JPH0533533Y2 - - Google Patents

Info

Publication number
JPH0533533Y2
JPH0533533Y2 JP1987117588U JP11758887U JPH0533533Y2 JP H0533533 Y2 JPH0533533 Y2 JP H0533533Y2 JP 1987117588 U JP1987117588 U JP 1987117588U JP 11758887 U JP11758887 U JP 11758887U JP H0533533 Y2 JPH0533533 Y2 JP H0533533Y2
Authority
JP
Japan
Prior art keywords
anchor
main body
substrate
slope
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1987117588U
Other languages
Japanese (ja)
Other versions
JPS6424121U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP1987117588U priority Critical patent/JPH0533533Y2/ja
Publication of JPS6424121U publication Critical patent/JPS6424121U/ja
Application granted granted Critical
Publication of JPH0533533Y2 publication Critical patent/JPH0533533Y2/ja
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Description

【考案の詳細な説明】 [産業上の利用分野] 本考案は山の斜面等に設置して道路や線路等を
雪崩・落石または崩土から保護するための雪崩・
落石等防護壁に関する。
[Detailed description of the invention] [Industrial application field] This invention is an avalanche protection system installed on mountain slopes to protect roads, railways, etc. from avalanches, falling rocks, or collapsed soil.
Regarding protective walls against falling rocks, etc.

[従来の技術] 従来、この種のものとして鋼板側の斜梁材と支
柱材と止雪材とをそれぞれ溶着一体化したもの
が、実開昭47−30903号公報で提案され、またコ
ンクリート製の支柱と横柱と控柱とを一体化して
ものが特公昭57−34406号公報で提案されている。
しかし、これらは両者共現場打で基礎コンクリー
トを施工し、この基礎コンクリート上に鋼板製ま
たはコンクリート製の柱または止雪材等を構築し
ていたため、山間部までコンクリート打設機械を
運搬しなければならず施工が面倒である上、基礎
コンクリートが固まるまで待たねばならず工期が
長くかかるという問題点があつた。そこで、基礎
コンクリートなどを用いずに施工ができるものと
して、実開昭53−62105号公報には基礎を必要と
しない落石防護柵用支柱が提案されており、この
防護柵は、斜面に載置する支圧板の下面に楔形の
挿入支持部材を設けるとともに、その支圧板の上
面に支柱を一体に立設し、前記挿入支持部材を斜
面に差し込んで支柱を仮固定するとともに、支柱
の上端に連結した複数の縦支持ロープ等を張設し
て防護柵の支柱を固定するものである。
[Prior Art] Conventionally, a structure of this type in which diagonal beam members, support members, and snow blocking materials on the steel plate side were welded and integrated was proposed in Japanese Utility Model Application Publication No. 47-30903, and a structure made of concrete was also proposed. Japanese Patent Publication No. 57-34406 proposes a structure in which the pillars, horizontal pillars, and retaining pillars are integrated.
However, in both cases, the foundation concrete was cast on site, and steel plate or concrete pillars, snow blocking materials, etc. were constructed on top of this foundation concrete, so concrete pouring machines had to be transported to mountainous areas. However, there were problems in that the construction was troublesome and the construction period took a long time as it required waiting until the foundation concrete had hardened. Therefore, Japanese Utility Model Application Publication No. 53-62105 proposes a pillar for a rockfall protection fence that does not require a foundation, and can be constructed without using foundation concrete. A wedge-shaped insertion support member is provided on the lower surface of the bearing pressure plate, and a column is integrally erected on the upper surface of the bearing pressure plate, the insertion support member is inserted into the slope to temporarily fix the column, and the column is connected to the upper end of the column. In this method, the posts of the protective fence are fixed by stretching multiple vertical support ropes, etc.

[考案が解決しようとする問題点] 上記防護柵では、支柱に加わつた雪崩・落石な
どの荷重が、該支柱に溶着一体化した支圧板及び
挿入支持部材に直接的に働くため、それらの荷重
の勢いを効果的に吸収することができない面があ
り、また、その荷重により支柱が倒れてしまう
と、この支柱に溶着一体化した支圧板及び挿入支
持部材も斜面から外れてしまい、斜面の地辷りを
防止する効果がまつたく失われてしまうという問
題があつた。
[Problems to be solved by the invention] In the above-mentioned protective fence, the loads of avalanches, falling rocks, etc. applied to the pillars act directly on the bearing plate and insertion support member that are welded and integrated with the pillars, so those loads are There is a surface that cannot effectively absorb the force of the slope, and if the support collapses due to that load, the bearing plate and insertion support member welded to the support will also come off the slope, causing the ground on the slope to fall. There was a problem that the effect of preventing slippage was quickly lost.

そこで本考案は工期の短縮および機械施工の割
合を削減でき、また、雪崩・落石などの荷重の勢
いを効果的に吸収することができ、さらに、斜面
の地辷防止効果を継続して備えた雪崩・落石等防
護壁を提供することを目的とする。
Therefore, this invention can shorten the construction period and reduce the ratio of mechanical construction, can effectively absorb the force of loads such as avalanches and falling rocks, and has the effect of continuously preventing landslides on slopes. The purpose is to provide a protective barrier against avalanches and falling rocks.

[問題点を解決するための手段] 本考案はアンカーにより斜面に定着されたプレ
キヤストコンクリート製基板と、この基板上に立
設され荷重を受ける防護面を山側に対向して設け
たプレキヤフトコンクリート製主体と、前記基板
と主体を連結する緩衝用連結部とを備え、この緩
衝用連結部を前記アンカーの定着力より小さくか
つ所定以上の荷重により破壊可能に設けて構成さ
れる。
[Means for solving the problem] The present invention consists of a precast concrete substrate fixed to a slope by an anchor, and a precast concrete substrate that is erected on this substrate and has a protective surface facing the mountain side that receives the load. It includes a main body made of concrete, and a buffer connecting portion that connects the base plate and the main body, and the buffer connecting portion is provided so as to be able to be broken by a load that is smaller than the fixing force of the anchor and exceeds a predetermined value.

[作用] 上記構成により、工場で製作したプレキヤスト
コンクリート製の基板と主体を用いて斜面に防護
壁を施工する。そして雪崩・落石などの荷重が、
アンカーの定着力より小さくかつ所定以上の場
合、緩衝用連結部が破壊してその荷重の勢いを緩
衝することができ、また、緩衝用連結部の破壊後
も基板はアンカーによつて定着された状態で斜面
に残るため、その基板とアンカーとにより継続し
て斜面の地辷りを防止することができる。
[Operation] With the above configuration, a protective wall is constructed on a slope using a precast concrete substrate and main body manufactured in a factory. And the loads of avalanches, falling rocks, etc.
If the anchoring force is smaller than the fixing force of the anchor, but greater than a predetermined value, the buffering connection will break and the force of the load can be buffered, and even after the buffering connection is broken, the board will remain fixed by the anchor. Since it remains on the slope in the same condition, the base plate and the anchor can continue to prevent the slope from sliding.

[実施例] 以下、本考案の実施例を添付図面を参照して説
明する。
[Embodiments] Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.

第1図および第2図は本考案の第1実施例を示
し、同図において、1は山の斜面2にアンカー3
により定着された基板であり、この基板1上には
前面部4Aと控部4Bとを有する側面三角形状の
主体4が前記基板1に固設されたアンカボルト・
ナツト5によつて締結され、このアンガボルト・
ナツト5による基板1と主体4との緩衝用連結部
である締結部5Aは、アンカー3による基板1の
定着力により小さくかつ所定以上の荷重を防護面
Aに受けると破壊するように構成されている。6
は前記主体4に複数段に配設された梁であり、こ
の梁6の前面と主体1の前面とにより、山側に対
向する防護面Aを構成している。7は地辷面であ
り、前記アンカー3はその地辷面7を貫通して岩
盤に達している。8はアンカーヘツドである。こ
の場合、前記主体4、梁6および基板1はPC材
または鉄筋補強さたコンクリートで成形し互いに
ボルト・ナツトで連結してもよくあるいはボル
ト・ナツト締してもよい。またアンカー3はアー
スアンカーあるいはロツクアンカー等を1又は2
以上用い、PC鋼材を用いて基板1を斜面に支圧
させてもよい。
1 and 2 show a first embodiment of the present invention, in which 1 indicates an anchor 3 attached to a mountain slope 2.
A main body 4 having a triangular side surface and having a front part 4A and a retaining part 4B is fixed to the board 1 by an anchor bolt fixed to the board 1.
It is fastened by nut 5, and this unga bolt
The fastening portion 5A, which is a buffer connecting portion between the substrate 1 and the main body 4 by the nut 5, is configured to break when the protection surface A receives a small but predetermined load or more due to the fixing force of the substrate 1 by the anchor 3. There is. 6
is a beam arranged in plural stages on the main body 4, and the front surface of the beam 6 and the front surface of the main body 1 constitute a protective surface A facing the mountain side. Reference numeral 7 indicates a sliding surface, and the anchor 3 penetrates through the sliding surface 7 and reaches the bedrock. 8 is an anchor head. In this case, the main body 4, the beam 6, and the substrate 1 may be made of prestressed concrete or reinforced concrete and connected to each other with bolts and nuts, or may be fastened with bolts and nuts. Also, anchor 3 can be used with 1 or 2 earth anchors, lock anchors, etc.
Using the above method, the substrate 1 may be pressed against the slope using a prestressed steel material.

そして、基板1、主体4および梁6を工場にて
製造し、基板1と主体4とを工場内または現場の
平地あるいは斜面にて組立て、その後斜面2の地
中深く固設したアンカー3に前記基板1を定着さ
せ、梁6を主体4に取付ける。または、工場にて
製造された基板1、主体4および梁6を工場内ま
たは現場の平地にて組立て、その後組立てられた
状態で基板1をアンカー3に定着し、隣接する各
梁6をコンクリートまたは鋼材等に接続する。
The substrate 1, the main body 4, and the beam 6 are manufactured in a factory, and the substrate 1 and the main body 4 are assembled in the factory or on a flat ground or slope at the site, and then the anchor 3 fixed deep underground on the slope 2 is attached to the base plate 1 and the main body 4. The substrate 1 is fixed and the beam 6 is attached to the main body 4. Alternatively, the board 1, main body 4, and beam 6 manufactured in a factory may be assembled in the factory or on a flat ground at the site, and then the assembled board 1 is fixed to the anchor 3, and each adjacent beam 6 is attached to concrete or Connect to steel materials, etc.

このようにして施工された後雪崩・落石または
崩土が発生した場合、その荷重が防護壁の許容範
囲内であれば防護壁で受け止められ、所定以上す
なわち許容範囲より大であれば、アンカボルト・
ナツト5による基板1と主体4との締結部が破壊
し、雪崩・落石等の勢いを緩衝させることができ
る。この場合、基板1はアンカー3によつて定着
された状態で残るためアンカー3による地辷面7
の地辷防止機能を維持することができる。
If an avalanche, falling rock, or collapsed earth occurs after construction is completed in this way, if the load is within the allowable range of the protective wall, it will be absorbed by the protective wall, and if it is greater than the specified value, that is, greater than the allowable range, the anchor bolt・
The fastening portion between the base plate 1 and the main body 4 by the nut 5 is destroyed, and the force of an avalanche, falling rock, etc. can be buffered. In this case, since the substrate 1 remains fixed by the anchors 3, the ground surface 7 caused by the anchors 3
The anti-slip function can be maintained.

上記実施例においては、基板1、主体4および
梁6を全て工場にて製造するものであるため、安
価で高品質の防護壁が得られる。また、斜面安定
化のためのアンカー3が防護壁の基礎工となつて
基板1を定着するものであるため、従来の基礎コ
ンクリートの現場打施工を省略でき工期を短縮で
き、機械施工の割合を削減することができる。さ
らに、斜面上の雪崩・落石または崩土防護対策と
傾斜地盤の安定化とを同時に実現できて合理的で
ある上、雪崩・落石等の荷重が一定許容範囲を超
えるきと防護壁が部分的に破損するように構成し
たため、その破損により荷重の勢いを緩衝でき、
かつ破損後も地辷面の7の下部まで達するアンカ
ー3と基板1とにより地盤安定化、地辷防止機能
を継続して維持することができる。
In the embodiment described above, the substrate 1, main body 4, and beam 6 are all manufactured in a factory, so that an inexpensive and high-quality protective wall can be obtained. In addition, since the anchors 3 for stabilizing the slope serve as the foundation for the protective wall and anchor the substrate 1, the conventional on-site pouring of foundation concrete can be omitted, shortening the construction period and reducing the proportion of mechanical construction. can be reduced. Furthermore, it is rational to simultaneously realize measures to protect against avalanches, falling rocks, or collapsed soil on slopes and stabilizing the sloped ground, and if the load of avalanches, falling rocks, etc. Since the structure is designed to cause damage, the damage can buffer the force of the load.
Furthermore, even after breakage, the anchor 3 and the base plate 1 that reach the lower part of the sliding surface 7 can continue to maintain the ground stabilization and landslide prevention functions.

第3図は本考案の第2実施例を示し、上記実施
例と同一部分に同一符号を用い同一箇所の説明を
省略して説明すると、アンカー3により斜面2に
定着される基板1の上面中央には突部9が一体に
形成され、この突部9には垂直な凹溝10および
斜めの凹溝11が形成され、その凹溝10には前
面柱12Aが挿入されているとともに、凹溝11
には控柱12Bが挿入され前面柱12Aと控柱1
2Bとを図示しないボルト・ナツトまたは溶着に
より一体化して主体12を形成している。また、
前面柱12Aおよび控柱12Bの下端は横締ボル
ト・ナツト13により突部9に固定されている。
また主体12の前面柱12Aには梁6が上記実施
例と同様に設けられている。
FIG. 3 shows a second embodiment of the present invention, in which the same parts as in the above embodiment are denoted by the same reference numerals, and the explanation of the same parts is omitted. The center of the upper surface of the substrate 1 is fixed to the slope 2 by the anchor 3. A protrusion 9 is integrally formed in the protrusion 9, and a vertical groove 10 and an oblique groove 11 are formed in the protrusion 9, and a front pillar 12A is inserted into the groove 10. 11
The retaining pillar 12B is inserted into the front pillar 12A and the retaining pillar 1.
2B are integrated with each other by bolts and nuts (not shown) or by welding to form the main body 12. Also,
The lower ends of the front pillar 12A and the retaining pillar 12B are fixed to the protrusion 9 by horizontal tightening bolts and nuts 13.
Also, a beam 6 is provided on the front pillar 12A of the main body 12 in the same manner as in the above embodiment.

そして、上記実施例と同様順序により施工され
るとともに、許容範囲以上の荷重が加わると、緩
衝用連結部である主体12の下部12Cが破壊さ
れて荷重の勢いを緩衝し、さらに上部工が除かれ
ても基板1はアンカー3によつて定着されたまま
保持され、傾斜面の安定化および地辷防止機能を
維持することもできる。
The construction is carried out in the same order as in the above embodiment, and when a load exceeding the allowable range is applied, the lower part 12C of the main body 12, which is a buffer connection part, is destroyed to buffer the force of the load, and the superstructure is removed. Even if the base plate 1 is tilted, the anchor 3 holds the base plate 1 fixed, and the function of stabilizing the slope and preventing sliding can be maintained.

なお、上記第1、第2実施例において、梁6を
主体12下部の強度より弱く形成することによつ
て許容範囲以上の荷重が加わると、梁6が破壊す
るようにしてもよい。
In the first and second embodiments described above, the beam 6 may be formed to have a lower strength than the lower part of the main body 12 so that the beam 6 breaks when a load exceeding an allowable range is applied.

第4図は第3実施例を示しており、上記実施例
と同一部分に同一符号を用い同一箇所の説明を省
略して説明すると、アンカー3により斜面2を定
着される基板1の上面には例えば側面三角形状の
主体4が複数並設され、この主体4の前面により
山側に対向する防護面Aを構成している。そし
て、上記実施例と同様順序で施工されるととも
に、許容範囲以上の荷重が加わるとアンカボル
ト・ナツト5による基板1と主体4との緩衝用連
結部である締結部5Aが破壊されるようにする構
成している。
FIG. 4 shows a third embodiment, and the same reference numerals are given to the same parts as in the above embodiment, and explanations of the same parts are omitted. For example, a plurality of main bodies 4 having triangular side surfaces are arranged side by side, and the front surface of the main bodies 4 constitutes a protective surface A facing the mountain side. The construction is carried out in the same order as in the above embodiment, and the fastening part 5A, which is the buffer connection part between the board 1 and the main body 4 by the anchor bolt/nut 5, is destroyed if a load exceeding the allowable range is applied. It is configured.

なお本考案は上記実施例に限定されるものでは
なく本考案の要旨の範囲内において種々の変形実
施が可能である。例えば基板、主体、アンカー等
の構造、形状は適宜選定すればよい。
Note that the present invention is not limited to the above-mentioned embodiments, and various modifications can be made within the scope of the gist of the present invention. For example, the structure and shape of the substrate, main body, anchor, etc. may be selected as appropriate.

[考案の効果] 本考案はアンカーにより斜面に定着されたプレ
キヤストコンクリート製基板と、この基板上に立
設され荷重を受ける防護面を山側に対向して設け
たプレキヤストコンクリート製主体と、前記基板
と主体を連結する緩衝用連結部とを備え、この緩
衝用連結部を前記アンカーの定着力より小さくか
つ所定以上の荷重により破壊可能に設けたもので
あり、防護壁は安価で高品質になるとともに、斜
面安定化のためのアンカーが防護壁の基礎工とな
つて基板を定着するものであるため従来の基礎コ
ンクリートの現場打施工を省略でき、かつ、工期
を短縮でき、機械施工の割合を削減することがで
きる。またアンカー、基板および主体基礎を共用
することにより、合理的かつ経済的に防護工を設
置することができ、また、雪崩・落石などの荷重
の勢いを効果的に吸収することができ、さらに、
斜面の地辷防止効果を継続して備えた雪崩・落石
等防護壁を提供することができる。
[Effects of the invention] The present invention consists of a precast concrete substrate fixed to a slope by an anchor, a precast concrete main body having a protective surface erected on the substrate facing the mountain side and receiving a load, and The protective wall is provided with a buffer connecting portion that connects the substrate and the main body, and the buffer connecting portion is provided so that it can be broken by a load that is smaller than the fixing force of the anchor and exceeds a predetermined value, and the protective wall is inexpensive and of high quality. In addition, because the anchors for stabilizing the slope serve as the foundation for the protective wall and anchor the substrate, the conventional on-site pouring of foundation concrete can be omitted, the construction period can be shortened, and the proportion of mechanical construction can be reduced. can be reduced. In addition, by sharing anchors, substrates, and main foundations, protection works can be installed rationally and economically, and the momentum of loads such as avalanches and falling rocks can be effectively absorbed.
It is possible to provide a protective wall against avalanches and falling rocks that continuously has the effect of preventing landslides on slopes.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図は本考案の第1実施例を示
し、第1図は断面図、第2図は平面図、第3図は
第2実施例を示す斜視図、第4図は第3実施例を
示す斜視図である。 1……基板、3……アンカー、4,12……主
体、5A……締結部(緩衝用連結部)、12C…
…下部(緩衝用連結部)、A……防護面。
1 and 2 show a first embodiment of the present invention, FIG. 1 is a sectional view, FIG. 2 is a plan view, FIG. 3 is a perspective view of the second embodiment, and FIG. 4 is a perspective view of the second embodiment. FIG. 3 is a perspective view showing a third embodiment. DESCRIPTION OF SYMBOLS 1... Board, 3... Anchor, 4, 12... Main body, 5A... Fastening part (buffer connection part), 12C...
...lower part (buffer connection), A...protective surface.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] アンカーにより斜面に定着されたプレキヤスト
コンクリート製基板と、この基板上に立設され荷
重を受ける防護面を山側に対向して設けたプレキ
ヤストコンクリート製主体と、前記基板と主体を
連結する緩衝用連結部とを備え、この緩衝用連結
部を前記アンカーの定着力により小さくかつ所定
以上の荷重により破壊可能に設けたことを特徴と
する雪崩・落石防護壁。
A precast concrete substrate fixed to the slope by an anchor, a precast concrete main body with a load-receiving protective surface erected on the substrate facing the mountain side, and a buffer for connecting the base and the main body. 1. An avalanche/rockfall protection wall, comprising: a connecting portion, the buffer connecting portion being small due to the anchoring force of the anchor and capable of being broken by a load exceeding a predetermined value.
JP1987117588U 1987-07-30 1987-07-30 Expired - Lifetime JPH0533533Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1987117588U JPH0533533Y2 (en) 1987-07-30 1987-07-30

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1987117588U JPH0533533Y2 (en) 1987-07-30 1987-07-30

Publications (2)

Publication Number Publication Date
JPS6424121U JPS6424121U (en) 1989-02-09
JPH0533533Y2 true JPH0533533Y2 (en) 1993-08-26

Family

ID=31361179

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1987117588U Expired - Lifetime JPH0533533Y2 (en) 1987-07-30 1987-07-30

Country Status (1)

Country Link
JP (1) JPH0533533Y2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5771027B2 (en) * 2011-03-07 2015-08-26 神鋼建材工業株式会社 Avalanche prevention structure
JP5781413B2 (en) * 2011-09-30 2015-09-24 神鋼建材工業株式会社 Anchor bolt installation structure, its maintenance method and construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5118401B2 (en) * 1972-10-24 1976-06-09

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4730903U (en) * 1971-04-30 1972-12-07
JPS5118401U (en) * 1974-07-29 1976-02-10
JPS5362105U (en) * 1976-10-29 1978-05-26

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5118401B2 (en) * 1972-10-24 1976-06-09

Also Published As

Publication number Publication date
JPS6424121U (en) 1989-02-09

Similar Documents

Publication Publication Date Title
EP3827133B1 (en) Method for stabilizing deep excavations or earth slope instability near existing civil objects
US4051570A (en) Road bridge construction with precast concrete modules
US20010023563A1 (en) Permanent foundation system for manufactured housing
JP3443739B2 (en) Foundation construction method, footing foundation and foundation structure of elevated traffic route
JPH09158212A (en) Foundation reinforcing structure for structure group
KR20010057453A (en) Steel pier anchorage system using large deformed bar
JPH0533533Y2 (en)
CN213653481U (en) Prestressed anchor cable frame beam device suitable for stability of strongly weathered rock slope
JP2787806B2 (en) Earth retaining wall
JP2000120081A (en) Slope footing structure
JP2000248515A (en) Footing structure of column for protective fence
JPH1082057A (en) Method of earthquake-resisting pile foundation construction
JP2567615B2 (en) Slope embankment method
JPH0237442B2 (en) DOROKAKUFUKUKOHO
JPH0674591B2 (en) Anchor support beam construction method
JP3661999B2 (en) Construction method of guardrail foundation
KR101498190B1 (en) the Infrastructure of Rockfall protection post
JPH0562161B2 (en)
CN219280754U (en) Stress system suitable for reinforcing pile plate wall
KR102272494B1 (en) Slope reinforcement structure using support and tension and Its Construction method
CN114934527B (en) Construction method of prestressed anchor cable hillside wall
CN217811180U (en) Road side slope protective structure
JPH1082056A (en) Method of earthquake-resisting pile foundation construction
KR200245970Y1 (en) A precast retaining wall unit for attaching beam to prevent falling stones
JP3594551B2 (en) Reinforcement structure of concrete structure