JP2510774B2 - Production planning method - Google Patents

Production planning method

Info

Publication number
JP2510774B2
JP2510774B2 JP19740390A JP19740390A JP2510774B2 JP 2510774 B2 JP2510774 B2 JP 2510774B2 JP 19740390 A JP19740390 A JP 19740390A JP 19740390 A JP19740390 A JP 19740390A JP 2510774 B2 JP2510774 B2 JP 2510774B2
Authority
JP
Japan
Prior art keywords
production
time
product
reservation table
delivery date
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP19740390A
Other languages
Japanese (ja)
Other versions
JPH0482660A (en
Inventor
良和 沖汐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Electric Works Co Ltd
Original Assignee
Matsushita Electric Works Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Electric Works Ltd filed Critical Matsushita Electric Works Ltd
Priority to JP19740390A priority Critical patent/JP2510774B2/en
Publication of JPH0482660A publication Critical patent/JPH0482660A/en
Application granted granted Critical
Publication of JP2510774B2 publication Critical patent/JP2510774B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は製品の生産計画作成を行うための方法に関す
るものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial field of use] The present invention relates to a method for production planning of a product.

[従来の技術] 従来、この種の方法としては特開昭63−28665号や、
特開平1−109469号がある。
[Prior Art] Conventionally, as a method of this kind, JP-A-63-28665 and
There is JP-A-1-109469.

前者の特開昭63−28665号は生産ラインにおいて夫々
の工程のリードタイムから、ボトルネック工程を割り出
し、その工程がフル稼働できるように投入順、投入時間
の決定を行うものである。また後者の特開平1−109469
号はジョブを機械に割り付けるときにジョブと機械の選
択を分離して、処理する組み合わせの数を減らし、計算
時間の短縮を可能としたものである。
In the former Japanese Patent Laid-Open No. 63-28665, the bottleneck process is determined from the lead time of each process in the production line, and the order of injection and the time of injection are determined so that the process can fully operate. The latter Japanese Patent Laid-Open No. 1-109469
When the job is assigned to the machine, the selection of the job and the machine is separated, the number of combinations to be processed is reduced, and the calculation time can be shortened.

[発明が解決しようとする課題] しかしながら前者の従来例は、一連のラインでショッ
プフロアのような多数と製品を多数を機械に割り付ける
場合には適用できない。また後者の従来例では解決しよ
うとする問題は同じであるが、制約条件を割り付ける前
に判断していないため、計画割り付け時に、不確実性が
ある。
[Problems to be Solved by the Invention] However, the former conventional example cannot be applied when a large number of products such as a shop floor and a large number of products are allocated to a machine in a series of lines. In the latter conventional example, the problem to be solved is the same, but there is uncertainty at the time of allocating the plan because the constraint condition is not judged before allocation.

特に多品種少量生産の工場における生産計画は、多く
の知識や多くの工数を必要とするため、コンピュータを
用いて自動化しても生産計画の組み合わせの多さから処
理時間が非常に長くかかってしまうという問題がある。
In particular, a production plan for a high-mix low-volume factory requires a lot of knowledge and a lot of man-hours, so even if it is automated using a computer, the processing time will be extremely long due to the large number of combinations of production plans. There is a problem.

本発明は高速に処理できる生産計画作成のアルゴリズ
ムを作成し、処理時間の短縮を図った生産計画作成方法
に関するものである。
The present invention relates to a production plan creation method for reducing the processing time by creating an algorithm for production plan creation that can be processed at high speed.

〔課題を解決するための手段〕[Means for solving the problem]

本発明は、上記の目的を達成するために、単位時間当
たりの設備の生産能力に基づいて単位時間数で示した生
産可能時間を納期に対応させて記述した生産計画予約テ
ーブルをメモリ上に予め設定する過程と、所定の品番の
製品を当該設備で生産するための割り付けに際して当該
品番における連続した必要生産時間と納期とのデータを
入力する入力過程と、入力された当該製品の納期に対応
する上記生産計画予約テーブルの生産予約テーブルの生
産可能時間が当該製品の生産に必要とする連続した必要
生産時間以上であれば、当該製品の納期以降の各生産計
画予約テーブルの生産可能時間から当該製品の必要生産
時間を差し引き、且つ当該製品の納期より一つ前の生産
計画予約テーブルの生産可能時間と、納期の生産計画予
約テーブルの生産可能時間とを比較して等しくなければ
上記必要生産時間から1単位時間を減算した値を必要生
産時間としてこの必要生産時間を当該製品の納期の一つ
の前の産計画予約テーブルの生産可能時間から差し引
き、該製品の納期より一つ前の生産計画予約テーブルの
生産可能時間と納期の生産計画予約テーブルの生産可能
時間とが等しければ当該製品の必要生産時間をそのまま
とし、以後当該製品の納期から当該製品を生産開始時ま
の期間に設定された生産計画予約テーブルの生産可能時
間の前後の値を順次比較して等しくなければ当該製品の
必要生産時間から1単位時間を減算した値を当該接品の
必要生産時間とし、該必要生産時間を一つ前の生産計画
予約テーブルの生産可能時間から差し引いて当該生産計
画予約テーブルの生産可能時間とする演算処理を行って
当該製品の割り付けを上記生産計画予約テーブルに登録
する過程とからなることを特徴とする。
In order to achieve the above object, the present invention preliminarily stores in a memory a production plan reservation table in which the producible time indicated by the number of unit hours based on the production capacity of equipment per unit time is described in correspondence with the delivery date. Corresponds to the setting process and the input process of inputting the data of continuous required production time and delivery date for the product number when allocating the product of the specified product number at the facility, and the input delivery date of the product If the producible time of the production reservation table of the production plan reservation table is equal to or longer than the continuous required production time required for production of the product, the product becomes available from the producible time of each production plan reservation table after the delivery date of the product. The production time of the production plan reservation table one before the delivery date of the product and the production plan reservation table of the delivery date If it is not equal by comparing with the time, the value obtained by subtracting 1 unit time from the above required production time is taken as the required production time, and this required production time is subtracted from the producible time in the production planning reservation table immediately before the delivery date of the product. , If the producible time of the production plan reservation table immediately before the delivery date of the product is equal to the producible time of the production plan reservation table of the delivery date, then the required production time of the product is left unchanged, The values before and after the producible time in the production plan reservation table set during the period from the start of production of the product are sequentially compared, and if they are not equal, the value obtained by subtracting 1 unit time from the required production time of the product is concerned. Required production time, and subtracting the required production time from the producible time of the preceding production plan reservation table to obtain the producible time of the production plan reservation table. Processing performed assignment of the product, characterized in that it consists of a process of registering to the production plan reservation table.

〔作用〕[Action]

而して本発明によれば、上記のような演算処理を行っ
て生産計画予約テーブルの生産可能時間の値を変更して
登録するため、一度所定の品番の製品を生産計画を割り
付けた後、他の品番の製品を割り付けるときに、移動な
ど再割付けしなくてもよいので設備の割りつけ時点での
組み合わせを減らすことができる。
Thus, according to the present invention, since the value of the producible time of the production plan reservation table is changed and registered by performing the above-described arithmetic processing, after once allocating the production plan of the product of the predetermined product number, When allocating products of other product numbers, it is not necessary to reallocate products such as movement, so the number of combinations at the time of equipment allocation can be reduced.

[実施例] 以下本発明を実施例により説明する。[Examples] The present invention will be described below with reference to Examples.

第1図は本発明方法を作用したシステムを示してお
り、基本的にはデータを入力する入力装置1と、演算処
理及び生産計画予約テーブルに対する登録処理などを行
う演算処理装置2と生産計画予約テーブルを書き込むメ
モリ3とから構成されている。
FIG. 1 shows a system which operates the method of the present invention. Basically, an input device 1 for inputting data, an arithmetic processing device 2 for performing arithmetic processing and registration processing for a production plan reservation table, and a production plan reservation. It is composed of a memory 3 for writing a table.

次に実際例に基づいて本発明方法を説明する。 Next, the method of the present invention will be described based on actual examples.

まず生産計画予約を行うに当たっては、第2図に示す
フローチャートのステップで入力装置1から予め単位
時間(実施例では一日を1単位時間としている)当たり
の設備の生産能力に基づいて納期を示す日付とその納期
日までを設備の生産可能時間数(単位時間数、実施例で
は日数で表現)とを入力し、この入力に基づいて演算処
理装置2の処理により生産可能時間数(以下生産可能日
数と称する)を納期に対応させた生産計画予約テーブル
をメモリ3上に設定する。
First, in order to make a production plan reservation, a delivery date is shown in advance from the input device 1 based on the production capacity of the equipment per unit time (one day is set as one unit time in the embodiment) in the step of the flowchart shown in FIG. The date and the delivery date are entered as the number of production hours of the equipment (unit hours, expressed in number of days in the embodiment), and based on this input, the number of production hours by the processing of the arithmetic processing unit 2 A production plan reservation table corresponding to the delivery date is set in the memory 3.

第3図(a)は設定した生産計画予約テーブルの一例
を示しており、上段は納期の日付を、下段は上述した生
産可能日数を示しており、例えば納期が4月4日の場
合、生産可能日数が“4"となっている。これは4月4日
までにこの設備に4日分の生産ができる時間が空いてい
ることを示す。つまり4月1日では1日分、4月10日で
は10日分となる。
FIG. 3 (a) shows an example of the set production plan reservation table. The upper row shows the date of delivery and the lower row shows the number of days that can be produced as described above. For example, if the delivery date is April 4, The number of possible days is "4". This means that by April 4, there will be four days left for this facility to produce four days. In other words, it will be one day for April 1 and 10 days for April 10.

さて生産計画予約テーブルをメモリ3で設定した後、
第2図のステップで当該設備で生産したい品番の製品
のデータを入力装置1から入力し、ステップにおける
データの有無の判定過程の経過後ステップにおいて、
必要生産時間数(単位時間数で示し、実施例では必要生
産日数となる。以下必要生産日数と称する)と納期とを
取り込む。
Now, after setting the production plan reservation table in memory 3,
In the step of FIG. 2, after inputting the data of the product of the product number desired to be produced by the equipment from the input device 1, in the step after the judgment process of the presence or absence of the data in the step,
The required number of production hours (indicated by the number of unit hours, which is the required number of production days in the embodiment; hereinafter referred to as the required number of production days) and the delivery date are taken in.

この取り込みが終了すると演算処理装置2は次の演算
処理を行う。例えば連続した必要生産日数が3日で納期
が4月6日のa品番の製品を予約を行う場合、演算処理
装置2ではステップで既に設定している4月6日の生
産計画予約テーブルに書き込まれている生産可能日数の
値A=“6"を参照し、この生産計画予約テーブル値“6"
と当該製品の必要生産日数B=“3"とを比較し、A≧B
であれば、設備に当該製品の生産を予約することにな
る。
When this acquisition is completed, the arithmetic processing unit 2 performs the following arithmetic processing. For example, when making a reservation for a product with a product number of which the required number of consecutive production days is 3 days and the delivery date is April 6th, the arithmetic processing unit 2 writes in the production plan reservation table of April 6th which is already set in step. Refer to the value of available production days A = "6", and set this production plan reservation table value "6"
And the required production days for the product B = "3", A ≥ B
In that case, the production of the product is reserved in the facility.

ここでステップで生産計画予約テーブルに当該製品
の予約登録を行うのであるが、このとき次のような演算
処理を行う。
In this step, reservation registration of the product is performed in the production plan reservation table. At this time, the following arithmetic processing is performed.

つまり当該製品の納期より後、第3図(a)では4月
6日以降の各生産計画予約テーブル値から当該製品の必
要生産日数を差し引く。次に当該製品の納期期日より1
日前(第3図(a)では4月5日)の生産計画予約テー
ブル値“5"と、納期の生産計画予約テーブル値“6"とを
比較して等しくなければ上記必要生産日数から単位時間
“1"を減算した値“2"を必要生産日数としてこの必要生
産日数“2"を当該製品の納期の一つ前の生産計画予約テ
ーブル値“5"から差し引くのである。更にこの差し引か
れる前の4月5日の生産計画予約テーブルの生産可能日
数の値“5"と、4月4日の生産計画予約テーブルの生産
可能日数の値“4"とを比較して等しくなければ上述と同
様に当該製品の必要生産日数(この場合“2"に変わって
いる)から単位時間“1"を減算し、この減算した値“1"
を新たな必要生産日数とし、この必要生産日数“1"を4
月4日の生産計画予約テーブルのテーブルの生産可能日
数の値“4"から差し引いて、4月4日の生産計画予約テ
ーブルのテーブルの生産可能日数の値“4"を“3"に変更
する。
That is, after the delivery date of the product, in FIG. 3 (a), the required number of production days of the product is subtracted from each production plan reservation table value after April 6th. Next, 1 from the delivery date of the product
The production plan reservation table value "5" of the day before (April 5 in Fig. 3 (a)) and the production plan reservation table value of the delivery date "6" are compared, and if they are not equal, the required number of production days becomes the unit time. The value "2" obtained by subtracting "1" is set as the required number of production days, and the required number of production days "2" is subtracted from the production plan reservation table value "5" immediately before the delivery date of the product. Furthermore, the value “5” of producible days in the production plan reservation table on April 5 before this deduction and the value “4” of producible days in the production plan reservation table on April 4 are compared and made equal. Otherwise, as in the above case, the unit time "1" is subtracted from the required production days of the product (in this case, it has changed to "2"), and this subtracted value "1"
Is set as a new required production day, and this required production day “1” is set to 4
Subtract from the value "4" for the number of days that can be produced in the table of the production planning reservation table on the 4th of a month, and change the value "4" for the number of days that can be produced in the table of the production planning reservation table on the 4th of April to "3" .

更に4月4日と当該製品の生産開始時に対応する4月
3日との間においても上記の演算処理を同様に行う。こ
の場合必要生産日数が“0"となるため、これより生産計
画予約テーブルの初日である4月1日までの生産計画予
約テーブルのテーブルの生産可能日数の値を第3図
(a)に示した値のままとする。
Further, the above arithmetic processing is similarly performed between April 4 and April 3 corresponding to the start of production of the product. In this case, the required number of production days is “0”, so the value of the number of days that can be produced in the table of the production plan reservation table up to April 1, which is the first day of the production plan reservation table, is shown in FIG. 3 (a). It remains the same value.

このようにして演算処理を行った結果に基づいて生産
計画予約テーブルを第3図(b)に示すように変更して
a品番の製品の生産割り付けを登録する。この生産計画
予約テーブルの内容は4月6日までの6日間の内3日は
予約されている状態を示している。つまり4月6日まで
には後3日の空きがあるということを示している。
Based on the result of the arithmetic processing as described above, the production plan reservation table is changed as shown in FIG. 3B to register the production allocation of the product of the product number a. The content of the production plan reservation table shows that three days out of the six days until April 6 are reserved. In other words, it means that there will be 3 days left by April 6th.

次に同じ設備を使用して必要生産日数が2日で、納期
4月6日のb品番の製品の生産割り付けを行う場合には
当該製品の必要生産日数と納期とからなるデータ入力を
上述と同様に行うと、a品番の製品の生産割り付けと同
様な演算処理が為されて、第3図(c)に示すような生
産計画予約テーブルに変更される。
Next, if the same equipment is used and the required production days are 2 days and the production allocation of the product with the b product number on April 6th is made, the data input consisting of the required production days and the delivery date of the product must be entered as described above. In the same manner, the same arithmetic processing as the production allocation of the product of the product number a is performed, and the production plan reservation table as shown in FIG. 3C is changed.

以後同様な処理を行って生産できる時間がなくなる
か、または生産する品番が無くなるまで、生産予約の割
り付けが可能となり、データ入力が無くなれば、第2図
に示す処理フローチャートを終了する(ステップ)。
Thereafter, the production reservation can be allocated until the time when the production can be performed by the same processing is exhausted or the product number to be produced is exhausted, and when the data input is eliminated, the processing flowchart shown in FIG. 2 is ended (step).

尚第3図(d)は必要生産日数が“1"で、納期が4月
6日のc品番の製品の生産予約の割り付けを行った場合
の生産計画予約テーブルを示す、第3図(e)は更に必
要生産日数が“4"で、納期が4月10日のd品番の製品の
生産予約の割り付けを行った場合の生産計画予約テーブ
ルの示す。
Incidentally, FIG. 3 (d) shows a production plan reservation table in the case where the production reservation is allocated for the product with the required production number "1" and the delivery date is April 6, and the product number c is shown in FIG. 3 (e). ) Shows the production plan reservation table when the production reservation is allocated for the product of d product number of which the required number of production days is "4" and the delivery date is April 10.

ところで、上記第3図(d)の状態から4月9日が納
期で必要生産日数が5日の製品の割り付けを行うとした
場合には、4月9日の生産可能日数の値は“3"であるた
め、この設備では4月9日より前に3日分の生産能力し
かない。従って4月9日で5日分の生産できないことに
なる。つまりこの製品の割り付けはできない。
By the way, from the state shown in FIG. 3 (d), if the product is allocated on April 9 with a delivery date of 5 days and a required production day of 5 days, the value of the number of producible days on April 9 is "3. "Therefore, this facility has a production capacity of 3 days before April 9th. Therefore, it will be impossible to produce 5 days by April 9. In other words, this product cannot be assigned.

以上のように本発明方法では、生産計画予約テーブル
の日付(納期日に対応)及び設備の生産可能日数、生産
計画製品の納期、必要生産日数とを用いて、納期日まで
の生産可能日数から必要生産日数を差し引いてその値が
0になるまで割り付けて行くものであり、第2図に示す
アリゴリズムによって、当該設備で生産可能な品番を決
定し、その後生産順序決定を行って最終的な生産計画を
確定するのである。この際ある製品をアルゴリズムにか
ける順番は、優先的に割り付けたい品番、生産を先に確
保したい品番、候補設備が少ない品番等の優先順により
決定する。
As described above, according to the method of the present invention, the date (corresponding to the delivery date) in the production plan reservation table, the number of production days of the equipment, the delivery date of the production plan product, and the required production days are used to calculate the number of production days until the delivery date. The required number of production days is subtracted and the value is allocated until it reaches 0. By the algorithm shown in Fig. 2, the product numbers that can be produced by the equipment are determined, and then the production order is determined to make the final production. Establish the plan. At this time, the order in which a certain product is applied to the algorithm is determined by a priority number such as a product number to be preferentially allocated, a product number to be secured for production first, and a product number with few candidate facilities.

