JPH06348720A - Production development control display device - Google Patents
Production development control display deviceInfo
- Publication number
- JPH06348720A JPH06348720A JP14105693A JP14105693A JPH06348720A JP H06348720 A JPH06348720 A JP H06348720A JP 14105693 A JP14105693 A JP 14105693A JP 14105693 A JP14105693 A JP 14105693A JP H06348720 A JPH06348720 A JP H06348720A
- Authority
- JP
- Japan
- Prior art keywords
- data
- progress
- schedule
- display
- days
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 26
- 238000011161 development Methods 0.000 title claims description 25
- 238000000034 method Methods 0.000 claims abstract description 68
- 230000000052 comparative effect Effects 0.000 claims 1
- 239000002131 composite material Substances 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 12
- 238000004458 analytical method Methods 0.000 description 5
- 230000003111 delayed effect Effects 0.000 description 4
- 238000012360 testing method Methods 0.000 description 4
- 230000002194 synthesizing effect Effects 0.000 description 3
- 241001315488 Inazuma Species 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000012938 design process Methods 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000002250 progressing effect Effects 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- General Factory Administration (AREA)
- Stored Programmes (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、生産開発工程毎の情報
の収集や分析を行ない管理するコンピュータシステムに
おける生産開発管理表示装置に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production development management display device in a computer system for collecting and analyzing information for each production development process and managing it.
【0002】[0002]
【従来の技術】各生産開発工程の進捗状況を管理するこ
とは、効率良く生産開発が進んでいるか否かを判断する
ための重要な要素である。従来は、特に進捗管理用とし
て作られた表示装置は無く、あえて表示するとすれば、
主に、以下に示すイナズマチャートやガントチャート等
によるものが多かった。2. Description of the Related Art Managing the progress of each production development process is an important factor for efficiently determining whether production development is proceeding. Conventionally, there is no display device made especially for progress management, and if you dare to display it,
Mainly, there were many charts such as the following Inazuma chart and Gantt chart.
【0003】イナズマチャートを用いて表示する場合に
ついて図1をもとに説明する。ここでは、工程aの予定
を「10月1日から10月30日まで」と設定し、工程
bの予定を「10月1日から10月25日まで」と設定
し、工程cの予定を「10月10日から11月10日ま
で」と設定する。A case where a display is made by using an outline chart will be described with reference to FIG. Here, the schedule of the process a is set as "October 1 to October 30", the schedule of the process b is set as "From October 1 to October 25", and the schedule of the process c is set. It is set as "from October 10th to November 10th".
【0004】横軸に日時、縦軸に工程をとり、工程aの
予定を予定10のように横長の長方形で表し、工程bの
予定を予定11のように横長の長方形で表し、工程cの
予定を予定12のように横長の長方形で表す。The horizontal axis represents the date and time, the vertical axis represents the process, and the schedule of the process a is represented by a horizontally long rectangle such as schedule 10, the schedule of the process b is represented by a horizontally long rectangle such as schedule 11, and the schedule of the process c. The schedule is represented by a horizontally long rectangle like Schedule 12.
【0005】ここで、10月25日の時点での実績を表
示するが、工程aは10月25日現在で、当初計画した
うち10月15日までの分の実績しかあげることができ
なかったとする。Here, the results as of October 25 are displayed, but the process a is as of October 25, and it is possible to give only the results up to October 15 out of the initially planned. To do.
【0006】同様に、工程bは10月20日までの分の
実績をあげ、工程cは10月30日までの分の実績をあ
げたとする。ここで、工程aの予定10上の10月15
日の点と、工程bの予定11上の10月20日の点と、
工程cの予定12上の10月30日の点を直線で結んで
(実線13)、10月25日の時点での実績を表した図
がイナズマチャートである。Similarly, it is assumed that the process b has achieved the results up to October 20, and the process c has achieved the results up to October 30. Here, October 15 on schedule 10 of process a
The point of day and the point of October 20 on schedule 11 of process b,
A diagram showing the results as of October 25 by connecting the points on October 30 on schedule 12 of process c with a straight line (solid line 13) is the Inazuma chart.
【0007】このイナズマチャートは、ある時点でひと
つの工程の何%が完了しているかを知る場合には有効で
あった。ガントチャートを用いて表示する場合について
図2をもとに説明する。ここでは、工程dの予定を「1
0月1日から10月30日まで」と「11月5日から1
1月10日まで」の2つの作業に分けて設定する。「1
0月10日から10月30日まで」の予定を、予定2
0、「11月5日から11月10日まで」の予定を、予
定21のように棒で設定する。同様に、工程e、工程f
の予定を、予定22、予定23、予定24のように棒で
設定する。This lightning chart was effective in knowing what percentage of one process was completed at a certain time. A case of displaying using a Gantt chart will be described with reference to FIG. Here, the schedule of process d is "1.
