JPH06264437A - Construction of continuous wall in underground - Google Patents

Construction of continuous wall in underground

Info

Publication number
JPH06264437A
JPH06264437A JP4930493A JP4930493A JPH06264437A JP H06264437 A JPH06264437 A JP H06264437A JP 4930493 A JP4930493 A JP 4930493A JP 4930493 A JP4930493 A JP 4930493A JP H06264437 A JPH06264437 A JP H06264437A
Authority
JP
Japan
Prior art keywords
ground
water level
wall
continuous wall
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4930493A
Other languages
Japanese (ja)
Inventor
Masao Arai
政男 荒井
Teiji Naito
禎二 内藤
Motoshige Ariyama
元茂 有山
Sunao Obara
直 小原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP4930493A priority Critical patent/JPH06264437A/en
Publication of JPH06264437A publication Critical patent/JPH06264437A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To simplify the construction work and reduce the cost, by erecting guide walls on the ground and arranging them on constructing a continuous wall in the underground with a shallow water level and keeping the level difference between the underground water level and a stabilizing liquid with a specified value. CONSTITUTION:The underground water level is measured in advance and a guide wall 13 provided with an upper retaining wall 14a to get a necessary water level difference 5 is installed in the ground 11 and a ditch 12 is excavated. A stabilizing liquid preventing collapse of the side walls on cutting this ditch, is injected so that the water difference (t) shows a specified figure (about 2m or more). After cutting the ditch, a steel rod cage is erected inside and concrete is placed to constrtuct a continuous wall. In this way, the construction work can be simplified without subsidence of the ground.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、特に地下水位の高い地
盤に建築構造物を構築する際に適用して好適な地中連続
壁構築法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground continuous wall suitable for application particularly when constructing a building structure on a ground having a high groundwater level.

【0002】[0002]

【従来の技術】地下水位の高い地盤に建築構造物を構築
するに際し、基礎構造として地中連続壁を用いる場合に
おいては、例えば図2に示すように、地盤1に断面L型
等のガイドウォール2を配設した後、このガイドウォー
ル2の配設区画に溝3を掘削しつつポリマーあるいはベ
ントナイト微粉末溶液等の安定液を満たす。このとき、
ガイドウォール2内の安定液の水位と地下水位との水位
差tが約2m以上あれば、溝3の側壁面3aに対する安
定液の押圧力によって側壁面3aの崩落を防止できるこ
とから、安定した地中連続壁を構築できるとされてい
る。
2. Description of the Related Art In constructing a building structure on a ground with a high groundwater level, when a continuous underground wall is used as a foundation structure, for example, as shown in FIG. After arranging No. 2, a stabilizing liquid such as a polymer or bentonite fine powder solution is filled while excavating the groove 3 in the section where the guide wall 2 is arranged. At this time,
If the water level difference t between the stabilizing liquid level in the guide wall 2 and the groundwater level is about 2 m or more, it is possible to prevent the side wall face 3a from collapsing due to the pressing force of the stabilizing liquid against the side wall face 3a of the groove 3, so that the stable ground surface is prevented. It is said that a medium continuous wall can be constructed.

【0003】そこで、この水位差tを満足できない場
合、従来は図3あるいは図4に示すような方法によって
対処していた。図3は、一般にディープウェル工法と呼
ばれるものであって、地下水位を強制的に低下させるも
のである。すなわち、ガイドウォール2の近傍の地盤1
に地下水面の下方まで掘削して掘削穴4を設け、この掘
削穴4内にポンプ5を配設し、このポンプ5に連結され
たディープウェル6から地下水を排水することによって
元の地下水位Aを低下させ、必要な水位差tを得るよう
にする。一方、図4は、地盤1に良質土,改良土等を用
いて盛り土7を施し、建築構造物の施工基盤を元の地盤
1よりも高くすることによって、必要な水位差tを得る
ようにしたものである。
Therefore, when the water level difference t cannot be satisfied, conventionally, a method as shown in FIG. 3 or 4 is used. FIG. 3 is a method generally called the deep well method, in which the groundwater level is forcibly lowered. That is, the ground 1 near the guide wall 2
An excavation hole 4 is formed by excavating to the bottom of the water table, a pump 5 is arranged in the excavation hole 4, and the groundwater is drained from a deep well 6 connected to the pump 5 to obtain the original groundwater level A. In order to obtain the required water level difference t. On the other hand, FIG. 4 shows that the ground 1 is filled with embankment 7 using good quality soil, improved soil, etc., and the construction base of the building structure is made higher than the original ground 1 to obtain the necessary water level difference t. It was done.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、ガイド
ウォール2の水位と地下水位との水位差tを得るための
上記従来の方法には、以下のような不都合が伴う。すな
わち、図3に示したディープウェル工法においては、排
水される地下水が莫大な水量であるため作業コストを助
長するとともに、この地下水の排水によって環境破壊を
引き起こす可能性がある。また、図4に示した盛り土に
よる方法は、施工規模が非常に大掛かりになる上、盛り
土用の土砂としてある程度良質のものを使用する必要が
あり、これによって作業コストを助長するとともに、大
量に盛り土を行うと地盤1の沈下を引き起こす可能性も
ある。
However, the above-described conventional method for obtaining the water level difference t between the water level of the guide wall 2 and the groundwater level has the following disadvantages. That is, in the deep well method shown in FIG. 3, the groundwater drained has a huge amount of water, which increases working costs and may cause environmental damage by draining this groundwater. In addition, the embankment method shown in Fig. 4 requires a very large scale construction and requires the use of a certain amount of good quality earth and sand for the embankment, which contributes to the working cost and a large amount of embankment. There is also a possibility of causing the subsidence of the ground 1.

【0005】本発明は、上記の問題を解決し得るもので
あって、その目的は、周囲の環境に対して悪影響を及ぼ
さず、地中連続壁を簡素にかつ経済的に構築することが
できる地中連続壁構築法を提供することにある。
The present invention is capable of solving the above-mentioned problems, and the purpose thereof is to exert no adverse effect on the surrounding environment and to construct a continuous underground wall simply and economically. It is to provide an underground continuous wall construction method.

【0006】[0006]

【課題を解決するための手段】本発明の地中連続壁構築
法は、地盤内に地中連続壁を構築するに際して、前記地
中連続壁のガイドウォールを前記地盤上に立ち上げて配
設し、溝の内部に前記地盤上面よりも高く安定液を満た
して地下水との水位差を確保することを特徴とする。
According to the method of constructing an underground continuous wall of the present invention, when the underground continuous wall is constructed in the ground, the guide wall of the underground continuous wall is erected on the ground. However, the inside of the groove is filled with a stabilizing liquid higher than the upper surface of the ground to secure a water level difference from the groundwater.

【0007】[0007]

【作用】本発明の地中連続壁構築法によれば、地中連続
壁のガイドウォールを地盤上に立ち上げて配設するの
で、このガイドウォールの配設区画にしたがって掘削し
た溝に安定液を満たしたとき、この安定液の水位が前記
地盤上面よりも高くなって地下水との十分な水位差が確
保され、溝の側壁面の崩落を防止するとともに構築作業
の簡素化並びに低コスト化を図ることが可能となる。ま
た、構築作業に伴う環境破壊や地盤沈下を引き起こすこ
とがない。
According to the method of constructing an underground continuous wall of the present invention, since the guide wall of the underground continuous wall is erected on the ground, the stabilizing liquid is provided in the groove excavated according to the section where the guide wall is arranged. When this condition is satisfied, the water level of this stabilizing liquid becomes higher than the top surface of the ground, and a sufficient water level difference with groundwater is secured, preventing the side wall surface of the groove from collapsing and simplifying construction work and reducing costs. It is possible to plan. In addition, environmental damage and ground subsidence due to construction work will not occur.

【0008】[0008]

【実施例】以下、本発明の実施例を図面を参照して詳細
に説明する。図1は本発明に係る地中連続壁構築法の実
施例を示す図であって、この図において符号11は地盤
である。この地盤11は、地下水が高水位の区域であっ
て、この地盤11には、地中連続壁構築用の溝12を掘
削したとき、前記地盤11の圧力に対抗して土砂の崩壊
を防ぐガイドウォール13が配設されている。
Embodiments of the present invention will now be described in detail with reference to the drawings. FIG. 1 is a diagram showing an embodiment of the method for constructing an underground continuous wall according to the present invention, in which reference numeral 11 is the ground. This ground 11 is an area where groundwater has a high water level, and a guide for preventing collapse of earth and sand against the pressure of the ground 11 when a groove 12 for constructing an underground continuous wall is excavated in the ground 11. A wall 13 is provided.

【0009】このガイドウォール13は、前記地盤11
に対して垂直に配設される擁壁部14と、この擁壁部1
4に垂設されかつ地盤11表面に配設される水平板部1
5とからなるものであり、このガイドウォール13は、
溝12の側壁面12aに沿ってそれぞれ平行に、かつ水
平板部15が溝12の側壁12aに対して互いに相対す
る方向に延出するように対となって配設され、更に詳し
くは、前記水平板部15と擁壁部14の下部14bが地
盤11に埋設され、擁壁部14の上部14aが地盤11
上に立ち上げて配設されている。そして、これらガイド
ウォール13の配設によって区画された領域に溝12が
掘削され、安定液が満たされている。
The guide wall 13 is the ground 11
Retaining wall portion 14 arranged perpendicularly to the retaining wall portion 1 and this retaining wall portion 1
A horizontal plate portion 1 vertically installed on the ground 4 and arranged on the surface of the ground 11
5 and the guide wall 13 is
The horizontal plate portions 15 are arranged in pairs along the side wall surfaces 12a of the grooves 12 so as to extend in directions opposite to each other with respect to the side walls 12a of the groove 12, and more specifically, The horizontal plate portion 15 and the lower portion 14b of the retaining wall portion 14 are embedded in the ground 11, and the upper portion 14a of the retaining wall portion 14 is the ground 11.
It stands up and is arranged. Then, the groove 12 is excavated in the area defined by the arrangement of the guide walls 13 and filled with the stabilizing solution.

【0010】上記のような地中連続壁を構築するには、
先ず地盤11内下方の地下水の水位を測定し、後述する
水位差を十分に確保できるガイドウォール13を設計す
る。そして、地盤11の地中連続壁構築区画に、擁壁部
14の下部14bを地盤11内にかつ水平板部15を地
盤11表面に埋設し、溝12の掘削幅だけ互いに平行に
離した上で、前記水平板部15が、この溝12から外方
へ互いに相対する方向に延出するようにガイドウォール
13を対に配設する。
In order to construct an underground continuous wall as described above,
First, the water level of the ground water below the ground 11 is measured, and the guide wall 13 that can sufficiently secure the water level difference described later is designed. Then, in the underground continuous wall construction section of the ground 11, the lower portion 14b of the retaining wall portion 14 is embedded in the ground 11 and the horizontal plate portion 15 is embedded on the surface of the ground 11, and the excavation width of the groove 12 is separated from each other in parallel. Then, the guide walls 13 are arranged in pairs so that the horizontal plate portions 15 extend outward from the groove 12 in the directions opposite to each other.

【0011】そして、このガイドウォール13による掘
削幅に沿って、地盤11をクラムシェル等の掘削機によ
って掘削して溝12を形成する。この場合の掘削機は、
地盤11の性状に応じて適当な機械器具を選定するよう
にする。前記掘削中から溝12の内部には安定液を満た
す。このとき、擁壁部14の上部14aは、地盤11上
に立ち上がっており、ガイドウォール13内の安定液の
水位は地盤11上面よりも高くなる。この安定液の水位
と地盤11内下方の地下水の水位との水位差tが約2m
以上であれば、上述したように安定した地中連続壁を構
築することができるので、設計段階において予め地下水
の水位を測定しておき、これに対して十分な水位差tを
確保するのに適当な擁壁部14の上部14aの高さを決
定する。その後、溝12の内部に鉄筋籠を建て込み、コ
ンクリートを打設する等の作業を行って地中連続壁を構
築する。
Then, along the excavation width by the guide wall 13, the ground 11 is excavated by an excavator such as a clam shell to form a groove 12. The excavator in this case is
Appropriate machinery and equipment should be selected according to the properties of the ground 11. The inside of the groove 12 is filled with the stabilizing liquid during the excavation. At this time, the upper portion 14a of the retaining wall portion 14 stands up on the ground 11, and the water level of the stabilizing liquid in the guide wall 13 becomes higher than the upper surface of the ground 11. The water level difference t between the water level of the stabilizing solution and the ground water level below the ground 11 is about 2 m.
If it is more than the above, a stable underground continuous wall can be constructed as described above. Therefore, it is necessary to measure the groundwater level in advance at the designing stage and secure a sufficient water level difference t against this. A suitable height of the upper portion 14a of the retaining wall portion 14 is determined. After that, a reinforcing rod cage is built inside the groove 12, and work such as placing concrete is performed to construct an underground continuous wall.

【0012】これによって、仮に地下水位との十分な水
位差tが満足できない場合でも、適切なガイドウォール
13を設計して配設するだけで溝12の側壁面12aの
崩落を防ぐことができ、構築作業を効率的に行うことが
できる。また、ディープウェル工法や盛り土等を行う必
要がないので、作業コストを削減できるとともに、周囲
の環境破壊や地盤11の沈下を引き起こすことがない。
As a result, even if the sufficient water level difference t from the groundwater level cannot be satisfied, the side wall surface 12a of the groove 12 can be prevented from collapsing simply by designing and disposing an appropriate guide wall 13. Construction work can be performed efficiently. Further, since it is not necessary to perform the deep well construction method or embankment, the working cost can be reduced and the surrounding environment is not destroyed or the ground 11 is not submerged.

【0013】なお、ガイドウォール13は、地盤11の
土圧に対抗して地盤11の土の崩壊を防ぐに必要な強度
を有するものであれば、鉄筋コンクリート構造やスチー
ル構造等いかなる材料で成形してもよい。
The guide wall 13 may be formed of any material such as a reinforced concrete structure or a steel structure as long as it has a strength required to resist the soil pressure of the ground 11 and prevent the soil of the ground 11 from collapsing. Good.

【0014】[0014]

【発明の効果】以上の説明から明らかなように、本発明
の地中連続壁構築法によれば、地中連続壁のガイドウォ
ールを地盤上に立ち上げて配設したことで、このガイド
ウォールの配設区画にしたがって掘削した溝に安定液を
満たしたとき、この安定液の水位が前記地盤上面よりも
高くなり、地下水との十分な水位差が確保されるので、
溝の側壁面の崩落を防止し、安定した地中連続壁を構築
することができる。さらにこの際、水位差確保のための
特殊な手段を必要としないので、構築作業の簡素化並び
に低コスト化を実現できるとともに、周囲の環境破壊や
地盤沈下といった悪影響を及ぼさないといった効果を奏
する。
As is apparent from the above description, according to the method of constructing an underground continuous wall of the present invention, the guide wall of the underground continuous wall is erected on the ground, and this guide wall is provided. When the ditch excavated according to the arrangement section of is filled with the stabilizing liquid, the water level of this stabilizing liquid becomes higher than the upper surface of the ground, and a sufficient water level difference with the groundwater is secured,
The collapse of the side wall surface of the groove can be prevented, and a stable underground continuous wall can be constructed. Further, at this time, since no special means for securing the water level difference is required, the construction work can be simplified and the cost can be reduced, and the adverse effects such as environmental damage to the surrounding environment and ground subsidence are not exerted.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例として示した地中連続壁の断
面図である。
FIG. 1 is a sectional view of an underground continuous wall shown as an embodiment of the present invention.

【図2】ガイドウォール内の水位と地下水位との水位差
を示す図である。
FIG. 2 is a diagram showing a water level difference between a water level in a guide wall and a groundwater level.

【図3】従来技術の一例として示したディープウェル工
法を示す断面構成図である。
FIG. 3 is a cross-sectional configuration diagram showing a deep well method shown as an example of a conventional technique.

【図4】従来技術の一例として示した盛り土を示す断面
構成図である。
FIG. 4 is a cross-sectional configuration diagram showing an embankment shown as an example of a conventional technique.

【符号の説明】[Explanation of symbols]

11 地盤 12 溝 12a 側壁面 13 ガイドウォール 14 擁壁部 14a 上部 14b 下部 15 水平板部 11 Ground 12 Groove 12a Side Wall 13 Guide Wall 14 Retaining Wall 14a Upper 14b Lower 15 Horizontal Plate

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小原 直 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Nao Ohara 1-25-1 Nishi-Shinjuku, Shinjuku-ku, Tokyo Taisei Corporation

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地盤内に地中連続壁を構築するに際し
て、前記地中連続壁のガイドウォールを前記地盤上に立
ち上げて配設し、溝の内部に、前記地盤上面よりも高く
安定液を満たして地下水との水位差を確保することを特
徴とする地中連続壁構築法。
1. When constructing an underground continuous wall in the ground, a guide wall of the underground continuous wall is erected upright on the ground, and a stabilizing liquid higher than the upper surface of the ground is provided inside the groove. The underground continuous wall construction method is characterized by satisfying the following conditions and ensuring a water level difference from groundwater.
JP4930493A 1993-03-10 1993-03-10 Construction of continuous wall in underground Pending JPH06264437A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4930493A JPH06264437A (en) 1993-03-10 1993-03-10 Construction of continuous wall in underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4930493A JPH06264437A (en) 1993-03-10 1993-03-10 Construction of continuous wall in underground

Publications (1)

Publication Number Publication Date
JPH06264437A true JPH06264437A (en) 1994-09-20

Family

ID=12827206

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4930493A Pending JPH06264437A (en) 1993-03-10 1993-03-10 Construction of continuous wall in underground

Country Status (1)

Country Link
JP (1) JPH06264437A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561316A (en) * 2012-01-20 2012-07-11 中国建筑第八工程局有限公司 Construction method for diaphragm walls
CN105649008A (en) * 2015-12-31 2016-06-08 华北冶建工程建设有限公司 Internal bracing device for and construction method of underground diaphragm walls
CN111794259A (en) * 2020-08-10 2020-10-20 中铁二十局集团第一工程有限公司 Method for preventing underground diaphragm wall from collapsing groove of neighboring existing building of high underground water level area

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561316A (en) * 2012-01-20 2012-07-11 中国建筑第八工程局有限公司 Construction method for diaphragm walls
CN105649008A (en) * 2015-12-31 2016-06-08 华北冶建工程建设有限公司 Internal bracing device for and construction method of underground diaphragm walls
CN111794259A (en) * 2020-08-10 2020-10-20 中铁二十局集团第一工程有限公司 Method for preventing underground diaphragm wall from collapsing groove of neighboring existing building of high underground water level area

Similar Documents

Publication Publication Date Title
JPH06264437A (en) Construction of continuous wall in underground
CN217419736U (en) Compensation type construction structure for underground engineering construction
CN216194845U (en) Pebble covering layer steel sheet pile cofferdam system
KR100376590B1 (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
JP2005133402A (en) Construction method of foundation or retaining wall
KR200183206Y1 (en) Block for breastwall
JP3957607B2 (en) Pneumatic caisson and pneumatic caisson method
JPH03281826A (en) Excavation method in cohesive soil ground
JPH01226921A (en) Earthquake-proof reinforced revetment construction
JPH0536044Y2 (en)
JP7398609B2 (en) Concrete frame construction method and underground structure
JP3360061B2 (en) Preceding plate-shaped beam of mountain retaining frame
CN111852114B (en) Rapid construction and anti-floating method for steel structure underground garage
JP2711748B2 (en) Construction method of large-scale underground space
JPH035528A (en) Base structure of structure
JP3176530B2 (en) Liquefaction countermeasures
JPH03281818A (en) Soil improvement method for cohesive soil ground
JP2000130066A (en) Construction method for vertical shaft
JPH0343518A (en) Continuous underground wall having enlarged bottom
JP2003074076A (en) Construction method of building having underground part
JPS5949974B2 (en) Construction methods for foundations such as abutments and piers
JPS60223530A (en) Enclosed foundation
CN115233754A (en) Pile foundation construction method adjacent to historical building
JPS62211418A (en) Construction of continuous wall
JPH10140557A (en) Construction method of cast-in-place diaphragm wall with hollow