JPH0540763A - Development project schedule management system - Google Patents
Development project schedule management systemInfo
- Publication number
- JPH0540763A JPH0540763A JP19565691A JP19565691A JPH0540763A JP H0540763 A JPH0540763 A JP H0540763A JP 19565691 A JP19565691 A JP 19565691A JP 19565691 A JP19565691 A JP 19565691A JP H0540763 A JPH0540763 A JP H0540763A
- Authority
- JP
- Japan
- Prior art keywords
- progress
- development project
- degree
- delay
- plan
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は新規開発プロジェクトの
日程管理方式に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a schedule management system for a new development project.
【0002】[0002]
【従来の技術】新規開発プロジェクトの日程管理は、管
理の迅速化、省力化の追求のために機械化されてきてい
るが、従来、実績進捗度が予め設定した計画日程よりも
遅延した場合には、表示装置等を介して警告を発する様
になっていた。2. Description of the Related Art The schedule management of a new development project has been mechanized in order to speed up the management and pursue labor saving, but conventionally, when the achievement progress is delayed from a preset schedule, , A warning was issued via a display device or the like.
【0003】[0003]
【発明が解決しようとする課題】上述した従来の新規開
発プロジェクト日程管理方式では、進捗実績度が計画進
捗度より遅延したことにより警告を発する方式としてい
るため、新規開発プロジェクトの開発期間に応じて遅延
限度を弾力的に管理できないという欠点がある。In the above-mentioned conventional new development project schedule management system, a warning is issued when the progress achievement level is delayed from the planned progress level, so that it is possible to change according to the development period of the new development project. There is a drawback that the delay limit cannot be managed flexibly.
【0004】[0004]
【課題を解決するための手段】本発明の新規開発プロジ
ェクト日程管理方式は、新規開発プロジェクトの開始時
期,終了時期,計画日程からの遅延限度値および開発プ
ロジェクトの開始から終了までを一定間隔で区切った場
合の各区切り時点における計画進捗度を入力しておき、
また新規開発プロジェクトの進展に伴い前記区切り時点
に到達した段階での進捗実績度を入力することにより、
前記計画進捗度と進捗実績度とから計画との遅延を計算
し、前記進捗実績度が前記計画進捗度よりも前記遅延限
度値以上に拡大していると計算される場合には表示装置
を介して警告を発することを特徴とする。[Means for Solving the Problems] The new development project schedule management system of the present invention divides a new development project start time, end time, delay limit value from a planned schedule, and development project start to end at regular intervals. Enter the plan progress at each break point in case of
In addition, by inputting the progress record level at the stage when the break point was reached as the new development project progresses,
A delay from the plan is calculated from the plan progress and the progress record, and when the progress record is calculated to be larger than the plan progress by the delay limit value or more, via a display device. It is characterized by issuing a warning.
【0005】[0005]
【実施例】次に、本発明について図面を参照して説明す
る。DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, the present invention will be described with reference to the drawings.
【0006】図1は本発明の新規開発プロジェクト日程
管理システムの処理を示したものである。以下、図1を
参照しながら詳細に説明する。FIG. 1 shows the processing of the newly developed project schedule management system of the present invention. Hereinafter, a detailed description will be given with reference to FIG.
【0007】まず、新規開発プロジェクトの開始時期と
終了時期を、日程管理システムと論理的に接続されたキ
ーボード(図示していない)より入力する(図の処理1
1)。次に、新規開発プロジェクトの開始時期と終了時
期を一定間隔に区切り、この場合、開発期間が1年間の
ケースを想定すると毎週の計画日程進捗目標点を上述と
同様にキーボードより入力する(処理12)。First, the start time and the end time of a new development project are input from a keyboard (not shown) logically connected to the schedule management system (process 1 in the figure).
1). Next, the start time and the end time of the new development project are divided at regular intervals, and in this case, assuming that the development period is one year, the weekly planned schedule progress target point is input from the keyboard as described above (Process 12). ).
【0008】次に、新規開発プロジェクトの今後の進捗
実績度が、処理12により入力された各週毎の進捗目標
点に到達せず、遅延している場合に外部表示装置(表示
していない)に警告を表示するか否かの遅延の度合いを
示すパラメータaを前述と同様にキーボードより入力す
る(処理13)。以上により、新規プロジェクト日程管
理システムへの初期データ入力が完了したことになり、
以降に述べることがプロジェクト完了まで接続される
(処理14)。Next, if the future progress record of the new development project does not reach the progress target point for each week input by the process 12 and is delayed, it is displayed on the external display device (not displayed). A parameter a indicating the degree of delay of whether or not to display a warning is input from the keyboard as described above (process 13). By the above, the initial data input to the new project schedule management system is completed,
The following is connected until the project is completed (process 14).
【0009】まず、新規開発プロジェクトが開始されて
1週間が経過する毎に日程管理システムへ進捗実績度を
入力する(処理15)。ここで、プロジェクト開始当初
は進捗目標点とほぼ同じ度合いで進捗実績度が推移して
いるものとする。First, each time one week has passed since the start of a new development project, the progress record level is input to the schedule management system (process 15). Here, at the beginning of the project, it is assumed that the progress achievement level has moved to a degree similar to the progress target point.
【0010】次に、40週間の経過時点で進捗目標点よ
りも遅延が生じたとする。この時点で、日程管理システ
ムは目標点と実績度の開きを計算し(処理16)、遅延
が生じていることから処理17へ進む。Next, it is assumed that there is a delay from the progress target point when 40 weeks have passed. At this point, the schedule management system calculates the difference between the target point and the achievement level (process 16), and since there is a delay, the process proceeds to process 17.
【0011】次に、日程管理システムは過去40週分の
進捗実績度から今後の実績度予測を行ない、処理13に
より入力されたパラメータaとの相関により警告を発す
るか否か判定する。判定方法の一例を次に示す。Next, the schedule management system predicts the future achievement level from the progress achievement level for the past 40 weeks, and determines whether or not to issue a warning based on the correlation with the parameter a input in the process 13. An example of the determination method is shown below.
【0012】今、パラメータaとして「105%」が与
えられていたとする。即ち現状の実績が計画よりも遅延
していた場合に、今までの進捗実績ベースを100%と
して、今後は105%にまでペースを高めても開発終了
時に計画日程通りに完了せず遅延すると予測される場合
に警告を発するものと解釈される。Now, assume that "105%" is given as the parameter a. In other words, if the current performance is behind schedule, it is predicted that the progress performance base up to now will be 100%, and even if the pace is increased to 105% in the future, it will not be completed according to the plan schedule at the end of development and will be delayed. If it is done, it will be interpreted as issuing a warning.
【0013】従って、40週経過時点で3日間の遅延が
生じていた場合、計画完了までの12週間を105%に
ベースアップしたとしてTherefore, if there is a delay of 3 days after the 40th week, it is assumed that the 12 weeks until the completion of the plan has been increased to 105%.
【0014】 [0014]
【0015】週で完了することになる。It will be completed in a week.
【0016】即ち、(12−11.43)=0.57週
の短縮が図れる訳で週7日であることから0.57×7
=3.4、即ち3.4日短縮可となり現状での遅延3日
間を挽回可能となる。従ってこの場合は元来考慮されて
いた5%余裕(マージン)の中でカバーし得ると判断し
警告にまでは至らない。That is, since (12-11.43) = 0.57 weeks can be shortened and it is 7 days a week, 0.57 × 7.
= 3.4, that is, 3.4 days can be shortened, and the current 3 days delay can be recovered. Therefore, in this case, it is judged that the coverage can be covered within the originally considered 5% margin, and no warning is given.
【0017】一方、40週経過時点で4日間の遅延が生
じた場合には、上記過程でも明らかな様に5%余裕の中
でカバーできない事になるので警告を発し注意を促す
(処理18)。On the other hand, if there is a delay of 4 days after the elapse of 40 weeks, as will be apparent from the above process, it cannot be covered within a 5% margin, so a warning is issued and caution is requested (process 18). .
【0018】[0018]
【発明の効果】以上説明したように、本発明は開発プロ
ジェクトの経時の進捗目標点に対する実績度との開き具
合と余裕マージン度とから遅延に対する警告の有無を判
断する構成としたことにより、柔軟な管理ができるとい
う効果がある。As described above, according to the present invention, whether or not there is a warning for a delay is determined based on the degree of difference between the achievement level with respect to the progress target point of the development project and the margin degree. There is an effect that can be managed properly.
【図1】本発明に示すプロジェクト日程管理システムの
処理を示したものである。FIG. 1 shows a process of a project schedule management system according to the present invention.
Claims (1)
時期,計画日程からの遅延限度値および開発プロジェク
トの開始から終了までを一定間隔で区切った場合の各区
切り時点における計画進捗度を入力しておき、 また新規開発プロジェクトの進展に伴い前記区切り時点
に到達した段階での進捗実績度を入力することにより、
前記計画進捗度と進捗実績度とから計画との遅延を計算
し、前記進捗実績度が前記計画進捗度よりも前記遅延限
度値以上に拡大していると計算される場合には表示装置
を介して警告を発することを特徴とする開発プロジェク
ト日程管理方式。1. The start time and end time of a new development project, the delay limit value from the planned schedule, and the plan progress at each break point when the start and end of the development project are separated at regular intervals. By inputting the progress record at the stage when the break point was reached as the new development project progresses,
A delay from the plan is calculated from the plan progress and the progress record, and when the progress record is calculated to be larger than the plan progress by the delay limit value or more, via a display device. Development project schedule management method characterized by issuing a warning.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19565691A JPH0540763A (en) | 1991-08-06 | 1991-08-06 | Development project schedule management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19565691A JPH0540763A (en) | 1991-08-06 | 1991-08-06 | Development project schedule management system |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0540763A true JPH0540763A (en) | 1993-02-19 |
Family
ID=16344807
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19565691A Pending JPH0540763A (en) | 1991-08-06 | 1991-08-06 | Development project schedule management system |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0540763A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002304456A (en) * | 2001-04-03 | 2002-10-18 | Yamatake Building Systems Co Ltd | Operation task control system |
KR20030093083A (en) * | 2002-05-29 | 2003-12-06 | 가부시끼가이샤 히다치 세이사꾸쇼 | Project risk management system and project risk management apparatus |
JP2008059368A (en) * | 2006-08-31 | 2008-03-13 | Ricoh Co Ltd | Workflow management system, workflow management method, workflow management program, and recording medium |
-
1991
- 1991-08-06 JP JP19565691A patent/JPH0540763A/en active Pending
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002304456A (en) * | 2001-04-03 | 2002-10-18 | Yamatake Building Systems Co Ltd | Operation task control system |
KR20030093083A (en) * | 2002-05-29 | 2003-12-06 | 가부시끼가이샤 히다치 세이사꾸쇼 | Project risk management system and project risk management apparatus |
JP2008059368A (en) * | 2006-08-31 | 2008-03-13 | Ricoh Co Ltd | Workflow management system, workflow management method, workflow management program, and recording medium |
US8155988B2 (en) | 2006-08-31 | 2012-04-10 | Ricoh Company, Ltd. | Workflow management including determination if a requestor is in charge of tasks |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4102695B2 (en) | Batch job management system and batch job management program | |
US6122621A (en) | Method and system for progress management assistance | |
JPH0540763A (en) | Development project schedule management system | |
JP3325789B2 (en) | Map display device | |
JP3012448B2 (en) | Work management system | |
US3483508A (en) | Offset transition control system for a traffic controller | |
JPH11156679A (en) | Production scheduling device and recording medium recording production scheduling program | |
JP2019212150A (en) | Operation schedule generation device, and operation schedule generation program | |
JPH11168039A (en) | Method for indicating procedure of manufacturing semiconductor device | |
JPH05290053A (en) | Providing method for flowing information in production management system of small scale many kinds | |
JPH04201675A (en) | Train operation control method | |
JP3198604B2 (en) | Continuous schedule management system | |
JPH02167654A (en) | Load adjustment in manufacture execution program of production control system | |
JPH06332909A (en) | Plan managing system | |
JPH05108116A (en) | Process control device | |
JPH10171666A (en) | Task control block management mechanism and its managing method | |
JP3260632B2 (en) | Multiple data format table management method | |
JP2785302B2 (en) | Expert system knowledge base management system. | |
JPH01311351A (en) | Recognition system for system constitution at formation of system | |
JPS6092955A (en) | Command device for recovery time of delay of train | |
JP2002175353A (en) | Operation plan planning method and operation plan planning device using the method | |
JP2001203776A (en) | System and method for displaying line state change and control program recording medium | |
JPH02127732A (en) | Job control system | |
JP2000056812A (en) | Lot starting order deciding system and work plan system | |
JPH05100808A (en) | Processing progress situation display system |