量、在庫量の面からの判定を行な
い、データ記憶装置11の判定の内容を更新する。
MRP calculation execution The data input / output device 12 issues a work start order adjustment instruction 31 to the work start order adjustment device 33 based on the work start order change result. The work start order adjustment device 31 is M
The RP control device 2 is instructed of the work start order adjustment result and the MRP execution instruction 23. The MRP control device 2 cooperates with the MRP expanding device based on the work start sequence adjustment result so that the MRP control device 2 satisfies the work start sequence adjustment result. Regenerate only the production plan. That is, only the production plans for the countermeasure items are recalculated with the production plans for the other order numbers as a precondition, and the production plans are corrected. The modified production plan is stored in the data storage device 11. When modifying this production plan, the MRP expansion device 8,
The work amount analysis device 27 and the production plan item determination device 101 are
The determination of the work amount and the inventory amount described above is performed again, and the determination content of the data storage device 11 is updated.

【0171】問題経路表示部変更 データ入出力装置12は、データ記憶装置11から、生
成された新たな生産計画を入力し、問題経路表示部16
6を修正表示する。
Change of problem route display unit The data input / output device 12 inputs the new production plan generated from the data storage device 11, and the problem route display unit 16
6 is corrected and displayed.

【0172】以上〜ににより、納期回答担当者は、
簡単な操作で作業着手順序を変更できると同時に、作業
着手順序の変更が生産計画にどのような影響を及ぼすか
をオンラインで確認することが可能になる。
As a result of the above,
It is possible to change the work start sequence with a simple operation, and at the same time, it is possible to confirm online how the change of the work start sequence affects the production plan.

【0173】次に、生産計画立案者が対策として生産数
量の変更を行なうことを決定した場合には、以下の手順
により、生産計画の調整を行なう。
Next, when the production planner decides to change the production quantity as a countermeasure, the production plan is adjusted by the following procedure.

【0174】図17に生産量変更用画面を示す。図17
の表示画面は、図11の生産量調整メニュー151をマ
ウスでピックすることにより呼びだされる。
FIG. 17 shows a screen for changing the production amount. FIG. 17
This display screen is called by picking the production amount adjustment menu 151 of FIG. 11 with the mouse.

【0175】図17中に、生産量調整表示部177に
は、問題経路のうちの任意の工程を選択した際に、その
工程を発生させた注番、その完成日と生産量、余裕と遅
れが表示される。
In FIG. 17, when the production process adjustment display unit 177 selects an arbitrary process in the problem route, the order number that generated the process, the completion date and the production amount, the margin and the delay. Is displayed.

【0176】生産量を変更しながらの生産計画調整は以
下の手順により実行される。
The production plan adjustment while changing the production amount is executed by the following procedure.

【0177】生産量調整工程の選択 問題経路表示部53の中で、生産量を変更しようとする
工程をマウスでピックする。たとえば、図17のsho
p3の太線で囲まれた部分をマウスでピックする。その
結果、生産量変更表示部177に示すフォ−マットで、
その工程を発生させた注番、その完成日と生産量、余裕
と遅れが表示される。
Selection of production amount adjustment process In the problem route display portion 53, the process for which the production amount is to be changed is picked with the mouse. For example, sho in FIG.
Pick the part surrounded by the thick line of p3 with the mouse. As a result, in the format shown in the production change display section 177,
The order number that generated the process, its completion date and production volume, margin and delay are displayed.

【0178】生産量変更 生産量変更表示部177に表示される製品の注番群の中
から生産量を変更したい注番の生産量変更量項目へ変更
量を入力する。たとえば、図17では注番1003の生
産量を15台から10台へ変更するために、変更量入力
項目に変更量10台を入力する。
[Production amount change] The change amount is input to the production amount change amount item of the order number of which the production amount is to be changed from the product order number group displayed in the production amount change display portion 177. For example, in FIG. 17, in order to change the production amount of the order number 1003 from 15 to 10, the change amount of 10 is input in the change amount input item.

【0179】MRP計算実行 調整実行メニュ−157がピックされると、データ入出
力装置12が、の生産量変更結果に基づき生産量調整
指示34を生産量調整装置40へ指令する。生産量調整
装置40は、MRP制御装置2へ生産量調整結果とMR
P実行指示39を出力する。MRP制御装置2は、作業
着手順序調整結果を満足するように、MRP制御装置2
は、生産量調整結果に基づき、MRP展開装置と協調し
て、生産量が変更された注番についての生産計画のみを
生成しなおす。すなわち、これ以外の注番に関する生産
計画を前提条件として対策品目についての生産計画のみ
を計算しなおし、生産計画を修正する。修正された生産
計画は、データ記憶装置11へ記憶される。ただし、生
産量調整結果に基づき完成スケジュ−ルを変更し、全て
の注番について生産計画を生成し直すようにしてもよ
い。なお、この生産計画の修正、生成の際には、MRP
展開装置8、作業量解析装置27、生産計画実行判定装
置101は、前述した作業量、在庫量の面からの判定
を、再度行ない、データ記憶装置11に記憶されている
判定の内容を更新する。
MRP Calculation Execution When the adjustment execution menu-157 is picked up, the data input / output device 12 commands the production amount adjustment instruction 34 to the production amount adjustment device 40 based on the production amount change result. The production amount adjusting device 40 sends the production amount adjusting result and the MR to the MRP control device 2.
The P execution instruction 39 is output. The MRP controller 2 controls the MRP controller 2 so as to satisfy the work start order adjustment result.
On the basis of the production amount adjustment result, regenerates only the production plan for the order number whose production amount has been changed, in cooperation with the MRP expansion device. That is, only the production plans for the countermeasure items are recalculated with the production plans for the other order numbers as a precondition, and the production plans are corrected. The modified production plan is stored in the data storage device 11. However, the completion schedule may be changed based on the production amount adjustment result, and the production plans may be regenerated for all the order numbers. When modifying or creating this production plan, the MRP
The expansion device 8, the work amount analysis device 27, and the production plan execution determination device 101 perform the above-described determination in terms of the work amount and the stock amount again, and update the content of the determination stored in the data storage device 11. .

【0180】問題経路表示部変更 データ入出力装置12は、データ記憶装置11から、修
正された生産計画を入力し、問題経路表示部176を修
正表示する。
Change Problem Route Display Unit The data input / output device 12 inputs the corrected production plan from the data storage device 11 and corrects and displays the problem route display unit 176.

【0181】以上〜により、生産計画担当者は簡単
な操作で生産量を変更できると同時に、生産量の変更が
生産計画にどのような影響を及ぼすかをオンラインで確
認することが可能になる。
As described above, the person in charge of production planning can change the production amount by a simple operation, and at the same time, can confirm online how the change of the production amount affects the production plan.

【0182】次に、生産計画立案者が対策として、ある
注番の生産計画の削除を行なうことを決定した場合に
は、以下の手順により、生産計画の調整を行なう。
Next, when the production planner decides to delete the production plan of a certain order as a countermeasure, the production plan is adjusted by the following procedure.

【0183】図18に計画削除用画面を示す。図18の
表示画面は、図11の計画削除メニュ−156をマウス
でピックすることにより呼びだされる。
FIG. 18 shows a screen for plan deletion. The display screen of FIG. 18 is called by picking the plan deletion menu-156 of FIG. 11 with the mouse.

【0184】図中の計画削除表示部187には、問題経
路表示部53に表示されている注番に関する完成日と生
産数量、余裕と遅れ、顧客引当状況が表示される。
In the plan deletion display portion 187 in the figure, the completion date and the production quantity, the margin and the delay, and the customer allocation status regarding the order number displayed in the problem route display portion 53 are displayed.

【0185】計画を削除しながらの生産計画調整は以下
の手順により実行される。
Production plan adjustment while deleting a plan is executed by the following procedure.

【0186】計画削除注番の選択 問題経路が複数個表示されている場合、どの注番の製品
を対象に計画を削除するかを選択する。注番の選択のた
めには、注番変更ダイアル189をマウスでピックす
る。マウスでのピックにおいては、たとえば2ボタン式
のマウスの場合は、マウスの左ボタンをピックした場合
は注番を増加し、右ボタンをピックした場合は注番を減
少する。図18においては問題経路が一つしか表示され
ていないので注番1003が計画削除の対象となる。
Selection of Plan Deletion Order Number When a plurality of problem routes are displayed, it is selected which order number product the plan is to be deleted from. To select a note number, pick the note number change dial 189 with the mouse. In picking with a mouse, for example, in the case of a two-button mouse, when the left mouse button is picked, the note number is increased, and when the right button is picked, the note number is decreased. In FIG. 18, since only one problem route is displayed, the order number 1003 is the target of plan deletion.

【0187】計画削除 計画削除表示部187に表示される注番に対し計画削除
の実行ボタンをピックする。
Plan deletion The plan deletion execution button is picked for the order number displayed in the plan deletion display area 187.

【0188】MRP計算実行 調整実行メニュ−157がピックされると、データ入出
力装置12が、の計画削除結果に基づき計画削除指示
34を計画削除装置103へ指令する。計画削除装置1
03は、MRP制御装置2へ計画削除結果とMRP実行
指示39を出力する。MRP制御装置2は、計画削除結
果に基づき、完成スケジュ−ルから、削除する注番につ
いての生産要求情報を削除し、MRP展開装置8に、新
たな生産計画の生成を指示する。生成された生産計画
は、データ記憶装置11へ記憶される。なお、この生産
計画の生成の際には、MRP展開装置8、作業量解析装
置27、生産計画実行判定装置101は、前述した作業
量、在庫量の面からの判定を、再度行ない、データ記憶
装置11に記憶されている判定の内容を更新する。
MRP Calculation Execution When the adjustment execution menu-157 is picked up, the data input / output device 12 issues a plan deletion instruction 34 to the plan deletion device 103 based on the plan deletion result. Plan deletion device 1
03 outputs the plan deletion result and the MRP execution instruction 39 to the MRP control device 2. Based on the plan deletion result, the MRP control device 2 deletes the production request information for the order number to be deleted from the completed schedule, and instructs the MRP expansion device 8 to generate a new production plan. The produced production plan is stored in the data storage device 11. Note that when the production plan is generated, the MRP expansion device 8, the work amount analysis device 27, and the production plan execution determination device 101 perform the above-described determination of the work amount and the stock amount again, and store the data. The contents of the judgment stored in the device 11 are updated.

【0189】問題経路表示部変更 データ入出力装置12は、データ記憶装置11から新た
な生産計画を入力し、問題経路表示部186を修正表示
する。
Change Problem Route Display Unit The data input / output device 12 inputs a new production plan from the data storage device 11 and corrects and displays the problem route display unit 186.

【0190】以上〜により、生産計画担当者は簡単
な操作で計画を削除できると同時に、計画の削除が生産
計画にどのような影響を及ぼすかをオンラインで確認す
ることが可能になる。
As described above, the person in charge of production planning can delete a plan by a simple operation, and at the same time, can confirm online how the deletion of the plan affects the production plan.

【0191】さて、このようにして、問題解析と生産計
画の調整を繰返し、最終的に問題経路のない生産計画が
立案できたら、生産立案者は、生産計画システム100
0に、受注システム1100に、受注に引き当てた注番
の完成予定日が、要求納期以前の日であればを要求納期
を請け負い納期として回答するよう指示し、受注に引き
当てた注番の完成予定日が、要求納期以降の日であれ
ば、これ以降の日を請け負い納期として回答するよう指
示する。
In this way, when the problem analysis and the adjustment of the production plan are repeated and finally the production plan having no problem route can be made, the production planner makes the production planning system 100.
0, the ordering system 1100 is instructed to answer the requested delivery date as the delivery date if the planned completion date of the order number assigned to the order is before the requested delivery date, and the completion date of the order number assigned to the order is scheduled. If the date is after the requested delivery date, the customer will be instructed to respond to the contracted delivery date after that date.

【0192】また、調整された生産計画は製造システム
1200に渡され、実行される。
The adjusted production plan is passed to the manufacturing system 1200 and executed.

【0193】以上のように、本実施例によれば、生産計
画のうち、顧客よりの受注に引き当てた生産を、受注に
引き当てられていない生産計画に優先することにより、
顧客よりの要求納期を満足させることができるか否か
を、ショップの作業量、在庫量を考慮して判定すること
のできる生産計画システムを提供することができる。
As described above, according to the present embodiment, in the production plan, the production allocated to the order from the customer is prioritized over the production plan not allocated to the order.
It is possible to provide a production planning system capable of determining whether or not a delivery date required by a customer can be satisfied in consideration of a work amount and an inventory amount of a shop.

【0194】また、さらに、このような生産計画システ
ムにおいて、顧客よりの受注に引き当てた生産を、どの
ように、受注に引き当てられていない生産計画に優先さ
せればよいかを計画立案者に示唆することができる。
Further, in such a production planning system, it is suggested to the planner how to prioritize the production allocated to the order from the customer over the production plan not allocated to the order. can do.

【0195】すなわち、見込生産計画で予定した量より
も、受注量が多かった場合には、柔軟に生産計画を、極
力、受注内容を満足するように変更することを支援する
ことができる。
That is, when the order quantity is larger than the quantity planned in the forecast production plan, it is possible to flexibly change the production plan so as to satisfy the order contents as much as possible.

【0196】[0196]

【発明の効果】以上のように、本発明によれば、実際の
必要数が予定量より多かった場合にも、生産計画を、極
力、実際の必要数を満足するように、計画立案者が容易
に変更することができるように支援することができる生
産計画システムを提供することができる。
As described above, according to the present invention, even if the actual required number is larger than the planned amount, the planner can make the production plan as much as possible to satisfy the actual required number. It is possible to provide a production planning system that can support changes that can be easily made.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例に係る生産計画システムの構
成を示すブロック図である。
FIG. 1 is a block diagram showing a configuration of a production planning system according to an embodiment of the present invention.

【図2】本発明の一実施例に係る生産計画生成処理の処
理手順を示すフロ−チャ−トである。
FIG. 2 is a flowchart showing a processing procedure of production plan generation processing according to an embodiment of the present invention.

【図3】本発明の一実施例に係るリ−ドタイム計算の手
法を示す図である。
FIG. 3 is a diagram showing a method of lead time calculation according to an embodiment of the present invention.

【図4】本発明の一実施例に係る生産能力変更時のリ−
ドタイム計算の手法を示す図である。
FIG. 4 is a diagram showing a change in production capacity according to an embodiment of the present invention.
It is a figure which shows the method of dead time calculation.

【図5】本発明の一実施例に係る、受注内容を満足する
実行可能な生産計画の立案可能性を作業量を考慮して判
定する手法を示す図である。
FIG. 5 is a diagram showing a method of determining the possibility of formulating an executable production plan that satisfies the contents of an order in consideration of the amount of work according to an embodiment of the present invention.

【図6】本発明の一実施例に係る、受注内容を満足する
実行可能な生産計画の立案可能性を在庫量を考慮して判
定する手法を示す図である。
FIG. 6 is a diagram showing a method of determining the possibility of formulating an executable production plan that satisfies an order content in consideration of an inventory amount according to an embodiment of the present invention.

【図7】本発明の一実施例に係る生産計画システムのグ
ラフィックユ−ザインタフェ−ス中の1表示画面を示す
図である。
FIG. 7 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図8】本発明の一実施例に係る生産計画システムのグ
ラフィックユ−ザインタフェ−ス中の1表示画面を示す
図である。
FIG. 8 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図9】本発明の一実施例に係る生産計画システムのグ
ラフィックユ−ザインタフェ−ス中の1表示画面を示す
図である。
FIG. 9 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図10】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 10 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図11】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 11 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図12】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 12 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図13】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 13 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図14】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 14 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図15】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 15 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図16】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 16 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図17】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 17 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【図18】本発明の一実施例に係る生産計画システムの
グラフィックユ−ザインタフェ−ス中の1表示画面を示
す図である。
FIG. 18 is a diagram showing one display screen in the graphic user interface of the production planning system according to the embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 リードタイム計算装置 2 MRP制御装置 3 作業量計算装置 7 問題点解析装置 8 MRP展開装置 11 データ記憶装置 12 データ入出力装置 101 生産計画実行判定装置 1000 生産計画システム 1100 受注システム 1200 見込生産計画システム 1 Lead Time Calculation Device 2 MRP Control Device 3 Work Load Calculation Device 7 Problem Analysis Device 8 MRP Expansion Device 11 Data Storage Device 12 Data Input / Output Device 101 Production Planning Execution Judgment Device 1000 Production Planning System 1100 Ordering System 1200 Prospect Production Planning System

Claims (10)

【特許請求の範囲】[Claims] 【請求項1】最終品目を製造するための製造工程の一部
の工程を担い、担った工程において最終品目の部品とし
て用いられる品目、もしくは、前記最終品目を生産する
複数のショップを有する製造システムの生産計画を生成
する生産計画システムであって、 最終品目を必要個数、必要時期に供給することを要求さ
れたときに、最終品目の完成予定を規定する完成スケジ
ュ−ルにおいて完成予定の最終品目の中に、指定された
必要時期以前に完成予定の、他の要求に引き当てられて
いない、前記必要個数以上の最終品目が存在する場合に
は、これを当該要求に引き当て、存在しない場合には、
当該要求を満足する最終品目の完成予定を完成スケジュ
−ルに追加する引当手段と、 完成スケジュ−ルに基づいて、生産計画により発生する
各工程の各日の作業量が、各日の対応するショップの能
力を超えないように、各最終品目を製造するための各工
程の作業期間を、その完成予定日より順次前倒ししてい
くことにより生産計画を生成する手段と、 生成された生産計画より、各工程について、各日毎に、
当該日に当該工程で完成予定の品目を全て製造するため
に要する作業量を累計した完成作業量を求め、各工程に
ついて、各日に割り当てられる作業量が当該日のショッ
プの能力を超えた場合に、超えた分の作業量を前日に割
り当て直すように、完成予定日の遅いものより順次、各
完成作業量に含まれる作業量を、対応する完成予定日よ
り過去に向かって順次、各日に割り当てる手段と、 各工程について、現在日より前の日に、作業量が割り当
てられた場合に、前の日に作業量を割り当て直された日
が現在日より将来に向かって連続する期間中に、前記要
求に引き当てられていない最終品目および当該最終品目
に部品として用いられる品目を生産するための作業量の
累計が、現在日より前の日に割り当てられた作業量の累
計以上存在するか否かを判定し、存在する場合に、当該
工程については、前記要求に引き当てられていない最終
品目についての生産計画を変更することにより、前記要
求に引き当てられている最終品目の完成予定を満たす生
産計画の立案の可能性がある旨を判定する生産計画実行
判定手段とを有することを特徴とする生産計画システ
ム。
1. A manufacturing system having a part of a manufacturing process for manufacturing a final item, the item being used as a part of the final item in the carried step, or a plurality of shops for producing the final item. Is a production planning system that generates a production plan for a final item that is scheduled to be completed in a completion schedule that specifies the completion schedule of the final item when it is required to supply the required number of final items at the required time. If there are more than the required number of final items that are scheduled to be completed before the specified required time and have not been allocated to other requirements, allocate them to the request, and if they do not exist, ,
Based on the allocation means that adds the completion schedule of the final item that satisfies the requirement to the completion schedule, and the work volume of each process generated by the production plan on each day corresponds to each day based on the completion schedule. In order not to exceed the capacity of the shop, the means for generating the production plan by sequentially advancing the work period of each process for manufacturing each final item from the planned completion date, and the production plan generated. , For each process, each day,
When the completed work amount obtained by accumulating the work amount required to manufacture all the items scheduled to be completed in the process on the relevant day is calculated, and the work amount allocated for each process on each day exceeds the capacity of the shop on that day. In order to reallocate the excess work amount to the previous day, the work amount included in each completed work amount is sequentially calculated from the latest completion date to the past from the corresponding planned completion date. For each process, if the work is allocated on the day before the current date, during the period when the work is re-allocated on the previous day, and the future is continuous from the current day. In addition, the total amount of work for producing the final item not allocated to the request and the item used as a part of the final item is more than the cumulative total of the amount of work allocated on the day before the current date. or not If it exists, the production plan that satisfies the completion schedule of the final item assigned to the requirement is changed by changing the production plan for the final item not assigned to the requirement. A production planning system, comprising: a production plan execution determining means for determining that there is a possibility of planning.
【請求項2】請求項1記載の生産計画システムであっ
て、 前記生産計画実行判定手段は、各工程について、現在日
より前の日に、作業量が割り当てられた場合に、前の日
に作業量を割り当て直された日が現在日より将来に向か
って連続する期間を区切った複数の子期間のうち、現在
日を含まない子期間の、それぞれについて、前記要求に
引き当てられていない最終品目および当該最終品目に部
品として用いられる品目を生産するための作業量の累計
が、当該子期間の先頭日から前日に割り当て直した作業
量から、当該子期間の最終日に、その次の日より割り当
て直された作業量を減じた作業量以上存在するか否かを
判定し、現在日を含む子期間について、前記要求に引き
当てられていない最終品目および当該最終品目に部品と
して用いられる品目を生産するための作業量の累計が、
現在日以前の日に割り当てられた作業量から、当該子期
間の最終日に、その次の日より割り当て直された作業量
を減じた作業量以上存在するか否かを判定し、 全ての子期間について存在する場合に、当該工程につい
ては、前記要求に引き当てられていない最終品目につい
ての生産計画を変更することにより、前記要求に引き当
てられている最終品目の完成予定を満たす生産計画の立
案の可能性がある旨判定することを特徴とする生産計画
システム。
2. The production planning system according to claim 1, wherein the production planning execution determining means determines a date before the current date for each process when the work amount is assigned to the previous day. The final item that is not allocated to the request for each of the child periods that do not include the current date among the multiple child periods that divide the period in which the day when the work amount is reassigned from the present date toward the future And the cumulative amount of work to produce the items used as parts for the final item is calculated from the amount of work reassigned from the first day of the child period to the last day of the child period. It is determined whether or not there is more work than the reallocated work, and it is used as a part of the final item not allocated to the request and the final item for the child period including the current date. The cumulative amount of work to produce the item is
It is judged whether or not there is more than the work amount obtained by subtracting the work amount re-assigned from the next day from the work amount assigned on the day before the current date, on the last day of the child period concerned, and all children If it exists for a period, for the process concerned, by changing the production plan for the final item not allocated to the requirement, the production plan is drafted to meet the completion schedule of the final item allocated to the requirement. A production planning system characterized by determining that there is a possibility.
【請求項3】最終品目を製造するための製造工程の一部
の工程を担い、担った工程において最終品目の部品とし
て用いられる品目、もしくは、前記最終品目を生産する
複数のショップを有する製造システムの生産計画を生成
する生産計画システムであって、 最終品目を必要個数、必要時期に供給することを要求さ
れたときに、最終品目の完成予定を規定する完成スケジ
ュ−ルにおいて完成予定の最終品目の中に、指定された
必要時期以前に完成予定の、他の要求に引き当てられて
いない前記必要個数以上の最終品目が存在する場合に
は、これを当該要求に引き当て、存在しない場合には、
当該要求を満足する最終品目の完成予定を完成スケジュ
−ルに追加する引当手段と、 完成スケジュ−ルに基づいて、生産計画を生成する手段
と、 外部より調達する品目である調達品目の在庫量および在
庫予定量を管理する手段と、 各調達品目について、現在日より、前記生産計画の実現
のために調達品目を外部より調達するのに要する期間中
の、いずれかの日において、調達品目の生産計画上の各
日の所要量が、対応する日の在庫量および在庫予定量を
超える場合に、調達品目を外部より調達するのに要する
期間中の、いずれの日においても、前記要求に引き当て
られている最終品目のみを製造するために必要となる、
調達品目の各日の所要量が、対応する日の在庫量および
在庫予定量を超えないか否かを、生成された生産計画に
基づいて判定し、超えない場合に、当該調達品目につい
ては、前記要求に引き当てられていない最終品目につい
ての生産計画を変更することにより、前記要求に引き当
てられている最終品目の完成予定を満たす生産計画の立
案の可能性がある旨判定する生産計画実行判定手段とを
有することを特徴とする生産計画システム。
3. A manufacturing system having a part of a manufacturing process for manufacturing a final item, the item being used as a part of the final item in the carried step, or a plurality of shops for producing the final item. Is a production planning system that generates a production plan for a final item that is scheduled to be completed in a completion schedule that specifies the completion schedule of the final item when it is required to supply the required number of final items at the required time. If there are more than the required number of final items that are scheduled to be completed before the specified required time and have not been allocated to other requirements, this is allocated to the request, and if not,
Allocation means for adding the completion schedule of the final item that satisfies the requirement to the completion schedule, means for generating a production plan based on the completion schedule, and the inventory quantity of the procurement item that is an item procured from outside. And a means for managing the planned inventory quantity, and for each procured item, the procured item's procured item will be If the required amount of each day in the production plan exceeds the inventory quantity and the planned inventory quantity on the corresponding day, the request is allocated on any day during the period required to procure the procurement item from the outside. Required to manufacture only the final item
Based on the generated production plan, determine whether the daily requirement of the procured item exceeds the inventory quantity and the planned inventory quantity on the corresponding day. Production plan execution determining means for determining that there is a possibility of drafting a production plan that satisfies the completion schedule of the final item assigned to the request by changing the production plan for the final item not assigned to the request A production planning system characterized by having.
【請求項4】最終品目の完成予定を規定する完成スケジ
ュ−ルに基づいて、最終品目を製造するための製造工程
の一部の工程を担い、担った工程において最終品目の部
品として用いられる品目、もしくは、前記最終品目を生
産する複数のショップを有する製造システムの生産計画
を生成する生産計画システムであって、 引当手段と、所要量展開手段と、作業量計算手段と、リ
−ドタイム計算手段と、生産計画実行判定手段とを有
し、 前記引当手段は、最終品目を必要個数、必要時期に供給
することを要求されたときに、最終品目の完成予定を規
定する完成スケジュ−ルにおいて完成予定の最終品目の
中に、指定された必要時期以前に完成予定の、他の要求
に引き当てられていない前記必要個数以上の最終品目が
存在する場合には、これを当該要求に引き当て、存在し
ない場合には、当該要求を満足する最終品目の完成予定
を完成スケジュ−ルに追加し、 前記所要量展開手段は、完成スケジュ−ルを満足するた
めに各工程で製造する、各品目の所要量と当該品目の当
該工程における完成予定日をショップ毎に算出し、 前記作業量計算手段は、各工程について、各完成予定日
毎に、当該完成予定日の品目を全て製造するために要す
る作業量を累計した完成作業量を求め、 前記リ−ドタイム計算手段は、各工程について、各日に
割り当てられる作業量が当該日のショップの能力を超え
た場合に、超えた分の作業量を前日に割り当て直すよう
に、完成予定日の遅いものより順次、各完成作業量に含
まれる作業量を、対応する完成予定日より過去に向かっ
て順次、各日に割り当て、対応する完成作業量に含まれ
る作業量が割り当てられた最先の日付と、品目を一つ製
造するのにリ−ドタイムとに基づいて、各完成予定日の
各品目についてのリ−ドタイムを求め、 前記生産計画実行判定手段は、各工程について、現在日
より前の日に、作業量が割り当てられた場合に、前記リ
−ドタイム計算手段によって前の日に作業量を割り当て
直された日が現在日より将来に向かって連続する期間中
に、前記要求に引き当てられていない最終品目および当
該最終品目に部品として用いられる品目を生産するため
の作業量の累計がが、当該期間以前に割り当てた作業量
の累計以上存在するか否かを判定し、存在する場合に、
当該工程については、前記要求に引き当てられていない
最終品目についての生産計画を変更することにより、前
記要求に引き当てられている最終品目の完成予定を満た
す生産計画の立案の可能性がある旨判定し、 前記所要量展開手段は、さらに、最終品目については完
成スケジュ−ルで規定された完成予定に従い完成予定日
を定め、当該完成予定日と前記リ−ドタイム計算測手段
が当該最終品目についてリ−ドタイムより、当該最終品
目についての着手日を求め、最終品目以外の品目につい
ては、当該品目を生産する工程の次工程の着手日を完成
予定日とし、当該完成予定日と、当該品目について前記
リ−ドタイム計算測手段が求めたリ−ドタイムより、当
該品目の着手日を求めることを特徴とする生産計画シス
テム。
4. An item used as a part of the final item in a part of a manufacturing process for manufacturing the final item based on a completion schedule that defines the completion schedule of the final item. Alternatively, a production planning system for producing a production plan of a manufacturing system having a plurality of shops for producing the final item, which comprises an allocation means, a requirement expansion means, a work amount calculation means, and a lead time calculation means. And a production plan execution determination means, wherein the allocation means is completed in a completion schedule that defines the completion schedule of the final item when required to supply the final item in the required number and at the required time. If there are more than the required number of final items that are scheduled to be completed before the specified required time and have not been allocated to other requirements, check these items. It is allocated to the requirement, and if it does not exist, the completion schedule of the final item that satisfies the requirement is added to the completed schedule, and the required amount developing means is manufactured in each step to satisfy the completed schedule. , The required amount of each item and the planned completion date of the item in the relevant process are calculated for each shop, and the work amount calculating means manufactures all the items of the expected completion date for each expected date of each process. In order to obtain the completed work amount by accumulating the work amount required for the above, the lead time calculation means, for each process, when the work amount allocated on each day exceeds the capacity of the shop on that day, Allocate the amount of work included in each completed work amount in order from the latest scheduled completion date to the past from the corresponding planned completion date to each day, so that the work amount is reassigned to the previous day Based on the earliest date to which the work amount included in the completed work amount is assigned and the lead time for manufacturing one item, the lead time for each item on each scheduled completion date is obtained, The production plan execution determination means, when the work amount is assigned to the day before the current date for each process, the date when the work amount is reassigned by the lead time calculation means to the previous day is the current date. The cumulative amount of work for producing the final item that is not allocated to the requirement and the item used as a part of the final item during the continuous period toward the future is the amount of work assigned before the period. It is determined whether there is more than the cumulative total of
Regarding this process, it is judged that there is a possibility of drafting a production plan that satisfies the completion schedule of the final item assigned to the requirement by changing the production plan for the final item not assigned to the requirement. The required amount developing means further sets a scheduled completion date for the final item in accordance with the completion schedule defined in the completion schedule, and the scheduled completion date and the lead time calculation and measurement means read the final item for the final item. From the dead time, the start date for the final item is calculated, and for items other than the final item, the start date for the process next to the process for producing the item is the scheduled completion date, and the scheduled completion date and the item -A production planning system characterized in that the start date of the item is obtained from the lead time obtained by the dead time calculating and measuring means.
【請求項5】請求項4記載の生産計画システムであっ
て、 前記生産計画実行判定手段は、各工程について、現在日
より前の日に、作業量が割り当てられた場合に、前の日
に作業量を割り当て直された日が現在日より将来に向か
って連続する期間を区切った複数の子期間のうち、現在
日を含まない子期間の、それぞれについて、前記要求に
引き当てられていない最終品目および当該最終品目に部
品として用いられる品目を生産するための作業量の累計
が、当該子期間の先頭日から前日に割り当て直した作業
量から、当該子期間の最終日に、その次の日より割り当
て直された作業量を減じた作業量以上存在するか否かを
判定し、現在日を含む子期間について、前記要求に引き
当てられていない最終品目および当該最終品目に部品と
して用いられる品目を生産するための作業量の累計が
が、現在日以前の日に割り当てられた作業量から、当該
子期間の最終日に、その次の日より割り当て直された作
業量を減じた作業量以上存在するか否かを判定し、 全ての子期間について存在する場合に、当該工程につい
ては、前記要求に引き当てられていない最終品目につい
ての生産計画を変更することにより、前記要求に引き当
てられている最終品目の完成予定を満たす生産計画の立
案の可能性がある旨判定することを特徴とする生産計画
システム。
5. The production planning system according to claim 4, wherein the production planning execution determining means determines, for each process, on a day before the current date, when a work amount is assigned, on the previous day. The final item that is not allocated to the request for each of the child periods that do not include the current date among the multiple child periods that divide the period in which the day when the work amount is reassigned from the present date toward the future And the cumulative amount of work to produce the items used as parts for the final item is calculated from the amount of work reassigned from the first day of the child period to the last day of the child period. It is determined whether or not there is more work than the reallocated work, and it is used as a part of the final item not allocated to the request and the final item for the child period including the current date. The cumulative amount of work to produce the item is the work that is allocated on the day before the current date, minus the work that was reallocated from the next day on the last day of the child period. If it exists for all the child periods, it is allocated to the request by changing the production plan for the final item not allocated to the request. A production planning system characterized by determining that there is a possibility of drafting a production plan that meets the completion schedule of the final item.
【請求項6】請求項1、2、4または5記載の生産計画
システムであって、 前記生産計画実行判定手段は、さらに、前記要求に引き
当てられていない最終品目についての生産計画を変更す
ることにより、前記要求に引き当てられている最終品目
の要求を満たす生産計画の立案の可能性がある旨判定し
た工程のみによって製造される前記要求に引き当てられ
ている最終品目は、前記要求に引き当てられていない最
終品目についての生産計画を変更することにより、完成
予定を満たす生産計画の立案の可能性がある旨判定する
ことを特徴とする生産計画システム。
6. The production planning system according to claim 1, 2, 4, or 5, wherein the production planning execution determination means further changes the production planning for the final item not allocated to the request. According to the above, the final item assigned to the requirement manufactured by only the process determined to have the possibility of drafting a production plan that satisfies the requirement of the final item assigned to the requirement is assigned to the requirement. A production planning system characterized by determining that there is a possibility of drafting a production plan that satisfies the completion schedule by changing the production plan for the final item that does not exist.
【請求項7】請求項1記載の生産計画システムであっ
て、 前記、生産計画実行判定手段は、前記要求に引き当てら
れていない最終品目についての生産計画を変更すること
により、前記要求に引き当てられている最終品目の完成
予定を満たす生産計画の立案の可能性がある旨の判定結
果と、前記期間中に作業量を発生させている、前記要求
に引き当てられていない最終品目の生産計画の識別とを
記憶し、 前記生産計画システムは、前記要求に引き当てられてい
ない最終品目についての生産計画を変更することによ
り、前記要求に引き当てられている最終品目の完成予定
を満たす生産計画の立案の可能性がある旨判定した工程
の識別を、記憶した判定結果と最終品目の生産計画の識
別と関連付けて表示する手段を有することを特徴とする
生産計画システム。
7. The production planning system according to claim 1, wherein the production planning execution determining means is assigned to the request by changing a production plan for a final item not assigned to the request. The determination result that there is a possibility of drafting a production plan that meets the completion schedule of the final item, and the identification of the production plan of the final item that has generated the workload during the period and is not allocated to the request The production planning system is capable of formulating a production plan that satisfies the completion schedule of the final item assigned to the requirement by changing the production plan for the final item not assigned to the requirement. And a method for displaying the identification of the process determined to have the property in association with the stored determination result and the identification of the production plan of the final item. System.
【請求項8】請求項3記載の生産計画システムであっ
て、 前記、生産計画実行判定手段は、前記要求に引き当てら
れていない最終品目についての生産計画を変更すること
により、前記要求に引き当てられている最終品目の完成
予定を満たす生産計画の立案の可能性がある旨の判定結
果と、前記期間中に、調達部品を必要としている、前記
要求に引き当てられていない最終品目についての生産計
画の識別とを記憶し、 前記生産計画システムは、前記要求に引き当てられてい
ない最終品目についての生産計画を変更することによ
り、前記要求に引き当てられている最終品目の完成予定
を満たす生産計画の立案の可能性がある旨判定した調達
品目の識別を、記憶した最終品目の生産計画の識別と関
連付けて表示する手段を有することを特徴とする生産計
画システム。
8. The production planning system according to claim 3, wherein the production planning execution determination means is assigned to the request by changing a production plan for a final item not assigned to the request. The decision result that there is a possibility of drafting a production plan that meets the completion schedule of the final item, and the production plan of the final item that requires procurement parts during the period and is not allocated to the request. And storing the identification, the production planning system modifies the production plan for the final item not assigned to the requirement to create a production plan that meets the completion schedule of the final item assigned to the requirement. It is characterized by having means for displaying the identification of the procured item determined to be possible in association with the stored identification of the production plan of the final item. Production planning system.
【請求項9】最終品目を製造するための製造工程の一部
の工程を担い、担った工程において最終品目の部品とし
て用いられる品目、もしくは、前記最終品目を生産する
複数のショップを有する製造システムの生産計画を評価
する方法であって、 最終品目を必要個数、必要時期に供給することを要求さ
れたときに、最終品目の完成予定を規定する完成スケジ
ュ−ルにおいて完成予定の最終品目の中に、指定された
必要時期以前に完成予定の、他の要求に引き当てられて
いない前記必要個数以上の最終品目が存在する場合に
は、これを当該要求に引き当て、存在しない場合には、
当該要求を満足する最終品目の完成予定を完成スケジュ
−ルに追加し、 完成予定が追加された完成スケジュ−ルに基づいて、生
産計画により発生する各工程の各日の作業量が、各日の
対応するショップの能力を超えないように、各最終品目
を製造するための各工程の作業期間を、その完成予定日
より順次前倒ししていくことにより生産計画を生成し、 生成された生産計画より、各工程について、各日毎に、
当該日に当該工程で完成予定の品目を全て製造するため
に要する作業量を累計した完成作業量を求め、各工程に
ついて、各日に割り当てられる作業量が当該日のショッ
プの能力を超えた場合に、超えた分の作業量を前日に割
り当て直すように、完成予定日の遅いものより順次、各
完成作業量に含まれる作業量を、対応する完成予定日よ
り過去に向かって順次、各日に割り当て、 各工程について、現在日より前の日に、作業量が割り当
てられた場合に、前の日に作業量を割り当て直された日
が現在日より将来に向かって連続する期間中に、前記要
求に引き当てられていない最終品目および当該最終品目
に部品として用いられる品目を生産するための作業量の
累計が、現在日より前の日に割り当てられた作業量の累
計以上存在するか否かを判定し、存在する場合に、当該
工程については、前記要求に引き当てられていない最終
品目についての生産計画を変更することにより、前記要
求に引き当てられている最終品目の完成予定を満たす生
産計画の立案の可能性がある旨判定することを特徴とす
る生産計画の評価方法。
9. A manufacturing system having a part of a manufacturing process for manufacturing a final item, the item being used as a part of the final item in the carried step, or a plurality of shops for producing the final item. Of the final product scheduled to be completed in the completion schedule that defines the completion schedule of the final product when it is required to supply the required number of final products at the required time. In the case where there is more than the required number of final items that are scheduled to be completed before the specified required period and have not been allocated to other requirements, this is allocated to the request, and if they do not exist,
The completion schedule of the final item that satisfies the requirement is added to the completion schedule, and the amount of work of each process generated by the production plan on each day is based on the completion schedule with the completion schedule added. The production schedule is generated by sequentially advancing the work period of each process for manufacturing each final item so that it does not exceed the capacity of the corresponding shop of Therefore, for each process, for each day,
When the completed work amount obtained by accumulating the work amount required to manufacture all the items scheduled to be completed in the process on the relevant day is calculated, and the work amount allocated for each process on each day exceeds the capacity of the shop on that day. In order to reallocate the excess work amount to the previous day, the work amount included in each completed work amount is sequentially calculated from the latest completion date to the past from the corresponding planned completion date. For each process, if the work is allocated on the day before the current day, during the period when the day when the work is re-allocated on the day before is continuous from the current day to the future, Whether the cumulative amount of work for producing the final item not allocated to the request and the item used as a part of the final item is greater than or equal to the cumulative amount of work assigned to the day before the current date. Judge , If it exists, by changing the production plan for the final item that is not assigned to the requirement for the process, it is possible to formulate a production plan that meets the completion schedule of the final item assigned to the requirement. A method for evaluating a production plan, characterized by determining that there is a property.
【請求項10】最終品目を製造するための製造工程の一
部の工程を担い、担った工程において最終品目の部品と
して用いられる品目、もしくは、前記最終品目を生産す
る複数のショップを有する製造システムの生産計画を評
価する方法であって、 外部より調達する品目である調達品目の在庫量および在
庫予定量を管理し、 最終品目を必要個数、必要時期に供給することを要求さ
れたときに、最終品目の完成予定を規定する完成スケジ
ュ−ルにおいて完成予定の最終品目の中に、指定された
必要時期以前に完成予定の、他の要求に引き当てられて
いない前記必要個数以上の最終品目が存在する場合に
は、これを当該要求に引き当て、存在しない場合には、
当該要求を満足する最終品目の完成予定を完成スケジュ
−ルに追加し、 完成予定が追加された完成スケジュ−ルに基づいて、生
産計画を生成し、 生成された生産計画より、現在日より、前記生産計画の
実現のために調達品目を外部より調達するのに要する期
間中の、いずれかの日において、調達品目の生産計画上
の各日の所要量が、対応する日の在庫量および在庫予定
量を超える場合に、調達品目を外部より調達するのに要
する期間中の、いずれの日においても、前記要求に引き
当てられている最終品目のみを製造するために必要とな
る、調達品目の各日の所要量が、対応する日の在庫量お
よび在庫予定量を超えないか否かを判定し、超えない場
合に、前記要求に引き当てられていない最終品目につい
ての生産計画を変更することにより、前記要求に引き当
てられている最終品目の完成予定を満たす生産計画の立
案の可能性がある旨判定することを特徴とする生産計画
の評価方法。
10. A manufacturing system having a part of a manufacturing process for manufacturing a final item, an item used as a part of the final item in the carried step, or a plurality of shops for producing the final item. Is a method of evaluating the production plan of, which manages the inventory quantity and planned inventory quantity of procurement items that are items to be procured from the outside, and when it is required to supply the required number of final items at the required time, Among the final items to be completed in the completion schedule that specifies the completion schedule of the final item, there are more than the required number of final items that are scheduled to be completed before the specified required time and are not allocated to other requirements. If so, assign this to the request; if not,
The completion schedule of the final item that satisfies the requirement is added to the completion schedule, the production plan is generated based on the completion schedule to which the completion schedule is added, and from the generated production plan from the current date, In any day during the period required to procure procured items from the outside to realize the production plan, the required amount on each day of the production plan for the procured items is the inventory amount and inventory on the corresponding day. Each of the procured items required to manufacture only the final item allocated to the requirement on any day during the period required to procure the procured items from the outside when the planned amount is exceeded. By determining whether the daily requirement does not exceed the inventory quantity and the planned inventory quantity on the corresponding day, and if not, by changing the production plan for the final item not allocated to the request, Evaluation method of production planning, characterized in that it determined that there is a possibility of the planning of the production plan to meet the completion schedule of the end item that is reserved to the serial request.
JP7101894A 1994-04-08 1994-04-08 Production planning system Expired - Lifetime JP3240237B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7101894A JP3240237B2 (en) 1994-04-08 1994-04-08 Production planning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7101894A JP3240237B2 (en) 1994-04-08 1994-04-08 Production planning system

Publications (2)

Publication Number Publication Date
JPH07282140A true JPH07282140A (en) 1995-10-27
JP3240237B2 JP3240237B2 (en) 2001-12-17

Family

ID=13448364

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7101894A Expired - Lifetime JP3240237B2 (en) 1994-04-08 1994-04-08 Production planning system

Country Status (1)

Country Link
JP (1) JP3240237B2 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09153090A (en) * 1995-11-30 1997-06-10 Matsushita Electric Ind Co Ltd Method and device for forming working process production plan
JP2003108836A (en) * 2001-09-27 2003-04-11 Nec Microsystems Ltd Stock control system including adjustment to work in progress
US6711449B1 (en) 1998-12-22 2004-03-23 Toyota Jidosha Kabushiki Kaisha Ordered product delivery date management system for management product or part production slot exchange
JP2005092274A (en) * 2003-09-12 2005-04-07 Amada Co Ltd Sheet metal product manufacturing method and system therefor, and recording medium stored with sheet metal model
JP2008066633A (en) * 2006-09-11 2008-03-21 Hitachi High-Technologies Corp Defect inspection analysis system, defect inspection analysis method and management computer used for the method
JP2008152381A (en) * 2006-12-14 2008-07-03 Fuji Electric Systems Co Ltd Production plan preparation system and production plan preparation program
CN108132650A (en) * 2016-12-01 2018-06-08 北京理工大学 A kind of Flow Shop control method and device
CN111489048A (en) * 2020-02-18 2020-08-04 深圳坤湛科技有限公司 Method and system for matching requirements and productivity of shoe manufacturing enterprise
JP2020197827A (en) * 2019-05-31 2020-12-10 株式会社日立製作所 Project management device and project management method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09153090A (en) * 1995-11-30 1997-06-10 Matsushita Electric Ind Co Ltd Method and device for forming working process production plan
US6711449B1 (en) 1998-12-22 2004-03-23 Toyota Jidosha Kabushiki Kaisha Ordered product delivery date management system for management product or part production slot exchange
JP2003108836A (en) * 2001-09-27 2003-04-11 Nec Microsystems Ltd Stock control system including adjustment to work in progress
JP2005092274A (en) * 2003-09-12 2005-04-07 Amada Co Ltd Sheet metal product manufacturing method and system therefor, and recording medium stored with sheet metal model
JP2008066633A (en) * 2006-09-11 2008-03-21 Hitachi High-Technologies Corp Defect inspection analysis system, defect inspection analysis method and management computer used for the method
JP2008152381A (en) * 2006-12-14 2008-07-03 Fuji Electric Systems Co Ltd Production plan preparation system and production plan preparation program
CN108132650A (en) * 2016-12-01 2018-06-08 北京理工大学 A kind of Flow Shop control method and device
CN108132650B (en) * 2016-12-01 2020-03-17 北京理工大学 Flow shop control method and device
JP2020197827A (en) * 2019-05-31 2020-12-10 株式会社日立製作所 Project management device and project management method
CN111489048A (en) * 2020-02-18 2020-08-04 深圳坤湛科技有限公司 Method and system for matching requirements and productivity of shoe manufacturing enterprise

Also Published As

Publication number Publication date
JP3240237B2 (en) 2001-12-17

Similar Documents

Publication Publication Date Title
JP3447286B2 (en) Production plan creation system and production plan creation method
JP3497348B2 (en) Production planning system
Frantzén et al. A simulation-based scheduling system for real-time optimization and decision making support
US7752020B2 (en) System and method for modeling construction risk using location-based construction planning models
US7532945B2 (en) Data model for supply chain planning
US5471408A (en) Method for optimizing resource allocation and an apparatus using the method
US7369910B2 (en) Method for the optimizing of a production process
JPH05225205A (en) Sequential defined production planning system
US8244569B2 (en) Non-destructive element splitting using location-based construction planning models
Selcuk et al. The effect of updating lead times on the performance of hierarchical planning systems
JP3610581B2 (en) Production plan adjustment device
JP3240237B2 (en) Production planning system
JP2002373013A (en) Production scheduling method, program for computer to execute the same method and computer-readable recording medium with the program recorded thereon
JPH08212261A (en) Starting plan forming device
Doctor et al. Scheduling for machining and assembly in a job-shop environment
JPH11120248A (en) System and method for scheduling production
JPS59214964A (en) Conversational scheduling system
JPH09128440A (en) Production planning method and system using it
JP3195385B2 (en) Production planning system and production planning method
US20070239410A1 (en) Location-based construction planning and scheduling system
JP3241714B2 (en) Plan type inference method and apparatus
JP2000010606A (en) System for generating production plan
JP4295926B2 (en) General-purpose cost calculation system and general-purpose cost calculation program
Pritsker et al. Production scheduling using FACTOR
JP2001356812A (en) System for controlling component synchronization and method for planning production

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071012

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081012

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091012

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091012

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101012

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111012

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121012

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121012

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131012

Year of fee payment: 12

EXPY Cancellation because of completion of term