JPH0533387A - Form panel - Google Patents
Form panelInfo
- Publication number
- JPH0533387A JPH0533387A JP18901391A JP18901391A JPH0533387A JP H0533387 A JPH0533387 A JP H0533387A JP 18901391 A JP18901391 A JP 18901391A JP 18901391 A JP18901391 A JP 18901391A JP H0533387 A JPH0533387 A JP H0533387A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- stretched
- formwork
- panel
- forms
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、型枠を形成する型枠パ
ネルの構造に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the structure of a form panel forming a form.
【0002】[0002]
【従来の技術】従来、鉄筋コンクリート構造物或いは鉄
骨鉄筋コンクリート構造物を構築する際には、施工場所
に鉄筋を配筋し、同鉄筋の周囲に型枠パネルを配設して
型枠を組立て、同型枠内にコンクリートを打設しして、
コンクリートが硬化した後に、型枠を解体するようにし
ている。2. Description of the Related Art Conventionally, when constructing a reinforced concrete structure or a steel frame reinforced concrete structure, reinforcing bars are arranged at a construction site, and a form panel is arranged around the reinforcing bars to assemble the form, Place concrete in the frame,
The formwork is dismantled after the concrete has hardened.
【0003】そして、型枠パネルとしては、矩形状の板
材を使用し、同型枠パネルにより形成した型枠より打設
したコンクリートがもれないようにしている。A rectangular plate material is used for the formwork panel so that concrete poured from the formwork formed by the formwork panel will not leak.
【0004】[0004]
【発明が解決しようとする課題】ところが、上記した型
枠パネルの場合、以下のような問題がある。However, the formwork panel described above has the following problems.
【0005】すなわち、型枠内のコンクリートの打設状
態を外部から視認することができないために、型枠解体
後にコンクリートの打設不良個所が発見されることがあ
り、後処理に手間を要するという問題がある。That is, since it is not possible to visually check the concrete pouring condition in the formwork from the outside, a defective pouring place of the concrete may be found after the formwork is dismantled, and the post-treatment requires time and effort. There's a problem.
【0006】一方、コンクリートの打設不良を解消する
目的で、バイブレーター等を使用して打設コンクリート
に振動を加えることも行なわれるが、不必要に振動を加
えることにより、骨材とセメントの分離等が生じ、コン
クリートの強度を均一に保持させることができなくなる
という不具合がある。On the other hand, for the purpose of eliminating defective placement of concrete, vibration may be applied to the placed concrete by using a vibrator or the like, but by adding vibration unnecessarily, the aggregate and the cement are separated. However, there is a problem in that the strength of concrete cannot be kept uniform.
【0007】また、コンクリートが硬化した後に、型枠
を解体して搬出しなければならず、かかる解体作業と搬
出作業に手間を要するという問題がある。Further, there is a problem that after the concrete is hardened, the formwork must be dismantled and carried out, which requires time and labor for the dismantling work and the carrying-out work.
【0008】[0008]
【課題を解決するための手段】そこで、本発明では、型
枠フレームに金網を張設し、同金網の内側面に透明な合
成樹脂製フィルムを張設し、同フィルムに微小径の孔を
多数個穿設したことを特徴とする型枠パネルを提供せん
とするものである。Therefore, in the present invention, a wire net is stretched on the form frame, a transparent synthetic resin film is stretched on the inner side surface of the wire mesh, and a fine hole is formed in the film. It is intended to provide a formwork panel characterized in that a large number of holes are formed.
【0009】[0009]
【作用】鉄筋コンクリート構造物或は鉄骨鉄筋コンクリ
ート構造物を構築する際には、施工場所に鉄筋を配筋
し、同鉄筋の周囲に型枠パネルを配設して、型枠を組立
て、同型枠内にコンクリートを打設し、コンクリートを
硬化させる。[Operation] When constructing a reinforced concrete structure or a steel-framed reinforced concrete structure, rebar is arranged at the construction site, a form panel is arranged around the rebar, and the form is assembled. Pour concrete into and harden the concrete.
