JPH0710105U - Column base plate fixing device - Google Patents

Column base plate fixing device

Info

Publication number
JPH0710105U
JPH0710105U JP3610593U JP3610593U JPH0710105U JP H0710105 U JPH0710105 U JP H0710105U JP 3610593 U JP3610593 U JP 3610593U JP 3610593 U JP3610593 U JP 3610593U JP H0710105 U JPH0710105 U JP H0710105U
Authority
JP
Japan
Prior art keywords
base plate
grout material
gap
anchor bolt
fixing device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3610593U
Other languages
Japanese (ja)
Other versions
JP2593355Y2 (en
Inventor
博 坂部
Original Assignee
株式会社トーアツ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社トーアツ filed Critical 株式会社トーアツ
Priority to JP1993036105U priority Critical patent/JP2593355Y2/en
Publication of JPH0710105U publication Critical patent/JPH0710105U/en
Application granted granted Critical
Publication of JP2593355Y2 publication Critical patent/JP2593355Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】 【目的】 グラウト材を注入する際、充填不良箇所を生
じることがない程充填度が高く、固定強度の強い注入が
行え、現場の状況に応じてその都度異なったグラウト材
を使用することができる、柱脚ベースプレート固定装置
を提供することを目的とする。 【構成】 ベースプレート3の下面にパッキン6を接着
した後、パッキン6と基礎コンクリート1の間の間隙に
下部グラウト材7を充填し、ナット5の上部グラウト材
注入口10より上部グラウト材9を注入し、アンカーボ
ルト8とベースプレート3の間隙を充填すると共にアン
カーボルト8と座金4の間隙、及びアンカーボルト8と
ナット5の間隙を一体的に充填することを特徴とする柱
脚ベースプレート固定装置。
(57) [Summary] [Purpose] When pouring grout material, the degree of filling is high enough to prevent defective filling, and strong fixed strength can be injected. Different grout materials are used depending on the situation at the site. It is an object of the present invention to provide a pedestal base plate fixing device that can be used. [Structure] After the packing 6 is adhered to the lower surface of the base plate 3, the lower grout material 7 is filled in the gap between the packing 6 and the basic concrete 1, and the upper grout material 9 is injected from the upper grout material injection port 10 of the nut 5. Then, the column base base plate fixing device is characterized in that the gap between the anchor bolt 8 and the base plate 3 is filled, and the gap between the anchor bolt 8 and the washer 4 and the gap between the anchor bolt 8 and the nut 5 are filled integrally.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、予め基礎コンクリート上に設けたレベルモルタルと、ベースプレー ト設置後に注入するモルタルとを挟持し、かつ基礎コンクリート中に埋設してな るアンカーボルトを、ナット及び座金を介して接合してなる柱脚ベースプレート 固定装置に関する。 The present invention sandwiches a level mortar previously installed on basic concrete and a mortar to be injected after the base plate is installed, and joins anchor bolts embedded in the basic concrete with nuts and washers. Column base plate fixing device.

【0002】[0002]

【従来の技術】[Prior art]

従来の鉄骨柱脚ベースプレートを固定する装置としては基礎コンクリート上に レベルモルタルを形成すると共にアンカーボルトをその上端部が突出するように 埋設する。次にベースプレートをアンカーボルトの上から挿入し、座金及びナッ トを同じくアンカーボルトの上から挿入する。その後、基礎コンクリート上面と ベースプレート下面との間隙に硬練りした無収縮モルタルを手詰めするか、ある いはベースプレートの周辺と相当の間隔をもって無収縮モルタルを堰板の内側に 流し込む装置が従来考え出されてきた。基本的には基礎上面とベースプレート下 面、ボルト穴とアンカーボルトの間隙にグラウト材を同時に充填して一体的に固 定したり、平板又は柱と接合する突出部を形成し、かつ中央部に貫通穴を設けた 柱脚金物を鋼管柱の下端内部と柱脚金物の貫通穴と基礎とを一体的にコンクリー ト打設したり、底面突出部を設けたり、ベースプレートとコンクリート基礎とを レベルモルタルとベースプレート設置後に注入するグラウト材を挿通して面内相 対移動を拘束するもの等がある。しかしこれらの装置では充填不良箇所を生じ易 く、また基礎上面とベースプレート下面との間の間隙が広くないと作業ができな い。さらに、無収縮モルタルの使用量が多く、不経済である。さらにいずれの装 置もベースプレートと基礎コンクリートとの密着はある程度期待できるが、アン カーボルトとベースプレートの密着までは期待できない。 従って、グラウト材の材質をも考慮した装置について開発する必要がある。 As a conventional device for fixing the steel column base plate, level mortar is formed on the foundation concrete and the anchor bolt is embedded so that its upper end projects. Then insert the base plate from above the anchor bolts, and the washer and nut from above the anchor bolts. After that, there has been conventionally devised a device for manually packing hardened non-shrink mortar into the gap between the upper surface of the base concrete and the lower surface of the base plate, or for pouring the non-shrink mortar into the weir plate at a considerable distance from the periphery of the base plate. Came. Basically, the upper surface of the foundation and the lower surface of the base plate, the gaps between the bolt holes and the anchor bolts are filled with grout material at the same time to solidify or integrally form a protrusion that joins with a flat plate or column, and at the center. A column pedestal with through holes is concretely placed inside the lower end of the steel pipe column, the through hole of the column pedestal and the foundation, a bottom projection is provided, and the base plate and concrete foundation are level mortar. In some cases, the in-plane relative movement is restricted by inserting the grout material that is injected after the base plate is installed. However, these devices tend to cause defective filling, and work cannot be performed unless the gap between the upper surface of the foundation and the lower surface of the base plate is wide. Furthermore, the amount of non-shrink mortar used is large, which is uneconomical. Further, in any of the devices, close contact between the base plate and the base concrete can be expected to some extent, but close contact between the anchor bolt and the base plate cannot be expected. Therefore, it is necessary to develop an apparatus that also considers the material of the grout material.

【0003】[0003]

【考案が解決しようとする課題】 本考案は従来の柱脚固定装置における問題点を解消し、グラウト材を注入する 際、充填不良箇所を生じることがない程充填度が高く、固定強度の強い注入が行 え、現場の状況に応じてその都度異なったグラウト材を使用することができる柱 脚ベースプレート固定装置を提供することを目的とする。The present invention solves the problems of the conventional column base fixing device, and when pouring grout material, the filling degree is high enough to prevent defective filling, and the fixing strength is strong. It is an object of the present invention to provide a column base plate fixing device that can be injected and can use different grout materials depending on the situation of the site.

【0004】[0004]

【課題を解決するための手段】[Means for Solving the Problems]

この問題を解決するために本願の実用新案登録請求の範囲の請求項1に記載の 柱脚ベースプレート固定装置、即ち、ベースプレートの下面にパッキンを接着し た後、パッキンと基礎コンクリートの間の間隙に下部グラウト材を充填し、ナッ トの上部グラウト材注入口より上部グラウト材を注入し、アンカーボルトとベー スプレートの間隙を充填すると共にアンカーボルトと座金の間隙、及びアンカー ボルトとナットの間隙を一体的に充填することを特徴とする柱脚ベースプレート 固定装置によって達成できる。 In order to solve this problem, the column base plate fixing device according to claim 1 of the utility model registration claim of the present application, that is, after the packing is adhered to the lower surface of the base plate, the gap is formed between the packing and the foundation concrete. Fill the lower grout material, then inject the upper grout material from the upper grout material inlet of the nut to fill the gap between the anchor bolt and the base plate and the gap between the anchor bolt and washer and the gap between the anchor bolt and nut. This can be achieved by a pedestal base plate fixing device characterized by monolithic filling.

【0005】[0005]

【実施例】【Example】

図面によって本考案の実施例について説明すると、図1は本考案に係わる柱脚 ベースプレート固定装置の概略図であり、基礎コンクリート1上に埋設してある アンカーボルト8の横にレベルモルタル2を設置し、ベースプレート3、座金4 、及びナット5をアンカーボルト8の上部から挿通した後、基礎コンクリート1 とベースプレート3の間にパッキン6を挿入してベースプレート下面に接着する 。次に下部グラウト材7によって、基礎コンクリート1とレベルモルタル2とベ ースプレート下面のパッキン6によって囲まれた下部分を充填する。上部グラウ ト材は予めナット5に設けられた上グラウト材注入穴10より注入し、アンカー ボルト8とベースプレート3との間の間隙、及びアンカーボルト8と座金4との 間の間隙を充填した後、アンカーボルト8とナット5との間の間隙も充填してア ンカーボルト8を固定する。 Referring to the drawings, an embodiment of the present invention will be described. FIG. 1 is a schematic view of a column base plate fixing device according to the present invention, in which a level mortar 2 is installed beside an anchor bolt 8 embedded on a concrete foundation 1. After inserting the base plate 3, the washer 4, and the nut 5 from the upper part of the anchor bolt 8, a packing 6 is inserted between the foundation concrete 1 and the base plate 3 and adhered to the lower surface of the base plate. Next, the lower grout material 7 fills the lower part surrounded by the basic concrete 1, the level mortar 2, and the packing 6 on the lower surface of the base plate. After the upper grout material is injected through the upper grout material injection hole 10 provided in the nut 5 in advance, after filling the gap between the anchor bolt 8 and the base plate 3 and the gap between the anchor bolt 8 and the washer 4. Then, the gap between the anchor bolt 8 and the nut 5 is also filled and the anchor bolt 8 is fixed.

【0006】 尚、上部グラウト材と下部グラウト材はパッキンにより分離するので異なった 種類のものでも良く、特に、アンカーボルトとベースプレート、座金、ナットの 固定に強度なものが要求される時は、上部グラウト材として高耐力のモルタルグ ランド、又は圧縮強度の強い、例えば400kg/cm2 のエポキシ樹脂等を使 用すると良い。Since the upper grout material and the lower grout material are separated by the packing, different kinds may be used. Especially, when the anchor bolt and the base plate, the washer, and the nut are required to be fixed firmly, As the grout material, it is preferable to use mortar ground having high yield strength or epoxy resin having high compressive strength, for example, 400 kg / cm 2 .

【0007】 図2はナット5の拡大図であり、上グラウト注入口10が明示されている。こ の上グラウト注入口10は単一でも複数でも良いが、注入のし易さから複数の方 が好ましい。FIG. 2 is an enlarged view of the nut 5, which clearly shows the upper grout injection port 10. The upper grout injection port 10 may be a single port or a plurality of ports, but a plurality of ports are preferable in terms of ease of injection.

【0008】 図3はパッキン6の拡大図であり、挿入用切り抜き11によってアンカーボル ト8に差し込まれる。FIG. 3 is an enlarged view of the packing 6, which is inserted into the anchor bolt 8 by the insertion cutout 11.

【0009】[0009]

【考案の効果】[Effect of device]

本考案による装置により、充填度が高く、固定強度の強いグラウト材の注入が 行え、下部グラウト材と下部グラウト材をパッキンを境にして異なった種類のも のでも良く、現場の状況に応じてその都度異なったグラウト材を使用することが できる、という効果を奏する。 With the device according to the present invention, it is possible to inject grout material with high filling degree and strong fixed strength, and different kinds of lower grout material and lower grout material with packing as a boundary may be used, depending on the situation of the site. The effect is that a different grout material can be used each time.

【図面の簡単な説明】[Brief description of drawings]

【図1】本願考案に係わる柱脚ベースプレート固定装置
の全体概略図。
FIG. 1 is an overall schematic view of a column base plate fixing device according to the present invention.

【図2】本願考案に係わる柱脚ベースプレート固定装置
のナットの拡大平面図。
FIG. 2 is an enlarged plan view of a nut of the column base plate fixing device according to the present invention.

【図3】本願考案に係わる柱脚ベースプレート固定装置
のパッキンの拡大正面図。
FIG. 3 is an enlarged front view of the packing of the column base plate fixing device according to the present invention.

