JPH07207928A - Construction facility of structure - Google Patents
Construction facility of structureInfo
- Publication number
- JPH07207928A JPH07207928A JP6004894A JP489494A JPH07207928A JP H07207928 A JPH07207928 A JP H07207928A JP 6004894 A JP6004894 A JP 6004894A JP 489494 A JP489494 A JP 489494A JP H07207928 A JPH07207928 A JP H07207928A
- Authority
- JP
- Japan
- Prior art keywords
- frame
- work
- elevating
- working
- framework
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/24—Safety or protective measures preventing damage to building parts or finishing work during construction
- E04G21/242—Safety or protective measures preventing damage to building parts or finishing work during construction for temporarily covering the whole worksite, e.g. building, trench
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Movable Scaffolding (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、構造物の建設設備に関
するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction facility for structures.
【0002】[0002]
【従来の技術】近年、中層の構造物を建設する場合、天
候に左右されず、かつ機械的に工事を行い得る設備が提
案されている。2. Description of the Related Art In recent years, there has been proposed a facility for constructing a medium-rise structure which is mechanically independent of the weather.
【0003】このような建設設備としては、例えば建設
中の構造物の全体を覆うような作業階を、順次構築され
る構築物の上部に配置し、この作業階の内部に、クレー
ン、各種ロボットなどの作業機械が配置されたものがあ
る。As such a construction facility, for example, a working floor covering the entire structure under construction is arranged above the sequentially constructed structures, and inside the working floor, a crane, various robots, etc. There is one that is equipped with a work machine.
【0004】[0004]
【発明が解決しようとする課題】ところで、上記のよう
な建設設備によると、構造物が大きい場合には、構造物
全体を覆う作業階自体が非常に大型化し、その設置およ
び解体作業が非常に面倒になるという問題があった。By the way, according to the above-mentioned construction equipment, when the structure is large, the working floor itself covering the entire structure becomes very large, and the installation and dismantling work thereof are very difficult. There was a problem of being troublesome.
【0005】そこで、本発明は上記問題を解消し得る構
造物の建設設備を提供することを目的とする。Therefore, an object of the present invention is to provide a construction facility for a structure which can solve the above problems.
【0006】[0006]
【課題を解決するための手段】上記課題を解決するた
め、本発明の第1の手段は、構築物の側部に昇降用架構
を配置するとともに、この昇降用架構に、作業用クレー
ン装置を有する作業用架構を昇降装置により昇降自在に
設け、かつこの作業用架構を、構築物の上部または側部
に配置された案内レール上を走行自在に構成した構造物
の建設設備である。In order to solve the above-mentioned problems, the first means of the present invention is to arrange an elevating frame on a side portion of a structure and to have a working crane device on the elevating frame. It is a construction facility of a structure in which a work frame is provided to be lifted and lowered by an elevating device, and the work frame is configured to be able to travel on guide rails arranged at the top or side of the structure.
【0007】また、上記課題を解決するため、本発明の
第2の手段は、上記第1の手段の構造物の建設設備にお
いて、作業用架構の上面に屋根部を設けたものである。
また、上記課題を解決するため、本発明の第3の手段
は、上記第1の手段の構造物の建設設備において、昇降
装置を、昇降用架構に配置されたラック体と、作業用架
構に設けられて上記ラック体に噛合するピニオンと、こ
のピニオンを回転させる回転駆動装置とから構成したも
のである。In order to solve the above-mentioned problems, a second means of the present invention is to provide a roof portion on the upper surface of the working frame in the construction facility for the structure of the above-mentioned first means.
Further, in order to solve the above-mentioned problems, a third means of the present invention is, in the construction equipment of the structure of the above-mentioned first means, an elevating device is provided in a rack body arranged in an elevating frame and a working frame. The pinion is provided and meshes with the rack body, and a rotation drive device that rotates the pinion.
【0008】さらに、上記課題を解決するため、本発明
の第4の手段は、上記第1の手段の構造物の建設設備に
おいて、昇降装置を、昇降用架構と作業用架構との間に
亘って設けられた油圧シリンダ装置により構成したもの
である。Further, in order to solve the above-mentioned problems, a fourth means of the present invention is, in the construction facility for a structure of the above-mentioned first means, an elevating device is provided between the elevating frame and the working frame. It is configured by a hydraulic cylinder device provided in the above.
【0009】[0009]
【作用】上記の構成によると、構造物を建設する場合、
構築される構築物の側端部に、昇降用架構を立設し、こ
の昇降用架構に作業用架構を、構築物との間で移動自在
に配置しておき、この作業用架構に設けられたクレーン
装置を使用するとともに、作業用架構を上昇させること
により、構造物の各階層部分を、順次、効率良く組み立
てることができる。According to the above construction, when constructing a structure,
A lifting frame is erected at the side end of the structure to be constructed, and a work frame is arranged on the lifting frame so as to be movable between the crane and the crane. By using the device and elevating the work frame, each layer portion of the structure can be sequentially and efficiently assembled.
【0010】したがって、簡単な構成でありながら、構
造物の建設作業の短縮化を図ることができる。Therefore, the construction work of the structure can be shortened while having a simple structure.
【0011】[0011]
【実施例】以下、本発明の第1の実施例を図1〜図5に
基づき説明する。図1〜図4において、1は例えば中層
の構造物2を構築するための建設設備で、例えば構築物
2aの一側部に設けられる(勿論、両側部に設けてもよ
い)。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A first embodiment of the present invention will be described below with reference to FIGS. In FIGS. 1 to 4, reference numeral 1 denotes a construction facility for constructing, for example, the intermediate-layer structure 2, which is provided, for example, on one side of the structure 2a (may be provided on both sides).
【0012】上記建設設備1は、構築物2aの幅と同一
幅(W)を有するとともに所定の長さ(L)を有し、か
つ構造物2の各階層部分の高さごとに順次継ぎ足される
昇降用架構5と、この昇降用架構5の両側面に案内され
て、昇降装置6により昇降自在に設けられるとともに作
業用クレーン装置7が設けられた作業用架構8と、この
作業用架構8の上面に設けられた屋根部8aおよび側壁
部8bとから構成されている。The construction equipment 1 has the same width (W) as the width of the structure 2a, a predetermined length (L), and is sequentially elevated and lowered according to the height of each layer portion of the structure 2. Work frame 5, work frame 8 guided by both side surfaces of the lift frame 5 so as to be lifted and lowered by a lifting device 6 and a work crane device 7, and an upper surface of the work frame 8. And a side wall portion 8b.
【0013】また、上記昇降装置6は、昇降用架構5の
各側面に取り付けられた一対のラック体11と、作業用
架構8側の両側下端部にそれぞれ設けられるとともに上
記ラック体11のラック歯に噛合するピニオン12と、
同じく作業用架構8側に設けられて上記ピニオン12を
回転させる回転駆動装置例えば電動機(図示せず)とか
ら構成されている。The elevating device 6 is provided at a pair of rack bodies 11 attached to each side surface of the elevating frame 5, and at both lower end portions on both sides of the work frame 8 and rack teeth of the rack body 11. A pinion 12 that meshes with
Similarly, it is provided with a rotation drive device, such as an electric motor (not shown), which is provided on the side of the work frame 8 and rotates the pinion 12.
【0014】さらに、上記作業用架構8は、昇降用架構
5側から構築物2a側に移動し得るように構成されてい
る。すなわち、図3に示すように、作業用架構8には走
行車輪15が設けられており、またこの作業用架構8
は、走行車輪15を介して、昇降用架構5の上面に配置
された一対の架構側案内レール(乗り移り用レール)1
6上を走行自在にされるとともに、構築物2aの上面に
も、上記架構側案内レール16と同一の構築物側案内レ
ール(移動用レール)17が一対配置されている。Further, the working frame 8 is constructed so as to be movable from the lifting frame 5 side to the structure 2a side. That is, as shown in FIG. 3, the work frame 8 is provided with traveling wheels 15, and the work frame 8 is also provided.