〔発明の効果〕〔The invention's effect〕

本発明は、単位時間当たりの設備の生産能力に基づい
て単位時間数で示した生産可能時間を納期に対応させて
記述した生産計画予約テーブルをメモリ上に予め設定す
る過程と、所定の品番の製品を当該設備で生産するため
の割り付けに際して当該品番における連続した必要生産
時間と納期とのデータを入力する入力過程と、入力され
た当該製品の納期に対応する上記生産計画予約テーブル
の生産予約テーブルの生産可能時間が当該製品の生産に
必要とする連続した必要生産時間以上であれば、当該製
品の納期以降の各生産計画予約テーブルの生産可能時間
から当該製品の必要生産時間を差し引き、且つ当該製品
の納期より一つ前の生産計画予約テーブルの生産可能時
間と、納期の生産計画予約テーブルの生産可能時間とを
比較して等しくなければ上記必要生産時間から1単位時
間を減算した値を必要生産時間としてこの必要生産時間
の当該製品の納期の一つの前の産計画予約テーブルの生
産可能時間から差し引き、該製品の納期より一つ前の生
産計画予約テーブルの生産可能時間と納期と生産計画予
約テーブルの生産可能時間とが等しければ当該製品の必
要生産時間をそのままとし、以後当該製品の納期から当
該製品の生産開始時までの期間に設定された生産計画予
約テーブルの生産可能時間の前後の値を順次比較して等
しくなければ当該製品の必要生産時間から1単位時間を
減算した値を当該製品の必要生産時間とし、該必要生産
時間を一つ前の生産計画予約テーブルの生産可能時間か
ら差し引いて当該生産計画予約テーブルの生産可能時間
とする演算処理を行って当該製品の割り付けを上記生産
計画予約テーブルに登録する過程とからなるので、一度
所定の品番の製品の生産計画を割り付けた後、他の品番
の製品の割り付けるときに移動などの再割り付けなどを
必要とせず、割り付け処理を高速にできる生産計画作成
のアルゴリズムが得られ、その結果多品種、少量生産の
場合においても設備の割り付け時点での組み合わせを減
らせて、生産計画の割り付けが簡単に且つ早い処理で行
えるというとう効果がある。
According to the present invention, a process of presetting a production plan reservation table on the memory in which the producible time indicated by the number of unit hours based on the production capacity of equipment per unit time is described in correspondence with a delivery date, and a predetermined product number. An input process of inputting data of continuous required production time and delivery date in the product number when allocating the product in the facility, and a production reservation table of the production plan reservation table corresponding to the input delivery date of the product If the available production time of the product is equal to or greater than the continuous required production time required to produce the product, the required production time of the product is subtracted from the production available time of each production plan reservation table after the delivery date of the product, and Compare the producible time of the production plan reservation table one before the delivery date of the product with the producible time of the production plan reservation table of the delivery date and make them equal. For example, the value obtained by subtracting one unit time from the above required production time is taken as the required production time, which is subtracted from the producible time of the production planning reservation table one before the delivery date of the product of this required production time, and one from the delivery date of the product. If the producible time and delivery date of the previous production plan reservation table are equal to the producible time of the production plan reservation table, the required production time of the product is left unchanged, and thereafter the period from the delivery date of the product to the start of production of the product. The values before and after the producible time in the production plan reservation table set in step 1 are sequentially compared, and if they are not equal, the value obtained by subtracting one unit time from the required production time of the product is set as the required production time of the product, and the required production The time is subtracted from the producible time of the previous production planning reservation table to obtain the producible time of the production planning reservation table, and the calculation processing is performed to allocate the product. Since it consists of the process of registering the production plan reservation table with the allocation, once the production plan of the product of the predetermined product number is allocated, it is not necessary to reallocate it when allocating the product of another product number. It is possible to obtain an algorithm for creating a production plan that enables high-speed allocation processing, and as a result, even in the case of high-mix, low-volume production, it is possible to reduce the number of combinations at the time of equipment allocation, and to allocate production plans easily and quickly. It has a good effect.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明方法を用いるシステムの構成図、第2図
は同上の処理フローチャート、第3図(a)〜(e)は
同上の生産計画予約テーブルの説明図を示す。 1は入力装置、2は演算処理装置、3はメモリである。
FIG. 1 is a block diagram of a system using the method of the present invention, FIG. 2 is a processing flowchart of the above, and FIGS. 3 (a) to 3 (e) are explanatory views of the production plan reservation table of the above. Reference numeral 1 is an input device, 2 is an arithmetic processing device, and 3 is a memory.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】単位時間当たりの設備の生産能力に基づい
て単位時間数で示した生産可能時間を納期に対応させて
記述した生産計画予約テーブルをメモリ上に予め設定す
る過程と、所定の品番の製品を当該設備で生産するため
の割り付けに際して当該品番における連続した必要生産
時間と納期とのデータを入力する入力過程と、入力され
た当該製品の納期に対応する上記生産計画予約テーブル
の生産予約テーブルの生産可能時間が当該製品の生産に
必要とする連続した必要生産時間以上であれば、当該製
品の納期以降の各生産計画予約テーブルの生産可能時間
から当該製品の必要生産時間を差し引き、且つ当該製品
の納期より一つ前の生産計画予約テーブルの生産可能時
間と、納期の生産計画予約テーブルの生産可能時間とを
比較して等しくなければ上記必要生産時間から1単位時
間を減算した値を必要生産時間としてこの必要生産時間
を当該製品の納期の一つの前の産計画予約テーブルの生
産可能時間から差し引き、該製品の納期より一つ前の生
産計画予約テーブルの生産可能時間と納期の生産計画予
約テーブルの生産可能時間とが等しければ当該製品の必
要生産時間をそのままとし、以後当該製品の納期から当
該製品の生産開始時までの期間に設定された生産計画予
約テーブルの生産可能時間の前後の値を順次比較して等
しくなければ当該製品の必要生産時間から1単位時間を
減算した値を当該製品を必要生産時間とし、該必要生産
時間を一つ前の生産計画予約テーブルの生産可能時間か
ら差し引いて当該生産計画予約テーブルの生産可能時間
とする演算処理を行って当該製品の割り付けを上記生産
計画予約テーブルに登録する過程とからなることを特徴
とする生産計画作成方法。
1. A process of presetting a production plan reservation table on a memory, in which a producible time indicated by the number of unit hours based on the production capacity of equipment per unit time is described in correspondence with a delivery date, and a predetermined product number. Process of inputting data of continuous required production time and delivery date for the product number when allocating the product of the product at the equipment, and production reservation of the production plan reservation table corresponding to the input delivery date of the product If the producible time of the table is equal to or longer than the continuous required production time required for producing the product, the required production time of the product is subtracted from the producible time of each production plan reservation table after the delivery date of the product, and Compare the producible time of the production planning reservation table one before the delivery date of the product with the producible time of the production planning reservation table of the delivery date and make them equal. If this is the case, the value obtained by subtracting one unit time from the above required production time is taken as the required production time, and this required production time is subtracted from the producible time in the production planning reservation table, which is one before the delivery date of the product, and is subtracted by If the producible time of the previous production plan reservation table and the producible time of the production plan reservation table of the delivery date are the same, the required production time of the product is left as it is, and thereafter, from the delivery date of the product to the start of production of the product. The values before and after the producible time of the production plan reservation table set for the period are sequentially compared, and if they are not equal, the value obtained by subtracting one unit time from the required production time of the product is set as the required production time of the product, and The production time is subtracted from the producible time of the preceding production plan reservation table to obtain the producible time of the production plan reservation table Production planning method characterized by comprising a process of a registered in the production plan reservation table with Ri.
JP19740390A 1990-07-25 1990-07-25 Production planning method Expired - Lifetime JP2510774B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19740390A JP2510774B2 (en) 1990-07-25 1990-07-25 Production planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19740390A JP2510774B2 (en) 1990-07-25 1990-07-25 Production planning method

Publications (2)

Publication Number Publication Date
JPH0482660A JPH0482660A (en) 1992-03-16
JP2510774B2 true JP2510774B2 (en) 1996-06-26

Family

ID=16373933

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19740390A Expired - Lifetime JP2510774B2 (en) 1990-07-25 1990-07-25 Production planning method

Country Status (1)

Country Link
JP (1) JP2510774B2 (en)

Also Published As

Publication number Publication date
JPH0482660A (en) 1992-03-16

Similar Documents

Publication Publication Date Title
JP2510774B2 (en) Production planning method
JPH1050571A (en) Method and device for controlling production
JPH0425350A (en) Preparation device for schedule of production process
JP2811827B2 (en) Production scheduling device
JPH06218659A (en) Preparation replacing instruction device and manufacturing system
JP2705649B2 (en) Work assignment method
JP2002055710A (en) Process chart editing system
JPH05174031A (en) Production load deciding method
JP5963190B2 (en) Production plan creation system and creation program
JP3106027B2 (en) Production plan creation method
JP2908076B2 (en) Scheduling system
JP2957711B2 (en) Scheduling method
JP3045075B2 (en) Production scheduling method
JP2008276412A (en) Process progress management system and process progress management method
JPH05204933A (en) Production plan preparing method
JP3115150B2 (en) Production planning equipment
JPH0573578A (en) Lot managing device
JPH0966442A (en) Process control device
JP3227736B2 (en) Work content switching instruction device
JPH0728892A (en) Method and device for generating schedule
JPH04311257A (en) Process management system
JPH08137949A (en) Method for changing plan of gantt chart
JPH11320343A (en) Production schedule planning method and device
JPH08147366A (en) Production planning device
JPH07114599A (en) Production plan making method