JPH06156931A - Main rope passing method for elevator - Google Patents

Main rope passing method for elevator

Info

Publication number
JPH06156931A
JPH06156931A JP30900692A JP30900692A JPH06156931A JP H06156931 A JPH06156931 A JP H06156931A JP 30900692 A JP30900692 A JP 30900692A JP 30900692 A JP30900692 A JP 30900692A JP H06156931 A JPH06156931 A JP H06156931A
Authority
JP
Japan
Prior art keywords
main rope
hoistway
sheave
rope
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP30900692A
Other languages
Japanese (ja)
Inventor
Nagamichi Shigetomi
修廸 繁富
Yukio Ota
幸男 太田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Engineering and Service Co Ltd
Hitachi Building Systems Engineering Co Ltd
Original Assignee
Hitachi Building Systems Engineering and Service Co Ltd
Hitachi Building Systems Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Engineering and Service Co Ltd, Hitachi Building Systems Engineering Co Ltd filed Critical Hitachi Building Systems Engineering and Service Co Ltd
Priority to JP30900692A priority Critical patent/JPH06156931A/en
Publication of JPH06156931A publication Critical patent/JPH06156931A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PURPOSE:To provide the main rope passing method for elevator capable of performing main rope passing work without necessitating troublesome work and sliding of the main rope into the groove of a sheave. CONSTITUTION:After a car frame 10 and a counterbalance weight 5 are assembled into the bottom of a hoistway 1, one end of a hoisting rope 6 is connected to the counterbalance weight 5, the other end of the hoisting rope 6 is wound up by a winch 9 to hoist the counterbalance weight 5 to the top of the hoistway 1, and the main rope 4 is stretched between the car frame 10 and the counterbalance weight 5 through a sheave 3 of a winch. By this, even a worker who is not familiar relatively with a work can perform the work. Thus wear on the groove of the sheave when the work is performed, can be prevented.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はエレベータの据付時にか
ご枠およびつり合いおもり間に主ロープを掛けるエレベ
ータの主ロープ掛け方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of hanging a main rope between an elevator car and a counterweight when the elevator is installed.

【0002】[0002]

【従来の技術】エレベータの据付に際しては、昇降路内
にあって一端につり合いおもりを連結した主ロープを、
昇降路上端部の機械室に配設された巻上機のシーブに巻
回し、主ロープの他端を昇降路下端部に配されたかごに
乗り込んで、前記主ロープとかごとを連結する主ロープ
掛け作業が必要である。
2. Description of the Related Art When installing an elevator, install a main rope in the hoistway that has a counterweight attached to one end.
A main rope that winds around a sheave of a hoisting machine installed in the machine room at the upper end of the hoistway and rides the other end of the main rope into a car arranged at the lower end of the hoistway to connect the main rope to the car. It requires hanging work.

【0003】図2は従来の主ロープ掛け方法を示す縦断
面図である。
FIG. 2 is a longitudinal sectional view showing a conventional main rope hanging method.

【0004】従来の主ロープ掛け方法では、昇降路1上
端部の機械室2に配設される巻上機のシーブ3に主ロー
プ4が巻回されるとともに、この主ロープ4の一端に
は、昇降路1の下部で組込まれたつり合いおもり5が連
結されている。そして、つり合いおもり5には吊上げロ
ープ6の一端が連結されており、この吊上げロープ6は
昇降路1の上方に向かって延長され、かつ機械室2に設
けられているそらせ車7に巻回されて昇降路1の下方に
延長されている。また、このように昇降路1内の下方に
延長された吊上げロープ6の他端は、昇降路1内に設け
られているそらせ車8に巻回されて昇降路1外に導出さ
れ、ウインチ9に巻きかけられる。このウインチ9は昇
降路1の下部で組込まれたかご枠10の上部に組み立て
られる作業床11と同等の高さ位置に据え付けられてい
る。また、シーブ3に巻回された主ロープ4の他端に
は、この主ロープ4をかご枠10に連結させるおもり1
2が取り付けられている。
In the conventional main rope hanging method, the main rope 4 is wound around the sheave 3 of the hoisting machine disposed in the machine room 2 at the upper end of the hoistway 1, and one end of the main rope 4 is attached. A balance weight 5 incorporated in the lower part of the hoistway 1 is connected. One end of a hoisting rope 6 is connected to the counterweight 5, and the hoisting rope 6 extends toward the upper part of the hoistway 1 and is wound around a deflecting wheel 7 provided in the machine room 2. And extends below the hoistway 1. Further, the other end of the lifting rope 6 extended downward in the hoistway 1 in this manner is wound around a deflecting wheel 8 provided in the hoistway 1 and led out of the hoistway 1 to winch 9. Wrapped around. The winch 9 is installed at the same height position as the work floor 11 assembled on the lower part of the hoistway 1 and assembled on the upper part of the car frame 10. A weight 1 for connecting the main rope 4 to the car frame 10 is provided at the other end of the main rope 4 wound around the sheave 3.
2 is attached.

【0005】従来の主ロープ掛け方法によって行われる
主ロープ掛け作業は、ウインチ9の操作を行う第1の作
業者と、機械室2内にて主ロープ4の送り込みを行う第
2の作業者とを要する。まず、第1の作業者がウインチ
9を操作し吊上ロープ6の他端を巻取ると、吊上ロープ
6を介してつり合いおもり5が吊上げられ、このつり合
いおもり5の吊上げに伴いシーブ3に巻回されている主
ロープ4がたるむ。このとき第2の作業者はつり合いお
もり5の移動距離に対応して主ロープ4をかご枠10へ
向けて送り込むようになっている。
The main rope hanging work performed by the conventional main rope hanging method is performed by a first operator who operates the winch 9 and a second operator who sends the main rope 4 in the machine room 2. Requires. First, when the first operator operates the winch 9 and winds the other end of the hoisting rope 6, the counterweight 5 is hoisted through the hoisting rope 6, and the sheave 3 is lifted by the hoisting of the counterweight 5. The main rope 4 wound around is slack. At this time, the second operator sends the main rope 4 toward the car frame 10 in accordance with the moving distance of the counterweight 5.

【0006】このように、従来の主ロープ掛け方法で
は、第1の作業者によるウインチ9の操作と、第2の作
業者による主ロープ4の送り込み作業とのタイミングを
合わせることにより、主ロープ4の他端側を昇降路1内
で昇降路機器に衝突させたり絡ませたりすることなくか
ご枠10に近づけ、主ロープ4をかご枠10へ連結させ
るようになっていた。
As described above, in the conventional main rope hanging method, the timing of the operation of the winch 9 by the first operator and the operation of feeding the main rope 4 by the second operator are matched to each other. The main rope 4 is connected to the car frame 10 by making the other end side of the car rope 10 approach the car frame 10 in the hoistway 1 without colliding with or entwining with the hoistway device.

【0007】[0007]

【発明が解決しようとする課題】ところで、上述した従
来のエレベータの主ロープ掛け方法では、第1の作業者
によるウインチ9の操作と、第2の作業者による主ロー
プ4の送り込み作業とのタイミングを合わせる必要があ
り、作業が複雑で作業者の熟練を要するという問題があ
った。また、主ロープ4の送り込み作業の際に、主ロー
プ4はシーブ3の溝内を摺接しながら移動するため、シ
ーブ3の溝に摩耗を生じさせるという問題もあった。
By the way, in the above-described conventional elevator main rope hanging method, the timing between the operation of the winch 9 by the first operator and the feeding operation of the main rope 4 by the second operator. However, there is a problem that the work is complicated and requires skill of the operator. In addition, when the main rope 4 is fed, the main rope 4 moves while sliding in the groove of the sheave 3, which causes a problem that the groove of the sheave 3 is worn.

【0008】本発明はこのような従来技術における実情
に鑑みてなされたもので、その目的は、煩雑な作業およ
び主ロープをシーブの溝内に摺動させることを要せずに
主ロープ掛け作業を行うことのできるエレベータの主ロ
ープ掛け方法を提供することにある。
The present invention has been made in view of the actual situation in the prior art as described above, and the purpose thereof is to carry out the main rope hanging work without requiring complicated work and sliding the main rope in the groove of the sheave. The purpose of the present invention is to provide a method for hanging a main rope of an elevator that can perform the above.

【0009】[0009]

【課題を解決するための手段】この目的を達成するため
に本発明は、昇降路内に設けられるかご枠およびつり合
いおもり間に巻上機のシーブを介して主ロープを掛ける
エレベータの主ロープ掛け方法において、昇降路の下部
に前記かご枠およびつり合いおもりを組込んだ後、この
つり合いおもりに吊上げロープの一端を連結して、この
吊上げロープの他端をウインチで巻き取ることにより前
記つり合いおもりを前記昇降路の上部まで吊上げ、次い
で、前記主ロープを前記シーブを介して前記かご枠およ
びつり合いおもり間に掛けるようになっている。
To achieve this object, the present invention provides a main rope hook for an elevator in which a main rope is hung between a car frame and a counterweight provided in a hoistway through a sheave of a hoist. In the method, after incorporating the car frame and the counterweight in the lower part of the hoistway, one end of the lifting rope is connected to the counterweight, and the other end of the lifting rope is wound by a winch to remove the counterweight. The main rope is hung up to the upper part of the hoistway, and then the main rope is hung between the car frame and the counterweight through the sheave.

【0010】[0010]

【作用】本発明は上記のように、昇降路の下部にかご枠
およびつり合いおもりを組込んだ後、このつり合いおも
りに吊上げロープの一端を連結するとともに、この吊上
げロープの他端に連結されるウインチを操作して、前記
吊上げロープを巻き取ることにより前記つり合いおもり
を前記昇降路の上部まで吊上げ、次いで、主ロープを巻
上機のシーブに巻き掛けるとともに、この主ロープの端
部を前記かご枠およびつり合いおもりのそれぞれに掛け
るようになっている。これによって、主ロープの送り込
み作業のように煩雑な作業を要することなく主ロープ掛
け作業を行うことができる。また、前記つり合いおもり
を前記昇降路の上部まで吊上げて、前記主ロープの端部
が前記かご枠および前記つり合いおもりのそれぞれに届
く位置としてから前記主ロープを前記シーブに巻きかけ
るので、前記主ロープをシーブ溝に摺動させることを要
せずに主ロープ掛け作業を行うことができる。
As described above, according to the present invention, after the car frame and the counterweight are incorporated in the lower part of the hoistway, one end of the hoisting rope is connected to the counterweight and the other end of the hoisting rope is connected. The winch is operated to wind up the hoisting rope to hoist the counterweight to the upper part of the hoistway, and then the main rope is wound around the sheave of the hoist, and the end of the main rope is moved to the car. It is designed to be hung on each of the frame and the counterweight. As a result, the main rope hanging operation can be performed without the need for complicated operations such as the main rope feeding operation. Further, since the balance weight is hung up to the upper part of the hoistway, and the main rope is wound around the sheave after the end of the main rope reaches the car frame and the balance weight, respectively, the main rope is wound around the sheave. The main rope hooking work can be performed without the need to slide the sheave into the sheave groove.

【0011】[0011]

【実施例】以下、本発明のエレベータの主ロープ掛け方
法の実施例を図に基づいて説明する。図1は本発明のエ
レベータの主ロープ掛け方法の一実施例を示す縦断面図
である。なお、前述した図2に示すものと同等のものに
は同一符号を付してある。すなわち、1は昇降路、2は
機械室、3は巻上機のシーブ、4は主ロープ、5はつり
合いおもり、6は吊上げロープ、7、8はそらせ車、9
はウインチ、10はかご枠、11は作業床である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method for hanging a main rope of an elevator according to the present invention will be described below with reference to the drawings. FIG. 1 is a vertical cross-sectional view showing an embodiment of a method of hanging an elevator main rope according to the present invention. The same components as those shown in FIG. 2 described above are designated by the same reference numerals. That is, 1 is a hoistway, 2 is a machine room, 3 is a sheave of a hoisting machine, 4 is a main rope, 5 is a counterweight, 6 is a lifting rope, 7 and 8 are deflector wheels, 9
Is a winch, 10 is a car frame, and 11 is a work floor.

【0012】本実施例の主ロープ掛け方法では図1に示
すように、昇降路壁1aに固設されたブラケット13と
最上階の床14との間に掛け渡された足場15が備えら
れている。
In the main rope hanging method of this embodiment, as shown in FIG. 1, a scaffold 15 is provided between a bracket 13 fixed to the hoistway wall 1a and a floor 14 on the uppermost floor. There is.

【0013】この実施例にあっては、昇降路1の下部に
かご枠10およびつり合いおもり5を組込んだ後、この
つり合いおもり5に吊上げロープ6の一端を連結する。
次いで、作業者はウインチ9を操作して吊上げロープ6
を巻き取ることにより、つり合いおもり5を図1の点線
で示す位置から実線で示す昇降路1の上部まで吊上げ、
この後、足場15をブラケット13と最上階の床14と
の間に掛け渡す。そして、機械室2にて主ロープ4の中
間部をシーブ3に巻きかけ、また、主ロープ4の一端を
かご枠10側へ、他端をつり合いおもり5側へ落とし、
次いで、昇降路1の下部にて主ロープ4の一端をかご枠
10に連結するとともに、足場15上にて主ロープ4の
他端をつり合いおもり5に連結するようになっている。
その後、足場15を取外して主ロープ掛け作業を終了す
る。
In this embodiment, after the car frame 10 and the counterweight 5 are installed in the lower part of the hoistway 1, one end of the lifting rope 6 is connected to the counterweight 5.
Next, the operator operates the winch 9 to lift the lifting rope 6.
By winding up, the balance weight 5 is lifted from the position shown by the dotted line in FIG. 1 to the upper part of the hoistway 1 shown by the solid line,
After this, the scaffold 15 is hung between the bracket 13 and the floor 14 on the top floor. Then, in the machine room 2, the middle portion of the main rope 4 is wrapped around the sheave 3, and one end of the main rope 4 is dropped to the car frame 10 side and the other end is dropped to the counterweight 5 side,
Next, one end of the main rope 4 is connected to the car frame 10 at the lower part of the hoistway 1, and the other end of the main rope 4 is connected to the counterweight 5 on the scaffold 15.
After that, the scaffold 15 is removed and the main rope hanging work is completed.

【0014】このように構成した実施例では、主ロープ
の送り込み作業のように煩雑な作業を要することなく主
ロープ掛け作業を行うことができる。また、つり合いお
もり5を昇降路1の上部まで吊上げて、主ロープ4の端
部がかご枠10およびつり合いおもり5のそれぞれに届
く位置としてから主ロープ4をシーブ3に巻きかけるの
で、主ロープ4をシーブ3の溝に摺動させることを要せ
ずに主ロープ掛け作業を行うことができる。
In the embodiment constructed as described above, the main rope hanging work can be performed without requiring a complicated work such as a feeding work of the main rope. In addition, since the counterweight 5 is hung up to the upper part of the hoistway 1 and the ends of the main rope 4 reach the car frame 10 and the counterweight 5, respectively, the main rope 4 is wound around the sheave 3. It is possible to carry out the main rope hooking work without the need to slide the groove into the groove of the sheave 3.

【0015】[0015]

【発明の効果】本発明は以上のように構成したので、煩
雑な作業を要することなく主ロープ掛け作業を行うこと
ができ、これによって、比較的作業に熟練していない作
業者でも主ロープ掛け作業を行うことができる。また、
主ロープをシーブの溝内に摺動させることを要せずに主
ロープ掛け作業を行うことができ、したがって、この主
ロープ掛け作業の際に前記シーブの溝に摩耗を生じさせ
ることを防止することができるという効果がある。
Since the present invention is constructed as described above, it is possible to carry out the main rope hanging work without requiring a complicated work, whereby an operator who is relatively unskilled in the work can carry out the main rope hanging work. You can do the work. Also,
It is possible to carry out the main rope hanging work without requiring the main rope to slide in the groove of the sheave, and thus to prevent the groove of the sheave from being worn during the main rope hanging work. The effect is that you can.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明のエレベータの主ロープ掛け方法の一実
施例を示す縦断面図である。
FIG. 1 is a vertical cross-sectional view showing an example of a method of hanging a main rope of an elevator according to the present invention.

【図2】従来のエレベータの主ロープ掛け方法を示す縦
断面図である。
FIG. 2 is a vertical cross-sectional view showing a conventional method of hanging a main rope of an elevator.

【符号の説明】[Explanation of symbols]

1 昇降路 3 シーブ 4 主ロープ 5 つり合いおもり 6 吊上げロープ 9 ウインチ 10 かご枠 1 hoistway 3 sheave 4 main rope 5 counterweight 6 lifting rope 9 winch 10 car frame

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 昇降路内に設けられるかご枠およびつり
合いおもり間に巻上機のシーブを介して主ロープを掛け
るエレベータの主ロープ掛け方法において、昇降路の下
部に前記かご枠およびつり合いおもりを組込んだ後、こ
のつり合いおもりに吊上げロープの一端を連結して、こ
の吊上げロープの他端をウインチで巻き取ることにより
前記つり合いおもりを前記昇降路の上部まで吊上げ、次
いで、前記主ロープを前記シーブを介して前記かご枠お
よびつり合いおもり間に掛けることを特徴とするエレベ
ータの主ロープ掛け方法。
1. A method of hanging a main rope between a car frame and a counterweight provided in a hoistway via a sheave of a hoist, wherein the car frame and the counterweight are provided at a lower part of the hoistway. After assembling, one end of the hoisting rope is connected to the counterweight, and the other end of the hoisting rope is wound by a winch to hoist the counterweight to the upper part of the hoistway, and then the main rope is A method for hanging a main rope of an elevator, characterized in that the rope is hung between the car frame and the counterweight via a sheave.
JP30900692A 1992-11-18 1992-11-18 Main rope passing method for elevator Pending JPH06156931A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30900692A JPH06156931A (en) 1992-11-18 1992-11-18 Main rope passing method for elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30900692A JPH06156931A (en) 1992-11-18 1992-11-18 Main rope passing method for elevator

Publications (1)

Publication Number Publication Date
JPH06156931A true JPH06156931A (en) 1994-06-03

Family

ID=17987770

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30900692A Pending JPH06156931A (en) 1992-11-18 1992-11-18 Main rope passing method for elevator

Country Status (1)

Country Link
JP (1) JPH06156931A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007060713A1 (en) * 2005-11-22 2007-05-31 Mitsubishi Denki Kabushiki Kaisha Hoist unit for elevator installation, and rope mounting method for elevator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007060713A1 (en) * 2005-11-22 2007-05-31 Mitsubishi Denki Kabushiki Kaisha Hoist unit for elevator installation, and rope mounting method for elevator
JP4810430B2 (en) * 2005-11-22 2011-11-09 三菱電機株式会社 Elevator installation hoist unit and main rope winding method of elevator

Similar Documents

Publication Publication Date Title
US8028393B2 (en) Elevator arrangement
JPWO2020035933A1 (en) How to apply elevator head extension technology
JP6750754B2 (en) Lifting elevator for construction work
WO2020035930A1 (en) Construction elevator lifting height extension method and elevator rope lowering jig
JP6611965B2 (en) Elevator installation method
JP3844944B2 (en) Demolition method of construction elevator
JPH09151053A (en) Fixing device for car of elevator
JPH06156931A (en) Main rope passing method for elevator
JP2705534B2 (en) Elevator equipment for construction
JPH09278325A (en) Construction work elevator lifting method and construction work elevator device
JPH0769559A (en) Elevator device for construction work
JPH06255944A (en) Main rope stretching method of elevator
WO2022230140A1 (en) Elevator and lifting/lowering path extension method
JPH0470235B2 (en)
JP2939064B2 (en) Elevator installation template
JPH04129981A (en) Method of installing construction for hydraulic elevator
JP2001072354A5 (en)
JPH0733355A (en) Installation method for elevator
JP4058915B2 (en) Lift equipment for elevator equipment
JP3888513B2 (en) Main rope end adjustment method for 2-to-1 roping elevator
JP2003112875A (en) Structure and method for mounting elevator compensation rope
JPH09235082A (en) Elevator modification method
JPH0672663A (en) Construction method for linking main rope of elevator
JPH0262390A (en) Main rope setting method for 2:1 roping elevator
JPH0262389A (en) Rope changing method for elevator