JPH10203751A - Main rope replacing method of 2:1 roping elevator and device thereof - Google Patents

Main rope replacing method of 2:1 roping elevator and device thereof

Info

Publication number
JPH10203751A
JPH10203751A JP1260697A JP1260697A JPH10203751A JP H10203751 A JPH10203751 A JP H10203751A JP 1260697 A JP1260697 A JP 1260697A JP 1260697 A JP1260697 A JP 1260697A JP H10203751 A JPH10203751 A JP H10203751A
Authority
JP
Japan
Prior art keywords
main rope
rope
thimble rod
main
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1260697A
Other languages
Japanese (ja)
Inventor
Katsunori Ishizaka
勝則 石坂
Yoshinori Hirota
喜則 広田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP1260697A priority Critical patent/JPH10203751A/en
Publication of JPH10203751A publication Critical patent/JPH10203751A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To recover an existing main rope simply by attaching a rope socket and a first simple rod to the other end of a newly installed main rope, then hoisting it up to a machine room, and installing the first simple rod on a floor of the machine room. SOLUTION: A winch 8 is wound up to cut a first cutting section 1B of a main rope 1, and the main rope 1 from the first cutting section 1B to a second cutting section 1C is lowered and is wound around a drum 10 installed on a floor FB at the lowest story. Next, a drum around which a newly installed main rope 1a on an end part of which a rope socket and a first simple rod 2A are attached in advance is wound is installed on a floor FA at the uppermost story, this newly installed main rope 1a is hoisted up to a machine room 3 by the winch 8 and a winch rope 8A through a cage 5, and the first simple rod 2A is installed on a floor of the machine room 3. Consequently, it is possible to recover the existing main rope 1 simply.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、2:1ローピング
エレベータの主索交換方法及びその装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for exchanging main ropes of a 2: 1 roping elevator.

【0002】[0002]

【従来の技術】従来、エレベータの主索を既設主索から
新設主索へ交換するときウィンチが使用される。このウ
ィンチを用いたエレベータの主索方法として、主索の両
端を上部で綱止めし、かご側及び釣合い錘側にそれぞれ
設けられた吊り車に主索を掛け渡し、巻上機の駆動によ
って昇降路内の乗りかごを懸垂しながら昇降させる2:
1ローピングエレベータの主索交換方法において、上部
階の床面より昇降路内のほぼ中央部に差し出した第1の
導板と、下部階の床面より釣合い錘の上端面に掛け渡し
た第2の導板とを仮設し、第1の導板上にロープ巻取り
機及びロープ繰出し機を設置し、新旧主索の仮中継によ
り旧主策の回収及び新主策の送給を行うようにした2:
1ローピングエレベータの主索交換方法が特開昭63−
282080号公報に記載されている。
2. Description of the Related Art Conventionally, a winch is used to replace an elevator main line from an existing main line to a new main line. As a main rope method of an elevator using this winch, both ends of the main rope are tied up at the upper part, and the main ropes are hung over hanging cars provided on the car side and the counterweight side respectively, and lifted by driving the hoist. Raising and lowering the car in the street 2:
(1) In the method for exchanging main ropes of a roping elevator, a first conductive plate extending from a floor surface of an upper floor to a substantially central portion in a hoistway, and a second conductive plate extending from a floor surface of a lower floor to an upper end surface of a counterweight. To temporarily install a rope winding machine and a rope unwinding machine on the first conductive plate, and to collect the old main policy and send the new main policy by temporary relay of the new and old main ropes. Done 2:
1 Roping elevator main rope replacement method
No. 2,820,080.

【0003】[0003]

【発明が解決しようとする課題】上記従来技術は、新設
主索と既設主索を連結させて既設主索を巻き取りながら
新設主索を巻き掛けるようにしたため、既設主索の切断
が不必要となるが巻き取った既設主索の重量が大とな
り、既設主索の回収には器材と人手が掛るという問題が
あった。
In the above prior art, the new main rope is connected to the existing main rope so that the new main rope is wound around the existing main rope, so that the cutting of the existing main rope is unnecessary. However, there was a problem that the weight of the existing main rope wound up became large, and the recovery of the existing main rope required equipment and labor.

【0004】また、新設主索と既設主索を連結させるこ
とにより、新設及び既設主索いずれかの撚りが戻るとき
に生じる回転力によって、新設及び既設主索が昇降路内
を動きまわり昇降路内機器に衝突して昇降路内機器を破
損させたり、汚れて撚りがある既設主索を巻き取り回収
するときに建物や作業者の衣服を汚したり、作業者に傷
を負わすという問題があった。
[0004] In addition, by connecting the new main line and the existing main line, the new and existing main lines move around in the hoistway and move around the hoistway due to the rotational force generated when the twist of either the new main line or the existing main line returns. There is a problem that the equipment in the hoistway may be damaged by colliding with the internal equipment, or the building and workers' clothes may be soiled and the workers may be damaged when winding up and collecting the dirty and twisted existing main rope. there were.

【0005】また、新設主索は一端が既設主索に接続さ
れ、他端が主索ドラムに巻き掛けられているので、新設
主索の撚りを完全に戻すことができず、主索取り替え後
に複数本の主索で撚りの戻り度合の差による主索張力の
差が生じ、主索を巻き掛ける綱車の溝に摩耗差が発生す
る問題があった。
[0005] Further, since the new main rope has one end connected to the existing main rope and the other end wound around the main rope drum, the twist of the new main rope cannot be completely returned. There is a problem in that a difference in main rope tension occurs due to a difference in the degree of twist return between a plurality of main ropes, and a difference in wear occurs in a groove of a sheave around which the main rope is wound.

【0006】本発明の第1の目的は、既設主索の回収が
簡便に行える2:1ローピングエレベータの主索交換方
法を提供することにある。
A first object of the present invention is to provide a method of exchanging main ropes of a 2: 1 roping elevator in which existing main ropes can be easily collected.

【0007】又、本発明の第2の目的は、主索交換時に
昇降路内機器の破損と建物の汚損を防止するとともに、
新設主索の撚りを戻すことのできる2:1ローピングエ
レベータの主索交換装置を提供することにある。
A second object of the present invention is to prevent damage to equipment in a hoistway and soiling of a building during replacement of a main cable,
It is an object of the present invention to provide a main rope exchanging device for a 2: 1 roping elevator that can untwist a new main rope.

【0008】[0008]

【課題を解決するための手段】上記第1の目的を達成す
るために、本発明は、機械室の床部に主索の両端に接続
される第1のシンブルロッド及び第2のシンブルロッド
がバネを介して設置され、前記第1のシブルロッドと巻
上機プーリから垂下させた前記主索を乗りかご上部に設
けたかご上プーリに巻き掛け、前記巻上機プーリと前記
第2のシンブルロッドから垂下させた前記主索を釣合い
錘上部に設けた釣合い錘プーリに巻き掛けるようにした
2:1ローピングエレベータの主索交換方法であって、
前記釣合い錘を昇降路底部で支持するとともに、前記乗
りかごを昇降路頂部で吊り上げた後固設して既設主索の
張力を無効とした状態で、複数本の主索を少なくとも1
本づつ交換する2:1ローピングエレベータの主索交換
方法において、前記乗りかごを最上階近傍に停止させた
状態で前記既設主索の張力を無効とした後、前記既設主
索の1本を前記釣合い錘プーリ上部の第1切断箇所で切
断し、ウィンチに取り付けられたロープ吊り具に前記第
2のシンブルロッドの頂部を螺着させて前記第1切断箇
所から前記第2のシンブルロッドまでの前記既設主索を
前記ウィンチで吊り下げて回収し、前記釣合い錘プーリ
と前記巻上機プーリ間の前記既設主索を前記巻上機プー
リの近傍にて主索保持装置で把持した後、この把持部分
の上方の第2切断箇所で概主索を切断し、前記主索保持
装置に前記ロープ吊り具を取り付けて前記第1切断箇所
から前記第2切断箇所までの前記既設主索を前記ウィン
チで吊り下げて回収し、前記第1のシンブルロッドから
前記かご上プーリへ垂下する前記既設主索の前記第2切
断箇所と略同位置の第3切断箇所で切断し、前記第2切
断箇所から前記第3切断箇所までの前記既設主索及び前
記第1のシンブルロッドから前記第3切断箇所までの前
記既設主索を前記機械室に引き上げて回収した後、次
に、新設主索は、最上階床から乗りかご天井に設けた救
出口を介し前記かご上プーリに巻き掛けて前記機械室に
引き上げ前記新設主索の一端にロープソケットを取り付
けた後、前記巻上機プーリに巻き掛け該当主索以外の主
索でガイドしながら昇降路へ下降させ、前記釣合い錘プ
ーリに巻き掛けて前記ロープソケットに前記第2のシン
ブルロッドを取り付け、前記ウィンチに取り付けられた
前記ロープ吊り具に前記第2のシンブルロッドを螺結さ
せて前記機械室に吊り上げ前記第2のシンブルロッドを
前記機械室床部に設置し、さらに、前記新設主索の他端
に前記ロープソケット及び前記第1のシンブルロッドを
取り付けた後、前記機械室に吊り上げ前記第1のシンブ
ルロッドを前記機械室床部に設置するようにしたもので
ある。
In order to achieve the first object, the present invention provides a machine room having a first thimble rod and a second thimble rod connected to both ends of a main rope at the floor. The main rope, which is installed via a spring and is suspended from the first sibble rod and the hoist pulley, is wound around a car pulley provided above the car, and the hoist pulley and the second thimble rod A method of exchanging main ropes of a 2: 1 roping elevator, wherein the main ropes suspended from the ropes are wound around a counterweight pulley provided above the counterweight.
While supporting the counterweight at the bottom of the hoistway, suspending the car at the top of the hoistway, and fixing it so that the tension of the existing main rope is invalid, at least one
In the method of replacing main ropes of a 2: 1 roping elevator, which is replaced one by one, after the tension of the existing main ropes is invalidated in a state where the car is stopped near the top floor, one of the existing main ropes is replaced with the main rope. Cut at the first cutting point on the upper part of the counterweight pulley, screw the top of the second thimble rod to a rope hanger attached to the winch, and screw the top part of the second thimble rod from the first cutting point to the second thimble rod. The existing main rope is suspended by the winch and collected, and the existing main rope between the counterweight pulley and the hoist pulley is gripped by a main rope holding device in the vicinity of the hoist pulley. A main rope is cut at a second cutting point above the portion, and the rope hanging device is attached to the main rope holding device, and the existing main rope from the first cutting point to the second cutting point is separated by the winch. Hanging and turning And cutting the existing main rope hanging from the first thimble rod to the pulley on the car at a third cutting point substantially at the same position as the second cutting point of the existing main rope, and moving from the second cutting point to the third cutting point. After the existing main ropes and the first main ropes from the first thimble rod to the third cutting point have been pulled up to the machine room and collected, the new main ropes are then placed in the car from the top floor. After being wound around the pulley on the car through a rescue exit provided on the ceiling and raised to the machine room, a rope socket is attached to one end of the newly installed main rope, and then wound around the pulley of the hoisting machine, the main rope other than the relevant main rope is wound. The guide is moved down to the hoistway, wound around the counterweight pulley, and the second thimble rod is attached to the rope socket, and the second simb is attached to the rope suspender attached to the winch. A second rod was screwed up and lifted in the machine room, the second thimble rod was installed on the machine room floor, and the other end of the new main rope was attached with the rope socket and the first thimble rod. Then, the first thimble rod is lifted up in the machine room and installed on the machine room floor.

【0009】このような方法により、既設主索は、釣合
い錘プーリ上部の第1切断箇所、かご上プーリと巻上機
プーリ間の既設主索を主索保持装置で把持した上方の第
2切断箇所、第1のシンブルロッドからかご上プーリへ
垂下する既設主索の前記第2切断箇所と略同位置の第3
切断箇所で切断し、第1切断箇所から第3切断箇所で切
断の都度既設主索の回収を行い、すなわち、第1切断箇
所から第2のシンブルロッドまでをウィンチで吊り下げ
て回収し、第1切断箇所から第2切断箇所までをウィン
チで吊り下げて回収し、第2切断箇所から第3切断箇所
まで及び第1のシンブルロッドから第3切断箇所までを
機械室に引き上げて回収した後、新設主索を主索以外の
主索でガイドさせながら配設し、第2のシンブルロッド
の取り付け後に第1のシンブルロッドを機械室床部に取
り付けるようにした。このように、既設主索は3箇所で
切断されるので、主索回収後の運搬は人手で行うことが
でき、重量物を運ぶ特別な機器が不必要となる。
According to such a method, the existing main rope is cut at the first cut portion above the counterweight pulley, and the second main cut above the existing main rope between the car pulley and the hoist pulley held by the main rope holding device. A third portion of the existing main rope hanging from the first thimble rod to the car pulley at the same position as the second cut portion.
The cutting is performed at the cutting point, and the existing main rope is collected every time the cutting is performed from the first cutting point to the third cutting point. That is, the parts from the first cutting point to the second thimble rod are suspended by a winch and collected. From the 1st cutting point to the 2nd cutting point, it is suspended and collected by a winch, and after the 2nd cutting point to the 3rd cutting point and the 1st thimble rod to the 3rd cutting point are pulled up to the machine room and collected, The new main rope is arranged while being guided by main ropes other than the main rope, and the first thimble rod is mounted on the machine room floor after the second thimble rod is mounted. As described above, since the existing main rope is cut at three places, the transportation after the main rope collection can be performed manually, and special equipment for transporting heavy objects is not required.

【0010】また、上記第2の目的を達成するために、
本発明は、機械室の床部に主索の両端に接続される第1
のシンブルロッド及び第2のシンブルロッドがバネを介
して設置され、前記第1のシンブルロッドと巻上機プー
リから垂下させた前記主索を乗りかご上部に設けたかご
上プーリに巻き掛け、前記巻上機プーリと前記第2のシ
ンブルロッドから垂下させた前記主索を釣合い錘上部に
設けた釣合い錘プーリに巻き掛けるようにした2:1ロ
ーピングエレベータの主索交換装置であって、前記釣合
い錘を昇降路底部で支持するとともに、前記乗りかごを
昇降路頂部で吊り上げた後固設して既設主索の張力を無
効とした状態で、複数本の主索を少なくとも1本づつ交
換する2:1ローピングエレベータの主索交換装置にお
いて、前記既設及び前記新設の主索を昇降させるとき、
一端をシンブルロッドに螺結させ他端をウィンチに装着
するロープ吊り具と、前記既設主索の取り外し及び前記
新設の主索取り付けのとき、前記機械室の床に前記シン
ブルロッドを固定するシンブルロッド固定雇と、前記既
設及び前記新設の主索に沿って上下方向に案内可能なガ
イド穴と既設及び新設の主索を昇降させる昇降体が着脱
可能な取付体を有する主索昇降ガイド体と、前記既設主
索を前記乗りかごの上で切断するとき、前記主索の切断
箇所の下方に装着する主索保持装置とを備えたものであ
る。
In order to achieve the second object,
The present invention relates to a first section connected to both ends of a main rope on the floor of a machine room.
The thimble rod and the second thimble rod are installed via a spring, and the first thimble rod and the main rope hung from the hoist pulley are wound around a car pulley provided at an upper part of a car, and A main rope exchanging device for a 2: 1 roping elevator, wherein the main rope hung from a hoisting machine pulley and the second thimble rod is wound around a counterweight pulley provided above a counterweight. The weight is supported at the bottom of the hoistway, and the car is lifted at the top of the hoistway and fixed to replace the at least one main rope at a time while the tension of the existing main rope is invalidated. : 1 In the main rope replacement device of the 1-roping elevator, when raising and lowering the existing and the new main rope,
A rope hanger having one end screwed to the thimble rod and the other end attached to the winch; and a thimble rod for fixing the thimble rod to the floor of the machine room when removing the existing main rope and attaching the new main rope. Fixed employment, a main rope elevating guide body having a guide hole capable of vertically guiding along the existing and the new main rope, and a mounting body capable of attaching and detaching an elevating body for elevating the existing and new main rope, When the existing main rope is cut on the car, a main rope holding device to be attached below a cut portion of the main rope is provided.

【0011】また、このように構成したので、既設及び
新設の主索を昇降させるウィンチに撚り戻し雇を介在さ
せ、また、既設及び新設の主索を昇降させるとき、主索
昇降ガイド体の主索が挿通可能な挿通孔に両端をシンブ
ルロッドで機械室に取り付けられた主索を挿入してガイ
ドしながら昇降させるようにしたので、主索の撚りが昇
降させながら戻るとともに、撚りが戻るときに主索が振
れて昇降路内機器に衝突することもない。
[0011] Also, with this configuration, the winch for elevating and lowering the existing and new main ropes is interposed with a twist-back employment, and when raising and lowering the existing and new main ropes, the main rope lifting guide body is used. The main rope attached to the machine room with thimble rods at both ends is inserted into the insertion hole through which the rope can be inserted, and the main rope is lifted up and down while guiding it. The main rope does not swing and collide with the equipment in the hoistway.

【0012】[0012]

【発明の実施の形態】以下、本発明の一実施の形態を図
1〜図9を用いて説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described below with reference to FIGS.

【0013】図1は本発明の2:1ローピングエレベー
タの主索交換方法の一実施形態を説明する昇降路の縦断
面図で、図2は本発明の一実施形態のロープ吊り具の装
着状態を示す図であり、図3は本発明の一実施形態のシ
ンブルロッド固定雇の取り付け状態を示す図であり、図
4は図3のA−A断面図であり、図5は本発明の一実施
形態のシンブルロッドにロープ吊り具の装着状態を示す
図であり、図6は本発明の一実施形態の主索保持装置で
既設主索を把持した状態を示す図であり、図7は本発明
の一実施形態の主索を下降させるときの主索昇降ガイド
体の取り付け図で、図8は本発明の一実施形態の主索を
上昇させるときの主索昇降ガイド体の取り付け図で、図
9は第1及び第2のシンブルロッドの機械室床への取り
付けを示す図である。
FIG. 1 is a longitudinal sectional view of a hoistway for explaining an embodiment of a method for replacing a main rope of a 2: 1 roping elevator according to the present invention, and FIG. 2 is an attached state of a rope hanging device according to an embodiment of the present invention. FIG. 3 is a view showing an attached state of a thimble rod fixing member according to an embodiment of the present invention, FIG. 4 is a sectional view taken along line AA of FIG. 3, and FIG. It is a figure which shows the attachment state of the rope hung on the thimble rod of embodiment, FIG. 6 is a figure which shows the state which clamped the existing main rope with the main rope holding device of one Embodiment of this invention, FIG. FIG. 8 is an installation view of the main rope elevating guide body when the main rope according to the embodiment of the present invention is lowered, and FIG. FIG. 9 is a diagram showing attachment of the first and second thimble rods to the machine room floor. .

【0014】図において、2:1ローピングエレベータ
の主索1は両端に接続される第1及び第2のシンブルロ
ッド2A、2Bによって機械室3の床に固設されたシン
ブルロッド取り付けブラケット3Aにバネ4A及びバネ
座4Bを介して取り付けられ、乗りかご5の上に取り付
けられた乗りかごプーリ5Aは第1のシンブルロッド2
Aと機械室3に設置される図示しない巻上機の綱車3B
間に主索1で巻き掛けられ、また、釣合い錘6の上部に
取り付けられた釣合い錘プーリ6Aは図示しない巻上機
のそらせ車3Cと第2のシンブルロッド2B間に主索1
で巻き掛けられている。ここで、主索1の端末処理は図
9に示すように、主索1の端部をバビットを詰めたり楔
作用等により取り付けられるソケット1Aに第1及び第
2のシンブルロッド2A、2Bが軸支され、この第1及
び第2のシンブルロッド2A、2Bが機械室3のシンブ
ルロッド取り付けブラケット3Aにバネ4A及びバネ座
4Bを介してナット4Cで止められている。
In the figure, a main rope 1 of a 2: 1 roping elevator is spring-mounted on a thimble rod mounting bracket 3A fixed to the floor of a machine room 3 by first and second thimble rods 2A, 2B connected to both ends. 4A and the car pulley 5A mounted on the car 5 via the spring seat 4B, the first thimble rod 2
A and a sheave 3B of a hoist (not shown) installed in the machine room 3
A counterweight pulley 6A wound around the main rope 1 between the main rope 1 and an upper part of the counterweight 6 is provided between the deflector wheel 3C of the hoist (not shown) and the second thimble rod 2B.
It is wound around. Here, as shown in FIG. 9, the terminal processing of the main rope 1 is such that the first and second thimble rods 2A, 2B are axially attached to a socket 1A in which the ends of the main rope 1 are stuffed with babbits or wedge action or the like. The first and second thimble rods 2A, 2B are supported and fixed to a thimble rod mounting bracket 3A of the machine room 3 by a nut 4C via a spring 4A and a spring seat 4B.

【0015】次に、主索1の取り替え作業の主索取り外
し作業を説明する。
Next, a description will be given of the work of removing the main rope 1 in the work of replacing the main rope 1.

【0016】まず、2:1ローピングエレベータの主索
1の取り外し作業の段取り作業として、昇降路7の底部
に釣合い錘6を支持する所定高の受け台7A及び釣合い
錘プーリ6Aに主索1が巻き掛けられる位置までの所定
高の足場7Bを設置し、次に、釣合い錘6をゆっくり下
降させて受け台7aに釣合い錘6を支持させたのち、最
上階FA近傍に停止している乗りかご5を乗りかご上部
から図示しないチェーンブロックで所定長吊り上げ主索
1の張力を無効とし、さらに、乗りかご5を昇降路7頂
部の図示しない中間ビームや乗りかご5を案内する図示
しないレール等に吊着固定して落下の安全強化を行う。
また、機械室3には主索1を昇降させるウィンチ8を移
動自在に設置し、ウィンチロープ8Aの先端に着脱自在
に取り付けられるロープ吊り具9は、2分した上部と下
部が方向自在に回転する撚り戻し雇9Aと、この撚り戻
し雇9Aの下端に熔着され第1及び第2のシンブルロッ
ド2A、2Bを螺結する長ナット9Bとで構成されてい
る。また、最下階FBには既設主索1を巻き取るドラム
10を設置する。
First, as a setup operation for removing the main rope 1 of the 2: 1 roping elevator, the main rope 1 is mounted on a receiving stand 7A having a predetermined height for supporting the counterweight 6 at the bottom of the hoistway 7 and a counterweight pulley 6A. A scaffold 7B having a predetermined height up to the position where the car is wound around is installed, and then the counterweight 6 is slowly lowered to support the counterweight 6 on the cradle 7a, and then the car stopped near the top floor FA. 5 is lifted from the top of the car by a chain block (not shown) to lift the main rope 1 for a predetermined length to invalidate the tension of the main rope 1, and further, the car 5 is moved to an intermediate beam (not shown) at the top of the hoistway 7 or a rail (not shown) for guiding the car 5. Hanging and fixing to enhance fall safety.
A winch 8 for raising and lowering the main rope 1 is movably installed in the machine room 3, and a rope hanger 9 detachably attached to the tip of a winch rope 8A is rotatable so that an upper part and a lower part which are divided into two parts can freely rotate. And a long nut 9B that is welded to the lower end of the twisting and rewinding 9A to screw the first and second thimble rods 2A and 2B. A drum 10 for winding the existing main rope 1 is installed on the lowermost floor FB.

【0017】次に、既設の主索1の第1及び第2のシン
ブルロッド2A、2Bからの取り外し及び巻取り作業を
説明する。
Next, the operation of removing and winding the existing main rope 1 from the first and second thimble rods 2A and 2B will be described.

【0018】まず、主索1の張力を無効とした状態で作
業者が足場7Bに登り、第1の切断箇所1Bである釣合
い錘プーリ6A上方の位置で主索1の1本を切断し、次
に、ウィンチ8を第2のシンブルロッド2Bの上方に移
動させ、図2に示すように、ロープ吊り具9の長ナット
9Bに第2のシンブルロッド2Bを螺結させた後、ウィ
ンチ8を起動してウィンチロープ8Aを所定長である例
えば20cm巻き上げてシンブルロッド取り付けブラケ
ット3Aとバネ座4Bの間に間隙を設ける。次に、この
間隙にシンブルロッド固定雇11を装着させて第2のシ
ンブルロッド2B及び主索1を保持する。ここで、図
3、図4に示すように、シンブルロッド固定雇11はシ
ャコ万力の改造品であり、略U字状部材11Aの一端に
設けた進退自在なボルト11Bの先端と、ボルト11B
の対向位置に第1及び第2のシンブルロッド2A、2B
の螺結するナットを2分割し、その一方をボルト11B
の先端に他方を略U字状部材11Aのボルト11Bの対
向位置に2分割したナット11Cをそれぞれ熔着させた
ものであり、その使用方法は、シンブルロッド取り付け
ブラケット3Aとバネ座4Bの間隙にシンブルロッド固
定雇11をおいて、2分割したナット11Cのねじがシ
ンブルロッドのねじに係合するまでボルト11Bを締め
る。このように第2のシンブルロッド2Bを保持した
後、第2のシンブルロッド2Bからロープ吊り具9を外
し、ナット4Cを緩めバネ4A及びバネ座4Bを外して
図5に示すように第2のシンブルロッド2Bにロープ吊
り具9を再び装着させ、ウィンチ8を起動してウィンチ
ロープ8A及び第2のシンブルロッド2Bから第1の切
断箇所1Bの主索1をロープ吊り具9が乗りかご5の上
部の位置まで下降させ、最下階床FBに設置したドラム
10に巻き取る。ここで、切り取った主索1に撚りが生
じていた場合は、ウィンチロープ8Aの端部に取り付け
たロープ吊り具9の撚り戻し雇9A部分で回転すること
によって撚りが戻り、昇降路7の下降時に機器に衝突す
ることはない。
First, an operator climbs the scaffold 7B in a state where the tension of the main rope 1 is invalidated, and cuts one of the main ropes 1 at a position above the counterweight pulley 6A which is the first cutting point 1B, Next, the winch 8 is moved above the second thimble rod 2B, and as shown in FIG. 2, after the second thimble rod 2B is screwed to the long nut 9B of the rope hanging tool 9, the winch 8 is Upon activation, the winch rope 8A is wound up by a predetermined length of, for example, 20 cm to provide a gap between the thimble rod mounting bracket 3A and the spring seat 4B. Next, the thimble rod fixing member 11 is attached to this gap to hold the second thimble rod 2B and the main rope 1. Here, as shown in FIG. 3 and FIG. 4, the thimble rod fixing member 11 is a modified product of a giant vise, and includes a tip of a retractable bolt 11B provided at one end of a substantially U-shaped member 11A and a bolt 11B.
And the first and second thimble rods 2A and 2B
Is divided into two, and one of the nuts is
A nut 11C, which is divided into two parts, is welded to the tip of the U-shaped member 11A at a position opposed to the bolt 11B of the substantially U-shaped member 11A. The method of using the nut 11C is in the gap between the thimble rod mounting bracket 3A and the spring seat 4B. With the thimble rod fixing member 11 in place, the bolt 11B is tightened until the screw of the nut 11C divided into two engages with the screw of the thimble rod. After holding the second thimble rod 2B in this manner, the rope hanging tool 9 is removed from the second thimble rod 2B, the nut 4C is loosened, the spring 4A and the spring seat 4B are removed, and the second thimble rod 2B is moved to the second thimble rod 2B as shown in FIG. The rope hanger 9 is re-attached to the thimble rod 2B, the winch 8 is activated, and the rope hanger 9 moves the winch rope 8A and the main rope 1 at the first cutting point 1B from the second thimble rod 2B. It is lowered to the upper position and wound up on the drum 10 installed on the lowest floor FB. Here, in the case where the cut main rope 1 is twisted, the twist is returned by the rotation at the twist unwinding 9A portion of the rope hanging tool 9 attached to the end of the winch rope 8A, and the twist is returned, and the hoistway 7 descends. Sometimes does not hit the equipment.

【0019】次に、ウィンチ8を起動してウィンチロー
プ8Aを巻き取り、作業者が乗りかご5からかご天井に
設けられる予め開いておいた図示しない非常救出口を用
いて乗りかご5の上部に登る。ここで、昇降路7の頂部
と乗りかご5の上部の距離Hが例えば3mとすると、そ
らせ車3Cから垂下する主索1の第2の切断箇所1Cは
乗りかご5の上部で作業可能である昇降路7の頂部から
の距離h1が例えば2mの箇所とし、この第2の切断箇
所1Cの下方の主索1に一端を連結具8Bや両カン撚り
戻し具8Cを介してウィンチロープ8Aに接続された主
索保持装置12を取り付ける。この主索保持装置12は
図6に示すように主索1を挟む2枚の板12Aと、板1
2を合わせた状態に保持するボルトナット12Bと、そ
れぞれの板12に設けられ連結具8Bに取り付ける取付
具12Cとから構成されている。次に、ウィンチ8を巻
き上げてウィンチロープ8A及び主索保持装置12を張
った後主索1の第2の切断箇所1Bを切断し、ウィンチ
8を起動してウィンチロープ8A及び第1の切断箇所1
Bから第2の切断箇所1Cまでの主索1を下降させ、最
下階床FBに設置したドラム10に巻き取る。
Next, the winch 8 is activated, the winch rope 8A is wound up, and the worker uses the emergency opening (not shown) provided on the car ceiling from the car 5 to open the top of the car 5 using a pre-opened emergency exit. climb. Here, assuming that the distance H between the top of the hoistway 7 and the upper part of the car 5 is, for example, 3 m, the second cut 1C of the main rope 1 hanging from the deflector wheel 3C can be operated at the upper part of the car 5. The distance h1 from the top of the hoistway 7 is, for example, 2 m, and one end of the main rope 1 below the second cutting point 1C is connected to the winch rope 8A via the connecting member 8B or the both-can twist return device 8C. The attached main rope holding device 12 is attached. As shown in FIG. 6, the main rope holding device 12 includes two plates 12A sandwiching the main rope 1 and a plate 1A.
2 and a fixture 12C provided on each plate 12 and attached to the connector 8B. Next, after the winch 8 is wound up and the winch rope 8A and the main rope holding device 12 are stretched, the second cut 1B of the main rope 1 is cut, and the winch 8 is started to activate the winch rope 8A and the first cut point. 1
The main rope 1 from B to the second cutting point 1C is lowered and wound around the drum 10 installed on the lowest floor FB.

【0020】次に、ウィンチロープ8Aをウィンチ8に
巻き戻した後、乗りかご5の上部の作業者は、綱車3B
と乗りかごプーリ5A間の主索1の昇降路7の頂部から
の距離h2が第2の切断箇所1Bと同じ距離の2mに位
置する第3の切断箇所1Dで主索1を切断し、第2の切
断箇所1Cと第3の切断箇所1D間の主索1を機械室3
に引き上げ、また、第1のシンブルロッド2Aにロープ
吊り具9の長ナット9Bを螺結させた後、ウィンチ8を
起動してウィンチロープ8Aを所定長である例えば20
cm巻き上げてシンブルロッド取り付けブラケット3A
とバネ座4Bの間に設けた間隙にシンブルロッド固定雇
11を装着させて第1のシンブルロッド2Aと第3の切
断箇所1Dの主索1を保持し、第1のシンブルロッド2
Aからナット4C、ばね4A、ばね座4Bを取り外した
後、第1のシンブルロッド2Aと第3の切断箇所1D間
の主索1を機械室3に引き上げて既設の主索1の取り外
し作業を終了する。ここで、第2の切断箇所1C及び第
3の切断箇所1Dの昇降路7の頂部からの距離h1及び
距離h2が略同一寸法であるので、第1及び第2の切断
箇所1C及び1Dで切断した主索1は左右バランスが取
れており落下することはない。
Next, after the winch rope 8A is rewound to the winch 8, the worker on the upper part of the car 5 moves to the sheave 3B.
The main rope 1 is cut at a third cutting point 1D in which the distance h2 of the main rope 1 from the top of the hoistway 7 between the car pulley 5A and the second cutting point 1B is the same distance as the second cutting point 1B. The main rope 1 between the cutting section 1C of the second section 2 and the third cutting section 1D is
After the long nut 9B of the rope hanging tool 9 is screwed to the first thimble rod 2A, the winch 8 is activated to move the winch rope 8A to a predetermined length, for example, 20 mm.
cm thimble rod mounting bracket 3A
The first thimble rod 2A and the main rope 1 at the third cutting point 1D are held by attaching the thimble rod fixing member 11 to a gap provided between the first thimble rod 2 and the first thimble rod 2B.
After removing the nut 4C, the spring 4A, and the spring seat 4B from A, the main rope 1 between the first thimble rod 2A and the third cutting point 1D is pulled up to the machine room 3 to remove the existing main rope 1. finish. Here, since the distance h1 and the distance h2 from the top of the hoistway 7 of the second cutting point 1C and the third cutting point 1D are substantially the same, cutting is performed at the first and second cutting points 1C and 1D. The left main rope 1 is left-right balanced and does not fall.

【0021】次に、新設の主索1aの取り付け作業を説
明する。
Next, the work of attaching the newly installed main rope 1a will be described.

【0022】まず、段取り作業として、端部に予めソケ
ット1Aを装着した新設の主索1aを巻いた図示しない
ドラムを最上階床FAに設置し、この新設の主索1a
は、乗りかご5の図示しない出入り口及び図示しない非
常救出口及び昇降路7を介してウィンチ8及びウィンチ
ロープ8Aにて機械室3へ吊り上げられ、綱車3B及び
そらせ車3Cに巻き掛けて昇降路7の乗りかご5の上部
まで一旦降ろされる。
First, as a setup operation, a drum (not shown) having a newly installed main rope 1a with a socket 1A mounted in advance at the end thereof is installed on the top floor FA, and the newly installed main rope 1a is installed.
Is lifted to the machine room 3 by the winch 8 and the winch rope 8A via the unillustrated doorway of the car 5 and the emergency rescue exit and the hoistway 7 not shown, and is wound around the sheave 3B and the deflector wheel 3C, It is once lowered to the upper part of car 7 of car 7.

【0023】次に、乗りかご5の上部で作業者は、図7
に示すように、そらせ車3Cから垂下するまだ切断して
いない既設の主索1b及び新設の主索1aを主索昇降ガ
イド体13に取り付ける。ここで、図7に示す主索昇降
ガイド体13は、2つに分割可能な板体13A、13B
の接合部に形成され、そらせ車3Cと釣合い錘プーリ6
A間に敷設された主索1にそれぞれ挿通可能な複数の挿
通孔13Ca、13Cb、13Ccと、板体13Aに設
けられる新設の主索1aの端部やウィンチロープ8Aを
固定する固定金具13Dと、板体13A、13Bをそれ
ぞれ接合する接合金具13Eとが備えられている。ま
た、主索昇降ガイド体13へ既設の主索1b及び新設の
主索1aの取り付けは、挿通孔13Ca、13Cbに既
設の主索1bをそれぞれ挿通させ、新設の主索1aのソ
ケット1Aを両カン撚り戻し具8Cを介して固定金具1
3Dに接続する。このように主索昇降ガイド体13に取
り付けられた新設の主索1aは自重で落下するため、作
業者は機械室3で新設の主索1aを押えながらゆっくり
釣合い錘プーリ6Aまで下降させる。ここで、新設の主
索1aは両カン撚り戻し具8Cで撚りを戻しながら下降
するとともに、主索昇降ガイド体13の挿通孔13C
a、13Cbに挿通する既設の主索1bに案内されなが
ら下降するので、昇降路7の機器を衝突で差損させるこ
とはない。
Next, the worker at the upper part of the car 5
As shown in (2), an uncut main rope 1b and a new main rope 1a that are suspended from the deflector wheel 3C and are not yet cut are attached to the main rope lifting guide body 13. Here, the main rope elevating guide body 13 shown in FIG. 7 is a plate body 13A, 13B that can be divided into two.
Of the deflector wheel 3C and the counterweight pulley 6
A plurality of insertion holes 13Ca, 13Cb, 13Cc, each of which can be inserted into the main rope 1 laid between A, a fixing bracket 13D for fixing the end of the newly installed main rope 1a and the winch rope 8A provided in the plate 13A. And a joint 13E for joining the plates 13A and 13B, respectively. In addition, when attaching the existing main rope 1b and the new main rope 1a to the main rope elevating guide body 13, the existing main rope 1b is inserted into the insertion holes 13Ca and 13Cb, respectively, and the socket 1A of the new main rope 1a is connected to both sides. Fixing bracket 1 via can twist back tool 8C
Connect to 3D. Since the newly installed main rope 1a attached to the main rope elevating guide body 13 falls under its own weight, the operator slowly descends to the counterweight pulley 6A while holding down the newly installed main rope 1a in the machine room 3. Here, the newly-installed main rope 1a descends while untwisting with the double-can twist return device 8C, and the insertion hole 13C of the main rope elevating guide body 13 is inserted.
a, 13Cb, while descending while being guided by the existing main rope 1b, the equipment on the hoistway 7 is not damaged by collision.

【0024】次に、足場7Bの作業者は、新設の主索1
aを主索昇降ガイド体13から外して釣合い錘プーリ6
Aに巻き掛け、ソケット1Aに第2のシンブルロッド2
Bを取り付けた後、図8に示すように、主索昇降ガイド
体13の挿通孔13Ca、13Cbに既設の主索1bを
挿通させるとともに、挿通孔13Ccに機械室3から降
ろしたウィンチロープ8Aを挿通させた後、ウィンチロ
ープ8Aを固定金具13Dに固定し、ウィンチロープ8
Aの先端に取り付けたロープ吊り具9の長ナット9Bに
第2のシンブルロッド2Bを螺結させる。次に、機械室
3の作業者は、ウィンチ8を起動させて新設の主索1a
を機械室3へ上昇させ、シンブルロッド固定雇11を第
2のシンブルロッド2Bに装着させて新設の主索1aの
保持を行い、ロープ吊り具9から第2のシンブルロッド
2Bを外した後、バネ4A、バネ座4B、ナット4Cを
第2のシンブルロッド2Bに装着しシンブルロッド固定
雇11を取り外す。
Next, the worker of the scaffold 7B receives the newly installed main rope 1
a from the main rope elevating guide body 13 and the counterweight pulley 6
A around the socket A and the second thimble rod 2 around the socket 1A.
After attaching B, as shown in FIG. 8, the existing main rope 1b is inserted through the insertion holes 13Ca, 13Cb of the main rope lifting guide body 13, and the winch rope 8A lowered from the machine room 3 is inserted into the insertion hole 13Cc. After the insertion, the winch rope 8A is fixed to the fixing bracket 13D, and the winch rope 8A is fixed.
The second thimble rod 2B is screwed to the long nut 9B of the rope hanging tool 9 attached to the tip of A. Next, the operator of the machine room 3 activates the winch 8 to activate the newly installed main rope 1a.
Is raised to the machine room 3, the thimble rod fixed employment 11 is attached to the second thimble rod 2B to hold the newly installed main rope 1a, and the second thimble rod 2B is removed from the rope hanging tool 9. The spring 4A, the spring seat 4B, and the nut 4C are mounted on the second thimble rod 2B, and the thimble rod fixing member 11 is removed.

【0025】また、乗りかご5の上部の作業者は、機械
室3のそらせ車3C及び綱車3Bに巻き掛けられて降ろ
された新設の主索1aを乗りかごプーリ5Aに巻き掛
け、新設の主索1aの端部に予め取り付けられたソケッ
ト1Aに第1のシンブルロッド2Aを装着し、機械室3
から降ろされたウィンチロープ8Aの先端に取り付けた
ロープ吊り具9の長ナット9Bに第1のシンブルロッド
2Aを螺結させる。以下、第1のシンブルロッド2Aを
シンブルロッド取り付けブラケット3Aに取り付ける作
業は、上述した第2のシンブルロッド2Bの取り付けと
同様であるので、説明は省略する。
The worker at the upper part of the car 5 winds the newly installed main rope 1a wound around the deflecting wheel 3C and the sheave 3B of the machine room 3 around the car pulley 5A, and The first thimble rod 2A is attached to the socket 1A previously attached to the end of the main rope 1a, and the machine room 3
The first thimble rod 2A is screwed to the long nut 9B of the rope hanging tool 9 attached to the tip of the winch rope 8A that has been lowered. Hereinafter, the operation of attaching the first thimble rod 2A to the thimble rod attachment bracket 3A is the same as the operation of attaching the second thimble rod 2B described above, and a description thereof will be omitted.

【0026】さらに、他の主索1の取り替え作業も上述
した作業と同様であるので、説明は省略する。
Further, the replacement work of the other main ropes 1 is the same as the above-described work, and the description is omitted.

【0027】このように、主索1を取り替えにあたる主
索1の昇降時に、主索昇降ガイド体13や撚り戻し雇9
Aを有するロープ吊り具9や両カン撚り戻し具8Cを使
用することで、主索1の昇降時の動きが制限され、主索
1の衝突による昇降路機器の破損が防止できる。また、
主索1に生じていた撚りを戻しながら昇降することで、
複数本の主索1の張力もほぼ均一となるので、取り替え
後の主索1の張力調整作業が簡単かつ短時間に行える。
As described above, when the main rope 1 is moved up and down to replace the main rope 1, the main rope elevating guide body 13 and the untwist 9 are used.
By using the rope suspending tool 9 having the A and the double-cance twisting and returning tool 8C, the movement of the main rope 1 at the time of ascent and descent is restricted, and damage to the hoistway equipment due to the collision of the main rope 1 can be prevented. Also,
By going up and down while returning the twist that had occurred on the main rope 1,
Since the tension of the plurality of main ropes 1 is also substantially uniform, the operation of adjusting the tension of the main ropes 1 after replacement can be performed easily and in a short time.

【0028】[0028]

【発明の効果】本発明によれば、既設主索は、釣合錘プ
ーリ上部の第1切断箇所、かご上プーリと巻上機プーリ
間の既設主索を主索保持装置で把持した上方の第2切断
箇所、第1のシンブルロッドからかご上プーリへ垂下す
る既設主索の前記第2切断箇所と略同位置の第3切断箇
所で切断し、第1切断箇所から第3切断箇所で切断の都
度既設主索の回収を行い、すなわち、第1切断箇所から
第2のシンブルロッドまでをウィンチで吊り下げて回収
し、第1切断箇所から第2切断箇所までをウィンチで吊
り下げて回収し、第2切断箇所から第3切断箇所まで及
び第1のシンブルロッドから第3切断箇所までを機械室
に引き上げて回収した後、新設主索を主索以外の主索で
ガイドさせながら配設し、第2のシンブルロッドの取り
付け後に第1のシンブルロッドを機械室床部に取り付け
るようにした。このように、既設主索は3箇所で切断さ
れるので、主索回収後の運搬は人手で行うことができ、
重量物を運ぶ特別な機器が不必要となる。
According to the present invention, the existing main rope is a first cut portion at the upper portion of the counterweight pulley, and the upper part of the existing main rope between the car pulley and the hoist pulley is gripped by the main rope holding device. The second cutting position, the existing main rope hanging from the first thimble rod to the pulley on the car is cut at a third cutting position substantially at the same position as the second cutting position, and is cut from the first cutting position at the third cutting position. In each case, the existing main ropes are collected, that is, the parts from the first cutting point to the second thimble rod are suspended and collected by a winch, and the parts from the first cutting point to the second cutting point are suspended and collected by a winch. After the second cutting section to the third cutting section and the first thimble rod to the third cutting section are lifted into the machine room and collected, the new main rope is arranged while being guided by a main rope other than the main rope. After the second thimble rod is attached, And to attach the machine room floor portion Bururoddo. In this way, the existing main rope is cut at three places, so the transportation after the recovery of the main rope can be performed manually.
Special equipment for carrying heavy objects is not required.

【0029】また、このように構成したので、既設及び
新設の主索を昇降させるウィンチに撚り戻し雇を介在さ
せ、また、既設及び新設の主索を昇降させるとき、主索
昇降ガイド体の主索が挿通可能な挿通孔に両端をシンブ
ルロッドで機械室に取り付けられた主索を挿入してガイ
ドしながら昇降させるようにしたので、主索の撚りが昇
降しながら戻るとともに、撚りが戻るときに主索が振れ
て昇降路内機器に衝突することもない。
Also, with this configuration, the winch for elevating and lowering the existing and new main ropes is provided with a twist-back employment, and when raising and lowering the existing and new main ropes, the main rope lifting guide body is used. The main rope attached to the machine room with thimble rods at both ends is inserted into the insertion hole through which the rope can be inserted, and the main rope is lifted up and down while guiding it. The main rope does not swing and collide with the equipment in the hoistway.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の2:1ローピングエレベータの主索交
換方法の一実施形態を説明する昇降路の縦断面図であ
る。
FIG. 1 is a vertical sectional view of a hoistway for explaining an embodiment of a method for exchanging main ropes of a 2: 1 roping elevator according to the present invention.

【図2】本発明の一実施形態のロープ吊り具の装着状態
を示す図である。
FIG. 2 is a view showing a mounted state of the rope hanging device of one embodiment of the present invention.

【図3】本発明の一実施形態のシンブルロッド固定雇の
取り付け状態を示す図である。
FIG. 3 is a view showing an attached state of a fixed thimble rod according to an embodiment of the present invention.

【図4】図3のA−A断面図である。FIG. 4 is a sectional view taken along line AA of FIG. 3;

【図5】本発明の一実施形態のシンブルロッドにロープ
吊り具の装着状態を示す図である。
FIG. 5 is a diagram showing a state in which a rope hanger is attached to the thimble rod according to the embodiment of the present invention.

【図6】本発明の一実施形態の主索保持装置で既設主索
を把持した状態を示す図である。
FIG. 6 is a diagram illustrating a state where an existing main rope is gripped by the main rope holding device according to the embodiment of the present invention.

【図7】本発明の一実施形態の主索を下降させるときの
主索昇降ガイド体の取り付け図である。
FIG. 7 is a mounting view of the main rope elevating guide body when the main rope according to the embodiment of the present invention is lowered.

【図8】本発明の一実施形態の主索を上昇させるときの
主索昇降ガイド体の取り付け図である。
FIG. 8 is a view showing how a main rope elevating guide is attached when the main rope according to the embodiment of the present invention is raised.

【図9】第1及び第2のシンブルロッドの機械室床への
取り付けを示す図である。
FIG. 9 is a diagram showing attachment of first and second thimble rods to a machine room floor.

【符号の説明】[Explanation of symbols]

1 主索 1B 第1の切断箇所 1C 第2の切断箇所 1D 第3の切断箇所 2A 第1のシンブルロッド 2B 第2のシンブルロッド 8 ウィンチ 8A ウィンチロープ 9 ロープ吊り具 9A 撚り戻し雇 9B 長ナット 11 シンブルロッド固定雇 12 主索保持装置 13 主索昇降ガイド体 DESCRIPTION OF SYMBOLS 1 Main rope 1B 1st cutting place 1C 2nd cutting place 1D 3rd cutting place 2A 1st thimble rod 2B 2nd thimble rod 8 Winch 8A Winch rope 9 Rope hanging tool 9A Twist return employment 9B Long nut 11 Fixed thimble rod 12 Main rope holding device 13 Main rope elevating guide

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 機械室の床部に主索の両端に接続される
第1のシンブルロッド及び第2のシンブルロッドがバネ
を介して設置され、前記第1のシブルロッドと巻上機プ
ーリから垂下させた前記主索を乗りかご上部に設けたか
ご上プーリに巻き掛け、前記巻上機プーリと前記第2の
シンブルロッドから垂下させた前記主索を釣合い錘上部
に設けた釣合い錘プーリに巻き掛けるようにした2:1
ローピングエレベータの主索交換方法であって、前記釣
合い錘を昇降路底部で支持するとともに、前記乗りかご
を昇降路頂部で吊り上げた後固設して既設主索の張力を
無効とした状態で、複数本の主索を少なくとも1本づつ
交換する2:1ローピングエレベータの主索交換方法に
おいて、前記乗りかごを最上階近傍に停止させた状態で
前記既設主索の張力を無効とした後、前記既設主索の1
本を前記釣合い錘プーリ上部の第1切断箇所で切断し、
ウィンチに取り付けられたロープ吊り具に前記第2のシ
ンブルロッドの頂部を螺着させて前記第1切断箇所から
前記第2のシンブルロッドまでの前記既設主索を前記ウ
ィンチで吊り下げて回収し、前記釣合い錘プーリと前記
巻上機プーリ間の前記既設主索を前記巻上機プーリの近
傍にて主索保持装置で把持した後、この把持部分の上方
の第2切断箇所で概主索を切断し、前記主索保持装置に
前記ロープ吊り具を取り付けて前記第1切断箇所から前
記第2切断箇所までの前記既設主索を前記ウィンチで吊
り下げて回収し、前記第1のシンブルロッドから前記か
ご上プーリへ垂下する前記既設主索の前記第2切断箇所
と略同位置の第3切断箇所で切断し、前記第2切断箇所
から前記第3切断箇所までの前記既設主索及び前記第1
のシンブルロッドから前記第3切断箇所までの前記既設
主索を前記機械室に引き上げて回収した後、次に、新設
主索は、最上階床から乗りかご天井に設けた救出口を介
し前記かご上プーリに巻き掛けて前記機械室に引き上げ
前記新設主索の一端にロープソケットを取り付けた後、
前記巻上機プーリに巻き掛け該当主索以外の主索でガイ
ドしながら昇降路へ下降させ、前記釣合い錘プーリに巻
き掛けて前記ロープソケットに前記第2のシンブルロッ
ドを取り付け、前記ウィンチに取り付けられた前記ロー
プ吊り具に前記第2のシンブルロッドを螺結させて前記
機械室に吊り上げ前記第2のシンブルロッドを前記機械
室床部に設置し、さらに、前記新設主索の他端に前記ロ
ープソケット及び前記第1のシンブルロッドを取り付け
た後、前記機械室に吊り上げ前記第1のシンブルロッド
を前記機械室床部に設置するようにした2:1ローピン
グエレベータの主索交換方法。
1. A first thimble rod and a second thimble rod connected to both ends of a main rope are installed on a floor of a machine room via springs, and droop from the first sibble rod and a pulley of a hoist. The main rope thus obtained is wound around a car pulley provided above the car, and the main rope suspended from the hoisting machine pulley and the second thimble rod is wound around a counterweight pulley provided above the counterweight. 2: 1
A method of exchanging main ropes of a roping elevator, wherein the counterweight is supported at the bottom of the hoistway, and the car is hung up at the top of the hoistway and fixed to nullify the tension of the existing main ropes, In the main rope exchanging method for a 2: 1 roping elevator in which a plurality of main ropes are exchanged at least one by one, the tension of the existing main rope is invalidated while the car is stopped near a top floor, and Existing main rope 1
Cutting the book at a first cutting point above the counterweight pulley,
The top of the second thimble rod is screwed to a rope suspending device attached to a winch, and the existing main rope from the first cut portion to the second thimble rod is suspended by the winch and collected. After the existing main rope between the counterweight pulley and the hoist pulley is gripped by the main rope holding device in the vicinity of the hoist pulley, the general main rope is pulled at a second cut point above the gripped portion. Cutting, attaching the rope hanging tool to the main rope holding device, suspending and recovering the existing main rope from the first cutting point to the second cutting point with the winch, and recovering the main rope from the first thimble rod. The existing main rope hanging down to the car pulley is cut at a third cutting point substantially at the same position as the second cutting point of the existing main rope, and the existing main rope from the second cutting point to the third cutting point and the second main cutting line are cut. 1
After the existing main rope from the thimble rod to the third cutting point is lifted into the machine room and collected, the new main rope is then moved from the top floor to the car through a rescue exit provided on the car ceiling. After wrapping around the upper pulley and pulling up to the machine room, attaching a rope socket to one end of the new main rope,
Wrap the hoisting machine pulley, lower it to the hoistway while guiding it with a main rope other than the applicable main rope, wind it around the counterweight pulley, attach the second thimble rod to the rope socket, and attach it to the winch The second thimble rod is screwed to the rope hanging tool, and the second thimble rod is lifted up in the machine room, and the second thimble rod is installed on the machine room floor. A method of exchanging main ropes of a 2: 1 roping elevator, wherein a rope socket and the first thimble rod are attached, and then the first thimble rod is lifted up in the machine room and installed on the floor of the machine room.
【請求項2】 機械室の床部に主索の両端に接続される
第1のシンブルロッド及び第2のシンブルロッドがバネ
を介して設置され、前記第1のシンブルロッドと巻上機
プーリから垂下させた前記主索を乗りかご上部に設けた
かご上プーリに巻き掛け、前記巻上機プーリと前記第2
のシンブルロッドから垂下させた前記主索を釣合い錘上
部に設けた釣合い錘プーリに巻き掛けるようにした2:
1ローピングエレベータの主索交換装置であって、前記
釣合い錘を昇降路底部で支持するとともに、前記乗りか
ごを昇降路頂部で吊り上げた後固設して既設主索の張力
を無効とした状態で、複数本の主索を少なくとも1本づ
つ交換する2:1ローピングエレベータの主索交換装置
において、前記既設及び前記新設の主索を昇降させると
き、一端をシンブルロッドに螺結させ他端をウィンチに
装着するロープ吊り具と、前記既設主索の取り外し及び
前記新設の主索取り付けのとき、前記機械室の床に前記
シンブルロッドを固定するシンブルロッド固定雇と、前
記既設及び前記新設の主索に沿って上下方向に案内可能
なガイド穴と既設及び新設の主索を昇降させる昇降体が
着脱可能な取付体を有する主索昇降ガイド体と、前記既
設主索を前記乗りかごの上で切断するとき、前記主索の
切断箇所の下方に装着する主索保持装置とを備えたこと
を特徴とする2:1ローピングエレベータの主索交換装
置。
2. A first thimble rod and a second thimble rod connected to both ends of a main rope are installed on a floor of a machine room via springs, and are connected to the first thimble rod and a pulley of a hoist. The suspended main rope is wound around a car pulley provided at an upper part of a car, and the hoist pulley and the second
The main rope hung from the thimble rod is wound around a counterweight pulley provided above the counterweight.
(1) A main rope exchanging device for a roping elevator, wherein the counterweight is supported at the bottom of the hoistway, and the car is hung up at the top of the hoistway and then fixed to invalidate the tension of the existing main rope. In a main rope exchanging device for a 2: 1 roping elevator for exchanging at least one main rope at a time, when raising and lowering the existing and the new main ropes, one end is screwed to a thimble rod and the other end is a winch. A rope hanger to be mounted on the floor, a thimble rod fixing member for fixing the thimble rod to the floor of the machine room when removing the existing main rope and attaching the new main rope, and the existing and the new main rope. A main hole elevating guide body having a guide hole capable of guiding up and down along a main body, and an attaching / detaching body on which an elevating body for elevating and lowering an existing and a new main rope is mounted; When cutting on your of 2, characterized in that a main rope holding device for mounting below the cut portion of the main ropes: 1 main rope replacement device roping elevator.
【請求項3】 前記ロープ吊り具は、前記ウィンチのロ
ープ端部に着脱自在に取り付けられ、上下の回転を自在
にする撚戻し雇を備えたことを特徴とする請求項2記載
の2:1ローピングエレベータの主索交換装置。
3. The 2: 1 rope according to claim 2, wherein the rope hanger is detachably attached to a rope end of the winch, and has a twist-back member that allows vertical rotation. Main rope replacement device for roping elevators.
【請求項4】 シンブルロッド固定雇は、シャコ万力の
対向する固定部と可動部に、2分割したシンブルロッド
と螺合するナットをそれぞれ熔着させたことを特徴とす
る請求項2記載の2:1ローピングエレベータの主索交
換装置。
4. The thimble rod fixing member according to claim 2, wherein the nut fixed to the two divided thimble rods is welded to the fixed portion and the movable portion facing each other, respectively. Main rope changer for 2: 1 roping elevator.
【請求項5】 前記主索昇降ガイド体の前記昇降体に
は、主索が挿通可能な少なくとも1個の挿通孔と、既設
及び新設の主索端部に前記撚戻し雇を介して取り付けら
れる固定金具とを備えたことを特徴とする請求項2記載
の2:1ローピングエレベータの主索交換装置。
5. The at least one elevating body of the main rope elevating guide body is attached to at least one insertion hole through which a main rope can be inserted, and at the end of an existing or newly installed main rope through the twist-back union. 3. The main rope exchanging device for a 2: 1 roping elevator according to claim 2, further comprising a fixture.
JP1260697A 1997-01-27 1997-01-27 Main rope replacing method of 2:1 roping elevator and device thereof Pending JPH10203751A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1260697A JPH10203751A (en) 1997-01-27 1997-01-27 Main rope replacing method of 2:1 roping elevator and device thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1260697A JPH10203751A (en) 1997-01-27 1997-01-27 Main rope replacing method of 2:1 roping elevator and device thereof

Publications (1)

Publication Number Publication Date
JPH10203751A true JPH10203751A (en) 1998-08-04

Family

ID=11810023

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1260697A Pending JPH10203751A (en) 1997-01-27 1997-01-27 Main rope replacing method of 2:1 roping elevator and device thereof

Country Status (1)

Country Link
JP (1) JPH10203751A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6345439B2 (en) 1998-11-10 2002-02-12 Kioritz Corp. Method for manufacturing a cylinder for internal combustion engine
WO2013004899A1 (en) * 2011-07-06 2013-01-10 Kone Corporation Elevator, rope anchorage assembly for an elevator, and method for modernizing an elevator
JP2013107765A (en) * 2011-11-24 2013-06-06 Toshiba Elevator Co Ltd Elevator device
JP6417459B1 (en) * 2017-09-19 2018-11-07 東芝エレベータ株式会社 Elevator rope change assist device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6345439B2 (en) 1998-11-10 2002-02-12 Kioritz Corp. Method for manufacturing a cylinder for internal combustion engine
WO2013004899A1 (en) * 2011-07-06 2013-01-10 Kone Corporation Elevator, rope anchorage assembly for an elevator, and method for modernizing an elevator
JP2013107765A (en) * 2011-11-24 2013-06-06 Toshiba Elevator Co Ltd Elevator device
JP6417459B1 (en) * 2017-09-19 2018-11-07 東芝エレベータ株式会社 Elevator rope change assist device
JP2019052043A (en) * 2017-09-19 2019-04-04 東芝エレベータ株式会社 Elevator rope replacement auxiliary device

Similar Documents

Publication Publication Date Title
WO2020035930A1 (en) Construction elevator lifting height extension method and elevator rope lowering jig
JP4089986B2 (en) Hydraulic rope main rope replacement method
JPH10203751A (en) Main rope replacing method of 2:1 roping elevator and device thereof
JP3277486B2 (en) Existing main rope winding device of the elevator
JP3807775B2 (en) How to lift the construction elevator
JP2839970B2 (en) Elevator main cable replacement method
JP3531504B2 (en) Elevator safety equipment
JP5841929B2 (en) How to change the main rope of the elevator
JP3340322B2 (en) Elevator main cable entanglement prevention device
JPH07133085A (en) Replacement of main rope of elevator
JPH0751432B2 (en) Main rope replacement method for elevators
JP7436126B1 (en) Elevator gondola installation method and gondola device
JPH082850A (en) Work method in elevator shaft
JP2815251B2 (en) Elevator main cable replacement method
JP4790941B2 (en) Elevator main rope hanging method
JP2000344440A (en) Method of operation for hanging main rope of 2:1 roping elevator and main rope guide device therefor
JP3020325B2 (en) Elevator main cable replacement method
JP6950458B2 (en) Elevator weight removal device and weight removal method
JP2849269B2 (en) Elevator main cable replacement method
JP3464395B2 (en) Elevator main cable replacement method
JP2654409B2 (en) Elevator main cable replacement method
JPH05262475A (en) Installation method of elevator
JP3888513B2 (en) Main rope end adjustment method for 2-to-1 roping elevator
JP2849281B2 (en) Elevator main cable replacement method
JP3020337B2 (en) Elevator main cable replacement method