JPH06187014A - Work scheduling method and device by process classifications - Google Patents

Work scheduling method and device by process classifications

Info

Publication number
JPH06187014A
JPH06187014A JP33729892A JP33729892A JPH06187014A JP H06187014 A JPH06187014 A JP H06187014A JP 33729892 A JP33729892 A JP 33729892A JP 33729892 A JP33729892 A JP 33729892A JP H06187014 A JPH06187014 A JP H06187014A
Authority
JP
Japan
Prior art keywords
work
date
waiting
start date
days
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP33729892A
Other languages
Japanese (ja)
Inventor
Ryuichi Hara
隆一 原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP33729892A priority Critical patent/JPH06187014A/en
Publication of JPH06187014A publication Critical patent/JPH06187014A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Abstract

PURPOSE:To improve producing efficiency by preventing the increase of the number of works in each process, thereby shortening a period required for production in the scheduling of a work start (input of products to the process) instruction in the plural processes. CONSTITUTION:A work start date and end date in a first process and the work start date in the second process are searched (step X1-X4), and the number of waiting days until the work start date in a second process obtained by subtracting the work end date in the first process from the work start date in the second process is compared with the preliminarily set number of permitted waiting days (step X5 and X6). When the number of waiting days is beyond the number of permitted waiting days, the work start date in the first process is delayed only by the difference (step X7). When the number of waiting days is less than the number of permitted waiting days, the work end date in the second process is calculated (step X8). Afterwards, the same operation is repeated in the following process.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、複数の工程での作業
開始(工程への製品の投入)指示をスケジューリングす
る工程別作業スケジューリング装置及び方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a step-by-step work scheduling apparatus and method for scheduling work start (product introduction to a step) instructions in a plurality of steps.

【0002】[0002]

【従来の技術】従来、この種の工程別作業スケジューリ
ング装置においては、既に処理されている注文書に基づ
く生産予定に従って稼働中の各工程に、新規注文書の製
品の生産作業開始を指示する場合、新規注文書の製品の
種類及び個数を示す注文情報を第一工程から順次連続し
て各工程の生産能力に引き当てて、各工程で生産能力に
余裕のある日を捜してその日をその工程での作業開始日
(作業開始時刻)としていた。
2. Description of the Related Art Conventionally, in this type of process-based work scheduling apparatus, when instructing each process in operation according to a production schedule based on an already processed order form to start production work of a product of a new order form , Order information indicating the type and quantity of products in the new order form is continuously allocated from the first process to the production capacity of each process, and the day when there is a margin in the production capacity at each process is searched for on that day. Was set as the work start date (work start time).

【0003】図3に、従来の工程別作業スケジューリン
グ装置の概念図を示す。同図に示すように、各工程での
作業開始日は、製品の種類及び個数を示す注文情報入力
1と、各工程の生産能力(個/日または個/時間)を示
す生産能力入力2と、各工程の製品別工期(加工時間)
を示す工期入力3とに基づく演算処理4により順次算出
されて、表示5が行われるように構成されていた。
FIG. 3 shows a conceptual diagram of a conventional process-based work scheduling apparatus. As shown in the figure, the work start date of each process includes an order information input 1 indicating the type and number of products, and a production capacity input 2 indicating the production capacity (pieces / day or pieces / hour) of each step. , Work period for each process (processing time)
The display 5 is configured to be sequentially calculated by the calculation process 4 based on the construction period input 3 indicating.

【0004】次に、上述した演算処理4を図4のフロー
チャートに基づいて説明する。まず、新規注文書の注文
情報の入力時に、第一工程の作業開始引き当て開始日を
本日Aに設定する(ステップY1)。
Next, the arithmetic processing 4 described above will be described with reference to the flowchart of FIG. First, when the order information of the new order form is input, the work start allocation start date of the first process is set to today's A (step Y1).

【0005】続いて、本日Aより第一工程の生産能力枠
(一日当たりの処理能力)に注文情報を引き当ててい
き、第一工程の生産能力に余裕のある日を作業開始日B
として捜す(ステップY2)。
Next, from today A, order information is allocated to the production capacity frame (processing capacity per day) of the first process, and the day when the production capacity of the first process has a margin is the work start date B.
(Step Y2).

【0006】そして、求めた第一工程での作業開始日B
に第一工程の工期を加算して第一工程の作業完了日Cを
算出する(ステップY3)。
[0006] Then, the work start date B in the obtained first process
The work completion date C of the first process is calculated by adding the construction period of the first process to (step Y3).

【0007】次に、第一工程の作業完了日Cより順次注
文情報を第二工程の生産能力枠に引き当てていき、第二
工程の生産能力に余裕のある日を第二工程での作業開始
日Dとして捜す(ステップY4)。
Next, from the work completion date C of the first process, the order information is sequentially assigned to the production capacity frame of the second process, and the day when the production capacity of the second process has a margin starts the work of the second process. Search for day D (step Y4).

