JPH1082056A - Method of earthquake-resisting pile foundation construction - Google Patents

Method of earthquake-resisting pile foundation construction

Info

Publication number
JPH1082056A
JPH1082056A JP8238094A JP23809496A JPH1082056A JP H1082056 A JPH1082056 A JP H1082056A JP 8238094 A JP8238094 A JP 8238094A JP 23809496 A JP23809496 A JP 23809496A JP H1082056 A JPH1082056 A JP H1082056A
Authority
JP
Japan
Prior art keywords
pile
ground
piles
foundations
earthquake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8238094A
Other languages
Japanese (ja)
Inventor
Sadahiko Takamori
貞彦 高森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP8238094A priority Critical patent/JPH1082056A/en
Publication of JPH1082056A publication Critical patent/JPH1082056A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce the number of piles and the diameters of the piles, and to resist even large seismic force while enabling an economic design by driving ground anchors into the piles without resisting against external force at the time of an earthquake as pile single bodies and working the piles as resistors to the pile drawing-out direction in a pile foundation. SOLUTION: In the method of earthquake-resisting pile foundation construction, ground anchors 11, 12 penetrated to a footing 5 on pile foundations 6, 7, 8, 9 and the insides of the piles 6, 9 are driven into the piles 6, 9 at both end sections of a plurality of the pile foundations 6, 7, 8, 9 buried into a ground and arranged and installed respectively, and each ground anchor 11, 12 is fixed to the fixing sections 13, 14 of a bearing layer 2 in the ground 1. Tensile force is given and the pile foundations are fastened by fasteners 15, 16 respectively on the footing 5.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、杭基礎の杭内部に
グランドアンカーを通す耐震杭基礎工法に関するもので
ある。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an earthquake-resistant pile foundation method in which a ground anchor is passed through a pile of a pile foundation.

【0002】[0002]

【従来の技術】例えば、橋脚基礎、鉄塔基礎、建築建屋
基礎、地中構造物基礎等、全ての構造物基礎に適用され
る杭基礎において、従来は、地震時の水平力に対して複
数の杭がそれぞれ単体として抵抗するものであった。そ
して、個々の杭の曲げせん断強度で大きな地震力に対し
て抵抗するには、多数の杭基礎が必要である。また、既
設の杭基礎構造物に対する耐震補強としては、増し杭を
打設していた。なお、近年、グランドアンカーの設計・
施工法の信頼性が高まってきており、例えば、斜面崩壊
防護工、建築基礎工等、永久アンカーとしての実績が多
くなってきている。
2. Description of the Related Art For example, a pile foundation applied to all structural foundations such as a pier foundation, a steel tower foundation, a building building foundation, an underground structural foundation, etc. Each stake resisted itself. In addition, a large number of pile foundations are required to resist large seismic forces with the bending and shear strength of individual piles. In addition, additional piles were cast as seismic reinforcement for existing pile foundations. In recent years, ground anchor design and
The reliability of the construction method is increasing, and the results as permanent anchors, for example, slope collapse protection works, building foundation works, etc. are increasing.

【0003】[0003]

【発明が解決しようとする課題】ところで、杭基礎構造
物は、杭として最大の水平・鉛直支持力を発揮させるに
は、適正な杭間隔が必要である。しかも、特に発生頻度
の少ない大きな地震力に抵抗するには、多くの杭本数も
しくは大口径杭が必要になる。そのため、基礎の平面寸
法も大きくなり、不経済なものとなってしまう。また、
既設の杭基礎構造物に対する耐震補強のために増し杭を
打設するには、フーチングの拡大もしくはフーチング既
存鉄筋の切断等、設計・施工上多くの問題があった。
By the way, an appropriate pile interval is necessary for a pile foundation structure to exhibit the maximum horizontal and vertical support force as a pile. In addition, a large number of piles or large-diameter piles are required in order to resist a large seismic force, which is particularly infrequent. Therefore, the plane dimensions of the foundation also become large, which is uneconomical. Also,
There are many design and construction problems, such as expansion of the footing or cutting of the existing reinforcing steel bar, for placing additional piles for seismic reinforcement of existing pile foundation structures.

