JPH07243221A - Construction method for structure having basement - Google Patents

Construction method for structure having basement

Info

Publication number
JPH07243221A
JPH07243221A JP6059849A JP5984994A JPH07243221A JP H07243221 A JPH07243221 A JP H07243221A JP 6059849 A JP6059849 A JP 6059849A JP 5984994 A JP5984994 A JP 5984994A JP H07243221 A JPH07243221 A JP H07243221A
Authority
JP
Japan
Prior art keywords
temporary
beam assembly
temporary beam
crane
assembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6059849A
Other languages
Japanese (ja)
Inventor
Yasuhiro Oda
康弘 小田
Masazumi Yoshino
正純 吉野
Hisanao Yamakage
久尚 山影
Takeo Kanekawa
武雄 金川
Shoichi Hashiguchi
正一 橋口
Yukihisa Okina
幸久 翁
Minoru Tanaka
實 田中
Masashi Takahashi
正志 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP6059849A priority Critical patent/JPH07243221A/en
Publication of JPH07243221A publication Critical patent/JPH07243221A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To improve work efficiency by moving a temporary support in a vertical direction through a temporary beam assembly, and sequentially constructing a permanent support and a beam at each floor by using a crane laid on the underside of the beam assembly. CONSTITUTION:One set 2a of temporary supports is moved downward, relative to a temporary beam assembly 1 with a lift-up device 4, and the assembly 1 is elevated to a level corresponding to the fourth floor. Then, a permanent support is lifted with a crane 5 installed on the lower side of the assembly 1 and fixed to the top of a structural stud 3. Thereafter, the other set 2b of temporary supports is moved downward and the lower end thereof is kept in contact with the forward end of the support, while the set 2a is lifted. Then, the support is erected with the crane 5 and a beam 8 for the second floor is laid under the assembly 1. Thereafter, the assembly 1 is elevated to a level corresponding to the fifth floor. Furthermore, the underground is excavated with a crane laid under a beam 8, a bucket, an excavation device 11 or the like for constructing the skeleton of a basement, and the assembly 1 is elevated to construct an upper floor skeleton.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は地下のある構造物の構築
工法、特に構造物の地上及び地下をビル構築用クレーン
を用いて同時に施工する地下のある構造物の構築工法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a structure having an underground structure, and more particularly to a method for constructing a structure having an underground structure by simultaneously constructing the structure above and below the structure with a crane for building a building.

【0002】[0002]

【従来の技術】従来、地下階のある中高層ビル等の各種
建造物の建設においては、地下階の施工作業完了後に地
上階の施工を行なうようにしている。また、施工時間の
短縮を図ることを目的として、地下工事と地上階の構築
を同時に行なうことも提案されているが、全天候型の機
械化施工は従来、地上部分に限られて実施されている。
2. Description of the Related Art Conventionally, in the construction of various structures such as middle and high-rise buildings having a basement floor, the ground floor is constructed after the construction work of the basement floor is completed. Further, it has been proposed that the underground construction and the construction of the above-ground floor are performed at the same time for the purpose of shortening the construction time, but the all-weather mechanized construction is conventionally carried out only in the above-ground portion.

【0003】[0003]

【発明が解決しようとする課題】然しながら、地盤の掘
削作業や地下躯体の構築作業はその作業能率が天候に左
右されやすく、大雨の場合は周辺地盤から流れ込んでく
る雨水の処理に苦労することがあった。また、市街地等
構築物外周部に敷地が残っていないような場合や地下の
面積そのものが大きい場合にその内部に仮設の乗り入れ
構台を設置して、地下の掘削工事や地下躯体工事を行う
必要があり、構台直下の掘削や躯体工事は資材の垂直揚
重が困難であった。また、従来逆打ちや1F床版先行打
ちにおいてみられる地下・地上の構造物の同時構築は狭
い地下の作業空間により、必ずしも期待通りの工期短縮
が達成されない場合があった。
However, the work efficiency of the ground excavation work and the construction of the underground skeleton is easily influenced by the weather, and in the case of heavy rain, it may be difficult to process the rainwater flowing from the surrounding ground. there were. In addition, if there is no site left on the outer periphery of the structure, such as an urban area, or if the underground area itself is large, it is necessary to install a temporary boarding gantry inside it and perform underground excavation work and underground structure work. However, it was difficult to vertically lift materials for excavation and building work directly under the gantry. Moreover, due to the small underground work space, the simultaneous construction of underground and above-ground structures, which has been seen in the conventional counter-strike or 1F floor slab advance strike, may not always achieve the expected shortening of the construction period.

【0004】本発明は地下工事を乗り入れ構台のない広
々とした全天候型の作業空間で地下工事を行い、上記の
欠点を除くようにしたものである。
The present invention is intended to eliminate the above-mentioned drawbacks by carrying out underground construction in a spacious all-weather working space without a pedestal.

【0005】[0005]

【課題を解決するための手段】本発明の地下のある構造
物の構築工法は、地上に梁組を仮設する第一の工程と、
仮設支柱を上記仮設の梁組に相対的に上記仮設の梁組を
貫通して上下動自在に併設する第二の工程と、この仮設
支柱の一方の組に相対的に上記仮設の梁組を上記仮設支
柱の他方の組と共にリフトアップする第三の工程と、上
記仮設の梁組の上昇により上記仮設支柱の他方の組の下
方に生じた空間を利用して上記仮設の梁組の下面にビル
構築用クレーンを配置し、このビル構築用クレーンを用
いて本設支柱を設置すると共に、同じく上記仮設の梁組
の下方に形成された空間に梁の建込みを行なう第四の工
程と、上記仮設支柱の他方の組を上記仮設の梁組に相対
的に上記設置された本設支柱上に下降せしめる第五の工
程と、上記仮設支柱の一方の組を上記仮設の梁組に相対
的に上記仮設の梁組上に上昇せしめると共に、上記仮設
の梁組を上記仮設支柱の他方の組に相対的にリフトアッ
プする第六の工程と、上記仮設の梁組の上昇により上記
仮設支柱の一方の組の下方に生じた空間に上記ビル構築
用クレーンを用いて本設支柱を設置すると共に、同じく
上記仮設の梁組の下方に形成された空間に梁の建込みを
行なう第七の工程と、上記第三〜第七の各工程を順次繰
り返した後仮設の梁組及び支柱を解体する第八の工程
と、上記第四〜第七の工程で形成した上記梁の下面に他
のビル構築用クレーンを配置し、その後の上記工程の間
に上記他のビル構築用クレーンにより地下の掘削と、地
下の各層の梁の建込みを行なう第九の工程とより成る。
The construction method of a structure with an underground of the present invention comprises a first step of temporarily installing a beam assembly on the ground,
The second step of arranging the temporary support columns vertically above and below the temporary beam set so as to be vertically movable, and the temporary beam set relative to one of the temporary support columns. A third step of lifting up together with the other set of the temporary columns, and utilizing the space generated below the other set of the temporary columns due to the rise of the temporary beam set to the lower surface of the temporary beam set. A fourth step of arranging a building construction crane, setting up a main strut using this building construction crane, and also constructing a beam in the space formed below the temporary beam assembly, A fifth step of lowering the other set of the temporary support columns relative to the temporary beam set onto the main support column installed above, and one set of the temporary support columns relative to the temporary beam set. And raise the above-mentioned temporary beam assembly to the above-mentioned temporary beam assembly. The sixth step of lifting up relatively to the other set of columns, and the main construction using the building construction crane in the space created below one set of the temporary columns by the rise of the temporary beam set. A temporary beam assembly after the pillars are installed and also a beam is erected in the space formed below the temporary beam assembly and the third step to the seventh step are sequentially repeated. And an eighth step of dismantling the pillars, and another crane for building construction is placed on the lower surface of the beam formed in the fourth to seventh steps, and for the construction of the other building during the subsequent steps. It consists of underground excavation by a crane and the ninth step of erection of underground beams.

【0006】上記仮設の梁組の上部には、仮設覆いが形
成されている。
A temporary cover is formed on the upper part of the temporary beam assembly.

【0007】上記仮設の梁組上には、その解体用のクレ
ーンを取り付けておく。
A crane for disassembling the temporary beam assembly is mounted on the temporary beam assembly.

【0008】また、本発明の地下のある構造物の構築工
法は、地上に梁組を仮設する第一の工程と、仮設支柱を
上記仮設の梁組に相対的に上記仮設の梁組を貫通して上
下動自在に併設する第二の工程と、この仮設支柱の一方
の組に相対的に上記仮設の梁組を上記仮設支柱の他方の
組と共にリフトアップする第三の工程と、上記仮設の梁
組の上昇により上記仮設支柱の他方の組の下方に生じた
空間を利用して上記仮設の梁組の下面にビル構築用クレ
ーンを配置し、このビル構築用クレーンを用いて本設支
柱を設置すると共に、同じく上記仮設の梁組の下方に形
成された空間に梁の建込みを行なう第四の工程と、上記
梁の下面に他のビル構築用クレーンを配置し、このビル
構築用クレーンにより地下の掘削と、地下の各層の梁の
建込みを行なう第五の工程と、上記仮設支柱の他方の組
を上記仮設の梁組に相対的に上記第四の工程で設置され
た本設支柱上に下降せしめる第六の工程と、上記仮設支
柱の一方の組を上記仮設の梁組に相対的に上記仮設の梁
組上に上昇せしめると共に、上記仮設の梁組を上記仮設
支柱の他方の組に相対的にリフトアップする第七の工程
と、上記仮設の梁組の上昇により上記仮設支柱の一方の
組の下方に生じた空間に上記ビル構築用クレーンを用い
て本設支柱を設置すると共に、同じく上記仮設の梁組の
下方に形成された空間に梁の建込みを行なう第八の工程
と、上記第三、第四、第六〜第八の各工程を順次繰り返
した後仮設の梁組及び支柱を解体する第九の工程とより
成る。
Further, in the construction method for a structure with a certain underground of the present invention, the first step of temporarily installing the beam set on the ground, and the temporary support column is pierced through the temporary beam set relatively to the temporary beam set. And a second step of vertically moving together, and a third step of lifting up the temporary beam set together with the other set of the temporary support columns relative to one set of the temporary support columns, and the temporary installation. The building construction crane is placed on the lower surface of the above-mentioned temporary beam assembly by utilizing the space created below the other of the above-mentioned temporary construction pillars, and this building construction crane is used to construct the main installation pillar. In the same manner as the above, the fourth step of installing the beam in the space formed below the temporary beam assembly and arranging another building construction crane on the underside of the beam. Underground excavation by a crane and erection of underground beams And a sixth step of lowering the other set of the temporary support columns onto the main support column installed in the fourth step relative to the temporary beam assembly, and one set of the temporary support columns. While raising the above-mentioned temporary beam set relative to the above-mentioned temporary beam set, and lifting up the above-mentioned temporary beam set relatively to the other set of the above-mentioned temporary support columns; While installing the main construction pillar using the building construction crane in the space created below one of the temporary pillar pairs due to the rise of the beam pillar, the beams are also installed in the space formed below the temporary pillar assembly. No. 8 and the ninth step of disassembling the temporary beam assembly and the post after repeating the above third, fourth, sixth to eighth steps in sequence.

【0009】上記地下の各層の梁の建込みは、地下1階
より順次下の階層に向かって行なう。
The construction of the beams of each layer of the underground is carried out sequentially from the first basement floor to the lower layers.

【0010】[0010]

【実施例】以下図面によって本発明の実施例を説明す
る。
Embodiments of the present invention will be described below with reference to the drawings.

【0011】図1において、1は地上に配置した仮設の
梁組、2a・・・,2b・・・はこの仮設の梁組1を支
持するためこれと相対的にこれを貫通して上下動自在に
設けた、本設支柱の本数と同一の複数本の仮設支柱、3
はこの仮設支柱2a・・・,2b・・・の下端を支える
ため基礎部分に設置した構真柱、4は上記仮設支柱2a
・・・,2b・・・を上記仮設の梁組1に相対的に上記
仮設の梁組1を貫通して上下動せしめるため上記梁組1
に固定した、リフトアップ装置を示し、本発明において
は地盤中に多軸オーガー等の掘削機(図示せず)を使用
して山留め壁(図示せず)を施工し、建造物の柱の位置
に構真柱3を現場造成杭3aに建て込みこの構真柱3を
足場としてその上部に仮設の梁組1を設置する。
In FIG. 1, reference numeral 1 denotes a temporary beam assembly 2a, ..., 2b. A plurality of temporary columns, the number of which is the same as the number of main columns, freely set.
, Are true columns installed on the foundation to support the lower ends of these temporary columns 2a ..., 2b.
, 2b, so as to move vertically through the temporary beam assembly 1 relative to the temporary beam assembly 1
A lift-up device fixed to the position of the pillar of the building is constructed in the present invention by constructing a mountain retaining wall (not shown) using an excavator (not shown) such as a multi-axis auger in the ground. Then, the structure pillar 3 is built on the site construction pile 3a, and the temporary beam assembly 1 is installed on the upper part of the structure pillar 3 as a scaffold.

【0012】上記仮設の梁組1が地上にあるとき、第1
の段階として、上記仮設支柱のうち一方の組2a・・・
のみを上記リフトアップ装置4により上記仮設の梁組1
に相対的に同時に下方に移動せしめ、この結果として、
上記仮設支柱の一方の組2a・・・に相対的に仮設の梁
組1が図2に示すように地上から四階の高さに上昇され
るようにする。
When the temporary beam assembly 1 is on the ground, the first
At the stage of, one set 2a ...
Only the temporary beam assembly 1 by the lift-up device 4
And move them downward at the same time, and as a result,
The temporary beam assembly 1 is relatively elevated to the one set 2a of the above-mentioned temporary support columns so as to be elevated from the ground to the height of the fourth floor as shown in FIG.

【0013】これにより図2に示すように、仮設支柱の
他方の組2b・・・は仮設の梁組1とともに上方に移動
するので仮設の梁組1の上昇によりその下方には、施工
作業空間が形成されるから、部材揚重用のビル構築用ク
レーン5等を仮設の梁組1の下面にレール6を介して取
り付け、下方に移動されていない上記仮設支柱の他方の
組2b・・・の下端とこれに対応する上記構真柱3の上
面との間に形成されている図2に示すような本設支柱施
工空間に上記ビル構築用クレーン5により地上にある本
設支柱7を持ち上げ、図3に示すように上記構真柱3上
に本設支柱7を熔接により固定せしめる。
As a result, as shown in FIG. 2, the other set 2b of the temporary columns moves upward together with the temporary beam set 1, so that the temporary working beam set 1 is lifted and the construction work space is provided below the temporary beam set 1. Therefore, the building construction crane 5 for lifting the members is attached to the lower surface of the temporary beam assembly 1 via the rails 6, and the other set 2b of the temporary support pillars that has not been moved downward. The main building support pillar 7 on the ground is lifted by the building construction crane 5 into the main building support pillar construction space as shown in FIG. 2 formed between the lower end and the corresponding upper surface of the true structure pillar 3. As shown in FIG. 3, the main support columns 7 are fixed on the above-mentioned structure columns 3 by welding.

【0014】次に、第2の段階として、上記仮設支柱の
他方の組2b・・・をリフトアップ装置4により上記仮
設の梁組1に相対的に下方に移動して図4に示すように
仮設支柱の他方の組2b・・・の下端が既に固定されて
いる上記本設支柱7の先端に接触せしめる。
Next, in a second step, the other set 2b of the temporary columns is moved downward by the lift-up device 4 relative to the temporary beam set 1 as shown in FIG. The lower end of the other set 2b ... Of the temporary columns is brought into contact with the tip of the main column 7 already fixed.

【0015】また、上記操作の間、上記仮設支柱の一方
の組2a・・・をリフトアップ装置4により上昇せしめ
図4に示すように、下方に本設支柱施工空間を確保せし
める。その後、上記と同様この空間にビル構築用クレー
ン5により本設支柱7を設置し、更に、仮設の梁組1の
下方に二階用の梁8を施工する。さらにリフトアップ装
置4を作動させるとその反力により、図5に示すように
仮設の梁組1が五階の高さに上昇するようになる。
Further, during the above operation, one set 2a of the temporary columns is lifted by the lift-up device 4 to secure a space for constructing the main columns below as shown in FIG. Thereafter, as in the above case, the main construction columns 7 are installed in this space by the building construction crane 5, and further the second floor beam 8 is constructed below the temporary beam assembly 1. When the lift-up device 4 is further operated, the reaction force causes the temporary beam assembly 1 to rise to the height of the fifth floor as shown in FIG.

【0016】次いで、本発明においては図6に示すよう
に、上記工程で形成した梁8の下にレール10を取り付
け、このレール10に上記ビル構築用クレーン5により
他のビル構築用クレーン、バケットまたは掘削装置11
等を取り付ける。
Next, in the present invention, as shown in FIG. 6, a rail 10 is attached below the beam 8 formed in the above-mentioned step, and another building construction crane or bucket is mounted on the rail 10 by the building construction crane 5. Or excavator 11
Etc.

【0017】上記ビル構築用クレーン等の取り付け後、
これにより図7〜図9に示すように地下の掘削、掘削土
排出を所定位置に切梁等の土留支保工を設置し、かつ構
真柱3の座掘防止を図りながら続け、最下階となる所ま
で掘削し、その後、上記他のビル構築用クレーン等11
により最下階の梁の建込みを行い、順に下層階から上層
階へ梁を立て込んで地下階の躯体工事を終了せしめる。
After installing the building construction crane, etc.,
As a result, as shown in Fig. 7 to Fig. 9, excavation underground and excavated soil discharge are installed at predetermined positions with earth retaining supports such as beams, and while continuing to prevent excavation of the structure columns 3, the bottom floor Excavate to the place where
The beam on the bottom floor will be erected by, and the beam will be erected from the lower floor to the upper floor in order to complete the skeleton construction on the basement floor.

【0018】この間、地上では上記リフトアップ装置4
を作動させ、その反力により上記仮設の梁組1を上層階
に上昇せしめ、以下上記第1段階操作と第2段階操作を
繰り返し行い、梁の建込みを行ないながら、最上階まで
の施工を行なうようにする。
During this period, the lift-up device 4 is on the ground.
The temporary beam assembly 1 is lifted to the upper floors by the reaction force, and the first step operation and the second step operation are repeatedly performed below, and the construction of the top floor is performed while building the beams. Try to do it.

【0019】なお、上記他のビル構築用クレーン等11
は四階以上の階の梁に設けても良く、また、雨対策とし
ては、上記施工作業空間を覆う仮設覆9を設置するのが
好ましい。
Incidentally, other building construction cranes, etc. 11
May be provided on the beams on the fourth and higher floors, and as a measure against rain, it is preferable to install a temporary cover 9 for covering the construction work space.

【0020】本発明の他の実施例においては、図9に示
すように上記仮設の梁組1上にあらかじめ解体用クレー
ン12を取り付けておき、最上階までの施工完了後この
解体用クレーン12によって上記最上階の仮設部分を解
体撤去できるようにする。
In another embodiment of the present invention, as shown in FIG. 9, a dismantling crane 12 is preliminarily mounted on the temporary beam assembly 1, and after the construction up to the top floor is completed, the dismantling crane 12 is used. Enable to dismantle and remove the temporary part on the top floor.

【0021】なお、本発明の他の実施例においては、最
下階まで掘削した後に梁を建て込む順打ち工法の代わり
に掘削しながら地下1階から順に下の階層へ梁の建て込
みを行なう逆打ち工法を採用する。
In another embodiment of the present invention, instead of the sequential driving method of digging a beam after digging up to the lowest floor, digging is performed from the first basement floor to a lower floor in order. Adopt the reverse construction method.

【0022】本発明の他の実施例においては上記他のビ
ル構築用クレーン等による地下階の躯体工事終了後三階
以上の地上階の躯体工事を行うようにする。
In another embodiment of the present invention, the construction work of the above ground floor of the third floor or more is carried out after the construction work of the basement floor is completed by the above-mentioned other building construction crane or the like.

【0023】また、上記ビル構築用クレーン等を複数設
け作業の分担を図ることによって工期の短縮を図ること
ができる。
Further, the construction period can be shortened by providing a plurality of the building construction cranes and the like to share the work.

【0024】なお、本発明の地下のある構造物の構築工
法において用いる上記リフトアップ装置4は例えば、上
記仮設支柱2a・・・,2b・・・にその上下方向に一
定のピッチングで形成したピン受孔と、仮設の梁組1に
固定した油圧シリンダーと、この油圧シリンダーに固定
した下方環状梁と、上記油圧シリンダーから上方に突出
するピストンロッドに固定した上方環状梁と、上記下方
及び上方環状梁に設けたピンシリンダとにより構成し、
上記ピストンロッドが最大に伸長された状態で上記上方
環状梁のピンシリンダからこれに合致する上記仮設支柱
のピン受孔にピンを差し込み、下方環状梁のピンシリン
ダを操作してそのピンを上記仮設支柱のピン受孔から抜
き取り、油圧シリンダを操作して上記仮設支柱に相対的
に上記油圧シリンダと下側環状梁を上記仮設の梁組1と
共に上昇せしめ、この位置で下側環状梁のピンシリンダ
を操作してそのピンを上記仮設支柱の対応するピン受孔
に差し込み、上記上方環状梁のピンシリンダを操作して
そのピンを上記仮設支柱のピン受孔から抜き取り、油圧
シリンダを操作して再びピストンロッドを最大に伸長し
て上方環状梁を押し上げ、この状態で上記上方環状梁の
ピンシリンダからこれに合致する上記仮設支柱のピン受
孔にピンを差し込み、以下このような操作を繰り返して
仮設支柱に相対的に仮設の梁組1を上昇せしめるものと
する。
The lift-up device 4 used in the method for constructing a certain underground structure of the present invention is, for example, a pin formed on the temporary columns 2a ..., 2b. A receiving hole, a hydraulic cylinder fixed to the temporary beam assembly 1, a lower annular beam fixed to the hydraulic cylinder, an upper annular beam fixed to a piston rod projecting upward from the hydraulic cylinder, and the lower and upper annular members. Composed of a pin cylinder provided on the beam,
With the piston rod extended to the maximum extent, a pin is inserted from the pin cylinder of the upper annular beam into the pin receiving hole of the temporary column that matches the pin cylinder, and the pin cylinder of the lower annular beam is operated to temporarily install the pin. It is pulled out from the pin receiving hole of the column, and the hydraulic cylinder is operated to raise the hydraulic cylinder and the lower annular beam together with the temporary beam set 1 to the temporary column, and at this position, the pin cylinder of the lower annular beam. To insert the pin into the corresponding pin receiving hole of the temporary support column, operate the pin cylinder of the upper annular beam to remove the pin from the pin receiving hole of the temporary support column, and operate the hydraulic cylinder again. The piston rod is extended to the maximum and the upper annular beam is pushed up, and in this state, insert the pin from the pin cylinder of the upper annular beam into the pin receiving hole of the above-mentioned temporary strut which matches It shall be allowed to increase the beam pairs 1 below relatively temporary such operations repeated temporary supports.

