JPH06336782A - Floor frame constructed of combined precast member - Google Patents
Floor frame constructed of combined precast memberInfo
- Publication number
- JPH06336782A JPH06336782A JP12884493A JP12884493A JPH06336782A JP H06336782 A JPH06336782 A JP H06336782A JP 12884493 A JP12884493 A JP 12884493A JP 12884493 A JP12884493 A JP 12884493A JP H06336782 A JPH06336782 A JP H06336782A
- Authority
- JP
- Japan
- Prior art keywords
- girders
- beams
- floor
- floor frame
- capital
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、耐震要素を外周回り
に配設した建物においてプレキャスト部材を組み合わせ
て構成される床架構に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a floor frame constructed by combining precast members in a building in which seismic resistant elements are arranged around the outer circumference.
【0002】[0002]
【従来の技術】耐震要素を外周回りに配設した建物の床
架構を設計する場合、鉛直時応力のみを対象としている
ため、従来においては、フラットスラブ構造や断面の比
較的小さいラーメン構造などの経済的な設計がなされて
いる。工法的には、合理化工法が殆ど採用されず、従来
型(木型枠+支保工)が依然として多い。2. Description of the Related Art When designing a floor frame structure of a building in which seismic resistant elements are arranged around the outer circumference, only the vertical stress is targeted. Therefore, conventionally, a flat slab structure or a rigid frame structure with a relatively small cross section is used. Economically designed. In terms of construction method, the rationalized construction method is rarely adopted, and there are still many conventional types (wooden formwork + support work).
【0003】[0003]
【発明が解決しようとする課題】しかしながら、将来の
建設業を取り巻く環境(木型枠の減少、建設労働者の減
少等)を考えた場合、木型枠・支保工を用いない、より
一層の合理化工法が望まれている。However, considering the environment surrounding the future construction industry (decrease in wooden formwork, decrease in construction workers, etc.) A rationalized construction method is desired.
【0004】そこで、柱・梁・床板を分割されたプレキ
ャスト部材で構成し、木型枠の使用を低減し、無支保工
化を図る工法が考えられているが、一般的な構造の床架
構では、一方向板になって床荷重が一方向の大梁に集中
作用し、また床板が大型化するなどプレキャスト化が容
易でない。また、床荷重を二方向の大梁に分散伝達させ
るべく格子梁を使用すると、施工が面倒となる。Therefore, a construction method has been considered in which the columns, beams, and floorboards are composed of divided precast members to reduce the use of wooden formwork and to eliminate unsupported construction. Then, it becomes a unidirectional plate, and the floor load concentrates on the unidirectional girder, and the floorboard becomes large, so it is not easy to precast. In addition, if grid beams are used to disperse and transfer the floor load to the large beams in two directions, the construction will be troublesome.
【0005】この発明は、前述のような事情に鑑みてな
されたもので、その目的は、耐震要素を外周回りに配設
した建物において、比較的簡単な構造で床荷重を二方向
の大梁に分散伝達でき、床架構のプレキャスト化が容易
となる床架構を提供することにある。The present invention has been made in view of the above-mentioned circumstances, and an object thereof is to provide a floor load to a large beam in two directions with a relatively simple structure in a building in which seismic resistant elements are arranged around the outer circumference. An object of the present invention is to provide a floor frame structure that can be distributed and transmitted and can be easily precast.
【0006】[0006]
【課題を解決するための手段】この発明に係る床架構
は、耐震要素を外周回りに配設した建物における柱・キ
ャピタル・梁・床板をプレキャスト部材で構成した床架
構(柱はプレキャスト部材に限らず現場打ちでもよい)
において、中心となる一つの柱を取り囲む4つの柱のキ
ャピタル間に大梁を掛け渡し、前記中心の柱のキャピタ
ルと4つの大梁の中間部との間に小梁を掛け渡し、これ
ら大梁と小梁で構成される小区画に床板を配設して大梁
と小梁で支持するように構成する。A floor frame structure according to the present invention is a floor frame structure in which a pillar, a capital, a beam, and a floor plate in a building in which seismic resistant elements are arranged around the outer periphery are composed of precast members (the pillar is not limited to the precast members. Instead, it may be cast on site.)
In the above, a large beam is bridged between the capitals of the four pillars that surround one central pillar, and a beam is bridged between the capital of the central pillar and the middle part of the four pillars. A floorboard is arranged in a small section composed of and supported by a large beam and a small beam.
【0007】[0007]
【作用】以上のような構成において、柱、梁等をプレキ
ャスト部材とすることにより、木型枠の使用を低減し、
無支保工化を図れる。床板は大梁と小梁に支持され、床
荷重は一方の大梁と、小梁を介して他方の大梁とに伝達
され、格子梁を使用しなくても二方向の大梁に分散伝達
される。In the above structure, the use of wooden formwork is reduced by using the pillars, beams, etc. as precast members,
Unsupported work can be achieved. The floorboard is supported by girders and girders, and the floor load is transmitted to one girder and the other girder via the girder, and is distributed and transmitted to the girders in two directions without using a grid beam.
【0008】また、方向の異なる床板を市松模様をなす
ように配設することにより、床荷重を二方向の大梁に均
等に伝達することができる。Further, by arranging the floor plates of different directions in a checkerboard pattern, the floor load can be evenly transmitted to the girders in two directions.
【0009】[0009]
【実施例】以下、この発明を図示する一実施例に基づい
て説明する。図1は、この発明に係る床架構を示す平面
図、図2(a) ないし図4は、図1における床架構の部分
断面図、図5は床架構の施工手順を示す概略断面図であ
る。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to an illustrated embodiment. FIG. 1 is a plan view showing a floor frame according to the present invention, FIGS. 2 (a) to 4 are partial sectional views of the floor frame in FIG. 1, and FIG. 5 is a schematic sectional view showing a construction procedure of the floor frame. .
【0010】図1ないし図4に示すように、この発明に
係る床架構は、主として柱1、キャピタル2、大梁3、
小梁4、床板5からなり、これらをプレキャスト部材に
より分割して構成する。なお、柱は現場打ちでもよい。As shown in FIGS. 1 to 4, the floor frame structure according to the present invention is mainly composed of a pillar 1, a capital 2, a girder 3,
It consists of beam 4 and floor board 5, and these are divided by a precast member. The pillars may be cast on site.
【0011】柱1は所定のスパンで配設されており、1
つの柱1Aを中心とする菱形の頂点に位置する4つの柱
1B1 〜1B4 のキャピタル2間に大梁3を掛け渡し、
中央の柱1Aのキャピタル2と大梁3の中間部との間に
小梁4を掛け渡す。これら大梁3および小梁4は斜め4
5°で配設されることになる。The pillars 1 are arranged with a predetermined span, and
Between 4 Pillars 1B 1 ~1B 4 Capital 2 located at the apex of the rhombus around the pillars 1A looped the girder 3,
A small beam 4 is bridged between the capital 2 of the central pillar 1A and the middle portion of the large beam 3. These large beams 3 and small beams 4 are diagonal 4
It will be arranged at 5 °.
【0012】キャピタル2は、図2に示すように、リン
グ状とし、柱1に設けた係止突起部1aに係止する。ま
た、その外周部には上部を切り欠くことにより支持段部
2aを形成する。一方の大梁3の両端部における上部に
は、下部を切り欠くことにより支持凸部3aを形成し、
この支持凸部3aを支持段部2aで支持する。この支持
段部2aおよび支持凸部3aには、コッター挿入孔を穿
設しておき、この孔にずれ止めコッター7を挿入してキ
ャピタル2と大梁3とを連結する。As shown in FIG. 2, the capital 2 has a ring shape and is locked to a locking projection 1a provided on the column 1. Further, a support step portion 2a is formed by notching the upper portion on the outer peripheral portion thereof. A supporting projection 3a is formed by notching the lower part on the upper part of both ends of one girder 3.
The support protrusion 3a is supported by the support step 2a. A cotter insertion hole is formed in each of the support step portion 2a and the support convex portion 3a, and a slip prevention cotter 7 is inserted into the hole to connect the capital 2 and the girder 3.
【0013】図3に示すように、大梁3の両側部にも、
上部を切り欠くことにより支持段部3bを形成し、この
支持段部3bに小梁4の一端部を支持させる。小梁4の
他端部は、キャピタル2の支持段部2aに支持させる。
この小梁4とキャピタル2・大梁3もずれ止めコッター
7を介して連結する。As shown in FIG. 3, on both sides of the girder 3,
A support step 3b is formed by notching the upper part, and one end of the beam 4 is supported by this support step 3b. The other end of the beam 4 is supported by the support step 2 a of the capital 2.
The small beam 4 and the capital 2 and the large beam 3 are also connected to each other via a slip prevention cotter 7.
【0014】床板5は、図1に示すように、長方形状と
し、大梁3と小梁4とで囲まれる小区画に2枚配設し、
大梁3と小梁4とで支持させる。また、隣合う小区画で
は長方形の床板5の方向を90°異ならせ、方向の異な
る床板5が市松模様をなすように配設する。As shown in FIG. 1, the floor board 5 has a rectangular shape, and two floor boards 5 are arranged in a small section surrounded by the large beam 3 and the small beam 4.
It is supported by the large beam 3 and the small beam 4. In the adjacent small sections, the directions of the rectangular floorboards 5 are different by 90 °, and the floorboards 5 having different directions are arranged in a checkered pattern.
【0015】以上のような構成において、次のように床
を施工する。With the above structure, the floor is constructed as follows.
【0016】(1) プレキャストの柱1を建て込み、また
は現場打ちにより柱1を構築する。(1) The precast pillar 1 is built or the pillar 1 is constructed by casting in situ.
【0017】(2) キャピタル2のブロックを柱1に設置
する。柱1とキャピタル2との隙間には楔部材6を挿入
して仮止めする。(2) The block of the capital 2 is installed on the pillar 1. A wedge member 6 is inserted into the gap between the pillar 1 and the capital 2 and temporarily fixed.
【0018】(3) 大梁3を架設する。大梁3とキャピタ
ル2をコッター7で接続する。(3) The girder 3 is installed. The girder 3 and the capital 2 are connected by a cotter 7.
【0019】(4) 小梁4を架設する。小梁4とキャピタ
ル2および大梁3とをコッター7で接続する。(4) The beam 4 is installed. The small beam 4, the capital 2 and the large beam 3 are connected by a cotter 7.
【0020】(5) 柱1とキャピタル2、キャピタル2と
大梁3および小梁4、大梁3と小梁4の各隙間、および
コッター挿入部にグラウト8を注入する。(5) The grout 8 is injected into the gap between the pillar 1 and the capital 2, the capital 2 and the large beam 3 and the small beam 4, the gap between the large beam 3 and the small beam 4, and the cotter insertion portion.
【0021】(6) 床板5を敷き込む。(6) The floor board 5 is laid.
【0022】(7) キャピタル2の上部に鉄筋9を配設
し、後打ちコンクリート10を打設する。大梁3と小梁
4上にも鉄筋9を配設し、後打ちコンクリート10を打
設する。(7) A reinforcing bar 9 is arranged on the upper portion of the capital 2, and a post-cast concrete 10 is poured. Reinforcing bars 9 are also arranged on the large beams 3 and the small beams 4, and post-cast concrete 10 is placed.
【0023】必要に応じて、床全面に後打ちコンクリー
ト11を打設し、合成床を形成することにより品質をさ
らに向上させる。If necessary, post-casting concrete 11 is placed on the entire surface of the floor to form a synthetic floor to further improve the quality.
【0024】[0024]
【発明の効果】前述の通り、この発明に係るプレキャス
ト部材の組み合わせによる床構造は、中心の柱を取り囲
む4つの柱のキャピタル間に大梁を掛け渡し、中心の柱
のキャピタルと4つの大梁の中間部との間に小梁を掛け
渡し、これら大梁と小梁で構成される小区画に床板を配
設して大梁と小梁で支持するようにしたため、格子梁を
使用しない比較的簡単な構成で、床荷重を二方向の大梁
に分散伝達することができ、床架構のプレキャスト化が
容易となる。As described above, in the floor structure using the combination of the precast members according to the present invention, the girder is bridged between the capitals of the four pillars surrounding the central pillar, and the center pillar capital and the four girder intermediate Since a small beam is hung between the large part and the small part, and a floorboard is placed in a small section composed of these large beams and small beams to be supported by the large beams and small beams, a comparatively simple structure without using grid beams Thus, the floor load can be distributed and transmitted to the large beams in two directions, which facilitates the precasting of the floor frame.
【0025】さらに、床板も比較的小さなものとするこ
とができ、工場プレキャストでも現場製作プレキャスト
でも選択することができる。In addition, the floorboard can also be relatively small and can be selected for factory precast or on-site precast.
【図1】この発明に係る床構造を示す平面図である。FIG. 1 is a plan view showing a floor structure according to the present invention.
【図2】(a) は図1の II-II線断面図、(b) は(a) の部
分平面図である。2A is a sectional view taken along line II-II of FIG. 1, and FIG. 2B is a partial plan view of FIG.
【図3】図1の III-III線断面図である。3 is a sectional view taken along line III-III in FIG.
【図4】図1の IV-IV線断面図である。FIG. 4 is a sectional view taken along line IV-IV in FIG.
【図5】この発明に係る床構造の施工手順を示す概略断
面図である。FIG. 5 is a schematic sectional view showing a construction procedure of the floor structure according to the present invention.
1…柱、1a…係止突起部、2…キャピタル、2a…支
持段部、3…大梁、3a…支持凸部、3b…支持段部、
4…小梁、5…床板、6…楔部材、7…コッター、8…
グラウト、9…鉄筋、10…後打ちコンクリート、11
…後打ちコンクリートDESCRIPTION OF SYMBOLS 1 ... Pillar 1a ... Locking projection part, 2 ... Capital, 2a ... Support step part, 3 ... Large beam, 3a ... Support convex part, 3b ... Support step part,
4 ... beam, 5 ... floor board, 6 ... wedge member, 7 ... cotter, 8 ...
Grout, 9 ... Reinforcing bar, 10 ... Post-cast concrete, 11
… Post-cast concrete
Claims (2)
ける柱・キャピタル・梁・床板をプレキャスト部材で構
成した床架構において、 中心となる一つの柱を取り囲む4つの柱のキャピタル間
に大梁を掛け渡し、前記中心の柱のキャピタルと4つの
大梁の中間部との間に小梁を掛け渡し、これら大梁と小
梁で構成される小区画に床板を配設して大梁と小梁で支
持したことを特徴とするプレキャスト部材の組み合わせ
による床架構。1. In a floor frame structure in which columns, capitals, beams, and floorboards are made of precast members in a building in which seismic resistant elements are arranged around the outer circumference, a large beam is provided between the capitals of the four columns surrounding one central column. Crossing over, a small beam is bridged between the capital of the center pillar and the middle part of the four girders, and a floorboard is placed in a small section composed of these girders and girders to be supported by the girders and girders. A floor frame composed of a combination of precast members.
区画で床板の方向を90°異ならせ、方向の異なった床
板が市松模様をなすように配設したことを特徴とするプ
レキャスト部材の組み合わせによる床架構。2. The floor frame structure according to claim 1, wherein the directions of the floorboards differ by 90 ° between adjacent small sections, and the floorboards having different directions are arranged in a checkered pattern. Floor frame by combination.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP12884493A JP2674470B2 (en) | 1993-05-31 | 1993-05-31 | Floor frame structure by combining precast members |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP12884493A JP2674470B2 (en) | 1993-05-31 | 1993-05-31 | Floor frame structure by combining precast members |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06336782A true JPH06336782A (en) | 1994-12-06 |
JP2674470B2 JP2674470B2 (en) | 1997-11-12 |
Family
ID=14994787
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP12884493A Expired - Lifetime JP2674470B2 (en) | 1993-05-31 | 1993-05-31 | Floor frame structure by combining precast members |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2674470B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0369333A2 (en) * | 1988-11-14 | 1990-05-23 | BEHRINGWERKE Aktiengesellschaft | Universal test for the main components of the fibrinolytic system |
KR20030075131A (en) * | 2002-07-09 | 2003-09-22 | (주)씨.에스 구조 엔지니어링 | beam-column connection detail of long-span pre-cast system |
KR20040003452A (en) * | 2002-07-03 | 2004-01-13 | 김상식 | Prestressed long span precast concrete frame structural system |
-
1993
- 1993-05-31 JP JP12884493A patent/JP2674470B2/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0369333A2 (en) * | 1988-11-14 | 1990-05-23 | BEHRINGWERKE Aktiengesellschaft | Universal test for the main components of the fibrinolytic system |
EP0369333B1 (en) * | 1988-11-14 | 1995-03-08 | BEHRINGWERKE Aktiengesellschaft | Universal test for the main components of the fibrinolytic system |
KR20040003452A (en) * | 2002-07-03 | 2004-01-13 | 김상식 | Prestressed long span precast concrete frame structural system |
KR20030075131A (en) * | 2002-07-09 | 2003-09-22 | (주)씨.에스 구조 엔지니어링 | beam-column connection detail of long-span pre-cast system |
Also Published As
Publication number | Publication date |
---|---|
JP2674470B2 (en) | 1997-11-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2674470B2 (en) | Floor frame structure by combining precast members | |
JP2836441B2 (en) | Flat slab construction without shoring | |
JP3701078B2 (en) | Road slab construction method | |
JP7012486B2 (en) | Bridge construction method | |
JPH046450Y2 (en) | ||
JPH0657710A (en) | Construction of concrete main tower | |
JP2734929B2 (en) | How to build a slab | |
JP2987469B2 (en) | Staircase structure | |
JPH1122106A (en) | Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member | |
JP2998572B2 (en) | Building structural frame | |
JP2853528B2 (en) | Construction method of composite floorboard | |
JP2001032376A (en) | Floor slab frame and construction method for skeleton | |
JP3189081B2 (en) | Manufacturing method of void type full precast two-way slab and void type full precast slab | |
JPH086383B2 (en) | Floor construction method | |
JP2904648B2 (en) | Construction method of earthquake-resistant wall using PC version | |
JPH01223248A (en) | Folded plate unit slab construction | |
JP2023022563A (en) | Concrete wall construction method | |
JPH0649936A (en) | Joist slab construction by use of semi-pc curved face plate | |
AU704885B2 (en) | Flooring system | |
KR100601097B1 (en) | plate girder | |
JP3366980B2 (en) | Composite slab and method of constructing the same | |
JPS62189239A (en) | Construction method of floor slab | |
JPH03172437A (en) | Executing method for grill-form joist pc slab | |
JPH0559777A (en) | Construction of composite slab having longer span | |
JPH0688393A (en) | Flat plate construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19970617 |