JP2006195677A - Apparatus for managing project information - Google Patents

Apparatus for managing project information Download PDF

Info

Publication number
JP2006195677A
JP2006195677A JP2005005757A JP2005005757A JP2006195677A JP 2006195677 A JP2006195677 A JP 2006195677A JP 2005005757 A JP2005005757 A JP 2005005757A JP 2005005757 A JP2005005757 A JP 2005005757A JP 2006195677 A JP2006195677 A JP 2006195677A
Authority
JP
Japan
Prior art keywords
progress
project
task
input
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2005005757A
Other languages
Japanese (ja)
Inventor
Toshiro Abe
俊郎 阿部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Canon Inc
Original Assignee
Canon Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Canon Inc filed Critical Canon Inc
Priority to JP2005005757A priority Critical patent/JP2006195677A/en
Publication of JP2006195677A publication Critical patent/JP2006195677A/en
Withdrawn legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To improve accuracy of estimation of a project schedule, and to allow each person in charge to input the progress of tasks assigned. <P>SOLUTION: An apparatus for managing project information includes: a project task list creation means for creating a list of tasks to be accomplished in the project, a project progress summarization time point setting means for setting a plurality of time points for summarizing the progress of the project, a task progress input time point setting means for allowing the person in charge of the task to select a prescribed progress input time point from among the plurality of project progress summarization time points, a task progress input means for inputting the progress of the task at the task progress input time point, a project progress summarizable time point specifying means for specifying the summarizable time point of the project progress based on the progress of each task entered, and a project progress summarization means for summarizing the progress of the project at the summarizable time point of the project progress. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、ソフトウェア等を開発するプロジェクトにおけるタスクの進捗入力及び集計を行うプロジェクト情報管理装置に関する。   The present invention relates to a project information management apparatus that inputs and summarizes tasks in a project for developing software or the like.

PMBOK等のプロジェクト管理の方法論においては、プロジェクトで実施すべき全てのタスク(作業や要件)の一覧をWBS(ワーク・ブレークダウン・ストラクチャ)という階層構造を持った一覧表で管理することが推奨されている。   In project management methodologies such as PMBOK, it is recommended to manage a list of all tasks (work and requirements) to be implemented in the project in a list with a hierarchical structure called WBS (work breakdown structure). ing.

そして、一般に或る時点におけるプロジェクト進捗は、或る時点におけるそのプロジェクトの全てのタスク進捗を集計した結果として算出することができる。このとき、正しい集計結果を出すには、集計を行う時点で、全てのタスクの最新の進捗状況が入力されていることが前提である。   In general, the project progress at a certain point in time can be calculated as a result of summing up all the task progresses of the project at a certain point in time. At this time, in order to obtain a correct counting result, it is premised that the latest progress statuses of all tasks are inputted at the time of counting.

ところが、現実のプロジェクトでは、決まった進捗集計日に全てのタスク担当者が進捗入力をきちんと終えていることは難しい。従来、様々な方法で、タスク進捗の入力を促し、プロジェクト進捗を測定する方法が考案されている。例えば、特許文献1に記載された「プロジェクト進捗管理システム」では、担当者に対して、最新のタスク進捗報告を要求する方法が考案されている。   However, in a real project, it is difficult for all task managers to complete the progress input properly on a fixed progress count date. Conventionally, a method of prompting input of task progress and measuring project progress by various methods has been devised. For example, in the “project progress management system” described in Patent Document 1, a method for requesting the latest task progress report from a person in charge has been devised.

又、特許文献2に記載された「ソフトウェア進捗管理装置」では、タスク進捗を決まった日に入力させるのは困難という考えに基づき、タスク進捗の入力を促すのではなく、成果物の出来高を自動的に収集してタスクの実績と見なす方法が考案されている。   In addition, the “software progress management device” described in Patent Document 2 is based on the idea that it is difficult to input task progress on a fixed date. A method has been devised that can be collected and considered as task achievements.

特開平09−022429号公報JP 09-022429 A 特開2001−014157号公報JP 2001-014157 A

しかしながら、上記従来の技術例では、タスクの進捗状況を各担当者が入力し、それをプロジェクト全体の進捗として集計する際に、
1)各担当者がそれぞれ入力した時点での各タスクの進捗度(例えば%)を入力するが、プロジェクト全体としていつの時点での進捗度であるかが確定できない。
However, in the above conventional technology example, each person in charge inputs the progress status of the task, and when it is counted as the progress of the entire project,
1) Although the degree of progress (for example,%) of each task at the time when each person in charge inputs each is input, it is not possible to determine when the degree of progress of the entire project is.

