JPH0673748A - Cut-off method of underground type storage tank structure - Google Patents

Cut-off method of underground type storage tank structure

Info

Publication number
JPH0673748A
JPH0673748A JP4227460A JP22746092A JPH0673748A JP H0673748 A JPH0673748 A JP H0673748A JP 4227460 A JP4227460 A JP 4227460A JP 22746092 A JP22746092 A JP 22746092A JP H0673748 A JPH0673748 A JP H0673748A
Authority
JP
Japan
Prior art keywords
cut
side wall
storage tank
crushed stone
tank structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4227460A
Other languages
Japanese (ja)
Other versions
JP2706407B2 (en
Inventor
Toru Komatsubara
徹 小松原
Shinichi Miyazaki
信一 宮崎
Satoru Amano
悟 天野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Tokyo Gas Co Ltd
Original Assignee
Obayashi Corp
Tokyo Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Tokyo Gas Co Ltd filed Critical Obayashi Corp
Priority to JP4227460A priority Critical patent/JP2706407B2/en
Publication of JPH0673748A publication Critical patent/JPH0673748A/en
Application granted granted Critical
Publication of JP2706407B2 publication Critical patent/JP2706407B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To conduct a cut-off between a clearance section in the periphery of a sidewall and a crushed stone layer in the lower section of a bottom block more effectively without requiring large numbers of execution labor hours and materials in an underground type storage tank structure. CONSTITUTION:A longitudinal ditch is excavated by using a chain cutter 10 along the predetermined position of the construction of a sidewall 1 in the lowermost section of the ground E. When mortar for a cut-off is placed under the state, in which a welding wire-gauze 14 for reinforcing a crack is installed into the excavated ditch 12, a longitudinal cut-off wall 16 is completed. Cut-off concrete 5 is placed at a position corresponding to the bottom of a gutter 4 as a clearance section as cut-off construction, the sidewall 1 is built continued to the upper section of the cut-off wall 16, and a crushed stone layer 2 is spread all over the inside of the side wall 1 and a bottom block 3 is constructed, thus completing the cut-off construction of an underground type storage tank structure having structure, in which the longitudinal cut-off wall 16 is unified into the lower ground E of the sidewall 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、地下式貯槽構造物に
おいて、側壁周囲の地下水が底版下部の砕石層へ迴り込
むことを防止するための止水方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of stopping water in an underground storage tank structure for preventing groundwater around the side wall from rushing into a crushed stone layer below the bottom slab.

【0002】[0002]

【従来の技術】図2は、従来の地下式貯槽構造物の構造
を示すもので、地盤Eの内側に逆巻きまたは順巻き工法
により構築された側壁1の底部内側に敷き詰められた砕
石層2と、砕石層2の上部にあって周囲を前記側壁に一
体化した状態に構築された底版3と、側壁1の外周に形
成され、砕石や砂等の透水性のある材料を充填したクリ
アランス部としての側溝4と、側壁1の上部に配置され
た図示しない屋根とを備えている。
2. Description of the Related Art FIG. 2 shows the structure of a conventional underground storage tank structure, in which a crushed stone layer 2 is laid on the inner side of a ground E on the bottom of a side wall 1 constructed by a reverse winding or forward winding method. , A bottom slab 3 formed on the top of the crushed stone layer 2 in a state where the periphery is integrated with the side wall, and a clearance portion formed on the outer periphery of the side wall 1 and filled with a water-permeable material such as crushed stone or sand. And a roof (not shown) arranged above the side wall 1.

【0003】そして、この側溝4には周囲の地盤Eから
供給される地下水が蓄えられ、その底部は前記側壁1の
最底部に到達しており、この部分には止水工として止水
コンクリート5を打設することによって地下水の砕石層
2側への迴り込みを防止している。
Groundwater supplied from the surrounding ground E is stored in the gutter 4, and the bottom of the groundwater reaches the bottom of the side wall 1. At this portion, a water-stopping concrete 5 is used as a water stop. By placing the above, it is possible to prevent the groundwater from running into the crushed stone layer 2 side.

【0004】[0004]

【発明が解決しようとする課題】すなわち、このような
構造を有する地下式貯槽構造物によれば、側溝4の内部
に蓄えられた地下水が、底版3に水圧がかからぬように
設けられた底版3の下部の砕石層2との水頭差によって
当該砕石層2に侵入するのを防止して、地下式貯槽構造
物における地下水の循環の管理を容易に行なうことがで
きる。そして、前記水頭差が増加する等により、砕石層
2に侵入しようとする水量が増加した場合に備えるとと
もに、地下水の循環の管理をより容易にすべく、さらに
効果的に地下水の砕石層2への侵入を防止することので
きる止水方法の開発が望まれている。
That is, according to the underground storage tank structure having such a structure, the ground water stored inside the gutter 4 is provided on the bottom slab 3 so that the water pressure is not applied. It is possible to prevent the intrusion into the crushed stone layer 2 due to the head difference from the crushed stone layer 2 below the bottom slab 3 and easily manage the circulation of groundwater in the underground storage tank structure. Then, in preparation for the case where the amount of water trying to enter the crushed stone layer 2 increases due to an increase in the water head difference or the like, the groundwater crushed stone layer 2 can be more effectively moved to more easily manage the circulation of groundwater. It is desired to develop a water blocking method that can prevent the intrusion of water.

【0005】そこで、この発明は上記のような状況を鑑
みてなされたもので、地下水の砕石層への侵入をより効
果的に防止することのできる、施工が容易でかつ経済的
な地下式貯槽構造物の止水方法を提供することを目的と
する。
Therefore, the present invention has been made in view of the above situation, and it is an economical and easy-to-construct underground storage tank that can more effectively prevent intrusion of groundwater into the crushed stone layer. It is an object to provide a method of stopping water for a structure.

【0006】[0006]

【課題を解決するための手段】前記目的を達成するた
め、この発明は、地盤内部に構築された側壁と、該側壁
の底部内側に配置された砕石層と、該砕石層上部にあっ
て前記側壁に周縁を一体化された底版と、前記側壁周囲
に設けた、砕石や砂等の材料が充填されるクリアランス
部としての側溝とを備えた地下式貯槽構造物において、
前記側壁下部の地盤を例えばチェーンカッター等の細溝
掘削機により縦長状に掘削し、該掘削溝内部に止水用モ
ルタル、止水用コンクリート等の固化材を打設して前記
側壁下部に連続する止水壁を形成するものである。
In order to achieve the above object, the present invention provides a side wall constructed inside the ground, a crushed stone layer arranged inside the bottom of the side wall, and an upper portion of the crushed stone layer. In an underground storage tank structure having a bottom slab having a peripheral edge integrated with a side wall, and a gutter provided around the side wall as a clearance portion filled with a material such as crushed stone or sand,
The ground at the lower part of the side wall is excavated in a vertically long shape by a fine groove excavator such as a chain cutter, and a solidifying material such as mortar for water stoppage or water stoppage concrete is placed inside the excavation groove to continuously connect to the lower part of the side wall. It forms a water blocking wall.

【0007】[0007]

【作用】以上の構成によれば、側壁下部の掘削溝を細溝
専用の掘削機で掘削するので、掘削溝を、地盤の周縁を
乱すことなく細い溝幅でかつ掘削深さを深く縦長状に掘
削でき、したがって、多くの材料を要することなく止水
壁を形成して地下水の浸透路長を容易に長くすることに
より、地下水の砕石層への侵入をより効果的に防止する
ことができる。
With the above construction, since the excavation groove at the bottom of the side wall is excavated by the excavator dedicated to the fine groove, the excavation groove has a narrow groove width without disturbing the peripheral edge of the ground and a deep excavation depth. Therefore, it is possible to more effectively prevent the intrusion of groundwater into the crushed stone layer by forming a water stop wall without increasing the amount of material and easily increasing the permeation path of groundwater. .

【0008】[0008]

【実施例】以下、この発明の一実施例を図面を用いて詳
細に説明する。図1(a)〜(c)はこの発明の止水方
法の施工手順を示すものである。なお、従来と同一部分
には同一符号を付して説明を行うものとする。まず、図
(a)において、地盤Eの最底部における側壁1の構築
予定箇所に沿って細溝用掘削機、例えばチェーンカッタ
ー10等を用いて縦長状の掘削溝12の掘削を行う。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described in detail below with reference to the drawings. 1 (a) to 1 (c) show the construction procedure of the water stopping method of the present invention. It should be noted that the same parts as those of the conventional art will be described with the same reference numerals. First, in FIG. 3A, a vertically long excavation groove 12 is excavated along a planned construction site of the side wall 1 at the bottom of the ground E using a fine groove excavator, for example, a chain cutter 10.

【0009】このチェーンカッター10は周知のもので
あり、簡略化された状態で描かれているが、アーム先端
のチェーンに沿って多数植設したカッターが無端状に回
転しつつ地盤を切削し、順次カッター幅に応じた溝幅で
地盤を掘削するもので、バックホウその他の掘削機に比
べて掘削溝12の周縁の地盤を乱すことなくカッター幅
に応じた幅で精度良く掘削が行え、本実施例において
は、一回の掘削作業で、掘削深さ約1.5m、溝幅約1
5cm程度の縦長状の掘削溝12が側壁1の下部に沿って
形成されることになる。
This chain cutter 10 is well known, and is drawn in a simplified state. However, a large number of cutters planted along the chain at the end of the arm cut the ground while rotating endlessly, It excavates the ground with a groove width that corresponds to the cutter width in sequence, and can excavate accurately with a width that corresponds to the cutter width without disturbing the ground at the periphery of the excavation groove 12 compared to backhoes and other excavators. In the example, the excavation depth is approximately 1.5 m and the groove width is approximately 1 in one excavation operation.
A vertically long excavation groove 12 of about 5 cm is formed along the lower portion of the side wall 1.

【0010】次いで、この掘削溝12内に図(b)に示
すように、ひびわれ補強用の溶接金網14を設置した状
態で止水用モルタル等を打設すれば、縦長状の止水壁1
6が完成する。
Next, as shown in FIG. 1B, if a mortar for stopping water is placed in a state where a welded wire net 14 for cracking is installed in the excavation groove 12, a vertically long water stopping wall 1 is formed.
6 is completed.

【0011】その後、側溝4の底部に当る箇所に止水工
として止水コンクリート5を打設し、また前記止水壁の
上部に連続して側壁1を構築し、この側壁1の内側に砕
石層2を敷き詰める。砕石層2の敷き均し後、底版3を
構築すれば図(c)に示すように側壁1の下部に縦長状
の止水壁16を一体化した構造の地下式貯槽構造物の止
水工が完成する。この止水壁16は縦長状であるため十
分な地下水の浸透路長を有し、これによって優れた止水
効果を得ることができる。
After that, water-stopping concrete 5 is placed as a water-stopping work at a position corresponding to the bottom of the gutter 4, and a side wall 1 is continuously constructed on the upper side of the water-stopping wall. Spread layer 2 over. After laying the crushed stone layer 2 and constructing the bottom slab 3, as shown in FIG. 1 (c), the water stop work of the underground storage tank structure in which the vertically long water stop wall 16 is integrated with the lower part of the side wall 1 Is completed. Since this water stop wall 16 is vertically long, it has a sufficient length of groundwater permeation path, and thereby an excellent water stop effect can be obtained.

【0012】[0012]

【発明の効果】以上実施例によって詳細に説明したよう
に、この発明による地下式貯槽構造物の止水方法にあっ
ては、浸透路長の増大によって地下水の砕石層への浸入
をより効果的に防止することができるとともに、細溝掘
削機によって地盤を乱すことなく形成される縦長状の掘
削溝内に止水用モルタル等の固化材を打設して、多くの
施工手間や使用材料を要することなく経済的に施工する
ことができる。
As described above in detail with reference to the embodiments, in the water stopping method for the underground storage tank structure according to the present invention, the infiltration path length is increased to more effectively infiltrate groundwater into the crushed stone layer. In addition to preventing this, a solid material such as water-stopping mortar is placed in a vertically elongated excavation groove formed without disturbing the ground by a fine groove excavator, which saves a lot of construction time and materials to be used. It can be constructed economically without any need.

【図面の簡単な説明】[Brief description of drawings]

【図1】(a)〜(c)はこの発明の止水方法の施工手
順を示す部分断面図である。
1A to 1C are partial cross-sectional views showing a construction procedure of a water stopping method of the present invention.

【図2】従来の地下式貯槽構造物の全体的構成を示す断
面説明図である。
FIG. 2 is an explanatory cross-sectional view showing the overall structure of a conventional underground storage tank structure.

