JPH06123152A - Method for constructing floor plate, floor and beam - Google Patents

Method for constructing floor plate, floor and beam

Info

Publication number
JPH06123152A
JPH06123152A JP27467192A JP27467192A JPH06123152A JP H06123152 A JPH06123152 A JP H06123152A JP 27467192 A JP27467192 A JP 27467192A JP 27467192 A JP27467192 A JP 27467192A JP H06123152 A JPH06123152 A JP H06123152A
Authority
JP
Japan
Prior art keywords
mold
floor
plate
floor slab
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27467192A
Other languages
Japanese (ja)
Other versions
JP3196147B2 (en
Inventor
Hiroo Takada
博尾 高田
Shiyou Meranii
メラニー・ショウ
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP27467192A priority Critical patent/JP3196147B2/en
Publication of JPH06123152A publication Critical patent/JPH06123152A/en
Application granted granted Critical
Publication of JP3196147B2 publication Critical patent/JP3196147B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE:To enhance construction properties by mounting a beam mold to the peripheral edge portion of a floor plate made of precast concrete, installing the beam mold in a predetermined position, and then placing concrete on the floor plate and inside the mold, thereby using the mold as a permanent mold. CONSTITUTION:A floor plate mold is installed at a construction site and a beam mold 14 is disposed around the mold and concrete is poured into the floor plate mold so as to fabricate a PICOS plate 11 provided with the mold 14 connected thereto by means of a pin, etc. Next, the plate 11 is placed on floor plate timbering 22 assembled in a predetermined position. Then bottom plates 16 are bent from the side faces 15 of the mold 14 and the lower end portions of the adjacent bottom plates 16 are made to abut to each other and beam timbering 23 is assembled therebelow. Concrete slabs are placed on the plate 11 and inside the mold 14, and a beam which uses the mold 14 as a permanent mold therefor and a composite floor are integrally constructed. The need for the work of installing the beam mold is therefore eliminated, and the labor required and the construction period can both be reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、建築構造物に使用され
る床版と、それを用いた床・梁の施工方法にに関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a floor slab used in a building structure and a floor / beam construction method using the same.

【0002】[0002]

【従来の技術】周知のように、床版の構築方法としては
従来より種々の工法が開発提供されているが、その一つ
に本出願人が提供した、工場又は現場における製作ヤー
ドで製作したプレキャストコンクリート製床版(以下、
「PICOS版」という。)と、現場打ちコンクリート
スラブとの床版及び床・梁の施工方法を構築する工法、
所謂PICOS工法がある。
2. Description of the Related Art As is well known, various construction methods have been developed and provided as a method for constructing a floor slab, and one of them has been manufactured in a factory or on-site production yard provided by the applicant. Precast concrete floor slab (below,
It is called "PICOS version". ), And a construction method for constructing a floor slab with a cast-in-place concrete slab and a floor / beam construction method,
There is a so-called PICOS method.

【0003】従来、このPICOS工法では、図11に
示すように、現場でPICOS版1の床版用型枠2を設
置し、この床版用型枠2にコンクリートを打設すること
により、PICOS版1を製造する。このPICOS版
1に合板からなる棧木3を載せ、この棧木3に床版用型
枠2を載せ、コンクリートを打設することにより、PI
COS版1を製造する。こうして、PICOS版1と棧
木3とを交互に積み重ねておく。
Conventionally, in this PICOS construction method, as shown in FIG. 11, a floor slab form 2 of a PICOS slab 1 is installed on site, and concrete is placed on the floor slab form 2 to form a PICOS. Produce version 1. By placing a wood 3 made of plywood on the PICOS plate 1, and placing a floor slab 2 on the wood 3 and placing concrete, the PI
COS plate 1 is manufactured. In this way, the PICOS plate 1 and the Satsuki 3 are alternately stacked.

【0004】一方、図12に示すように、現場に、床版
用支保工4を組み立てるとともに、梁用支保工5を組み
立てる。この梁用支保工5の上部に梁型枠6を架設す
る。前記PICOS版1のコンクリートが養生した後、
このPICOS版1を揚重して前記床版用支保工4の上
に載せる。その後、PICOS版1の上にコンクリート
スラブを打設するとともに、梁型枠6にコンクリートを
打設することにより、床版及び床・梁の施工方法と梁と
を構築するものである。
On the other hand, as shown in FIG. 12, the floor slab support 4 and the beam support 5 are assembled on site. The beam formwork 6 is installed on the upper part of the beam supporting structure 5. After the PICOS version 1 concrete is cured,
The PICOS plate 1 is lifted and placed on the floor plate supporter 4. After that, a concrete slab is cast on the PICOS plate 1 and concrete is cast on the beam form 6, thereby constructing a floor slab, a floor / beam construction method, and a beam.

【0005】[0005]

【発明が解決しようとする課題】前記PICOS版1
は、床工事を合理化できるものであるが、PICOS版
1を固定する梁は、PICOS版が揚重される前に、梁
型枠を設置し、PICOS版が揚重された後に、梁型枠
にコンクリートを打設して構築される。このため、梁の
施工作業に多大な期間を要するとともに、梁の施工作業
に多大な労力を要した。
[Problems to be Solved by the Invention] The PICOS version 1
Is a floor work that can be rationalized. However, for the beam that fixes the PICOS plate 1, the beam form is installed before the PICOS plate is lifted, and after the PICOS plate is lifted, the beam form It is constructed by pouring concrete into. Therefore, the construction work of the beam requires a great deal of time, and the construction work of the beam requires a great deal of labor.

【0006】本発明は前記課題を有効に解決するもの
で、梁の施工作業に要する期間を短縮できるとともに、
梁の施工作業に要する労力を低減させた床版及び床・梁
の施工方法を提供することを目的とする。
The present invention effectively solves the above-mentioned problems, and shortens the period required for the construction work of beams, and
It is an object of the present invention to provide a floor slab and a floor / beam construction method that reduce the labor required for beam construction work.

【0007】[0007]

【課題を解決するための手段】請求項1記載の床版は、
プレキャストコンクリート製床版の周縁部に、該プレキ
ャストコンクリート製床版を支持する梁を構築するため
の梁型枠を取り付けてなることを特徴とするものであ
る。
A floor slab according to claim 1 is
A beam form for constructing a beam for supporting the precast concrete floor slab is attached to a peripheral portion of the precast concrete floor slab.

【0008】請求項2記載の床・梁の施工方法は、あら
かじめ製作したプレキャストコンクリート製床版の周縁
部に梁型枠を取り付けてなる床版を床及び梁の構築位置
に設置し、前記梁型枠内及び前記プレキャストコンクリ
ート製床版の上面側にコンクリートを打設して、捨て型
枠とする前記梁型枠と前記コンクリートとからなる梁
と、前記床版と前記コンクリートとからなる合成床とを
構築することを特徴とするものである。
According to a second aspect of the present invention, in the method of constructing a floor / beam, a floor slab having a beam form attached to a peripheral portion of a precast concrete floor slab produced in advance is installed at a construction position of the floor and the beam. Concrete is placed in the formwork and on the upper surface side of the precast concrete floor slab, and a beam composed of the beam formwork and the concrete as a discard formwork, and a composite floor composed of the floor slab and the concrete It is characterized by constructing and.

【0009】[0009]

【作用】請求項1記載の床版では、プレキャストコンク
リート製床版の周縁部に、該プレキャストコンクリート
製床版を支持する梁を構築するための梁型枠を取り付け
てなるから、プレキャストコンクリート製床版を現場に
組み立てることにより、梁型枠が現場に設置される。こ
のため、梁型枠の設置作業が不要になる。
In the floor slab according to claim 1, since a beam form for constructing a beam for supporting the precast concrete floor slab is attached to a peripheral portion of the precast concrete floor slab, the precast concrete floor The beam formwork is installed on site by assembling the plates on site. Therefore, the work of installing the beam form becomes unnecessary.

【0010】請求項2記載の床・梁の施工方法では、あ
らかじめ製作したプレキャストコンクリート製床版の周
縁部に梁型枠を取り付けてなる床版を床及び梁の構築位
置に設置するから、梁型枠の設置作業が不要になる。そ
の後、前記梁型枠内及び前記プレキャストコンクリート
製床版の上面側にコンクリートを打設して、捨て型枠と
する前記梁型枠と前記コンクリートとからなる梁と、前
記床版と前記コンクリートとからなる合成床とを構築す
るから、床・梁が一体に構築される。
In the floor / beam construction method according to the second aspect of the present invention, since the floor slab in which the beam form is attached to the peripheral portion of the precast concrete floor slab that is manufactured in advance is installed at the construction position of the floor and the beam. Eliminates the work of installing the formwork. Then, by placing concrete in the beam formwork and on the upper surface side of the precast concrete floor slab, a beam consisting of the beam formwork and the concrete to be a discard formwork, the floor slab and the concrete Since the composite floor consisting of is constructed, the floor and the beams are constructed integrally.

【0011】[0011]

【実施例】以下、本発明の床版及び床・梁の施工方法の
一実施例について、図1ないし図5を参照しながら説明
する。図1に示すように、床版(図示略)は、プレキャ
ストコンクリート製床版11(以下、PICOS版とい
う。)と、現場打ちコンクリートスラブ(図示略)とを
有してなるものである。以下、詳細に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the floor slab and floor / beam construction method of the present invention will be described below with reference to FIGS. As shown in FIG. 1, the floor slab (not shown) includes a precast concrete floor slab 11 (hereinafter referred to as PICOS plate) and a cast-in-place concrete slab (not shown). The details will be described below.

【0012】PICOS版11は、工場もしくは現場で
製作され、プレキャストコンクリートからなる外観視長
方形状の床版本体12と、この床版本体12の周縁部に
取り付けられた梁型枠14とから構成されている。この
梁型枠14は、図2ないし図3に示すように、床版本体
12に上端部が回動自在にピン結合された側板15と、
この側板15の下端部に上端部が回動自在にピン結合さ
れた底板16とから構成されている。
The PICOS plate 11 is manufactured in a factory or on-site, and is composed of a floor slab main body 12 made of precast concrete and having a rectangular shape in appearance, and a beam form 14 attached to the peripheral portion of the floor slab main body 12. ing. As shown in FIGS. 2 to 3, the beam form frame 14 includes a side plate 15 whose upper end is rotatably pin-coupled to the floor slab body 12,
The side plate 15 is composed of a bottom plate 16 whose upper end is rotatably pin-connected to the lower end.

【0013】すなわち、梁型枠14は、その延びる方向
に沿って二分割されており、底板16の下端部が別の梁
型枠14の底板16の下端部に当接される構成にされて
いる。ここで、床版本体12と梁型枠14との接合部で
は、床版本体12の各辺の下端部が面取りされ、梁型枠
14の側板15が下方に回動自在に取り付けられてい
る。
That is, the beam form 14 is divided into two along the extending direction thereof, and the lower end of the bottom plate 16 is in contact with the lower end of the bottom plate 16 of another beam form 14. There is. Here, at the joint between the floor slab main body 12 and the beam form 14, the lower end of each side of the floor slab main body 12 is chamfered, and the side plate 15 of the beam form 14 is rotatably attached downward. .

【0014】このようなPICOS版を使用したPIC
OS工法について、図面を用いて説明する。図4に示す
ように、現場に床版用型枠20を設置し、この床版用型
枠20の周囲に梁型枠14を配置する。前記床版用型枠
20にコンクリートを打設することにより、PICOS
版11を製造する。このPICOS版11に棧木21を
載せ、この棧木3に床版用型枠20と梁型枠とを載せ、
コンクリートを打設することにより、PICOS版11
を製造する。こうして、PICOS版11と棧木21と
を交互に積み重ねておく。
PIC using such PICOS plate
The OS method will be described with reference to the drawings. As shown in FIG. 4, the floor slab formwork 20 is installed on the site, and the beam formwork 14 is arranged around the floor slab formwork 20. By placing concrete on the floor slab 20, PICOS
The plate 11 is manufactured. The wood 21 is placed on the PICOS plate 11, and the floor slab form 20 and the beam form are placed on the wood 3.
By placing concrete, PICOS plate 11
To manufacture. In this way, the PICOS plates 11 and the Satsuki 21 are alternately stacked.

【0015】一方、図1に示すように、現場に、床の構
築位置に床版用支保工22を組み立てておき、PICO
S版11のコンクリートが養生した後、このPICOS
版11を揚重して前記床版用支保工22の上に載せる。
このときに、床版本体12から梁型枠14が吊り下げら
れる。その後、図5に示すように、梁型枠14の側板1
5から底板16を折り曲げ、この底板16の下端部を別
の梁型枠14の底板16に当接させ、これら梁型枠14
を覆う梁用支保工23を組み立てる。その後、PICO
S版1の上と梁型枠14とにコンクリートスラブを打設
することにより、梁型枠14を捨て型枠とする梁(図示
略)と、合成床(図示略)とを一体に構築するものであ
る。
On the other hand, as shown in FIG. 1, a floor slab support 22 has been assembled at the construction position of the floor at the site, and PICO
After curing the S plate 11 concrete, this PICOS
The plate 11 is lifted and placed on the floor slab support 22.
At this time, the beam formwork 14 is suspended from the floor slab body 12. After that, as shown in FIG. 5, the side plate 1 of the beam form 14 is formed.
The bottom plate 16 is bent from 5, and the lower end portion of this bottom plate 16 is brought into contact with the bottom plate 16 of another beam form 14,
Assembling the beam support 23 for covering. After that, PICO
By placing a concrete slab on the S plate 1 and the beam form 14, a beam (not shown) using the beam form 14 as a discard form and a composite floor (not shown) are integrally constructed. It is a thing.

【0016】このような床版によれば、PICOS版1
1の周縁部に、PICOS版11を支持する梁を構築す
るための梁型枠14を取り付けてなるから、PICOS
版11を床版用支保工22に載置することにより、梁型
枠14が現場に設置される。この梁型枠14を梁用支保
工23で覆うことにより、梁型枠14が組み立てられ
る。このため、PICOS版11の施工作業とは別個に
梁型枠14を設置する必要性をなくすことができ、梁の
施工作業に要する労力を低減できる。そして、PICO
S版11を組み立てるときに、梁型枠14を設置できる
から、PICOS版11梁の施工作業に要する期間を短
縮できる。
According to such a floor slab, the PICOS plate 1
A beam form frame 14 for constructing a beam for supporting the PICOS plate 11 is attached to the peripheral edge of the PICOS 1.
By placing the plate 11 on the floor slab support 22, the beam formwork 14 is installed on site. The beam formwork 14 is assembled by covering the beam formwork 14 with the beam support 23. For this reason, it is possible to eliminate the need to install the beam formwork 14 separately from the construction work of the PICOS plate 11, and it is possible to reduce the labor required for the construction work of the beam. And PICO
Since the beam formwork 14 can be installed when assembling the S plate 11, the period required for the construction work of the PICOS plate 11 beam can be shortened.

【0017】一方、床・梁の施工方法によれば、前記床
版を床及び梁の構築位置に設置するから、梁型枠14の
設置作業を不要にでき、梁型枠14の設置作業に要する
労力を低減できる。その後、梁型枠14内及びPICO
S版11の上面側にコンクリートを打設して、捨て型枠
とする前記梁型枠14と前記コンクリートとからなる梁
と、前記床版と前記コンクリートとからなる合成床とを
構築するから、床及び梁を一体に構築することができ
る。このため、床の施工作業と梁の施工作業とを別個に
行なう場合に比べ、これら床と梁との施工に要する期間
を短縮でき、さらに、作業者も少なくて良くなる。
On the other hand, according to the floor / beam construction method, since the floor slab is installed at the building position of the floor and the beam, the installation work of the beam formwork 14 can be eliminated, and the installation work of the beam formwork 14 can be performed. The labor required can be reduced. After that, in the beam form 14 and PICO
Since concrete is cast on the upper surface side of the S plate 11 to construct a beam composed of the beam form 14 and the concrete to be a discard form, and a composite floor composed of the floor slab and the concrete, The floor and beams can be constructed in one piece. Therefore, as compared with the case where the floor construction work and the beam construction work are performed separately, the period required for the construction of the floor and the beams can be shortened, and the number of workers can be reduced.

【0018】なお、前記実施例では、床版本体12と梁
型枠14の側板15とをピン結合したが本願はこれに限
定するものでなく、図6ないし図7に示すように、床版
本体12と梁型枠14の側板15とに、ゴム、鉄、プラ
スチック、繊維等の可撓性材料30を打ち込み、床版本
体12の周縁部の下端部を切り欠き、この床版本体12
の切り欠かれた部分31に対向する梁型枠14の側板1
5に、切り欠き部分31を形成してもよい。これら床版
本体12と梁型枠14との切り欠かれた部分31が当接
することにより、床版本体14から梁型枠14が下方に
吊り下げられた状態になる。そして、可撓性材料30の
可撓性を高めるために、該可撓性材料30に、スリット
加工、穴開け加工、折り曲げ加工を施してもよい。さら
に、図8に示すように、可撓性材料30の位置に、床版
用アンカー32と、梁型枠用アンカー33とを打ち込
み、これら床版用アンカー32と梁型枠用アンカー33
とをヒンジ部34で結合してもよい。
Although the floor slab main body 12 and the side plate 15 of the beam form 14 are pin-coupled in the above embodiment, the present invention is not limited to this, and as shown in FIGS. A flexible material 30 such as rubber, iron, plastic, or fiber is driven into the main body 12 and the side plate 15 of the beam form 14, and the lower end of the peripheral edge of the floor slab main body 12 is cut out.
Side plate 1 of the beam formwork 14 facing the notched portion 31 of the
The notch 31 may be formed in the groove 5. By contacting the notched portions 31 of the floor slab body 12 and the beam form frame 14, the beam form frame 14 is suspended downward from the floor slab body 14. Then, in order to increase the flexibility of the flexible material 30, the flexible material 30 may be subjected to slit processing, punching processing, and bending processing. Further, as shown in FIG. 8, a floor slab anchor 32 and a beam form anchor 33 are driven into the position of the flexible material 30, and the floor slab anchor 32 and the beam form anchor 33 are inserted.
And may be connected by the hinge portion 34.

【0019】また、可撓性材料30の代わりとして、図
9ないし図10に示すように、床版本体12に床用アン
カー35を打ち込み、この床用アンカー35に略鉛直方
向に延びる接続プレート36を取り付け、この接続プレ
ート36に断面視L字状の梁型枠36をボルト等の締結
部材38で取り付けてもよい。
Further, as an alternative to the flexible material 30, as shown in FIGS. 9 to 10, a floor anchor 35 is driven into the floor slab body 12, and a connection plate 36 extending substantially vertically to the floor anchor 35. The beam form 36 having an L-shaped cross section may be attached to the connection plate 36 with a fastening member 38 such as a bolt.

【0020】[0020]

【発明の効果】以上説明したように、本発明の床版及び
床・梁の施工方法によれば、以下の効果を奏することが
できる。請求項1記載の床版によれば、プレキャストコ
ンクリート製床版の周縁部に、該プレキャストコンクリ
ート製床版を支持する梁を構築するための梁型枠を取り
付けてなる構成にしたから、プレキャストコンクリート
製床版を現場で組み立てることにより、梁型枠が組み立
てられる。このため、プレキャストコンクリート製床版
の施工作業とともに梁型枠を設置することができ、梁の
施工作業に要する労力を低減できる。そして、プレキャ
ストコンクリート製床版を組み立てるときに、梁型枠を
組み立てることができるから、梁の施工作業に要する期
間を短縮できる。
As described above, according to the floor slab and floor / beam construction method of the present invention, the following effects can be achieved. According to the floor slab of claim 1, since the beam form for constructing the beam for supporting the precast concrete floor slab is attached to the peripheral portion of the precast concrete floor slab, the precast concrete is constructed. The beam formwork is assembled by assembling the floor slab on site. Therefore, the beam form can be installed together with the construction work of the precast concrete floor slab, and the labor required for the construction work of the beam can be reduced. Then, when the precast concrete floor slab is assembled, the beam form can be assembled, so that the period required for the construction work of the beam can be shortened.

【0021】請求項2記載の床・梁の施工方法によれ
ば、あらかじめ製作したプレキャストコンクリート製床
版の周縁部に梁型枠を取り付けてなる床版を床及び梁の
構築位置に設置する構成にしたから、梁型枠の設置作業
を不要にでき、梁型枠の設置作業に要する労力を低減で
きる。そして、前記梁型枠内及び前記プレキャストコン
クリート製床版の上面側にコンクリートを打設して、捨
て型枠とする前記梁型枠と前記コンクリートとからなる
梁と、前記床版と前記コンクリートとからなる合成床と
を構築する構成にしたから、床及び梁を一体に構築する
ことができる。このため、床の施工作業と梁の施工作業
とを別個に行なう場合に比べ、これら床と梁との施工に
要する期間を短縮でき、さらに、作業者も少なくて良
い。
According to the floor / beam construction method of the second aspect, the floor slab, in which the beam form is attached to the peripheral portion of the precast concrete floor slab produced in advance, is installed at the construction position of the floor and the beam. Therefore, the installation work of the beam formwork can be eliminated, and the labor required for the installation work of the beam formwork can be reduced. Then, by placing concrete in the beam formwork and on the upper surface side of the precast concrete floor slab, a beam composed of the beam formwork and the concrete to be a discard formwork, the floor slab and the concrete. The floor and the beams can be integrally constructed because the composite floor consisting of is constructed. For this reason, compared with the case where the floor construction work and the beam construction work are performed separately, the period required for the construction of the floor and the beam can be shortened, and the number of workers can be reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の床版におけるPICOS版を示す側面
図である。
FIG. 1 is a side view showing a PICOS plate in a floor slab of the present invention.

【図2】図1の床版本体と梁型枠との接続部分を示す側
面図である。
FIG. 2 is a side view showing a connecting portion between the floor slab main body and the beam formwork of FIG.

【図3】水平方向に延びる梁型枠を示す側面図である。FIG. 3 is a side view showing a beam form frame extending in a horizontal direction.

【図4】図1のPICOS版を積み上げた状態を示す側
面図である。
FIG. 4 is a side view showing a state in which the PICOS plates of FIG. 1 are stacked.

【図5】図1のPICOS版を組み立てた状態を示す側
面図である。
5 is a side view showing an assembled state of the PICOS plate of FIG. 1. FIG.

【図6】図2の第一変形例を示す側面図である。FIG. 6 is a side view showing a first modified example of FIG.

【図7】図6における梁型枠を水平方向に延ばした状態
を示す側面図である。
7 is a side view showing a state where the beam form in FIG. 6 is extended in the horizontal direction.

【図8】図2の第二変形例を示す側面図である。FIG. 8 is a side view showing a second modified example of FIG.

【図9】図2の第三変形例を示す側断面図である。FIG. 9 is a side sectional view showing a third modified example of FIG.

【図10】図9の正面図である。FIG. 10 is a front view of FIG. 9.

【図11】従来のPICOS版を積み上げた状態を示す
側面図である。
FIG. 11 is a side view showing a state in which conventional PICOS plates are stacked.

【図12】図11のPICOS版を組み立てた状態を示
す側面図である。
12 is a side view showing a state where the PICOS plate of FIG. 11 is assembled.

【符号の説明】[Explanation of symbols]

11 PICOS版(プレキャストコンクリート製床
版) 14 梁型枠
11 PICOS version (precast concrete floor slab) 14 Beam formwork

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 プレキャストコンクリート製床版の周縁
部に、該プレキャストコンクリート製床版を支持する梁
を構築するための梁型枠を取り付けてなることを特徴と
する床版。
1. A floor slab, wherein a beam form for constructing a beam for supporting the precast concrete floor slab is attached to a peripheral portion of the precast concrete floor slab.
【請求項2】 あらかじめ製作したプレキャストコンク
リート製床版の周縁部に梁型枠を取り付けてなる床版を
床及び梁の構築位置に設置し、前記梁型枠内及び前記プ
レキャストコンクリート製床版の上面側にコンクリート
を打設して、捨て型枠とする前記梁型枠と前記コンクリ
ートとからなる梁と、前記床版と前記コンクリートとか
らなる合成床とを構築することを特徴とする床・梁の施
工方法。
2. A prefabricated concrete floor slab having a beam form attached to the periphery of the prefabricated concrete floor slab is installed at the construction position of the floor and the beam, and the precast concrete slab A floor characterized by placing concrete on the upper surface side to construct a beam composed of the beam formwork and the concrete to be a discard formwork, and a composite floor composed of the floor slab and the concrete. Beam construction method.
JP27467192A 1992-10-13 1992-10-13 Construction method of floor slab and floor / beam Expired - Fee Related JP3196147B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27467192A JP3196147B2 (en) 1992-10-13 1992-10-13 Construction method of floor slab and floor / beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27467192A JP3196147B2 (en) 1992-10-13 1992-10-13 Construction method of floor slab and floor / beam

Publications (2)

Publication Number Publication Date
JPH06123152A true JPH06123152A (en) 1994-05-06
JP3196147B2 JP3196147B2 (en) 2001-08-06

Family

ID=17544942

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27467192A Expired - Fee Related JP3196147B2 (en) 1992-10-13 1992-10-13 Construction method of floor slab and floor / beam

Country Status (1)

Country Link
JP (1) JP3196147B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485654A (en) * 2019-01-25 2020-08-04 河南天久装配式建筑有限公司 Connecting structure of descending plate and steel beam in prefabricated building and construction method
CN114704014A (en) * 2021-12-15 2022-07-05 上海结奕建筑咨询事务所 Construction method of semi-prefabricated assembly type steel-concrete structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485654A (en) * 2019-01-25 2020-08-04 河南天久装配式建筑有限公司 Connecting structure of descending plate and steel beam in prefabricated building and construction method
CN114704014A (en) * 2021-12-15 2022-07-05 上海结奕建筑咨询事务所 Construction method of semi-prefabricated assembly type steel-concrete structure

Also Published As

Publication number Publication date
JP3196147B2 (en) 2001-08-06

Similar Documents

Publication Publication Date Title
KR100760393B1 (en) Precast concrete panel and method for constructing a slab using the panel
KR101482522B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
JPH06123152A (en) Method for constructing floor plate, floor and beam
KR200434622Y1 (en) Precast concrete panel
JPH05311680A (en) Wiring pit ditch and its construction method
JP2566872B2 (en) Megane Bridge Wind Assembly Bridge
JP2000303602A (en) Pc floor slab, and floor slab execution method using the same
JPH0762779A (en) Constitution of floor opened port part
JPH11256765A (en) Structure and method for reinforcing concrete beam
JP2985595B2 (en) PC formwork
KR102375439B1 (en) Pc slab structure using horizontal connecting reinforcement
JPS5817053Y2 (en) Frame frame for wall with opening
JP3082147B2 (en) Construction method of reinforced concrete structures
JPH07113321A (en) Construction of continuous footing for house
JPH0444550A (en) Semi-precast rc building
JP3677093B2 (en) Concrete foundation
JPH0841899A (en) Construction method for foundation beam and pc plate for beam
KR910006123Y1 (en) Form units for the floor
JPH02120446A (en) Precast concrete panel
JPH0725363Y2 (en) Concrete beam
JPS59177445A (en) Semi-pc slab construction method and semi-pc panel used therein
JP2512327Y2 (en) Concrete formwork for underground beams
JPH07197475A (en) Structure of foundation
JPH01271526A (en) Construction method for foundation
JP2890132B2 (en) Manufacturing method of precast concrete slab

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20010424

LAPS Cancellation because of no payment of annual fees