JPH0470235B2 - - Google Patents

Info

Publication number
JPH0470235B2
JPH0470235B2 JP9537787A JP9537787A JPH0470235B2 JP H0470235 B2 JPH0470235 B2 JP H0470235B2 JP 9537787 A JP9537787 A JP 9537787A JP 9537787 A JP9537787 A JP 9537787A JP H0470235 B2 JPH0470235 B2 JP H0470235B2
Authority
JP
Japan
Prior art keywords
rope
main rope
lifting
temporary
hoistway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP9537787A
Other languages
Japanese (ja)
Other versions
JPS63262385A (en
Inventor
Shoichi Oosako
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Elevator Engineering and Service Co Ltd
Original Assignee
Hitachi Elevator Engineering and Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Elevator Engineering and Service Co Ltd filed Critical Hitachi Elevator Engineering and Service Co Ltd
Priority to JP9537787A priority Critical patent/JPS63262385A/en
Publication of JPS63262385A publication Critical patent/JPS63262385A/en
Publication of JPH0470235B2 publication Critical patent/JPH0470235B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 <産業上の利用分野> 本発明はエレベータの主ロープ掛け工法、特に
エレベータの据付時における足場なし据付工法に
最適なエレベータの主ロープ掛け工法に関するも
のである。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to an elevator main rope hanging method, and particularly to an elevator main rope hanging method that is most suitable for a scaffold-less installation method during elevator installation.

<従来の技術> エレベータの据付に際しては、昇降路内におい
て一端につり合い重りを連結した主ロープを、昇
降路上端部の機械室に配設された巻上機のシーブ
に巻回し、主ロープの他端を昇降路下端部に配さ
れたかご側に送り込んで、主ロープとかごとを連
結する主ロープ掛け作業が必要である。
<Prior art> When installing an elevator, a main rope with a counterweight connected to one end in the hoistway is wound around a sheave of a hoist installed in a machine room at the end of the hoistway. It is necessary to connect the main rope to the car by feeding the other end into the car at the lower end of the hoistway.

この主ロープ掛け作業を行なう場合に、昇降路
内に足場を組むことなしにかごに対して主ロープ
を連結する工法として従来用いられている主ロー
プ掛け工法は、第2図に示すようなものであつ
た。
When performing this main rope hanging work, the main rope hanging method that has been conventionally used to connect the main rope to the car without setting up scaffolding in the hoistway is as shown in Figure 2. It was hot.

この従来の主ロープ掛け工法では、昇降路1の
上端部の機械室5に配設される巻上機のシーブ6
に主ロープ7が巻回される。この主ロープ7の一
端には、昇降路1の下端部において、つり合い重
り4が連結されている。
In this conventional main rope hanging construction method, the sheave 6 of the hoisting machine is installed in the machine room 5 at the upper end of the hoistway 1.
The main rope 7 is wound around. A counterweight 4 is connected to one end of the main rope 7 at the lower end of the hoistway 1.

一方、前述のつり合い重り4には吊り上げロー
プ11の一端が連結され、吊り上げロープ11は
昇降路1内を上方に延長され、機械室5に設けら
れているそらせ車15に巻回されて、昇降路1内
を下方に延長される。
On the other hand, one end of a lifting rope 11 is connected to the above-mentioned counterweight 4, and the lifting rope 11 is extended upward in the hoistway 1, wound around a deflection wheel 15 provided in the machine room 5, and then lifted and lowered. It is extended downward within Road 1.

このようにして昇降路1内を下方に延長された
吊り上げロープ11は、昇降路1内に設けられて
いるそらせ車16に巻回されて昇降路1外に導出
される。昇降路1外に導出された吊り上げロープ
11の他端側はウインチ10に巻き付けられる。
このウインチ10は、昇降路1の下端部に配され
るかご2の上部に組立てられる作業床3とほぼ同
一高さに据付けられている。
The lifting rope 11 thus extended downward within the hoistway 1 is wound around a deflection wheel 16 provided within the hoistway 1 and guided out of the hoistway 1. The other end of the lifting rope 11 led out of the hoistway 1 is wound around a winch 10.
This winch 10 is installed at approximately the same height as a work floor 3 assembled on top of a car 2 disposed at the lower end of the hoistway 1.

また、巻上機のシーブ6に巻回された前述せる
主ロープ7の他端には、主ロープ7をかご2に連
結させるための重り8が取り付けられている。
Further, a weight 8 for connecting the main rope 7 to the car 2 is attached to the other end of the above-mentioned main rope 7 wound around the sheave 6 of the hoist.

前述の設定現場において、ウインチ10の操作
を行なう作業者12をウインチ10のそばに配置
させ、主ロープ7の送り込みを行なう作業者13
を機械室5内に配置させる。
At the aforementioned setting site, the worker 12 who operates the winch 10 is placed near the winch 10, and the worker 13 who feeds the main rope 7.
is placed in the machine room 5.

作業者12がウインチ10を操作して吊り上げ
ロープの他端側を巻き取ると、主ロープ7の一端
側、つり合い重り4及び吊り上げロープ11の一
端側で構成される吊り上げ系が、昇降路1内を上
方に移動する。この移動によつて巻上機のシーブ
6に巻回されている主ロープ7がたるむので、機
械室5内の作業員13は、前述せる吊り上げ系の
移動距離に対応して主ロープ7を、かご2に対し
て送り込む。
When the worker 12 operates the winch 10 and winds up the other end of the lifting rope, the lifting system consisting of one end of the main rope 7, the counterweight 4, and one end of the lifting rope 11 moves into the hoistway 1. move upward. This movement causes the main rope 7 wound around the sheave 6 of the hoist to slacken, so the worker 13 in the machine room 5 moves the main rope 7 according to the distance the lifting system has moved. Feed to car 2.

このようにして、作業員12によるウインチ1
0の操作と、機械室5内の作業員13による主ロ
ープ7の送り込み操作とのタイミングを合せるこ
とにより、主ロープ7の他端を昇降路1内で他部
分に衝突させたり、他部分に絡ませたりすること
なしにかご2に近付けて、最終的には主ロープ7
をかご2と連結させることが出来る。
In this way, the winch 1 by the worker 12
0 and the feeding operation of the main rope 7 by the worker 13 inside the machine room 5, it is possible to prevent the other end of the main rope 7 from colliding with other parts in the hoistway 1, or from colliding with other parts. It is brought closer to car 2 without getting entangled, and finally the main rope 7
can be connected to car 2.

<発明が解決しようとする問題点> 前述せる従来の主ロープ掛け工法では、昇降路
1の下端部の近くでウインチ10を操作する作業
者12と、機械室5内で主ロープ7の送り込みを
する作業者13との2名の作業者が必要であつ
て、人件費が嵩む。
<Problems to be Solved by the Invention> In the conventional main rope hanging method described above, the worker 12 operates the winch 10 near the lower end of the hoistway 1, and the worker 12 operates the winch 10 near the lower end of the hoistway 1, and the main rope 7 is fed inside the machine room 5. Two workers, including worker 13, are required to perform the work, which increases personnel costs.

また、作業者12によるウインチ10の巻付け
作業と、機械室5内における作業者13による主
ロープ7の送り込み作業をタイミングを取つて同
時に行なう必要があり、作業も複雑で熟練を要す
る。さらに、作業者13は狭い機械室5内で身を
屈めて作業をしなくてはならず、しかも機械室5
が昇降路1の上端部にあるために作業の危険性が
大きい。
Furthermore, the winding work of the winch 10 by the worker 12 and the feeding work of the main rope 7 by the worker 13 into the machine room 5 must be performed at the same time, and the work is complicated and requires skill. Furthermore, the worker 13 has to bend down to work in the narrow machine room 5, and moreover, the worker 13 has to work in the narrow machine room 5
The work is very dangerous because it is located at the upper end of the hoistway 1.

本発明は前述せるようなエレベータの主ロープ
掛け工法の現状に鑑みてなされたものであり、そ
の目的は1名の作業者で安全且つ容易にかごに対
して主ロープを連結させることが出来るエレベー
タの主ロープ掛け工法を提供することにある。
The present invention was made in view of the current state of the method of hanging the main rope of an elevator as described above, and its purpose is to provide an elevator in which the main rope can be safely and easily connected to the car by one worker. The main purpose is to provide a rope hanging method.

<問題点を解決するための手段> 前述せる問題点を解決するために、本発明では
昇降路上端部の機械室に配設される巻上機のシー
ブに主ロープを巻回し、該主ロープの一端に前記
昇降路下端部においてつり合い重りを連結し、該
つり合い重りに吊り上げロープの一端を連結し、
該吊り上げロープの他端側をウインチで巻き取る
ことにより、前記主ロープの一端側、前記つり合
い重り及び前記吊り上げロープの一端側で構成さ
れる吊り上げ系を吊り上げ移動させ、該吊り上げ
移動の距離に対応して前記主ロープの他端を前記
昇降路下端部に配されたかごに対して送り込んで
前記かごに連結する、据付時におけるエレベータ
の主ロープ掛け工法において、前記昇降路内にお
いて前記かごの上方に仮設プーリを配設し、前記
主ロープの他端に仮設ロープの一端を連結し、該
仮設ロープの他端を前記仮設プーリを巻回経由し
て前記吊り上げ系に連結させ、前記ウインチの巻
き取りによる前記吊り上げ系の吊り上げ移動の距
離に対応して、前記仮設プーリを介して前記仮設
ロープが移動することにより、前記主ロープの他
端を前記かごに接近させて連結するような構成を
とつている。
<Means for solving the problem> In order to solve the above-mentioned problem, in the present invention, the main rope is wound around a sheave of a hoist installed in a machine room at the end of the hoistway. A counterweight is connected to one end at the lower end of the hoistway, and one end of a lifting rope is connected to the counterweight;
By winding the other end of the lifting rope with a winch, a lifting system consisting of one end of the main rope, the counterweight, and one end of the lifting rope is lifted and moved, corresponding to the distance of the lifting movement. In the elevator main rope hanging method during installation, the other end of the main rope is fed into a car disposed at the lower end of the hoistway and connected to the car. A temporary pulley is provided at the main rope, one end of the temporary rope is connected to the other end of the main rope, and the other end of the temporary rope is connected to the lifting system via the winding of the temporary pulley. The other end of the main rope is connected to the car by moving the temporary rope via the temporary pulley in accordance with the distance of lifting movement of the lifting system by the handle. It's on.

<作用> 本発明では、ウインチを作業者が操作すること
によつて、吊り上げロープが巻き取られて吊り上
げ系が昇降路を上方に移動する。そして、この吊
り上げ系の上方への移動に対応して、仮設プーリ
を介して仮設ロープが主ロープとの連結側で引き
下げられる。
<Function> In the present invention, when a worker operates the winch, the lifting rope is wound up and the lifting system moves upward on the hoistway. Then, in response to the upward movement of the lifting system, the temporary rope is pulled down on the side connected to the main rope via the temporary pulley.

このようにして、ウインチの巻き取り距離に対
応して巻上機のシーブに巻回されている主ロープ
が、自動的に引き下げられるので1名の作業者に
よつて安全且つ容易に据付時におけるエレベータ
の主ロープ掛け作業を行なうことが出来る。
In this way, the main rope that is wound around the sheave of the hoist is automatically lowered in accordance with the winding distance of the winch, allowing one worker to safely and easily install the rope. Can perform work of hanging the main rope of the elevator.

<実施例> 以下に本発明の実施例を第1図に用いて、詳細
に説明する。
<Example> An example of the present invention will be described in detail below with reference to FIG.

ここで第1図は本発明の実施例の構成を示す側
面説明図であり、第2図と同一部分には同一符号
が付されている。
Here, FIG. 1 is an explanatory side view showing the configuration of an embodiment of the present invention, and the same parts as in FIG. 2 are given the same reference numerals.

第1図に示すように、本発明の実施例では第2
図に示す従来のエレベータの主ロープ掛け工法に
対して、かご2の上部に組立てられる作業床3に
仮設プーリ14を固定配設し、この仮設プーリ1
4に仮設ロープ17を巻回させる。
As shown in FIG. 1, in the embodiment of the present invention, the second
In contrast to the conventional elevator main rope hanging construction method shown in the figure, a temporary pulley 14 is fixedly arranged on the work floor 3 assembled on the top of the car 2.
4 and wind the temporary rope 17 around it.

このようして、仮設プーリ14に巻回させた仮
設ロープ17の一端は、主ロープ7の重り8が取
り付けられている他端に連結される。また、仮設
ロープ17の他端は、主ロープ7のつり合い重り
4が取り付けられている一端に連結される。
In this way, one end of the temporary rope 17 wound around the temporary pulley 14 is connected to the other end of the main rope 7 to which the weight 8 is attached. Further, the other end of the temporary rope 17 is connected to one end of the main rope 7 to which the counterweight 4 is attached.

このような設定状態において、本発明の実施例
では、ウインチ10を操作する1名の作業者12
のみで、エレベータの主ロープ掛け作業が行なわ
れる。
In this setting state, in the embodiment of the present invention, one worker 12 who operates the winch 10
The work of hanging the main rope of the elevator is carried out using a chisel.

即ち、作業者12がウインチ10を操作して吊
り上げロープ11の他端側を巻き取ると、吊り上
げロープ11の1端はつり合い重り4を昇降路1
内を上方に引き上げ移動させる。
That is, when the worker 12 operates the winch 10 to wind up the other end of the lifting rope 11, one end of the lifting rope 11 pulls the counterweight 4 onto the hoistway 1.
Pull the inside upwards and move it.

第1図で実線で示す位置から二点鎖線で示す位
置につり合い重り4が上昇すると、仮設ロープ1
7も実線で示す位置から二点鎖線で示す位置に上
方に引き上げられる。また、この引き上げ移動に
よつて、主ロープ7の他端は引き下げられて重り
8は実線で示す位置から、二点鎖線で示す位置に
移動する。
When the counterweight 4 rises from the position shown by the solid line to the position shown by the two-dot chain line in Fig. 1, the temporary rope 1
7 is also pulled upward from the position shown by the solid line to the position shown by the two-dot chain line. Further, due to this lifting movement, the other end of the main rope 7 is pulled down, and the weight 8 moves from the position shown by the solid line to the position shown by the two-dot chain line.

この場合、作業床3上における仮設プーリ14
の取り付け位置、つり合い重り4に対する重り8
の重量比を選定することにより、ウインチ10の
巻取り操作で主ロープ7は円滑に降下して、かご
2の所定位置に到達する。
In this case, the temporary pulley 14 on the work floor 3
installation position, weight 8 relative to counterweight 4
By selecting the weight ratio of , the main rope 7 is smoothly lowered by the winding operation of the winch 10 and reaches a predetermined position of the car 2.

この状態で、作業者12はウインチ10のロツ
ク状態とし、作業床3上において主ロープ7とか
ご2との連結作業を行なうことが出来る。
In this state, the worker 12 can lock the winch 10 and perform the work of connecting the main rope 7 and the car 2 on the work floor 3.

このようにして、本発明の実施例においては、
危険な機械室5内に作業者を配置することなし
に、1名の作業者12によつて安全且つ容易に、
エレベータの据付時における主ロープ7とかご2
との連結作業を行なうことが出来る。
Thus, in embodiments of the invention:
safely and easily by one worker 12 without placing the worker in the dangerous machine room 5.
Main rope 7 and car 2 during elevator installation
It is possible to perform connection work with

実施例においては、仮設ロープの他端を主ロー
プのつり合い重りが取り付けられている一端に連
結した構成のものを説明したが、本発明の構成は
実施例のものに限定されものでなく、仮設ロープ
の他端がつり合い重り、吊り上げロープの一端側
及び主ロープの一端側よりなる吊り上げ系に連結
された各種の構成をとることが出来る。
In the embodiment, a structure in which the other end of the temporary rope is connected to one end of the main rope to which the counterweight is attached has been described, but the structure of the present invention is not limited to the embodiment. Various configurations are possible in which the other end of the rope is connected to a lifting system consisting of a counterweight, one end of the lifting rope, and one end of the main rope.

従つて例えば、仮設ロープの他端をつり合い重
りに連結した構成のもの、或は仮設ロープの他端
を吊り上げロープの一端側に連結した構成のもの
とすることが出来る。
Therefore, for example, the other end of the temporary rope may be connected to a counterweight, or the other end of the temporary rope may be connected to one end of the lifting rope.

<発明の効果> 以上詳細に説明したように、本発明によると1
名の作業者による簡単で安全な作業により、工事
費用を大幅に削減して据付時における主ロープと
かごの連結作業を行なわせることが可能な、エレ
ベータの主ロープ掛け工法を提供することが出来
る。
<Effects of the Invention> As explained in detail above, according to the present invention, 1
It is possible to provide a main rope hanging method for an elevator, which allows simple and safe work by a number of workers to significantly reduce construction costs and connect the main rope and car during installation. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の実施例の構成を示す側面説明
図、第2図は従来のエレベータの主ロープ掛け工
法の構成を示す側面説明図である。 1……昇降路、2……かご、3……作業床、4
……つり合い重り、5……機械室、6……シー
ブ、7……主ロープ、8……重り、10……ウイ
ンチ、11……吊り上げロープ、12,13……
作業者、14……仮設プーリ、15,16……そ
らせ車、17……仮設ロープ。
FIG. 1 is an explanatory side view showing the configuration of an embodiment of the present invention, and FIG. 2 is an explanatory side view showing the configuration of a conventional elevator main rope hanging method. 1... hoistway, 2... cage, 3... work floor, 4
... Counterweight, 5 ... Machine room, 6 ... Sheave, 7 ... Main rope, 8 ... Weight, 10 ... Winch, 11 ... Lifting rope, 12, 13 ...
Worker, 14... Temporary pulley, 15, 16... Deflection wheel, 17... Temporary rope.

Claims (1)

【特許請求の範囲】[Claims] 1 昇降路上端部の機械室に配設される巻上機の
シーブに主ロープを巻回し、該主ロープの一端に
前記昇降路下端部においてつり合い重りを連結
し、該つり合い重りに吊り上げロープの一端を連
結し、該吊り上げロープの他端側をウインチで巻
き取ることにより、前記主ロープの一端側、前記
つり合い重り及び前記吊り上げロープの一端側で
構成される吊り上げ系を吊り上げ移動させ、該吊
り上げ移動の距離に対応して前記主ロープの他端
を前記昇降路下端部に配されたかごに対して送り
込んで前記かごに連結する、据付時におけるエレ
ベータの主ロープ掛け工法において、前記昇降路
内において前記かごの上方に仮設プーリを配設
し、前記主ロープの他端に仮設ロープの一端を連
結し、該仮設ロープの他端を前記仮設プーリの巻
回経由して前記吊り上げ系に連結させ、前記ウイ
ンチの巻き取りによる前記吊り上げ系の吊り上げ
移動の距離に対応して、前記仮設プーリを介して
前記仮設ロープが移動することにより、前記主ロ
ープの他端を前記かごに接近させて連結すること
を特徴とするエレベータの主ロープ掛け工法。
1. Wrap the main rope around the sheave of the hoist installed in the machine room at the end of the hoistway, connect a counterweight to one end of the main rope at the lower end of the hoistway, and attach the lifting rope to the counterweight. By connecting one end of the lifting rope and winding the other end of the lifting rope with a winch, the lifting system consisting of one end of the main rope, the counterweight, and one end of the lifting rope is lifted and moved, and the lifting rope is lifted and moved. In an elevator main rope hanging method during installation, in which the other end of the main rope is fed into a car arranged at the lower end of the hoistway and connected to the car in accordance with the distance of movement, A temporary pulley is arranged above the car, one end of the temporary rope is connected to the other end of the main rope, and the other end of the temporary rope is connected to the lifting system via the winding of the temporary pulley. , the temporary rope moves via the temporary pulley in accordance with the lifting distance of the lifting system due to winding of the winch, thereby bringing the other end of the main rope closer to and connecting to the car. An elevator main rope hanging construction method characterized by:
JP9537787A 1987-04-20 1987-04-20 Method of main-rope stretching construction of elevator Granted JPS63262385A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9537787A JPS63262385A (en) 1987-04-20 1987-04-20 Method of main-rope stretching construction of elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9537787A JPS63262385A (en) 1987-04-20 1987-04-20 Method of main-rope stretching construction of elevator

Publications (2)

Publication Number Publication Date
JPS63262385A JPS63262385A (en) 1988-10-28
JPH0470235B2 true JPH0470235B2 (en) 1992-11-10

Family

ID=14135951

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9537787A Granted JPS63262385A (en) 1987-04-20 1987-04-20 Method of main-rope stretching construction of elevator

Country Status (1)

Country Link
JP (1) JPS63262385A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4790941B2 (en) * 2001-08-23 2011-10-12 三菱電機株式会社 Elevator main rope hanging method
JP3961895B2 (en) * 2001-10-26 2007-08-22 株式会社日立ビルシステム Elevator confinement rescue method and apparatus
JP4841171B2 (en) * 2004-05-20 2011-12-21 フジテック株式会社 Rise-up elevator installation method

Also Published As

Publication number Publication date
JPS63262385A (en) 1988-10-28

Similar Documents

Publication Publication Date Title
US8028393B2 (en) Elevator arrangement
EP2349902B1 (en) Method of installing an elevator
JPH07100582B2 (en) Elevator work platform and elevator installation method
JPH0470235B2 (en)
JP3170559B2 (en) Elevator car fixing device
JPS5935822B2 (en) Construction elevator installation method
JP3531504B2 (en) Elevator safety equipment
JPH09278325A (en) Construction work elevator lifting method and construction work elevator device
CN217676204U (en) Construction elevator provided with automatic construction elevator floor channel
JPH0734073Y2 (en) Man lift for tower crane
JP2654412B2 (en) How to reset the emergency stop device
JPS5918309B2 (en) Installation method of mobile mechanical room elevator
JPH05201648A (en) Installation of elevator
WO2022230140A1 (en) Elevator and lifting/lowering path extension method
JPH0733355A (en) Installation method for elevator
JPH06156931A (en) Main rope passing method for elevator
JPH10203751A (en) Main rope replacing method of 2:1 roping elevator and device thereof
JP2022126286A (en) Replacement assist device of governor rope and replacement method of governor rope
CN116262586A (en) Jump elevator and jump method thereof
JPH0672663A (en) Construction method for linking main rope of elevator
WO2023160818A1 (en) An elevator construction arrangement and a method
JPS5934633B2 (en) Construction elevator installation method
JPH06255943A (en) Device and method for installing guide rail
WO2023160817A1 (en) An elevator construction arrangement and a method
JPH02300081A (en) Installation work method for elevator