From 1st October to 30th October "and" 5th November to 1st
It will be set separately for two tasks, "until January 10th.""1
Schedule from October 10th to October 30th, schedule 2
0, "Schedule from November 5th to November 10th" is set with a stick like Schedule 21. Similarly, steps e and f
The schedule is set with a bar like schedule 22, schedule 23, and schedule 24.
【0008】予定に対する実績は、横長の斜線で示した
長方形の箱で表示する。工程dの「10月1日から10
月20日」の予定に対して実際は、10月30日までか
かった場合には、横長の斜線で示した長方形の箱を、作
業が開始した日から10月30日のところまでのばす
(箱25)。同様に、作業実績を箱26のように横長の
斜線で示した長方形の箱で示す。11月10日の時点
で、進捗をチェックしたところ、工程dと工程fの作業
が行なわれていた。このときの進捗状況を、記号で表現
する(図中「A」)。アルファベットの記号に、進捗の
状況を設定しておき、その記号を利用して、進捗状況を
表現するものである。例えば、「A:作業進行中、B:
準備作業待ち」などである。このように、ある一定期間
の計画と実施状況および作業状況を一つにまとめたもの
がガントチャートである。The actual results for the schedule are displayed in a rectangular box indicated by a horizontally long diagonal line. Process d, “From October 1st to 10th
If it actually takes until October 30 for the schedule of "20th of a month", extend the rectangular box indicated by the horizontal diagonal line from the day when the work started to the point of October 30 (box 25 ). Similarly, the work record is shown by a rectangular box indicated by a horizontally long diagonal line like the box 26. As of November 10, when the progress was checked, the work of process d and process f was performed. The progress status at this time is represented by a symbol ("A" in the figure). The progress status is set in the alphabetic symbol, and the progress status is expressed using the symbol. For example, "A: work in progress, B:
Waiting for preparatory work ". In this way, the Gantt chart is a collection of plans, implementation statuses, and work statuses for a certain period of time.
【0009】[0009]
【発明が解決しようとする課題】上述のような従来の表
示装置は、イナズマチャートの場合、工程全体のどの程
度まで終了し、どの程度の日数分の遅れが出ているか一
目で分かる。ガントチャートの場合、予定と実績が平行
にならんでいるため予定と実績のズレは一目で分かる。In the conventional display device as described above, in the case of the lightning chart, it is possible to see at a glance how much the entire process is completed and how many days are delayed. In the case of Gantt chart, the gap between the schedule and the performance can be seen at a glance because the schedule and the performance are parallel.
【0010】しかし、これら従来の装置は進捗管理用と
して作られたものではないため、プロジェクトが、複数
のサブシステムに分割され生産開発する場合、複数のサ
ブシステムをまとめてひとつのプロジェクトとして表示
することができず、現状の生産開発にそぐわないという
問題点があった。また、進捗の定量的把握ということに
関しては、定期的にチェックする場合、作業の進捗が前
回のチェック時に比べて進んでいるのか、遅れているの
か判断ができないという問題があった。さらに、例え
ば、図2に示すガントチャートでは、工程dの箱25に
ついていえば、該作業が完了しているのかどうかを一目
で把握することは容易ではなかった。However, since these conventional devices are not created for progress management, when a project is divided into a plurality of subsystems for production development, the plurality of subsystems are collectively displayed as one project. However, there was a problem that it was not suitable for the current production development. Further, regarding the quantitative grasp of the progress, there is a problem that it is impossible to judge whether the progress of the work is advanced or delayed compared to the time of the last check, when regularly checking. Further, for example, in the Gantt chart shown in FIG. 2, regarding the box 25 of the step d, it is not easy to grasp at a glance whether or not the work is completed.
【0011】そこで本発明は、上述したような事情に対
処してなされたもので、プロジェクトが複数サブシステ
ムに分割された各生産開発工程の進捗状況をまとめて全
体のプロジェクトとしての進捗状況を表示することによ
り、管理者に負担をかけず容易な進捗管理を可能とする
ことと、作業の進み/遅れが容易に判断できるような定
量的な指標を示すことにより、より精度の高い進捗管理
を可能とすることを目的とする。Therefore, the present invention has been made in consideration of the above-mentioned circumstances, and displays the progress status of the entire project by collecting the progress status of each production development process in which the project is divided into a plurality of subsystems. By doing so, it is possible to easily manage progress without burdening the manager and to show more accurate progress management by showing quantitative indicators that can easily judge the progress / delay of work. The purpose is to enable.
【0012】[0012]
【課題を解決するための手段】本発明は、プロジェクト
を複数のサブシステムに分割し、そのサブシステム毎に
入力された生産開発工程に関するデータ情報を分析し、
表示する生産開発管理表示装置において、前記生産開発
工程に関するデータは、予定更新日数データ、計画デー
タ及び実績データからなり、前記計画データに基づく前
記プロジェクトの各サブシステムの計画工程を表示する
第1の表示手段と、前記実績データを前記計画工程に対
応させて比較表示する第2の表示手段と、前記予定更新
日数データを前記計画工程に対応させるとともに、前記
実績データと識別可能に付加して比較表示する第3の表
示手段とを備えたことを特徴とする生産開発管理表示装
置である。According to the present invention, a project is divided into a plurality of subsystems, and data information relating to a production development process input for each subsystem is analyzed.
In the production / development management display device for displaying, the data on the production / development process is composed of scheduled update days data, plan data and actual data, and displays the plan process of each subsystem of the project based on the plan data. Display means, second display means for comparing and displaying the actual result data in correspondence with the planned process, and making the planned update days data correspond to the planned process, and adding the result data in a distinguishable manner for comparison. It is a production and development management display device comprising a third display means for displaying.
【0013】[0013]
【作用】本発明により、予定に対して作業実績がどの程
度の進み/遅れを生じているのかが定量的にかつビジュ
アル化された情報として把握することができる。さら
に、複数の分割された各サブシステムの進捗状況をまと
めて、プロジェクト全体としての進捗状況を表示するこ
とにより、ネックとなっている生産開発の遅れの把握を
より高い精度で行うことができ、管理者に負担をかけず
容易に生産開発管理が可能となる。According to the present invention, it is possible to grasp quantitatively and visually the information as to how much the work result is advanced or delayed with respect to the schedule. Furthermore, by summarizing the progress status of each of the divided subsystems and displaying the progress status of the entire project, it is possible to grasp the bottleneck of production development delay with higher accuracy. This makes it possible to easily manage production development without burdening the administrator.
【0014】[0014]
【実施例】本発明の一実施例であるソフトウエアの開発
プロジェクトにおける進捗状況を表示する生産開発管理
表示装置について図面を参照して説明する。図3は本発
明の一実施例に係る生産開発管理表示装置の全体構成図
である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A production development management display device for displaying the progress status of a software development project according to an embodiment of the present invention will be described with reference to the drawings. FIG. 3 is an overall configuration diagram of a production development management display device according to an embodiment of the present invention.
【0015】入力部31が表示要求入力手段32によっ
て進捗チェックの要求を受けると、解析実行部33に処
理が移る。解析実行部33では、表示要求を分析して、
対象とするプロジェクトの予定更新日数データ、計画デ
ータ及び実績データを、予定更新日数入力手段34、計
画データ入力手段35、実績データ入力手段36を利用
して各々入力され、記憶部37に蓄積された磁気ディス
ク上から収集し、上記各データを、編集部38の、予定
更新日数編集手段39、計画データ編集手段310、実
績データ編集手段311に渡す。そして、各編集部で編
集されたデータを、表示データ合成手段312でまとめ
て、表示部313に、表示要求入力手段32によって設
定された表示要求に対応した進捗状況を表示する。When the input unit 31 receives a progress check request from the display request input unit 32, the process is transferred to the analysis execution unit 33. The analysis execution unit 33 analyzes the display request,
The planned update days data, the plan data, and the actual data of the target project are respectively input using the planned update days input means 34, the plan data input means 35, and the actual data input means 36, and accumulated in the storage unit 37. The data is collected from the magnetic disk and is passed to the scheduled update days editing means 39, the plan data editing means 310, and the actual data editing means 311 of the editing unit 38. Then, the data edited by each editing unit is collected by the display data synthesizing unit 312, and the progress status corresponding to the display request set by the display request input unit 32 is displayed on the display unit 313.
【0016】以下、具体的に本発明の一実施例であるソ
フトウエアの開発プロジェクトにおける進捗状況を表示
する生産開発管理表示装置について説明する。図4に、
プロジェクトの概要を示す。ここでは、ソフトウエアの
開発プロジェクト名は「Xシステム」という名称である
ものとする。対象とするシステム「Xシステム」は、サ
ブシステムX−1とサブシステムX−2に分割される。
本プロジェクトの予定は、「基本設計工程」、「機能設
計工程」、「テスト仕様書作成工程」、「プログラム作
成工程」及び「テスト工程」の5つの工程からなり、
「基本設計」は担当者Aが4月1日から5月10日の間
に担当する。そして、各サブシステムごとに「機能設
計」は担当者Bと担当者Cが分割して5月10日から6
月15日の間に担当し、「テスト仕様書作成」は担当者
Bと担当者Cが分割して5月20日から7月20日の間
に担当し、「プログラム作成」は担当者Bと担当者Cが
分割して7月20日から8月15日の間に担当する。
「テスト」は担当者Aが9月1日から9月30日の間に
担当する。また、それぞれの工程での予定成果物と成果
物量が決まっている。A production development management display device for displaying the progress status of a software development project, which is an embodiment of the present invention, will be specifically described below. In Figure 4,
The outline of the project is shown. Here, it is assumed that the software development project name is “X system”. The target system "X system" is divided into subsystem X-1 and subsystem X-2.
The schedule of this project consists of five processes: "Basic design process", "Function design process", "Test specification creation process", "Program creation process" and "Test process".
Person A will be in charge of "basic design" from April 1st to May 10th. The "functional design" for each subsystem is divided between the person in charge B and the person in charge C from 6th May to 6th.
Responsible during the 15th of the month, the person in charge of "test specification creation" is divided between the person in charge B and the person in charge of C, and is in charge of from May 20th to July 20th. Person in charge C will be divided and will be in charge from July 20th to August 15th.
The "test" is performed by the person in charge A from September 1 to September 30. In addition, the planned deliverables and deliverables for each process are fixed.
【0017】生産開発管理者である利用者は、図3に示
した入力部31の計画データ入力手段35を利用して、
上述した本プロジェクトの予定情報を入力する。図5
は、図3に示した予定更新日数入力手段34を用いて入
力したデータの例である。ここでは、Xシステムのサブ
システムX−1を担当している開発者が、進捗チェック
日51に、現在作業を行なっている工程名52と、その
工程でのチェック日時点での成果物量及び現工程の予定
更新日数53を入力した例を示している。予定更新日数
とは、進捗状況を報告している工程が、残り何日あれば
終了するのかを、日単位で入力するものである。The user who is the production development manager uses the plan data input means 35 of the input unit 31 shown in FIG.
Enter the schedule information for this project described above. Figure 5
Is an example of data input using the scheduled update days input means 34 shown in FIG. Here, the developer in charge of the subsystem X-1 of the X system, on the progress check date 51, the process name 52 that is currently working, the amount of deliverables at the time of the check date in the process, and the current product amount. It shows an example of inputting the scheduled update days 53 of the process. The scheduled renewal number of days is to input the number of remaining days of the process reporting the progress status on a daily basis.
【0018】図6は、図3の実績データ入力手段36を
用いて入力した例である。ここではXシステムのサブシ
ステムX−1を担当している開発者が、進捗チェック日
に、進捗チェック日61、対象工程名62、対象工程の
成果物の成果物量63を入力した例を示している。FIG. 6 shows an example in which the actual data input means 36 shown in FIG. 3 is used. Here, an example is shown in which the developer in charge of the subsystem X-1 of the X system inputs the progress check date 61, the target process name 62, and the deliverable amount 63 of the target process deliverable on the progress check date. There is.
【0019】図5及び図6に示すように、本システムの
入力部31を利用して計画データ、予定更新日数デー
タ、実績データが入力されたとする。ここで、進捗の表
示要求が出された場合の処理を以下に説明する。なお、
ここでは担当者Bの担当分のシステムをサブシステムX
−1、担当者Cの担当分のシステムサブシステムX−2
とする。As shown in FIGS. 5 and 6, it is assumed that the input data 31 of the present system is used to input the plan data, the scheduled update date data, and the actual data. Here, a process when a progress display request is issued will be described below. In addition,
Here, the system in charge of the person in charge B is defined as subsystem X.
-1, the system subsystem X-2 in charge of the person C
And
【0020】進捗の表示要求を本システムの表示要求入
力手段32が受け付けると、処理は、解析実行部33に
移る。実行解析部33では、表示要求を分析して、対象
とするプロジェクトの予定更新日数データと計画データ
と実績データが、予定更新日数入力手段34、計画デー
タ入力手段35及び実績データ入力手段36を利用して
入力され、磁気ディスク等からなる記憶部37に蓄積さ
れた磁気ディスク上から収集し、上記各データを、予定
更新日数編集手段39と計画データ編集手段310と表
示データ編集手段311に渡す。そして、各編集部で編
集されたデータを、表示データ合成手段312で合成し
て、表示部313に進捗状況を表示する。図7は、この
手順をさらに詳細にフローチャートで示したものであ
る。When the display request input means 32 of the present system accepts the progress display request, the process proceeds to the analysis executing section 33. In the execution analysis unit 33, the display request is analyzed, and the scheduled update days data, the plan data, and the actual data of the target project use the scheduled update days input means 34, the plan data input means 35, and the actual data input means 36. Is input and collected from the magnetic disk stored in the storage unit 37 composed of a magnetic disk or the like, and each of the above-mentioned data is passed to the scheduled update days editing means 39, the plan data editing means 310, and the display data editing means 311. Then, the data edited by each editing unit is combined by the display data combining unit 312, and the progress status is displayed on the display unit 313. FIG. 7 is a flowchart showing this procedure in more detail.
