JPH06146311A - Construction method of underground work by completely automatic building construction system - Google Patents

Construction method of underground work by completely automatic building construction system

Info

Publication number
JPH06146311A
JPH06146311A JP4307349A JP30734992A JPH06146311A JP H06146311 A JPH06146311 A JP H06146311A JP 4307349 A JP4307349 A JP 4307349A JP 30734992 A JP30734992 A JP 30734992A JP H06146311 A JPH06146311 A JP H06146311A
Authority
JP
Japan
Prior art keywords
underground
construction
columns
automatic
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4307349A
Other languages
Japanese (ja)
Other versions
JP2845060B2 (en
Inventor
Etsunori Tamura
悦徳 田村
Toru Ono
徹 大野
Toshitaka Sakami
敏孝 酒見
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP4307349A priority Critical patent/JP2845060B2/en
Publication of JPH06146311A publication Critical patent/JPH06146311A/en
Application granted granted Critical
Publication of JP2845060B2 publication Critical patent/JP2845060B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To provide a construction method of underground work by a completely automatic building construction system capable of promoting greatly work efficiency by making use of columns to install an automatic construction device after the columns in an underground part are constructed. CONSTITUTION:A plurality of pile holes 14 are excavated in the inside surrounded by a continuous underground wall 12, pile reinforced cages are inserted into parts under the excavated bottom 16 of the pile holes 14 to cast pile concretes 18, and underground columns 20 are penetrated and are installed in an unsolidified stage of pile concretes 18. The underground columns 20 are equipped with long columns 20a and short columns 20b. After the pile concretes 18 are solidified, An automatic construction device 22 is installed across a part projecting the long columns 20a from the ground. After the installation of the automatic construction device 22, the inside of the continuous underground wall 12 is excavated, and beam materials 38 conveyed by means of a ceiling crane 30 of the automatic construction device 22 are subsequently installed as parts of the basement first floor, second floor... between the exposed underground columns 20.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、自動構築装置を用いて
行う全自動ビル建設システムによる地下工事の施工方法
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for underground construction by a fully automatic building construction system using an automatic construction device.

【0002】[0002]

【従来の技術】近年、高層ビルを自動構築装置を用いて
自動的に構築して行く全自動ビル建設システムが、例え
ば平成3年8月17日付けの建設技術新聞によって提案
されている。このように全自動建設システムを用いてビ
ルの建設作業を自動化することにより、大幅な省力化お
よび工期の短縮化等を達成することができ、また、かか
る自動構築装置を地下工事の段階から活用することによ
り、その効果を一段と向上することができる。
2. Description of the Related Art In recent years, a fully automatic building construction system for automatically constructing a high-rise building using an automatic construction apparatus has been proposed, for example, by the Construction Technology Newspaper dated August 17, 1991. By automating the construction work of the building using the fully automatic construction system in this way, it is possible to achieve significant labor saving and shortening of the construction period, and also to utilize such automatic construction equipment from the stage of underground construction. By doing so, the effect can be further improved.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、かかる
従来の全自動建設システムにあっては、通常は地上部分
の建設に用いるものであり、この全自動建設システムを
地下工事の段階から活用する場合には、まず最初に自動
構築装置を地上部分に設置した状態で地下工事を行うこ
とが考えられる。ところが、このように自動構築装置を
地上部分に設置した後に地下工事を行う場合は、地下部
分に柱を構築する際に、既に構築された自動構築装置が
邪魔になって地下部分の作業能率が著しく低下されてし
まうという課題があった。
However, such a conventional full-automatic construction system is usually used for the construction of the above-ground portion, and when this full-automatic construction system is utilized from the stage of underground construction. It is conceivable that the underground construction will be carried out with the automatic construction equipment installed on the ground first. However, when performing underground construction after installing the automatic building device on the above-ground part, when constructing a pillar in the underground part, the already built automatic building device interferes with the work efficiency of the underground part. There was a problem that it would be significantly reduced.

【0004】そこで、本発明はかかる従来の課題に鑑み
て、地下部分の柱を構築した後に、この柱を利用して自
動構築装置を設置することにより、作業能率を大幅に向
上することができる全自動ビル建設システムによる地下
工事の施工方法を提供する事を目的とする。
In view of such conventional problems, the present invention can remarkably improve work efficiency by constructing a pillar for an underground portion and then installing an automatic construction apparatus using the pillar. The purpose is to provide a construction method for underground construction using a fully automatic building construction system.

【0005】[0005]

【課題を解決するための手段】かかる目的を達成するた
めに本発明は、継足し可能な柱間に跨がって昇降可能に
取り付けられる自動構築装置を備え、この自動構築装置
を上昇しつつ地上部分の建物を逐次上層階へと構築して
行く全自動ビル建設システムによる地下工事の施工方法
において、地盤に杭孔を掘削すると共に、この杭孔の根
伐り底以下の部分にコンクリートを打設し、このコンク
リートが未硬化の状態で地上に突出する地下柱をコンク
リート内に根入れして立設し、このコンクリートが硬化
した後、この地下柱の地上突出部分に前記自動構築装置
を設置し、この状態で掘削により前記地下柱を露出させ
ると共に、自動構築装置に取り付けた天井クレーンによ
り地下階の梁部材を運搬し、この梁部材を露出した地下
柱の間に設置する。
[Means for Solving the Problems]
For this reason, the present invention is capable of going up and down across columns that can be added.
Equipped with an automatic construction device that can be installed, this automatic construction device
As the building rises, the buildings on the ground are gradually constructed to the upper floors.
Construction method of underground construction by Go-Fully Automatic Building Construction System
At the time of excavation of a pile hole in the ground,
Place concrete in the area below the felled bottom and
Concave the underground pillar protruding above the ground in the uncured state.
This concrete hardens when it is erected in the reet and erected.
After that, the above-mentioned automatic construction device
Is installed and the underground pillar is exposed by excavation in this state.
And an overhead crane attached to the automatic construction equipment.
Carrying beam members on the basement floor and exposing the beam members to the basement
Install between pillars.

【0006】[0006]

【作用】以上の構成により本発明の全自動ビル建設シス
テムによる地下工事の施工方法にあっては、地盤に掘削
した杭孔の根伐り底以下の部分にコンクリートを打設し
て、このコンクリート部分に根入れして立設した地下柱
の地上突出部分に自動構築装置を設置し、この状態で地
下部分の掘削および自動構築装置を活用した梁部分の設
置を行うようにしたので、地下柱の立設を自動構築装置
が邪魔になることなくスムーズにかつ正確に行うことが
できる。従って、このように、まず地下柱を立設した後
に、この地下柱に自動構築装置を設置してビルの構築を
進めることにより、地下部分のみならず地上部分の建物
をも効率良く、かつ、高精度をもって構築することがで
きる。
According to the construction method of the underground construction by the fully automatic building construction system of the present invention having the above construction, concrete is placed in the portion below the root cutting bottom of the pile hole excavated in the ground, and this concrete portion An automatic construction device was installed on the aboveground projecting part of the underground pillar that was erected in the ground, and in this state the excavation of the underground part and the installation of the beam part using the automatic building device were performed. The automatic construction device can be erected smoothly and accurately without getting in the way. Therefore, in this way, after the underground pillar is first erected, by installing an automatic construction device on this underground pillar to proceed with building construction, not only the underground portion but also the building on the ground portion is efficiently, and It can be built with high precision.

【0007】[0007]

【実施例】以下、本発明の実施例を添付図面を参照して
詳細に説明する。図1は本発明にかかる全自動ビル建設
システムによる地下工事の施工方法の一実施例を示す断
面図である。
Embodiments of the present invention will now be described in detail with reference to the accompanying drawings. FIG. 1 is a sectional view showing an embodiment of a construction method for underground construction by the fully automatic building construction system according to the present invention.

【0008】即ち、本実施例の全自動ビル建設システム
による地下工事の施工方法では、まず、地盤10にビル
を構築しようとする部分の周囲に連続地中壁12を構築
する。この連続地中壁12は一般に知られるように地盤
10に所定幅の溝を掘削し、その中にコンクリートを打
設することにより構築される。そして、前記連続地中壁
12で囲まれた内側に所定間隔をもって複数の杭孔1
4,14…を掘削し、この杭孔14,14…の根伐り底
16以下の部分に図外の杭用鉄筋籠を挿入して杭用コン
クリート18を流し込む。
That is, in the construction method for underground construction by the fully automatic building construction system of this embodiment, first, the continuous underground wall 12 is constructed around the portion where the building is to be constructed on the ground 10. As is generally known, the continuous underground wall 12 is constructed by excavating a groove having a predetermined width in the ground 10 and placing concrete in the groove. Then, a plurality of pile holes 1 are formed inside the continuous underground wall 12 at predetermined intervals.
4, 14, ... Are excavated, and a rebar cage for piles (not shown) is inserted into a portion of the pile holes 14, 14 ... below the root cutting bottom 16 to pour concrete 18 for piles.

