JPH07102639A - Column base hardware and construction method for steel frame column base section - Google Patents

Column base hardware and construction method for steel frame column base section

Info

Publication number
JPH07102639A
JPH07102639A JP6514294A JP6514294A JPH07102639A JP H07102639 A JPH07102639 A JP H07102639A JP 6514294 A JP6514294 A JP 6514294A JP 6514294 A JP6514294 A JP 6514294A JP H07102639 A JPH07102639 A JP H07102639A
Authority
JP
Japan
Prior art keywords
anchor bolt
column
hole
mortar
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6514294A
Other languages
Japanese (ja)
Inventor
Masami Sakai
正美 坂井
Akio Kimijima
昭男 君島
Osamu Kojima
修 小島
Shinji Suzuki
伸二 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Chuzo Co Ltd
Original Assignee
Nippon Chuzo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Chuzo Co Ltd filed Critical Nippon Chuzo Co Ltd
Priority to JP6514294A priority Critical patent/JPH07102639A/en
Publication of JPH07102639A publication Critical patent/JPH07102639A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE:To easily execute a construction work and reduce cost by obtaining column base hardware having a shape suitable for stress distribution as well as allowing the easy filling of post-cast mortar and the easy detection of a filling condition, and then using the hardware for the construction work. CONSTITUTION:This hardware is formed to be suitable for a stress condition occurring in a steel frame column 1, and an anchor bolt hole 23 where an anchor bolt 5 is inserted, is made large. Also, a filling hole 24 for post-cast mortar 11 and a filling condition detecting hole therefor are provided so as to be communicated with the anchor bolt hole 23.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、ビル等の建造物の露出
型鉄骨柱脚部において、鉄骨柱に生じる応力を確実に基
礎梁に伝達できるように耐力・剛性を確保した柱脚金
物、及びこの柱脚金物を使用した鉄骨柱脚部の施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an exposed steel column post of a building such as a building, in which a stress and rigidity are ensured so that the stress generated in the steel column can be reliably transmitted to the foundation beam, And a method of constructing a steel column base using the column base metal.

【0002】[0002]

【従来の技術】従来の露出型の鉄骨柱脚部構造の代表的
な例を図12に示す。この鉄骨柱脚部は、鉄骨柱1に溶
接された鋳鋼製の柱脚金物2を、アンボンド型アンカー
ボルト5と定着板6によって基礎コンクリート9及び基
礎鉄筋4に固定したものである。
2. Description of the Related Art A typical example of a conventional exposed steel column base structure is shown in FIG. This steel column base is a cast steel column base metal 2 welded to a steel frame column 1 fixed to a base concrete 9 and a base rebar 4 by an unbonded anchor bolt 5 and a fixing plate 6.

【0003】建方の手順は、先ず、鉄筋4及び定着板6
を有するアンボンド型アンカーボルト5を施工したの
ち、基礎コンクリート9を打設する。ついで、基礎コン
クリート9の上に中心塗部分モルタル10を施工し、こ
の上に図13に示すような鉄骨柱1の応力分布に適合し
た形状の柱脚金物2が溶接された鉄骨柱1を建込み、柱
脚金物2のアンカーボルト穴3をアンボンド型アンカー
ボルト5に嵌入し、ナット7で固定する。そして、柱脚
金物2と基礎コンクリート9との間に形成されたすき間
に後詰めモルタル11を施工し、硬化させる。なお、柱
脚金物2のアンカーボルト穴3の径d1 は、アンボンド
型アンカーボルト5の径dより5mm程度大きく形成さ
れている。
The procedure for erection is as follows. First, the reinforcing bar 4 and the fixing plate 6
After the unbonded anchor bolt 5 having the above is constructed, the foundation concrete 9 is poured. Next, a center-painted mortar 10 is applied onto the basic concrete 9, and a steel frame pillar 1 is constructed by welding a column base metal piece 2 having a shape suitable for the stress distribution of the steel frame pillar 1 as shown in FIG. Then, the anchor bolt holes 3 of the column base metal fitting 2 are fitted into the unbonded anchor bolts 5 and fixed with the nuts 7. Then, the backfilling mortar 11 is installed in the gap formed between the column base metal member 2 and the basic concrete 9 and hardened. The diameter d 1 of the anchor bolt hole 3 of the pillar pedestal 2 is larger than the diameter d of the unbonded anchor bolt 5 by about 5 mm.

【0004】図14は鉄骨柱脚部構造の他の代表的な例
を示すもので、鉄骨柱1に溶接された鋼板製のベースプ
レート12を、ボンド型アンカーボルト5aとアンカー
フレーム15によって基礎コンクリート9と基礎鉄筋4
に固定したものである。
FIG. 14 shows another typical example of a steel column base structure, in which a base plate 12 made of a steel plate welded to the steel column 1 is used as a base concrete 9 by a bond type anchor bolt 5a and an anchor frame 15. And basic rebar 4
It is fixed to.