【符号の説明】[Explanation of symbols]

1 側壁 2 砕石層 3 底版 4 側溝 10 細溝掘削機(チェーンカッター) 12 掘削溝 16 止水壁 1 Sidewall 2 Crushed stone layer 3 Bottom plate 4 Gutter 10 Fine groove excavator (chain cutter) 12 Excavation groove 16 Water stop wall

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地盤内部に構築された側壁と、該側壁の
底部内側に配置された砕石層と、該砕石層上部にあって
前記側壁に周縁を一体化された底版と、前記側壁周囲に
設けたクリアランス部としての側溝とを備えた地下式貯
槽構造物において、 前記側壁下部の地盤を細溝掘削機により縦長状に掘削
し、該掘削溝内部に止水用モルタル、止水用コンクリー
ト等の固化材を打設して前記側壁下部に連続する止水壁
を形成することを特徴とする地下式貯槽構造物の止水方
法。
1. A side wall constructed inside the ground, a crushed stone layer arranged inside a bottom portion of the side wall, a bottom slab above the crushed stone layer and having a peripheral edge integrated with the side wall, and around the side wall. In an underground storage tank structure provided with a gutter as a clearance portion provided, the ground at the lower part of the side wall is vertically elongated by a fine groove excavator, and mortar for water stop, concrete for water stop, etc. inside the groove. 2. A method of stopping water for an underground storage tank structure, which comprises forming a continuous water stop wall below the side wall by pouring the solidified material.
JP4227460A 1992-08-26 1992-08-26 Water stopping method for underground storage tank structure Expired - Fee Related JP2706407B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4227460A JP2706407B2 (en) 1992-08-26 1992-08-26 Water stopping method for underground storage tank structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4227460A JP2706407B2 (en) 1992-08-26 1992-08-26 Water stopping method for underground storage tank structure

Publications (2)

Publication Number Publication Date
JPH0673748A true JPH0673748A (en) 1994-03-15
JP2706407B2 JP2706407B2 (en) 1998-01-28

Family

ID=16861226

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4227460A Expired - Fee Related JP2706407B2 (en) 1992-08-26 1992-08-26 Water stopping method for underground storage tank structure

Country Status (1)

Country Link
JP (1) JP2706407B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5898393U (en) * 1981-12-25 1983-07-04 日立造船株式会社 Groundwater pressure adjustable underground tank
JPH0198250U (en) * 1987-12-18 1989-06-30
JPH04131429A (en) * 1990-09-21 1992-05-06 Shimizu Corp Underground structure
JPH04131430A (en) * 1990-09-21 1992-05-06 Shimizu Corp Underground structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5898393U (en) * 1981-12-25 1983-07-04 日立造船株式会社 Groundwater pressure adjustable underground tank
JPH0198250U (en) * 1987-12-18 1989-06-30
JPH04131429A (en) * 1990-09-21 1992-05-06 Shimizu Corp Underground structure
JPH04131430A (en) * 1990-09-21 1992-05-06 Shimizu Corp Underground structure

Also Published As

Publication number Publication date
JP2706407B2 (en) 1998-01-28

Similar Documents

Publication Publication Date Title
JP3284047B2 (en) Construction method of underground diaphragm wall
JP2003020631A (en) Impervious structure and construction method for fill dam
JPS60500875A (en) Method and device for constructing reinforced concrete walls underground
JPH1171748A (en) Structure in periphery of underground structure in soft ground and method of construction thereof
JP3893056B2 (en) Construction method of underground structure
JP4410572B2 (en) Construction method of revetment for landfill
JPH0673748A (en) Cut-off method of underground type storage tank structure
JP4020858B2 (en) Manufacturing method for underground structures
JP2000087361A (en) Construction method of underground structure
JP2927727B2 (en) Construction method of underground structure
JP2809105B2 (en) How to build an underground tank
JP3318495B2 (en) Method of forming a permeable layer on soil cement underground wall
JP2874906B2 (en) Shaft construction method
JP3700121B2 (en) Water blocking wall under culvert and its construction method
KR102625776B1 (en) Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function
JP2846248B2 (en) Earth retaining wall and construction method
JP3027685B2 (en) Earth retaining wall and construction method
JP2933546B2 (en) Basement construction method and lower frame material used in the construction method
JPH0310200Y2 (en)
JPS6030814B2 (en) Method to prevent subsidence of surrounding ground due to excavation
JPS598826A (en) Construction of underground wall by excavation of inside of pc plate
JPH01121414A (en) Excavation work of ground
JPH0553890B2 (en)
JPH0122410B2 (en)
JP2001107361A (en) Earth retaining work structure and ground excavation method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees