JPH0657774A - Repair work of paved road provided with facilities - Google Patents

Repair work of paved road provided with facilities

Info

Publication number
JPH0657774A
JPH0657774A JP4231620A JP23162092A JPH0657774A JP H0657774 A JPH0657774 A JP H0657774A JP 4231620 A JP4231620 A JP 4231620A JP 23162092 A JP23162092 A JP 23162092A JP H0657774 A JPH0657774 A JP H0657774A
Authority
JP
Japan
Prior art keywords
road
layer
overlay
bed
manhole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4231620A
Other languages
Japanese (ja)
Inventor
Shogo Miyamoto
本 正 吾 宮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TASUTETSUKU KK
Original Assignee
TASUTETSUKU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TASUTETSUKU KK filed Critical TASUTETSUKU KK
Priority to JP4231620A priority Critical patent/JPH0657774A/en
Publication of JPH0657774A publication Critical patent/JPH0657774A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)
  • Road Repair (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To calmly repair a paved road around facilities thereon in a short time with high quality. CONSTITUTION:After existing facilities on a road are removed, an opening of a concrete pipe CP buried in a basic bed BL is closed by a cover. Next, after the upper face of the cover is covered with a temporary recovery bed TL, an overlay bed OL is laid further thereon. The superficial bed is cut with the overlay bed. After the overlay bed, the temporary recovery bed, and the cover are all removed, the manhole MA is again installed and fixed by the repair bed. After the surface of temporary recovery bed is excavated by a specified thickness, an overlay bed is laid on the upper face thereof.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、マンホールなどの道
路設置物を備えた舗装道路において、既設の道路設置物
を一旦撤去し、再度、この設置物を据付けるようにした
舗装道路の補修工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for repairing a paved road, in which an existing road installation is once removed from a paved road provided with a road installation such as a manhole and the installation is installed again. It is about.

【0002】[0002]

【従来の技術】従来、マンホールや取水弁などの道路設
備や、その周辺の舗装路面が損壊され、その補修を要す
る際の工法としては、たとえば、オーバーレイ工法もし
くは切削打換え工法などが広く知られているところであ
る。
2. Description of the Related Art Conventionally, as a method for repairing road facilities such as manholes and intake valves and the paved road surface around them, which require repair, for example, an overlay method or a cutting replacement method is widely known. It's about to come.

【0003】この各工法の内で、前記オーバーレイ工法
にあっては、所要のカッターなどにより道路設置物の周
辺の舗装道路を切断し、ブレーカーなどを利用して道路
設置物の外周に付着した舗装道路の切断片を破砕・除去
した後、この道路設置物を撤去し、適宜、高さ調整の工
事を施工した後、再度道路設置物を据付け、その外周部
にスリツケ復旧処理し、最後にオーバーレイ層としてア
スファルトなどを敷設施工するものである。
Among the above construction methods, in the overlay construction method, the pavement around the road installation is cut with a required cutter or the like, and the pavement attached to the outer periphery of the road installation using a breaker or the like. After crushing and removing the cut pieces of the road, this road installation is removed, the height adjustment work is properly performed, the road installation is installed again, and the slippery recovery processing is performed on the outer periphery of the road installation, and finally overlay. Asphalt is laid as a layer.

【0004】又、道路の切削打換え工法にあっては、予
め舗装道路の表面を切削処理した後、道路設置物の外周
に付着した舗装道路部分を破砕して除去し、一旦道路設
置物の外周辺をスリツケ仮復旧させた後、この道路設置
物を撤去するものであり、以後の工程は、前記のオーバ
ーレイ工法と共通しているのでその詳細な説明は割愛す
る。
Further, in the road cutting and replacement method, after cutting the surface of the paved road in advance, the paved road portion adhering to the outer periphery of the road installation is crushed and removed, and the road installation is temporarily removed. This road installation is to be removed after the outer circumference has been temporarily restored, and the subsequent steps are common to the above-mentioned overlay construction method, so a detailed description thereof will be omitted.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、前記の
従来の各工法にあっては、以下に述べる如き幾つかの解
決すべき課題が残されていた。
However, in each of the above-mentioned conventional construction methods, there still remain some problems to be solved as described below.

【0006】(1) 交通の危険性。 即ち、オーバーレイ工法にあっては、前記の如くにスリ
ツケ仮復旧工事により道路設置物の外周部の道路が傾斜
状に仮復旧されているとは言え、再度据付けた前記の道
路設置物は、復旧工事中の周辺の道路よりも比較的に高
く突出しているため、道路閉鎖が仮解除された際にあっ
ては、運行車輌がこの道路設置物に乗り上げて、運転者
が不用意にハンドルをとられ交通事故の発生の危険性が
あるものであり、又同様に切削打換え工法の場合にあっ
ても、道路設置物が切削された道路表面から高く突出し
ているため、道路交通上の危険性は前記のオーバーレイ
工法と同様であった。
(1) Danger of traffic. That is, in the overlay method, although the road on the outer periphery of the road installation is temporarily restored to the slope by the Surisuke temporary restoration work as described above, the above-mentioned road installation re-installed is restored. Since it projects relatively higher than the surrounding road under construction, when the road closure is temporarily released, the operating vehicle rides on this road installation and the driver inadvertently removes the steering wheel. There is a risk that a traffic accident will occur. Similarly, even in the case of the cutting and replacement method, the road installation is highly protruding from the surface of the cut road, so there is a risk of road traffic. Was similar to the above overlay method.

【0007】(2) 道路設置物の破損・変位。 前記の各工法のいずれの場合にも、道路が仮解放された
際の通行車輌のみならず、道路舗装工事用のアスファル
トフィニッシャや、マカダム・ダンデム鉄輪ローラもし
くはタイヤローラなどがこの道路設置物上に乗り上げた
場合などにあっては、道路設置物が破損され、又は、モ
ルタルやボルトなどによって仮固定された道路設置物
が、所要の正常位置からズレ動いて変位して施工の正確
性を損なうおそれがあった。
(2) Damage / displacement of road installations. In any of the above construction methods, not only the vehicles that pass when the road is temporarily released, but also the asphalt finisher for road paving work, Macadam / Dandem iron wheel roller, tire roller, etc. When riding, etc., the road installation may be damaged, or the road installation temporarily fixed with mortar, bolts, etc. may be displaced from the required normal position and displaced, impairing the accuracy of construction. was there.

【0008】(3) 舗装道路の品質上の不安。 前記のオーバーレイ工法および切削打換え工法のいずれ
の工法の場合にも、完成された道路の高さを想定し、こ
れに整合する高さ位置に予め道路設置物を据付け処理す
るものであるため、未だ打設されていない完成された道
路表面の高さを想定して道路設置物の高さの位置決めを
行い、これを据付ける方法であるため、補修工事が終了
した際には道路工事と、道路設置物の高さが一致せず、
舗装道路面と道路設置物との間に段差が生じ、道路の平
坦性が損なわれるおそれがあった。
(3) Concerns about the quality of paved roads. In the case of any of the above-mentioned overlay construction method and cutting replacement construction method, the height of the completed road is assumed, and because the road installation is preliminarily installed at a height position that matches this, It is a method of positioning the height of the road installation assuming the height of the completed road surface that has not been cast and installing this, so when the repair work is completed, The heights of road installations do not match,
There is a possibility that a level difference may occur between the paved road surface and the road installation, and the flatness of the road may be impaired.

【0009】又、現実にアルファルトフィニッシャなど
により道路舗装を施工する際には、そのクローラやタイ
ヤなどの足廻り部が突出状の道路設置物に乗り上げ、車
体が傾斜し、結果的にスクリード高さに変化を生じ、舗
装道路面の平坦性が保証されないという結果をも招いて
いた。
In addition, when actually constructing a road pavement using an Alfalto finisher or the like, the underbody of the crawler, tires, etc. rides on a projecting road installation, the vehicle body leans, and as a result, the screed height increases. However, the flatness of the paved road surface could not be guaranteed, resulting in the result.

【0010】以上の如くに、従来の各工法においては、
道路交通上の不安のみならず、完成された舗装道路の品
質にも改善すべき課題が残されていた。
As described above, in each conventional construction method,
Not only anxiety about road traffic, but also the quality of the finished paved road remains to be improved.

【0011】従って、道路補修施工業者からは、工事中
の交通の安全が図れ、しかも高品質に舗装路面の補修が
完了する工法の提供が要請されていた。
Therefore, a road repair contractor has been requested to provide a construction method capable of ensuring the safety of traffic during construction and of completing the repair of the paved road surface with high quality.

【0012】[0012]

【課題を解決するための手段】この発明の目的とすると
ころは、工事中の交通の安全性が確保でき、又、道路設
置物の損傷などが未然防止でき、しかも完成された舗装
道路の品質が保証されうるという優れた工法を提供する
ことであって、その構成上の特徴点は、マンホールなど
の道路設置物を備えた舗装道路の補修工法において、既
設の道路設置物の撤去後に、基層に埋設したコンクリー
ト管の開口部を蓋手段で閉塞させ、次で、この蓋手段の
上面を仮復旧層で被覆させ、更にその上面にオーバーレ
イ層を敷設し、このオーバーレイ層と共に表層を切断
し、オーバーレイ層と仮復旧層ならびに蓋手段を取り除
いた後、再びマンホールを据付け、補修層によりこのマ
ンホールを固定するようにし、又、前記の仮復旧層の表
面を、所要の厚み分だけ切削した後、その上面にオーバ
ーレイ層を敷設するようにした道路設置物を備えた舗装
道路の補修工法となした点にある。
The object of the present invention is to ensure the safety of traffic during construction, prevent damage to road installations, etc., and ensure the quality of completed paved roads. Is to provide an excellent construction method that can be guaranteed, and the characteristic feature of the construction is that in the method of repairing paved roads with road installations such as manholes, after removing existing road installations, The opening of the concrete pipe buried in is closed by a lid means, then, the upper surface of this lid means is covered with a temporary restoration layer, an overlay layer is laid on the upper surface, and the surface layer is cut together with this overlay layer, After removing the overlay layer, the temporary restoration layer, and the lid means, the manhole is installed again, and the manhole is fixed by the repair layer, and the surface of the temporary restoration layer is fixed to the required thickness. Only after cutting, it is in that no a repairing method of pavement having a road installed object which is adapted to lay an overlay layer on the upper surface thereof.

【0013】[0013]

【作 用】この発明の工法は、前記の通りであるか
ら、補修を要する箇所の道路設置物を取り外した後、そ
の開口部を蓋手段で仮閉塞し、その上面に仮復旧層なら
びにオーバーレイ層を敷設し、これら各層を切断して蓋
手段と共に取り除いた後で、道路設置物を設置するもの
である。
[Operation] Since the construction method of the present invention is as described above, after removing the road installation at the place requiring repair, the opening is temporarily closed by the lid means, and the temporary restoration layer and the overlay layer are provided on the upper surface. Is laid, each of these layers is cut and removed together with the lid means, and then the road installation object is installed.

【0014】[0014]

【実 施 例】次に、この発明の内容を、その一実施例
を示す図面に基づいて説明する。
EXAMPLES Next, the contents of the present invention will be explained based on the drawings showing an example thereof.

【0015】図1乃至図8には、道路設置物の一例とし
てマンホールの周辺を補修する切削打換え形式の工法が
示されており、図9には、この工法において利用される
舗装路面の切断装置が記載されている。
1 to 8 show a cutting and replacement type construction method for repairing the periphery of a manhole as an example of a road installation, and FIG. 9 shows cutting of a paved road surface used in this construction method. The device is described.

【0016】そこで、この実施例の工法の説明に先立っ
て、前記の切断装置(1)の構成について、図9を参照
して説明する。
Therefore, prior to the description of the construction method of this embodiment, the construction of the cutting device (1) will be described with reference to FIG.

【0017】図9に示す如くにこの切断装置(1)は図
示しない駆動源によって旋回駆動される駆動筒(11)
の下端に一体的に連設した前記の円筒カッター(12)
の下縁には多数の切断刃(12a)を周設し、又、この
円筒カッター(12)の昇降移動を案内するガイド(1
3)には、円板状のベース部(13a)と、その中心部
に突設したガイド軸(13b)とが設けられており、こ
のガイド軸(13b)を前記の駆動筒(11)の案内孔
(11a)に挿入自在に構成したものであり、又、前記
のベース部(13a)の外周部にはコンクリート釘(1
4)を透通させる透孔(13c)が開設された構成とさ
れている。
As shown in FIG. 9, the cutting device (1) has a drive cylinder (11) which is driven to rotate by a drive source (not shown).
The cylindrical cutter (12) integrally connected to the lower end of the
A plurality of cutting blades (12a) are provided around the lower edge of the lower edge, and a guide (1) for guiding the vertical movement of the cylindrical cutter (12).
3) is provided with a disk-shaped base portion (13a) and a guide shaft (13b) protruding from the center thereof, and the guide shaft (13b) is connected to the drive cylinder (11). It is configured so that it can be inserted into the guide hole (11a), and the concrete nail (1) is attached to the outer peripheral portion of the base portion (13a).
It is configured such that a through hole (13c) for allowing 4) to pass therethrough is opened.

【0018】以下に、この実施例の工法について図1乃
至図8に基づいて各工程毎に詳しく説明する。
The construction method of this embodiment will be described below in detail for each step with reference to FIGS. 1 to 8.

【0019】(1) 切断工程 図1に示す如くに基層(BL)内に埋設されたマンホー
ル用のコンクリート管(CP)上にマンホール(MA)
を載置し、その周囲を表層(FL)で舗装した状態にお
いて、マンホール(MA)の周辺の舗装路面を補修する
に当っては、切断装置(1)の円筒カッター(12)の
下縁の切断刃(12a)を、図1に示す如くに舗装道路
の表層(FL)に臨ませ、その駆動筒(11)を図示し
ない駆動源によって旋回させつつ下降させることによ
り、マンホール(MA)の外周の表層(FL)を切断処
理するものである。
(1) Cutting Step As shown in FIG. 1, a manhole (MA) is placed on a concrete pipe (CP) for a manhole embedded in a base layer (BL).
When the paved road surface around the manhole (MA) is to be repaired in a state in which the surface is paved with the surface layer (FL), the lower edge of the cylindrical cutter (12) of the cutting device (1) is As shown in FIG. 1, the cutting blade (12a) is exposed to the surface layer (FL) of the paved road, and the drive cylinder (11) is rotated and lowered by a drive source (not shown) to lower the outer periphery of the manhole (MA). The surface layer (FL) is cut.

【0020】(2) マンホール除去工程 次に、チェンブロックもしくは油圧式取外し装置その他
の図示しない取外し手段によって、図2におけるマンホ
ール(MA)とその周辺の表層部分(FP)を除去する
ものであるが、この際には、たとえばブレーカなどの破
砕具によって、予め表層部分(FP)をマンホール(M
A)から破断させ、マンホール(MA)と、破断された
表層部分(FP)を個別的に除去する方法が好ましいも
のである。
(2) Manhole Removing Step Next, the manhole (MA) and the peripheral surface layer portion (FP) in FIG. 2 are removed by a chain block, a hydraulic removing device, or other removing means (not shown). At this time, the surface layer portion (FP) is previously manhole (M) with a crushing tool such as a breaker.
A method in which the manhole (MA) and the ruptured surface layer portion (FP) are individually removed by rupturing from A) is preferable.

【0021】(3) 仮復旧工程 次に、図3に示すように、コンクリート管(CP)上を
目暗し蓋(BC)によって塞いだ後、図4に示すように
その上面にアスファルトなどにより仮復旧層(TL)を
敷設する。
(3) Temporary Restoration Step Next, as shown in FIG. 3, after the concrete pipe (CP) is darkened and covered with a lid (BC), the upper surface thereof is covered with asphalt or the like as shown in FIG. Laying a temporary restoration layer (TL).

【0022】(4) オーバーレイ工程 次で、この仮復旧層(TL)を所望の厚み、即ち、後述
のオーバーレイ層(OL)が敷設された際に、その高さ
が所望の高さとなるように、これに適合する程度の厚み
になるまで道路平滑処理装置(図示略)によって、図5
に破線で示す如くにこの仮復旧層(TL)の頂面を切削
し、次でその表面上に表層(FL)を形成するオーバー
レイ層(OL)を敷設する(図6参照)。
(4) Overlay step Next, the provisional restoration layer (TL) is adjusted to have a desired thickness, that is, when the overlay layer (OL) described below is laid, the height of the temporary restoration layer (TL) becomes a desired height. , A road smoothing device (not shown) is used to adjust the thickness to the level shown in FIG.
The top surface of the temporary restoration layer (TL) is cut as indicated by a broken line in FIG. 2 and then an overlay layer (OL) for forming a surface layer (FL) is laid on the surface (see FIG. 6).

【0023】(5) 切断工程 次に、図7に示す如くに、図9に示すガイド(13)を
オーバーレイ層(OL)上の所望の個所、例えば予め計
測済みのマンホール(MA)の中心位置に載置し、コン
クリート釘(14)をそのベース(13a)の透孔(1
3b)に透通させると共に、オーバーレイ層(OL)に
打ち込んでガイド(13)を固定する。
(5) Cutting Step Next, as shown in FIG. 7, a guide (13) shown in FIG. 9 is provided at a desired position on the overlay layer (OL), for example, a center position of a pre-measured manhole (MA). Place the concrete nail (14) on the through hole (1) of its base (13a).
3b) and penetrate into the overlay layer (OL) to fix the guide (13).

【0024】その後、図9に示す切断装置(1)の駆動
筒(11)を、ガイド(13)のガイド軸(13c)に
嵌合させ、この状態で駆動筒(11)を旋回させながら
下降させることにより、円筒カッター(12)によりオ
ーバーレイ層(OL)が切断するものである。
Thereafter, the drive cylinder (11) of the cutting device (1) shown in FIG. 9 is fitted to the guide shaft (13c) of the guide (13), and in this state, the drive cylinder (11) is rotated and lowered. By doing so, the overlay layer (OL) is cut by the cylindrical cutter (12).

【0025】(6) 取外し工程 次で、図示しない取外し手段によって、円板状に切断さ
れた切断層(OP)と共に、仮復旧層(TL)ならびに
目暗い蓋(BC)を取外し、コンクリート管(CP)の
開口が露呈された状態とする。
(6) Removal Step Next, the temporary restoration layer (TL) and the dark cover (BC) are removed together with the cutting layer (OP) cut into a disc shape by a removing means (not shown), and the concrete pipe ( The opening of (CP) is exposed.

【0026】(7) マンホール設置工程 次に、前工程によって露呈されたコンクリート管(C
P)上にマンホール(MA)を載置し、最後にその外周
部を補修材によって充填してオーバーレイ層(OL)と
同一表面を形成する補修層(RL)を形成することによ
り、マンホール(MA)の外周辺の舗装路面の補修処理
が完了するものである(図8参照)。
(7) Manhole installation process Next, the concrete pipe (C
P), the manhole (MA) is placed on the manhole (MA), and the outer periphery of the manhole (MA) is finally filled with a repair material to form a repair layer (RL) that forms the same surface as the overlay layer (OL). The repair processing of the paved road surface around the outer periphery of () is completed (see FIG. 8).

【0027】[0027]

【発明の効果】この発明は、以上のようにその実施例に
よって詳細に説明した如くに構成された工法であるか
ら、次に述べるような顕著な効果を発揮しうるものであ
る。
Since the present invention is a construction method constructed as described above in detail with reference to its embodiments, the following remarkable effects can be exhibited.