【符号の説明】[Explanation of symbols]

1 基礎コンクリート 2 レベルモルタル 3 ベースプレート 4 座金 5 ナット 6 パッキン 7 下部グラウト材 8 アンカーボルト 9 上部グラウト材 10 上部グラウト材注入口 11 挿入用切り抜き 1 Foundation concrete 2 Level mortar 3 Base plate 4 Washer 5 Nut 6 Packing 7 Lower grout material 8 Anchor bolt 9 Upper grout material 10 Upper grout material inlet 11 Cutout for insertion

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 予め基礎コンクリート上に設けたレベル
モルタルと、ベースプレート設置後に注入するモルタル
とを挟持し、かつ基礎コンクリート中に埋設してなるア
ンカーボルトを、ナット及び座金を介して接合してなる
柱脚ベースプレート固定装置において、 前記ベースプレート3の下面にパッキン6を接着した
後、前記パッキン6と基礎コンクリート1の間隙に下部
グラウト材7を充填し、前記ナット5の上部グラウト材
注入口10より上部グラウト材9を注入し、前記アンカ
ーボルト8と前記ベースプレート3の間隙を充填すると
共にアンカーボルト8と座金4の間隙、及びアンカーボ
ルト8とナット5の間隙を一体的に充填することを特徴
とする柱脚ベースプレート固定装置。
1. An anchor bolt sandwiching a level mortar previously provided on a foundation concrete and a mortar to be injected after the base plate is installed and being embedded in the foundation concrete is joined through a nut and a washer. In the column base plate fixing device, after the packing 6 is adhered to the lower surface of the base plate 3, the lower grout material 7 is filled in the gap between the packing 6 and the basic concrete 1, and the upper portion of the nut 5 above the upper grout material injection port 10 is filled. A grout material 9 is injected to fill the gap between the anchor bolt 8 and the base plate 3 and to integrally fill the gap between the anchor bolt 8 and the washer 4 and the gap between the anchor bolt 8 and the nut 5. Column base plate fixing device.
JP1993036105U 1993-07-01 1993-07-01 Column base fixing device Expired - Lifetime JP2593355Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1993036105U JP2593355Y2 (en) 1993-07-01 1993-07-01 Column base fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1993036105U JP2593355Y2 (en) 1993-07-01 1993-07-01 Column base fixing device

Publications (2)

Publication Number Publication Date
JPH0710105U true JPH0710105U (en) 1995-02-14
JP2593355Y2 JP2593355Y2 (en) 1999-04-05

Family

ID=12460499

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1993036105U Expired - Lifetime JP2593355Y2 (en) 1993-07-01 1993-07-01 Column base fixing device

Country Status (1)

Country Link
JP (1) JP2593355Y2 (en)

Also Published As

Publication number Publication date
JP2593355Y2 (en) 1999-04-05

Similar Documents

Publication Publication Date Title
JP2006077566A (en) Grout layer reinforcing device
JP2003055984A (en) Column base connecting structure
JP2000008483A (en) Baseplate fixing device
JPH0710104U (en) Column base plate fixing method
JPH0710105U (en) Column base plate fixing device
JPH02164931A (en) Foundation construction method for building
JP3672748B2 (en) Construction method of the joint structure of steel middle legs
JPH093913A (en) Column base fixing method for steel pipe column
JPS5961626A (en) Construction of foundation, pillar and leg
JP3052032U (en) Base plate fixing device
JP3838165B2 (en) Joining structure and joining method of steel pipe column and steel pipe pile
JPH01203523A (en) Fixing of column base
JPS6133761Y2 (en)
JP2532813Y2 (en) Attachment equipment for pillars such as buildings
JP3838472B2 (en) Exposed column base construction method
KR200354124Y1 (en) Structure fixing plate
JPH0649657U (en) Formwork equipment for precast reinforced concrete column joints
JPS60258345A (en) Pillar leg fixing method
JP7375281B1 (en) Fixing method of plate material, fixing structure and position adjustment fittings
JP2000291018A (en) Grout applying method in exposed column base
JP2002088775A (en) Foundation structure equipped with anchor bolt and method for constructing the same
JPH0355349A (en) Erection construction of handrail post
JPH04370797A (en) Constuction of lined tank
JP2000282571A (en) Fixing structure of exposed column base
JPH10169010A (en) Base of column fixing method and grout filing device using this method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990112