Is a pair of frame-side guide rails (transfer rails) 1 arranged on the upper surface of the lifting frame 5 via the traveling wheels 15.
6 is free to travel, and a pair of structure-side guide rails (moving rails) 17 identical to the frame-side guide rails 16 are arranged on the upper surface of the structure 2a.
【0015】なお、作業用架構8の下部には、作業用架
構8自体の風などによる横振れを防止するためのガイド
ローラ18が設けられている。したがって、作業用架構
8の走行車輪15を、走行装置(図示しないが、例えば
電動機などにより構成されている)により駆動すれば、
作業用架構8を、昇降用架構5側と構築物2a側とで自
由に移動し得ることになる。A guide roller 18 is provided in the lower part of the work frame 8 to prevent lateral vibration of the work frame 8 itself due to wind or the like. Therefore, if the traveling wheels 15 of the work frame 8 are driven by a traveling device (not shown, it is constituted by, for example, an electric motor),
The work frame 8 can be freely moved between the lifting frame 5 side and the structure 2a side.
【0016】次に、上記の建設設備1を使用して、構造
物2の組み立て作業について説明する。まず、構造物2
の二階部分までを、例えば地上のクレーン車などを使用
して組み立て(通常は、一階部分までが地上にて組み立
てられる)、またこの構造物2の一側端部に対応する位
置に、昇降用架構5を立設し、この昇降用架構5の上面
の架構側案内レール16上に作業用架構8を載置する。
勿論、この作業用架構8には、クレーン装置7および屋
根部8aおよび側壁部8bが設けられている。Next, the work of assembling the structure 2 using the above-mentioned construction equipment 1 will be described. First, structure 2
Up to the second floor of the structure (for example, a crane truck on the ground is used) (usually the first floor is assembled on the ground), and the structure 2 is moved up and down to a position corresponding to one side end. The work frame 5 is erected, and the work frame 8 is placed on the frame-side guide rail 16 on the upper surface of the lifting frame 5.
Of course, the working frame 8 is provided with the crane device 7, the roof 8a, and the side wall 8b.
【0017】この状態で、クレーン装置7を使用して、
図2に示すように、昇降用架構5の側方に載置された組
立部材3を吊り上げるとともに、それぞれの案内レール
16,17を介して、作業用架構8を構築物2a側に走
行させ、所定の階層部分を構築する。In this state, using the crane device 7,
As shown in FIG. 2, the assembling member 3 placed on the side of the elevating frame 5 is lifted, and the working frame 8 is caused to travel to the building 2a side via the respective guide rails 16 and 17, and the predetermined structure is obtained. Build the hierarchy part of.
【0018】そして、例えば三階部分の構築が終われ
ば、図3の仮想線にて示すように、クレーン装置7を使
用して、昇降用架構5を上方に一階層分だけ継ぎ足し、
その後、図5に示すように、ピニオン12を回転させて
作業用架構8を一階層分だけ上昇させる。勿論、継ぎ足
された昇降用架構5の側面には、ラック体11が取り付
けられている。Then, for example, when the construction of the third floor is completed, as shown by the phantom line in FIG. 3, the crane device 7 is used to connect the elevating frame 5 upward by one layer.
Then, as shown in FIG. 5, the pinion 12 is rotated to raise the working frame 8 by one layer. Of course, a rack body 11 is attached to the side surface of the vertically movable frame 5 that has been added.