2)進捗集計時点(例えば毎週1回、決まった曜日の決まった時間)には、必ず全担当者は入力を完了していないと正確にプロジェクト全体の進捗が集計できない。
という課題があった。
2) At the time of progress counting (for example, once every week, at a fixed time on a fixed day of the week), the progress of the entire project cannot be accurately calculated unless all the persons in charge have completed the input.
There was a problem.

本発明では、タスクごとの進捗を入力する際に、どの時点までの進捗度であるかを明示的に指定することにより、1)或る時点のプロジェクトの確定進捗が分かる、2)各担当者がタスクの進捗を入力する時間的猶予が与えられる、3)特に進捗入力が遅れている担当者に通知を出すことができるようになる。   In the present invention, when inputting the progress for each task, by specifying explicitly to what point the progress is, 1) the finalization of the project at a certain point can be known, and 2) each person in charge Is given a time delay to input the progress of the task. 3) In particular, the person in charge who is late in inputting the progress can be notified.

本発明の目的は、或る時点でのプロジェクト全体の確定進捗を集計し、集計時点ごとの進捗データを蓄積することによって、プロジェクト日程の見積もりの正確さを向上させるとともに、各担当者が自分に割り当てられたタスクの進捗入力を確実に行うことができるようにすることである。   The purpose of the present invention is to improve the accuracy of the estimation of the project schedule by accumulating the finalization progress of the entire project at a certain point of time, and accumulating progress data at each point of time of aggregation, and each person in charge is in charge of himself / herself. It is to be able to reliably input the progress of the assigned task.

前述の課題を解決するため、本発明のプロジェクト情報管理装置は、プロジェクトタスク一覧作成手段と、プロジェクト進捗集計時点設定手段と、タスク進捗入力時点設定手段と、タスク進捗入力手段と、プロジェクト進捗集計可能時点特定手段と、プロジェクト進捗集計手段と、タスク進捗入力確認手段と、タスク進捗入力遅延通知手段と、を設けた。   In order to solve the above-mentioned problems, the project information management device of the present invention is capable of project task list creation means, project progress count time setting means, task progress input time setting means, task progress input means, and project progress count. Time point specifying means, project progress totaling means, task progress input confirming means, and task progress input delay notifying means are provided.

プロジェクト進捗集計時点設定手段、タスク進捗入力時点設定手段、プロジェクト進捗集計可能時点特定手段、プロジェクト進捗集計手段、により、或る時点のプロジェクトの確定進捗が分かるようになる。   The project progress totaling time setting means, task progress input time setting means, project progress totalable time specifying means, and project progress totaling means make it possible to know the finalization of the project at a certain time.

又、タスク進捗入力時点設定手段、タスク進捗入力手段により、各担当者がタスクの進捗を入力する時間的猶予が与えられるようになる。   Also, the task progress input time setting means and the task progress input means allow each person in charge to give time to input the task progress.

更に、タスク進捗入力確認手段、タスク進捗入力遅延通知手段、により、特に進捗入力が遅れている担当者に通知を出すことができるようになる。   Further, the task progress input confirming means and the task progress input delay notifying means can particularly notify a person in charge of the progress input being delayed.

本発明では、タスクごとの進捗を入力する際に、どの時点までの進捗度であるかを明示的に指定することにより、1)或る時点のプロジェクトの確定進捗が分かる、2)各担当者がタスクの進捗を入力する時間的猶予が与えられる、3)特に、進捗入力が遅れている担当者に通知を出すことができるようになる。   In the present invention, when inputting the progress for each task, by specifying explicitly to what point the progress is, 1) the finalization of the project at a certain point can be known, and 2) each person in charge 3) In particular, the person in charge of the progress input can be notified.

本発明によれば、プロジェクトの進捗を集計する時点を予め決めておき、又、タスクごとの進捗を入力する際には、どの時点までの進捗度であるかを明示することにより、特定の時点のプロジェクトの確定進捗が計算できるようになる。   According to the present invention, when the progress of the project is totalized in advance, and when the progress for each task is input, by specifying the time until which the degree of progress is specified, The finalization progress of the project can be calculated.

又、別の効果として、現時点の全タスク進捗が入力されていなくても、それより過去の特定の時点のプロジェクト確定進捗、現時点でのプロジェクト推定進捗を計算することができるので、各担当者がタスクの進捗を入力する時間的猶予が与えられるようになる。   Another effect is that even if all current task progresses are not entered, the project confirmation progress at a specific point in the past and the estimated project progress at the present time can be calculated. Allow time to enter task progress.

更に、特定の時点のプロジェクト進捗を集計するに当たり、どのタスクの進捗入力が遅延しているかを検出することにより、進捗入力が遅れている担当者に通知を出すことができるようになる。   Furthermore, when the progress of a project at a specific time is aggregated, by detecting which task's progress input is delayed, it becomes possible to notify a person in charge of the progress input being delayed.

以下、本発明の実施の形態を添付図面に基づいて説明する。   Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.

<実施の形態1>
[システム構成]
本発明の実施の形態1に係るプロジェクト情報管理システム(以下、本システム)のサーバコンピュータ(以下、サーバ)及び各クライアントコンピュータ(以下、クライアント)は同様のハードウェア構成であり、図1はこれを示すブロック図である。
<Embodiment 1>
[System configuration]
A server computer (hereinafter referred to as a server) and each client computer (hereinafter referred to as a client) of a project information management system (hereinafter referred to as the system) according to Embodiment 1 of the present invention have the same hardware configuration, and FIG. FIG.

図1において、101はCPU、102はメインメモリ、103はROM、104は表示インターフェイス(I/F)、105はモニタ、106は入力I/F、107はキーボード、108はマウス、109はディスクI/F、110はハードディスクドライブ(HDD)、111はフロッピーディスクドライブ(FDD)、112はネットワークI/F、113はLAN、114はシステムバスである。   In FIG. 1, 101 is a CPU, 102 is a main memory, 103 is a ROM, 104 is a display interface (I / F), 105 is a monitor, 106 is an input I / F, 107 is a keyboard, 108 is a mouse, 109 is a disk I / F, 110 is a hard disk drive (HDD), 111 is a floppy disk drive (FDD), 112 is a network I / F, 113 is a LAN, and 114 is a system bus.

サーバ及び各クライアントは、ネットワークI/F112を介してLAN113に接続されており、サーバ上で動作している本システムと必要なデータのやり取りを行う。   The server and each client are connected to the LAN 113 via the network I / F 112, and exchange necessary data with the present system operating on the server.

[動作手順]
本システムのプログラム及びデータは、システムが動作するサーバ上のHDD110又はFDD111に格納されており、ディスクI/F109を介して、メインメモリ102に取り込まれる。プログラム及びデータがROM103に格納されている場合は、ROM103からメインメモリ102に読み込まれる。CPU101は、メインメモリ102にアクセスしてプログラムを動作させる。
[Operation procedure]
Programs and data of this system are stored in the HDD 110 or the FDD 111 on the server on which the system operates, and are taken into the main memory 102 via the disk I / F 109. When programs and data are stored in the ROM 103, they are read from the ROM 103 into the main memory 102. The CPU 101 accesses the main memory 102 and operates the program.

ユーザは、クライアントのモニタ105に表示されたWebブラウザ等の画面の指示に従い、クライアントのキーボード107又はマウス108を使用して、必要な情報を入力又は指示する。入力データは、クライアントの入力I/F106を介してCPU101に伝えられ、ネットワークI/F112とLAN113を介してサーバに送信される。サーバで処理された結果は、ネットワークI/F112とLAN113を介して、再びクライアントに送信され、クライアントのモニタ105のWebブラウザ等の画面に表示される。   The user inputs or instructs necessary information using the keyboard 107 or the mouse 108 of the client in accordance with an instruction on a screen of a Web browser or the like displayed on the client monitor 105. The input data is transmitted to the CPU 101 via the client input I / F 106 and transmitted to the server via the network I / F 112 and the LAN 113. The result processed by the server is transmitted to the client again via the network I / F 112 and the LAN 113, and displayed on the screen of the client monitor 105 such as a Web browser.

[プロジェクト進捗の集計]
図2は本発明の動作手順を示すフローチャートである。
[Aggregation of project progress]
FIG. 2 is a flowchart showing the operation procedure of the present invention.

先ず、プロジェクトリーダ(以下、リーダ)がプロジェクトで達成すべきタスク一覧を作成する(S101:プロジェクトタスク一覧作成手段)。   First, a project leader (hereinafter referred to as a leader) creates a task list to be achieved in the project (S101: project task list creation means).

図3はプロジェクトタスク一覧の例を示した図である。   FIG. 3 shows an example of a project task list.

タスク一覧は、Microsoft Excel等の汎用表計算ソフトウェア(以下、ソフト)、Microsoft Project等の汎用プロジェクト管理ソフト、これらに相当する機能を持つ独自ソフト等で作成し、サーバ上のデータベースに保管しておく。タスク一覧は、分類のため、適当に階層化されていても良い。特に、タスク一覧が階層化されている場合、子ノードの無い末端のタスクをリーフタスクと呼ぶことにする。各リーフタスクに対して、リーダはタスク担当者(以下、担当者)を割り当てる。又、各タスクには、着手予定日を定めておく。   The task list is created with general-purpose spreadsheet software (hereinafter referred to as software) such as Microsoft Excel, general-purpose project management software such as Microsoft Project, or original software having functions equivalent to these, and stored in a database on the server. . The task list may be appropriately hierarchized for classification. In particular, when the task list is hierarchized, a terminal task without a child node is called a leaf task. For each leaf task, the leader assigns a task person (hereinafter, person in charge). Each task has a scheduled start date.

リーダは、プロジェクトの進捗を集計したい複数の時点(プロジェクト進捗集計時点、又は簡単に、集計日と呼ぶ)をプロジェクトごとに予め設定しておく(S102:プロジェクト進捗集計時点設定手段)。   The leader sets in advance a plurality of time points (project progress time points, or simply referred to as a total date) at which the project progress is to be totaled for each project (S102: project progress total time point setting means).

例えば、毎月1日と15日に設定する、毎週月曜日に設定する、等がある。   For example, it is set on the 1st and 15th of every month, and set on every Monday.

以下、簡単のために、毎月1日と15日にプロジェクト進捗集計時点が設定してあり、タスクの進捗度はパーセント値で入力、現在、2004年6月10日である場合を想定して説明する。   In the following, for the sake of simplicity, it is assumed that the project progress count time is set on the 1st and 15th of each month, and the progress of the task is entered as a percentage, and is currently assumed to be June 10, 2004. To do.

各担当者は、自分の担当するタスクについて、タスクに着手してからタスクが完了するまでの期間、全てのプロジェクト進捗集計時点におけるタスク進捗度を入力しなければならない。   Each person in charge must input the degree of task progress at the time when all the project progresses are totaled during the period from the start of the task to the completion of the task.

例えば、図3のタスクT11やT12のように、未だ着手予定日に到達していないタスクは、進捗入力を行う必要はない。又、タスクT21やT22のように、既に前回のプロジェクト進捗集計時点(6月1日)以前に既に完了済であったタスクは、進捗入力を以後行なう必要はない。   For example, a task that has not yet reached the scheduled start date, such as tasks T11 and T12 in FIG. In addition, as with tasks T21 and T22, a task that has already been completed before the previous project progress count time (June 1) does not need to be input after that.

各担当者は、タスクの進捗度を入力する際には、どの時点(タスク進捗入力時点と呼ぶ)までのタスク進捗度を入力するか、を複数のプロジェクト進捗集計時点の中から1つ選択する(S103:タスク進捗入力時点設定手段)。   Each person in charge, when inputting the progress of the task, selects one of a plurality of project progress aggregation time points to which task progress is to be input (referred to as task progress input time). (S103: task progress input time setting means).

次に、各担当者は、S103で選択したタスク進捗入力時点におけるタスクの進捗度を入力する(S104:タスク進捗入力手段)。   Next, each person in charge inputs the progress of the task at the task progress input time selected in S103 (S104: task progress input means).

例えば、図3のタスクT24の次回プロジェクト進捗集計時点(6月15日) のタスク進捗を入力する際には、先ず、図3でT24の「情報」と表示されたリンクをクリックする。すると、図4のタスクプロパティ画面が表示される。ここでグレーアウトされている項目は、タスク担当者は編集不可の項目である。   For example, when inputting the task progress at the time of the next project progress aggregation (June 15) of task T24 in FIG. 3, first, the link labeled “Information” in T24 in FIG. 3 is clicked. Then, the task property screen of FIG. 4 is displayed. Items that are grayed out here are items that cannot be edited by the person in charge of the task.

T24は、前回プロジェクト進捗集計時点(6月1日) までのタスク進捗が入力済であるので、タスク担当者は「2004/6/15(次回集計日)」を選択してから、進捗度を入力すれば良い。ステータス欄は、進捗度と連動して「未着手」「着手」「完了」等と表示が自動的に変わるようにしても良く、進捗度とは独立してタスク担当者が入力するようにしても良い。   At T24, the task progress up to the previous project progress count (June 1) has already been entered, so the task manager selects “2004/6/15 (next count date)” and then the progress is shown. Enter it. In the status column, the display may change automatically such as “Unstarted”, “Started”, “Completed” etc. in conjunction with the progress, and the task person in charge inputs it independently of the progress Also good.

次回集計日(6月15日)までのタスク進捗として、確定した値を入力したときには、同時に「確定進捗」のチェックボックスにチェックを入れるようにすれば、未だタスク実施中の進捗を都度入力している途中の値なのか、次回集計日までにもうタスク進捗は変化しない確定した値なのか、が分かって良い。   When you enter a confirmed value as the task progress until the next aggregation date (June 15), if you check the “Confirmed progress” check box at the same time, you can enter the progress that is still in progress. You can tell whether it is a value that is in the middle of the process, or a fixed value that does not change the task progress by the next aggregation date.

タスクの進捗度は、パーセント値で入力したり、0から5までの整数値で入力したりする等の方法がある。例えば、ソフトウェア開発のタスク進捗度を、パーセント値で入力する場合、未着手(0%)、着手(20%)、設計完了(40%)、実装完了(60%)、単体テスト完了(80%)、完了(100%)等、ステータスに合わせた進捗度のガイドラインをプロジェクト単位や組織単位で決めておくことが必要である。   The progress of a task can be entered as a percentage value or as an integer value from 0 to 5, for example. For example, when the software development task progress is entered as a percentage, it has not yet started (0%), started (20%), design completed (40%), implementation completed (60%), unit test completed (80%) It is necessary to determine progress guidelines according to the status such as completion (100%) for each project or organization.

又、別の例として、図3のタスクT23のタスク進捗を入力する際には、先ず、図3でT23の「情報」と表示されたリンクをクリックする。すると、図5のタスクプロパティ画面が表示される。このタスクは、前回プロジェクト進捗集計時点(6月1日) のタスク進捗が未入力であるので、タスク担当者は、図5で「2004/6/1(前回集計日)」を選択してから、前回集計日時点の進捗度を入力し、更に、次回プロジェクト進捗集計時点(6月15日) のタスク進捗も入力しなければならない。   As another example, when inputting the task progress of task T23 in FIG. 3, first, the link labeled “Information” in T23 in FIG. 3 is clicked. Then, the task property screen of FIG. 5 is displayed. For this task, since the task progress at the time of the previous project progress aggregation (June 1) has not been entered, the person in charge of the task has selected “2004/6/1 (previous aggregation date)” in FIG. The progress at the time of the previous aggregation date must be entered, and the task progress at the time of the next project progress aggregation (June 15) must also be entered.

尚、図4及び図5の上部の各ボタンの意味は以下の通りである。   In addition, the meaning of each button of the upper part of FIG.4 and FIG.5 is as follows.

1)Apply:編集状態のときこのボタンを押すとデータが保存される。   1) Apply: When this button is pressed in the editing state, data is saved.

2)Edit(又はEditEnd):タスクプロパティ画面を開いたときは、編集不可状態(表示のみ)で、このとき「Edit」ボタンを押すと各プロパティは編集可能状態となり、ボタン表示は「EditEnd」に変わる。編集可能状態のとき「EditEnd」ボタンを押すと編集不可状態に戻る。   2) Edit (or EditEnd): When the task property screen is opened, it is in an edit-disabled state (display only). At this time, if the “Edit” button is pressed, each property is in an editable state, and the button display is changed to “EditEnd”. change. When the “EditEnd” button is pressed in the editable state, the editable state is restored.

3)Close:タスクプロパティ画面を閉じる。   3) Close: Close the task property screen.

又、図3のプロジェクトタスク一覧では、各タスクの進捗入力状況を色分けして表示すると分かり易い。例えば、タスクT23は、確定進捗入力日(5月15日)が前回集計日を過ぎているので、赤で表示する。又、進捗入力期限(6月1日)も過ぎているのでこれも赤で表示する。又、T25は、既に前回集計日(6月1日)を過ぎているのに未だ着手していないタスクなので、ステータス、着手予定日、確定進捗入力日を赤で表示する。現在進行中の(着手予定日を過ぎており、且つ、前回集計日時点で完了していない)タスクは、青で表示し、次回集計日(6月15日)までに進捗入力されるべきタスクである。図3では、この期間に現在進行中のタスクで、且つ、この期間に完了したタスクを、更に緑で色分けしている。   In the project task list of FIG. 3, it is easy to understand if the progress input status of each task is displayed in different colors. For example, the task T23 is displayed in red because the confirmed progress input date (May 15) has passed the previous aggregation date. Since the progress input deadline (June 1) has passed, this is also displayed in red. Since T25 is a task that has already passed the previous aggregation date (June 1) but has not yet started, the status, scheduled start date, and confirmed progress input date are displayed in red. Tasks that are currently in progress (the scheduled start date has passed and have not been completed as of the previous aggregation date) are displayed in blue, and tasks that should be entered by the next aggregation date (June 15) It is. In FIG. 3, tasks that are currently in progress during this period and tasks completed during this period are further color-coded in green.

プロジェクト進捗集計時点が来るたびに、システムは、適当な猶予期間をもって(例えば、プロジェクト進捗集計時点の2日後程度)プロジェクトの予定全タスク(予定タスクとは、その時点までに何らかの進捗があると計画されている、即ち、着手予定日を過ぎているタスクのこと)の進捗入力状況をチェックする。そして、プロジェクト進捗が集計可能である時点を特定する(S105:プロジェクト進捗集計可能時点特定手段)。   Each time the project progress count comes, the system will schedule all the planned tasks for the project (for example, about two days after the project progress count) (scheduled tasks are planned to have some progress up to that point). That is, that is, a task that has passed the scheduled start date). Then, a time point at which the project progress can be tabulated is identified (S105: Project progress tabular time point identifying means).

この特定方法は、以下の通りである。   This specifying method is as follows.

1)各プロジェクト進捗集計時点において、その時点までの予定全タスクの進捗が入力済であるかをチェックする。   1) At each project progress calculation point, check whether the progress of all scheduled tasks up to that point has been entered.

2)予定タスクのうち、最も進捗の入力が遅れているタスクを見つけ、そのタスク進捗入力時点をプロジェクト進捗集計可能時点と定める。   2) Find the task with the most delayed input of scheduled tasks, and determine the task progress input time as the project progress totalable time.

図3の例では、このまま次回プロジェクト進捗集計時点(6月15日)までタスク進捗入力がなかったとすると、最も進捗入力が遅れている予定タスクT23の、5月15日までのプロジェクト進捗が確定する。   In the example of FIG. 3, if there is no task progress input until the next project progress calculation time point (June 15), the project progress until May 15 of the scheduled task T23 with the latest progress input is confirmed. .

しかし、これでは進捗入力が遅れているタスクが1つあるだけで、プロジェクト進捗が計算できなくなるので、プロジェクト進捗集計時点におけるプロジェクト進捗(未入力者がいるので未確定推定値)は、進捗入力が遅れているタスクは進捗度に変化がない、と見なして計算しておけば良い。   However, since there is only one task whose progress input is delayed, the project progress cannot be calculated, so the project progress at the time of project progress aggregation (unestablished estimated value because there are unentered persons) It can be calculated by assuming that the delayed task has no change in progress.

そして、システムは、特定されたプロジェクト進捗集計可能時点におけるプロジェクト全体の進捗を集計する(S106:プロジェクト進捗集計手段)。   Then, the system totals the progress of the entire project at the specified project progress totaling possible time (S106: project progress totaling means).

簡単のために、プロジェクトのタスクが、図3に表示されているT11〜T12及びT21〜T28の全10タスク、各タスクの重み付けは同等であると仮定すると、各プロジェクト進捗集計時点におけるタスク進捗及びプロジェクト進捗は、図6のようになる。既に例示したように、T23の6月1日の進捗入力、T23,T24,T25,T28の6月15日の進捗入力は確定していないので、プロジェクト進捗も、6月1日と6月15日については、未確定推定値ということになる。図6では、数値の後に「?」印を記述している。計算は、単純に、
各タスクの進捗度の合計値(%)/プロジェクト全タスク数 … (式1)
を、各プロジェクト進捗集計時点ごとに算出すれば良い。
For the sake of simplicity, assuming that the tasks of the project are all 10 tasks T11 to T12 and T21 to T28 displayed in FIG. The project progress is as shown in FIG. As already illustrated, since the progress input on June 1 of T23 and the progress input on June 15 of T23, T24, T25, and T28 have not been confirmed, the project progress is also on June 1 and June 15. For days, this is an uncertain estimate. In FIG. 6, a “?” Mark is described after the numerical value. The calculation is simply
Total progress (%) of each task / total number of tasks in the project ... (Formula 1)
May be calculated for each project progress aggregation time point.

[進捗入力遅延の通知]
S105においてシステムは、プロジェクト進捗集計時点の「後」に、プロジェクト進捗が集計可能である時点を特定していたが、プロジェクト進捗集計時点の「前」(例えば、プロジェクト進捗集計時点の1日前程度)にS105の処理を行っておき、この時点で未だ次回集計日(例では6月15日)までの確定進捗が入力されていない「予定」タスクを抽出する(S107:タスク進捗入力確認手段)。
[Notification of progress input delay]
In S105, the system has specified a time point at which the project progress can be totaled “after” the project progress time point, but “before” the project progress time point (for example, about one day before the project progress time point). Then, the process of S105 is performed, and a “scheduled” task for which the confirmed progress up to the next counting date (June 15 in the example) has not been input at this time is extracted (S107: task progress input confirming means).

そして、システムはこれらのタスクの担当者に対して、タスク進捗が未入力であることを通知する(S108:タスク進捗入力遅延通知手段)。   Then, the system notifies the person in charge of these tasks that the task progress has not been input (S108: task progress input delay notification means).

通知の方法は、担当者に直接メールを送信する、担当者が通常最初にログインするポータルサイトに表示する、等の方法がある。   Notification methods include sending an e-mail directly to the person in charge, displaying on a portal site where the person in charge usually logs in first, and so on.

<他の実施の形態>
図2のS101の処理とS102の処理は順序が前後しても良い。即ち、プロジェクト進捗集計時点を先にプロジェクトごとに定めておき、その後、プロジェクトタスク一覧を作成しても良い。
<Other embodiments>
The order of the processing of S101 and the processing of S102 in FIG. That is, the project progress calculation time point may be determined for each project first, and then a project task list may be created.

本発明の実施の形態1に係るプロジェクト情報管理システムのハードウェア構成を示すブロック図である。It is a block diagram which shows the hardware constitutions of the project information management system which concerns on Embodiment 1 of this invention. 本発明の実施の形態1に係るプロジェクト情報管理システムの処理手順を示すフローチャートである。It is a flowchart which shows the process sequence of the project information management system which concerns on Embodiment 1 of this invention. プロジェクトタスク一覧を表示する画面の例を示す図である。It is a figure which shows the example of the screen which displays a project task list. 進捗入力が遅延していないタスクのタスクプロパティを表示及び編集する画面の例を示す図である。It is a figure which shows the example of the screen which displays and edits the task property of the task whose progress input is not delayed. 進捗入力が遅延しているタスクのタスクプロパティを表示及び編集する画面の例を示す図である。It is a figure which shows the example of the screen which displays and edits the task property of the task which progress input is overdue. 集計時点ごとのプロジェクト進捗を算出した例を示す図である。It is a figure which shows the example which calculated the project progress for every total time.

符号の説明Explanation of symbols

101 CPU
102 メインメモリ
103 ROM
104 表示インターフェイス(I/F)
105 モニタ
106 入力インターフェイス(I/F)
107 キーボード
108 マウス
109 ディスクインターフェイス(I/F)
110 HDD
111 FDD
112 ネットワークインターフェイス(I/F)
113 LAN
114 システムバス
101 CPU
102 Main memory 103 ROM
104 Display interface (I / F)
105 Monitor 106 Input interface (I / F)
107 Keyboard 108 Mouse 109 Disk interface (I / F)
110 HDD
111 FDD
112 Network interface (I / F)
113 LAN
114 System bus

Claims (3)

プロジェクトで達成すべきタスクの一覧を作成するプロジェクトタスク一覧作成手段と、プロジェクトの進捗を集計すべき複数の時点を設定するプロジェクト進捗集計時点設定手段と、前記複数のプロジェクト進捗集計時点からタスク担当者が特定の進捗入力時点を選択するタスク進捗入力時点設定手段と、前記タスク進捗入力時点におけるタスクの進捗度を入力するタスク進捗入力手段と、入力された各タスクの進捗度に基づいてプロジェクト進捗の集計可能時点を特定するプロジェクト進捗集計可能時点特定手段と、前記プロジェクト進捗の集計可能時点におけるプロジェクトの進捗を集計するプロジェクト進捗集計手段と、を有することを特徴とするプロジェクト情報管理装置。   Project task list creation means for creating a list of tasks to be achieved in the project, project progress count time setting means for setting a plurality of time points at which the project progress should be totaled, and a task person in charge from the plurality of project progress time points A task progress input time setting means for selecting a specific progress input time, a task progress input means for inputting a task progress at the task progress input time, and a project progress based on the input progress of each task. A project information management apparatus comprising: a project progress totaling time specifying unit for specifying a totalable time point; and a project progress totaling unit for totalizing a project progress at the project progress totaling time point. 特定のプロジェクト進捗集計時点におけるタスク進捗が入力済であるかどうかを確認するタスク進捗入力確認手段と、タスク進捗が未入力であることをタスク担当者に通知する タスク進捗入力遅延通知手段と、を有することを特徴とする請求項1記載のプロジェクト情報管理装置。   Task progress input confirmation means for confirming whether or not the task progress at the time of specific project progress aggregation has been input, and task progress input delay notification means for notifying the task staff that task progress has not been entered. The project information management apparatus according to claim 1, further comprising: 前記プロジェクト進捗集計可能時点特定手段は、タスク進捗入力の最も遅延しているタスクのタスク進捗入力時点をプロジェクト進捗の集計可能時点と判定することを特徴とする請求項1記載のプロジェクト情報管理装置。   2. The project information management apparatus according to claim 1, wherein the project progress totalable time specifying means determines a task progress input time of a task that is most delayed in task progress input as a project progress totalable time.
JP2005005757A 2005-01-12 2005-01-12 Apparatus for managing project information Withdrawn JP2006195677A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005005757A JP2006195677A (en) 2005-01-12 2005-01-12 Apparatus for managing project information

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005005757A JP2006195677A (en) 2005-01-12 2005-01-12 Apparatus for managing project information

Publications (1)

Publication Number Publication Date
JP2006195677A true JP2006195677A (en) 2006-07-27

Family

ID=36801731

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005005757A Withdrawn JP2006195677A (en) 2005-01-12 2005-01-12 Apparatus for managing project information

Country Status (1)

Country Link
JP (1) JP2006195677A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011022734A (en) * 2009-07-15 2011-02-03 Fujitsu Ltd Information processor
JP2013080417A (en) * 2011-10-05 2013-05-02 Toshiba Corp Data interface device of process management tool, data interface method, data interface program, and process control system
JP2014115707A (en) * 2012-12-06 2014-06-26 Danway Co Ltd Schedule management device and computer processing system including schedule management device
JP2023079537A (en) * 2021-11-29 2023-06-08 株式会社バルカー Construction management method, system, program, apparatus, and recording medium

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011022734A (en) * 2009-07-15 2011-02-03 Fujitsu Ltd Information processor
JP2013080417A (en) * 2011-10-05 2013-05-02 Toshiba Corp Data interface device of process management tool, data interface method, data interface program, and process control system
JP2014115707A (en) * 2012-12-06 2014-06-26 Danway Co Ltd Schedule management device and computer processing system including schedule management device
JP2023079537A (en) * 2021-11-29 2023-06-08 株式会社バルカー Construction management method, system, program, apparatus, and recording medium

Similar Documents

Publication Publication Date Title
Sacks et al. Construction flow index: a metric of production flow quality in construction
US8296170B2 (en) Process management system and method
Mans et al. Mining processes in dentistry
US20080010543A1 (en) Test planning assistance apparatus, test planning assistance method, and recording medium having test planning assistance program recorded therein
JPH08190584A (en) Work flow system
US20150242782A1 (en) Interactive Planning Method And Tool
US8108232B1 (en) System and method for project contract management
JP5003084B2 (en) Business monitoring device, business monitoring system, business monitoring method and program
JP2006195677A (en) Apparatus for managing project information
US20090222277A1 (en) Defining and implementing custom task processes
JP5196991B2 (en) Manufacturing process management apparatus, manufacturing process management method, and computer program
JP2018206000A (en) Production planning system, production planning method and personnel ability calculation method
JP2011145982A (en) System, method, and program for managing development process evaluation
JP2006313429A (en) Schedule management system, client terminal, schedule management server, schedule management apparatus, schedule management method, and schedule management program and recording medium
KR20180013474A (en) Method and apparatus for assisting strategy map management based on schedule-assessment item and todo-assessment item
JP4312789B2 (en) Business continuity analysis program and business continuity analyzer
US20110054865A1 (en) Simulator with user interface indicating parameter certainty
JPH06348720A (en) Production development control display device
JP2009187330A (en) Improvement guide system of job quality
JP2009157489A (en) Project progress management device and its control method, project progress management system, program and recording medium with the program recorded
JP2011048459A (en) System and method for supporting project planning
JP2007183729A (en) System and method for detecting and responding to problem sign in early stage
US20040220819A1 (en) Automated web-based tool to manage legal agreements and projects
JP2007122216A (en) Performance target analysis system and performance target analysis method
JPH086783A (en) Software quality guarantee supporting device

Legal Events