【0010】この際、型枠パネルは、型枠フレームに金
網を張設し、同金網の内側面に透明な合成樹脂製フィル
ムを張設し、同フィルムに微小径の孔を多数個穿設して
いるために、打設したコンクリート中の水分のみを合成
樹脂製フィルムの微小径の孔、さらには金網の目を通し
て外部へ排出させることができるために、壁枠パネルの
受ける側圧を軽減させることができる。At this time, in the formwork panel, a wire net is stretched on the formwork frame, a transparent synthetic resin film is stretched on the inner surface of the wire mesh, and a large number of holes having a small diameter are punched in the film. Therefore, only the water in the placed concrete can be discharged to the outside through the small-diameter holes of the synthetic resin film, and further through the mesh of the wire mesh, so that the side pressure received by the wall frame panel is reduced. be able to.
【0011】しかも、金網と透明な合成樹脂フィルムを
透してコンクリートの打設状況を外部より視認すること
ができるために、コンクリートの打設不良個所を発明し
た場合には、バイブレーター等を利用してコンクリート
に必要なだけ振動を加えることにより、かかる打設不良
を速やかに解消して、コンクリートの均質性を良好に保
つことができると共に、後処理を不要にして構築作業を
迅速かつ確実に行なうことができる。In addition, since it is possible to visually confirm the concrete pouring condition from the outside through the wire mesh and the transparent synthetic resin film, when a defective concrete pouring point is invented, a vibrator or the like is used. By applying as much vibration as necessary to the concrete, it is possible to promptly eliminate such placement defects and maintain good homogeneity of the concrete, and to carry out construction work quickly and reliably without the need for post-treatment. be able to.
【0012】また、型枠パネルは、取外すことなく、壁
面の内外装材の下地材として使用することにより、合成
樹脂製フィルムによりコンクリートの風化を防止して、
鉄筋に錆が発生するのを確実に防止することができ、し
かも、金網によりコンクリートのくいつきを良好にし
て、同コンクリートの剥離防止やクラックの発生の防止
を図ることができる。Further, the form panel is used as a base material for interior and exterior materials of the wall surface without being removed, so that weathering of concrete is prevented by the synthetic resin film,
It is possible to reliably prevent rust from being generated on the reinforcing bar, and to improve the clinging of concrete by the wire netting to prevent the concrete from peeling off and from cracking.
【0013】そして、型枠を解体する手間や解体後の型
枠パネルを搬出する手間を省くことができるために、こ
の点からも構築作業能率を高めることができる。Since the labor for dismantling the formwork and the labor for carrying out the formwork panel after disassembly can be omitted, the construction work efficiency can be improved also from this point.
【0014】[0014]
【実施例】以下、本発明の実施例を図面を参照しながら
説明する。Embodiments of the present invention will be described below with reference to the drawings.
【0015】図1及び図2に示すAは、本発明に係る型
枠パネルを具備する梁用のプレハブ型鉄骨鉄筋型枠ユニ
ットであり、同ユニットAは、鉄骨Sとプレハブ型鉄筋
ユニットRと型枠Kとを、工場等で組立て形成するよう
にしている。1 and 2 shows a prefabricated steel frame rebar formwork unit for a beam having a formwork panel according to the present invention. The unit A includes a steel frame S and a prefabricated rebar unit R. The form K is assembled and formed in a factory or the like.
【0016】プレハブ型鉄筋ユニットRは、図2及び図
3に示すように、略門型に形成して前後方向に一定の間
隔を開けて多数個配置した剪断補強筋2と、各剪断補強
筋の少なくとも左右側隅部位置にそれぞれ直交状態に連
設した主筋1と、前後方向に伸延形成して、剪断補強筋
2の前後方向に隣接する各先端同士を一体的に連結する
左右一対の連結体3,3とから一対のユニット形成体r
1,r2を形成し、両ユニット形成体r1,r2 を、連結体3,
3同士を突き合せて連結金具としての連結ボルト4によ
り連結可能に構成している。As shown in FIGS. 2 and 3, the prefabricated rebar unit R is formed in a substantially gate shape and has a large number of shear reinforcing bars 2 arranged at regular intervals in the front-rear direction, and each shear reinforcing bar. Of at least the left and right side corners of the main reinforcement 1 and the pair of left and right connections that extend in the front-rear direction and integrally connect the ends of the shear reinforcement 2 that are adjacent in the front-rear direction. A pair of unit forming bodies r from the bodies 3 and 3
1, r2 are formed, both unit forming bodies r1, r2 are connected to each other,
3 are abutted against each other and can be connected by a connecting bolt 4 as a connecting fitting.
【0017】そして、図3に示すように、一方のユニッ
ト形成体r2に取付けた連結体3には、突き合せ時に他方
のユニット形成体r1に取付けた連結体3の内側方に重合
すべく連結片3aを伸延形成し、内外側に重合した連結体
と連結片3aとを連結ボルト4により連結するようにして
いる。5は、連結片3aと連結体3にそれぞれ穿設したボ
ルト孔、6は、鉄骨Sに穿設した連結孔である。Then, as shown in FIG. 3, the connecting body 3 attached to one unit forming body r2 is connected so as to overlap with the inside of the connecting body 3 attached to the other unit forming body r1 at the time of butting. The piece 3a is formed by extension, and the connecting body that has been polymerized on the inside and outside and the connecting piece 3a are connected by the connecting bolt 4. 5 is a bolt hole formed in each of the connecting piece 3a and the connecting body 3, and 6 is a connecting hole formed in the steel frame S.
【0018】かかる鉄筋ユニットRは、図2及び図3に
示すように、一対のユニット形成体r1,r2 を、鉄骨Sの
上下方向より囲むようにして、両ユニット形成体r1,r2
の連結片3aと連結体同士を連結ボルト4により連結する
ことにより配筋することができるものであり、両ユニッ
ト形成体r1,r2 の位置決めは、鉄骨Sのフランジ部s1,s
2 にそれぞれ軸線方向に一定の間隔を開けて固設したか
んざし筋7,7により行なうようにしており、同かんざ
し筋7,7の先端縁左右側部に主筋嵌合用凹部7a,7a を
形成して、各凹部7a,7a に各ユニット形成板r1,r2 に配
筋した主筋1,1を嵌合させると共に、溶接して位置決
め固定する。As shown in FIGS. 2 and 3, the reinforcing bar unit R surrounds a pair of unit forming bodies r1 and r2 in the vertical direction of the steel frame S so that both unit forming bodies r1 and r2 are surrounded.
The connecting piece 3a and the connecting body can be reinforced by connecting them with the connecting bolts 4, and the positioning of both unit forming bodies r1 and r2 is performed by the flange portions s1 and s
It is designed to be carried out by means of the knitting muscles 7 and 7 which are fixedly provided at a constant interval in the axial direction on the 2nd. Then, the main bars 1 and 1 arranged on the unit forming plates r1 and r2 are fitted into the recesses 7a and 7a, and are welded and positioned and fixed.
【0019】型枠Kは、図1及び図2に示すように、上
記したプレハブ型鉄筋ユニットRの左右側方及び下側方
において、それぞれ本発明に係る型枠パネル8,9,10
を、鉄骨Sにかんざし筋7,7とステー11,11 を介して
取付けたパネル支持フレーム16に張設して組立てるよう
にしている。As shown in FIGS. 1 and 2, the mold K is formed on the left and right sides and the lower side of the above-mentioned prefabricated rebar unit R, respectively, according to the present invention.
Is stretched on the panel support frame 16 attached to the steel frame S via the knitting bars 7, 7 and stays 11, 11 for assembly.
【0020】そして、型枠パネル8は、図4及び図5に
示すように、型枠フレーム12に金網13を張設し、同金網
13の内側面に透明な合成樹脂製フィルム14を張設し、同
フィルム14に微小径(例えば、0.1〜3mm )の孔15を多
数個穿設して形成している。13a は金網に形成した断面
V字状の補強リブである。As shown in FIGS. 4 and 5, the formwork panel 8 comprises a formwork frame 12 and a wire mesh 13 stretched over the formwork panel 8.
A transparent synthetic resin film 14 is stretched on the inner surface of 13 and a large number of holes 15 having a minute diameter (for example, 0.1 to 3 mm) are formed in the film 14. Reference numeral 13a is a reinforcing rib formed in the wire mesh and having a V-shaped cross section.
【0021】また、他の型枠パネル9,10も、上記型枠
パネル8と基本構造を同じくしており、型枠パネル10
は、上方にスラブを接続する関係上、型枠のパネル8よ
りも高さを低く形成している。The other formwork panels 9 and 10 have the same basic structure as the formwork panel 8 described above.
Has a lower height than that of the panel 8 of the form because of the connection of the slab to the upper side.
【0022】パネル支持フレーム16は、型枠パネル8,
9,10を嵌入可能な断面U字状に形成したパネル嵌込み
レール16a を、左右側にそれぞれ上下一対、また下側に
左右一対、開口部16b が対向するように配置し、対向す
る各レール16a,16a 間に型枠パネル8,9,10をそれぞ
れ倹飩式に嵌込んで張設することができるようにしてい
る。なお、必要に応じて、張設した型枠パネル8,9,
10を各レール16a に固定ピンにより固定することもでき
る。The panel support frame 16 includes the form panel 8,
Panel-mounting rails 16a each having a U-shaped cross section into which 9 and 10 can be fitted are arranged so that a pair of upper and lower sides are respectively on the left and right sides, and a pair of left and right sides are on the lower side. Form panels 8, 9 and 10 can be fitted and stretched between 16a and 16a in a spatula manner. In addition, if necessary, the stretched formwork panels 8, 9,
It is also possible to fix 10 to each rail 16a with a fixing pin.
【0023】そして、各パネル嵌込みレール16a は、鉄
骨Sに取付けたかんざし筋7,7の各左右側部よりステ
ー11,11 を突設して、各ステー11,11 の先端に取付けて
支持させている。Each panel fitting rail 16a is provided with projecting stays 11 and 11 from the left and right side portions of the knitting bars 7 and 7 attached to the steel frame S, and is attached to the tips of the stays 11 and 11 to be supported. I am letting you.
【0024】このように、形成したパネル支持フレーム
16の配設位置は、プレハブ型鉄筋ユニットRとの相対間
隔、すなわち、コンクリートのかぶりを考慮して設計す
る。The panel support frame thus formed
The arrangement position of 16 is designed in consideration of the relative distance to the prefabricated rebar unit R, that is, the covering of concrete.
【0025】また、型枠パネル8,9,10の中途部と鉄
骨Sとの間には、図2、図4、及び図5に示すように、
セパレーター17を介設して、同セパレーター17により、
コンクリート打設時の型枠パネル8,9,10の撓み等を
防止している。Further, as shown in FIG. 2, FIG. 4 and FIG. 5, between the middle portion of the form panel 8, 9, 10 and the steel frame S,
Through the separator 17, by the separator 17,
The bending of the formwork panels 8, 9 and 10 at the time of placing concrete is prevented.
【0026】そして、かかるセパレーター17は、型枠パ
ネル8の金網13に形成した補強リブ13a を貫通させて一
端を取付け、鉄骨Sのフランジ部s1,s2 又はウエブ部s3
に取付けた連結ナット18に他端を連結するようにしてい
る。The separator 17 is attached at its one end by penetrating the reinforcing rib 13a formed in the metal net 13 of the formwork panel 8 to attach the flanges s1, s2 or the web portion s3 of the steel frame S.
The other end is connected to the connection nut 18 attached to the.
【0027】図6は、柱用のプレハブ型鉄骨鉄筋型枠ユ
ニットAであり、プレハブ型鉄筋ユニットRの前後左右
側方の周囲に型枠パネル20,21,22,23 をパネル支持フレ
ーム16を介して張設して型枠Kを組立て形成している。FIG. 6 shows a prefabricated steel frame rebar formwork unit A for columns, in which formwork panels 20, 21, 22 and 23 are provided around the prefabricated rebar unit R in front, rear, left and right sides. The form K is assembled by being stretched through.
【0028】そして、図7は、かかるユニットAに組込
む柱用のプレハブ型鉄筋ユニットRであり、24は、梁用
のユニットAとの接続用空間である。25は接続金具であ
り、主筋1,1同士をかしめて接続するようにしてい
る。FIG. 7 shows a prefabricated rebar unit R for columns to be incorporated in the unit A, and 24 is a space for connecting with the unit A for beams. Reference numeral 25 is a connection fitting, which is designed to be caulked to connect the main bars 1 and 1.
【0029】本発明の実施例は、上記のように構成して
いるものであり、本実施例によれば、以下のような作用
効果が生起される。The embodiment of the present invention is configured as described above, and according to this embodiment, the following operational effects are produced.
【0030】すなわち、鉄骨鉄筋コンクリート構造物を
構築する際には、プレハブ型鉄骨鉄筋型枠ユニットA
を、予め工場等で柱用又は梁用として組立て形成し、各
ユニットAを施工現場に搬入して指定場所に建方し、各
ユニットAの型枠K内にコンクリートを打設して、コン
クリートを硬化させた後は、型枠パネル8,9,10を取
外すことなく壁面の内外装材の下地材として使用する。That is, when constructing a steel reinforced concrete structure, a prefabricated steel reinforced form unit A is used.
Are assembled and formed in advance in a factory or the like for pillars or beams, and each unit A is brought to the construction site and erected at a designated place, and concrete is placed in the form K of each unit A to make concrete. After being cured, it is used as a base material for the interior / exterior material of the wall surface without removing the form panel 8, 9, 10.
【0031】この際、型枠パネル8,9,10は、型枠フ
レーム12に金網13を張設し、同金網13の内側面に透明な
合成樹脂製フィルム14を張設し、同フィルム14に微小径
の孔15を多数個穿設して形成しているために、打設した
コンクリート中の水分のみを合成樹脂製フィルム14の微
小径の孔15、さらには金網13の目を通して外部へ排出さ
せることができるために、壁枠パネル8,9,10の受け
る側圧を軽減させることができる。At this time, in the mold frame panels 8, 9 and 10, a wire net 13 is stretched on the mold frame 12, and a transparent synthetic resin film 14 is stretched on the inner surface of the wire mesh 13, and the film 14 Since a large number of minute holes 15 are formed in the hole, only the water in the cast concrete is discharged to the outside through the minute holes 15 in the synthetic resin film 14 and further through the wire mesh 13. Since it can be discharged, the side pressure received by the wall frame panels 8, 9, 10 can be reduced.
【0032】しかも、金網13と透明な合成樹脂製フィル
ム14を透してコンクリートの打設状況を外部より視認す
ることができるために、コンクリートの打設不良個所を
発明した場合には、バイブレーター等を利用してコンク
リートに必要なだけ振動を加えることにより、かかる打
設不良を速やかに解消して、コンクリートの均質性を良
好に保つことができると共に、後処理を不要にして、構
築作業を迅速かつ確実に行なうことができる。In addition, since it is possible to visually confirm the concrete pouring condition from the outside through the wire net 13 and the transparent synthetic resin film 14, when a defective concrete pouring point is invented, a vibrator or the like is used. By applying as much vibration as necessary to the concrete using, it is possible to promptly eliminate such placement defects and maintain good homogeneity of the concrete. And it can be done reliably.
【0033】また、型枠パネル8,9,10は、取外すこ
となく、壁面の内外装材の下地材として使用することに
より、合成樹脂製フィルム14によりコンクリートの風化
を防止して、鉄筋に錆が発生するのを確実に防止するこ
とができ、しかも、金網13によりコンクリートのくいつ
きを良好にして、同コンクリートの剥離防止やクラック
の発生の防止を図ることができる。Further, the form panel 8, 9, 10 is used as a base material for interior and exterior materials of the wall surface without being removed, so that the synthetic resin film 14 prevents weathering of concrete and rusts the rebar. It is possible to reliably prevent the occurrence of cracks, and moreover, it is possible to improve the clinging of concrete by the wire netting 13 and prevent the concrete from peeling off and cracks from occurring.
【0034】そして、型枠Kを解体する手間や解体した
型枠パネルを搬出する手間を省くことができるために、
この点からも構築作業能率を高めることができる。Since it is possible to save the trouble of dismantling the mold K and the trouble of carrying out the dismantled mold panel,
From this point as well, the construction work efficiency can be improved.
【0035】[0035]
【効果】本発明によれば、以下のような効果が得られ
る。According to the present invention, the following effects can be obtained.
【0036】合成樹脂製フィルムに多数個穿設した微
小径の孔と金網の目を通して、コンクリート中の水分の
みを外部へ排出することができるために、型枠パネルが
受ける側圧を軽減させることができて、同型枠パネルの
変形、さらにはコンクリート構造物の構築不良等を防止
することができる。Only the water in the concrete can be discharged to the outside through the small-diameter holes and the wire mesh formed in the synthetic resin film, so that the side pressure received by the form panel can be reduced. As a result, it is possible to prevent deformation of the same formwork panel and further prevent defective construction of the concrete structure.
【0037】金網の目と透明な合成樹脂製フィルムを
透してコンクリートの打設状況を外部より視認すること
ができるために、打設不良個所の早期発明、早期対処が
行なえて、コンクリートの均質性を良好に確保すること
ができる。Since it is possible to visually check the concrete placing condition from the outside through the mesh of the wire mesh and the transparent synthetic resin film, it is possible to early invent the defective place of the placing and take an early countermeasure, and to make the concrete uniform. It is possible to ensure good performance.
【0038】そして、コンクリート硬化後の打設不良個
所の後処理が不要となるために、構築作業能率を高める
ことができる。Further, since the post-treatment of the defective pouring place after hardening of the concrete is unnecessary, the construction work efficiency can be improved.
【0039】型枠パネルは取外すことなく、いわゆる
捨殺しにすることにより、壁面の内外装材の下地材とし
て使用することができる。The form panel can be used as a base material for the interior / exterior material of the wall surface by removing the form panel without removing it.
【0040】合成樹脂製フィルムによりコンクリート
の風化を防止して、鉄筋への錆の発生防止を確保するこ
とができる。The synthetic resin film can prevent weathering of concrete and can prevent rust from occurring on the reinforcing bars.
【0041】金網によりコンクリートのくいつきを良
好にして、同コンクリートの剥離防止やクラックの発生
防止を図ることができる。The wire mesh can improve the clinging of concrete to prevent the concrete from peeling off and from cracking.
【0042】型枠の解体作業や解体した型枠パネルの
搬出作業の手間を省くことができるために、この点から
も構築作業能率を高めることができる。Since it is possible to save the labor of disassembling the formwork and carrying out the disassembled formwork panel, the construction work efficiency can be improved also from this point.
【図1】本発明に係る型枠パネルを具備する梁用のプレ
ハブ型鉄骨鉄筋型枠ユニットの斜視説明図。FIG. 1 is a perspective explanatory view of a prefabricated steel frame rebar form unit for a beam including a form panel according to the present invention.
【図2】同ユニットの断面正面図。FIG. 2 is a sectional front view of the unit.
【図3】梁用のプレハブ型鉄筋ユニットの分解斜視図。FIG. 3 is an exploded perspective view of a prefabricated rebar unit for a beam.
【図4】本発明に係る型枠パネルの一部切欠斜視説明
図。FIG. 4 is a partially cutaway perspective explanatory view of a formwork panel according to the present invention.
【図5】同型枠パネルの断面図。FIG. 5 is a cross-sectional view of the same formwork panel.
【図6】柱用のプレハブ型鉄骨鉄筋型枠ユニットの断面
正面図。FIG. 6 is a cross-sectional front view of a prefabricated steel frame rebar form unit for a pillar.
【図7】柱用のプレハブ型鉄筋ユニットの分解斜視図。FIG. 7 is an exploded perspective view of a prefabricated rebar unit for a pillar.
A プレハブ型鉄骨鉄筋型枠ユニット S 鉄骨 R ブレハブ型鉄筋ユニット K 型枠 1 主筋 2 剪断補強筋 3 連結体 8 型枠パネル 12 型枠フレーム 13 金網 14 合成樹脂製フィルム 15 孔 A Prefabricated steel frame rebar formwork unit S Steel frame R Brehab type rebar unit K Formwork 1 Main bar 2 Shear reinforcement 3 Connected body 8 Formwork panel 12 Formwork frame 13 Wire mesh 14 Synthetic resin film 15 holes
Claims (1)
内側面に透明な合成樹脂製フィルムを張設し、同フィル
ムに微小径の孔を多数個穿設したことを特徴とする型枠
パネル。Claims: 1. A wire mesh is stretched on a form frame, a transparent synthetic resin film is stretched on the inner surface of the wire mesh, and a large number of holes having small diameters are punched in the film. Form panel characterized by doing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18901391A JP3191955B2 (en) | 1991-07-29 | 1991-07-29 | Formwork of prefabricated steel frame formwork unit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18901391A JP3191955B2 (en) | 1991-07-29 | 1991-07-29 | Formwork of prefabricated steel frame formwork unit |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0533387A true JPH0533387A (en) | 1993-02-09 |
JP3191955B2 JP3191955B2 (en) | 2001-07-23 |
Family
ID=16233843
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18901391A Expired - Fee Related JP3191955B2 (en) | 1991-07-29 | 1991-07-29 | Formwork of prefabricated steel frame formwork unit |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3191955B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2019173547A (en) * | 2018-03-29 | 2019-10-10 | 大和ハウス工業株式会社 | Lath form |
-
1991
- 1991-07-29 JP JP18901391A patent/JP3191955B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2019173547A (en) * | 2018-03-29 | 2019-10-10 | 大和ハウス工業株式会社 | Lath form |
Also Published As
Publication number | Publication date |
---|---|
JP3191955B2 (en) | 2001-07-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2000170285A (en) | Connecting method for steel sheet concrete structural wall and junction structure | |
JPH03250130A (en) | Constructing method using reinforced steel framed reinforced half-precast concrete beam without main reinforcing steel | |
KR100203016B1 (en) | Monolithic beam form | |
KR101720122B1 (en) | concrete form Integrated structures | |
JPH07229202A (en) | Joint construction between reinforced concrete column and steel frame beam | |
JP3069407B2 (en) | Prefabricated steel frame formwork unit and construction method of the unit | |
JPH0533387A (en) | Form panel | |
KR20040102391A (en) | Composite Beam Stiffened with In-Situ Concrete Panel Having Embedded Lower Flange and Constructing Method thereof | |
JPH11166294A (en) | Steel frame-contained concrete beam and floor construction method using the concrete beam | |
KR101078292B1 (en) | Concrete slab mold assembly and method for constructing slab | |
JPH10227010A (en) | Steel form with main reinforcement for bridge floor panel and bridge floor panel construction method using it | |
JPH07292683A (en) | Anchor frame and foundation construction method using the frame | |
JPH07292855A (en) | Steel encased reinforcing concrete girder | |
JP3275017B2 (en) | Method of manufacturing caisson using precast member | |
JP2000073448A (en) | Connection method and structure for precast concrete beam and column | |
JP3193399B2 (en) | Prefabricated rebar unit | |
JPH10121417A (en) | Concrete frame, and method for constructing concrete structure using this concrete frame | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
KR102585526B1 (en) | Composite frame with end-buried girder joint | |
JPH10183533A (en) | Bridge girder, bridge girder component, and work execution method for bridge girder | |
JP2001200594A (en) | Method for constructing structure consisting of column with large section and beam | |
KR960011364B1 (en) | Fixing method of steel-frame/steel concrete beam | |
JPH06299718A (en) | Construction of wall, floor in atomic power plant and wall slab thereof | |
JP2707966B2 (en) | Floor construction method using prestressed concrete plate as beam-side formwork | |
JP2797023B2 (en) | Construction method of beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |