JP2008276412A - Process progress management system and process progress management method - Google Patents

Process progress management system and process progress management method Download PDF

Info

Publication number
JP2008276412A
JP2008276412A JP2007117617A JP2007117617A JP2008276412A JP 2008276412 A JP2008276412 A JP 2008276412A JP 2007117617 A JP2007117617 A JP 2007117617A JP 2007117617 A JP2007117617 A JP 2007117617A JP 2008276412 A JP2008276412 A JP 2008276412A
Authority
JP
Japan
Prior art keywords
lot
priority
date
order
product
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007117617A
Other languages
Japanese (ja)
Inventor
Atsuhiko Hamashima
厚彦 浜島
Tatsunori Uchida
龍徳 内田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Digital Solutions Corp
Original Assignee
Toshiba Corp
Toshiba Solutions Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Solutions Corp filed Critical Toshiba Corp
Priority to JP2007117617A priority Critical patent/JP2008276412A/en
Publication of JP2008276412A publication Critical patent/JP2008276412A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

<P>PROBLEM TO BE SOLVED: To make clear the priority of a lot to set up, and to support execution of warehousing work according to a daily warehousing plan. <P>SOLUTION: This process progress management system has: a database means for storing process order related to production of a product, a set up process of the lot, an amount of the products included in the lot, a warehousing plan number and warehousing results number in each data of the product; a comparison means for comparing the beginning process of the lot and the process order stored in the database means; a rearrangement means for rearranging an already set up lot group in order wherein the beginning process is approximate to a final process based on a comparison result by the comparison means, and obtaining allocation order of priority order; a necessary number calculation means for calculating a warehousing necessary number in each data based on a difference between the warehousing results number and the warehousing plan number stored in the database means; and a priority order determination means for allocating the amount of the products included in each lot to the warehousing necessary number according to the allocation order, and determining work priority order of the lot based on the allocated date. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、半導体・液晶・電子部品などの複数の製造工程を持つ製造現場で、仕掛かるロットの優先順位を明確に指示する工程進捗管理システムおよび工程進捗管理方法に関する。   The present invention relates to a process progress management system and a process progress management method that clearly indicate the priority order of lots to be processed in a manufacturing site having a plurality of manufacturing processes such as semiconductors, liquid crystals, and electronic components.

半導体・液晶・電子部品などの複数の製造工程を持つ製造現場において仕掛かるロットをスケジュール機能、先入れ先だし機能、およびロット毎につけられた倉入予定日(納期)などによって決定し、作業員への指示情報を出力する技術が知られている。   Lots to be processed at manufacturing sites with multiple manufacturing processes such as semiconductors, liquid crystals, and electronic parts are determined by the schedule function, first-in first-out function, and the expected date of arrival (delivery date) assigned to each lot. A technique for outputting instruction information to is known.

例えば、特許文献1では、製造工程に仕掛済の製品について、ロット毎に倉入予定日を算出し、予め定められた倉入予定日より遅れているロットに対して追い上げ指示情報を出力している。
特開2004−295188号公報
For example, in Patent Document 1, for a product that has already been processed in the manufacturing process, the expected date of entering the warehouse is calculated for each lot, and the catch-up instruction information is output for the lot that is behind the predetermined scheduled date of entering the warehouse. Yes.
JP 2004-295188 A

しかし、オフラインで製造する工場においては、必ずしもスケジュール通りに製造作業が行われない場合がある。例えば、作業員が最終工程のロットを処理する予定にも関わらず、誤って優先順位の低い中間工程のロットを処理する場合が挙げられる。このような場合、従来技術では、倉入予定日に対して余裕のあるロットを後回しにしているため、最終工程に近いロットがあっても付されている倉入予定日が遅ければ、着工の優先度が下がり、結果として倉入計画を達成できなくなってしまう。すなわち、製造作業の進捗状況に柔軟に対応できないという問題があった。   However, in a factory that manufactures offline, manufacturing operations may not always be performed as scheduled. For example, there is a case where an operator mistakenly processes a low-priority intermediate process lot even though the worker plans to process the final process lot. In such a case, in the prior art, since a lot with a margin with respect to the planned entry date is postponed, even if there is a lot close to the final process, The priority is lowered, and as a result, the Kurari plan cannot be achieved. That is, there has been a problem that the progress of manufacturing work cannot be flexibly handled.

そこで、本発明は、仕掛かるロットの優先順位を容易に把握でき、日々の倉入計画に対する倉入作業の遂行を支援する工程進捗管理システムおよび工程進捗管理方法を提供することを目的とする。   Accordingly, an object of the present invention is to provide a process progress management system and a process progress management method that can easily grasp the priority order of lots to be processed and support the execution of a storehouse operation for a daily storehouse plan.

本発明に係る工程進捗管理システムは、ロット単位で管理される製品の製造工程に仕掛かる複数のロットに対して製造作業における優先順位を決定する優先ロット決定装置と、この優先ロット決定装置に接続され、前記決定された優先順位を取得し、表示する優先ロット表示装置と、からなり、前記優先ロット決定装置が、前記製品の製造に係る工程順序、前記ロットの仕掛工程、前記ロットに含まれる前記製品の数量、前記製品の各日付における倉入計画数および倉入実績数を記憶するデータベース手段と、このデータベース手段に記憶される前記工程順序と仕掛済のロットの仕掛工程とを比較する比較手段と、この比較手段による比較結果に基づいて前記仕掛済のロット群を前記仕掛工程が最終工程から近い順に並べ替え、前記優先順位の割付順を求める並び替え手段と、前記データベース手段に記憶される前記倉入計画数と前記倉入実績数との差分に基づいて各日付における倉入必要数を算出する必要数算出手段と、前記割付順に従って各ロットに含まれる前記製品の数量を各日付における前記倉入必要数に対して割付け、前記割付けられた日付に基づいて前記ロットの製造作業における優先順位を決定する優先順位決定手段と、を有することを特徴とする。     A process progress management system according to the present invention is connected to a priority lot determination device that determines a priority order in a manufacturing operation for a plurality of lots in the manufacturing process of a product managed in units of lots, and the priority lot determination device. And a priority lot display device that acquires and displays the determined priority order, and the priority lot determination device is included in the process sequence relating to the manufacture of the product, the in-process process of the lot, and the lot. The database means for storing the quantity of the product, the number of planned warehouses and the number of actual warehouses for each date of the product, and the comparison for comparing the process sequence stored in the database means with the in-process of the in-process lot And the priorities based on the comparison result by the comparing means, and sorting the in-process lot group in the order in which the in-process process is closer to the final process. Reordering means for obtaining an allocation order; necessary number calculating means for calculating the required number of warehouse entries on each date based on the difference between the number of planned warehouse entries and the actual number of warehouse entries stored in the database means; Priority order determining means for allocating the quantity of the product included in each lot according to the allocation order to the required number of warehouses on each date, and determining the priority in the manufacturing operation of the lot based on the allocated date; It is characterized by having.

本発明に係る工程進捗管理方法は、ロット単位で管理される製品の製造工程に仕掛かる複数の前記ロットに対し、前記製品の情報を記憶するデータベースを備えるコンピュータが製造作業における優先順位を決定する工程進捗管理方法であって、前記データベースから前記製品の製造における工程順序を取得する工程順序取得ステップと、前記データベースから前記製品に係るロットの仕掛工程、前記ロットに含まれる前記製品の数量を含むロット在庫情報を取得するロット在庫情報取得ステップと、前記取得された仕掛工程と前記工程順序とを比較し、仕掛済の前記ロット群を前記仕掛工程が最終工程から近い順に並べ替え、前記優先順位の割付順を求める並び替えステップと、前記データベースから前記製品の各日付における倉入計画数を取得する倉入計画取得ステップと、前記データベースから前記製品の各日付における倉入実績数を取得する倉入実績取得ステップと、前記取得された倉入実績数と倉入計画数との差分に基づいて各日付における倉入必要数を算出する必要数算出ステップと、前記割付順に従って各ロットに含まれる前記製品の数量を前記各日付における倉入必要数に対して割付け、前記割付けられた日付に基づいて前記ロットの製造作業における優先順位を決定する優先順位決定ステップと、前記決定された優先順位を表示する優先ロット表示ステップと、を有することを特徴とする。   In the process progress management method according to the present invention, a computer having a database for storing product information is determined for a plurality of lots in a manufacturing process of products managed in units of lots, and priorities in manufacturing operations are determined. A process progress management method, comprising: a process sequence acquisition step of acquiring a process sequence in manufacturing of the product from the database; an in-process process of a lot related to the product from the database; and a quantity of the product included in the lot The lot inventory information acquisition step for acquiring the lot inventory information, the acquired in-process process and the process sequence are compared, the in-process lot group is rearranged in order of the in-process process from the last process, and the priority Reordering step to determine the order of allocation of the products, and the number of plans to store in each date of the product from the database Based on the difference between the acquired Kurashiri plan acquisition step, the Kuradori actual acquisition step for acquiring the Kurashiri actual number on each date of the product from the database, and the acquired Kurashiri actual number and the Kurashiri plan number A required number calculating step for calculating the required number of warehouses on each date, and assigning the quantity of the product included in each lot to the required number of warehouses on each date according to the order of allocation, and assigning to the allocated date And a priority order determining step for determining a priority order in the manufacturing operation of the lot, and a priority lot display step for displaying the determined priority order.

本発明によれば、仕掛かるロットの優先順位を容易に把握でき、日々の倉入計画に対する倉入作業の遂行を支援する工程進捗管理システムおよび工程進捗管理方法が提供される。   According to the present invention, there are provided a process progress management system and a process progress management method capable of easily grasping priorities of lots to be processed and supporting execution of a storehouse operation for a daily storehouse plan.

以下、本発明の実施形態について図面を用いて説明する。図1に本発明の一実施形態の全体構成例を示す。本実施形態に係る工程進捗管理システムは、優先ロット決定装置1と優先ロット表示装置2から構成され、各装置はバス3を介して接続されている。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 shows an example of the overall configuration of an embodiment of the present invention. The process progress management system according to this embodiment includes a priority lot determination device 1 and a priority lot display device 2, and each device is connected via a bus 3.

優先ロット決定装置1は、演算処理を行うCPU11、各種プログラムの展開先である主記憶部12、プログラム等を記憶する補助記憶部13、および各種のデータを記憶するデータベース部14を備えるコンピュータである。   The priority lot determination apparatus 1 is a computer including a CPU 11 that performs arithmetic processing, a main storage unit 12 that is a development destination of various programs, an auxiliary storage unit 13 that stores programs, and a database unit 14 that stores various data. .

CPU11は、当日作業の開始時およびロットの新規投入時に、補助記憶部13内に記憶されているロットの優先度決定プログラム131を主記憶部12に読み込んで実行し、その時点でのデータベース部14内の情報を使用して優先ロット情報を作成する。   The CPU 11 reads the lot priority determination program 131 stored in the auxiliary storage unit 13 into the main storage unit 12 and executes it at the start of the day work and when a new lot is input, and the database unit 14 at that time. Priority lot information is created using the information in

また、データベース部14は、例えば製造フロー情報テーブル141、ロット在庫情報テーブル142、倉入計画テーブル143、倉入実績テーブル144、および優先ロット情報テーブル145などを備えている。各テーブルの記憶内容は以下の通りである。
製造フロー情報テーブル141は、製造工程の順序を製品毎に記憶する。
ロット在庫情報テーブル142は、ロットの所在(仕掛工程)、在庫数(仕掛数)、状態情報(流品可否、倉入可否など)をロット毎に記憶する。
倉入計画テーブル143は、各日付における製品毎の倉入計画数を記憶する。
倉入実績テーブル144は、各日付における製品毎の倉入した数量(倉入実績数)を記憶する。
優先ロット情報テーブル145は、製品毎に決定されたロットの優先順位情報を記憶する。
Further, the database unit 14 includes, for example, a manufacturing flow information table 141, a lot stock information table 142, a warehouse entry plan table 143, a warehouse entry record table 144, a priority lot information table 145, and the like. The stored contents of each table are as follows.
The manufacturing flow information table 141 stores the order of manufacturing processes for each product.
The lot stock information table 142 stores the location of a lot (in-process), the number of stocks (in-process), and state information (such as availability of goods, availability of warehouse) for each lot.
The Kurairi plan table 143 stores the number of Kurairi plans for each product on each date.
The warehouse entry record table 144 stores the quantity of warehouses entered for each product on each date (the number of warehouse entries).
The priority lot information table 145 stores lot priority information determined for each product.

優先ロット表示装置2は、入力部21および表示部22を備えるコンピュータであり、設置台数は任意である。
入力部21は、製造管理者がキーボード等のユーザインターフェイスから入力する対象製品情報、ロット投入日、投入数などの各種情報を受付け、接続先の優先ロット決定装置1に出力する。
表示部22は、優先ロット決定装置1で決定された倉入対象区分に基づいて並べ替えられたロット情報を表示する。具体的には、着工可能ロットの内、倉入対象区分の一番小さいロットを最優先ロットとして表示する。製造管理者は、この優先ロット表示に基づいて操作担当者へ仕掛の指示を行う。尚、表示する方法は、画面表示に限らない。
The priority lot display device 2 is a computer including an input unit 21 and a display unit 22, and the number of installed devices is arbitrary.
The input unit 21 accepts various pieces of information such as target product information, lot input date, and input number input from the user interface such as a keyboard by the manufacturing manager, and outputs the information to the priority lot determination device 1 as a connection destination.
The display unit 22 displays the lot information rearranged based on the store entry target category determined by the priority lot determination device 1. Specifically, among the lots that can be started, the smallest lot in the warehouse entry category is displayed as the highest priority lot. The production manager gives an in-process instruction to the person in charge of operation based on the priority lot display. The display method is not limited to the screen display.

図2は、優先ロット決定装置1における優先度決定プログラム131の処理の概要を説明する機能ブロック図である。優先度決定プログラム131の処理は、判定処理、並び替え処理、必要数算出処理、割付処理、新規投入処理に大別される。以下、各処理を詳細に説明する。   FIG. 2 is a functional block diagram for explaining the outline of processing of the priority determination program 131 in the priority lot determination device 1. The processing of the priority determination program 131 is roughly divided into determination processing, rearrangement processing, necessary number calculation processing, allocation processing, and new input processing. Hereinafter, each process will be described in detail.

1.判定処理
優先ロット決定装置1は、当日作業の開始時およびロットの新規投入時にロットの優先順位を決定するが、装置の起動時によって処理が異なる。判定処理は、割付のタイミングを判定する処理であり、判定した結果が当日作業の開始時ならば並び替え処理、ロットの新規投入時ならば新規投入処理が行われる。具体的には、優先ロット表示装置2からロットの新規投入が行われたか否か判定が行われ、起動時によって割付のアルゴリズムを切り換える。
1. Judgment processing The priority lot determination device 1 determines the priority order of lots at the start of work on the day and when a new lot is input, but the processing differs depending on when the device is activated. The determination process is a process for determining the allocation timing. If the determined result is the start of work on the day, the rearrangement process is performed, and if the lot is newly input, a new input process is performed. Specifically, it is determined whether or not a new lot has been input from the priority lot display device 2, and the allocation algorithm is switched depending on the time of activation.

2.並び替え処理
並び替え処理は、既に投入されているロットを最終工程に近い方から順に並べ替え、優先順位の前提となる割付順を設定する処理である。
まず、製造フロー情報テーブル141およびロット在庫情報テーブル142から対象製品の工程情報と各工程に対する在庫の所在情報(仕掛工程)をそれぞれ取得する。取得した情報の具体例を表1に示す。

Figure 2008276412
2. Rearrangement process The rearrangement process is a process of rearranging already input lots in order from the closest to the final process, and setting an allocation order that is a premise of the priority order.
First, the process information of the target product and the inventory location information (in-process) for each process are acquired from the manufacturing flow information table 141 and the lot inventory information table 142, respectively. Specific examples of the acquired information are shown in Table 1.
Figure 2008276412

ここで、LOT001(100)のLOT001は流品単位につけられたロットNO、カッコ内の数字は、そのロットの持つ部品数(ウェハ数、シート枚数。単位は、倉入計画に従う)を表す。
また、反転色のロット(LOT008(120))は、既にスクラップ登録(流品不可)されているロットを表す。
また、ロット在庫情報テーブル142から各ロットの投入日情報を取得する。取得した情報の具体例を表2に示す。

Figure 2008276412
Here, LOT001 of LOT001 (100) is the lot number assigned to the unit of goods, and the numbers in parentheses indicate the number of parts (number of wafers, number of sheets. The unit follows the Kuroi plan).
Further, the lot of the reverse color (LOT008 (120)) represents a lot that has already been registered as a scrap (unusable).
Further, the input date information of each lot is acquired from the lot stock information table 142. Specific examples of the acquired information are shown in Table 2.
Figure 2008276412

次に、流品不可のロットを除外したロット群を対象として割付順を設定する。割付の設定条件は変更可能であるが、基本的には、並べ替えの優先順位を、1)最終工程に近い順、2)投入日順、として設定する。表1および表2の情報に基づいて割付順を設定した結果を表3に示す。

Figure 2008276412
Next, an allocation order is set for the lot group excluding the lots that cannot be handled. Allocation setting conditions can be changed, but basically, the order of rearrangement is set as 1) the order close to the final process, and 2) the order of input date. Table 3 shows the result of setting the allocation order based on the information in Tables 1 and 2.
Figure 2008276412

尚、同一工程にあるロットの投入日が同じ場合には、ロットNOが自動発番などにより投入した順に発番されているならばロットNO順を条件に追加してもよい。また、在庫数の多い順などの条件を付加してもよい。   If the lots in the same process have the same insertion date, the lot NO order may be added as a condition if the lot numbers are issued in the order in which they are entered by automatic numbering or the like. Moreover, you may add conditions, such as order with many stock numbers.

3.必要数算出処理
必要数算出処理は、倉入計画と前日までの倉入実績を比較して前日までの計画未達成数を計算し、各日付における倉入れの必要数を算出する処理である。
倉入計画テーブル143から取得した倉入計画の具体例を表4に示す。
尚、ここでは3/21以降は未計画とする。

Figure 2008276412
3. Necessary number calculation process The necessary number calculation process is a process of calculating the number of unsuccessful plans for the previous day by calculating the number of unsuccessful plans up to the previous day by comparing the storey plan and the previous record of the previous year.
Table 4 shows a specific example of the Kurairi plan acquired from the Kurairi plan table 143.
Here, 3/21 and beyond are not planned.
Figure 2008276412

例えば、3/10終了時点において、月初からの倉入計画数の累計に1000に対して750が倉入済とすると、前日までの計画未達成数は250である。
したがって、3/11における必要数は倉入計画数の100に250を加算した350に補正する。表4を補正した結果を表5に示す。

Figure 2008276412
For example, at the end of 3/10, if the number of planned warehouses from the beginning of the month is 750, the number of unsuccessful plans up to the previous day is 250.
Therefore, the required number in 3/11 is corrected to 350, which is 250 added to the number of planned entrances. The results of correcting Table 4 are shown in Table 5.
Figure 2008276412

4.割付処理
割付処理は、並び替え処理で求めた割付順と必要数算出処理で補正された各日の倉入計画数に基づいて製造した場合に、各工程に仕掛かる在庫が倉入の対象となる日(以下、「倉入対象日」という。)を設定する処理である。また、設定された倉入対象日から倉入対象区分を求め、倉入対象日と共に優先ロット情報テーブル145へ記憶する。
4). Allocation process The allocation process is based on the allocation order obtained in the rearrangement process and the planned number of warehouses for each day corrected in the required number calculation process. This is a process of setting a certain day (hereinafter referred to as “date of entry”). Further, the store entry target classification is obtained from the set store entry date, and stored in the priority lot information table 145 together with the store entry date.

並び替え処理(表4)と必要数算出処理(表5)の結果に基づいて倉入対象日は表6のように設定される。

Figure 2008276412
Based on the results of the rearrangement process (Table 4) and the required number calculation process (Table 5), the date for entering the warehouse is set as shown in Table 6.
Figure 2008276412

例えば、倉入予定日が3/11の場合には、必要数算出処理から必要数は350である。そして、並び替え処理で求めた優先順位で製造を行った場合には、LOT010およびLOT001の在庫数の合計(300)とLOT006の在庫数の一部(50)によって必要数を満たすことができる。
したがって、LOT010、LOT001、LOT006の倉入対象日は3/11となる。
尚、LOT006のように同一のロット内で倉入予定日が異なってしまう場合は、倉入対象日には当日に近い方の日付が設定される。
また、倉入対象区分を「(倉入対象日)−(当日)+1」として求める。すなわち、当日を1、翌日を2、翌々日を3と設定する。
For example, if the expected date of entry is 3/11, the required number is 350 from the required number calculation process. When manufacturing is performed in the priority order obtained by the rearrangement process, the required number can be satisfied by the total number of stocks of LOT010 and LOT001 (300) and a part of the number of stocks of LOT006 (50).
Therefore, the date of entry into LOT010, LOT001, and LOT006 is 3/11.
If the planned date of entering the warehouse is different within the same lot, such as LOT006, the date closer to the current day is set as the date of entering the warehouse.
Also, the warehouse entry classification is obtained as “(date of warehouse entry) − (today) +1”. That is, the current day is set to 1, the next day is set to 2, and the next day is set to 3.

各ロットの倉入対象日より倉入対象区分を求めた結果を表7に示す。

Figure 2008276412
Table 7 shows the result of obtaining the warehouse entry classification from the warehouse entry date of each lot.
Figure 2008276412

ここで、LOT003およびLOT012には倉入対象区分として有得ない値である99999が設定されているが、これは倉入対象日が設定されていなかったためである。ゆえに、設定された優先順位に影響を与えない値であれば他の値(例えば10)としてもよい。   Here, LOT003 and LOT012 are set to 99999, which is a value that cannot be obtained as a store entry target category, because the store entry date has not been set. Therefore, other values (for example, 10) may be used as long as they do not affect the set priority order.

上記のように求められた倉入対象日および倉入対象区分は、優先ロット情報テーブル145に登録される。したがって、製造管理者は、優先ロット表示装置2から対象製品番号などを入力することにより、優先ロット決定装置1から仕掛かるロットの優先順位を容易に把握できる。   The store entry target date and store entry target category obtained as described above are registered in the priority lot information table 145. Accordingly, the manufacturing manager can easily grasp the priority order of the lots to be processed from the priority lot determination device 1 by inputting the target product number or the like from the priority lot display device 2.

5.新規投入処理
新規投入処理は、優先ロット表示装置2からロットの新規投入が指示された場合に、既に投入済のロットに含まれる在庫数と、当日割付直前に退避した倉入計画と、投入時点の倉入実績から投入分に関して割付を行う処理である。
5. New input process The new input process is performed when the new lot input is instructed from the priority lot display device 2, the number of stocks included in the already input lot, the store entry plan evacuated immediately before the allocation on the day, and the input time This is a process of assigning the amount of input from the past record of Kurano.

割付に際しては、まず、投入時点の倉入実績と対象製品の当日倉入数から前日までの倉入実績を求め、これを前日までの倉入計画と比較し、その差分から当日以降の倉入計画を補正する。そして、仕掛済の在庫数、新規投入するロットの部品数の順に補正された倉入計画に当てはめ、投入するロットの倉入対象日および倉入対象区分を設定する。尚、仕掛済の在庫に対しての割付は、当日の作業開始時に設定されたままでよい。
また、割付けた倉入対象区分は、倉入対象日と共に優先ロット情報テーブル145へ登録する。
When assigning, first of all, the warehouse entry record at the time of introduction and the number of entries in the same day for the target product are obtained, and the previous entry is compared with the previous entry, and from that difference, Correct the plan. Then, it is applied to the warehouse entry plan corrected in the order of the number of in-process inventory and the number of parts in the newly introduced lot, and the warehouse entry date and the warehouse entry classification of the lot to be introduced are set. Note that the allocation to the in-process inventory may remain set at the start of the day's work.
Moreover, the assigned warehouse entry classification is registered in the priority lot information table 145 together with the warehouse entry date.

例えば、4/1における倉入計画が表8の場合に、

Figure 2008276412
For example, if Kurashiri plan in 4/1 is Table 8,
Figure 2008276412

「前日まで150部品超過で倉入実施済、かつ、仕掛済の在庫が0」であるならば、4/1に投入するロットは最初に処理されるが、4/1の必要数は0であるので倉入対象日は、翌日の4/2(倉入対象区分は、「4/2−4/1+1」で2)となる。
また、「前日まで150部品超過で倉入実施済、かつ、仕掛済の在庫が100」であるならば、4/1に投入するロットは仕掛済の在庫の後に処理されるので、倉入対象日は、4/3(倉入対象区分は、「4/3−4/1+1」で3)となる。
また、「前日まで150部品不足し、かつ、仕掛済の在庫が0」であるならば、4/1に投入するロットは最初に処理されるので、倉入対象日は、当日の4/1(倉入対象区分は、「4/1−4/1+1」で1)となる。
If “there are more than 150 parts up to the previous day and the inventory is already in progress and the in-process inventory is 0”, the lot to be input on 4/1 is processed first, but the required number of 4/1 is 0. Therefore, the date of entry into the warehouse is 4/2 the next day (the entry into the warehouse is 2 for “4 / 2-4 / 1 + 1”).
In addition, if “there are more than 150 parts up to the previous day and the inventory in progress is 100”, the lot to be input on 4/1 is processed after the inventory in progress. The day is 4/3 (the warehouse entry classification is “4 / 3-4 / 1 + 1” is 3).
In addition, if “150 parts are insufficient until the previous day and the in-process inventory is 0”, the lot to be input on 4/1 is processed first, so the target date is 4/1 on the current day. (Kurairi target classification is “4 / 1-4 / 1 + 1” is 1).

次に、ロット優先度決定プログラム131の処理を図3乃至図5に基づいて詳細に説明する。図3および図4は、優先ロットの決定処理の具体例を示すフローチャートである。尚、ステップS310とS311は、連続した処理とする。   Next, the processing of the lot priority determination program 131 will be described in detail with reference to FIGS. 3 and 4 are flowcharts showing a specific example of the priority lot determination process. Steps S310 and S311 are continuous processing.

先ず、ロット在庫情報テーブル142から仕掛済の各ロットの在庫情報および工程情報(仕掛工程)を取得する(ステップS301)。
次に、ロット在庫情報テーブル142から各ロットの投入日情報を取得する(ステップS302)。
次に、製造フロー情報テーブル141において定義される工程順序に流品可能なロットの仕掛工程を当てはめ、ロット群を最終工程から近い順に並び替える(ステップS303)。
次に、倉入計画テーブル143から当月以降の倉入計画を取得する(ステップS304)。
次に、当月月初からの倉入実績を倉入実績テーブル144から取得する(ステップS305)。
次に、倉入計画と倉入実績を比較して計画未達成数を算出する(ステップS306)。
次に、ステップS306で算出された計画未達成数を考慮して倉入計画を補正し、各日付の倉入計画数を求める(ステップS307)。以下、日付を変数Xで表し、各日付における倉入計画数を倉入計画数(X)で表すものとする。
次に、当日日付を変数Xに代入する(ステップS308)。
次に、ステップS303において並べ替えられたロット群から割付順が最上位のロットを割付処理の対象(以下、「対象ロット」という。)とし、その在庫数を変数Yに代入する(ステップS309)。
次に、対象ロットに対する倉入対象日を未設定として初期化する(ステップS310)。
First, inventory information and process information (in-process) for each in-process lot are acquired from the lot inventory information table 142 (step S301).
Next, the input date information of each lot is acquired from the lot stock information table 142 (step S302).
Next, the in-process processes of the lots that can be flowed are applied to the process order defined in the manufacturing flow information table 141, and the lot group is rearranged in the order closer to the final process (step S303).
Next, a storehouse plan for the current month and after is acquired from the storehouse plan table 143 (step S304).
Next, the storehouse record from the beginning of the current month is acquired from the storehouse record table 144 (step S305).
Next, the number of unsuccessful plans is calculated by comparing the Kurairi plan and the Kurairi record (step S306).
Next, the warehouse entry plan is corrected in consideration of the plan unachieved number calculated in step S306, and the warehouse entry plan number for each date is obtained (step S307). Hereinafter, the date is represented by a variable X, and the number of Kurashiri plans on each date is represented by the number of Kurashiri plans (X).
Next, the current day date is substituted into the variable X (step S308).
Next, from the lot group rearranged in step S303, the lot with the highest allocation order is set as an allocation process target (hereinafter referred to as “target lot”), and the number of stocks is substituted into the variable Y (step S309). .
Next, the warehouse entry date for the target lot is initialized as unset (step S310).

次に、全ての流品可能ロットへの割付処理が完了、あるいは、倉入計画の全ての日付について処理されたか否かを判定する(ステップS311)。
ここで、割付処理がなされていないロットが存在する場合、または倉入計画の中で未処理の日付が存在する場合にはステップS312へ進む。
これに対し、全ての流品可能ロットへの割付処理が完了、あるいは、倉入計画の全ての日付について処理済と判定した場合には、ステップS323へ進む。
Next, it is determined whether or not the allocation process to all the miscible lots has been completed or the process has been performed for all dates in the warehouse plan (step S311).
Here, if there is a lot that has not been assigned, or if there is an unprocessed date in the warehouse plan, the process proceeds to step S312.
On the other hand, if it is determined that the allocation process to all the miscible lots has been completed, or that all dates in the warehouse plan have been processed, the process proceeds to step S323.

ステップS312においては、倉入計画数(X)が0より大きいか否かを判定する。
ここで、倉入計画数(X)が0より多い場合にはステップS313へ進む。これに対し、倉入計画数(X)が0の場合には、ステップS322へ進む。
In step S312, it is determined whether or not the number of planned stores (X) is greater than zero.
Here, if the number of planned entrances (X) is greater than 0, the process proceeds to step S313. On the other hand, if the number of planned stores (X) is 0, the process proceeds to step S322.

ステップS313においては、対象ロットに倉入対象日が設定されているか否かを判定する。
ここで、倉入対象日が設定されていない場合には、変数Xに格納されている日付を対象ロットの倉入対象日として設定し(ステップS314)、ステップS315へ進む。
これに対し、倉入対象日が設定済みの場合(各日付の必要数に応じて割付処理を行った結果、同一ロットで倉入予定日が異なった場合)にはステップS315へ進む。
In step S313, it is determined whether or not the date for entering the warehouse is set for the target lot.
Here, if the target date for storage is not set, the date stored in the variable X is set as the target date for storage of the target lot (step S314), and the process proceeds to step S315.
On the other hand, when the date for entering the warehouse has been set (when the planned date for entering the warehouse is different for the same lot as a result of the allocation process according to the required number of each date), the process proceeds to step S315.

ステップS315においては、変数Yに格納された在庫数が倉入計画数(X)より多いか否かを判定する。
ここで、変数Yに格納された在庫数が倉入計画数(X)より多い場合には、変数Yから倉入計画数(X)を差し引いた数を変数Yに代入し(ステップS316)、ステップS317へ進む。
これに対し、変数Yに格納された在庫数が倉入計画数(X)以下の場合には、ステップS318へ進む。
In step S315, it is determined whether or not the number of stocks stored in the variable Y is larger than the planned number of stores (X).
Here, when the number of stocks stored in the variable Y is larger than the number of planned stores (X), the number obtained by subtracting the number of planned stores (X) from the variable Y is substituted into the variable Y (step S316), The process proceeds to step S317.
On the other hand, if the number of stocks stored in the variable Y is equal to or less than the planned number of stores (X), the process proceeds to step S318.

ステップS317においては、変数Xに格納された日付における必要数について割付処理が完了したものとして、その翌日日付(X+1)を変数Xに代入し、変数Yに格納されている対象ロットの残りの在庫についての倉入予定日を設定するためにステップS311へ戻る。   In step S317, assuming that the allocation process has been completed for the required number of dates stored in variable X, the next day date (X + 1) is substituted into variable X, and the remaining inventory of the target lot stored in variable Y The process returns to step S311 in order to set the expected date of entering the warehouse.

ステップS318においては、変数Yに格納された在庫数が倉入計画数(X)より少ないか否かを判定する。
ここで、変数Yに格納された在庫数が倉入計画数(X)より少ない場合には、倉入計画数から変数Yに格納されている在庫数を差し引いて倉入計画数(X)へ代入し(ステップS319)、ステップS321へ進む。
これに対し、変数Yに格納された在庫数が倉入計画数(X)と等しい場合には、変数Xに格納された日付の翌日日付(X+1)を割付処理の対象日として変数Xに代入し(ステップS320)、ステップS321へ進む。
In step S318, it is determined whether or not the number of stocks stored in the variable Y is smaller than the planned number of stores (X).
Here, when the number of stocks stored in the variable Y is smaller than the number of planned stores (X), the number of stocks stored in the variable Y is subtracted from the number of stored plans to the number of planned stores (X). Substitution is performed (step S319), and the process proceeds to step S321.
On the other hand, when the number of stocks stored in the variable Y is equal to the number of planned stores (X), the next day date (X + 1) of the date stored in the variable X is assigned to the variable X as the target date of the allocation process. (Step S320), the process proceeds to step S321.

ステップS321においては、優先順位が次のロットを対象ロットとしてその在庫数を変数Yに代入し、対象ロットに対する割り当てを行うためにステップS311へ戻る。
ステップS322においては、変数Xに格納された日付の翌日(X+1)を割付処理の対象日として変数Xに代入し、ステップS311へ戻る。
ステップS323においては、倉入対象日が設定済みのロットに算出した倉入対象区分を設定して処理を終了する。
In step S321, the next lot in the priority order is set as the target lot, the stock quantity is substituted into the variable Y, and the process returns to step S311 in order to perform allocation to the target lot.
In step S322, the next day (X + 1) of the date stored in the variable X is assigned to the variable X as the target date of the allocation process, and the process returns to step S311.
In step S323, the calculated storage target classification is set for the lot for which the storage target date has been set, and the process ends.

図5は、ロットの新規投入処理の具体例を示すフローチャートである。
先ず、月初から投入時点までの倉入実績を取得する(ステップS501)。
次に、ロット在庫情報テーブル142から流品ロットの在庫数を取得する(ステップS502)。
次に、倉入計画テーブル143から当月以降の倉入計画取得する(ステップS503)。
次に、倉入実績テーブル144から取得される投入時点での倉入実績数と当日倉入数から前日までの倉入実績を求め、これを前日までの倉入計画と比較し、その差分から当日以降の倉入計画を補正する(ステップS504)。
FIG. 5 is a flowchart showing a specific example of a new lot input process.
First, the warehouse entry record from the beginning of the month to the time of introduction is acquired (step S501).
Next, the number of stocks of the luxury lot is acquired from the lot stock information table 142 (step S502).
Next, a warehouse entry plan for the current month and after is obtained from the warehouse entry plan table 143 (step S503).
Next, the number of warehouse entries at the time of entry obtained from the warehouse entry table 144 and the number of warehouse entries from the previous day to the previous day are obtained, and this is compared with the previous day's warehouse entry plan. The warehouse entry plan after that day is corrected (step S504).

次に、仕掛済の在庫数を補正された当日以降の倉入計画に当てはめる(ステップS505)。
次に、未引き当てとなる倉入対象日を取得し、投入分の倉入対象日とする(ステップS506)。
Next, the in-process inventory quantity is applied to the warehouse entry plan after the corrected day (step S505).
Next, an unassigned warehouse entry date is acquired and set as an input warehouse entry date (step S506).

次に、新規投入分に対して倉入対象日が設定されたか否かを判定する(ステップS507)。
ここで、倉入対象日が設定されている場合には、新規投入するロットの部品数を補正後の倉入計画に当てはめ、投入するロットに対して倉入対象日および倉入対象区分を設定し(ステップS508)、処理を終了する。
これに対し、倉入対象日が設定されていない場合、すなわち、新規投入したロットが必要な数量として割付けられていない場合には、他の倉入対象区分に影響を与えない値を倉入対象区分として設定し(ステップS509)、処理を終了する。
Next, it is determined whether or not the warehouse entry date has been set for the new entry (step S507).
Here, if the target date for storage is set, the number of parts in the newly input lot is applied to the corrected storage plan, and the target date and the target category are set for the input lot. (Step S508), and the process ends.
On the other hand, if the target date is not set, that is, if the newly entered lot is not assigned as the required quantity, the value that does not affect other target items It sets as a division (step S509), and ends processing.

ロットの新規投入時に当日割付と異なるアルゴリズムを用いることで、仕掛済みのロットに対して割付を再度行う必要がない。すなわち、新規投入の場合は、すでに投入されているロットについては何も処理する必要はなく、新規に投入するロットについてのみ割付ける。   By using an algorithm different from the allocation on the day when a lot is newly introduced, it is not necessary to allocate the already-processed lot again. That is, in the case of a new input, it is not necessary to process anything for a lot that has already been input, and only a lot that is newly input is assigned.

上記のようにロットの優先順位が設定され、優先ロット表示装置2に表示されるので、製造管理者は優先的に処理すべきロットを容易に把握でき、操作担当者に的確に指示することができる。また、優先ロット情報を要求してから表示されるまでの時間も短時間で済む。更に、各ロットに対する割付処理を毎日行うことで、作業の進捗に柔軟に対応し、日々の倉入計画に対する倉入作業の遂行を支援することができる。   Since the priority order of lots is set and displayed on the priority lot display device 2 as described above, the manufacturing manager can easily grasp the lots to be preferentially processed and can instruct the person in charge accurately. it can. Also, it takes a short time to display the priority lot information until it is displayed. Furthermore, by performing the allocation process for each lot every day, it is possible to flexibly respond to the progress of the work, and to support the execution of the storehouse work for the daily storehouse plan.

尚、本発明は上記実施形態に限定されるものではなく、本発明の技術的思想の範囲内で種々変形して実施可能である。例えば、上記実施形態では、日々の計画を基にしているが、月計画にも適応可能である。また、要求単位を変えることで、ウェハや液晶パネルなどの管理にも使用可能である。また、倉入対象日や倉入対象区分を優先ロット情報テーブル145に記憶してから優先ロット表示装置2で表示する構成としたが、割付処理の中で優先ロット表示装置2へ出力する構成としてもよい。   The present invention is not limited to the above-described embodiment, and various modifications can be made within the scope of the technical idea of the present invention. For example, in the above embodiment, the daily plan is used as a basis, but the present invention can also be applied to a monthly plan. It can also be used to manage wafers and liquid crystal panels by changing the required units. In addition, the store entry date and store entry classification are stored in the priority lot information table 145 and then displayed on the priority lot display device 2. However, as a configuration for output to the priority lot display device 2 during the allocation process. Also good.

本発明の一実施形態に係る工程進捗管理システムの全体構成例を示す図。The figure which shows the example of whole structure of the process progress management system which concerns on one Embodiment of this invention. 本発明の一実施形態に係る優先度決定プログラム131の処理の概要を説明する機能ブロック図。The functional block diagram explaining the outline | summary of the process of the priority determination program 131 which concerns on one Embodiment of this invention. 本発明の一実施形態に係るロット優先度決定処理の具体例を示すフローチャート。The flowchart which shows the specific example of the lot priority determination process which concerns on one Embodiment of this invention. 本発明の一実施形態に係るロット優先度決定処理の具体例を示すフローチャート。The flowchart which shows the specific example of the lot priority determination process which concerns on one Embodiment of this invention. 本発明の一実施形態に係る新規ロット投入時の処理の具体例を示すフローチャート。The flowchart which shows the specific example of the process at the time of new lot injection | pouring which concerns on one Embodiment of this invention.

符号の説明Explanation of symbols

1…優先ロット決定装置、2…優先ロット表示装置、
11…CPU、12…主記憶部、13…補助記憶部、
14…データベース部、
21…入力部、22…表示部、
131…優先度決定プログラム、
141…製造フロー情報テーブル、142…ロット在庫情報テーブル、
143…倉入計画テーブル、144…倉入実績テーブル、
145…優先ロット情報テーブル。
1 ... priority lot determination device, 2 ... priority lot display device,
11 ... CPU, 12 ... main storage unit, 13 ... auxiliary storage unit,
14 ... Database section
21 ... Input unit, 22 ... Display unit,
131 ... priority determination program,
141 ... Manufacturing flow information table, 142 ... Lot inventory information table,
143 ... Kurairi plan table, 144 ... Kurairi results table,
145 ... Priority lot information table.

Claims (4)

ロット単位で管理される製品の製造工程に仕掛かる複数のロットに対して製造作業における優先順位を決定する優先ロット決定装置と、
この優先ロット決定装置に接続され、前記決定された優先順位を取得し、表示する優先ロット表示装置と、からなり、
前記優先ロット決定装置が、
前記製品の製造に係る工程順序、前記ロットの仕掛工程、前記ロットに含まれる前記製品の数量、前記製品の各日付における倉入計画数および倉入実績数を記憶するデータベース手段と、
このデータベース手段に記憶される前記工程順序と仕掛済のロットの仕掛工程とを比較する比較手段と、
この比較手段による比較結果に基づいて前記仕掛済のロット群を前記仕掛工程が最終工程から近い順に並べ替え、前記優先順位の割付順を求める並び替え手段と、
前記データベース手段に記憶される前記倉入計画数と前記倉入実績数との差分に基づいて各日付における倉入必要数を算出する必要数算出手段と、
前記割付順に従って各ロットに含まれる前記製品の数量を各日付における前記倉入必要数に対して割付け、前記割付けられた日付に基づいて前記ロットの製造作業における優先順位を決定する優先順位決定手段と、
を有することを特徴とする工程進捗管理システム。
A priority lot determination device that determines the priority in manufacturing operations for a plurality of lots in the manufacturing process of products managed in lot units;
A priority lot display device connected to the priority lot determination device to obtain and display the determined priority order;
The priority lot determination device is
A database means for storing a process sequence relating to the manufacture of the product, a work-in-process of the lot, a quantity of the product included in the lot, a planned number of purchases and a number of actual purchases in each date of the product;
A comparison means for comparing the process sequence stored in the database means with the in-process process of the in-process lot;
Based on the comparison result by the comparison means, the in-process lot group is rearranged in the order in which the in-process process is closer to the final process, and the rearrangement means for obtaining the priority order assignment;
Necessary number calculating means for calculating the required number of warehouse entries on each date based on the difference between the number of planned warehouse entries and the actual number of warehouse entries stored in the database means;
Priority determining means for allocating the quantity of the product included in each lot according to the allocation order to the required number of warehouses on each date, and determining the priority in the manufacturing operation of the lot based on the allocated date When,
A process progress management system characterized by comprising:
前記優先順位は、前記割付けられた日付を倉入対象日とし、この倉入対象日から所定の演算によって求められることを特徴とする請求項1記載の工程進捗管理システム。   2. The process progress management system according to claim 1, wherein the priority is determined by a predetermined calculation from the assigned date as the date to be assigned to the store. ロット単位で管理される製品の製造工程に仕掛かる複数の前記ロットに対し、前記製品の情報を記憶するデータベースを備えるコンピュータが製造作業における優先順位を決定する工程進捗管理方法であって、
前記データベースから前記製品の製造における工程順序を取得する工程順序取得ステップと、
前記データベースから前記製品に係るロットの仕掛工程、前記ロットに含まれる前記製品の数量を含むロット在庫情報を取得するロット在庫情報取得ステップと、
前記取得された仕掛工程と前記工程順序とを比較し、仕掛済の前記ロット群を前記仕掛工程が最終工程から近い順に並べ替え、前記優先順位の割付順を求める並び替えステップと、
前記データベースから前記製品の各日付における倉入計画数を取得する倉入計画取得ステップと、
前記データベースから前記製品の各日付における倉入実績数を取得する倉入実績取得ステップと、
前記取得された倉入実績数と倉入計画数との差分に基づいて各日付における倉入必要数を算出する必要数算出ステップと、
前記割付順に従って各ロットに含まれる前記製品の数量を前記各日付における倉入必要数に対して割付け、前記割付けられた日付に基づいて前記ロットの製造作業における優先順位を決定する優先順位決定ステップと、
前記決定された優先順位を表示する優先ロット表示ステップと、
を有することを特徴とする工程進捗管理方法。
A process progress management method in which a computer including a database for storing information on the product determines a priority order in a manufacturing operation for a plurality of lots set in a manufacturing process of a product managed in lot units,
A process order obtaining step for obtaining a process order in manufacturing the product from the database;
Lot inventory information acquisition step of acquiring lot inventory information including the in-process of the lot related to the product from the database, the quantity of the product included in the lot,
Comparing the acquired in-process with the process order, rearranging the in-process lot group in the order in which the in-process is closer to the final process, and obtaining the priority order,
Kurashiri plan acquisition step for obtaining the number of Kurashiri plans for each date of the product from the database;
A storehouse record acquisition step for acquiring the storehouse record number for each date of the product from the database;
A required number calculating step of calculating the required number of warehouses for each date based on the difference between the number of actual warehouses acquired and the number of planned warehouses;
A priority determination step of allocating the quantity of the product included in each lot according to the allocation order to the required number of warehouses on each date, and determining the priority in the manufacturing operation of the lot based on the allocated date When,
A priority lot display step for displaying the determined priority order;
A process progress management method characterized by comprising:
前記優先順位は、前記割付けられた日付を倉入対象日とし、この倉入対象日から所定の演算によって求められることを特徴とする請求項3記載の工程進捗管理方法。   4. The process progress management method according to claim 3, wherein the priority is determined by a predetermined calculation from the assigned date as the date to which the assigned date is assigned.
JP2007117617A 2007-04-26 2007-04-26 Process progress management system and process progress management method Pending JP2008276412A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007117617A JP2008276412A (en) 2007-04-26 2007-04-26 Process progress management system and process progress management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007117617A JP2008276412A (en) 2007-04-26 2007-04-26 Process progress management system and process progress management method

Publications (1)

Publication Number Publication Date
JP2008276412A true JP2008276412A (en) 2008-11-13

Family

ID=40054302

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007117617A Pending JP2008276412A (en) 2007-04-26 2007-04-26 Process progress management system and process progress management method

Country Status (1)

Country Link
JP (1) JP2008276412A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019229880A1 (en) * 2018-05-30 2019-12-05 ヤマハ発動機株式会社 Component replenishment management system and component mounting system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019229880A1 (en) * 2018-05-30 2019-12-05 ヤマハ発動機株式会社 Component replenishment management system and component mounting system
JPWO2019229880A1 (en) * 2018-05-30 2021-04-01 ヤマハ発動機株式会社 Parts supply management system and parts mounting system
US11653486B2 (en) 2018-05-30 2023-05-16 Yamaha Hatsudoki Kabushiki Kaisha Component replenishment management system and component mounting system

Similar Documents

Publication Publication Date Title
US20070073575A1 (en) Progress management system
JP2008299762A (en) Production management program
US8494893B2 (en) Production plan making program, device, and method
WO2017203598A1 (en) Work assistance system, allocation system, and allocation method
JPS59214964A (en) Conversational scheduling system
JP2007213141A (en) Personnel distribution system, personnel distribution method, personnel distribution program, and recording medium with the program recorded thereon
JPH05143613A (en) Production planning system
JP6214835B2 (en) Work guidance assignment system and work guidance assignment method
JP2008276412A (en) Process progress management system and process progress management method
JP2005301653A (en) Manufacturing process management method
JP2017134619A (en) Work shift creation support system and work shift creation support program
JP6005535B2 (en) Production plan creation device, production plan creation method, and production plan creation program
JP5359312B2 (en) Manufacturing line process management method and process management system
JP4945010B1 (en) Shelf management system and shelf management program in semiconductor production line
JP2007128368A (en) Production plan drafting apparatus
TWI784311B (en) Management device, management system, and management program
JPH1086044A (en) Worker&#39;s discretion utilization schedule planning method and device therefor
JP4897097B1 (en) Shelf management system and shelf management program in semiconductor production line
US20220335391A1 (en) Management apparatus, management system, and program
JP2009230382A (en) Gantt chart display method, gantt chart display program and gantt chart display
JP2006039624A (en) Demand-and-supply adjusting program and device
JPH0966442A (en) Process control device
JPH08147366A (en) Production planning device
TWI322967B (en)
JP2510774B2 (en) Production planning method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090820

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090825

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20100105