JPH0214358A - Method and device for supporting schedule planning - Google Patents

Method and device for supporting schedule planning

Info

Publication number
JPH0214358A
JPH0214358A JP63162540A JP16254088A JPH0214358A JP H0214358 A JPH0214358 A JP H0214358A JP 63162540 A JP63162540 A JP 63162540A JP 16254088 A JP16254088 A JP 16254088A JP H0214358 A JPH0214358 A JP H0214358A
Authority
JP
Japan
Prior art keywords
work
data
schedule
equipment
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP63162540A
Other languages
Japanese (ja)
Inventor
Toru Mitsuda
満田 透
Hisanori Nonaka
久典 野中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP63162540A priority Critical patent/JPH0214358A/en
Publication of JPH0214358A publication Critical patent/JPH0214358A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Automatic Assembly (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • Control By Computers (AREA)

Abstract

PURPOSE:To easily judge the possibility of carrying-in to a work, which next continues, and the securing of an installation work space only with observing a lay-out drawing by uniting a work proceeding condition at a certain time and the lay-out drawing and expressing them. CONSTITUTION:The attribute data of a constituting element for construction such as the body and equipment of a storage 5, the work data of a storage 6 and the schedule planning data of a storage 7 area read and stored to an intermediate data storing part 2c. In a processing step 2c, a schedule plan is displayed on a display screen and an arbitrary period is designated for the schedule plan. From the designated period and schedule planning data, work, which is finished in the plan up to the designated period, is retrieved. The type of the work and the name of the constituting element, which goes to be the subject of the work are retrieved and the arrangement data of the constituting element are retrieved from lay-out drawing data. As a result, the lay-out drawing data are prepared to show the work proceeding condition of each constituting element and displayed on the display picture.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、演算処理装置による日程計画支援方式に係り
、特に、日程計画を搬入可能性や据付作業スペースの確
保の観点から評価するための支援方式に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a schedule planning support method using an arithmetic processing device, and in particular, to a method for evaluating schedule planning from the viewpoint of transportability and securing of installation work space. Regarding support methods.

〔従来の技術〕[Conventional technology]

日程計画を計算機化する技術として特開昭62−152
066号、特開昭62−43768号、特開昭62−9
7051号、特開昭62−38966号公報がある。
Japanese Patent Publication No. 62-152 as a technology for computerizing schedule planning
No. 066, JP-A-62-43768, JP-A-62-9
No. 7051 and Japanese Unexamined Patent Publication No. 62-38966.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

これらは、日程計画やスケジュールの作成を支援するこ
と、あるいは、計画の進行状況を管理することを目的と
している。これらの従来例をプラントなどの構造物の建
設作業を対象とした日程計画に適用した場合でも、まだ
、次のような課題が残る。
These are intended to support the creation of schedules and schedules, or to manage the progress of plans. Even when these conventional examples are applied to schedule planning for construction work of structures such as plants, the following problems still remain.

プラントの建設作業では、躯体9機器の搬入可能性や据
付作業スペースの確保などを考慮しながら日程計画を作
成する必要がある。このため、計画作成者は、作業デー
タだけでなく、プラントのレイアウトデータも用いなが
ら計画を立案する必要がある。通常、日程計画はガント
チャート図で表わせるため、これとレイアラ!・図面を
見比べて計画の評価、修正を行ないながら計画を立案す
るが、同じ機器に対して複数の種類の作業が関連してお
り、また、レイアウト図面も複雑なため、搬入可能性や
据付作業スペースの確保などの判断が難しく、計画の効
率が悪いという問題点がある。
When constructing a plant, it is necessary to create a schedule while taking into account factors such as the possibility of transporting the nine components of the main body and securing space for the installation work. Therefore, the planner needs to create a plan using not only work data but also plant layout data. Normally, schedule planning can be expressed as a Gantt chart, so this and Leila!・Plans are drawn up by comparing drawings, evaluating and modifying plans, but since multiple types of work are related to the same equipment and the layout drawings are complex, it is important to consider the possibility of delivery and installation work. The problem is that it is difficult to make decisions about securing space, etc., and planning is inefficient.

本発明の目的は、日程計画に対し、Wi人の可能性や据
付作業スペースの確保などを評価する場合にその判断の
手助けとなるように、レイアウト図面を作業の進行状況
が分かるように表示することにより、日程計画の効率を
向上することにある。
The purpose of the present invention is to display layout drawings so that the progress of the work can be seen in order to assist in making decisions when evaluating the possibility of free labor and the securing of installation work space in relation to the schedule plan. The purpose of this is to improve the efficiency of schedule planning.

〔課題を解決するための手段〕[Means to solve the problem]

上記課題は、以下に示す手順により、各機器。 The above issues can be solved for each device using the steps shown below.

躯体の作業進行状況を区別できる形でレイアウト図面デ
ータを作成し、これを表示装置に出力することで解決さ
れる。
This problem can be solved by creating layout drawing data in a form that allows the work progress status of the building blocks to be distinguished and outputting this data to a display device.

(1)立案した日程計画に対し、入力装置から任意の日
程計画上の時期を入力する。
(1) For the planned schedule, input any time on the schedule using the input device.

(2)各作業の実施時期データから、指定時期までに計
画上終了している作業を判定する。
(2) From the implementation timing data of each task, determine which tasks are scheduled to be completed by the designated time.

(3)この結果と、各作業の作業種類データ、各作業の
対象となる躯体9機器名から、各躯体9機器が指定時期
までに、どの種類の作業まで終了しているかを判定する
(3) Based on this result, the work type data of each work, and the name of the 9 equipment in the building blocks targeted for each work, it is determined which type of work each of the 9 equipment in the building blocks has completed by the specified time.

(4)この結果と、各機器、躯体の構造物内での配置デ
ータから、各機器、躯体の終了作業種類を区別できる形
で、構造物のレイアウト図面データを作成し、これを表
示装置に出力する。
(4) From this result and the placement data of each piece of equipment and frame within the structure, create layout drawing data for the structure in a form that allows you to distinguish the type of finished work for each piece of equipment and frame, and display this on a display device. Output.

〔作用〕[Effect]

本発明では、ある時期の作業進行状況とレイアウト図面
とを一体化して表現できるため、レイアウト図面を見る
だけで、次に続く作業に対する搬入の可能性や据付作業
スペースの確保などの判断が容易となり、計画作成の効
率が向上する。
With the present invention, since the work progress status at a certain time and the layout drawing can be expressed in an integrated manner, it is easy to judge the possibility of carrying in for the next work and securing the installation work space just by looking at the layout drawing. , the efficiency of planning will be improved.

〔実施例〕〔Example〕

以下1本発明の実施例を具体的に説明する。 One embodiment of the present invention will be specifically described below.

第1図は1本発明による日程計画支援装置の構成の一実
施例を示したものである。表示装置1は、画像出力装置
4の表示画面に画像9文字を表示するため、演算装置2
で作成したデータを入力する。
FIG. 1 shows an embodiment of the configuration of a schedule planning support device according to the present invention. The display device 1 uses the arithmetic device 2 to display nine characters in an image on the display screen of the image output device 4.
Enter the data created in .

この処理のため、演算処理装置2は、演算部2a。For this process, the arithmetic processing device 2 includes a calculation section 2a.

処理手順記憶部2b、中間データ記憶部2c、画像デー
タ出力部2d、入力部2eより構成されている。処理手
順記憶部2bに記憶した処理手順は。
It is composed of a processing procedure storage section 2b, an intermediate data storage section 2c, an image data output section 2d, and an input section 2e. The processing procedure stored in the processing procedure storage section 2b is as follows.

逐次、演算部2aから呼び出された上、実行される。It is sequentially called from the calculation unit 2a and executed.

以下1本発明によるプラント建設作業の日程計画支援の
一実施例を示す。第2図に演算処理装置2で実行する処
理手順の一実施例を示す、以下。
An example of support for schedule planning of plant construction work according to the present invention will be described below. FIG. 2 shows an example of the processing procedure executed by the arithmetic processing unit 2, as follows.

本実施例の処理手順をステップを追って説明する。The processing procedure of this embodiment will be explained step by step.

まず、処理ステップ1では、記憶部r15の躯体。First, in processing step 1, the main body of the storage unit r15 is processed.

機器などの構造物の構成要素の属性データ、記憶装置6
の作業データ、記憶装置7の日程計画データを読み込み
、中間データ記憶部2cに格納する。
Attribute data of structural elements such as equipment, storage device 6
The work data and the schedule data in the storage device 7 are read and stored in the intermediate data storage section 2c.

第3図、第4図、第5図にこれらのデータの例を示す。Examples of these data are shown in FIGS. 3, 4, and 5.

処理ステップ2では、日程計画を第6図のように表示両
面に表示する。
In processing step 2, the schedule is displayed on both sides of the display as shown in FIG.

処理ステップ3では1日程計画上の任意の時期を指定す
る6 処理ステップ4では、指定時期と日程計画データから、
指定時期までに計画上終了している作業を探索する。
In processing step 3, specify an arbitrary time on the daily schedule6.In processing step 4, from the specified time and schedule planning data,
Search for work that has been planned to be completed by a specified time.

処理ステップ5では、これらの作業に対し、作業データ
から作業種類9作業の対象となる構成要素名、レイアウ
ト図面データから構成要素の配置データを探索する。
In processing step 5, for these tasks, the name of the component to be the object of the work type 9 task is searched from the work data, and the arrangement data of the component is searched from the layout drawing data.

処理ステップ6では、この結果から、各構成要素の作業
進行状況を示すレイアウト図面データを作成する。この
例を第7図に示す。
In processing step 6, layout drawing data indicating the work progress of each component is created from this result. An example of this is shown in FIG.

処理ステップ7では、レイアウト図面を表示画面に表示
する。この例を第8図に示す。
In processing step 7, the layout drawing is displayed on the display screen. An example of this is shown in FIG.

以上の例では1作業時期を入力装置で指定しているが、
作業名を指定した場合にも同様な処理が可能である。
In the above example, one work period is specified using the input device,
Similar processing is possible when a work name is specified.

次に、日程計画の実績の評価を支援する場合の実施例を
以下に示す。第9図に処理手順を示す。
Next, an example of supporting the evaluation of schedule planning performance will be described below. FIG. 9 shows the processing procedure.

以下2本実施例の処理手順をステップを追って説明する
The processing procedure of the two embodiments will be explained step by step below.

処理ステップ1では、入力装置より日程計画のそれまで
の実績データを入力する。
In processing step 1, actual performance data of the schedule up to that point is inputted from the input device.

処理ステップ2では、記憶装置に格納されている日程計
画の予定データと入力された実績データを比較し、予定
どうり実行されていない作業(着目作業)を探索する。
In processing step 2, the schedule data of the schedule stored in the storage device and the input performance data are compared to search for work (work of interest) that has not been executed as scheduled.

処理ステップ3では1着目作業の対象物、及び、作業種
類を作業データから、対象物の配置データをレイアウト
図面データから探索する。
In processing step 3, the object and type of work of the first task are searched from the work data, and the arrangement data of the object is searched from the layout drawing data.

処理ステップ4では、これらの結果から、着目作業の対
象物に対し、その作業種類が区別できる形でレイアウト
図面データを作成する。
In processing step 4, from these results, layout drawing data is created for the object of interest in a form that allows the type of work to be distinguished.

処理ステップ5では、レイアウト図面を表示画面上に表
示する。
In processing step 5, the layout drawing is displayed on the display screen.

本発明では、レイアウト図面と作業進行状況を一体化し
て表示し1日程計画そのものの評価は、これを見た計画
作成者が行なっているのが、工程評価に関する専門家の
判断基準が明確なルールとして表現可能ならば、これを
知識ベースに格納し、これと本発明を組合せることによ
り、ある時期の日程計画の評価を自動化することができ
る。
In the present invention, the layout drawing and the work progress status are displayed in an integrated manner, and the evaluation of the daily schedule itself is carried out by the planner who sees this, based on clear rules for expert judgment regarding process evaluation. If it can be expressed as , it is possible to automate the evaluation of a schedule for a certain period by storing this in a knowledge base and combining this with the present invention.

〔発明の効果〕〔Effect of the invention〕

本発明によれば、ある時期の作業進行状況がレイアウト
画面を見ただけで判断できるため、次に続く作業に対す
る搬入の可能性や据付作業スペースの確保などの判断が
容易となり、計画作成の効率が向上する。
According to the present invention, the work progress status at a certain time can be judged just by looking at the layout screen, making it easy to judge the possibility of carrying in work for the next work and securing the installation work space, making planning more efficient. will improve.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例のU程計画支援装置のブロッ
ク図、第2図は処理手順のフローチャート、第3図は構
成要素の属性データの柄図、第4図は作業データの柄図
、第5図は日程計画データの柄図、第6図は日程計画表
の表示例図、第7図はレイアウト図面データの柄図、第
8図は作業進行状況を表わすレイアウト図、第9図は本
発明の他の実施例の処理手順のフローチャー1・を示す
。 1・・・表示装置、2・・・演算処理装置、3・・・入
力装置、4・・・画像出力装置。 5〜7 ・・記憶装置。 第 図 第 図 第 図 第4図 第 図 第6図 第7図 14S8図
Fig. 1 is a block diagram of a U process planning support device according to an embodiment of the present invention, Fig. 2 is a flowchart of the processing procedure, Fig. 3 is a pattern of attribute data of constituent elements, and Fig. 4 is a pattern of work data. Figure 5 is a pattern diagram of schedule planning data, Figure 6 is a display example diagram of a schedule planning table, Figure 7 is a pattern diagram of layout drawing data, Figure 8 is a layout diagram showing the work progress status, and Figure 9 is a diagram of the schedule planning data. The figure shows a flowchart 1 of the processing procedure of another embodiment of the present invention. 1... Display device, 2... Arithmetic processing device, 3... Input device, 4... Image output device. 5-7...Storage device. Figure Figure Figure Figure 4 Figure Figure 6 Figure 7 Figure 14S8 Figure

Claims (1)

【特許請求の範囲】 1、複数の躯体、機器から構成される構造物を組み立て
るために実施すべき作業の日程計画の立案を支援するシ
ステムにおいて、 前記日程計画に対し、入力装置から入力した任意の計画
上の時期に対し、 (1)各作業の作業時期から、指定時期までに計画上終
了している作業を判定し、 (2)この結果と、前記各作業の作業種類、前記各作業
の対象となる前記躯体、前記機器名から、前記各躯体、
前記機器が指定時期までに、どの種類の作業まで終了し
ているかを判定し、 (3)この結果と、前記各機器、前記躯体の構造物内で
の配置から、前記各機器、前記躯体の終了作業種類を区
別できる形で、構造物のレイアウト図面データを作成し
、これを表示装置に出力することにより前記日程計画の
評価を支援することを特徴とする日程計画支援方法。 2、一つまたは複数の表示装置と、躯体、機器などの構
造物の構成要素の属性データを記憶した第一の記憶装置
と、作業データを記憶した第二の記憶装置と、日程計画
を記憶した第三の記憶装置と、入力装置と、演算処理装
置と、演算装置から呼出し実行する処理手順を記憶した
第四の記憶装置からなる電子計算機において、 前記日程計画に対し、入力装置から入力した任意の計画
上の時期に対し、 (1)各作業の作業時期から、指定時期までに計画上終
了している作業を判定する手段と(2)この結果と、前
記各作業の作業種類、前記各作業の対象となる前記躯体
、前記機器名から、前記各躯体、前記機器が指定時期ま
でに、どの種類の作業まで終了しているかを判定する手
段と、 (3)この結果と、前記各機器、前記躯体の構造物内で
の配置から、前記各機器、前記躯体の終了作業種類を区
別できる形で、構造物のレイアウト図面データを作成し
、これを表示装置に出力することにより前記日程計画の
評価を支援する手段とからなることを特徴とする日程計
画支援装置。 3、複数の躯体、機器から構成される構造物を組み立て
るために実施すべき作業の日程計画の立案を支援するシ
ステムにおいて、 前記日程計画に対し、入力装置から指定した計画上の任
意の作業に対し、 (1)指定作業の対象となる前記躯体、前記機器などの
対象物名および指定作業の作業種類を作業データから探
索し、 (2)前記指定作業の対象物の配置データをレイアウト
図面データから探索し、 (3)前記日程計画上の前記指定作業以前に実施される
各作業の対象物名及び作業種類を前記作業データから、
対象物の前記配置データを前記レイアウト図面データか
ら探索し、(5)以上の結果から、前記指定作業と前記
指定作業以前に実施する作業に関し、終了作業種類が区
別できる形で前記レイアウト図面データを作成し、これ
を表示装置に出力することにより前記日程計画の評価を
支援することを特徴とする日程計画支援方法。 4、特許請求の範囲第1項において、 日程計画表とレイアウト図面を同時に表示することを特
徴とした日程計画支援方法。 5、特許請求の範囲第1項において、 前記各作業で必要となる作業空間も合わせて前記レイア
ウト図面上に表示することを特徴とする日程計画支援方
法。 6、入力装置より入力される日程、計画の実績データと
記憶装置に格納されている前記日程計画の予定データと
を比較し、予定と異なつている作業に対し、 (1)前記作業の対象となる躯体、機器などの対象物名
および作業種類を作業データから探索し、 (2)前記作業の対象物の配置データをレイアウト図面
データから探索し、 (3)以上の結果から、予定と異なつている前記作業に
関し、前記作業の種類が区別できる形で前記レイアウト
図面のデータを作成し、これを表示装置に出力すること
により前記日程計画の実績評価を支援することを特徴と
する日程計画支援方法。
[Scope of Claims] 1. In a system that supports planning of a work schedule to be carried out in order to assemble a structure composed of a plurality of frames and equipment, an arbitrary input input from an input device is provided for the schedule plan. (1) Determine the work that has been completed by the specified time based on the work time of each work, and (2) Determine this result, the work type of each work, and the work type of each work described above. From the target body and equipment name, each body,
Determine what type of work has been completed on the equipment by the specified time; (3) Based on this result and the arrangement of each equipment and the framework within the structure, A schedule planning support method comprising: creating layout drawing data of a structure in a form that allows distinguishing types of completed work, and outputting the data to a display device to support evaluation of the schedule plan. 2. One or more display devices, a first storage device that stores attribute data of structural elements such as skeletons and equipment, a second storage device that stores work data, and a schedule plan. In an electronic computer comprising a third storage device, an input device, an arithmetic processing device, and a fourth storage device that memorizes processing procedures to be called and executed from the arithmetic device; For any planned period, (1) means for determining from the work period of each work the work that has been completed according to the plan by the designated time; and (2) this result, the work type of each work, and the above. means for determining what type of work has been completed on each of the building blocks and the equipment by the designated time based on the names of the building blocks and equipment that are the targets of each work; Layout drawing data of the structure is created in a form that allows distinguishing the type of work to be completed for each piece of equipment and the frame based on the arrangement of the equipment and the frame within the structure, and this is output to a display device to determine the schedule. A schedule planning support device comprising means for supporting plan evaluation. 3. In a system that supports the planning of schedules for work to be carried out in order to assemble a structure consisting of multiple frames and equipment, a system that supports the planning of schedules for work to be carried out to assemble a structure consisting of multiple frames and equipment, includes a system that supports the planning of schedules for work to be carried out in order to assemble a structure consisting of a plurality of frames and equipment. (1) Search the work data for the names of the objects such as the framework and the equipment that are the targets of the designated work, and the work type of the designated work, and (2) search for the location data of the objects for the designated work from the layout drawing data. (3) From the work data, search for the object name and work type of each work to be performed before the designated work on the schedule,
Search the layout drawing data for the placement data of the object, and (5) based on the above results, search the layout drawing data in a form that allows the types of completed tasks to be distinguished regarding the designated work and the work to be performed before the designated work. A schedule planning support method characterized by supporting evaluation of the schedule plan by creating and outputting it to a display device. 4. A schedule planning support method according to claim 1, characterized by displaying a schedule plan and a layout drawing at the same time. 5. The schedule planning support method according to claim 1, characterized in that a work space required for each of the operations is also displayed on the layout drawing. 6. Compare the schedule and actual data of the plan input from the input device with the schedule data of the schedule stored in the storage device, and if the work differs from the schedule, (1) select the target of the work. (2) Search for the location data of the objects of the work from the layout drawing data; A schedule planning support method comprising: creating data of the layout drawing in a form in which the type of work can be distinguished with respect to the work being performed, and outputting the data to a display device to support performance evaluation of the schedule plan. .
JP63162540A 1988-07-01 1988-07-01 Method and device for supporting schedule planning Pending JPH0214358A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63162540A JPH0214358A (en) 1988-07-01 1988-07-01 Method and device for supporting schedule planning

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63162540A JPH0214358A (en) 1988-07-01 1988-07-01 Method and device for supporting schedule planning

Publications (1)

Publication Number Publication Date
JPH0214358A true JPH0214358A (en) 1990-01-18

Family

ID=15756550

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63162540A Pending JPH0214358A (en) 1988-07-01 1988-07-01 Method and device for supporting schedule planning

Country Status (1)

Country Link
JP (1) JPH0214358A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000024882A (en) * 1998-07-15 2000-01-25 Honda Motor Co Ltd Workpiece control system
JP2000024883A (en) * 1998-07-15 2000-01-25 Honda Motor Co Ltd Workpiece control system
WO2003005139A1 (en) * 2001-07-03 2003-01-16 Toyota Jidosha Kabushiki Kaisha System for assisting planning of work allocation utilizing visual display screen
JP2004078037A (en) * 2002-08-21 2004-03-11 Cad Center:Kk Progress managing method and progress managing program for three-dimensional city model generation, recording medium with recorded progress managing program, and progress management server

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000024882A (en) * 1998-07-15 2000-01-25 Honda Motor Co Ltd Workpiece control system
JP2000024883A (en) * 1998-07-15 2000-01-25 Honda Motor Co Ltd Workpiece control system
WO2003005139A1 (en) * 2001-07-03 2003-01-16 Toyota Jidosha Kabushiki Kaisha System for assisting planning of work allocation utilizing visual display screen
CN100373276C (en) * 2001-07-03 2008-03-05 丰田自动车株式会社 System for assisting planning of work allocation utilizing visual display screen
JP2004078037A (en) * 2002-08-21 2004-03-11 Cad Center:Kk Progress managing method and progress managing program for three-dimensional city model generation, recording medium with recorded progress managing program, and progress management server

Similar Documents

Publication Publication Date Title
US7925526B2 (en) Production management system and associated warning process
US7042468B2 (en) Text overlay for multi-dimensional construction project models
US20100114635A1 (en) Construction progress visualization system and method of visualizing construction progress
WO2007130180A1 (en) Visual workflow process notation and layout
JP2003015723A (en) Work distribution planning supporting device using visual display screen
JPH08314526A (en) Manufacture management system
JPH0214358A (en) Method and device for supporting schedule planning
JP3926496B2 (en) Project management system
JPH1040272A (en) Center design support method and system
JP2003002203A (en) Diagram data editing information on execution train diagram making, storage medium and diagram data editor
JPH07296062A (en) Method for supporting decision of staff arrangement
JP3333908B2 (en) Timetable creation support system
JP2002207511A (en) Support system for creation of operation on production line and for setting of man-hour thereof, computer- readable storage medium, and computer program product
JP2839540B2 (en) Schedule information creation device
JPH0935103A (en) Device for managing production planning information
JPH0516041A (en) Work instruction system in assembly line
JPH0496104A (en) Work plan generation processor
JPH07129667A (en) Work progress control method for job
JP2004171163A (en) Resource management device, resource management method, program and recording medium
JP3036918B2 (en) Semiconductor device manufacturing support equipment
JPH08241347A (en) Processor and method for information processing
JPH106189A (en) Manufacturing shop control method and device
JPH01312669A (en) Design supporting device and automatic arranging device for printed wiring board
JPH02162463A (en) Back-up device for production of process network
JPH07254002A (en) Cad parts selecting device