【0009】次いで、前記流し込んだ杭用コンクリート
18が未硬化の段階で、前記杭孔14,14…にそれぞ
れ本設の地下柱20を挿入し、これら地下柱20を未硬
化の杭用コンクリート18に根入れして設置する。尚、
前記地下柱20は半PC柱が用いられる。ところで、前
記地下柱20は地上から突出して設置される長尺柱20
a,20a…と、地上で止められる短尺柱20b,20
b…とを備え、これら長尺柱20a,20a…と短尺柱
20b,20b…とは、長尺柱20aが前記連続地中壁
12に接するようにして交互に設置される。
Next, when the poured concrete 18 for piles is uncured, the underground pillars 20 which are permanently installed are inserted into the pile holes 14, 14 ..., and these underground pillars 20 are uncured concrete 18 for piles. Rooted in and installed. still,
A semi-PC pillar is used as the underground pillar 20. By the way, the underground pillar 20 is a long pillar 20 installed so as to project from the ground.
a, 20a ... and short columns 20b, 20 that can be stopped on the ground
b, and the long columns 20a, 20a ... And the short columns 20b, 20b ... Are alternately installed so that the long columns 20a are in contact with the continuous underground wall 12.

【0010】そして、前記杭用コンクリート18が硬化
した後、前記長尺柱20a,20a…が地上から突出す
る部分に跨がって自動構築装置22を設置する。自動構
築装置22は、移動フレーム24と、この移動フレーム
24の上部に取り付けられる上方クレーンガーダー26
と、下部に取り付けられる下方クレーンガーダー28と
を備え、本実施例では下方クレーンガーダー28に天井
クレーン30が走行可能に取り付けられる。
After the concrete 18 for piles is hardened, the automatic construction device 22 is installed across the portion where the long columns 20a, 20a ... The automatic construction device 22 includes a moving frame 24 and an upper crane girder 26 attached to an upper portion of the moving frame 24.
And a lower crane girder 28 attached to the lower part, and an overhead crane 30 is movably attached to the lower crane girder 28 in this embodiment.

【0011】前記移動フレーム24は、長尺柱20a,
20a…の外周を覆うように枠状に構成され、その下端
部に設けられた昇降装置32を介して、これら長尺柱2
0a,20a…およびこれら長尺柱20a,20a…の
上端に順次継ぎ足される図外の地上部分の柱をクライミ
ング(上方移動)できるようになっている。即ち、前記
昇降装置32は、上下一対の締付バンド32a,32b
と、これら締付バンド32a,32b間に取り付けられ
る伸縮ジャッキ32cとを備え、一対の締付バンド32
a,32bを交互に解放することに伴って、伸縮ジャッ
キ32cを伸縮させることにより、この伸縮ジャッキ3
2cの伸長分を移動単位として上方に順次移動される。
尚、前記自動構築装置22には上方クレーンガーダー2
6の上側間に跨がって膜屋根34が敷設され、この膜屋
根34で作業現場を覆うことにより、雨天での作業が可
能になっている。
The moving frame 24 is composed of long columns 20a,
These long columns 2 are formed in a frame shape so as to cover the outer periphery of the long columns 20a.
0a, 20a, ..., And the pillars of the above-mentioned ground portion, which are successively added to the upper ends of these long pillars 20a, 20a, can be climbed (moved upward). That is, the lifting device 32 includes a pair of upper and lower tightening bands 32a and 32b.
And a telescopic jack 32c attached between these tightening bands 32a and 32b.
By expanding and contracting the expansion / contraction jack 32c along with alternately releasing a and 32b, the expansion / contraction jack 3
The extension of 2c is used as a movement unit to sequentially move upward.
The automatic construction device 22 includes an upper crane girder 2
A membrane roof 34 is laid across the upper side of 6, and by covering the work site with the membrane roof 34, work in rainy weather is possible.

【0012】そして、前記自動構築装置22を設置した
後、長尺柱20a,20a…の地上突出部分に図外の梁
材を組立てして、これら長尺柱20a,20a…を固定
し、次いで、連続地中壁12の内側をパワーショベル等
の掘削機36を用いて一次掘削し、地下1階部分の前記
地下柱20を露出する。そして、このように地下1階部
分の地下柱20が露出されると、前記自動構築装置22
の天井クレーン30を用いて梁材38を運搬し、この梁
材38を地下柱20間に設置して固定する。このように
地下1階の梁材38が設置された後、更に二次掘削して
地下2階部分の地下柱20を露出し、この露出した地下
柱20間に天井クレーン30で運搬した梁材38を設置
する。このようにして逐次下層階へと掘削し、露出した
地下柱20間に梁材38を設置して行く。
After the automatic construction device 22 is installed, a beam member (not shown) is assembled to the above-ground protruding portions of the long columns 20a, 20a ... And these long columns 20a, 20a. The inside of the continuous underground wall 12 is primarily excavated by using an excavator 36 such as a power shovel to expose the underground pillar 20 on the first basement. When the underground pillar 20 on the first basement floor is exposed in this manner, the automatic construction device 22
The beam member 38 is transported by using the overhead crane 30, and the beam member 38 is installed and fixed between the underground columns 20. After the beam material 38 on the first basement floor is installed in this manner, the secondary material is further excavated to expose the underground pillars 20 on the second basement floor, and the beam material carried by the overhead crane 30 between the exposed underground pillars 20. Install 38. In this way, excavation is sequentially performed on the lower floors, and the beam member 38 is installed between the exposed underground columns 20.

【0013】従って、本実施例の地下工事の施工方法を
用いた全自動ビル建設システムでは、まず、地盤10に
掘削した杭孔14の根伐り底16以下の部分に杭用コン
クリート18を打設し、このコンクリート18部分に根
入れして地下柱20を立設した後、この地下柱20の長
尺柱20a,20a…間に自動構築装置22を設置す
る。そして、地下部分の一次掘削,二次掘削…を行いつ
つ、地下1階部分,地下2階部分…と順次露出した地下
柱20間に梁材38を設置するようになっている。従っ
て、地下柱20を立設した後に自動構築装置22を設置
するため、この自動構築装置22が邪魔になること無く
地下柱20の立設を可能にし、延いては、地下柱20の
構築をスムーズにかつ正確に行うことができる。従っ
て、本実施例では全自動ビル建設システムを用いて地下
工事の着工時から地上工事の躯体最終時まで、同一シス
テムを用いることができ、ビル工事の大幅な工期短縮お
よび工費節減を図ることができる。
Therefore, in the fully-automatic building construction system using the construction method for the underground construction of this embodiment, first, the concrete 18 for piles is placed in the portion below the root cutting bottom 16 of the pile hole 14 excavated in the ground 10. Then, after the underground pillar 20 is erected by being embedded in the concrete 18 portion, the automatic construction device 22 is installed between the long pillars 20a, 20a ... Of the underground pillar 20. Then, while performing the primary excavation, the secondary excavation ... of the underground portion, the beam member 38 is installed between the underground pillars 20 which are sequentially exposed from the underground first floor portion, the underground second floor portion ... Therefore, since the automatic construction device 22 is installed after the underground pillar 20 is erected, the automatic construction device 22 enables the underground pillar 20 to be erected without any hindrance, and in turn, the construction of the underground pillar 20. It can be done smoothly and accurately. Therefore, in this embodiment, the same system can be used from the start of the underground construction to the final stage of the skeleton of the ground construction by using the fully automatic building construction system, and it is possible to significantly shorten the construction period of the building construction and reduce the construction cost. it can.

【0014】また、本実施例では前記地下柱20の長尺
柱20a,20a…を利用して自動構築装置22を設置
するようにしたので、地上部分に余分に自動構築装置2
2の取付用の柱を構築する必要がなくなるため、大幅な
コストダウンを図ることができる。また、地下部分を掘
削する際、地下1階部分,地下2階部分…と順次露出し
た地下柱20間に梁材38を設置するようにしたので、
これら梁材38が桟橋,切梁等の役目をして地下柱20
間を補強することができ、この点からもコストダウンを
図ることができる。
Further, in the present embodiment, since the automatic construction device 22 is installed by utilizing the long columns 20a, 20a ... Of the underground column 20, the automatic construction device 2 is additionally provided on the ground portion.
Since it is not necessary to construct the second mounting pillar, it is possible to significantly reduce the cost. Further, when excavating the underground portion, since the beam member 38 is installed between the underground pillar 20 that is sequentially exposed from the underground first floor portion, the underground second floor portion ...
These beam members 38 function as piers, beams, etc.
The space can be reinforced, and the cost can be reduced from this point as well.

【0015】[0015]

【発明の効果】以上説明したように、本発明にかかる全
自動ビル建設システムにより地下工事の施工方法にあっ
ては、まず、地盤に杭孔を掘削して、この杭孔の根伐り
底以下の部分に打設したコンクリート部分に根入れして
地下柱を立設し、この地下柱の地上突出部分に自動構築
装置を設置した後に、地下部分の掘削および自動構築装
置を活用した梁部分の設置を行うようにしたので、地下
柱の立設を自動構築装置が邪魔になることなくスムーズ
にかつ正確に行うことができる。従って、このように、
まず地下柱を立設した後に、この地下柱に自動構築装置
を設置してビルの構築を進めることにより、地下部分の
みならず地上部分の建物をも効率良く、かつ、高精度を
もって構築することができる。
As described above, in the construction method for underground construction by the fully automatic building construction system according to the present invention, first, a pile hole is excavated in the ground, and the root of the pile hole is cut below the root. The underground column is erected by embedding it in the concrete part that was placed in the section of the basement, and after installing the automatic building device on the aboveground projecting part of this underground column, excavation of the underground part and the beam part using the automatic building device Since the installation is performed, the underground pillar can be erected smoothly and accurately without the automatic construction device interfering. So, like this,
First of all, after constructing an underground pillar, install an automatic construction device on this underground pillar to proceed with building construction, so that not only the underground portion but also the aboveground building can be constructed efficiently and with high accuracy. You can

【0016】また、本発明では地下工事から地上工事に
移行する際に、自動建設装置の架け代えを必要としない
ため、地下工事の着工時から地上工事の躯体最終時まで
同一システムにより行うことができるため、全自動建設
システムによる建設をスムーズに行うことができるた
め、工期の大幅な短縮および工費節減を図ることができ
るという各種優れた効果を奏する。
Further, according to the present invention, when the underground construction is transferred to the ground construction, it is not necessary to replace the automatic construction equipment. Therefore, the same system can be used from the start of the underground construction to the final construction of the ground construction. Therefore, the construction by the fully-automatic construction system can be smoothly carried out, so that various excellent effects that the construction period can be greatly shortened and the construction cost can be reduced can be obtained.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明にかかる全自動ビル建設システムによる
地下工事の施工方法の一実施例を示す断面図である。
FIG. 1 is a sectional view showing an embodiment of a construction method for underground construction by a fully automatic building construction system according to the present invention.

【符号の説明】[Explanation of symbols]

10 地盤 12 連続地中
壁 14 杭孔 16 根伐り底 18 杭用コンクリート 20 地下柱 20a 長尺柱 20b 短尺柱 22 自動構築装置 30 天井クレ
ーン 36 掘削機 38 梁材
10 Ground 12 Continuous Underground Wall 14 Pile Hole 16 Clearing Bottom 18 Concrete for Pile 20 Underground Column 20a Long Column 20b Short Column 22 Automatic Construction Device 30 Overhead Crane 36 Excavator 38 Beam Material

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 継足し可能な柱間に跨がって昇降可能に
取り付けられる自動構築装置を備え、この自動構築装置
を上昇しつつ地上部分の建物を逐次上層階へと構築して
行く全自動ビル建設システムによる地下工事の施工方法
において、 地盤に杭孔を掘削すると共に、この杭孔の根伐り底以下
の部分にコンクリートを打設し、このコンクリートが未
硬化の状態で地上に突出する地下柱をコンクリート内に
根入れして立設し、このコンクリートが硬化した後、こ
の地下柱の地上突出部分に前記自動構築装置を設置し、
この状態で掘削により前記地下柱を露出させると共に、
自動構築装置に取り付けた天井クレーンにより地下階の
梁部材を運搬し、この梁部材を露出した地下柱の間に設
置することを特徴とする全自動ビル建設システムによる
地下工事の施工方法。
1. An automatic building device which is mounted so as to be able to move up and down across pillars that can be added, and which builds up the automatic building device to successively build a building on the ground to the upper floors. In the underground construction method using the automatic building construction system, a pile hole is excavated in the ground, and concrete is placed below the root cut bottom of this pile hole, and this concrete projects to the ground in an uncured state. Underground pillars are embedded in the concrete and erected, and after this concrete has hardened, the above-mentioned automatic building device is installed in the aboveground protruding portion of this underground pillar,
While exposing the underground pillar by excavation in this state,
A construction method for underground construction by a fully automatic building construction system, characterized in that a beam member on the basement floor is carried by an overhead crane attached to an automatic construction device, and the beam member is installed between exposed underground columns.
JP4307349A 1992-11-17 1992-11-17 Construction method of underground construction by fully automatic building construction system Expired - Fee Related JP2845060B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4307349A JP2845060B2 (en) 1992-11-17 1992-11-17 Construction method of underground construction by fully automatic building construction system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4307349A JP2845060B2 (en) 1992-11-17 1992-11-17 Construction method of underground construction by fully automatic building construction system

Publications (2)

Publication Number Publication Date
JPH06146311A true JPH06146311A (en) 1994-05-27
JP2845060B2 JP2845060B2 (en) 1999-01-13

Family

ID=17968039

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4307349A Expired - Fee Related JP2845060B2 (en) 1992-11-17 1992-11-17 Construction method of underground construction by fully automatic building construction system

Country Status (1)

Country Link
JP (1) JP2845060B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804115A (en) * 2016-02-29 2016-07-27 济南轨道交通集团有限公司 Integrated construction device and construction method for fabricated diaphragm wall or precast pile and fabricated underground station
CN106759487A (en) * 2017-02-14 2017-05-31 中国冶集团有限公司 Underground pipe gallery inner formwork system continuous-flow type construction method
WO2021031860A1 (en) * 2019-08-22 2021-02-25 上海建工二建集团有限公司 Beam lowering construction method of subsurface structure in top-down method
CN112663619A (en) * 2020-11-18 2021-04-16 中铁二局集团有限公司 Foundation pit cover plate and support system construction method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10138616B2 (en) * 2016-08-12 2018-11-27 Wuhan Zhihe Geotechnical Engineering Co., Ltd. Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0270845A (en) * 1988-09-05 1990-03-09 Ohbayashi Corp Construction apparatus
JPH04323467A (en) * 1991-01-17 1992-11-12 Toda Constr Co Ltd Building method for building

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0270845A (en) * 1988-09-05 1990-03-09 Ohbayashi Corp Construction apparatus
JPH04323467A (en) * 1991-01-17 1992-11-12 Toda Constr Co Ltd Building method for building

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804115A (en) * 2016-02-29 2016-07-27 济南轨道交通集团有限公司 Integrated construction device and construction method for fabricated diaphragm wall or precast pile and fabricated underground station
CN106759487A (en) * 2017-02-14 2017-05-31 中国冶集团有限公司 Underground pipe gallery inner formwork system continuous-flow type construction method
WO2021031860A1 (en) * 2019-08-22 2021-02-25 上海建工二建集团有限公司 Beam lowering construction method of subsurface structure in top-down method
CN112663619A (en) * 2020-11-18 2021-04-16 中铁二局集团有限公司 Foundation pit cover plate and support system construction method

Also Published As

Publication number Publication date
JP2845060B2 (en) 1999-01-13

Similar Documents

Publication Publication Date Title
EP0537189B1 (en) A method of erecting a foundation structure for a building substructure
JPH06146311A (en) Construction method of underground work by completely automatic building construction system
CN100529274C (en) Method of constructing strip, foundations with longitudinal socket
KR102149662B1 (en) Method for constructing transfer layer of building using precast concrete slab
KR100455247B1 (en) Cast-in-site diaphragms wall and the method with benoto method and grouting method of high pressure
KR0179708B1 (en) Working method for underground structure of a building
JPH0684690B2 (en) Building basement extension method
JPH01256636A (en) Construction method of building
KR910007423B1 (en) Method for construction p.c - beam on the bridge
JPH10299003A (en) Foundation work using precast concrete member
JPH07103583B2 (en) Construction method for large span underground structure
JPH0584773B2 (en)
JPH09151470A (en) Work execution method for underground structure
JP2002194759A (en) Underground structure constructing method
JPS63537A (en) Construction work of underground structure
SU1000519A1 (en) Method of erecting a foundation with a sleeve
SU853031A1 (en) High-building construction method
JPH0881964A (en) Body structure of building with underground section and execution method thereof
JP2761526B2 (en) How to build structures
SU718586A1 (en) Method of erecting multistorey building floors
JPS6217233A (en) Foundation base column
JPH04363470A (en) Floor construction device
JP2761528B2 (en) How to build structures
JPH04363471A (en) Building construction method
JPH10280434A (en) Construction method for basement under application of outside waterproofing

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees