JPH07129667A - Work progress control method for job - Google Patents
Work progress control method for jobInfo
- Publication number
- JPH07129667A JPH07129667A JP27680093A JP27680093A JPH07129667A JP H07129667 A JPH07129667 A JP H07129667A JP 27680093 A JP27680093 A JP 27680093A JP 27680093 A JP27680093 A JP 27680093A JP H07129667 A JPH07129667 A JP H07129667A
- Authority
- JP
- Japan
- Prior art keywords
- work
- data
- unit
- added
- project
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、商品開発や生産のプ
ロジェクトなどの業務を管理するときに用いられる業務
の工程管理方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a business process management method used for managing business such as product development and production projects.
【0002】[0002]
【従来の技術】商品開発や生産などのプロジェクトをP
ERT(Program Evaluation and Review Technique)
で管理し、このPERTをコンピュータを用いて処理す
る。この場合、プロジェクトは、複数の業務で構成され
る。各業務には、この業務に係る日程や人員などの情報
が付加される。これらの情報がコンピュータに入力され
ると、コンピュータは、付加された情報に基づいて、業
務の工程表などを画面上に表示する。[Prior Art] P for projects such as product development and production
ERT (Program Evaluation and Review Technique)
The PERT is processed using a computer. In this case, the project consists of multiple tasks. Information such as schedules and personnel related to this work is added to each work. When these pieces of information are input to the computer, the computer displays a work process chart on the screen based on the added information.
【0003】この種の工程管理方法としては、特開昭6
4ー29965号公報に記載されているようなものがあ
る。As a process control method of this kind, Japanese Patent Laid-Open No.
There is one as described in JP-A-4-29965.
【0004】[0004]
【発明が解決しようとする課題】しかし、処理するプロ
ジェクトの業務は、それぞれ別に処理されている。この
ために、プロジェクト全体の業務の進捗状況などの把握
が難しく、プロジェクトの、どの業務の処理を重点的に
行う必要があるかなどの判断が迅速にできない。However, the work of the project to be processed is processed separately. For this reason, it is difficult to grasp the progress status of the work of the entire project, and it is not possible to quickly determine which work of the project needs to be focused on.
【0005】この発明の目的は、このような欠点を除
き、プロジェクトの全体の進捗状況を出力できる業務の
工程管理方法を提供することにある。An object of the present invention is to provide a work process management method capable of outputting the overall progress status of a project, excluding such drawbacks.
【0006】[0006]
【課題を解決するための手段】その目的を達成するた
め、請求項1の発明は、複数の業務で構成されると共に
各業務が複数の作業単位で構成されるプロジェクトであ
って、各作業単位には少なくとも作業順序を示すデータ
が付加されたプロジェクトを管理する業務の工程管理方
法において、作業単位の作業期間のデータが入力される
と、この入力データをこの作業単位のデータに付加する
第1処理過程と、1つの画面に2つ以上の業務を表示す
ると共に、この画面上に、第1処理過程で付加された、
作業単位の作業期間を時系列的に、かつ業務毎に表示す
る第2処理過程とを含む。In order to achieve the object, the invention of claim 1 is a project which is composed of a plurality of works and each work is composed of a plurality of work units. In a process management method for managing a project to which at least data indicating a work order is added, when data of a work period of a work unit is input, the input data is added to the data of the work unit. The process and two or more tasks are displayed on one screen, and the process added on the screen in the first process,
A second processing step of displaying the work period of the work unit in time series and for each work.
【0007】請求項2の発明は、複数の業務で構成され
ると共に各業務が複数の作業単位で構成されるプロジェ
クトであって、各作業単位には少なくとも作業順序を示
すデータが付加されたプロジェクトを管理する業務の工
程管理方法において、作業単位の作業期間のデータと作
業工数のデータとの少なくとも1つが入力されると、入
力データをこの作業単位のデータに付加する第1処理過
程と、1つの画面に2つ以上の業務を表示すると共に、
この画面上に、第1処理過程で付加された、作業単位の
作業期間を時系列的に、かつ業務毎に表示する第2処理
過程と、第1処理過程で付加された作業工数のデータに
基づいて、第2処理過程で時系列的に表示されたそれぞ
れの作業単位の、同じ時間での作業工数をそれぞれ累積
して表示する第3処理過程とを含む。The invention of claim 2 is a project which is composed of a plurality of jobs and each job is composed of a plurality of work units, wherein each work unit is added with at least data indicating a work order. In a process control method for managing work, when at least one of work period data and work man-hour data of a work unit is input, a first processing step of adding the input data to the work unit data, and In addition to displaying two or more jobs on one screen,
On this screen, the second process step that displays the work period of the work unit added in the first process step in time series and for each job, and the data of the work man-hour added in the first process step are displayed. Based on the above, a third processing step of accumulating and displaying the work man-hours of the respective work units displayed in time series in the second processing step at the same time is included.