【0008】そして、算出した第二工程での作業開始日
Dに第二工程の工期を加算して第二工程での作業完了日
Fを算出する(ステップY5)。
Then, the work start date D in the second process is added to the calculated work start date D in the second process to calculate the work completion date F in the second process (step Y5).

【0009】続いて、第二工程での作業完了日Fより注
文書を第三工程の生産能力枠に引き当てていき、第三工
程の生産能力に余裕のある日を第三工程での作業開始日
Gとし(ステップY6)、その第三工程での作業開始日
Gに第三工程の工期を加算して第三工程の作業完了日I
を算出する(ステップY7)。
Next, from the work completion date F in the second process, the order sheet is allocated to the production capacity frame of the third process, and the work in the third process is started on the day when the production capacity of the third process has a margin. The date is G (step Y6), and the work start date G in the third process is added to the construction period of the third process to finish the work in the third process I.
Is calculated (step Y7).

【0010】このようにして順次連続して各工程毎に演
算処理し、最終の第N工程での作業完了日Yを算出する
(ステップY(M−1))。そして、第N工程での作業完了
日Yを基に、注文情報に対する回答納期(製品を収める
ことができる予定日)Zを算出して(ステップY
(M))、表示する。
In this manner, the arithmetic processing is successively performed for each process to calculate the work completion date Y in the final N-th process (step Y (M-1)). Then, based on the work completion date Y in the N-th process, a response delivery date (scheduled date when the product can be stored) Z is calculated (step Y).
(M)), display.

【0011】[0011]

【発明が解決しようとする課題】ところで、他の工程よ
りも生産能力が小さい工程では作業開始(加工)待ちす
る製品が多数発生して、生産が円滑に進まない。このこ
とは、その工程よりも前の工程での作業開始指示が早い
ために起こり、製品が出来上がる日からみれば結果的に
第一工程で必要以上に早く作業開始を指示していること
がある。そのため、工程内で仕掛り数量が増加すると、
生産に要する期間が長くなるので、生産効率が悪く、ま
た製品生産のために必要な素材や材料などを維持するた
めの金利負担が増加するという問題点があった。
By the way, in a process having a smaller production capacity than other processes, a large number of products wait for the start (working) of work, and the production does not proceed smoothly. This happens because the work start instruction in the process before that process is early, and as a result from the day when the product is completed, as a result, the work start may be instructed earlier than necessary in the first process. . Therefore, if the quantity in process increases in the process,
Since the period required for production is long, the production efficiency is poor, and the interest burden for maintaining the materials necessary for product production increases.

【0012】この発明は、このような問題点を解決する
ためになされたもので、各工程内の仕掛り数量の増加を
防ぐことにより生産期間を短くして生産効率を向上させ
ることができる工程作業スケジューリング方法を提供す
ることを目的とする。
The present invention has been made in order to solve such a problem, and it is a process capable of shortening the production period and improving the production efficiency by preventing the increase of the quantity in process in each process. The purpose is to provide a work scheduling method.

【0013】また、この発明は、注文情報が替わって
も、各工程内に仕掛り数量を増加させない各工程での作
業開始日を簡単に求めることができる工程別作業スケジ
ューリング装置を得ることを目的とする。
Another object of the present invention is to provide a process-based work scheduling device which can easily obtain a work start date in each process without increasing the quantity in process even if the order information is changed. And

【0014】[0014]

【課題を解決するための手段】この発明の請求項1に係
る工程別作業スケジューリング方法は、製品の種類及び
個数を示す注文情報と稼働中の各工程の製品別工期及び
生産能力の余裕を示す入力情報に基づいて順次連続する
各工程毎に作業開始日及び作業完了日を求める際、次工
程での作業開始日を求めた後、この次工程での作業開始
日から前工程での作業完了日を減算して次工程での作業
開始日までの待ち日数を得て、この待ち日数とあらかじ
め設定した許容待ち日数とを比較し、上記待ち日数が上
記許容待ち日数を越える場合に前工程での作業開始日を
上記待ち日数と上記許容待ち日数との差分遅らせて前工
程での作業完了日と次工程での作業開始日を算出し直し
その後次工程での作業完了日を算出すると共に、上記待
ち日数が上記許容待ち日数以下である場合には次工程で
の作業完了日を算出するものである。
A process-specific work scheduling method according to claim 1 of the present invention shows order information indicating the type and quantity of products, and the product-specific work period and production capacity margin of each process in operation. When obtaining the work start date and work completion date for each consecutive process based on the input information, after obtaining the work start date in the next process, the work completion date in the previous process from the work start date in this next process Subtract the days to obtain the number of waiting days until the work start date in the next process, compare this number of waiting days with the preset allowable number of waiting days, and if the number of waiting days exceeds the number of allowable waiting days in the previous process, The work start date of is delayed by the difference between the number of waiting days and the number of allowable waiting days, and the work completion date in the previous process and the work start date in the next process are recalculated, and then the work completion date in the next process is calculated. The number of waiting days is the above If it is less Chi days is to calculate the work completion date for the next step.

【0015】また、この発明の請求項2に係る工程別作
業スケジューリング装置は、製品の種類及び個数を示す
注文情報を格納した記憶部と、稼働中の各工程の生産能
力及び製品別工期の余裕を示す入力情報と作業開始の許
容待ち日数を入力する入力部と、上記記憶部から読み出
した上記注文情報と上記入力部によって入力された上記
入力情報及び上記作業開始の許容待ち日数とに基づいて
各工程の作業開始日及び作業完了日を順次求める処理部
とを備えると共に、上記処理部を、上記注文情報、上記
入力情報及び遅延日数指示情報に基づいて順次連続する
工程毎に製品の作業開始日及び作業完了日を求める作業
開始日及び作業完了日算出部と、この作業開始日及び作
業完了日算出部により次工程での作業開始日が得られた
後、次工程での作業開始日から前工程での作業完了日を
減算して待ち日数を算出する待ち日数算出部と、この待
ち日数算出部で算出した上記待ち日数と上記入力部に入
力された上記許容待ち日数とを比較してその比較差に応
じた遅延日数指示情報を上記作業開始日及び完了日算出
部に出力する待ち日数比較部とで構成したものである。
According to a second aspect of the present invention, there is provided a storage unit for storing order information indicating the type and number of products, a production capacity of each operating process, and a product-specific work schedule. Based on the input information indicating the input information and the allowable waiting days to start the work, the order information read from the storage unit, the input information input by the input unit, and the allowable waiting days to start the work. A processing unit that sequentially obtains the work start date and work completion date of each process is provided, and the work unit starts the product work for each successive process based on the order information, the input information, and the delay days instruction information. Date and work completion date calculation part, and after the work start date and work completion date calculation part obtain the work start date in the next process, The waiting day number calculation unit that calculates the number of waiting days by subtracting the work completion date in the previous process from the start date, the number of waiting days calculated by this waiting day number calculation unit, and the allowable number of waiting days input in the input unit The number of waiting days comparison unit for comparing and outputting the delay days instruction information according to the comparison difference to the work start date and completion date calculation unit.

【0016】[0016]

【作用】この発明の請求項1に係る工程別作業スケジュ
ーリング方法においては、製品の種類及び個数を示す注
文情報と稼働中の各工程での製品別工期及び生産能力を
示す入力情報に基づいて順次連続する各工程毎に作業開
始日及び作業完了日を求める際、次工程での作業開始日
を求めた後、この次工程での作業開始日から前工程での
作業完了日を減算して次工程での作業開始日までの待ち
日数を得て、この待ち日数とあらかじめ設定した許容待
ち日数とを比較し、上記待ち日数が上記許容待ち日数を
越える場合に前工程での作業開始日を上記待ち日数と上
記許容待ち日数との差分遅らせて前工程での作業完了日
と次工程での作業開始日を算出し直しその後次工程での
作業完了日を算出すると共に、上記待ち日数が上記許容
待ち日数以下である場合には次工程での作業完了日を算
出することによって、各工程での作業開始待ち日数が許
容待ち日数を越えないように決定され、各工程での仕掛
り数量が少なくなる。
In the work scheduling method according to the first aspect of the present invention, the order information indicating the type and quantity of the product and the input information indicating the work period and the production capacity for each product in each operating process are sequentially input. When calculating the work start date and work completion date for each successive process, after calculating the work start date in the next process, subtract the work completion date in the previous process from the work start date in this next process Obtain the number of waiting days until the work start date in the process, compare this waiting day number with the preset allowable waiting day number, and if the waiting day number exceeds the allowable waiting day number, set the work starting date in the previous process as above. The difference between the number of waiting days and the allowable number of waiting days is delayed to recalculate the work completion date in the previous process and the work start date in the next process, and then the work completion date in the next process is calculated. Less than or equal to the number of waiting days By calculating the work completion date for the next step in the case, the work start waiting days in each step is determined so as not to exceed the allowable waiting days, work-in-progress quantity in each process is reduced.

【0017】また、この発明の請求項2に係る工程別作
業スケジューリング装置においては、製品の種類及び個
数を示す注文情報を記憶部に格納し、各工程の生産能力
及び製品別工期を示す入力情報と作業開始の許容待ち日
数を入力部により入力する。さらに、処理部において、
作業開始日及び作業完了日算出部により、上記注文情
報、上記入力情報及び遅延日数指示情報に基づいて順次
連続する工程毎に製品の作業開始日及び作業完了日を求
め、次工程での作業開始日が求められた後、待ち日数算
出部により、次工程での作業開始日から前工程での作業
完了日を減算して待ち日数を算出する。そして、待ち日
数比較部により、上記待ち日数算出部で算出された上記
待ち日数と上記入力部に入力された上記許容待ち日数と
を比較してその比較差に応じた遅延日数指示情報を上記
作業開始日及び作業完了日算出部に出力する。
In the process-specific work scheduling apparatus according to the second aspect of the present invention, the order information indicating the type and the number of products is stored in the storage unit, and the input information indicating the production capacity of each process and the product-specific work period is stored. Enter the allowable number of days to wait for the work to start in the input section. Furthermore, in the processing unit,
The work start date and work completion date calculation unit calculates the work start date and work completion date of the product for each successive process based on the order information, the input information, and the delay days instruction information, and starts the work in the next process. After the day is obtained, the waiting day number calculation unit calculates the waiting day number by subtracting the work completion date of the previous process from the work start date of the next process. Then, the number of waiting days comparison unit compares the number of waiting days calculated by the number of waiting days calculating unit with the allowable number of waiting days input to the input unit, and the delayed number of days instruction information corresponding to the comparison difference is used for the work. Output to the start date and work completion date calculation unit.

【0018】[0018]

【実施例】【Example】

実施例1.図1は、この発明の実施例1の概念図であ
る。同図に示すように、各工程での作業開始日は、図3
と同じ注文情報入力1、各工程の生産能力入力2及び各
工程の製品別工期入力3と、ここで新たに追加される許
容待ち日数入力6とに基づき演算処理4Aにより順次算
出されて、表示5が行われる。
Example 1. 1 is a conceptual diagram of Embodiment 1 of the present invention. As shown in the figure, the work start date in each process is shown in FIG.
Based on the same order information input 1, production capacity input 2 for each process, product-specific work period input 3 for each process, and allowable waiting days input 6 newly added here, the calculation process 4A sequentially calculates and displays. 5 is performed.

【0019】その際の演算処理4Aは、各工程での作業
開始までの待ち日数を算出し(待ち日数算出7)、この
待ち日数と許容待ち日数入力6とを比較して(待ち日数
比較8)、その比較結果に基づき各工程での作業開始日
が許容待ち日数以下になるようにする。
In the arithmetic processing 4A at that time, the number of waiting days until the start of work in each process is calculated (waiting day number calculation 7), and this waiting day number is compared with the allowable waiting day number input 6 (waiting day number comparison 8 ), And based on the comparison result, the work start date in each process should be less than the allowable waiting days.

【0020】図2に、上述した概念に基づくブロック図
を示す。同図において、11は注文情報が格納される例
えばファイルなどの記憶部、12は各工程の生産能力及
び製品別工期と各工程での許容待ち日数を入力する例え
ばキーボードなどの入力部、13はファイル11と入力
部12の情報に基づき順次連続して各工程での作業開始
日及び作業完了日を求める処理部、14は処理部13の
処理結果を表示出力する表示部である。
FIG. 2 shows a block diagram based on the above concept. In the figure, 11 is a storage unit such as a file in which order information is stored, 12 is an input unit such as a keyboard for inputting the production capacity of each process and the construction period for each product and the allowable waiting days in each process, and 13 is A processing unit that sequentially obtains a work start date and a work completion date in each process based on the information of the file 11 and the input unit 12, and a display unit 14 that displays and outputs the processing result of the processing unit 13.

【0021】上記処理部13は、各工程での作業開始日
及び作業完了日を順次連続して求める作業開始日及び作
業完了日算出部13aと、各工程での作業開始日までの
待ち日数を算出する待ち日数算出部13bと、算出され
た待ち日数と入力部12から入力された許容待ち日数と
を比較して作業開始日の遅延指示情報を作業開始日及び
作業完了日算出部13aに出力する待ち日数比較部13
cとを有する。
The processing unit 13 calculates the work start date and the work completion date in each process successively and the work start date and work completion date calculation unit 13a, and the number of waiting days until the work start date in each process. The calculated waiting days calculation unit 13b compares the calculated waiting days with the allowable waiting days input from the input unit 12, and outputs the work start date delay instruction information to the work start date and work completion date calculation unit 13a. Waiting day comparison section 13
with c and.

【0022】次に、処理部の動作を図2のフローチャー
トに基づいて説明する。作業開始日及び作業完了日算出
部13aは、注文情報記憶部11から注文書の注文情報
が入力されると、第一工程の作業開始枠引き当て開始日
を本日Aに設定した後(ステップX1)、本日Aより第
一工程の生産能力枠(一日当たりの処理能力)に注文情
報を引き当てていき、第一工程の生産能力に余裕のある
日を第一工程での作業開始日Bとする(ステップX
2)。
Next, the operation of the processing section will be described with reference to the flowchart of FIG. When the order information of the order form is input from the order information storage unit 11, the work start date and work completion date calculation unit 13a sets the work start frame allocation start date of the first process to today A (step X1). From today's A, the order information is allocated to the production capacity frame (processing capacity per day) of the first process, and the day when the production capacity of the first process has a margin is the work start date B in the first process ( Step X
2).

【0023】続いて、作業開始日及び作業完了日算出部
13aは、求めた第一工程での作業開始日Bに第一工程
の工期を加算して第一工程での作業完了日Cを算出する
(ステップX3)。
Subsequently, the work start date and work completion date calculation unit 13a calculates the work completion date C in the first process by adding the work period of the first process to the work start date B in the first process obtained. Yes (step X3).

【0024】続いて、作業開始日及び作業完了日算出部
13bは、第一工程での作業完了日Cより注文情報を第
二工程の生産能力枠に引き当てていき、第二工程の生産
能力に余裕のある日を第二工程での作業開始日Dとする
(ステップX4)。
Subsequently, the work start date and work completion date calculation unit 13b assigns the order information to the production capacity frame of the second process from the work completion date C of the first process, and determines the production capacity of the second process. A day with a margin is set as a work start date D in the second process (step X4).

【0025】次に、待ち日数算出部13bは、第二工程
に於ける作業開始待ち日数E=D−Cを算出する(ステ
ップX5)。
Next, the waiting day number calculating unit 13b calculates the number of waiting days for starting work E = D-C in the second step (step X5).

【0026】待ち日数比較部13cは、第二工程に於け
る作業開始待ち日数Eが入力部12により入力された第
二工程の許容待ち日数T1よりも大きいか否かを比較
し、第二工程での作業開始日Dまでの待ち日数数Eが許
容待ち日数T1よりも大きい場合は、その差(E−T
1)を遅延指示情報として作業開始日及び作業完了日算
出部13aに出力する(ステップX6)。
The waiting day number comparing unit 13c compares whether or not the work start waiting day number E in the second step is larger than the allowable waiting day number T1 of the second step inputted by the input section 12, and the second step. If the number E of waiting days until the work start date D in E is larger than the allowable number of waiting days T1, the difference (E−T
1) is output as delay instruction information to the work start date and work completion date calculation unit 13a (step X6).

【0027】作業開始日及び作業完了日13aは、遅延
指示情報を受けて、第一工程での作業開始日Bを(E−
T1)分遅らせた日を新たに第一工程での作業開始枠引
き当て開始日Aとして、再び第一工程での作業開始日B
を求める(ステップX1)。
The work start date and work completion date 13a are the work start date B in the first process (E-
T1) The date delayed by 1 minute is newly set as the work start frame allocation start date A in the first process, and the work start date B in the first process is again set.
Is calculated (step X1).

【0028】このようにステップX2〜X7を繰り返
し、ステップX6において、待ち日数比較部13cでの
比較の結果、第二工程に於ける作業開始待ち日数Eが許
容待ち日数T1よりも小さくなれば、待ち日数比較部1
3cから遅延日数が0であることを示す遅延日数指示情
報が作業開始日及び作業完了日算出部13aに出力す
る。
In this way, steps X2 to X7 are repeated, and in step X6, as a result of comparison in the waiting day number comparing unit 13c, if the work start waiting day E in the second process becomes smaller than the allowable waiting day number T1, Waiting days comparison section 1
From 3c, the delay days instruction information indicating that the delay days is 0 is output to the work start date and work completion date calculation unit 13a.

【0029】作業開始日及び作業完了日算出部13a
は、遅延日数指示情報を受けて、第二工程での作業開始
日Dに第二工程の工期を加算して第二工程での作業完了
日を算出する(ステップX8)。
Work start date and work completion date calculation unit 13a
Receives the delay days instruction information and calculates the work completion date in the second process by adding the construction period of the second process to the work start date D in the second process (step X8).

【0030】これ以降の工程でも同じく、待ち日数が許
容待ち日数を越えた場合に1つ前の工程での作業開始日
を遅らせて待ち日数を許容待ち日数以下にし、最終の第
N工程まで実施して第N工程での作業完了日Yを算出す
る(ステップX(M−2)〜M)。そして、第N工程での作
業完了日Yを基に回答納期(製品を収めることができる
予定日)Zを算出し(ステップX(M))、これを表示部
14に表示する。
Also in the subsequent processes, when the number of waiting days exceeds the allowable number of waiting days, the work start date of the immediately preceding process is delayed to reduce the number of waiting days to less than the allowable number of waiting days until the final Nth process. Then, the work completion date Y in the Nth process is calculated (steps X (M-2) to M). Then, based on the work completion date Y in the N-th process, an answer delivery date (scheduled date when the product can be stored) Z is calculated (step X (M)), and this is displayed on the display unit 14.

【0031】[0031]

【発明の効果】以上のように、この発明の請求項1に係
る工程別作業スケジューリング方法は順次連続する稼働
中の各工程毎に作業開始日及び作業完了日を求める際、
次工程での作業開始日から前工程での作業完了日を減算
して得られる次工程での作業開始日までの待ち日数があ
らかじめ設定された許容待ち日数を越える場合に、前工
程での作業開始日を上記待ち日数と上記許容待ち日数と
の差分遅らせて前工程での作業完了日と次工程での作業
開始日を算出し直すと共に、上記許容待ち日数以下であ
る場合には次工程での作業完了日を算出するようにした
ことによって、各工程での作業開始日までの待ち日数が
許容待ち日数以下になるので、各工程内の仕掛り数量の
増加を防ぐことができるため生産期間を短くできて生産
効率を向上させることができ、また製品生産のために必
要な素材や材料などを維持するための金利負担を最小限
にすることができるという効果を奏する。
As described above, according to the step-by-step work scheduling method of the present invention, when the work start date and the work completion date are obtained for each successive operating step,
Work in the previous process when the number of waiting days until the work start date in the next process, which is obtained by subtracting the work completion date in the previous process from the work start date in the next process, exceeds the preset allowable waiting days Delay the start date by the difference between the number of waiting days and the number of allowable waiting days and recalculate the work completion date in the previous process and the work starting date in the next process. By calculating the work completion date of, the number of waiting days until the work start date in each process will be less than the allowable number of waiting days, so it is possible to prevent the increase of the in-process quantity in each process It is possible to shorten the time period, improve the production efficiency, and minimize the interest rate burden for maintaining the materials and materials necessary for product production.

【0032】また、この発明の請求項2に係る工程別作
業スケジューリング装置は、製品の種類及び個数を示す
注文情報を記憶部に格納し、処理部において、作業開始
日及び作業完了日算出部により、上記注文情報と入力部
から入力される各工程の生産能力及び製品別工期に基づ
いて順次連続する稼働中の工程毎に製品の作業開始日及
び作業完了日を求め、待ち日数算出部により、次工程で
の作業開始日から前工程での作業完了日を減算して待ち
日数を算出し、待ち日数比較部により、上記待ち日数算
出部で算出した上記待ち日数と入力部に入力された許容
待ち日数とを比較してその比較差に応じた遅延日数指示
情報を上記作業開始日及び完了日算出部に出力するよう
に構成したことによって、記憶手段に格納された注文情
報が変わっても、各工程での仕掛かり数量を増加させな
い作業開始日を簡単に算出することができるという効果
を奏する。
The process-based work scheduling apparatus according to claim 2 of the present invention stores order information indicating the type and number of products in the storage unit, and the processing unit uses the work start date and work completion date calculation unit to store the order information. , The work start date and work completion date of the product are sequentially obtained for each continuously operating process based on the order information and the production capacity of each process input from the input unit and the work period for each product, and the waiting day calculation unit The work start date in the next process is subtracted from the work completion date in the previous process to calculate the number of waiting days, and the number of waiting days comparison unit calculates the number of waiting days calculated in the number of waiting days calculation unit and the tolerance input in the input unit. Even if the order information stored in the storage means is changed by comparing the number of waiting days and outputting the delay day instruction information corresponding to the comparison difference to the work start date and completion date calculation unit, An effect that the work start date does not increase-process quantity in step can be easily calculated.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の実施例の概念図である。FIG. 1 is a conceptual diagram of an embodiment of the present invention.

【図2】この発明の実施例1のブロック図である。FIG. 2 is a block diagram of a first embodiment of the present invention.

【図3】この発明の実施例1の動作を説明するためのフ
ローチャートである。
FIG. 3 is a flow chart for explaining the operation of the first embodiment of the present invention.

【図4】従来装置を示すブロック図である。FIG. 4 is a block diagram showing a conventional device.

【図5】従来装置の動作を説明するためのフローチャー
トである。
FIG. 5 is a flowchart for explaining the operation of the conventional device.

【符号の説明】[Explanation of symbols]

11 ファイル 12 入力部 13 処理部 13a 作業開始日及び作業完了日算出部 13b 待ち日数算出部 13c 待ち日数比較部 14 表示部 11 File 12 Input Section 13 Processing Section 13a Work Start Date and Work Completion Date Calculation Section 13b Waiting Day Count Calculation Section 13c Waiting Day Comparison Section 14 Display Section

【手続補正書】[Procedure amendment]

【提出日】平成5年4月14日[Submission date] April 14, 1993

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0003[Name of item to be corrected] 0003

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【0003】図に、従来の工程別作業スケジューリン
グ装置の概念図を示す。同図に示すように、各工程での
作業開始日は、製品の種類及び個数を示す注文情報入力
1と、各工程の生産能力(個/日または個/時間)を示
す生産能力入力2と、各工程の製品別工期(加工時間)
を示す工期入力3とに基づく演算処理4により順次算出
されて、表示5が行われるように構成されていた。
FIG. 4 shows a conceptual diagram of a conventional process-based work scheduling apparatus. As shown in the figure, the work start date of each process includes an order information input 1 indicating the type and number of products, and a production capacity input 2 indicating the production capacity (pieces / day or pieces / hour) of each step. , Work period for each process (processing time)
The display 5 is sequentially calculated by the arithmetic processing 4 based on the construction period input 3 indicating

【手続補正2】[Procedure Amendment 2]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0004[Correction target item name] 0004

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【0004】次に、上述した演算処理4を図のフロー
チャートに基づいて説明する。まず、新規注文書の注文
情報の入力時に、第一工程の作業開始引き当て開始日を
本日Aに設定する(ステップY1)。
[0004] Next, a description will be given of a calculation process 4 described above in the flowchart of FIG. First, when the order information of the new order form is input, the work start allocation start date of the first process is set to today's A (step Y1).

【手続補正3】[Procedure 3]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0018[Correction target item name] 0018

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【0018】[0018]

【実施例】 実施例1.図1は、この発明の実施例1の概念図であ
る。同図に示すように、各工程での作業開始日は、図
と同じ注文情報入力1、各工程の生産能力入力2及び各
工程の製品別工期入力3と、ここで新たに追加される許
容待ち日数入力6とに基づき演算処理4Aにより順次算
出されて、表示5が行われる。
EXAMPLES Example 1. 1 is a conceptual diagram of Embodiment 1 of the present invention. As shown in the figure, the work start date in each step, Figure 4
Based on the same order information input 1, production capacity input 2 for each process, product-specific work period input 3 for each process, and allowable waiting days input 6 newly added here, the calculation process 4A sequentially calculates and displays. 5 is performed.

【手続補正4】[Procedure amendment 4]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0022[Name of item to be corrected] 0022

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【0022】次に、処理部の動作を図のフローチャー
トに基づいて説明する。作業開始日及び作業完了日算出
部13aは、注文情報記憶部11から注文書の注文情報
が入力されると、第一工程の作業開始枠引き当て開始日
を本日Aに設定した後(ステップX1)、本日Aより第
一工程の生産能力枠(一日当たりの処理能力)に注文情
報を引き当てていき、第一工程の生産能力に余裕のある
日を第一工程での作業開始日Bとする(ステップX
2)。
Next, it will be described with reference to operation of the processing unit in the flowchart of FIG. When the order information of the order form is input from the order information storage unit 11, the work start date and work completion date calculation unit 13a sets the work start frame allocation start date of the first process to today A (step X1). From today's A, the order information is allocated to the production capacity frame (processing capacity per day) of the first process, and the day when the production capacity of the first process has a margin is the work start date B in the first process ( Step X
2).

【手続補正5】[Procedure Amendment 5]

【補正対象書類名】図面[Document name to be corrected] Drawing

【補正対象項目名】図5[Name of item to be corrected] Figure 5

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図5】 [Figure 5]

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 製品の種類及び個数を示す注文情報と稼
働中の各工程の製品別工期及び生産能力の余裕を示す入
力情報に基づいて順次連続する各工程毎に作業開始日及
び作業完了日を求める際、次工程での作業開始日を求め
た後、この次工程での作業開始日から前工程での作業完
了日を減算して次工程での作業開始日までの待ち日数を
得て、この待ち日数とあらかじめ設定した許容待ち日数
とを比較し、上記待ち日数が上記許容待ち日数を越える
場合に前工程での作業開始日を上記待ち日数と上記許容
待ち日数との差分遅らせて前工程での作業完了日と次工
程での作業開始日を算出し直しその後次工程での作業完
了日を算出すると共に、上記待ち日数が上記許容待ち日
数以下である場合には次工程での作業完了日を算出する
ことを特徴とする工程別作業スケジューリング方法。
1. A work start date and a work completion date for each successive process based on order information indicating the type and quantity of products and input information indicating a product-specific work period and production capacity margin of each process in operation. When calculating the work start date in the next process, subtract the work completion date in the previous process from the work start date in the next process to obtain the number of waiting days until the work start date in the next process. If the number of waiting days exceeds the allowable number of waiting days, the work start date in the previous process is delayed by the difference between the number of waiting days and the number of allowable waiting days. Recalculate the work completion date in the process and the work start date in the next process, and then calculate the work completion date in the next process. If the number of waiting days is less than the allowable number of waiting days, work in the next process is performed. A feature characterized by calculating the completion date Scheduled work scheduling method.
【請求項2】 製品の種類及び個数を示す注文情報を格
納した記憶部と、稼働中の各工程の生産能力及び製品別
工期の余裕を示す入力情報と作業開始の許容待ち日数を
入力する入力部と、上記記憶部から読み出した上記注文
情報と上記入力部によって入力された上記入力情報及び
上記作業開始の許容待ち日数とに基づいて各工程の作業
開始日及び作業完了日を順次求める処理部とを備えると
共に、上記処理部を、上記注文情報、上記入力情報及び
遅延日数指示情報に基づいて順次連続する工程毎に製品
の作業開始日及び作業完了日を求める作業開始日及び作
業完了日算出部と、この作業開始日及び作業完了日算出
部により次工程での作業開始日が得られた後、次工程で
の作業開始日から前工程での作業完了日を減算して待ち
日数を算出する待ち日数算出部と、この待ち日数算出部
で算出した上記待ち日数と上記入力部に入力された上記
許容待ち日数とを比較してその比較差に応じた遅延日数
指示情報を上記作業開始日及び完了日算出部に出力する
待ち日数比較部とで構成したことを特徴とする工程別作
業スケジューリング装置。
2. A storage unit in which order information indicating the type and quantity of products is stored, input information indicating the production capacity of each operating process and the margin of the work period for each product, and an input for inputting the allowable waiting days for starting work. Unit, a processing unit that sequentially obtains a work start date and a work completion date of each process based on the order information read from the storage unit, the input information input by the input unit, and the allowable waiting days for the work start. In addition to the above, the processing unit calculates the work start date and the work completion date of the product for each successive process based on the order information, the input information, and the delay number instruction information After the work start date of the next process is obtained by the department and the work start date and work completion date calculation unit, the work completion date of the previous process is subtracted from the work start date of the next process to calculate the number of waiting days. Waiting to do The number-of-days calculation unit is compared with the number of waiting days calculated by the number-of-waiting-days calculation unit and the allowable number of waiting days input in the input unit, and the delay-day instruction information corresponding to the comparison difference is input to the work start date and completion. A work-scheduling device for each process, which is configured by a waiting days comparison unit that outputs to a day calculation unit.
JP33729892A 1992-12-17 1992-12-17 Work scheduling method and device by process classifications Pending JPH06187014A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33729892A JPH06187014A (en) 1992-12-17 1992-12-17 Work scheduling method and device by process classifications

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33729892A JPH06187014A (en) 1992-12-17 1992-12-17 Work scheduling method and device by process classifications

Publications (1)

Publication Number Publication Date
JPH06187014A true JPH06187014A (en) 1994-07-08

Family

ID=18307309

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33729892A Pending JPH06187014A (en) 1992-12-17 1992-12-17 Work scheduling method and device by process classifications

Country Status (1)

Country Link
JP (1) JPH06187014A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6816530B2 (en) * 2002-09-30 2004-11-09 Lucent Technologies Inc. Nonlinear semiconductor light sources

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6816530B2 (en) * 2002-09-30 2004-11-09 Lucent Technologies Inc. Nonlinear semiconductor light sources

Similar Documents

Publication Publication Date Title
JPH10118896A (en) Schedule preparation support system
JPH06187014A (en) Work scheduling method and device by process classifications
JPH05314143A (en) Product production planning system in batch plant
JPH06218659A (en) Preparation replacing instruction device and manufacturing system
JPH07182420A (en) Production planning device
JPH08147366A (en) Production planning device
JPH0966442A (en) Process control device
JP2953223B2 (en) Scheduling planning equipment
JPH07234897A (en) Production schedule preparing device
JP2002073142A (en) Production schedule generating device and recording medium with recorded production schedule generating program of production schedule generating device
JP3825642B2 (en) Production planning method
JPH08315033A (en) Advancement managing device
JPH06162037A (en) Plan forming system for production planning
JPH01244607A (en) Apparatus for displaying in-process of semiconductor device group
JP2001100832A (en) System for delivery date calculation, and method for calculating delivery date for ordered product
JPH11282923A (en) Circulation type production process schedule planning method
JPH06139248A (en) Schedule information control system
JPH0573107A (en) System and method for planning production
JPH0830679A (en) Generation and update processor for bar chart for schedule control
JPH06332909A (en) Plan managing system
JP2008276412A (en) Process progress management system and process progress management method
JP3033319B2 (en) Self-process planning equipment
JP2510774B2 (en) Production planning method
JP2002304504A (en) Distributing device and distributing method
JP3117786B2 (en) Production machine operation schedule management device