【0004】そこで、本発明の目的は、杭単体として地
震時外力に抵抗するのではなく、杭内部にグランドアン
カーを打設して、杭引き抜き方向に対する抵抗体として
機能させることにより、杭本数、杭径を減少させて、経
済設計を可能としながら、大きな地震力にも抵抗できる
ようにした耐震杭基礎工法を提供することにある。
Therefore, an object of the present invention is to provide a ground anchor in a pile and to function as a resistor in the pulling-out direction of the pile, instead of resisting an external force at the time of an earthquake as a single pile. It is an object of the present invention to provide an earthquake-resistant pile foundation method capable of reducing a pile diameter, enabling economic design, and resisting a large seismic force.

【0005】[0005]

【課題を解決するための手段】以上の課題を解決すべく
請求項1記載の発明は、例えば、橋脚基礎等の耐震杭基
礎工法であって、地中に埋設される鋼管杭等の杭基礎の
杭内部に、その杭内部を貫通する、例えば、PC鋼材等
の引張材によるグランドアンカーを打設して、地盤内の
支持層にアンカー体を定着させるようにしたこと、を特
徴としている。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, the invention according to claim 1 is, for example, an earthquake-resistant pile foundation method for a pier foundation or the like, wherein the pile foundation is a steel pipe pile or the like buried underground. A ground anchor made of, for example, a tensile material such as PC steel is penetrated through the inside of the pile, and the anchor body is fixed to a support layer in the ground.

【0006】ここで、本発明は、例えば、橋脚基礎、鉄
塔基礎、建築建屋基礎、地中構造物基礎等、杭基礎に係
る全ての構造物基礎に適用できるものである。また、杭
としては、鋼管杭や場所打ちコンクリート杭等が挙げら
れる。なお、本発明は、既設の杭基礎にも適用可能であ
る。
Here, the present invention can be applied to all structural foundations related to pile foundations, such as pier foundations, steel tower foundations, building building foundations, underground structural foundations, and the like. Examples of the pile include a steel pipe pile and a cast-in-place concrete pile. The present invention is also applicable to an existing pile foundation.

【0007】以上のように、杭基礎の杭内部にグランド
アンカーを打設して地盤内の支持層に定着したので、杭
内部を貫通したグランドアンカーが杭引き抜き方向に対
する抵抗体として機能することにより、大きな地震力に
も抵抗できる。また、低廉なグランドアンカーの採用に
より、杭基礎としての引き抜き方向に対する強度が増大
するので、杭本数、杭径を減少させて、経済設計ができ
る。
As described above, since the ground anchor is cast inside the pile of the pile foundation and fixed to the support layer in the ground, the ground anchor penetrating the inside of the pile functions as a resistor in the pull-out direction. , Can resist large seismic force. In addition, the adoption of the inexpensive ground anchor increases the strength of the pile foundation in the pulling-out direction, so that the number of piles and the diameter of the piles can be reduced, and economic design can be performed.

【0008】さらに、請求項2記載の発明は、請求項1
記載の耐震杭基礎工法であって、前記グランドアンカー
は、複数の杭基礎の上に施工される、例えば、橋脚等の
フーチングにアンカー頭部が定着される構成、を特徴と
している。なお、フーチングにグランドアンカーを貫通
させて、そのアンカー頭部をフーチング上面に定着した
り、フーチング内部にアンカー頭部を定着するようにし
てもよい。
[0008] Further, the invention according to claim 2 is based on claim 1.
The method according to the above-mentioned earthquake-resistant pile foundation method, wherein the ground anchor is constructed on a plurality of pile foundations, for example, the anchor head is fixed to a footing such as a bridge pier. The ground anchor may be fixed to the footing upper surface by penetrating the ground anchor through the footing, or the anchor head may be fixed inside the footing.

【0009】このように、請求項1記載のグランドアン
カーのアンカー頭部を、杭基礎上のフーチングに定着し
たので、フーチング及び杭内部に打設したグランドアン
カーによって、フーチングごと杭引き抜き方向に対する
抵抗力を合理的に増大できる。
As described above, the anchor head of the ground anchor according to the first aspect is fixed to the footing on the pile foundation, so that the foot anchor and the ground anchor cast inside the pile are used to resist the footing together with the footing in the pile pull-out direction. Can be reasonably increased.

【0010】そして、請求項3記載の発明は、請求項1
または2記載の耐震杭基礎工法であって、前記グランド
アンカーは、複数並んで設けられる杭基礎の少なくとも
両端部の杭内部にそれぞれ打設される構成、を特徴とし
ている。
[0010] The invention according to claim 3 is based on claim 1.
Or the seismic pile foundation method according to 2, wherein the ground anchors are respectively driven into the piles at least at both ends of a plurality of pile foundations provided side by side.

【0011】このように、請求項1または2記載のグラ
ンドアンカーを、少なくとも両端部の杭内部にそれぞれ
打設したので、そのグランドアンカーを杭内部に打設し
た両端部側の両側方からの地震時外力による杭引き抜き
方向に対する抵抗力が合理的に具備できる。
As described above, the ground anchor according to claim 1 or 2 is installed at least in the inside of the pile at both ends, so that the ground anchor is installed inside the pile at both ends of the pile. It is possible to reasonably provide a resistance against the pile pull-out direction due to the external force.

【0012】[0012]

【発明の実施の形態】以下に、本発明に係る耐震杭基礎
工法の実施の形態例を図1から図3に基づいて説明す
る。先ず、図1は本発明を適用した一例としての耐震杭
基礎の施工構造を示す要部破断の側面図で、図2はその
杭基礎及び杭通しグランドアンカーの配列を示した概略
平面図である。これらの図1及び図2において、1は地
盤、2は支持層、3は橋脚、4は上部構造物、5はフー
チング、6,7,8,9は杭基礎(鋼管杭基礎)、1
1,12はグランドアンカー、13,14はグランドア
ンカー定着部、15,16は締め付け金具である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of an earthquake-resistant pile foundation method according to the present invention will be described below with reference to FIGS. First, FIG. 1 is a side view of an essential part showing a construction structure of an earthquake-resistant pile foundation as an example to which the present invention is applied, and FIG. 2 is a schematic plan view showing an arrangement of the pile foundation and a pile-through ground anchor. . 1 and 2, 1 is the ground, 2 is the support layer, 3 is the pier, 4 is the superstructure, 5 is the footing, 6, 7, 8, and 9 are pile foundations (steel pipe pile foundations), 1
Reference numerals 1 and 12 denote ground anchors, 13 and 14 denote ground anchor fixing portions, and 15 and 16 denote fastening fittings.

【0013】即ち、この実施の形態例は、図1に示すよ
うに、例えば、橋脚基礎に適用した場合であり、地盤1
には、杭基礎の一例として多数の鋼管杭基礎6,7,
8,9,・・・が支持層2までそれぞれ打ち込まれてお
り、その上に施工したフーチング5上に橋脚3が構築さ
れ、この橋脚3により上部構造物4が支持されている。
そして、図2に示すように、平面視で縦横4本ずつで計
16本の鋼管杭基礎6,7,8,9,・・・の配列とな
っており、これら16本の鋼管杭基礎6,7,8,9,
・・・の内、図示左右両端部の平行する4本ずつの鋼管
杭基礎6,6,6,6,9,9,9,9に、その上のフ
ーチング5及び各杭内部を貫通してグランドアンカー1
1,11,11,11,12,12,12,12がそれ
ぞれ打設されている。
That is, this embodiment is a case where the present invention is applied to, for example, a pier foundation as shown in FIG.
As examples of pile foundations, many steel pipe pile foundations 6,7,
.. Are respectively driven up to the support layer 2, and the pier 3 is constructed on the footing 5 constructed thereon, and the upper structure 4 is supported by the pier 3.
As shown in FIG. 2, a total of 16 steel pipe pile foundations 6, 7, 8, 9,... , 7,8,9,
..., four steel pipe pile foundations 6,6,6,6,9,9,9,9 parallel to each other at the right and left ends of the figure are passed through the footing 5 and the inside of each pile. Ground anchor 1
1,11,11,11,12,12,12,12 are respectively cast.

【0014】次に、このような杭通しグランドアンカー
11,12による耐震杭基礎の具体的な施工例について
説明する。先ず、図1に示すように、地盤1に鋼管杭基
礎6,7,8,9,・・・を打設してその下端部を支持
層2まで打ち込んだ後、その上に鉄筋の配筋及び型枠工
事並びにコンクリート打設によるフーチング5を構築し
ておく。そして、フーチング5上において、そのフーチ
ング5を含んで図示左右両端部の平行する4本ずつの鋼
管杭基礎6,6,6,6,9,9,9,9の各杭内部を
削孔する。この削孔は、図示しないが、適宜のボーリン
グ機械(削孔機)によりドリルパイプを用いて、フーチ
ング5の上面から鋼管杭基礎6,6,6,6,9,9,
9,9の各杭内部を貫通し、さらに、その下の支持層2
まで鉛直に削孔する。
Next, a concrete example of the construction of an earthquake-resistant pile foundation using such pile penetrating ground anchors 11 and 12 will be described. First, as shown in FIG. 1, steel pipe pile foundations 6, 7, 8, 9,... Are cast on the ground 1 and the lower end thereof is driven into the support layer 2, and then reinforcing bars of reinforcing steel are placed thereon. And footing 5 is constructed by formwork and concrete casting. Then, on the footing 5, the inside of each pile of four steel pipe pile foundations 6, 6, 6, 6, 9, 9, 9, 9 including the footing 5, which are parallel to each other at the left and right ends in the drawing, are drilled. . Although not shown, the drilling is performed by using a drill pipe with an appropriate boring machine (drilling machine) from the upper surface of the footing 5 to the steel pipe pile foundation 6, 6, 6, 6, 9, 9, 9,
9, the inside of each stake, and the support layer 2 thereunder
Drill vertically to

【0015】その後、削孔された各孔に、引張材として
のPC鋼材(JIS)によるグランドアンカー11,1
2を支持層2に削孔した孔まで挿入してから、その支持
層2に削孔した孔に、図示しない注入パイプによりセメ
ントペーストまたはセメントモルタルによるグラウト材
を注入する。この時、ドリルパイプを引き抜きながらグ
ラウト材を加圧注入する。こうして注入したグラウト材
が所定の圧縮強度に達すると、グランドアンカー11,
12の下端部(アンカー体)が、固化したグラウト材の
中に定着されたグランドアンカー定着部13,14とな
り、このようにグラウト材が所定の圧縮強度に達した時
点で、グランドアンカー11,12に緊張力を与える。
Then, ground anchors 11 and 1 made of PC steel (JIS) as a tensile material are inserted into the drilled holes.
2 is inserted up to the hole drilled in the support layer 2, and a grout material such as cement paste or cement mortar is injected into the hole drilled in the support layer 2 by an injection pipe (not shown). At this time, the grout material is injected under pressure while pulling out the drill pipe. When the grout thus injected reaches a predetermined compressive strength, the ground anchor 11,
The lower end portions (anchor bodies) of the ground anchor fixing portions 13 and 14 fixed in the solidified grout material. When the grout material reaches a predetermined compressive strength, the ground anchors 11 and 12 are fixed. To tension.

【0016】即ち、フーチング5上において、図示しな
い緊張ジャッキを用いて、グランドアンカー11,12
に所定の緊張力を加えた状態で、締め付け金具15,1
6によりグランドアンカー11,12の上端部(アンカ
ー頭部)をフーチング5の上面に固定する。以上によ
り、図1及び図2に示したように、フーチング5から図
示左右両端部の鋼管杭基礎6,6,6,6,9,9,
9,9の各杭内部を貫通するグランドアンカー11,1
1,11,11,12,12,12,12の打設が完了
する。
That is, the ground anchors 11 and 12 are mounted on the footing 5 using a tension jack (not shown).
With a predetermined tension applied to the fasteners,
6, the upper ends (anchor heads) of the ground anchors 11 and 12 are fixed to the upper surface of the footing 5. As described above, as shown in FIGS. 1 and 2, the steel pipe pile foundations 6, 6, 6, 6, 9, 9, 9,
Ground anchors 11 and 1 penetrating the insides of the piles 9 and 9
The installation of 1, 11, 11, 12, 12, 12, 12 is completed.

【0017】以上の通り、本発明の実施の形態例に係る
杭通しグランドアンカーによる耐震杭基礎工法によれ
ば、以下に説明する効果を発揮できる。地震が発生した
場合、その地震時外力による杭引き抜き方向に対する抵
抗力の作用を図面上誇張して端的に示した図3のよう
に、例えば、図示左側からの矢印I方向の外力に対して
は、図示左端部の鋼管杭基礎6,6,6,6及びその各
杭内部を貫通するグランドアンカー11,11,11,
11とその隣の列の鋼管杭基礎7,7,7,7によっ
て、杭引き抜き方向に作用する力に対し抵抗する。この
時、図示右端部の鋼管杭基礎9,9,9,9及びその隣
の列の鋼管杭基礎8,8,8,8は圧縮力を受け、地震
力に対し抵抗するが、図示右端部の鋼管杭基礎9,9,
9,9の各杭内部を貫通するグランドアンカー12,1
2,12,12は緩み、抵抗体としては寄与しない。
As described above, according to the earthquake-resistant pile foundation method using the pile-through ground anchor according to the embodiment of the present invention, the following effects can be exerted. When an earthquake occurs, as shown in FIG. 3, which shows the effect of the resistance force on the pile pull-out direction due to the external force during the earthquake exaggeratedly in the drawing, for example, with respect to the external force in the direction of arrow I from the left side of the drawing, , Steel pipe pile foundations 6, 6, 6, 6 at the left end of the figure and ground anchors 11, 11, 11, 11,
11 and the adjacent row of steel pipe pile foundations 7,7,7,7 resist forces acting in the pull-out direction. At this time, the steel pipe pile foundations 9, 9, 9, 9 at the right end in the figure and the steel pipe pile foundations 8, 8, 8, 8 in the row adjacent thereto receive compressive force and resist seismic force. Steel pipe pile foundation 9,9,
Ground anchors 12,1 penetrating the inside of each pile of 9,9
2, 12, 12 are loose and do not contribute as a resistor.

【0018】また、逆に図示右側からの矢印II方向の
外力に対しては、図示右端部の鋼管杭基礎9,9,9,
9及びその各杭内部を貫通するグランドアンカー12,
12,12,12とその隣の列の鋼管杭基礎8,8,
8,8によって、杭引き抜き方向に作用する力に対し抵
抗する。この時、図示左端部の鋼管杭基礎6,6,6,
6及びその隣の列の鋼管杭基礎7,7,7,7は圧縮力
を受け、地震力に対し抵抗するが、図示左端部の鋼管杭
基礎6,6,6,6の各杭内部を貫通するグランドアン
カー11,11,11,11は緩み、抵抗体としては寄
与しない。以上にようにして、大きな地震力に対して抵
抗できる強度を具備したものとなる。
Conversely, when an external force is applied in the direction of arrow II from the right side in the figure, the steel pipe pile foundations 9, 9, 9, 9
9 and a ground anchor 12 penetrating the inside of each pile,
12, 12, 12 and the adjacent row of steel pipe pile foundations 8, 8,
8, 8 resists forces acting in the pull-out direction. At this time, the steel pipe pile foundation 6, 6, 6,
6 and the adjacent row of steel pipe pile foundations 7, 7, 7, 7 receive the compressive force and resist the seismic force, but the inside of each pile of the steel pipe pile foundations 6, 6, 6, 6 at the left end shown in the figure. The penetrating ground anchors 11, 11, 11, 11 are loosened and do not contribute as resistors. As described above, a structure having strength capable of resisting a large seismic force is provided.

【0019】ところで、杭基礎構造物は、地震発生時の
外力に対抗できるよう杭本数が決定されている。特に、
地震の水平力に対し杭で抵抗するには、杭の曲げせん断
強度と周辺地盤のせん断強度で抵抗するのであるが、多
くの杭本数が必要になる。しかし、実施の形態例のよう
に、杭基礎6,7,8,9,・・・上のフーチング5か
ら両端部の杭基礎6,6,6,6,9,9,9,9内部
にグランドアンカー11,11,11,11,12,1
2,12,12を打設したことによって、そのフーチン
グ5及び両端部の杭基礎6,6,6,6,9,9,9,
9内部を貫通したグランドアンカー11,11,11,
11,12,12,12,12が杭引き抜き方向に対す
る抵抗体として機能するため、杭本数を減少させたり、
もしくは杭径を減少させることができ、低廉なグランド
アンカー工法の採用と併せ、合理的・経済的な設計によ
る低廉な工事費により実現できる。また、既設の杭基礎
構造物の耐震補強としても有効であり、しかも、容易に
行える。
Incidentally, the number of pile foundations is determined so as to be able to withstand the external force at the time of an earthquake. Especially,
In order for a pile to resist the horizontal force of an earthquake, it is necessary to resist the bending shear strength of the pile and the shear strength of the surrounding ground, but a large number of piles is required. However, as in the embodiment, from the footing 5 on the pile foundations 6, 7, 8, 9, ... to the inside of the pile foundations 6, 6, 6, 6, 9, 9, 9, 9, 9 at both ends. Ground anchor 11, 11, 11, 11, 12, 1
By placing 2,12,12, its footing 5 and pile foundations 6,6,6,6,9,9,9,9
9, ground anchors 11, 11, 11,
Since 11, 12, 12, 12, 12 function as a resistive element in the pile pull-out direction, the number of piles can be reduced,
Alternatively, the diameter of the pile can be reduced, and this can be realized with the use of a low-cost ground anchor method and the low construction cost through rational and economical design. In addition, it is effective as seismic reinforcement of the existing pile foundation structure, and can be easily performed.

【0020】なお、以上の実施の形態例においては、橋
脚基礎に適用したが、本発明はこれに限定されるもので
はなく、他に鉄塔基礎、建築建屋基礎、地中構造物基礎
等、杭基礎に係る全ての構造物基礎に適用できるもので
あり、既設の杭基礎にも適用可能である。また、実施の
形態例では、杭として鋼管杭としたが、本発明はこれに
限らず、場所打ちコンクリート杭等にも適用可能であ
る。
In the above embodiment, the present invention is applied to a pier foundation. However, the present invention is not limited to this, and other examples include a steel tower foundation, a building building foundation, an underground structure foundation and the like. The present invention can be applied to all structural foundations related to foundations, and can also be applied to existing pile foundations. Further, in the embodiment, the steel pipe pile is used as the pile, but the present invention is not limited to this, and is applicable to a cast-in-place concrete pile or the like.

【0021】そして、実施の形態例において、杭基礎の
平行する両端部に杭内部を貫通するグランドアンカーを
打設したが、4方向の各端部に沿って同様のグランドア
ンカーを打設してもよく、また、全ての杭内部を貫通す
るグランドアンカーを打設してもよい。また、実施の形
態例では、フーチングを貫通するグランドアンカーのア
ンカー頭部をフーチング上面に定着したが、フーチング
内部にアンカー頭部を定着するようにしてもよい。さら
に、その他、具体的な細部構造等についても適宜に変更
可能であることは勿論である。
In the embodiment, the ground anchors penetrating the inside of the pile are installed at the two parallel end portions of the pile foundation. However, similar ground anchors are installed along each end in four directions. Alternatively, a ground anchor penetrating the inside of all the piles may be cast. In the embodiment, the anchor head of the ground anchor penetrating the footing is fixed on the upper surface of the footing, but the anchor head may be fixed inside the footing. Further, it goes without saying that other specific detailed structures can be appropriately changed.

【0022】[0022]

【発明の効果】以上のように、請求項1記載の発明に係
る耐震杭基礎工法によれば、杭内部にグランドアンカー
を打設したため、その杭内部を貫通したグランドアンカ
ーが杭引き抜き方向に対する抵抗体として機能して、大
きな地震力にも抵抗することができる。また、低廉なグ
ランドアンカーの採用で、杭基礎の引き抜き方向に対す
る強度が増大するため、杭本数、杭径を減少できて、経
済設計をすることができる。
As described above, according to the earthquake-resistant pile foundation method according to the first aspect of the present invention, since the ground anchor is cast inside the pile, the ground anchor penetrating the inside of the pile has a resistance in the pull-out direction. It can function as a body and resist large seismic forces. In addition, the adoption of the inexpensive ground anchor increases the strength of the pile foundation in the pull-out direction, so that the number of piles and the diameter of the piles can be reduced, and economic design can be achieved.

【0023】さらに、請求項2記載の発明に係る耐震杭
基礎工法によれば、杭内部に打設するグランドアンカー
のアンカー頭部を杭基礎上のフーチングに定着させたた
め、請求項1記載の発明により得られる効果に加えて、
フーチング及び杭内部に打設したグランドアンカーによ
って、フーチングごと杭引き抜き方向に対する抵抗力を
合理的に増大することができるといった利点が得られ
る。
Further, according to the seismic pile foundation method according to the second aspect of the present invention, the anchor head of the ground anchor to be cast into the pile is fixed to the footing on the pile foundation. In addition to the effect obtained by
The footing and the ground anchor cast inside the pile provide an advantage that the resistance in the pile pullout direction can be reasonably increased with the footing.

【0024】そして、請求項3記載の発明に係る耐震杭
基礎工法によれば、少なくとも両端部の杭内部にグラン
ドアンカーをそれぞれ打設したため、請求項1または2
記載の発明により得られる効果に加えて、そのグランド
アンカーを杭内部に打設した両端部側の両側方からの地
震時外力による杭引き抜き方向に対する抵抗力を合理的
に具備することができるといった利点が得られる。
According to the seismic pile foundation method according to the third aspect of the present invention, the ground anchors are cast at least inside the piles at both ends.
In addition to the effects obtained by the described invention, the advantage that the ground anchor can be rationally provided with resistance to the pulling-out direction due to an external force at the time of an earthquake from both sides on both ends where the ground anchor is driven into the inside of the pile. Is obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明を適用した一例としての耐震杭基礎の施
工構造を示す要部破断の側面図である。
FIG. 1 is a side view of an essential part showing a construction structure of an earthquake-resistant pile foundation as an example to which the present invention is applied.

【図2】図1の杭基礎及び杭通しグランドアンカーの配
列を示した概略平面図である。
FIG. 2 is a schematic plan view showing an arrangement of a pile foundation and a pile-through ground anchor of FIG. 1;

【図3】図1の耐震杭基礎施工例による側方からの地震
時外力による杭引き抜き方向に対する抵抗力の作用を図
面上誇張して端的に示した要部破断の側面図である。
FIG. 3 is a side view of a breakage of a main part, in which the effect of a resistance force in a pile pull-out direction due to an external force at the time of an earthquake from the side according to the example of the foundation of the earthquake-resistant pile shown in FIG.

【符号の説明】[Explanation of symbols]

1 地盤 2 支持層 3 橋脚 4 上部構造物 5 フーチング 6,7,8,9 杭基礎 11,12 グランドアンカー 13,14 グランドアンカー定着部 15,16 締め付け金具 DESCRIPTION OF SYMBOLS 1 Ground 2 Support layer 3 Bridge pier 4 Upper structure 5 Footing 6,7,8,9 Pile foundation 11,12 Ground anchor 13,14 Ground anchor anchoring part 15,16 Fastening metal

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】地中に埋設される杭基礎の杭内部に、その
杭内部を貫通して地盤内の支持層にアンカー体が定着さ
れるグランドアンカーを打設したこと、を特徴とする耐
震杭基礎工法。
1. A seismic resistance, wherein a ground anchor which penetrates through the inside of a pile and is anchored to a support layer in the ground is cast inside a pile of a pile foundation buried underground. Pile foundation method.
【請求項2】前記グランドアンカーは、複数の杭基礎の
上に施工されるフーチングにアンカー頭部が定着される
こと、を特徴とする請求項1記載の耐震杭基礎工法。
2. The seismic pile foundation method according to claim 1, wherein said ground anchor has an anchor head fixed to a footing constructed on a plurality of pile foundations.
【請求項3】前記グランドアンカーは、複数並んで設け
られる杭基礎の少なくとも両端部の杭内部にそれぞれ打
設されること、を特徴とする請求項1または2記載の耐
震杭基礎工法。
3. The seismic pile foundation method according to claim 1, wherein said ground anchors are respectively installed at least inside the piles at both ends of a pile foundation provided side by side.
JP8238094A 1996-09-09 1996-09-09 Method of earthquake-resisting pile foundation construction Pending JPH1082056A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8238094A JPH1082056A (en) 1996-09-09 1996-09-09 Method of earthquake-resisting pile foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8238094A JPH1082056A (en) 1996-09-09 1996-09-09 Method of earthquake-resisting pile foundation construction

Publications (1)

Publication Number Publication Date
JPH1082056A true JPH1082056A (en) 1998-03-31

Family

ID=17025084

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8238094A Pending JPH1082056A (en) 1996-09-09 1996-09-09 Method of earthquake-resisting pile foundation construction

Country Status (1)

Country Link
JP (1) JPH1082056A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008255615A (en) * 2007-04-03 2008-10-23 Ohbayashi Corp Head anchoring structure of anchor, head anchoring method of anchor and injection method of grout material
JP2010031568A (en) * 2008-07-30 2010-02-12 Shimizu Corp Aseismatic reinforcing construction method for existing foundation and aseismatic reinforcing structure of existing foundation
JP2011043049A (en) * 2010-12-03 2011-03-03 Ohbayashi Corp Method and structure for reinforcing existing building
CN106351217A (en) * 2016-09-20 2017-01-25 太原理工大学 Self-resetting multidimensional damping pipe pile group foundation and construction method
JP2021173102A (en) * 2020-04-28 2021-11-01 日本製鉄株式会社 Pile foundation structure, and construction method of structure foundation
CN113638361A (en) * 2021-08-26 2021-11-12 哈尔滨工业大学 Connection structure of port and pier PHC tubular pile and superstructure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008255615A (en) * 2007-04-03 2008-10-23 Ohbayashi Corp Head anchoring structure of anchor, head anchoring method of anchor and injection method of grout material
JP2010031568A (en) * 2008-07-30 2010-02-12 Shimizu Corp Aseismatic reinforcing construction method for existing foundation and aseismatic reinforcing structure of existing foundation
JP2011043049A (en) * 2010-12-03 2011-03-03 Ohbayashi Corp Method and structure for reinforcing existing building
CN106351217A (en) * 2016-09-20 2017-01-25 太原理工大学 Self-resetting multidimensional damping pipe pile group foundation and construction method
CN106351217B (en) * 2016-09-20 2018-07-17 太原理工大学 A kind of Self-resetting multidimensional damping tube pile group pile foundation and construction method
JP2021173102A (en) * 2020-04-28 2021-11-01 日本製鉄株式会社 Pile foundation structure, and construction method of structure foundation
CN113638361A (en) * 2021-08-26 2021-11-12 哈尔滨工业大学 Connection structure of port and pier PHC tubular pile and superstructure

Similar Documents

Publication Publication Date Title
EP3827133B1 (en) Method for stabilizing deep excavations or earth slope instability near existing civil objects
US5551810A (en) Retaining wall with an outer face and method of forming the same
US9683347B2 (en) Systems and methods to reinforce excavation walls
CN113123373A (en) Pressure-bearing uplift pile with rear-inserted unbonded steel strand U-shaped pipe and construction method thereof
JP3689840B2 (en) Seismic reinforcement method for existing structure foundation
JP4663541B2 (en) Seismic reinforcement method for existing concrete pier
JP4448592B2 (en) Reinforcement pile fixture
JPH1082056A (en) Method of earthquake-resisting pile foundation construction
JPH1082057A (en) Method of earthquake-resisting pile foundation construction
JP4181192B2 (en) Ground anchor and ground anchor method
CN216515697U (en) Rock drilling anchor cable and bearing platform combined anti-seismic foundation
JP5504951B2 (en) Seismic reinforcement method for structures and seismic reinforcement structure for structures
CN214784243U (en) Back-inserted unbonded steel strand U-shaped pipe pressure-bearing uplift pile
CN114016534A (en) Rock drilling anchor cable and bearing platform combined anti-seismic foundation and construction method thereof
CN210766868U (en) Reinforcing structure for existing gravity retaining wall
JP2001303592A (en) Method for installing and fixing block
JPH1077644A (en) Earthquake resisting pile foundation construction method
JP2559394Y2 (en) Rock anchored octopus foot anchor foundation
JPH11323988A (en) Earthquake resistant reinforcing construction method
JPH10292393A (en) Method for reinforcing foundation of existing structure
KR200255715Y1 (en) Anchorage of earth anchor in steel pipe pile for pull-out resistance in the water
JP3444720B2 (en) Connection method between pile head and foundation
KR102264595B1 (en) Self supporting type phc pile and construction method for the same
JPH1082055A (en) Method of earthquake-resisting pile foundation construction
KR102614988B1 (en) Pre-stressed composite pile for retaining wall in remodeling

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080430

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20090430

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20090430

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20100430

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20100430

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110430

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120430

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20130430

LAPS Cancellation because of no payment of annual fees