【0019】この後、上記と同様に、作業用架構8を使
用して、構造物2の四階層部分を構築し、さらにその上
層部分を構築すればよい。そして、構造物2の構築が終
了すれば、上記とは逆の手順により、すなわちクレーン
装置7を使用して、作業用架構8を上層部から順番に、
一階層分づつ、分解して地上に降ろせばよい。なお、最
後の部分については、地上のクレーン車などにより分解
される。After that, similarly to the above, the work frame 8 may be used to construct the four-layer portion of the structure 2 and further construct the upper layer portion thereof. Then, when the construction of the structure 2 is completed, the work frame 8 is arranged in order from the upper layer portion by the procedure reverse to the above, that is, the crane device 7 is used.
It can be disassembled and placed on the ground one by one. The last part is disassembled by a crane truck on the ground.
【0020】このように、構造物2の一側方部に、昇降
用架構5を設けるととももに、この昇降用架構5上に、
構築物2aとの間で移動自在な作業用架構8を設けたの
で、従来のように、構築物2a全体を覆うような大きい
作業階を設ける必要がなく、したがってその組立および
分解作業が極めて容易に行うことができるとともに、作
業行程の短縮化を図ることができる。As described above, the elevating frame 5 is provided on one side portion of the structure 2, and the elevating frame 5 is
Since the work frame 8 that can move freely with the structure 2a is provided, it is not necessary to provide a large work floor that covers the entire structure 2a as in the conventional case, and therefore the assembling and disassembling work can be performed very easily. In addition, it is possible to shorten the work process.
【0021】また、構造物全体を覆うような作業階とは
異なり、構造物の一部を覆うようなものであるため、そ
の設置および分解作業時には、他の作業を中断する必要
がない。Further, unlike a work floor that covers the entire structure, since it covers a part of the structure, it is not necessary to interrupt other works when installing and disassembling the structure.
【0022】また、上述したように、作業用架構8が小
さいため、異なる構造物の構築作業にも、簡単に使用す
ることができる。さらに、作業用架構8には、屋根部8
aおよび側壁部8bが設けられているため、天候のいか
んに拘らず、常に、作業を行うことができる。Further, as described above, since the work frame 8 is small, it can be easily used for construction work of different structures. Further, the work frame 8 has a roof portion 8
Since a and the side wall portion 8b are provided, the work can be always performed regardless of the weather.
【0023】次に、本発明の第2の実施例を図6〜図1
5に基づいて説明する。上記第1の実施例においては、
作業用架構を、構築物の上面を移動させるようにしたも
のについて説明したが、本第2の実施例では、作業用架
構を、構築物の側部を移動させるようにしたものであ
る。この点を除いて、第1の実施例とほぼ同様の構成で
あるため、同一機能を有する構成部品については、その
詳細な説明を省略する。Next, a second embodiment of the present invention will be described with reference to FIGS.
It will be described based on 5. In the first embodiment,
Although the work frame has been described in which the upper surface of the structure is moved, in the second embodiment, the work frame is configured to move the side part of the structure. Except for this point, the configuration is almost the same as that of the first embodiment, and therefore detailed description of components having the same function will be omitted.
【0024】図6および図7に示すように、本第2の実
施例における建設設備21は、構築物22aの両側端部
(図面には、一方しか図示していない)に配置される。
この建設設備21は、昇降用架構25と、この昇降用架
構25に、昇降装置26を介して、作業用架構28が昇
降自在に設けられるとともに、この作業用架構28は、
構築物22a側との間で移動自在に設けられている。As shown in FIGS. 6 and 7, the construction equipment 21 in the second embodiment is arranged at both end portions (only one is shown in the drawings) of the building 22a.
The construction equipment 21 includes an elevating frame 25, and a working frame 28 that is vertically movable on the elevating frame 25 via an elevating device 26.
It is movably provided between the structure 22a side.
【0025】すなわち、昇降用架構25の側壁部には、
レール架台41が水平に設けられるとともに、このレー
ル架台41の上面に架構側案内レール36が設けられ、
さらに構築物22aの側壁部には、構築側案内レール3
7(図10参照)がやはり水平に取り付けられている。That is, on the side wall of the lifting frame 25,
The rail mount 41 is provided horizontally, and the frame-side guide rail 36 is provided on the upper surface of the rail mount 41.
Further, on the side wall of the building 22a, the building side guide rail 3
7 (see FIG. 10) is also mounted horizontally.
【0026】なお、レール架台41は、昇降用架構25
の側壁部25aに、ボルトなどの固定部材42により、
取り外し可能に取り付けられており、またレール架台4
1側には、作業用足場43が一体的に取り付けられてい
る。The rail mount 41 is used for the lifting frame 25.
To the side wall portion 25a of the
Removably attached, also rail mount 4
A work scaffold 43 is integrally attached to the first side.
【0027】また、本第2の実施例における作業用架構
28の側壁部としては、風雨除け用のカーテン28b
が、屋根部28aから垂下されている。なお、図6およ
び図7中、31はラック体、32はピニオン、35は走
行車輪である。Further, as the side wall portion of the work frame 28 in the second embodiment, the wind and rain protection curtain 28b is used.
Is hung from the roof portion 28a. 6 and 7, 31 is a rack body, 32 is a pinion, and 35 is a traveling wheel.
【0028】次に、本第2の実施例における建設設備2
1を使用して、構造物22を構築する手順を、図8〜図
15に基づき説明する。まず、図8に示すように、構築
される構造物22の両側端部位置において、例えばクレ
ーン車44により、昇降用架構25を立設するととも
に、図9に示すように、この昇降用架構25の両側部
に、作業用架構28を組み立てて支持させる。Next, the construction equipment 2 in the second embodiment.
A procedure for constructing the structure 22 using the No. 1 will be described with reference to FIGS. First, as shown in FIG. 8, the elevating frame 25 is erected by the crane trucks 44 at both side end positions of the structure 22 to be constructed, and as shown in FIG. The work frame 28 is assembled and supported on both sides of the work frame 28.
【0029】次に、図10に示すように、建設される構
造物22の一階層部分の構築物22aを、地上のクレー
ン車44にて、両昇降用架構25間に構築するととも
に、この一階層部分の側面に、構築物側案内レール37
を取り付ける。勿論、この場合も、昇降用架構25側と
同じように、レール架台(図示せず)を介して取り付け
られる。Next, as shown in FIG. 10, the structure 22a, which is one layer of the structure 22 to be constructed, is constructed between the two elevating frames 25 by the ground crane truck 44, and this one layer is constructed. On the side of the part, the guide rail 37 on the structure side
Attach. Of course, in this case as well, it is mounted via a rail mount (not shown) in the same manner as the lifting frame 25 side.
【0030】そして、図11に示すように、作業用架構
28に設けられたクレーン装置(例えば、ガーダクレー
ン)27を使用して、例えば構造物22の二階および三
階層部分の構築物22aを構築する。Then, as shown in FIG. 11, for example, a crane device (for example, a girder crane) 27 provided on the work frame 28 is used to construct a structure 22a of the second and third floors of the structure 22, for example. .
【0031】次に、図12に示すように、昇降用架構2
5を、作業用架構28により、上方に所定階層分だけ継
ぎ足すとともに、構築物22aの一階層部分に取り付け
られた構築物側案内レール37を、三階層部分の構築物
22a側に移す(盛り替え作業を行う)。Next, as shown in FIG. 12, the lifting frame 2
5 is added upward by a predetermined level by the work frame 28, and the structure side guide rail 37 attached to one layer part of the structure 22a is moved to the structure 22a side of the three layer part (refilling work is performed. Do).
【0032】このような手順を繰り替えすことにより、
図13に示すように、所定の階層の構造物22を構築す
る。その後、図14に示すように、昇降用架構25を、
作業用架構28のクレーン装置27を使用して、順次、
分解し、そして図15に示すように、最後の部分を、地
上のクレーン車44にて分解する。By repeating such a procedure,
As shown in FIG. 13, the structure 22 of a predetermined hierarchy is constructed. After that, as shown in FIG.
Using the crane device 27 of the work frame 28,
Disassemble, and disassemble the last portion with a mobile crane 44 on the ground, as shown in FIG.
【0033】このように、作業用架構28の移動用の案
内レールを、昇降用架構25および構造物22の構築物
22aの側面に設けた場合でも、上記第1の実施例と同
様の効果が得られる。Thus, even when the guide rails for moving the work frame 28 are provided on the side surfaces of the elevating frame 25 and the structure 22a of the structure 22, the same effect as that of the first embodiment can be obtained. To be
【0034】ところで、上記各実施例においては、作業
用架構の昇降装置をラック・ピニオン機構を使用したも
のとして説明したが、例えば油圧シリンダ装置を複数個
使用することにより、尺取り虫のように、作業用架構を
昇降用架構に対して、上昇させることができる。By the way, in each of the above-mentioned embodiments, the elevating device for the working frame has been described as the one using the rack and pinion mechanism. However, by using a plurality of hydraulic cylinder devices, the work can be performed like a scale insect. The frame can be raised with respect to the lifting frame.
【0035】例えば、複数個の油圧シリンダ装置を2群
に分け、一方の群の油圧シリンダ装置により、作業用架
構を押し上げた状態で支持し、他方の群の油圧シリンダ
装置のロッド部を退入させた状態で、この油圧シリンダ
装置により作業用架構と昇降用架構とを互いに連結す
る。For example, a plurality of hydraulic cylinder devices are divided into two groups, one of the hydraulic cylinder devices supports the work frame in a pushed-up state, and the other hydraulic cylinder device rod portion is retracted. In this state, the work frame and the elevating frame are connected to each other by this hydraulic cylinder device.
【0036】次に、上記一方の群の油圧シリンダ装置の
ロッド部を昇降用架構側から離脱させておき、他方の群
の油圧シリンダ装置のロッド部を突出させれば、作業用
架構が昇降用架構に対して上昇させられる。Next, if the rod portion of the hydraulic cylinder device of the one group is detached from the lifting frame side and the rod portion of the hydraulic cylinder device of the other group is projected, the working frame is lifted. Raised against the frame.
【0037】この手順を、繰り返すことにより、油圧シ
リンダ装置を使用して作業用架構を上昇させることがで
きる。また、上記第1の実施例において、構築物の上面
に、構築物側案内レールを設けたが、構築物自体の梁材
の上面を、案内レールとして利用することもできる。By repeating this procedure, the working frame can be raised by using the hydraulic cylinder device. Further, in the first embodiment described above, the building-side guide rail is provided on the upper surface of the building, but the upper surface of the beam member of the building itself can be used as the guiding rail.
【0038】さらに、上記各実施例における昇降用架構
内に、人荷用エレベータなどを設置することにより、作
業用スペースとしても利用することができる。Furthermore, by installing an elevator for a person's load in the lifting frame in each of the above embodiments, it can be used as a working space.
【0039】[0039]
【発明の効果】以上のように本発明の構成によると、構
築物の側部に、昇降用架構を設けるととももに、この昇
降用架構上に、構築物との間で移動自在な作業用架構を
設けたので、従来のように、構築物全体を覆うような大
きい作業階を設ける必要がなく、したがってその組立お
よび分解作業が極めて容易に行うことができるととも
に、作業行程の短縮化を図ることができる。As described above, according to the structure of the present invention, the elevating frame is provided on the side portion of the building, and the working frame movable on the elevating frame is movable with the structure. Since there is no need to provide a large work floor that covers the entire structure as in the conventional case, the assembly and disassembly work can be performed very easily, and the work process can be shortened. it can.
【0040】また、作業用架構に、屋根部を設けること
により、天候のいかんに拘らず、常に、作業を行うこと
ができる。Further, by providing the roof portion on the work frame, work can be always performed regardless of the weather.
【図1】本発明の第1の実施例における建設設備の概略
構成を示す斜視図である。FIG. 1 is a perspective view showing a schematic configuration of construction equipment according to a first embodiment of the present invention.
【図2】同第1の実施例における建設設備の側面図であ
る。FIG. 2 is a side view of the construction equipment according to the first embodiment.
【図3】図2のA−A矢視図である。FIG. 3 is a view taken along the line AA of FIG.
【図4】図2のB−B矢視図である。FIG. 4 is a view taken along the line BB of FIG.
【図5】同第1の実施例における作業手順を説明する建
設設備の正面図である。FIG. 5 is a front view of the construction equipment for explaining the work procedure in the first embodiment.
【図6】本発明の第2の実施例における建設設備の概略
構成を示す要部斜視図である。FIG. 6 is a perspective view of a main part showing a schematic configuration of construction equipment in a second embodiment of the present invention.
【図7】同第2の実施例における建設設備の要部正面図
である。FIG. 7 is a front view of a main part of the construction equipment according to the second embodiment.
【図8】同第2の実施例の建設設備による構造物の組立
手順を示す側面図である。FIG. 8 is a side view showing a procedure for assembling a structure by the construction equipment according to the second embodiment.
【図9】同第2の実施例の建設設備による構造物の組立
手順を示す側面図である。FIG. 9 is a side view showing a procedure for assembling a structure by the construction equipment according to the second embodiment.
【図10】同第2の実施例の建設設備による構造物の組
立手順を示す正面図である。FIG. 10 is a front view showing a procedure for assembling a structure by the construction equipment according to the second embodiment.
【図11】同第2の実施例の建設設備による構造物の組
立手順を示す正面図である。FIG. 11 is a front view showing the procedure for assembling a structure by the construction equipment of the second embodiment.
【図12】同第2の実施例の建設設備による構造物の組
立手順を示す正面図である。FIG. 12 is a front view showing a procedure for assembling a structure by the construction equipment according to the second embodiment.
【図13】同第2の実施例の建設設備による構造物の組
立手順を示す正面図である。FIG. 13 is a front view showing the procedure for assembling a structure by the construction equipment according to the second embodiment.
【図14】同第2の実施例における建設設備の分解手順
を示す正面図である。FIG. 14 is a front view showing a disassembling procedure of the construction equipment in the second embodiment.
【図15】同第2の実施例における建設設備の分解手順
を示す正面図である。FIG. 15 is a front view showing the disassembling procedure of the construction equipment in the second embodiment.
1 建設設備 2 構造物 2a 構築物 5 昇降用架構 6 昇降装置 7 クレーン装置 8 作業用架構 8a 屋根部 8b 側壁部 11 ラック体 12 ピニオン 15 走行車輪 16 架構側案内レール 17 構築物側案内レール 21 建設設備 22 構造物 22a 構築物 25 昇降用架構 26 昇降装置 27 クレーン装置 28 作業用架構 28a 屋根部 28b カーテン 31 ラック体 32 ピニオン 36 架構側案内レール 37 構築物側案内レール 1 Construction Equipment 2 Structure 2a Structure 5 Lifting Frame 6 Lifting Equipment 7 Crane Device 8 Working Frame 8a Roof 8b Side Wall 11 Rack Body 12 Pinion 15 Traveling Wheel 16 Frame Side Guide Rail 17 Structure Side Guide Rail 21 Construction Equipment 22 Structure 22a Structure 25 Elevating frame 26 Elevating device 27 Crane device 28 Working frame 28a Roof 28b Curtain 31 Rack body 32 Pinion 36 Frame side guide rail 37 Structure side guide rail
Claims (4)
もに、この昇降用架構に、作業用クレーン装置を有する
作業用架構を昇降装置により昇降自在に設け、かつこの
作業用架構を、構築物の上部または側部に配置された案
内レール上を走行自在に構成したことを特徴とする構造
物の建設設備。1. An elevating frame is arranged on a side of a building, and a working frame having a work crane device is provided on the elevating frame so as to be vertically movable by the elevating device, and the working frame is constructed. A construction facility for a structure, characterized in that the structure is constructed so that it can travel freely on guide rails arranged on the upper part or the side part of
特徴とする請求項1記載の構造物の建設設備。2. The construction equipment for a structure according to claim 1, wherein a roof portion is provided on an upper surface of the work frame.
ク体と、作業用架構に設けられて上記ラック体に噛合す
るピニオンと、このピニオンを回転させる回転駆動装置
とから構成したことを特徴とする請求項1記載の構造物
の建設設備。3. An elevating device comprises a rack body arranged on an elevating frame, a pinion provided on a working frame and meshing with the rack body, and a rotary drive device for rotating the pinion. The construction equipment for the structure according to claim 1.
亘って設けられた油圧シリンダ装置により構成したこと
を特徴とする請求項1記載の構造物の建設設備。4. The construction equipment for a structure according to claim 1, wherein the elevating device comprises a hydraulic cylinder device provided over the elevating frame and the working frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6004894A JPH07207928A (en) | 1994-01-21 | 1994-01-21 | Construction facility of structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6004894A JPH07207928A (en) | 1994-01-21 | 1994-01-21 | Construction facility of structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH07207928A true JPH07207928A (en) | 1995-08-08 |
Family
ID=11596386
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6004894A Pending JPH07207928A (en) | 1994-01-21 | 1994-01-21 | Construction facility of structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH07207928A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104328903A (en) * | 2014-11-06 | 2015-02-04 | 上海建工一建集团有限公司 | Flame-retardant assembled integral elevating scaffold and disassembly and assembly methods thereof |
WO2021156625A1 (en) * | 2020-02-06 | 2021-08-12 | Bam Nuttall Limited | Modular structure for providing on-site protection |
-
1994
- 1994-01-21 JP JP6004894A patent/JPH07207928A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104328903A (en) * | 2014-11-06 | 2015-02-04 | 上海建工一建集团有限公司 | Flame-retardant assembled integral elevating scaffold and disassembly and assembly methods thereof |
WO2021156625A1 (en) * | 2020-02-06 | 2021-08-12 | Bam Nuttall Limited | Modular structure for providing on-site protection |
EP4100595A1 (en) * | 2020-02-06 | 2022-12-14 | Bam Nuttall Limited | Modular structure for providing on-site protection |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2019015243A1 (en) | Shaft module splicing system and splicing method therefor | |
JPH055987B2 (en) | ||
JP2971042B2 (en) | Girder transporter and girder transport method | |
JPH07207928A (en) | Construction facility of structure | |
JP4067096B2 (en) | Electric balance arm device for outdoor wall work | |
KR20040104223A (en) | Scaffolding having vertically moving workplace | |
JP3142819B2 (en) | How to build a roof frame | |
JP2612974B2 (en) | Mounting method of outer wall PC members | |
JP2597947B2 (en) | Scaffolding equipment | |
CN113513149A (en) | Attached type protection platform | |
JPH092780A (en) | Jib-type traveling crane provided with jack up device | |
JPH05133016A (en) | Peripheral supporting self-rising type building engineering method | |
JPH10245994A (en) | Temporary curing body | |
JP3192543B2 (en) | Building demolition method | |
JPH06272371A (en) | Work equipment for building external facing | |
JP2592980B2 (en) | Construction method of steel frame material for high-rise structure | |
JPH09137506A (en) | Construction method of building | |
JP3055878B2 (en) | Mobile scaffolding for curved roofs | |
JPH0745778B2 (en) | Lifting method and device for lotus stand | |
JPH026906B2 (en) | ||
JPH06167122A (en) | Temporary roof device | |
JPH0791078A (en) | Lifting type opening roof for mounting | |
JPH086461B2 (en) | Climbing all-weather temporary roof | |
JPH028098B2 (en) | ||
JP2002349077A (en) | Method for repairing building |