【0008】[0008]
【作用】請求項1の発明では、作業単位の作業期間のデ
ータが入力される。第1処理過程により、入力されたデ
ータは、作業単位のデータに付加される。According to the first aspect of the invention, the data of the work period of the work unit is input. In the first processing step, the input data is added to the work unit data.
【0009】第2処理過程では、1つの画面に2つ以上
の業務が表示される。同時に、この画面上に、第1処理
過程で付加された、作業単位の作業期間が、時系列的
に、かつ、業務毎に表示される。In the second processing step, two or more jobs are displayed on one screen. At the same time, the work period of the work unit added in the first process is displayed on this screen in time series and for each work.
【0010】請求項2の発明では、作業単位の作業期間
のデータと作業工数のデータとの少なくとも1つが入力
される。第1処理過程により、入力データは、この作業
単位のデータに付加される。According to the second aspect of the present invention, at least one of the work period data and the work man-hour data of the work unit is input. The input data is added to the data of this work unit by the first processing step.
【0011】第2処理過程では、1つの画面に2つ以上
の業務が表示される。同時に、この画面上に、第1処理
過程で付加された、作業単位の作業期間が、時系列的
に、かつ、業務毎に表示される。In the second processing step, two or more jobs are displayed on one screen. At the same time, the work period of the work unit added in the first process is displayed on this screen in time series and for each work.
【0012】さらに、第3処理過程により、第1処理過
程で付加された作業工数のデータに基づいて、第2処理
過程で時系列的に表示されたそれぞれの作業単位の、同
じ時間での作業工数が、それぞれ累積して表示される。Further, in the third processing step, based on the work man-hour data added in the first processing step, the respective work units displayed in time series in the second processing step are operated at the same time. The man-hours are accumulated and displayed.
【0013】[0013]
【実施例】次に、この発明の実施例を、図面を用いて説
明する。Embodiments of the present invention will now be described with reference to the drawings.
【0014】図1は、この発明の一実施例を示すフロー
チャートであり、図2は、この発明を実施するための装
置のブロック図である。FIG. 1 is a flow chart showing an embodiment of the present invention, and FIG. 2 is a block diagram of an apparatus for carrying out the present invention.
【0015】この実施例で処理されるプロジェクトは、
複数の業務で構成され、さらに、各業務は、複数の作業
単位で構成される。この実施例では、まず、プロジェク
トの業務のデータが、作業者により入力部1から入力さ
れると(ステップS1)、制御部2が入力データを、P
ERTのネットワークとして記憶部3に登録する(ステ
ップS2)。この後、各業務対象の作業単位のデータ、
つまり作業単位の期間と工数を示すデータが入力部1に
より入力されると(ステップS3)、制御部2は、入力
されたデータを業務に対応させて記憶部3に登録する
(ステップS4)。The project processed in this embodiment is
It is composed of a plurality of jobs, and each job is composed of a plurality of work units. In this embodiment, first, when the work data of the project is input by the worker from the input unit 1 (step S1), the control unit 2 sets the input data to P
It is registered in the storage unit 3 as an ERT network (step S2). After this, the data of the work unit of each work target,
That is, when the data indicating the period of the work unit and the man-hours are input by the input unit 1 (step S3), the control unit 2 registers the input data in the storage unit 3 in association with the work (step S4).
【0016】これらのデータの入力が終了すると、制御
部2は、図3に示すような図を、表示部4の画面上に表
示させる(ステップS5)。この画面上では、縦軸が業
務A,B,Cを表し、横軸が、「9月」、「10月」、
「11月」のような期間を表す。When the input of these data is completed, the control unit 2 displays the diagram shown in FIG. 3 on the screen of the display unit 4 (step S5). On this screen, the vertical axis represents work A, B, and C, and the horizontal axis represents "September", "October",
It represents a period such as "November".
【0017】制御部2は、ステップS5で表示させた画
面上に、ステップS3で入力された作業単位の期間のデ
ータを描く(ステップS6)。このとき、制御部2は、
業務Aの作業単位a1,a2,a3の横軸方向の長さ
を、作業期間の長さに対応させて描く。業務Bの作業単
位b1,b2,b3や業務Cの作業単位c1,c2も同
様にして描く。The control unit 2 draws the data of the period of the work unit input in step S3 on the screen displayed in step S5 (step S6). At this time, the control unit 2
The lengths of the work units a1, a2, and a3 of the work A in the horizontal axis direction are drawn in correspondence with the length of the work period. The work units b1, b2, b3 of the work B and the work units c1, c2 of the work C are also drawn in the same manner.