【0028】(1) 補修工事の品質の向上。 この発明の工法においては、予め計画高さにオーバーレ
イ層を打設した後、道路設置物を据付け施工するもので
あるから、舗装道路面と道路設置物との高さ位置が完全
に整合させうるものであり、道路の平坦性が保証される
ものであり、又スリツケ工程が不要であるなど工期は大
巾に短縮され、道路交通上の利点は極めて大きいもので
ある。
(1) Improving the quality of repair work. In the construction method of the present invention, since the road installation is installed after the overlay layer has been cast at the planned height in advance, the height positions of the paved road surface and the road installation can be perfectly matched. However, the flatness of the road is guaranteed, and the construction process is greatly shortened, such as the need for a picking process, and the advantages of road traffic are extremely great.

【0029】(2) 補修工事の静粛化。 この発明の工法にあっては、既設の道路設置物を撤去す
る際に、短時間だけ道路を切断する騒音が発生されるだ
けで、それ以外の全工法にわたっては、極めて静粛に工
事が遂行されるものであって、近隣に与える騒音による
不快感を大巾に低減させうるものであり、特に都市部で
の補修工事に最適の工法が得られるものである。
(2) Quiet repair work. In the construction method of the present invention, when removing the existing road installation, only the noise of cutting the road for a short time is generated, and the construction is performed extremely quietly over all other construction methods. In addition, the uncomfortable feeling due to noise in the neighborhood can be greatly reduced, and an optimal construction method can be obtained especially for repair work in urban areas.

【0030】(3) 道路交通上の安全性の確保。 道路補修工事中は、道路設置物の撤去後は、直ちにコン
クリート管が閉止され仮復旧されるものであるから、道
路交通上の危険性が解消されるものであり、オーバーレ
イ層が打設された後に道路設置物が再び据付けられるも
のであるから、通行車輌の運転に支障がなく安全であ
る。
(3) Ensuring safety of road traffic. During road repair work, after removing the road installation, the concrete pipe will be closed and temporarily restored, so the danger of road traffic will be eliminated and the overlay layer was laid. Since the road installation will be installed again later, there is no obstacle in driving the vehicle and it is safe.

【0031】(4) 道路設置物の安全保証。 前記の如くに、道路設置物は、オーバーレイ層の打設後
に据付けられるため、通行車輌や道路工事車輌によって
損傷され、変位されることがなく、正確に据付けられ
る。
(4) Safety assurance of road installations. As described above, since the road installation object is installed after the overlay layer is placed, the road installation object can be accurately installed without being damaged or displaced by a traffic vehicle or a road construction vehicle.

【図面の簡単な説明】[Brief description of drawings]

【図1】マンホールの周辺の舗装路面を補修するこの発
明の一実施例の切断工程図。
FIG. 1 is a cutting process diagram of an embodiment of the present invention for repairing a paved road surface around a manhole.

【図2】同マンホール除去工程図。FIG. 2 is a process drawing of the same manhole removal process.

【図3】同仮復旧工程図。FIG. 3 is a temporary restoration process diagram.

【図4】同仮復旧工程図。FIG. 4 is a temporary restoration process diagram.

【図5】同仮復旧工程図。FIG. 5 is a temporary restoration process diagram.

【図6】同オーバーレイ工程図。FIG. 6 is a view of the overlay process.

【図7】同切断工程図。FIG. 7 is a cutting process diagram of the same.

【図8】同マンホール設置工程図。FIG. 8 is a process drawing of the manhole installation.

【図9】切断装置の一部縦断面図。FIG. 9 is a partial vertical cross-sectional view of the cutting device.

【符号の説明】[Explanation of symbols]

BL 基層 FL 表層 CP コンクリート管 MA マンホール BC 目暗し蓋 TL 仮復旧層 OL オーバーレイ層 RL 補修層 BL Base layer FL Surface layer CP Concrete pipe MA Manhole BC Darkening lid TL Temporary restoration layer OL Overlay layer RL Repair layer