【0005】建方の手順は、先ず、基礎鉄筋4及びアン
カーフレーム15とアンカーボルト5aを施工したの
ち、基礎コンクリート9を打設する。ついで、図15に
示すように基礎コンクリート9の上に中心塗部分モルタ
ル10を施工し、この上にベースプレート12が溶接さ
れた鉄骨柱1を建込み、ボンド型アンカーボルト5aに
注入座金16を介してナット7で固定する。そして、ベ
ースプート12に設けたアンカーボルト穴13とアンカ
ーボルト5aとの間のすき間、及びベースプレート12
と基礎コンクリート9との間のすき間に、注入座金16
の注入口17から後詰めモルタル11を注入し、硬化さ
せる。なお、ベースプレート12のアンカーボルト穴1
3の径d2 は、アンカーボルト5aの径より20mm程
度大きく形成されている。
In the procedure of erection, first, the foundation rebar 4, the anchor frame 15 and the anchor bolt 5a are constructed, and then the foundation concrete 9 is poured. Next, as shown in FIG. 15, a center-coated part mortar 10 is constructed on the foundation concrete 9, the steel frame column 1 to which the base plate 12 is welded is built on this, and the injection washer 16 is inserted into the bond type anchor bolt 5a. And fix with nut 7. Then, the clearance between the anchor bolt hole 13 and the anchor bolt 5a provided in the base plate 12, and the base plate 12
The injection washer 16 in the gap between the base and the concrete 9
The back-filled mortar 11 is injected from the injection port 17 of and is cured. In addition, the anchor bolt hole 1 of the base plate 12
The diameter d 2 of 3 is larger than the diameter of the anchor bolt 5a by about 20 mm.

【0006】[0006]

【発明が解決しようとする課題】図12、図13に示し
た従来の工法では、柱脚金物2のアンカーボルト穴3の
径はアンボンド型アンカーボルト5の径より僅かに5m
m程度大きいだけなので、鉄骨柱1の建方に際して、ア
ンボンド型アンカーボルト5の位置と、柱脚金物2のア
ンカーボルト穴3の位置に十分な精度を確保しなければ
ならず、このため施工がきわめて面倒で多くの工数を要
するという問題がある。
In the conventional method shown in FIGS. 12 and 13, the diameter of the anchor bolt hole 3 of the column base metal member 2 is only 5 m, which is smaller than the diameter of the unbonded anchor bolt 5.
Since it is only about m large, it is necessary to secure sufficient accuracy in the position of the unbonded type anchor bolt 5 and the position of the anchor bolt hole 3 of the column base metal fitting 2 when constructing the steel frame column 1. There is a problem that it is extremely troublesome and requires a lot of man-hours.

【0007】また、図14、図15に示した従来の工法
では、応力分布に適合した形状の柱脚金物の代りに、力
学的に不必要な部分を有する鋼板製のベースプレート1
2を使用していること、及び特殊な構造の注入座金16
を介して後詰めモルタル11を注入するようにしている
ため、コストが割高になり、その上後詰めモルタル11
の注入作業が複雑になるという問題がある。
Further, in the conventional method shown in FIGS. 14 and 15, instead of a column base metal member having a shape adapted to the stress distribution, a steel plate base plate 1 having a mechanically unnecessary portion is formed.
2 and the special structure of the injection washer 16
Since the stuffing mortar 11 is injected via the above, the cost is high, and the stuffing mortar 11 is also expensive.
However, there is a problem that the injection work becomes complicated.

【0008】本発明は、上記の課題を解決すべくなされ
たもので、応力分布に適合した形状を有し、その上後詰
めモルタルの注入が容易かつ注入状態を確実に検知する
ことのできる柱脚金物を得ることを目的としたものであ
る。また、上記の柱脚金物を使用することにより、施工
が容易でコストを低減できる鉄骨柱脚部の施工方法を得
ることを目的としたものである。
The present invention has been made to solve the above-mentioned problems, and has a shape adapted to the stress distribution, and on top of that, the post-filling mortar can be easily injected and the injection state can be reliably detected. The purpose is to obtain a metal fitting. Further, it is an object of the present invention to obtain a method of constructing a steel column base by using the above-described column pedestal, which is easy to construct and can reduce the cost.

【0009】[0009]

【課題を解決するための手段及び作用】本発明に係る柱
脚金物は、鉄骨柱に生じる応力状態に適合した形状に構
成され、アンカーボルト穴を大きく形成すると共に、こ
のアンカーボルト穴に連通して後詰めモルタルの注入穴
及び後詰めモルタルの充填状態を検知する充填検知穴を
設けたものである。
The pedestal metal article according to the present invention is configured to have a shape adapted to the stress state generated in the steel frame column, has a large anchor bolt hole, and communicates with the anchor bolt hole. And a filling detection hole for detecting the filling state of the back-filled mortar.

【0010】また、上記の柱脚金物において、アンカー
ボルト穴の径を、アンカーボルトの径より15mm〜3
0mm、好ましくは20mm程度大きく形成したもので
ある。さらに、アンカーボルトに柱脚金物を固定する際
に用いる楕円形の座金を備えたものである。
Further, in the above-mentioned column pedestal, the diameter of the anchor bolt hole is 15 mm to 3 mm larger than the diameter of the anchor bolt.
It is formed to have a size of about 0 mm, preferably about 20 mm. Further, the anchor bolt is provided with an elliptical washer used for fixing the pillar pedestal.

【0011】また、本発明に係る鉄骨柱脚部の施工方法
は、鉄骨柱に生じる応力状態に適合した形状に構成さ
れ、基礎コンクリートに埋設されたアンカーボルトに挿
入するアンカーボルト穴を大きく形成すると共に、この
アンカーボルト穴に連通して後詰めモルタルの注入穴及
び充填検知穴が設けられた柱脚金物が固定された鉄骨柱
を有し、この鉄骨柱の柱脚金物を基礎コンクリート上に
施工した中心塗部分モルタル上に設置し、アンカーボル
ト穴をアンカーボルトに挿入して固定し、ついで、注入
穴からアンカーボルト穴とアンカーボルトの間及び柱脚
金物と基礎コンクリートの間に形成されたすき間に後詰
めモルタルを注入し、必要に応じて柱脚金物と基礎コン
クリートの間に柱脚金物の周囲から後詰めモルタルを注
入し、充填検知穴から後詰めモルタルが溢れたときは注
入を中止して硬化させるようにしたものである。さら
に、柱脚金物のアンカーボルト穴をアンカーボルトに挿
入して固定するにあたり、アンカーボルトに楕円形の座
金を挿入してナットで固定するようにしたものである。
Further, the method of constructing the steel column foot portion according to the present invention is configured to have a shape adapted to the stress state generated in the steel column, and the anchor bolt hole to be inserted into the anchor bolt embedded in the basic concrete is formed large. At the same time, it has a steel column to which the column pedestal with the filling hole and the filling detection hole for the backfilled mortar in communication with the anchor bolt hole is fixed, and the column pedestal of this steel column is constructed on the foundation concrete. Installed on the mortar that has been painted centrally, insert the anchor bolt holes into the anchor bolts to fix them, and then insert the holes from the injection holes between the anchor bolt holes and the anchor bolts and between the column pedestals and the foundation concrete. Back-filled mortar into the space between the column base metal and the foundation concrete, if necessary. When justified mortar overflows are those so as to cure discontinue infusion. Further, when inserting and fixing the anchor bolt hole of the column pedestal into the anchor bolt, an elliptical washer is inserted into the anchor bolt and fixed with a nut.

【0012】このように、本発明に係る柱脚金物及び鉄
骨柱脚部の施工方法は、柱脚金物をこれに加わる応力状
態に合致した合理的な構造としたこと、柱脚金物のアン
カーボルト穴の径を大きく形成したこと、アンカーボル
ト穴に連通する専用の後詰めモルタルの注入穴及び充填
検知穴を設けたこと、及び楕円形の座金を使用すること
を特徴とするものであり、これにより、材料の無駄がな
く、アンカーボルトに対する鉄骨柱の建方が容易で、後
詰めモルタルを確実に充填することができる。
As described above, the method of constructing a column pedestal and a steel frame column pedestal according to the present invention is such that the column pedestal has a rational structure that matches the stress state applied thereto, and the anchor bolt of the column pedestal. It is characterized by forming a large hole diameter, providing a dedicated backfill mortar injection hole and filling detection hole communicating with the anchor bolt hole, and using an oval washer. As a result, there is no waste of material, it is easy to construct the steel frame column with respect to the anchor bolt, and it is possible to reliably fill the back-filled mortar.

【0013】[0013]

【実施例】【Example】

実施例1 図1は本発明の第1の実施例の構成説明図である。な
お、図12〜図15で説明した従来技術と同じ部分には
これと同じ符号を付し、説明を省略する。図において、
20は柱脚金物で、図2にその平面図を、また、図3に
図2のA−A拡大一部断面図を示す。
First Embodiment FIG. 1 is a configuration explanatory diagram of a first embodiment of the present invention. The same parts as those of the conventional technique described with reference to FIGS. 12 to 15 are denoted by the same reference numerals, and the description thereof will be omitted. In the figure,
Reference numeral 20 denotes a column base metal piece, and FIG. 2 is a plan view thereof, and FIG. 3 is an enlarged partial sectional view taken along line AA of FIG.

【0014】この柱脚金物20は、鉄骨柱1の応力分布
に適合した形状に構成された鋳鋼製又は鍛鋼製のもの
で、中心部には角形鋼管柱1の溶接部21が突設されて
おり、その周囲の対称位置には複数の座22が設けられ
ている。そして、各座22の中心部には、図4に示すよ
うに、アンカーボルト穴23が貫設され、さらに、アン
カーボルト穴23の両側には、アンカーボルト穴23に
連通し、上面及び座22の側壁に開口する後詰めモルタ
ルの注入穴24及び後詰めモルタル11の充填状態を検
知する充填検知穴25が設けられている。なお、アンカ
ーボルト穴23の径d3 は、図5に示すように、アンボ
ンド型アンカーボルト5の径dより15mm〜30mm
程度大きく形成されている。
This column base metal 20 is made of cast steel or forged steel having a shape adapted to the stress distribution of the steel frame column 1, and a welded portion 21 of the rectangular steel tube column 1 is projected at the center thereof. And a plurality of seats 22 are provided at symmetrical positions around it. As shown in FIG. 4, anchor bolt holes 23 are provided at the center of each seat 22, and the anchor bolt holes 23 are communicated with the anchor bolt holes 23 on both sides of the upper surface and the seat 22. A filling hole 24 for the backfilled mortar and a filling detection hole 25 for detecting the filling state of the backfilled mortar 11 are provided in the side wall of the. The diameter d 3 of the anchor bolt hole 23 is 15 mm to 30 mm from the diameter d of the unbonded anchor bolt 5 as shown in FIG.
It is formed to a large extent.

【0015】上記のような柱脚金物20が固定された鉄
骨柱1を建込むには、先ず、基礎鉄筋4及び定着板6を
有するアンボンド型アンカーボルト5が施工された基礎
コンクリート9上に中心塗部分モルタル10を施工し、
その上に柱脚金物20が溶接された鉄骨柱1を建込み、
アンボンド型アンカーボルト5に座22の上部を覆う大
きさの平座金8aを介してナット7を螺入し、固定す
る。
In order to construct the steel frame column 1 to which the column base metal fitting 20 is fixed as described above, first, the center is placed on the foundation concrete 9 on which the unbond type anchor bolt 5 having the foundation rebar 4 and the fixing plate 6 is constructed. Apply painted part mortar 10,
Build the steel column 1 with the column base metal 20 welded on it,
The nut 7 is screwed into and fixed to the unbonded anchor bolt 5 through a flat washer 8a having a size that covers the upper portion of the seat 22.

【0016】ついで、柱脚金物20の座22の側壁に開
口する注入穴24から、アンボンド型アンカーボルト5
とアンカーボルト穴23との間に形成されたすき間、及
び柱脚金物20と基礎9との間に形成されたすき間に後
詰めモルタル11を注入し、硬化される。このとき、柱
脚金物20に設けた充填検知穴25から後詰めモルタル
11が溢れるまで注入することにより、施工を確実に行
なうことができる。
Next, the unbonded anchor bolt 5 is inserted through the injection hole 24 opened in the side wall of the seat 22 of the column base metal member 20.
The stuffed mortar 11 is poured into the gap formed between the base bolt 9 and the anchor bolt hole 23 and the gap formed between the pedestal metal fitting 20 and the foundation 9 and hardened. At this time, the work can be reliably performed by injecting the filling mortar 11 from the filling detection hole 25 provided in the column base metal member 20 until it overflows.

【0017】この場合、柱脚金物20と基礎コンクリー
ト9との間に形成されたすき間には、柱脚金物20の周
囲から後詰めコンクリート11を注入してもよい。な
お、柱脚金物20のアンカーボルト穴23の径d3 は、
前述のようにアンボンド型アンカーボルト5の径dより
15mm〜30mm程度大きく形成されているが、実験
の結果によれば、柱脚金物20の強度、鉄骨柱1の建方
及び後詰めモルタル11の注入の容易さなどの点から、
両者の差は20mm程度(したがって、両者間のすき間
は10mm程度)が好ましいことが明らかになった。
In this case, the backfilled concrete 11 may be poured from the periphery of the column base metal fitting 20 into the gap formed between the column base metal base 20 and the basic concrete 9. In addition, the diameter d 3 of the anchor bolt hole 23 of the column base metal fitting 20 is
As described above, it is formed to be larger than the diameter d of the unbonded anchor bolt 5 by about 15 mm to 30 mm, but according to the results of the experiment, the strength of the column base metal 20, the erection of the steel column 1, and the rear-filling mortar 11 are determined. In terms of ease of injection,
It has become clear that the difference between the two is preferably about 20 mm (thus, the gap between the two is about 10 mm).

【0018】このように構成した本実施例によれば、鉄
骨柱1の応力(軸力、曲げモーメント及びせん断力)
は、柱脚金物20、中心塗部分モルタル10と後詰めモ
ルタル11、アンボンド型アンカーボルト5を介して、
基礎コンクリート9及び基礎鉄筋4に伝えられる。
According to the present embodiment constructed as described above, the stress (axial force, bending moment and shearing force) of the steel frame column 1
Is through the column base metal 20, the central coating part mortar 10, the backfilled mortar 11, and the unbonded anchor bolt 5.
It is transmitted to the base concrete 9 and the base rebar 4.

【0019】実施例2 本発明の第2の実施例を図6、図7に示す。本実施例は
第1の実施例のアンボンド型アンカーボルト5に代え
て、4本のボンド型アンカーボルト5aにより鉄骨柱1
に溶接された柱脚金物20を固定するようにしたもの
で、その他の構成及びその施工方法は、第1の実施例の
場合と同様である。なお、第1、第2の実施例において
は、鉄骨柱1として角形鋼管を用いた場合を示したが、
円形鋼管を用いてよい。また、特に説明しなかったが、
図10に示すようなアンカーフレーム15を使用した工
法の場合にも本発明を実施することができる。
Second Embodiment A second embodiment of the present invention is shown in FIGS. In this embodiment, instead of the unbonded type anchor bolts 5 of the first embodiment, four bond type anchor bolts 5a are used to construct the steel column 1.
The column base metal member 20 welded to is fixed, and the other configurations and the construction method thereof are the same as those in the first embodiment. In addition, in the first and second embodiments, the case where the square steel pipe is used as the steel frame column 1 is shown.
Round steel pipe may be used. Also, although I did not specifically explain,
The present invention can also be implemented in the case of a construction method using the anchor frame 15 as shown in FIG.

【0020】実施例3 図8は本発明の第3の実施例の平面図、図9はそのB−
B拡大断面図である。図において、20は鋳鋼製又は鍜
鋼製の柱脚金物で、鉄骨柱1の応力分布に適合した形状
の基盤の中心部には、鉄骨柱1の溶接部21が突設され
ており、溶接部21の内側は重量を軽減するために凹状
に形成されている。23は柱脚金物20の四隅に貫設し
たアンカーボルト穴で、その両側にはアンカーボルト穴
23に連通し、上面が開口し外端部が閉じられた断面半
円状の後詰めモルタルの注入穴24、及び後詰めモルタ
ルの充填状態を検知する充填検知穴25がそれぞれ設け
られている。なお、アンカーボルト穴23の径は、アン
カーボルト5の径より15mm〜30mm程度、好まし
くは20mm程度大きく形成されている。
Embodiment 3 FIG. 8 is a plan view of a third embodiment of the present invention, and FIG.
It is a B expanded sectional view. In the figure, 20 is a cast-iron or wrought-steel column pedestal, and a welded portion 21 of the steel column 1 is projected at the center of the base having a shape adapted to the stress distribution of the steel column 1. The inside of the portion 21 is formed in a concave shape to reduce the weight. Reference numeral 23 denotes anchor bolt holes penetrating at four corners of the column base metal fitting 20, communicating with the anchor bolt holes 23 on both sides thereof, and injecting rearward-filled mortar having a semicircular cross section whose upper surface is open and whose outer end is closed. A hole 24 and a filling detection hole 25 for detecting the filling state of the back-filled mortar are provided respectively. The diameter of the anchor bolt hole 23 is larger than the diameter of the anchor bolt 5 by about 15 mm to 30 mm, preferably about 20 mm.

【0021】27は柱脚金物20をアンカーボルト5に
固定する際に、柱脚金物20の上面とナット26との間
に配設する座金で、図10に示すようにその外形は楕円
形状に形成されており、中心部にはアンカーボルト5の
径より僅かに大きいアンカーボルト挿入穴28が設けら
れている。
Reference numeral 27 denotes a washer which is arranged between the upper surface of the column base metal piece 20 and the nut 26 when the column base metal piece 20 is fixed to the anchor bolt 5, and its outer shape is elliptical as shown in FIG. An anchor bolt insertion hole 28 that is slightly larger than the diameter of the anchor bolt 5 is provided in the center portion.

【0022】上記のような柱脚金物20が固定された鉄
骨柱1の建込み手順は、実施例1,2の場合とほぼ同じ
であるが、柱脚金物20のアンカーボルト穴23をアン
カーボルト5aにそれぞれ嵌入したのち、座金27のア
ンカーボルト挿入穴28をアンカーボルト5aに嵌入し
て柱脚金物20の上面に位置させ、ナット26を締付け
て固定する。
The procedure for assembling the steel frame pillar 1 to which the column base metal fitting 20 is fixed is almost the same as in the first and second embodiments, but the anchor bolt hole 23 of the column base metal fitting 20 is inserted into the anchor bolt. 5a, respectively, and then the anchor bolt insertion hole 28 of the washer 27 is fitted into the anchor bolt 5a to be positioned on the upper surface of the column base metal member 20, and the nut 26 is tightened and fixed.

【0023】このとき、アンカーボルト5aの施工が良
好で位置精度が確保されている場合は、柱脚金物20を
据付けたときに、そのアンカーボルト穴23がアンカー
ボルト5aの外周にこれとほぼ同心的に位置する。この
場合は、例えば、図11(a)に示すように、座金27
の長軸を柱脚金物20の隅部と中心を結ぶ線上、したが
って、モルタルの注入穴24と充填検知穴25と直交し
て配置すればよい。
At this time, if the anchor bolt 5a is well constructed and the positional accuracy is secured, the anchor bolt hole 23 is substantially concentric with the outer periphery of the anchor bolt 5a when the column base metal fitting 20 is installed. Position. In this case, for example, as shown in FIG.
The long axis may be arranged on the line connecting the corner and the center of the column base metal 20, and therefore orthogonal to the mortar injection hole 24 and the filling detection hole 25.

【0024】これにより、座金27の長軸側の両端部は
柱脚金物20の上面に当接して確実に座金の機能を発揮
し、また、短軸側の両側にはモルタルの注入穴24と充
填検知穴25が開口し、容易にモルタルを注入し、ま
た、モルタルの充填状態を検知することができる。
As a result, both ends of the washer 27 on the major axis side are brought into contact with the upper surface of the pedestal metal fitting 20 to reliably perform the function of the washer, and mortar injection holes 24 are provided on both sides of the minor axis. The filling detection hole 25 is opened so that the mortar can be easily injected and the filling state of the mortar can be detected.

【0025】また、アンカーボルト5aがアンカーボル
ト穴23内の偏った位置にあるときは、例えば図11
(b)又は(c)に示すように、座金27をその長軸が
柱脚金物20の一方の縁部又は他方の縁部とほぼ平行に
なるように配置することにより、座金27の長軸側の両
端部は柱脚金物20の上面に当接し、また、座金27の
両側にはモルタルの注入穴24と充填検知穴25が開口
する。
Further, when the anchor bolt 5a is located at a biased position in the anchor bolt hole 23, for example, as shown in FIG.
As shown in (b) or (c), by disposing the washer 27 such that its long axis is substantially parallel to one edge or the other edge of the column base metal fitting 20, the long axis of the washer 27 is set. Both end portions of the side contact the upper surface of the column base metal member 20, and a mortar injection hole 24 and a filling detection hole 25 are opened on both sides of the washer 27.

【0026】このように、本実施例においては、座金2
7を楕円形状に形成してその中心部にアンカーボルト挿
入穴28を設けたので、アンカーボルト5aに対する柱
脚金物20の位置精度が充分に確保されていない場合で
も、座金27の取付角度を適宜変えることにより座金の
機能を確実に発揮すると共に、モルタルの注入穴24及
びモルタルの充填状態を検知する充填検知穴25の開口
を確保することができる。
Thus, in this embodiment, the washer 2
Since 7 is formed into an elliptical shape and the anchor bolt insertion hole 28 is provided in the center thereof, the mounting angle of the washer 27 can be appropriately adjusted even when the positional accuracy of the column base metal member 20 with respect to the anchor bolt 5a is not sufficiently ensured. By changing it, the function of the washer can be surely exhibited, and the openings of the mortar injection hole 24 and the filling detection hole 25 for detecting the filling state of the mortar can be secured.

【0027】上記の各実施例では、鉄骨柱として角形鋼
管を用いた場合を示したが、円形鋼管を用いてもよい。
また、特に説明しなかったが、図14に示すようなアン
カーフレームを使用した工法の場合にも本発明を実施す
ることができる。さらに、第3の実施例に示した座金
は、第1、第2の実施例あるいは従来の工法の場合にも
実施することができる。
In each of the above-mentioned embodiments, the case where the square steel pipe is used as the steel column is shown, but a circular steel pipe may be used.
Further, although not particularly described, the present invention can be implemented even in the case of a construction method using an anchor frame as shown in FIG. Furthermore, the washer shown in the third embodiment can be applied to the first and second embodiments or the conventional method.

【0028】[0028]

【発明の効果】上記のように、本発明に係る柱脚金物
は、鋳鋼又は鍛鋼によりこの柱脚金物に加わる応力状態
に合致した合理的な構造とし、柱脚金物のアンカーボル
ト穴の径をアンカーボルトの径より15mm〜30mm
程度大きく形成すると共にアンカーボルト穴に連通する
専用の後詰めモルタルの注入穴と充填検知穴を設け、ア
ンカーボルト穴とアンカーボルトとのすき間、及び柱脚
金物と基礎コンクリートとのすき間に、注入穴24から
後詰めモルタル11を注入し、また、必要に応じて柱脚
金物と基礎コンクリートの間に柱脚金物の周囲から後詰
めモルタルを注入して、充填検知穴から後詰めモルタル
が溢れ出したときは注入を中止し、硬化させるようにし
たもので、次のような顕著な効果を得ることができる。
As described above, the pillar pedestal according to the present invention has a rational structure made of cast steel or forged steel in accordance with the stress state applied to the pillar pedestal, and the diameter of the anchor bolt hole of the pillar pedestal is adjusted. 15mm to 30mm from the diameter of the anchor bolt
The injection hole and the filling detection hole for the special stuffing mortar that is formed to a large size and communicates with the anchor bolt hole are provided, and the injection hole is provided in the gap between the anchor bolt hole and the anchor bolt The backfilling mortar 11 was injected from 24, and the backfilling mortar overflowed from the filling detection hole by injecting the backfilling mortar from the periphery of the column base metal between the column base metal and the foundation concrete as required. In this case, the injection is stopped and the resin is cured, and the following remarkable effects can be obtained.

【0029】(1)柱脚金物を鉄骨柱に生じる応力分布
に適合した形状としたので、材料の無駄がない。 (2)柱脚金物のアンカーボルト穴を大きく構成したの
で、アンカーボルトに対する位置精度が充分に確保され
ていない場合でも鉄骨柱の建方を容易に行なうことがで
き、その上後詰めモルタルの充填も容易である。
(1) Since the pillar pedestal has a shape adapted to the stress distribution generated in the steel frame pillar, there is no waste of material. (2) Since the anchor bolt hole of the column base metal is configured to be large, it is possible to easily construct the steel column even if the positional accuracy with respect to the anchor bolt is not sufficiently secured. Is also easy.

【0030】(3)柱脚金物に後詰めモルタルの注入穴
及び充填検知穴を設けたので、従来のような特殊構造の
注入座金も不要になり、施工、後詰めモルタルの注入が
容易で、その上後詰めモルタルの充填状態を確実に検知
することができる。 (4)これらのことから、施工の省力化、工期の短縮、
コストの低減をはかることができる。
(3) Since the post-filling mortar injection hole and the filling detection hole are provided in the column base metal, there is no need for a conventional injection washer having a special structure, and construction and injection of the post-filling mortar are easy. Moreover, it is possible to reliably detect the filling state of the back-filled mortar. (4) From the above, labor saving in construction, shortening of construction period,
The cost can be reduced.

【0031】(5)また、中心部にアンカーボルト挿入
穴を有する座金を介して柱脚金物を固定するようにした
ので、アンカーボルトに対する柱脚金物の位置精度が充
分に確保されていない場合でも、座金の取付角度を適宜
変えることにより座金の機能を発揮すると共に、モルタ
ル注入穴及びモルタルの充填状態を検知する充填検知穴
の開口を確保することができる。
(5) Further, since the pedestal metal object is fixed through the washer having the anchor bolt insertion hole at the center, even if the positional accuracy of the pedestal metal object with respect to the anchor bolt is not sufficiently secured. By properly changing the mounting angle of the washer, the function of the washer can be exhibited, and the opening of the mortar injection hole and the filling detection hole for detecting the filling state of the mortar can be secured.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の第1の実施例を説明するための縦断面
図である。
FIG. 1 is a vertical cross-sectional view for explaining a first embodiment of the present invention.

【図2】図1の柱脚金物の平面図である。FIG. 2 is a plan view of the column pedestal of FIG.

【図3】一部を図2のA−A断面で示した柱脚金物の側
面図である。
3 is a side view of a pedestal metal piece, a part of which is taken along the line AA in FIG. 2. FIG.

【図4】図2の柱脚金物の要部の平面図(a)及び側面
図(b)である。
FIG. 4 is a plan view (a) and a side view (b) of a main part of the column pedestal of FIG.

【図5】第1の実施例の施工状態を示す説明図である。FIG. 5 is an explanatory diagram showing a construction state of the first embodiment.

【図6】本発明の第2の実施例を説明するための断面図
である。
FIG. 6 is a sectional view for explaining a second embodiment of the present invention.

【図7】図6の柱脚金物の平面図である。FIG. 7 is a plan view of the column pedestal of FIG.

【図8】本発明の第3の実施例の柱脚金物の平面図であ
る。
FIG. 8 is a plan view of a column pedestal of a third embodiment of the present invention.

【図9】一部を図8のB−B断面で示した柱脚金物の側
面図である。
9 is a side view of a pedestal metal piece, a part of which is taken along the line BB of FIG. 8. FIG.

【図10】座金の実施例の平面図及び側面図である。FIG. 10 is a plan view and a side view of an embodiment of a washer.

【図11】(a),(b),(c)は第3の実施例の作
用説明図である。
11 (a), (b) and (c) are explanatory views of the operation of the third embodiment.

【図12】従来の鉄骨柱脚部構造の一例の断面図であ
る。
FIG. 12 is a cross-sectional view of an example of a conventional steel column base structure.

【図13】図12の柱脚金物の平面図(a)及びそのB
−B断面図(b)である。
FIG. 13 is a plan view (a) of the column base metal fitting of FIG. 12 and B thereof.
-B is a sectional view (b).

【図14】従来の鉄骨柱脚部構造の他の例の斜視図であ
る。
FIG. 14 is a perspective view of another example of the conventional steel column base structure.

【図15】図14の従来例の施工状態を示す説明図であ
る。
FIG. 15 is an explanatory view showing a construction state of the conventional example of FIG.

【符号の説明】[Explanation of symbols]

1 鉄骨柱 4 鉄筋 5,5a アンカーボルト 9 基礎コンクリート 20 柱脚金物 22 座 23 アンカーボルト穴 24 注入穴 25 充填検知穴 26 ナット 27 座金 28 アンカーボルト挿入穴 1 Steel column 4 Reinforcing bar 5, 5a Anchor bolt 9 Foundation concrete 20 Column base metal fittings 22 Seat 23 Anchor bolt hole 24 Injection hole 25 Filling detection hole 26 Nut 27 Washer 28 Anchor bolt insertion hole

フロントページの続き (72)発明者 鈴木 伸二 神奈川県川崎市川崎区白石町2番1号 日 本鋳造株式会社内Front page continued (72) Inventor Shinji Suzuki 2-1, Shiraishi-cho, Kawasaki-ku, Kawasaki-shi, Kanagawa Nihon Foundry Co., Ltd.

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 鉄骨柱に取付けられ、アンカーボルトに
より基礎コンクリート上に固定される柱脚金物におい
て、 前記鉄骨柱に生じる応力状態に適合した形状に構成さ
れ、前記アンカーボルトに挿入するアンカーボルト穴を
大きく形成すると共に、該アンカーボルト穴に連通し上
面に開口する後詰めモルタルの注入穴及び後詰めモルタ
ルの充填状態を検知する充填検知穴を設けたことを特徴
とする柱脚金物。
1. A column pedestal attached to a steel frame column and fixed on a foundation concrete by anchor bolts, the anchor bolt hole having a shape adapted to a stress state generated in the steel frame column and inserted into the anchor bolt. And a filling detection hole for detecting the filling state of the back-filled mortar, which is communicated with the anchor bolt hole and opens on the upper surface, and a filling detection hole for detecting the filling state of the back-filled mortar.
【請求項2】 アンカーボルト穴の径を、アンカーボル
トの径より15〜30mm、好ましくは20mm程度大
きく形成したことを特徴とする請求項1記載の柱脚金
物。
2. The column pedestal according to claim 1, wherein the diameter of the anchor bolt hole is larger than the diameter of the anchor bolt by 15 to 30 mm, preferably about 20 mm.
【請求項3】 中心部にアンカーボルト挿入穴を有する
楕円形状の座金を備えたことを特徴とする請求項1又は
2記載の柱脚金物。
3. The column pedestal according to claim 1, further comprising an elliptical washer having an anchor bolt insertion hole at a central portion thereof.
【請求項4】 鉄骨柱に取付けられた柱脚金物をアンカ
ーボルトによって基礎コンクリート上に固定する鉄骨柱
脚部の施工方法において、 前記鉄骨柱に生じる応力状態に適合した形状に構成さ
れ、前記基礎コンクリートに埋設されたアンカーボルト
に挿入するアンカーボルト穴を大きく形成すると共に、
該アンカーボルト穴に連通し上面に開口する後詰めモル
タルの注入穴及び充填検知穴が設けられた柱脚金物が固
定された鉄骨柱を有し、 該鉄骨柱の柱脚金物を前記基礎コンクリート上に施工し
た中心塗部分モルタル上に設置し、前記アンカーボルト
穴を前記アンカーボルトに挿入して固定し、ついで、前
記注入穴からアンカーボルト穴とアンカーボルトの間及
び柱脚金物と基礎コンクリートの間に形成されたすき間
に後詰めモルタルを注入すると共に、必要に応じて前記
柱脚金物と基礎コンクリートの間に柱脚金物の周囲から
後詰めモルタルを注入し、前記充填検知穴から後詰めモ
ルタルが溢れたときは注入を中止して硬化させることを
特徴とする鉄骨柱脚部の施工方法。
4. A method of constructing a steel column base, comprising fixing a column pedestal attached to a steel frame column on a foundation concrete with anchor bolts, wherein the steel frame column is constructed in a shape adapted to a stress state occurring in the steel column. While forming a large anchor bolt hole to insert into the anchor bolt embedded in concrete,
The steel column has a steel column to which a post-filling mortar injection hole and a filling detection hole, which communicate with the anchor bolt hole and open on the upper surface, are fixed, and the steel column post is mounted on the foundation concrete. Installed on the mortar coated centrally, the anchor bolt hole is inserted into the anchor bolt and fixed, and then from the injection hole between the anchor bolt hole and the anchor bolt and between the column base metal and the concrete foundation. While injecting backfilled mortar into the gap formed in, if necessary, injecting backfilled mortar from around the column base metal between the column base metal and the foundation concrete, the backfilled mortar from the filling detection hole is When overflowing, the method of constructing a steel column base is characterized by stopping injection and hardening.
【請求項5】 鉄骨柱に取付けられた柱脚金物をアンカ
ーボルトによって基礎コンクリート上に固定する鉄骨柱
脚部の施工方法において、 前記鉄骨柱に生じる応力状態に適合した形状に構成さ
れ、前記基礎コンクリートに埋設されたアンカーボルト
に挿入するアンカーボルト穴を大きく形成すると共に、
該アンカーボルト穴に連通し上面に開口する後詰めモル
タルの注入穴及び充填検知穴が設けられた柱脚金物が固
定された鉄骨柱を有し、 該鉄骨柱の柱脚金物を前記基礎コンクリート上に施工し
た中心塗部分モルタル上に設置し、前記アンカーボルト
穴を前記アンカーボルトに挿入したのち該アンカーボル
トに楕円形状の座金の中心部に設けたアンカーボルト挿
入穴を挿入してナットで固定し、ついで、前記注入穴か
らアンカーボルト穴とアンカーボルトの間及び柱脚金物
と基礎コンクリートの間に形成されたすき間に後詰めモ
ルタルを注入すると共に、必要に応じて前記柱脚金物と
基礎コンクリートの間に柱脚金物の周囲から後詰めモル
タルを注入し、前記充填検知穴から後詰めモルタルが溢
れたときは注入を中止して硬化させることを特徴とする
鉄骨柱脚部の施工方法。
5. A method for constructing a steel column foot, comprising fixing a column pedestal attached to a steel column on a foundation concrete with anchor bolts, wherein the steel frame column has a shape adapted to a stress state generated in the steel column. While forming a large anchor bolt hole to insert into the anchor bolt embedded in concrete,
The steel column has a steel column to which a post-filling mortar injection hole and a filling detection hole, which communicate with the anchor bolt hole and open on the upper surface, are fixed, and the steel column post is mounted on the foundation concrete. Installed on the mortar coated centrally, the anchor bolt hole is inserted into the anchor bolt, and then the anchor bolt insertion hole provided in the center of the oval washer is inserted into the anchor bolt and fixed with a nut. Then, while injecting a back-filled mortar from the injection hole into the gap formed between the anchor bolt hole and the anchor bolt and between the column base metal product and the base concrete, if necessary, It is characterized by injecting backfilled mortar from around the column base metal in between, and when the backfilled mortar overflows from the filling detection hole, the injection is stopped and cured. The method of constructing a steel column base.
JP6514294A 1993-08-13 1994-04-01 Column base hardware and construction method for steel frame column base section Pending JPH07102639A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6514294A JPH07102639A (en) 1993-08-13 1994-04-01 Column base hardware and construction method for steel frame column base section

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP20137493 1993-08-13
JP5-201374 1993-08-13
JP6514294A JPH07102639A (en) 1993-08-13 1994-04-01 Column base hardware and construction method for steel frame column base section

Publications (1)

Publication Number Publication Date
JPH07102639A true JPH07102639A (en) 1995-04-18

Family

ID=26406272

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6514294A Pending JPH07102639A (en) 1993-08-13 1994-04-01 Column base hardware and construction method for steel frame column base section

Country Status (1)

Country Link
JP (1) JPH07102639A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09100822A (en) * 1995-10-06 1997-04-15 Artes:Kk Fixing method of base plate and anchor bolt, and the base plate, the anchor bolt and nut
JPH1077636A (en) * 1996-09-02 1998-03-24 Natl House Ind Co Ltd Anchor bolt and anchor bolt installation structure
JP2007046940A (en) * 2005-08-08 2007-02-22 Akebono Brake Ind Co Ltd Method for detecting filling, mortar pie manufacturing apparatus and system for detecting filling
JP2011012402A (en) * 2009-06-30 2011-01-20 Nippon Chuzo Kk Structure for fixing steel column base portion
JP2017061803A (en) * 2015-09-25 2017-03-30 大成建設株式会社 Positioning jig for anchor bolt for column, and construction method for steel column base part

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09100822A (en) * 1995-10-06 1997-04-15 Artes:Kk Fixing method of base plate and anchor bolt, and the base plate, the anchor bolt and nut
JPH1077636A (en) * 1996-09-02 1998-03-24 Natl House Ind Co Ltd Anchor bolt and anchor bolt installation structure
JP2007046940A (en) * 2005-08-08 2007-02-22 Akebono Brake Ind Co Ltd Method for detecting filling, mortar pie manufacturing apparatus and system for detecting filling
JP2011012402A (en) * 2009-06-30 2011-01-20 Nippon Chuzo Kk Structure for fixing steel column base portion
JP2017061803A (en) * 2015-09-25 2017-03-30 大成建設株式会社 Positioning jig for anchor bolt for column, and construction method for steel column base part

Similar Documents

Publication Publication Date Title
JPH07102639A (en) Column base hardware and construction method for steel frame column base section
JP2748244B2 (en) Fixing method of steel pedestal column
JPH07173843A (en) Foundation coupling metal fittings and foundation construction method
JP2980886B1 (en) How to install column bases
JP3958453B2 (en) Precast concrete joint structure
JPH02132241A (en) Column base structure
JP4057204B2 (en) Formwork fixing structure
JP3236950B2 (en) Embedded column base and method of construction
JP3482621B2 (en) Reinforcement method of existing reinforced concrete wall
JPH04370797A (en) Constuction of lined tank
JP2607137B2 (en) How to bury the mounting bracket for mounting the support material
JPH07158161A (en) Joint structure between reinforced concrete post and steel beam and joint member thereof
JPH11324174A (en) Structure of aseismatic wall
JPH0714501Y2 (en) PC wall panel mounting device
JP2570085B2 (en) Anchor bolt construction method
JP2000096576A (en) Joint structure of steel framed column leg section and construction method thereof
JPH06220938A (en) Construction of form panel for placement of concrete, employing board doubling as form
JPH0634520Y2 (en) Formwork assembly equipment
JPH06257218A (en) Frame mounting structure of post/beam joint
JPH08199677A (en) Connecting method for reinforced concrete pillar and steelwork beam
JP3019140U (en) Balcony mounting structure
JPS6210333A (en) Fundation work for pier of reinforced base frame
JPH027837Y2 (en)
JP2647638B2 (en) Concrete panel for slope construction
JPH0598735A (en) Synthesizing method of steel frame and precast concrete