【0018】ステップS6が終了すると、作業単位a1
〜a3,b1〜b3,c1,c2に付加されている、ス
テップS3で入力された工数のデータを期間で積算した
図、つまり、作業単位の山積み図を描く(ステップS
7)。このとき、山積み図に、例えば体制人員能力Hを
あらかじめ入力しておけば、体制人員能力Hを越えた部
分101が視覚的に描かれる。When step S6 ends, work unit a1
To a3, b1 to b3, c1, c2, a diagram in which the data of the man-hours input in step S3 is integrated in a period, that is, a stacking diagram of work units is drawn (step S
7). At this time, if the systematic personnel ability H is input in advance in the stacking diagram, a portion 101 that exceeds the systematic personnel ability H is visually drawn.
【0019】ステップS7の後、ステップS3で入力さ
れた、作業単位の期間と工数を示すデータに変更、つま
り、作業単位の期間の短縮、延長、移動、追加、削除が
あれば、制御部2は、処理をステップS3に戻す(ステ
ップS8)。また、ステップS8でデータに変更が無け
れば、表示部4に描かれている山積み図を、例えば出力
部5から打ち出す(ステップS9)。After step S7, if the data indicating the period and man-hours of the work unit input in step S3 is changed, that is, the work unit period is shortened, extended, moved, added or deleted, the control unit 2 Returns the process to step S3 (step S8). If there is no change in the data in step S8, the stacking diagram drawn on the display unit 4 is output from, for example, the output unit 5 (step S9).
【0020】このように、この実施例により、プロジェ
クトの各業務の状態を全体的に表示することができる。
これにより、使用者は、各業務の進捗状態や、山積み図
を視覚的に把握でき、作業計画の作成が簡単化される。As described above, according to this embodiment, the status of each work of the project can be displayed as a whole.
As a result, the user can visually understand the progress status of each work and the stacking diagram, and the work plan can be easily created.
【0021】また、ステップS8でデータを変更するこ
とにより、作業単位の表示の変更や山積み図の変更が可
能になる。これにより、利用者は、プロジェクトを達成
可能にする計画を容易に作成できる。Further, by changing the data in step S8, it becomes possible to change the display of the work unit and the stacking diagram. This allows the user to easily create a plan that makes the project achievable.
【0022】なお、この実施例では、作業単位a1〜a
3,b1〜b3,c1,c2を表す長方形の幅、つまり
縦軸方向の長さを一定にしたが、特にこれに限定されな
い。例えば、作業単位a1〜a3,b1〜b3,c1,
c2に付加されている工数に比例して、作業単位a1〜
a3,b1〜b3,c1,c2の幅を変えてもよい。In this embodiment, the work units a1 to a are
Although the widths of the rectangles representing 3,3 b1 to b3, c1 and c2, that is, the lengths in the vertical axis direction are constant, the present invention is not particularly limited to this. For example, work units a1 to a3, b1 to b3, c1,
In proportion to the man-hours added to c2, work units a1 to
The widths of a3, b1 to b3, c1 and c2 may be changed.
【0023】[0023]
【発明の効果】以上、説明したように、請求項1に記載
された発明は、同じプロジェクトの中で、複数の業務を
1つの画面上に同時に出力する。つまり、プロジェクト
全体の進捗状況を表示する。これにより、例えばプロジ
ェクトの管理者による、各業務の進捗状況や力を注ぐべ
き業務の迅速な判断を可能にする。As described above, according to the invention described in claim 1, a plurality of jobs are simultaneously output on one screen in the same project. That is, the progress status of the entire project is displayed. This enables, for example, the project manager to quickly determine the progress status of each work and the work to be focused on.
【0024】請求項2に記載された発明は、複数の業務
を表示した画面上に、同じ時間での、各作業単位の作業
工程を累積的に表示する。つまり、画面上には、工数の
山積み図が表示される。これにより、プロジェクト全体
の業務の進捗状況を詳細に表示するので、例えばプロジ
ェクトの管理者は、各業務の進捗状況を直ちに把握でき
る。According to the second aspect of the present invention, the work process of each work unit at the same time is cumulatively displayed on the screen displaying a plurality of jobs. That is, a stack of man-hours is displayed on the screen. As a result, since the progress status of the work of the entire project is displayed in detail, for example, the project manager can immediately grasp the progress status of each work.
【図1】この発明の一実施例を示すフローチャートであ
る。FIG. 1 is a flow chart showing an embodiment of the present invention.
【図2】この発明を実施するための装置の一例を示すブ
ロック図である。FIG. 2 is a block diagram showing an example of an apparatus for carrying out the present invention.
【図3】この実施例の処理で作成される、工数を表す図
である。FIG. 3 is a diagram showing man-hours created by the processing of this embodiment.
ステップS1〜ステップS6 処理ステップ Steps S1 to S6 Processing steps
Claims (2)
複数の作業単位で構成されるプロジェクトであって、各
作業単位には少なくとも作業順序を示すデータが付加さ
れたプロジェクトを管理する業務の工程管理方法におい
て、 作業単位の作業期間のデータが入力されると、この入力
データをこの作業単位のデータに付加する第1処理過程
と、 1つの画面に2つ以上の業務を表示すると共に、この画
面上に、前記第1処理過程で付加された、作業単位の作
業期間を時系列的に、かつ業務毎に表示する第2処理過
程とを含むことを特徴とする業務の工程管理方法。1. A project for managing a project which is composed of a plurality of jobs and each job is composed of a plurality of work units, and in which each work unit is added with at least data indicating a work order In the process control method, when the data of the work period of the work unit is input, the first processing step of adding the input data to the data of this work unit and displaying two or more jobs on one screen, A work process management method comprising: on this screen, a second process process that displays the work period of the work unit added in the first process process in time series and for each work.
複数の作業単位で構成されるプロジェクトであって、各
作業単位には少なくとも作業順序を示すデータが付加さ
れたプロジェクトを管理する業務の工程管理方法におい
て、 作業単位の作業期間のデータと作業工数のデータとの少
なくとも1つが入力されると、入力データをこの作業単
位のデータに付加する第1処理過程と、 1つの画面に2つ以上の業務を表示すると共に、この画
面上に、前記第1処理過程で付加された、作業単位の作
業期間を時系列的に、かつ業務毎に表示する第2処理過
程と、 前記第1処理過程で付加された作業工数のデータに基づ
いて、前記第2処理過程で時系列的に表示されたそれぞ
れの作業単位の、同じ時間での作業工数をそれぞれ累積
して表示する第3処理過程とを含むことを特徴とする業
務の工程管理方法。2. A project for managing a project that is composed of a plurality of jobs and each job is composed of a plurality of work units, and in which each work unit is added with at least data indicating a work order In the process control method, when at least one of the work period data and the work man-hour data of the work unit is input, the first processing step of adding the input data to the work unit data and two in one screen A second processing step of displaying the above-mentioned work and displaying the work period of the work unit added in the first processing step on this screen in time series and for each work; A third process for accumulating and displaying the work man-hours at the same time of each work unit displayed in time series in the second processing process based on the work man-hour data added in the process. A business process management method comprising: a process.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27680093A JPH07129667A (en) | 1993-11-05 | 1993-11-05 | Work progress control method for job |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27680093A JPH07129667A (en) | 1993-11-05 | 1993-11-05 | Work progress control method for job |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH07129667A true JPH07129667A (en) | 1995-05-19 |
Family
ID=17574562
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP27680093A Pending JPH07129667A (en) | 1993-11-05 | 1993-11-05 | Work progress control method for job |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH07129667A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7428511B2 (en) | 1997-03-31 | 2008-09-23 | Hitachi, Ltd. | Electronic business transaction system |
-
1993
- 1993-11-05 JP JP27680093A patent/JPH07129667A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7428511B2 (en) | 1997-03-31 | 2008-09-23 | Hitachi, Ltd. | Electronic business transaction system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2007130180A1 (en) | Visual workflow process notation and layout | |
JP2008299762A (en) | Production management program | |
JPH1196222A (en) | Method for managing process progress and its device | |
JPH07129667A (en) | Work progress control method for job | |
JP2002244716A (en) | Line capacity evaluation system | |
JP4133680B2 (en) | Holiday acquisition status management device | |
JPH06348720A (en) | Production development control display device | |
JP6875317B2 (en) | Process chart creation system and its creation method | |
JPH04347769A (en) | Process management device | |
JPH08212273A (en) | Suporting device for controlling product cost | |
JP2000172759A (en) | Process control system | |
JPH03239460A (en) | Production completion schedule calculating method and device | |
JPH01244607A (en) | Apparatus for displaying in-process of semiconductor device group | |
JPH0214358A (en) | Method and device for supporting schedule planning | |
JPH07296062A (en) | Method for supporting decision of staff arrangement | |
JPH06332909A (en) | Plan managing system | |
JPH0966442A (en) | Process control device | |
JP2004171163A (en) | Resource management device, resource management method, program and recording medium | |
CN117632669A (en) | Signboard data generation method and device | |
JPH01309146A (en) | Process monitor device and production of network chart used for the same | |
JPH06176086A (en) | Drawing processing method | |
JP2004213148A (en) | Plant monitor control system | |
JPH0877248A (en) | Material assortment support and management system | |
JPH05174027A (en) | Project plan back-up device | |
JPH04311258A (en) | Production scheduling device |