【0025】[0025]

【発明の効果】上記のように本発明の地下のある構造物
の構築工法によれば、市街地等で複数の地上クレーン設
置空間が確保出来ない場合であっても、建造物施工に支
障がなく、また、地上階の施工と地下階の施工を独立し
て行なうことができるので、施工時間の短縮を図ること
ができる。また、地上階の施工をすべて仮設材により行
なうので工事の自動化、省力化を図れる。
As described above, according to the method for constructing a structure with an underground structure of the present invention, even if a plurality of aboveground crane installation spaces cannot be secured in an urban area or the like, there is no obstacle to the construction of the structure. Moreover, since the construction on the ground floor and the construction on the basement floor can be performed independently, the construction time can be shortened. In addition, since all construction on the ground floor is done with temporary materials, the construction can be automated and labor-saving.

【0026】また、従来では地上に乗入構台を作り、こ
の上に掘削のためのクラムシェル等の揚重機を乗せ掘削
作業を行っていたので、上記乗入構台下面の作業が困難
または不可能であったが、本発明によればこのような欠
点がなく、地上階が屋根となるので全天候作業となり、
作業能率も向上する等種々な利益がある。
Further, conventionally, since a boarding gantry is formed on the ground and a lifting machine such as a clam shell for digging is placed on the ground for excavation work, it is difficult or impossible to work the bottom surface of the boarding gantry. However, according to the present invention, there is no such drawbacks, and the ground floor serves as a roof, so it becomes all-weather work,
There are various benefits such as improved work efficiency.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 1 is an explanatory diagram of a construction method for a structure with an underground of the present invention.

【図2】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 2 is an explanatory diagram of a method of constructing a structure with an underground of the present invention.

【図3】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 3 is an explanatory diagram of a method of constructing a structure with an underground according to the present invention.

【図4】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 4 is an explanatory diagram of a method for constructing a structure with an underground according to the present invention.

【図5】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 5 is an explanatory diagram of a method for constructing a structure with an underground according to the present invention.

【図6】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 6 is an explanatory view of a method for constructing a structure with an underground according to the present invention.

【図7】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 7 is an explanatory diagram of a method of constructing a structure with an underground according to the present invention.

【図8】本発明の地下のある構造物の構築工法の説明図
である。
FIG. 8 is an explanatory diagram of a method for constructing a structure with an underground of the present invention.

【図9】本発明の地下のある構造物の構築工法により完
成した構造物の最上階仮設部分の撤去状態説明図であ
る。
FIG. 9 is an explanatory view of a removed state of the temporary uppermost floor portion of the structure completed by the construction method of the underground structure of the present invention.

【符号の説明】[Explanation of symbols]

1 梁組 2a 仮設支柱 2b 仮設支柱 3 構真柱 3a 現場造成杭 4 リフトアップ装置 5 ビル構築用クレーン 6 レール 7 本設支柱 8 梁 9 仮設覆 10 レール 11 他のビル構築用クレーン、バケットまたは掘削装
置 12 解体用クレーン
1 Beam assembly 2a Temporary support pillar 2b Temporary support pillar 3 Structure true pillar 3a Site construction pile 4 Lift-up device 5 Building crane 6 Rail 7 Main support pillar 8 Beam 9 Temporary cover 10 Rail 11 Other building construction crane, bucket or excavation Equipment 12 Crane for dismantling

───────────────────────────────────────────────────── フロントページの続き (72)発明者 金川 武雄 東京都品川区東大井1丁目11番25号 五洋 建設株式会社技術研究所内 (72)発明者 橋口 正一 東京都文京区後楽2丁目2番8号 五洋建 設株式会社内 (72)発明者 翁 幸久 東京都文京区後楽2丁目2番8号 五洋建 設株式会社内 (72)発明者 田中 實 東京都品川区東大井1丁目11番25号 五洋 建設株式会社技術研究所内 (72)発明者 高橋 正志 東京都品川区東大井1丁目11番25号 五洋 建設株式会社技術研究所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Takeo Kanakawa 1-11-25 Higashiooi, Shinagawa-ku, Tokyo Inside the Technical Research Institute, Goyo Construction Co., Ltd. (72) Shoichi Hashiguchi 2-chome Koraku, Bunkyo-ku, Tokyo No. 8 In Goyo Construction Co., Ltd. (72) Inventor Yukisa Okina 2-8 Koraku, Bunkyo-ku, Tokyo No. 8 In Goyo Construction Co., Ltd. (72) Inventor Minoru Tanaka 1-chome, Higashi Oi, Shinagawa-ku, Tokyo No. 11-25 Goyo Construction Co., Ltd. Technical Research Laboratory (72) Inventor Masashi Takahashi 1-11-25 Higashiooi, Shinagawa-ku, Tokyo Goyo Construction Co., Ltd. Technical Research Center

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 地上に梁組を仮設する第一の工程と、 仮設支柱を上記仮設の梁組に相対的に上記仮設の梁組を
貫通して上下動自在に併設する第二の工程と、 この仮設支柱の一方の組に相対的に上記仮設の梁組を上
記仮設支柱の他方の組と共にリフトアップする第三の工
程と、 上記仮設の梁組の上昇により上記仮設支柱の他方の組の
下方に生じた空間を利用して上記仮設の梁組の下面にビ
ル構築用クレーンを配置し、このビル構築用クレーンを
用いて本設支柱を設置すると共に、同じく上記仮設の梁
組の下方に形成された空間に梁の建込みを行なう第四の
工程と、 上記仮設支柱の他方の組を上記仮設の梁組に相対的に上
記設置された本設支柱上に下降せしめる第五の工程と、 上記仮設支柱の一方の組を上記仮設の梁組に相対的に上
記仮設の梁組上に上昇せしめると共に、上記仮設の梁組
を上記仮設支柱の他方の組に相対的にリフトアップする
第六の工程と、 上記仮設の梁組の上昇により上記仮設支柱の一方の組の
下方に生じた空間に上記ビル構築用クレーンを用いて本
設支柱を設置すると共に、同じく上記仮設の梁組の下方
に形成された空間に梁の建込みを行なう第七の工程と、 上記第三〜第七の各工程を順次繰り返した後仮設の梁組
及び支柱を解体する第八の工程と、 上記第四〜第七の工程で形成した上記梁の下面に他のビ
ル構築用クレーンを配置し、その後の上記工程の間に上
記他のビル構築用クレーンにより地下の掘削と、地下の
各層の梁の建込みを行なう第九の工程とより成ることを
特徴とする地下のある構造物の構築工法。
1. A first step of temporarily installing a beam assembly on the ground, and a second step of arranging a temporary support post vertically through the temporary beam assembly relative to the temporary beam assembly. A third step of lifting up the temporary beam set together with the other set of the temporary support columns relative to one set of the temporary support columns, and the other set of the temporary support columns by raising the temporary beam set. Using the space generated below the building, a building construction crane is placed on the lower surface of the temporary beam assembly, and the building construction crane is used to install the main construction column, and also below the temporary beam assembly. A fourth step of constructing a beam in the space formed in the above, and a fifth step of lowering the other set of the temporary support columns onto the main support column installed above the relative support of the temporary beam set. And one of the temporary support columns is relatively attached to the temporary beam set. The sixth step of raising the temporary beam set relative to the other set of the temporary support columns while raising the temporary beam set to the lower side of the one set of the temporary support columns by raising the temporary beam set. A seventh step of installing the main pillars in the generated space using the building construction crane and also constructing the beams in the space formed below the temporary beam assembly, and the third to After repeating each of the 7th steps in sequence, the 8th step of dismantling the temporary beam assembly and columns, and placing another building construction crane on the underside of the beams formed in the 4th to 7th steps. During the subsequent steps, the underground construction is performed by the other building construction crane and the ninth step of constructing the beams of each underground layer is constructed. Construction method.
【請求項2】 上記仮設の梁組の上部に仮設覆いが形成
されていることを特徴とする請求項1記載の地下のある
構造物の構築工法。
2. The method for constructing an underground structure according to claim 1, wherein a temporary cover is formed on an upper portion of the temporary beam assembly.
【請求項3】 上記仮設の梁組上にその解体用のクレー
ンを取り付けておく工程を更に含むことを特徴とする請
求項1または2記載の地下のある構造物の構築工法。
3. The method for constructing an underground structure according to claim 1, further comprising the step of mounting a crane for disassembling the temporary beam assembly on the temporary beam assembly.
【請求項4】 地上に梁組を仮設する第一の工程と、 仮設支柱を上記仮設の梁組に相対的に上記仮設の梁組を
貫通して上下動自在に併設する第二の工程と、 この仮設支柱の一方の組に相対的に上記仮設の梁組を上
記仮設支柱の他方の組と共にリフトアップする第三の工
程と、 上記仮設の梁組の上昇により上記仮設支柱の他方の組の
下方に生じた空間を利用して上記仮設の梁組の下面にビ
ル構築用クレーンを配置し、このビル構築用クレーンを
用いて本設支柱を設置すると共に、同じく上記仮設の梁
組の下方に形成された空間に梁の建込みを行なう第四の
工程と、 上記梁の下面に他のビル構築用クレーンを配置し、この
ビル構築用クレーンにより地下の掘削と、地下の各層の
梁の建込みを行なう第五の工程と、 上記仮設支柱の他方の組を上記仮設の梁組に相対的に上
記第四の工程で設置された本設支柱上に下降せしめる第
六の工程と、 上記仮設支柱の一方の組を上記仮設の梁組に相対的に上
記仮設の梁組上に上昇せしめると共に、上記仮設の梁組
を上記仮設支柱の他方の組に相対的にリフトアップする
第七の工程と、 上記仮設の梁組の上昇により上記仮設支柱の一方の組の
下方に生じた空間に上記ビル構築用クレーンを用いて本
設支柱を設置すると共に、同じく上記仮設の梁組の下方
に形成された空間に梁の建込みを行なう第八の工程と、 上記第三、第四、第六〜第八の各工程を順次繰り返した
後仮設の梁組及び支柱を解体する第九の工程とより成る
ことを特徴とする地下のある構造物の構築工法。
4. A first step of temporarily installing a beam assembly on the ground, and a second step of arranging a temporary support column vertically through the temporary beam assembly relative to the temporary beam assembly. A third step of lifting up the temporary beam set together with the other set of the temporary support columns relative to one set of the temporary support columns, and the other set of the temporary support columns by raising the temporary beam set. Using the space generated below the building, a building construction crane is placed on the lower surface of the temporary beam assembly, and the building construction crane is used to install the main construction column, and also below the temporary beam assembly. The fourth step of constructing a beam in the space formed in the above, and another building construction crane is placed on the lower surface of the beam, and this building construction crane is used for underground excavation and The fifth step of building and the other set of the temporary support The sixth step of lowering the beam to the main beam installed on the permanent pillar installed in the fourth step, and one set of the temporary pillars relative to the temporary beam group. The seventh step of raising the above-mentioned temporary beam set to the other set of the above-mentioned temporary support columns while raising the above-mentioned temporary beam set, and the one step of one of the above-mentioned temporary support columns by raising the above-mentioned temporary beam set. The eighth step of installing the main pillars in the space generated below by using the building construction crane and also constructing the beams in the space formed below the temporary beam assembly; A construction method for a structure with an underground, comprising a ninth step of disassembling a temporary beam assembly and columns after sequentially repeating the third, fourth, and sixth to eighth steps.
【請求項5】 上記地下の各層の梁の建込みを地下1階
より順次下の階層に向かって行なうことを特徴とする請
求項1,2,3または4記載の地下のある構造物の構築
工法。
5. Construction of an underground structure according to claim 1, 2, 3 or 4, wherein the beams of each layer of the underground are constructed toward the lower layers from the first basement floor in order. Construction method.
JP6059849A 1994-03-07 1994-03-07 Construction method for structure having basement Pending JPH07243221A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6059849A JPH07243221A (en) 1994-03-07 1994-03-07 Construction method for structure having basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6059849A JPH07243221A (en) 1994-03-07 1994-03-07 Construction method for structure having basement

Publications (1)

Publication Number Publication Date
JPH07243221A true JPH07243221A (en) 1995-09-19

Family

ID=13125064

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6059849A Pending JPH07243221A (en) 1994-03-07 1994-03-07 Construction method for structure having basement

Country Status (1)

Country Link
JP (1) JPH07243221A (en)

Similar Documents

Publication Publication Date Title
JP2684155B2 (en) Excavation method used for construction of underground structures
JP3820517B2 (en) Seismic isolation structure of building
CN112681340A (en) Inclined cast support supporting device for large-area deep foundation pit partition construction and construction method thereof
CN108612129B (en) Reverse construction method based on recyclable steel platform
KR0179708B1 (en) Working method for underground structure of a building
JPH0684690B2 (en) Building basement extension method
JPH07243221A (en) Construction method for structure having basement
JP6404508B1 (en) Rebuilding method
JPH06341154A (en) Construction of underground building frame
JP2004176434A (en) Method for constructing structure and underground skeleton
JP2000104257A (en) Installation method for hoisting equipment in constructing structure on slope
JP2536249B2 (en) Lift-down underground structure construction method
JPH0742179A (en) Modified inversion placing construction method
JPH05148837A (en) Slide-down type strut and inverted construction method using the slide-down type strut
JPH0874278A (en) Construction method for large underground space
JPH06101348A (en) Method for constructing tower
JP2936365B2 (en) Underground structure frame construction method
JPH0874279A (en) Construction method for large underground space
JP2634101B2 (en) Building construction method and equipment
JP2696486B2 (en) Building construction method
JP3416759B2 (en) Underground structure frame building equipment
JPH03158574A (en) Construction of new building capable of operating existing structure
JPH06346521A (en) Method for constructing building structure
JPH07103696B2 (en) Building construction method
JPH04363470A (en) Floor construction device