JPH069051Y2 - Concrete frame for seawall - Google Patents

Concrete frame for seawall

Info

Publication number
JPH069051Y2
JPH069051Y2 JP1990114858U JP11485890U JPH069051Y2 JP H069051 Y2 JPH069051 Y2 JP H069051Y2 JP 1990114858 U JP1990114858 U JP 1990114858U JP 11485890 U JP11485890 U JP 11485890U JP H069051 Y2 JPH069051 Y2 JP H069051Y2
Authority
JP
Japan
Prior art keywords
concrete
vertical
frame
vertical frame
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1990114858U
Other languages
Japanese (ja)
Other versions
JPH0473024U (en
Inventor
武治郎 山田
Original Assignee
南濃コンクリート工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 南濃コンクリート工業株式会社 filed Critical 南濃コンクリート工業株式会社
Priority to JP1990114858U priority Critical patent/JPH069051Y2/en
Publication of JPH0473024U publication Critical patent/JPH0473024U/ja
Application granted granted Critical
Publication of JPH069051Y2 publication Critical patent/JPH069051Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【考案の詳細な説明】 (産業上の利用分野) この考案は、河川や海岸の堤防をコンクリートで補強す
る際に堤防上に設置される護岸用コンクリート枠に関す
るものである。
[Detailed Description of the Invention] (Industrial field of application) The present invention relates to a concrete wall for seawall installation which is installed on the embankment when reinforcing the embankment of a river or a coast with concrete.

(従来の技術) 従来、護岸工事のため、河川等の堤防の表面等をコンク
リートで固めて補強するにあたっては、表面を平滑にし
た上、板材等を用いて表面の横方向および縦方向に所定
の間隔をおいて型枠を組立て、この型枠内にコンクリー
トを流し込んでコンクリートの岸壁を形成していた。
(Prior art) Conventionally, for the purpose of solidifying the surface of rivers and other embankments with concrete for revetment work, after smoothing the surface, a plate material etc. was used to determine the horizontal and vertical directions of the surface. The molds were assembled at intervals of, and concrete was poured into the molds to form a concrete quay.

(考案が解決しようとする課題) このため、コンクリートの岸壁を形成する護岸工事にお
いては、工事現場での型枠の組立等のために作業に熟練
した人を多数必要とするだけでなく、コンクリートの打
設並びに養生のため長い工期を必要とするという欠点が
あった。
(Problems to be solved by the invention) Therefore, in revetment work for forming a concrete quay, not only a large number of skilled workers are required for assembling the formwork at the construction site, but also concrete There was a drawback that a long construction period was required for casting and curing.

この考案は上記に鑑み、護岸工事にあたり工事現場での
作業に熟練した人を多く必要とせず、かつ工期を従来よ
り大幅に短縮することのできる護岸用コンクリート枠の
提供を目的とするものである。
In view of the above, the present invention is intended to provide a concrete wall for a seawall that does not require many skilled workers at the construction site for the seawall construction and that the construction period can be significantly shortened as compared with the conventional case. .

(課題を解決するための手段) 上記の目的を達成するためにこの考案では、縦方向の略
全長に渉って配置された適数本の縦筋を、組立筋によっ
て結合して形成された鉄筋籠を内部に収納して工場にて
製作され、堤防等の下部及び上部の横方向にそれぞれ打
設した基礎工と保護工間に直列状で、かつ所定の間隔を
持って複数列に配置されるコンクリート製の縦枠と、前
記縦枠同様に鉄筋籠を収納して工場にて製作され、前記
基礎工と保護工間に直列状で、かつ所定の間隔を持って
配置された縦枠間の所定の個所に配置されるコンクリー
ト製の横枠とからなり、前記縦枠及び横枠がその中間部
分に打設されたコンクリートの中間材により堤防等の表
面に固定されるようにしたものである。
(Means for Solving the Problems) In order to achieve the above object, in the present invention, a suitable number of vertical streaks arranged across substantially the entire length in the vertical direction are formed by connecting them by an assembly bar. Reinforcement cages are housed inside and manufactured at the factory, and they are arranged in multiple rows in series at a predetermined interval between the foundation work and the protection work that are placed in the lower and upper parts of the embankment, etc. in the lateral direction. A vertical frame made of a concrete vertical frame and a rebar cage like the vertical frame that is manufactured in a factory, and is arranged in series between the foundation work and the protection work at a predetermined interval. A concrete horizontal frame placed at a predetermined location between the vertical frame and the horizontal frame fixed to the surface of an embankment or the like by an intermediate material of concrete placed in the middle part thereof Is.

(実施例) つぎに、この考案を実施例示す図面を参照して説明する
と、第1図〜第4図において、工場内で製作されるコン
クリート製の縦枠1は、その内部の縦方向の略全長に渉
って鉄筋4(以下縦筋という)が上,下に3本づつ所定
の間隔をおいて平行に配置されている。縦枠1の製作に
あたっては、この各縦筋4がその長手方向に所定の間隔
をおいて設けられた適数本の組立筋5により組付けられ
て鉄筋籠6が形成される。そして、この鉄筋籠6が型枠
(図示せず)内に配置された後、型枠内にコンクリート
が流し込まれると、鉄筋籠6が内蔵された縦枠1が形成
される。
(Embodiment) Next, the present invention will be described with reference to the drawings showing an embodiment. In FIGS. 1 to 4, a vertical frame 1 made of concrete in a factory has a vertical direction inside thereof. Reinforcing bars 4 (hereinafter referred to as vertical bars) are arranged parallel to each other over a substantially entire length, with three bars at the top and three bars at a predetermined interval. In manufacturing the vertical frame 1, the vertical reinforcing bars 4 are assembled by an appropriate number of assembly reinforcing bars 5 provided at predetermined intervals in the longitudinal direction to form a reinforcing bar cage 6. Then, when the rebar cage 6 is placed in a mold (not shown) and concrete is poured into the mold, the vertical frame 1 having the rebar cage 6 built therein is formed.

この縦枠1はその使用個所により種々の長さのもの及び
端面形状の異なるものが製作される。
The vertical frame 1 is manufactured in various lengths and in different end face shapes depending on the use place.

第5図及び第6図は河川の表面に形成された護岸Gを示
している。この図において、岸壁はその傾斜に従って、
平らに整地された傾斜法面Kと、この傾斜法面Kの上部
で略水平に整地された水平断面Sとになっている。この
傾斜法面Kの下端部には傾斜法面Kに対して横方向に、
基礎工Bが現場で型枠を組む従来の方法でコンクリート
により打設され、また水平段面Sには傾斜法面Kの上端
部から多少入った個所に長方形をした保護工Pが基礎工
Bと略平行になるように、コンクリートにより打設され
る。
5 and 6 show a revetment G formed on the surface of a river. In this figure, the quay follows its slope,
There are an inclined slope K that is leveled flat and a horizontal section S that is leveled above the inclined slope K. At the lower end of the sloped surface K, in the lateral direction with respect to the sloped surface K,
The foundation work B is placed by concrete by the conventional method of assembling the formwork on the site, and the horizontal work surface S is provided with a rectangular protection work P at a portion slightly entering from the upper end of the slope K. It is placed by concrete so that it is almost parallel to.

そして、基礎工Bと保護工Pとの間の傾斜法面Kには基
礎コンクリートCが所定の高さ均一に打設される。基礎
工B側に配置される最下部の縦枠1(以下下部縦枠とい
う)は起重機等(図示せず)を使用して移動させられた
後、その前端面1aを基礎工Bの傾斜した内側上面Ba
に当接させた状態でコンクリートCの上面に載置され
る。ついで、同じく起重機等を使用して、下部縦枠1の
上方に中間の縦枠2(以下中間縦枠という)を一列に配
置し、中間縦枠2の前端面2aを下部縦枠1の後端面1
bに当接させて、下部縦枠1の上方に中間縦枠2を一列
に整列させる(第6図参照)。同様にして、中間の縦枠
2の後端面2bの上方に縦枠3(以下上部縦枠という)
の前端面3aを当接させるとともに上部縦枠3の後端面
3bを保護工Pの前面Paに当接させて、水平断面Sの
コンクリートCの上部に上部縦枠3を水平に載置して、
この上部縦枠3と中間縦枠2及び下部縦枠1とを直列状
に整列させる。この時、上部縦枠3の上面は保護工Pの
上面と同じ高さになっている(第5図参照)。
Then, on the slope K between the foundation work B and the protection work P, the foundation concrete C is poured uniformly at a predetermined height. The lowermost vertical frame 1 (hereinafter referred to as the lower vertical frame) arranged on the side of the foundation work B is moved by using a hoist or the like (not shown), and then the front end face 1a of the foundation work B is inclined. Inside upper surface Ba
It is placed on the upper surface of the concrete C while being brought into contact with the concrete C. Then, similarly using a hoist or the like, an intermediate vertical frame 2 (hereinafter referred to as an intermediate vertical frame) is arranged in a line above the lower vertical frame 1, and the front end face 2a of the intermediate vertical frame 2 is arranged behind the lower vertical frame 1. End face 1
The intermediate vertical frames 2 are aligned in a row above the lower vertical frame 1 by abutting against b (see FIG. 6). Similarly, a vertical frame 3 (hereinafter referred to as an upper vertical frame) is provided above the rear end surface 2b of the intermediate vertical frame 2.
The front end face 3a of the upper vertical frame 3 and the rear end face 3b of the upper vertical frame 3 to the front face Pa of the protective work P, and the upper vertical frame 3 is placed horizontally on the concrete C of the horizontal section S. ,
The upper vertical frame 3, the intermediate vertical frame 2, and the lower vertical frame 1 are aligned in series. At this time, the upper surface of the upper vertical frame 3 is at the same height as the upper surface of the protective work P (see FIG. 5).

上記と同様にして、下部縦枠1,中間縦枠2及び上部縦
枠3を第6図に示すように所定の間隔をおいて適数並列
に配置する。
Similarly to the above, an appropriate number of lower vertical frames 1, intermediate vertical frames 2 and upper vertical frames 3 are arranged in parallel at predetermined intervals as shown in FIG.

第5図及び第6図に示す横枠7(以下、下横枠という)
と横枠8(以下、中横枠という)とは、何れも下部縦枠
1と同様の方法で工場で製作されたコンクリートのブロ
ックであり、その高さは下部縦枠1と同じ高さになって
いる。
Horizontal frame 7 shown in FIG. 5 and FIG. 6 (hereinafter referred to as lower horizontal frame)
The horizontal frame 8 (hereinafter referred to as the middle horizontal frame) is a concrete block manufactured at the factory by the same method as the lower vertical frame 1, and its height is the same as that of the lower vertical frame 1. Has become.

下横枠7はその厚さが高さより薄い長方形の断面になっ
ている。この下横枠7は、一対の下部縦枠1,1の後部
側面にその両側端面7a,7aを当接させた状態で下部
縦枠1,1の間で基盤部C上に載置される。この時、下
横枠7の後端面7bは下部縦枠1の後端面1bと略同一
面内にある。
The lower horizontal frame 7 has a rectangular cross section whose thickness is thinner than its height. The lower horizontal frame 7 is placed on the base portion C between the lower vertical frames 1, 1 in a state where both side end surfaces 7a, 7a are in contact with the rear side surfaces of the pair of lower vertical frames 1, 1. . At this time, the rear end surface 7b of the lower horizontal frame 7 is substantially in the same plane as the rear end surface 1b of the lower vertical frame 1.

中横枠8は下横枠7と同様の方法で製作されたもので、
下横枠7と同じ高さと長さを有し、その厚さは下横枠7
より厚くなっている。この中横枠8は上部の後側が下方
に傾斜した傾斜面8bになっており、その前端面8aを
下横枠7の後端面7bに当接させて、下横枠7と並列に
コンクリートC上に載置される。
The middle horizontal frame 8 is manufactured in the same manner as the lower horizontal frame 7,
It has the same height and length as the lower horizontal frame 7, and its thickness is
It is thicker. The middle horizontal frame 8 has an inclined surface 8b whose upper rear side is inclined downward, and its front end surface 8a is brought into contact with the rear end surface 7b of the lower horizontal frame 7 so that the concrete C is parallel to the lower horizontal frame 7. Placed on top.

中横枠8より上方に配置される横枠9(以下、上横枠と
いう)は厚さが中横枠8より薄いことを除いて中横枠8
と似た形をしており、その上部の後側が下方に傾斜した
傾斜面9aになっている。この上横枠9は中間縦枠2の
中央付近において両中間縦枠2,2の間のコンクリート
C上に載置される。
A horizontal frame 9 (hereinafter, referred to as an upper horizontal frame) arranged above the middle horizontal frame 8 has a thickness smaller than that of the middle horizontal frame 8 except for the thickness.
Has a shape similar to that of the above, and the rear side of the upper part thereof is an inclined surface 9a inclined downward. The upper horizontal frame 9 is placed on the concrete C between the intermediate vertical frames 2 and 2 in the vicinity of the center of the intermediate vertical frame 2.

上記のようにして、河川のコンクリートC上に複数の下
部縦枠1,中間縦枠2及び上部縦枠3をそれぞれ載置
し、各下部縦枠1,1の間に下横枠7を、また各中間縦
枠2,2の間に中横枠8及び上横枠9をそれぞれ配置し
た後、これらの縦枠及び横枠の間にコンクリートの中間
材10を所定の高さ(第5図に線10aで示す)まで打
設すると護岸Gが形成される。
As described above, a plurality of lower vertical frames 1, intermediate vertical frames 2 and upper vertical frames 3 are placed on the concrete C of the river, respectively, and a lower horizontal frame 7 is provided between the lower vertical frames 1, 1. Moreover, after arranging the middle horizontal frame 8 and the upper horizontal frame 9 between the respective intermediate vertical frames 2 and 2, a concrete intermediate material 10 is provided between these vertical frames and horizontal frames at a predetermined height (see FIG. 5). (Indicated by the line 10a in FIG. 2), a revetment G is formed.

(考案の効果) この考案は、以上説明したように構成されているので、
以下に記載されるような効果を奏する。
(Effect of the Invention) Since the present invention is configured as described above,
The following effects are achieved.

各縦枠及び各横枠は工場で製作されるので、従来のよう
に護岸現場における縦枠及び横枠形成のための型枠の組
立、型枠に対するコンクリート打設作業及びその養生期
間を必要としないので、護岸形成のための工期を従来よ
り大幅に短縮することができるだけでなく、従来のよう
に熟練工を必要とせずに現場作業工数を大幅に減少させ
ることができる。また、各種縦枠並びに横枠は工場にお
いて正確な型を用いてその形並びに寸法を正確に形成す
ることができて相互に互換性を持たせることができるの
で、現場における縦,横枠の組付作業を簡単且容易にす
ることができる。
Since each vertical frame and each horizontal frame is manufactured at the factory, it is necessary to assemble the formwork for forming the vertical frame and the horizontal frame at the revetment site, concrete placing work on the formwork, and its curing period as in the past. Therefore, not only can the construction period for revetment formation be significantly shortened as compared with the conventional method, but also the number of on-site work steps can be greatly reduced without requiring skilled workers as in the conventional case. In addition, various vertical frames and horizontal frames can be formed in the factory by using accurate molds and their shapes and dimensions can be formed accurately, and they can be made compatible with each other. Attaching work can be done easily and easily.

【図面の簡単な説明】[Brief description of drawings]

図はこの考案の一実施例を示し、第1図はコンクリート
製縦枠1の平面図、第2図は第1図の側面図、第3図は
第2図内における鉄筋籠の状態を示す図、第4図は縦枠
内の縦筋の配置を示す図、第5図は縦枠及び横枠を用い
て形成された護岸の側面図(第6図のVI-VI線断面
図)、第6図は第5図の平面図である。 1,2,3……縦枠、4……縦筋 5……組立筋、6……鉄筋籠 7,8,9……横枠、B……基礎工 G……護岸、K……傾斜法面 P……保護工、S……水平断面
FIG. 1 shows an embodiment of the present invention, FIG. 1 is a plan view of a concrete vertical frame 1, FIG. 2 is a side view of FIG. 1, and FIG. 3 is a state of a rebar cage in FIG. Figures and 4 are diagrams showing the arrangement of vertical streaks in the vertical frame, and Figure 5 is a side view of the seawall formed using the vertical and horizontal frames (cross-sectional view taken along the line VI-VI in Figure 6). FIG. 6 is a plan view of FIG. 1, 2, 3 ... Vertical frame, 4 ... Vertical bar 5 ... Assembly bar, 6 ... Reinforcing bar cage 7, 8, 9 ... Horizontal frame, B ... Foundation work G ... Revetment, K ... Inclination Slope P …… Protection work, S …… Horizontal cross section

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】縦方向の略全長に渉って配置された適数本
の縦筋を、組立筋によって結合して形成された鉄筋篭を
内部に収納して工場にて製作され、堤防等の下部及び上
部の横方向にそれぞれ打設した基礎工と保護工間に直列
状で、かつ所定の間隔を持って複数列に配置されるコン
クリート製の縦枠と、前記縦枠同様に鉄筋篭を収納して
工場にて製作され、前記基礎工と保護工間に直列状で、
かつ所定の間隔を持って配置された縦枠間の所定の個所
に配置されるコンクリート製の横枠とからなり、前記縦
枠及び横枠がその中間部分に打設されたコンクリートの
中間材により堤防等の表面に固定されることを特徴とす
る護岸用コンクリート枠。
1. A reinforcing bar cage formed by connecting a suitable number of vertical bars arranged over substantially the entire length in the vertical direction by an assembly bar is housed inside and manufactured at a factory. Vertical frames made of concrete, which are placed in a plurality of rows at a predetermined interval in series between the foundation work and the protection work that are placed in the lower and upper parts of the horizontal direction, respectively. It is stored in the factory and manufactured at the factory, and in series between the foundation work and the protection work,
And a horizontal frame made of concrete arranged at a predetermined position between the vertical frames arranged at a predetermined interval, and the vertical frame and the horizontal frame are made of an intermediate material of concrete placed in the middle part thereof. A concrete wall for revetment, which is fixed on the surface of levee.
JP1990114858U 1990-10-31 1990-10-31 Concrete frame for seawall Expired - Lifetime JPH069051Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1990114858U JPH069051Y2 (en) 1990-10-31 1990-10-31 Concrete frame for seawall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1990114858U JPH069051Y2 (en) 1990-10-31 1990-10-31 Concrete frame for seawall

Publications (2)

Publication Number Publication Date
JPH0473024U JPH0473024U (en) 1992-06-26
JPH069051Y2 true JPH069051Y2 (en) 1994-03-09

Family

ID=31862579

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1990114858U Expired - Lifetime JPH069051Y2 (en) 1990-10-31 1990-10-31 Concrete frame for seawall

Country Status (1)

Country Link
JP (1) JPH069051Y2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4524833Y1 (en) * 1965-06-19 1970-09-29
JPH0640677Y2 (en) * 1987-02-17 1994-10-26 前田製管株式会社 Assembly material for slope lining

Also Published As

Publication number Publication date
JPH0473024U (en) 1992-06-26

Similar Documents

Publication Publication Date Title
JPH069051Y2 (en) Concrete frame for seawall
JPS609178B2 (en) How to install garden or boundary wall panels
EP0107460A2 (en) Method of constructing concrete structure
JPH08209653A (en) Form block for civil engineering and construction building, building structure using it, and construction thereof
JP2755888B2 (en) Abutment
JPH0320410Y2 (en)
JPS5929743B2 (en) Framing method for basic concrete formwork
JPS5926741B2 (en) Foundation construction equipment
JPS6123092Y2 (en)
JPH0421874Y2 (en)
JPH05187030A (en) Gravity-type retaining wall and manufacture thereof
JPS6115087Y2 (en)
JPH01271526A (en) Construction method for foundation
JPH0674590B2 (en) Block for building legal framework and method for building legal framework
JP2591600Y2 (en) Concrete sinking
JP2586468Y2 (en) Building foundation
JPS6016527B2 (en) Seawall formation method and locking member used therein
JP2824374B2 (en) Concrete block for foundation, manufacturing method thereof, and foundation construction method using the same
JPS60341Y2 (en) stacked block foundation frame
JPS6268926A (en) Construction for underwater reinforced concrete
JPS607409Y2 (en) Frame panel for concrete pouring
JPS624587Y2 (en)
JPH026096Y2 (en)
KR790001540Y1 (en) Block for retaining wall
JP3028394U (en) Concrete block for earth retaining

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term