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 マンホールなどの道路設置物を備えた舗
装道路の補修工法において、既設の道路設置物の撤去後
に、基層に埋設したコンクリート管の開口部を蓋手段で
閉塞させ、次で、この蓋手段の上面を仮復旧層で被覆さ
せ、更にその上面にオーバーレイ層を敷設し、このオー
バーレイ層と共に表層を切断し、オーバーレイ層と仮復
旧層ならびに蓋手段を取り除いた後、再びマンホールを
据付け、補修層によりこのマンホールを固定するように
した道路設置物を備えた舗装道路の補修工法。
1. In a method for repairing a paved road having a road installation such as a manhole, after removing the existing road installation, the opening of the concrete pipe buried in the base layer is closed by a lid means, and then, The upper surface of the lid means is covered with a temporary restoration layer, an overlay layer is further laid on the upper surface, the surface layer is cut together with this overlay layer, and after removing the overlay layer, the temporary restoration layer and the lid means, the manhole is installed again, A repair method for paved roads with road installations that fix this manhole by a repair layer.
【請求項2】 前記の仮復旧層の表面を、所要の厚み分
だけ切削した後、その上面にオーバーレイ層を敷設する
ようにした請求項1記載の道路設置物を備えた舗装道路
の補修工法。
2. The method for repairing a paved road with a road installation according to claim 1, wherein the surface of the temporary restoration layer is cut by a required thickness, and then an overlay layer is laid on the upper surface thereof. .
JP4231620A 1992-08-07 1992-08-07 Repair work of paved road provided with facilities Pending JPH0657774A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4231620A JPH0657774A (en) 1992-08-07 1992-08-07 Repair work of paved road provided with facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4231620A JPH0657774A (en) 1992-08-07 1992-08-07 Repair work of paved road provided with facilities

Publications (1)

Publication Number Publication Date
JPH0657774A true JPH0657774A (en) 1994-03-01

Family

ID=16926368

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4231620A Pending JPH0657774A (en) 1992-08-07 1992-08-07 Repair work of paved road provided with facilities

Country Status (1)

Country Link
JP (1) JPH0657774A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002044477A1 (en) * 2000-12-01 2002-06-06 Hanex Road Co., Ltd. Steel cover-less manhole and method of constructing the manhole
JP2006283493A (en) * 2005-04-04 2006-10-19 Yamaichi Kenki Kk Cutter for manhole

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05179607A (en) * 1991-12-30 1993-07-20 Shinichi Tsubakimori Cutting overlay construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05179607A (en) * 1991-12-30 1993-07-20 Shinichi Tsubakimori Cutting overlay construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002044477A1 (en) * 2000-12-01 2002-06-06 Hanex Road Co., Ltd. Steel cover-less manhole and method of constructing the manhole
JP2006283493A (en) * 2005-04-04 2006-10-19 Yamaichi Kenki Kk Cutter for manhole

Similar Documents

Publication Publication Date Title
CN111648408A (en) Inspection well lifting construction method
RU2266370C2 (en) Method for manhole chimney and cover replacement
KR101586808B1 (en) Circle cutter using engine power having axis of rotation
JPH0657774A (en) Repair work of paved road provided with facilities
JP2623491B2 (en) Cutting overlay method
US8375551B2 (en) Method for covering an above ground access opening to a conduit assembly
KR100488401B1 (en) Execution method for repairing manhole and manhole structure repaired by the same execution method
JPH086284B2 (en) How to repair height of sunken concrete pavement
JP3171675U (en) Anti-sinking floor slab with maneuvering prevention function
JPH03194004A (en) Precast concrete pavement plate having both surface usable and method of laying thereof
KR960004915B1 (en) Overlay method for height adjustable manhole
KR950014585B1 (en) Cutting & paving method of incline manhole
CA2553726A1 (en) Setting utility access covers
KR960004916B1 (en) Overlay method for height adjustable manhole
JPS621315Y2 (en)
GB2519168A (en) A kerb arrangement
JP4587524B2 (en) Pavement method around the ground surface composition
JP2004332522A (en) Overlay construction method, cutting overlay construction method, and paving construction method
KR20130047094A (en) Overspeed protection road block
JPS6133938B2 (en)
JP3759493B2 (en) Repair method around the manhole cover frame
US9988769B2 (en) Method for forming a surface around an embedded conduit