【0021】システムが起動されると、表示要求受け付
け(メニュー画面)に移る(STEP 71)。そし
て、編集部で今まで蓄積されたデータを読み込み(ST
EP72〜74)、その結果にもとづいてユーザは、入
力部を介して、進捗状況を表示するプロジェクトを選択
する(STEP 75)。選択が終了すると、処理は表
示データ合成部に移る。選択したプロジェクトが複数の
サブシステム(担当者)を有していれば、各サブシステ
ムごとの工程の開始日と終了日を計算する。開始日と終
了日の計算が終了すると、進捗状況の表示に移る。表示
は、以下の手順で行なわれる。対象プロジェクトの予定
工程を横棒で表示する(STEP 77)。チェック日
以前の実績情報を斜線で示した横長の箱で表示する(S
TEP78)。チェック日に入力された予定更新日数を
空白の横長の箱で表示する(STEP 79)。空白の
横長の箱の横に、予定更新日数を表示する(STEP7
10)。以前にチェックした日を縦棒で表示する(ST
EP 711)。今回のチェック日の進捗係数と前回の
チェック日の進捗係数を表示する(STEP712)。When the system is activated, the display request is accepted (menu screen) (STEP 71). Then, the editorial department reads the data accumulated so far (ST
EP72-74), and based on the result, the user selects the project whose progress is to be displayed via the input unit (STEP 75). When the selection is completed, the process moves to the display data synthesizing unit. If the selected project has multiple subsystems (persons in charge), calculate the start date and end date of the process for each subsystem. When the calculation of the start date and the end date is completed, the progress status is displayed. The display is performed by the following procedure. The planned process of the target project is displayed with a horizontal bar (STEP 77). The actual information before the check date is displayed in a horizontally long box with diagonal lines (S
TEP78). The number of scheduled update days input on the check day is displayed in a blank horizontal box (STEP 79). The scheduled renewal days are displayed next to the blank oblong box (STEP7
10). Display the date checked before with a vertical bar (ST
EP 711). The progress coefficient of this check date and the progress coefficient of the previous check date are displayed (STEP 712).
【0022】図8に、対象工程がサブシステムに分割さ
れている場合の各工程の開始日と終了日の計算方法を示
す。これは、図7のSTEP 76に対応するものであ
る。まず、初期化を行ない(STEP 81)、対象プ
ロジェクトのサブシステム数を読み込む(STEP 8
2)。サブシステムの数だけ、情報を取り込み(STE
P 83)、進捗のチェックを行なう(STEP 8
4)。チェック日の作業工程が、サブシステム間で違い
がある場合には(STEP 85)、一番遅れている工
程の進捗を全体の進捗とする(STEP 86)。相違
がなければ、一番遅れているサブシステムの工程の進捗
を全体の進捗とする(STEP 87)。FIG. 8 shows a method of calculating the start date and end date of each process when the target process is divided into subsystems. This corresponds to STEP 76 in FIG. First, initialization is performed (STEP 81), and the number of subsystems of the target project is read (STEP 8).
2). Import information as many as the number of subsystems (STE
P83), check progress (STEP 8)
4). If there is a difference in the work process on the check day between the subsystems (STEP 85), the progress of the process that is the latest is set as the overall progress (STEP 86). If there is no difference, the progress of the process of the most delayed subsystem is set as the overall progress (STEP 87).
【0023】図9及び図10は、進捗係数の計算方法と
シミュレーション例を示す図である。ある工程の作業の
予定91が横棒で設定されている。この工程の開始予定
日92は10月1日である。また終了予定日93は、1
0月30日となっている。このとき、10月15日の進
捗チェック日94の時点での進捗係数を計算する。10
月15日の時点での作業実績95は、横長の斜線の箱で
示されている。そして、この作業工程があと何日で終了
するのかという、予定更新日数データ96が、横長の空
白の箱で示されている。ここでは、予定更新日数は10
日である。このときの進捗係数は、 (実績作業日数+チェック日時点での予定更新日数)/
予定作業日数 で計算される。本実施例では、その進捗係数97は、
0.83となる。これは、予定作業日数の0.83倍の
日数で、工程が終わることを意味している。予定に対す
る実績の表れ方もさまざまなパターンがある。ここで
は、(a)から(f)までの6パターンの進捗係数の算
出方法について図9に示す。図9(a)は、予定通り作
業が始まり、予定より早く作業が終了する場合を示して
いる。つまり、進捗チェック日94において、作業実績
95は15日であり、残り作業日数96は10日である
から、進捗係数97は、 (15+10)/30=0.83 となる。図9(b)〜(f)の進捗係数も同様である。9 and 10 are diagrams showing a method of calculating the progress coefficient and a simulation example. A work schedule 91 of a certain process is set by a horizontal bar. The scheduled start date 92 for this process is October 1. The scheduled end date 93 is 1
It's 30th of October. At this time, the progress coefficient as of the progress check date 94 of October 15 is calculated. 10
The work record 95 as of the 15th day of the month is indicated by a horizontally elongated box. Then, the planned renewal day count data 96 indicating how many days the work process will be completed is shown by a horizontally long blank box. Here, the scheduled update days are 10
Is the day. The progress coefficient at this time is (actual work days + planned renewal days at the check date) /
Calculated by planned work days. In this embodiment, the progress coefficient 97 is
It becomes 0.83. This means that the process ends in 0.83 times the planned work days. There are various patterns in how performance is displayed for an appointment. Here, FIG. 9 shows a method of calculating the progress coefficient of 6 patterns from (a) to (f). FIG. 9A shows a case where the work starts as planned and the work ends earlier than planned. That is, on the progress check date 94, the work record 95 is 15 days, and the remaining work days 96 is 10 days. Therefore, the progress coefficient 97 is (15 + 10) /30=0.83. The same applies to the progress coefficient in FIGS. 9B to 9F.
【0024】図10は、ある工程の進捗係数の推移をシ
ミュレーションした結果である。ある工程の作業予定が
10月1日から11月1日までとなっている。ここで、
10月15日にチェックしたときには、進捗係数は1と
なり、オンスケジュールで作業が進んでいることを示し
ている。次に11月1日の時点でチェックしたときに、
予定更新日数が5日となり、進捗係数は1.16となっ
ている。さらに、11月15日の時点でチェックする
と、ここでも予定更新日数が5日となっており、進捗係
数は1.67と増加している。このように、各チェック
日ごとの進捗係数を評価することで、作業の進み/遅れ
が定量的に判断できるようになり、効率的な進捗管理が
可能となる。FIG. 10 is a result of simulating the transition of the progress coefficient of a certain process. The work schedule for a certain process is from October 1st to November 1st. here,
When checked on October 15, the progress coefficient is 1, indicating that the work is progressing on schedule. Next time I checked on November 1,
The number of scheduled renewal days is 5, and the progress coefficient is 1.16. Furthermore, when checked as of November 15, the number of scheduled renewal days is also 5 here, and the progress coefficient has increased to 1.67. In this way, by evaluating the progress coefficient for each check date, it becomes possible to quantitatively judge the progress / delay of the work, and efficient progress management becomes possible.
【0025】実際の進捗状況をグラフィカルに表示した
例を図11に示す。各工程の予定を横棒111で表示す
る。チェック日以前の実績情報を横長の斜線の箱112
で表示する。チェック日113に入力された予定更新日
数を、横長の空白の箱114で表示する。空白の箱11
4の横に、予定更新日数115を表示する。今回のチェ
ック日を含めた以前のチェック日を縦棒116で表示す
る。また、今回のチェック日の進捗係数と前回のチェッ
ク日の進捗係数を表示する(図中、「1.14」及び
「1.57」)。ここでは、5月1日の時点では、予定
に対して1.14倍で作業が終わる予定であったのに、
6月1日の時点では、予定に対して1.57倍もの日数
がかかってしまうことが一目で把握できる。すなわち、
進捗の遅れが拡大していることが容易に把握できるよう
になる。FIG. 11 shows an example in which the actual progress is graphically displayed. The schedule of each process is indicated by a horizontal bar 111. Horizontal slanted box 112 showing the actual information before the check date
Display with. The number of scheduled update days input to the check date 113 is displayed in a horizontally long blank box 114. Blank box 11
Next to 4, the scheduled update days 115 are displayed. The previous check date including the current check date is displayed by the vertical bar 116. Further, the progress coefficient of the current check date and the progress coefficient of the previous check date are displayed (“1.14” and “1.57” in the figure). Here, as of May 1, the work was supposed to be completed 1.14 times the schedule,
As of June 1, it can be seen at a glance that it will take 1.57 times as many days as planned. That is,
It will be easy to understand that the delay in progress is increasing.
【0026】以上のように、本発明によれば、進捗状況
をグラフィカルに表示することによって、予定に対する
実績、予定更新日数、進捗の進み/遅れの確認が容易に
行なえるようになる。As described above, according to the present invention, by displaying the progress status graphically, it is possible to easily confirm the actual result of the schedule, the number of scheduled update days, and the progress / delay of the progress.
【0027】[0027]
【発明の効果】上述のように、本発明の生産発管理表示
装置では、複数の分割された各サブシステムの進捗状況
と、複数の分割された各サブシステムの進捗状況をまと
めて、プロジェクト全体としての進捗状況を表示するこ
とが可能となる。さらに、進捗の遅れ/進みを示す進捗
係数の計算が可能となる。これらの情報をグラフィカル
に表示することによって、生産開発全体の進捗把握がよ
り高い精度で行なうことができ、管理者に負担をかけず
容易に進捗管理を含めた生産開発管理が可能となる。As described above, in the production start-up management display device of the present invention, the progress status of each of the plurality of divided subsystems and the progress status of each of the plurality of divided subsystems are summarized, and the entire project is completed. It is possible to display the progress status as. Further, it is possible to calculate the progress coefficient indicating the progress / delay of progress. By graphically displaying this information, the progress of the entire production development can be grasped with higher accuracy, and the production development management including the progress management can be easily performed without imposing a burden on the manager.
【図1】イナズマチャートを説明するための図。FIG. 1 is a diagram for explaining an outline chart.
【図2】ガントチャートを説明するための図。FIG. 2 is a diagram for explaining a Gantt chart.
【図3】本発明に係る生産開発管理表示装置の全体構成
を示した図。FIG. 3 is a diagram showing an overall configuration of a production development management display device according to the present invention.
【図4】本発明の一実施例におけるプロジェクトの予定
の情報を表した図。FIG. 4 is a diagram showing project schedule information according to an embodiment of the present invention.
【図5】本発明の一実施例における進捗チェック日の予
定更新日数の設定結果を表した図。FIG. 5 is a diagram showing a result of setting scheduled update days on a progress check date according to an embodiment of the present invention.
【図6】本発明の一実施例における進捗チェック日の作
業実績値の設定結果を表した図。FIG. 6 is a diagram showing a result of setting work performance values on a progress check date in an embodiment of the present invention.
【図7】本発明の処理概要をフローチャートで示した
図。FIG. 7 is a flowchart showing an outline of processing of the present invention.
【図8】複数のサブシステムの進捗を全体の進捗とする
ための方法をフローチャートで示した図。FIG. 8 is a flowchart showing a method for setting progress of a plurality of subsystems as overall progress.
【図9】進捗係数を説明するための図。FIG. 9 is a diagram for explaining a progress coefficient.
【図10】進捗係数のシミュレーションによる進捗状況
を説明するための図。FIG. 10 is a diagram for explaining a progress situation by simulation of a progress coefficient.
【図11】本発明の一実施例におけるプロジェクトの進
捗状況を表した図。FIG. 11 is a diagram showing the progress status of a project in one embodiment of the present invention.
31…入力部 33…解析実行部 37…記憶部 38…編集部 312…表示データ合成手段 313…表示部 31 ... Input part 33 ... Analysis execution part 37 ... Storage part 38 ... Editing part 312 ... Display data synthesizing means 313 ... Display part
Claims (1)
割し、そのサブシステム毎に入力された生産開発工程に
関するデータ情報を分析し、表示する生産開発管理表示
装置において、 前記生産開発工程に関するデータは、予定更新日数デー
タ、計画データ及び実績データからなり、 前記計画データに基づく前記プロジェクトの各サブシス
テムの計画工程を表示する第1の表示手段と、 前記実績データを前記計画工程に対応させて比較表示す
る第2の表示手段と、 前記予定更新日数データを前記計画工程に対応させると
ともに、前記実績データと識別可能に付加して比較表示
する第3の表示手段とを備えたことを特徴とする生産開
発管理表示装置。1. A production development management display device for dividing a project into a plurality of subsystems, analyzing and displaying data information relating to the production development process input for each subsystem, wherein the data relating to the production development process is: First display means for displaying planned process days of each subsystem of the project based on the planned data and scheduled display update date data, plan data, and actual data, and comparative display of the actual data in correspondence with the planned process. And a third display means for making the scheduled update days data correspond to the planned process and additionally displaying the result data in a distinguishable manner for comparison display. Development management display device.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14105693A JPH06348720A (en) | 1993-06-14 | 1993-06-14 | Production development control display device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14105693A JPH06348720A (en) | 1993-06-14 | 1993-06-14 | Production development control display device |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH06348720A true JPH06348720A (en) | 1994-12-22 |
Family
ID=15283234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14105693A Pending JPH06348720A (en) | 1993-06-14 | 1993-06-14 | Production development control display device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH06348720A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07219995A (en) * | 1994-01-31 | 1995-08-18 | Nec Corp | Preparing system for process progress management table |
JPH0922429A (en) * | 1995-07-06 | 1997-01-21 | Nec Corp | Project progress management system |
JPH1011507A (en) * | 1996-06-26 | 1998-01-16 | Toshiba Corp | Work flow management system and its display method |
JPH11203364A (en) * | 1998-01-20 | 1999-07-30 | Fujitsu Ltd | Resource assignment processor |
JP2006004430A (en) * | 2004-06-15 | 2006-01-05 | Microsoft Corp | Method and system for restarting project management system scheduling engine based on user input of contractual start/finish data |
KR101292077B1 (en) * | 2010-12-16 | 2013-07-31 | 한국전자통신연구원 | Apparatus and method for monitoring progress |
JP2014112275A (en) * | 2012-12-05 | 2014-06-19 | Mitsubishi Electric Corp | Apparatus for creating logic drawing and test table |
WO2020039559A1 (en) * | 2018-08-23 | 2020-02-27 | ソニー株式会社 | Information processing device, information processing method, and work evaluation system |
-
1993
- 1993-06-14 JP JP14105693A patent/JPH06348720A/en active Pending
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07219995A (en) * | 1994-01-31 | 1995-08-18 | Nec Corp | Preparing system for process progress management table |
JPH0922429A (en) * | 1995-07-06 | 1997-01-21 | Nec Corp | Project progress management system |
JPH1011507A (en) * | 1996-06-26 | 1998-01-16 | Toshiba Corp | Work flow management system and its display method |
JPH11203364A (en) * | 1998-01-20 | 1999-07-30 | Fujitsu Ltd | Resource assignment processor |
JP2006004430A (en) * | 2004-06-15 | 2006-01-05 | Microsoft Corp | Method and system for restarting project management system scheduling engine based on user input of contractual start/finish data |
KR101292077B1 (en) * | 2010-12-16 | 2013-07-31 | 한국전자통신연구원 | Apparatus and method for monitoring progress |
JP2014112275A (en) * | 2012-12-05 | 2014-06-19 | Mitsubishi Electric Corp | Apparatus for creating logic drawing and test table |
WO2020039559A1 (en) * | 2018-08-23 | 2020-02-27 | ソニー株式会社 | Information processing device, information processing method, and work evaluation system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20080010543A1 (en) | Test planning assistance apparatus, test planning assistance method, and recording medium having test planning assistance program recorded therein | |
JP2008299762A (en) | Production management program | |
JPH06348720A (en) | Production development control display device | |
JP2018206000A (en) | Production planning system, production planning method and personnel ability calculation method | |
JP2000039904A (en) | Project management system | |
JP2000024850A (en) | Manual assembly line efficiency evaluation device | |
JPH0665458B2 (en) | Process control data display device | |
JP2002244716A (en) | Line capacity evaluation system | |
CN111311187B (en) | Project progress monitoring method, system and storage medium based on Revit | |
JP2006195677A (en) | Apparatus for managing project information | |
JP2009043188A (en) | Operation management support system, and program | |
JP3022423B2 (en) | Material requirement development method | |
JP2011048459A (en) | System and method for supporting project planning | |
JPH0394331A (en) | Device for controlling advancing state of software development | |
JPH08234977A (en) | Manifold progress management system for software project | |
JP4185994B2 (en) | Nurse placement method and system | |
JP2007280085A (en) | Workload computing unit, workload computing method, and workload computing program | |
JPH06332909A (en) | Plan managing system | |
JPH05233247A (en) | Method and device for managing software developing process | |
JP2006163833A (en) | Method and program for displaying time series | |
JP2012133669A (en) | Maintenance plan management system and maintenance plan management method | |
JPH07175668A (en) | Automatic center batch operating system | |
JP2004310317A (en) | Business support device | |
JP3234713B2 (en) | Schedule management method and schedule management device | |
JP2000181953A (en) | Work progress schedule, progress schedule display device, device for managing the cost or the like and medium recording program for managing the cost or the like |