JPH05311735A - Pole-beam structure - Google Patents

Pole-beam structure

Info

Publication number
JPH05311735A
JPH05311735A JP14651192A JP14651192A JPH05311735A JP H05311735 A JPH05311735 A JP H05311735A JP 14651192 A JP14651192 A JP 14651192A JP 14651192 A JP14651192 A JP 14651192A JP H05311735 A JPH05311735 A JP H05311735A
Authority
JP
Japan
Prior art keywords
steel pipe
pillar
steel
column
space
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14651192A
Other languages
Japanese (ja)
Inventor
Tetsuya Yamada
哲也 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP14651192A priority Critical patent/JPH05311735A/en
Publication of JPH05311735A publication Critical patent/JPH05311735A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE:To obtain efficient accurate pole-beam structure by a reinforced concrete pole and a steel beam. CONSTITUTION:Beams 3 suspended between poles 2, 2 are composed of structural steel pipes 30 consisting of two steel pipes 31, internal covers 35 are installed near the pole 2 sides in each steel pipe 31, and the insides of the steel pipes 31 are partitioned into placing spaces 29, in which bodies 21 can be moved forward and filled, and spaces 310 remaining in the beams 3. The studs 32 of the steel pipes 31 and main reinforcements 51 for connecting the poles and the beams are disposed previously into the placing spaces 29, these studs and main reinforcements are buried and fixed into the bodies 21 forwarded into the placing spaces 29, and the beams 3 are connected and supported integrally to the poles 2.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、コンクリート構造によ
る柱と鋼管等による鋼材梁を接合してなる柱・梁構造に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pillar / beam structure formed by joining a pillar made of concrete structure and a steel beam made of steel pipe or the like.

【0002】[0002]

【従来の技術】従来、高層建築においては、地震や風圧
に対する耐久性が強く要求されることから、柱や梁等か
らなる構造体に、靱性に優れた鉄骨構造や鉄骨鉄筋コン
クリート構造が広く用いられている一方で、中低層建築
においては、経済性が重視されることから、主として鉄
筋コンクリート構造が用いられていた。ところが、最近
では鉄筋コンクリート構造とその他のプレキャスト材等
を用いて、それ等の各々の長所を活かした複合構造を採
用せんとする動きが強まっており、そういったことの可
能な柱・梁構造の開発が求められている。
2. Description of the Related Art Conventionally, in high-rise buildings, since durability against earthquakes and wind pressure is strongly required, steel structures and steel reinforced concrete structures having excellent toughness are widely used for structures such as columns and beams. On the other hand, in middle- and low-rise buildings, reinforced concrete structures were mainly used because economic efficiency is important. However, recently, there has been an increasing movement to adopt a composite structure that uses reinforced concrete structures and other precast materials to take advantage of their respective strengths. It has been demanded.

【0003】[0003]

【発明が解決しようとする課題】しかし、こういった複
合構造により構造体を構成する場合には、各柱と梁を接
合する際に、該柱と梁を一体に連結する形で両者を構成
している各々の部材を結合しなければ両者間の十分な接
合強度を確保することが出来ないために、その接合作業
は非常に煩雑で、その分施工効率が悪い。本発明は、上
記事情に鑑み、鉄筋コンクリート柱と鋼材梁を用いて、
両者を簡単且つ適格に接合することが出来、施工効率の
良い、柱・梁構造を提供するものである。
However, in the case of constructing a structure with such a composite structure, when the columns and beams are joined together, the columns and beams are integrally connected to each other. Since it is not possible to secure a sufficient joint strength between the two members unless they are joined together, the joining work is very complicated, and the construction efficiency is correspondingly low. In view of the above circumstances, the present invention uses a reinforced concrete column and a steel beam,
It is possible to easily and properly join the both, and to provide a pillar / beam structure with good construction efficiency.

【0004】[0004]

【課題を解決するための手段】即ち本発明は、隣接する
コンクリート材(21)からなる柱(2)、(2)間に
梁(3)を懸架した形の柱・梁構造において、前記梁
(3)は、前記隣接する柱(2)、(2)を接続する形
の鋼管体(30)を有し、前記鋼管体(30)内部の両
端部近傍に遮蔽蓋(35)を、該鋼管体(30)の内部
の空間(29)、(310)を仕切る形で設け、前記鋼
管体(30)内部の前記遮蔽蓋(35)より柱(2)側
の空間(29)に、柱(2)と梁(3)との連結手段
(51)、(32)を、該鋼管体(30)と前記コンク
リート材(21)とを繋ぐ形で設けて構成される。ま
た、前記鋼管体(30)は、前記隣接する柱(2)、
(2)を接続する形で直列に並ぶ複数の分割管体(3
1)を、その接続部(31c)を介して隣接する分割管
体(31)、(31)の双方に跨る形で被嵌した接続用
管体(33)を介して一体に接続して構成されることも
ある。なお、( )内の番号等は、図面における対応す
る要素を示す、便宜的なものであり、従って、本記述は
図面上の記載に限定拘束されるものではない。以下の
That is, the present invention provides a pillar-beam structure in which a beam (3) is suspended between adjacent pillars (2) and (2) made of concrete material (21). (3) has a steel pipe body (30) of a shape that connects the adjacent columns (2) and (2), and a shielding lid (35) near both ends inside the steel pipe body (30), Spaces (29) and (310) inside the steel pipe body (30) are provided so as to be partitioned, and a pillar is provided in the space (29) inside the steel pipe body (30) closer to the pillar (2) than the shielding lid (35). The connecting means (51) and (32) for connecting the (2) and the beam (3) are provided so as to connect the steel pipe body (30) and the concrete material (21). Further, the steel pipe body (30) includes the adjacent pillars (2),
A plurality of divided pipe bodies (3
1) is integrally connected via the connecting portion (31c) and the connecting pipe body (33) fitted so as to extend over both of the adjacent divided pipe bodies (31) and (31). It may be done. The numbers in parentheses () indicate the corresponding elements in the drawings for the sake of convenience, and therefore the present description is not limited to the description in the drawings. below

【作用】の欄についても同様である。The same applies to the column of [Operation].

【0005】[0005]

【作用】上記した構成により、本発明は、柱(2)が梁
(3)を一体に支持するように作用する。また、接続用
管体(33)は複数の分割管体(31)を、その接続部
(31c)を相互に付き合わせた形で接続するように作
用する。
With the above-mentioned structure, the present invention functions so that the pillar (2) integrally supports the beam (3). Further, the connecting pipe body (33) acts so as to connect the plurality of divided pipe bodies (31) with their connecting portions (31c) abutting each other.

【0006】[0006]

【実施例】図1は本発明による柱・梁構造の一実施例を
示す断側面図、図2は図1に示す柱・梁構造における柱
・梁接合部分の拡大図、図3は図1のIII、III矢視断面
図、図4は図1のIV、IV矢視断面図、図5乃至図7は図
1に示す柱・梁構造の施工手順を示す一連の側面図であ
る。
1 is a sectional side view showing an embodiment of a pillar / beam structure according to the present invention, FIG. 2 is an enlarged view of a pillar / beam joint portion in the pillar / beam structure shown in FIG. 1, and FIG. III, a sectional view taken along the arrow III in FIG. 4, FIG. 4 is a sectional view taken along the line IV, IV in FIG. 1, and FIGS. 5 to 7 are a series of side views showing the construction procedure of the pillar / beam structure shown in FIG.

【0007】構造物1は、図1に示すように、矩形断面
に形成された垂直部材である柱2を有しており、柱2
は、その各々が図1上下方向に伸延する形の鉄筋コンク
リートにより構成されて、水平方向である図1左右方向
及び図1紙面と交差方向に所定の間隔で複数立設されて
いる。また、構造物1には水平部材である梁3が、該構
造物1の各階において図1左右方向又は図1紙面と交差
方向に隣接する柱2、2間に懸架支持された形で、図1
上下方向にも複数並んで設けられており、梁3は、柱2
の各階に設定された梁取り付け部5に、各々の梁3の材
軸方向が柱2の材軸方向と交差するように接続支持され
た形で、両者2、3が接合されている。従って、構造物
1には柱2の梁取り付け部5が、図1上下、左右並びに
図1紙面と交差する方向に並ぶ形で複数設けられてい
る。
As shown in FIG. 1, the structure 1 has a pillar 2 which is a vertical member formed in a rectangular cross section.
Each of them is made of reinforced concrete that extends in the vertical direction in FIG. 1, and a plurality of them are erected at predetermined intervals in the horizontal direction in FIG. Further, in the structure 1, a beam 3 which is a horizontal member is suspended and supported between columns 2 which are adjacent to each other on each floor of the structure 1 in the lateral direction of FIG. 1
A plurality of beams are provided side by side in the vertical direction.
The beams 2 and 3 are joined to the beam attachment portion 5 set on each floor so that the beam axis direction of each beam 3 is connected and supported so as to intersect the beam axis direction of the column 2. Therefore, the structure 1 is provided with a plurality of beam attachment portions 5 of the pillars 2 arranged in the vertical direction, the horizontal direction in FIG. 1, and in the direction intersecting the plane of FIG.

【0008】各柱2は、図1に示すように、所定の圧縮
強度をなす形で矩形断面に打設されたコンクリートから
なる躯体21を有しており、躯体21はいま、図1下側
から上側に向けて順次打ち継がれてきた形で、その上端
21a部分まで既に構築完了されている。躯体21中に
は所定の引張り強度を有する鉄筋等の棒状部材からなる
主筋22が、その配筋方向を該躯体21の伸延方向であ
る上下方向に向けた形で所定の本数づつ埋設されてお
り、また、躯体21中には主筋22と同一素材からなる
フープ筋23が、該躯体21中に埋設された隣接する主
筋22間を連結する形で図1上下方向に所定の間隔で複
数埋設されている。これ等フープ筋23に連結された躯
体21の主筋22は、いま、躯体21の上端21a部分
より更に図1上側に示す天空に向けて若干長さ分だけ突
出した形になっており、躯体21の上端21aから図1
上側に向けて突出した分の主筋22及びフープ筋23の
周囲には、上端21aを介して躯体21に打ち継がれる
柱2のコンクリートを成型し得る型枠9が、函型枠状に
組み立て配設されている。
As shown in FIG. 1, each pillar 2 has a skeleton body 21 made of concrete which is placed in a rectangular cross section in a form having a predetermined compressive strength. The skeleton body 21 is now on the lower side of FIG. The construction has been completed up to the upper end 21a portion in such a manner that it has been successively spliced from the top to the top. A main bar 22 made of a bar-shaped member such as a reinforcing bar having a predetermined tensile strength is embedded in the body 21 in a predetermined number in a form in which the reinforcing bar direction is oriented in the up-down direction which is the extension direction of the body 21. Further, a plurality of hoop muscles 23 made of the same material as the main muscles 22 are embedded in the body 21 at predetermined intervals in the vertical direction in FIG. 1 so as to connect the adjacent main muscles 22 embedded in the body 21. ing. The main muscles 22 of the skeleton body 21 connected to the hoop muscles 23 are now in a shape protruding from the upper end 21a of the skeleton body 21 toward the sky shown in the upper side of FIG. 1 from the upper end 21a of the
Around the main bar 22 and the hoop bar 23 protruding upward, a mold 9 capable of molding the concrete of the pillar 2 that is spliced to the skeleton 21 via the upper end 21a is assembled and arranged in a box form. It is set up.

【0009】各梁3は、図1に示すように、隣接する柱
2、2間を接続する形の鋼管体である構造鋼管30によ
り構成されており、構造鋼管30は、隣接する柱2、2
間の距離L1の略半分の長さをなす形で角筒状に形成さ
れた2本の鋼管31、31を、後述するジョイント鋼管
33を介してこれを該鋼管31、31に被嵌する形で連
結して構成されている。2本の鋼管31、31は、両者
の側端面31c、31cを突き合わせた形で図1左右方
向に直列に配設されており、2本の鋼管31、31の連
結部には、該鋼管31、31を連結接続するためのジョ
イント鋼管33が、図1左右方向に隣接する柱2、2間
の略真中近傍に、図1左右に隣接する鋼管31、31を
跨いでその各々の外周31a、31aを長さL2分被覆
する形で設けられている。各ジョイント鋼管33は、図
4に示すように、その内周33bが、鋼管31の外周3
1aに略沿った断面形状をなし、且つ鋼管31に対して
図1左右方向に摺動自在な形で角筒状に形成されている
が、既に梁3中に配設完了されたジョイント鋼管31
は、図1に示すその左右両側端部33c、33cが、鋼
管31、31の外周31a、31aに溶接等により固定
された形で、既に配置固定されている。
As shown in FIG. 1, each beam 3 is composed of a structural steel pipe 30 which is a steel pipe body in which adjacent columns 2 and 2 are connected to each other. Two
A shape in which two steel pipes 31, 31 formed in a rectangular tube shape having a length approximately half the distance L1 between them are fitted into the steel pipes 31, 31 via a joint steel pipe 33 described later. It is configured by connecting with. The two steel pipes 31, 31 are arranged in series in the left-right direction of FIG. 1 with their side end faces 31c, 31c butted to each other. 1, a joint steel pipe 33 for connecting and connecting the steel pipes 31 and 31 adjacent to each other in the left-right direction of FIG. It is provided in a form of covering 31a by a length L2. As shown in FIG. 4, each joint steel pipe 33 has an inner circumference 33 b that is the outer circumference 3 of the steel pipe 31.
The joint steel pipe 31 has a cross-sectional shape substantially along 1a and is formed in a rectangular tube shape so as to be slidable in the left-right direction in FIG.
The left and right end portions 33c, 33c shown in FIG. 1 are already arranged and fixed in such a manner that they are fixed to the outer peripheries 31a, 31a of the steel pipes 31, 31 by welding or the like.

【0010】構造鋼管30の両端部近傍である各鋼管3
1の柱2側の端部近傍には、図2に示すように、内蓋3
5が、該鋼管31の内部の空間を図2左右に仕切る形で
設けられており、内蓋35の図2左側には、後にコンク
リートが打設充填され得る形の打設空間29が、側端面
31cから所定の長さL3分だけ鋼管31内に形成配設
されている。内蓋35の図2右側には、後に空隙部分と
して梁3中に残留する空間310が鋼管31内に形成さ
れており、図1左右方向に隣接する鋼管31、31の空
間310、310は互いに連通した状態になっている。
また、鋼管31の打設空間29には、図2又は図3に示
すように、柱2と梁3との連結手段であるスタッド32
が、該鋼管31の上下の管壁から該打設空間29側に向
けて突出した形で所定の本数づつ打ち込み装着されてお
り、打設空間29内には、鋼管31の図2左端部に示す
側端面31cを介して、柱2・梁3連結用の主筋51及
び該主筋51を連結するフープ筋52が、前記梁取り付
け部5において柱2中を図1においては左右に貫通する
形で所定の本数づつ配設されている。梁取り付け部5の
主筋51は、その各々の配筋方向を梁3の材軸方向と一
致させた形で、図1左右方向に伸延配設されており、一
方、フープ筋52は、図3に示すように、その各々が主
筋51をU字状に包囲する形で、図1左右方向に所定の
ピッチで並んでいる。柱2・梁3連結用の主筋51は、
前記柱2の主筋22に結束、溶接等により連結固定され
ているが、該主筋51及びこれを連結するフープ筋52
は、図1に示す状態において未だ仮固定状態にあって、
後に柱2の躯体21と構造鋼管30を構成している鋼管
31を繋ぐ形で該躯体21中に埋設定着されることにな
る。
Each steel pipe 3 near both ends of the structural steel pipe 30
As shown in FIG. 2, the inner lid 3 is provided near the end of the column 1 on the side of the column 2.
2 is provided in such a manner that the space inside the steel pipe 31 is divided into the left and right sides in FIG. 2, and the casting space 29 in a shape in which concrete can be later poured and filled is provided on the left side of the inner lid 35 in FIG. It is formed and arranged in the steel pipe 31 by a predetermined length L3 from the end surface 31c. On the right side in FIG. 2 of the inner lid 35, a space 310, which later remains in the beam 3 as a void portion, is formed in the steel pipe 31, and the spaces 310, 310 of the steel pipes 31, 31 adjacent in the left-right direction in FIG. It is in a state of communication.
Further, as shown in FIG. 2 or FIG. 3, in the casting space 29 of the steel pipe 31, a stud 32 that is a connecting means of the pillar 2 and the beam 3 is provided.
2 are mounted by driving in a predetermined number from the upper and lower pipe walls of the steel pipe 31 toward the casting space 29 side. A main bar 51 for connecting the column 2 and the beam 3 and a hoop bar 52 connecting the main bar 51 through the side end surface 31c shown in the form of penetrating left and right in the column 2 in FIG. A predetermined number of them are arranged. The main reinforcements 51 of the beam attachment portion 5 are arranged so as to extend in the left-right direction in FIG. 1 in such a manner that their respective reinforcement arrangements are aligned with the material axis direction of the beams 3, while the hoop reinforcements 52 are shown in FIG. As shown in FIG. 1, each of them surrounds the main bar 51 in a U shape and is arranged at a predetermined pitch in the left-right direction in FIG. The main bar 51 for connecting the pillar 2 and the beam 3 is
The pillar 2 is connected and fixed to the main bar 22 of the pillar 2 by bundling, welding, etc., but the main bar 51 and the hoop bar 52 connecting the main bar 51.
Is still temporarily fixed in the state shown in FIG.
After that, the frame 21 of the pillar 2 and the steel pipe 31 forming the structural steel pipe 30 are connected and embedded in the frame 21.

【0011】従って、梁3を構成している構造鋼管30
の2本の鋼管31のそれぞれは、その側端面31cの一
方側が柱2を構成している躯体21の図1左又は右の側
面21bと面一に整合した形で、既に構築完了された躯
体21の上端21aと型枠9の下端との間にそれぞれ配
置されており、鋼管31と躯体21とは、後に柱2・梁
3連結用の主筋51及びフープ筋52が、該躯体21の
上端面21a上に打ち継がれるコンクリート中に定着支
持されることにより、一体をなし得るように構成されて
いる。なお、図1に示す実施例においては、梁取り付け
部5において柱2を挾んで隣接する鋼管31、31は、
柱2・梁3連結用の主筋51が該柱2を貫通することに
より、両者31、31が該柱2を介して接続連結された
形になっている。また、2本の鋼管31、31が構成し
ている構造鋼管30上には、後に鉄筋コンクリート等か
らなるスラブ7(図示せず)が、柱2及び梁3に囲まれ
た空間に水平方向(図1左右及び紙面の奥手前方向)に
展開する形で、その四方に配置する構造鋼管30上に載
戴支持されることになり、従って、スラブ7の水平方向
4隅には垂直部材である4本の前記柱2が、各階のスラ
ブ7を上下方向である図1紙面と交差方向に貫通する形
になる。
Therefore, the structural steel pipe 30 constituting the beam 3
Each of the two steel pipes 31 of FIG. 1 has already been completed in a form in which the one side of the side end face 31c is flush with the left or right side face 21b of FIG. 21 are respectively arranged between the upper end 21a of 21 and the lower end of the form 9, and the steel pipe 31 and the skeleton 21 have a main bar 51 and a hoop bar 52 for connecting the post 2 and the beam 3 on the skeleton 21. It is configured so that it can be integrated by being fixedly supported in concrete that is spliced onto the end face 21a. In the embodiment shown in FIG. 1, the steel pipes 31, 31 that are adjacent to each other with the pillar 2 in the beam attachment portion 5 are
A main bar 51 for connecting the pillar 2 and the beam 3 penetrates the pillar 2 so that the both 31, 31 are connected and connected via the pillar 2. A slab 7 (not shown) later made of reinforced concrete or the like is horizontally arranged in a space surrounded by the columns 2 and the beams 3 on the structural steel pipe 30 constituted by the two steel pipes 31, 31 (see FIG. (1) to the left and right and in the front of the paper), and is mounted and supported on the structural steel pipes 30 arranged on all four sides thereof. Therefore, at the four horizontal corners of the slab 7, there are vertical members. The pillar 2 of the book penetrates the slab 7 of each floor in a direction intersecting with the vertical plane of FIG.

【0012】構造物1等は以上のような構成を有してい
るので、該構造物1の隣接する柱2、2間に梁3を打設
構築する際には、まず、図5に示すように、隣接する柱
2、2のそれぞれの梁取り付け部5、5まで躯体21を
打設構築する。すると、いま、図5に示す状態において
は躯体21の上端21a上に、該躯体21から主筋22
が上方に向けてそれぞれ突出した形になっている。そこ
で、図5左側に示す柱2の梁取り付け部5に、図5一点
鎖線で示すように鋼管31を、その伸延方向を梁3の材
軸方向に一致させて柱2に片持ち支持させる形で、躯体
21の上面21a上に後述する型枠9等を利用して仮固
定すると共に、該鋼管31内に、柱2・梁3連結用の主
筋51及びフープ筋52を組付けて、該主筋51と躯体
21の主筋22とを適宜結束することにより、主筋51
及びフープ筋52を柱2側に連結支持させる。また、躯
体21の上端21aから突出した主筋22の周囲に、図
6一点鎖線で示すように、該上端21aに打ち継がれる
躯体21の打設構築形状に対応した形で、型枠9を組み
立てると共に、該型枠9内には、躯体21に必要な主筋
22及びフープ筋23を所定の本数づつ、構築済み躯体
21の上端21a上に突出している主筋22に適宜継ぎ
足す形で組み立て配設する。
Since the structure 1 and the like have the above-mentioned structure, when constructing the beam 3 between the adjacent columns 2 and 2 of the structure 1, first, FIG. 5 is shown. In this way, the frame 21 is driven and constructed up to the beam attachment portions 5 and 5 of the adjacent columns 2 and 2, respectively. Then, now in the state shown in FIG. 5, the main bar 22 is attached to the upper end 21a of the body 21 from the body 21.
Are projected upwards. Therefore, in the beam mounting portion 5 of the column 2 shown on the left side of FIG. 5, a steel pipe 31 is cantilever-supported by the column 2 with the extension direction thereof aligned with the axial direction of the beam 3 as shown by the chain line in FIG. Then, while temporarily fixing it on the upper surface 21a of the skeleton 21 by using a mold 9 or the like described later, the main bar 51 for connecting the column 2 and the beam 3 and the hoop bar 52 are assembled in the steel pipe 31, By appropriately binding the main muscles 51 and the main muscles 22 of the body 21, the main muscles 51
The hoop muscles 52 are connected and supported on the column 2 side. Further, as shown by the alternate long and short dash line in FIG. 6, around the main bar 22 protruding from the upper end 21a of the skeleton body 21, the form 9 is assembled in a shape corresponding to the driving construction shape of the skeleton body 21 to be spliced to the upper end 21a. At the same time, a predetermined number of main muscles 22 and hoop muscles 23 required for the skeleton 21 are assembled and arranged in the form 9 in such a manner that they are appropriately added to the main muscles 22 protruding above the upper end 21a of the constructed skeleton 21. To do.

【0013】すると、いま、柱2の梁取り付け部5に
は、躯体21の上端21aと型枠9の下端部との間に鋼
管31が挾まれた状態になり、該鋼管31の柱2側はそ
の内部の打設空間29が型枠9内に連通した形で、該柱
2側に仮支持される。こうして鋼管31は図6左側の柱
2に仮支持されるが、この際該鋼管31には予め図6一
点鎖線で示すように、該鋼管31の右端側にジョイント
鋼管33を嵌装しておく。なお、ジョイント鋼管33
は、未だ鋼管31の外周31aに溶接等により固定され
ていない状態においては、該鋼管31に対して左右に摺
動することが出来るので、該ジョイント鋼管33は、鋼
管31に直列に隣接する鋼管31の位置決め配設作業の
障害にならないように、これを適宜な位置に仮止めして
おく。こうしておいて、次に図6右側に示すように、柱
2、2間に配設すべきもう一本の鋼管31を、その伸延
方向を鋼管31の伸延方向と一致する梁3の材軸方向に
向けた形で図6矢印方向に降ろしてきて、該もう一本の
鋼管31を既に図6左側の柱2の梁取り付け部5に仮支
持された鋼管31の側端面31cにその側端面31bを
整合させると共に、その図6右側に示す側端面31cを
図6右側の柱2の梁取り付け部5に合わせる形で、適宜
配設する。そして、図6右側に示す柱2における、柱2
・梁3連結用の主筋51及びフープ筋52を適宜その梁
取り付け部5において組み立て配筋し、これを躯体21
の主筋22と結束連結しておく。
Then, at the beam mounting portion 5 of the column 2, the steel pipe 31 is now sandwiched between the upper end 21a of the frame 21 and the lower end of the formwork 9, and the steel pipe 31 has the column 2 side. Is temporarily supported on the side of the pillar 2 in a form in which the casting space 29 inside the mold communicates with the inside of the mold 9. In this way, the steel pipe 31 is temporarily supported by the column 2 on the left side of FIG. 6, and at this time, a joint steel pipe 33 is fitted to the steel pipe 31 in advance on the right end side of the steel pipe 31, as indicated by the alternate long and short dash line in FIG. .. The joint steel pipe 33
Can slide left and right with respect to the steel pipe 31 in a state where it is not yet fixed to the outer circumference 31a of the steel pipe 31 by the welding or the like, the joint steel pipe 33 is a steel pipe that is adjacent to the steel pipe 31 in series. This is temporarily fixed to an appropriate position so as not to hinder the positioning and arrangement work of 31. Then, as shown in the right side of FIG. 6, another steel pipe 31 to be disposed between the columns 2 and 2 is provided in the axial direction of the beam 3 whose extension direction matches the extension direction of the steel pipe 31. 6 in the direction of the arrow in FIG. 6 and the other steel pipe 31 is attached to the side end face 31c of the steel pipe 31 which is already temporarily supported by the beam mounting portion 5 of the column 2 on the left side of FIG. 6 and the side end surface 31c shown on the right side of FIG. 6 is appropriately arranged in a form of being aligned with the beam mounting portion 5 of the column 2 on the right side of FIG. And the pillar 2 in the pillar 2 shown on the right side of FIG.
-A main bar 51 and a hoop bar 52 for connecting the beam 3 are appropriately assembled and arranged in the beam attachment portion 5, and the bar 21 is attached to the frame 21.
The main muscles 22 are bound and connected.

【0014】こうして柱2、2間に梁3を構成している
2本の鋼管31、31が懸架仮支持されて、これにより
構造鋼管30が一体に連結形成されたところで、先に図
6左側の柱2の右側に片持ち支持された鋼管31の右端
側に図6一点鎖線で示すように嵌装仮固定されたジョイ
ント鋼管33を、図7に示すように、隣接する鋼管3
1、31の両者に跨ってこれを被嵌する形に掛け渡し、
該鋼管31、31に掛け渡したジョイント鋼管33を、
その各々の外周31a、31aと溶接等により固定一体
化する。(即ちこの状態が、図1に示す状態になってい
る。)なお、こうして2本の鋼管31、31を柱2、2
間に懸架する際に該鋼管31、31はそれぞれが柱2、
2に片持ち状に仮支持される形になるところから、その
両者のジョイント部分において側端面31c、31cを
完全に整合一致させることは極めて難しいが、この際、
鋼管31はその打設空間29内に後述するように躯体2
1のコンクリートが打設充填される迄の間は、若干移動
させることが出来ることと、2本の鋼管31、31の両
者を位置決め固定して後、ジョイント鋼管33を横方向
にずらす形で、両者31、31をジョイントすることが
出来ることにより、これ等鋼管31、31の位置決め固
定及びそのジョイント作業は円滑に行われることが出来
る。
In this way, the two steel pipes 31, 31 forming the beam 3 between the columns 2, 2 are temporarily supported by suspension, and thereby the structural steel pipe 30 is integrally formed. Of the steel pipe 31 cantilevered on the right side of the column 2, the joint steel pipe 33 fitted and temporarily fixed as shown by the alternate long and short dash line in FIG.
Straddle both 1 and 31 so as to fit it,
The joint steel pipe 33 hung over the steel pipes 31 and 31,
The outer peripheries 31a and 31a are fixed and integrated by welding or the like. (That is, this state is the state shown in FIG. 1.) In this way, the two steel pipes 31, 31 are connected to the columns 2, 2.
When suspended between the steel pipes 31, 31, the pillars 2,
It is extremely difficult to completely align and match the side end faces 31c and 31c at the joint portions of the two because they are temporarily supported in a cantilevered manner by the two.
The steel pipe 31 is provided in the casting space 29 in the frame 2 as described later.
It can be moved a little until the concrete of 1 is poured and filled, and after both the two steel pipes 31, 31 are positioned and fixed, the joint steel pipe 33 is laterally displaced. By being able to joint both 31, 31, the positioning and fixing of these steel pipes 31, 31 and their joint work can be performed smoothly.

【0015】こうしておいて、次に図7に示すように、
図7左側の柱2において、その型枠9内にコンクリート
を打設する。すると、型枠9内に打設されたコンクリー
トは、躯体21の上端21a上に打ち継がれる形で新規
な躯体21を構成すると共に、該コンクリートが鋼管3
1内の内蓋35により仕切られた打設空間31に、図2
に示す長さL3分だけ進入する形で梁3側にも充填され
る。すると、打設空間29内に進入充填されたコンクリ
ート中には、柱2の主筋22に結束連結された柱2・梁
3連結用の主筋51及びフープ筋52が、構造鋼管30
を構成している鋼管31と躯体21とを繋ぐ形で該躯体
21を構成するコンクリート中に埋設定着される形にな
ることから、打設空間29内のコンクリートは、当該柱
2・梁3連結用の主筋51及びフープ筋52により柱2
側の躯体21と一体をなす形で硬化する。即ち柱2の躯
体21は、梁取り付け部21において、打設空間29分
だけ突出した状態の形状で、構築完了される。また、打
設空間29内には鋼管31の上下の管壁からスタッド3
2が突出する形になっていることから、当該スタッド3
2は該打設空間29内に打設充填された部分の躯体21
中に埋設定着されることにより該躯体21と構造鋼管3
0の鋼管31を、該鋼管31の管壁との付着を十分確保
した形で繋いで、これにより、梁3を構成している鋼管
31は、柱2を構成している躯体21に十分な接合強度
で以って確実に片持ち状に接合支持される。
Then, as shown in FIG.
In the pillar 2 on the left side of FIG. 7, concrete is placed in the mold 9. Then, the concrete cast in the mold 9 constitutes a new skeleton 21 in a form of being spliced onto the upper end 21a of the skeleton 21, and the concrete is made into the steel pipe 3
In the placement space 31 partitioned by the inner lid 35 in FIG.
The beam 3 side is also filled so as to enter the length L3 shown in FIG. Then, in the concrete that has entered and filled into the casting space 29, the main bar 51 and the hoop bar 52 for connecting the column 2 and the beam 3 that are connected to the main bar 22 of the column 2 by binding are connected to the structural steel pipe 30.
Since the steel pipe 31 and the skeleton 21 forming the structure are embedded and set in the concrete forming the skeleton 21, the concrete in the casting space 29 is connected to the pillar 2 and the beam 3. Main column 51 and hoop muscle 52 for the pillar 2
It cures in a form that is integral with the side body 21. That is, the construction of the skeleton body 21 of the pillar 2 is completed in the beam attachment portion 21 in a shape in which it is projected by the placement space 29. Further, in the casting space 29, the studs 3 are formed from the upper and lower pipe walls of the steel pipe 31.
Since the stud 3 has a protruding shape, the stud 3
The reference numeral 2 designates a skeleton body 21 of a portion filled in the casting space 29 by casting.
The body 21 and the structural steel pipe 3 are embedded and set in the inside.
No. 0 steel pipe 31 is connected to the pipe wall of the steel pipe 31 with sufficient adhesion, so that the steel pipe 31 forming the beam 3 is sufficient for the frame 21 forming the column 2. The joining strength ensures that the joining is supported in a cantilevered manner.

【0016】こうして、図7右側に示す柱2の梁取り付
け部5においても、上述したと同じ動作を繰返すことに
より、柱2、2間に隣接する構造鋼管30を構成してい
る2本の鋼管31、31は、そのそれぞれが図7左右に
隣接する柱2、2に確実に片持ち状に接合支持されるこ
とになる。こうして、上述したように鋼管31、31に
よる構造鋼管30を柱2、2間に懸架する形で仮支持固
定しておいて、該鋼管31、31の各々の打設空間2
9、29に柱2の躯体21の打設構築作業と同時にコン
クリートを打設充填するだけの簡単な作業手順で、柱
2、2間に梁3を掛け渡す作業が、梁用の型枠組み及び
コンクリート打設作業を必要とすることなく極短時間で
確実に出来、こうして柱2と梁3とは、施工効率良く且
つ適格に接合される。なお、梁3の構造鋼管30を構成
している2本の鋼管31のそれぞれは、上述したように
柱2側に確実に片持ち状に接合支持されることに加え
て、構造鋼管30内には、2本の鋼管31のそれぞれの
内部に形成された空間310が、コンクリート充填され
ない形で空隙部分として梁3中に残留するところから、
各鋼管31の自重を極軽く抑えることが出来、これによ
り、柱2、2間において隣接する鋼管31、31を連結
するためのジョイント鋼管33に作用する荷重を極小さ
く抑えることが可能となる。また、鋼管31、31内の
空間310、310は互いに連通した状態で、梁3中に
残されるので、当該空間310、310を設備スペース
として利用して、例えば該空間310をここを制振用の
ダンパ設置スペースとして利用すれば、該梁3上に搭載
支持されるスラブ7を極めて効果的に制振することが可
能となる。さらに、こうして柱2と梁3とが簡単且つ適
格に接合されたところで、これに引き続き、該柱2に接
合された梁3の構造鋼管30上に支持させる形のスラブ
7の打設構築や、梁3における鋼管31のモルタル等に
よる化粧被覆の作業を円滑且つ迅速に行うことが出来る
ので、構造物1を短い工期で且つ鉄筋コンクリート造と
鉄骨造の両方の長所を十分活かした形で構築仕上げする
ことが可能となる。
In this way, also in the beam mounting portion 5 of the column 2 shown on the right side of FIG. 7, two steel pipes constituting the structural steel pipe 30 adjacent to the columns 2 and 2 are formed by repeating the same operation as described above. Each of the 31, 31 is surely cantilevered and supported by the columns 2, 2 adjacent to each other in the left and right direction of FIG. 7. In this way, as described above, the structural steel pipe 30 made of the steel pipes 31, 31 is temporarily supported and fixed in the form of being suspended between the columns 2 and 2, and the casting space 2 of each of the steel pipes 31, 31 is fixed.
The operation of placing the beam 3 between the pillars 2 and 2 is a simple work procedure in which the construction and the construction of the skeleton 21 of the pillar 2 to the pillars 9 and 29 are performed at the same time as the concrete is poured and filled. It is possible to surely perform the work in a very short time without requiring concrete placing work, and thus the pillar 2 and the beam 3 can be joined efficiently and properly. Each of the two steel pipes 31 constituting the structural steel pipe 30 of the beam 3 is surely cantilevered and supported on the side of the column 2 as described above. The space 310 formed inside each of the two steel pipes 31 remains in the beam 3 as a void portion without being filled with concrete,
The self-weight of each steel pipe 31 can be suppressed to an extremely low level, whereby the load acting on the joint steel pipe 33 for connecting the adjacent steel pipes 31 between the columns 2 and 2 can be suppressed to an extremely low level. Further, since the spaces 310, 310 in the steel pipes 31, 31 are left in the beam 3 in a state of communicating with each other, the spaces 310, 310 are used as equipment space, and for example, the space 310 is used for vibration damping. If it is used as a damper installation space, the slab 7 mounted and supported on the beam 3 can be effectively damped. Further, when the pillar 2 and the beam 3 are simply and properly joined in this way, subsequently, the construction and construction of the slab 7 that is supported on the structural steel pipe 30 of the beam 3 joined to the pillar 2, Since the work of decorative coating of the steel pipe 31 on the beam 3 with mortar or the like can be carried out smoothly and quickly, the structure 1 is constructed and finished in a short construction period and while making full use of the advantages of both reinforced concrete construction and steel frame construction. It becomes possible.

【0017】[0017]

【発明の効果】以上説明したように、本発明によれば、
隣接する躯体21等のコンクリート材からなる柱2、2
間に梁3を懸架した形の柱・梁構造において、前記梁3
は、前記隣接する柱2、2を接続する形の構造鋼管30
等の鋼管体を有し、前記鋼管体内部の両端部近傍に内蓋
35等の遮蔽蓋を、空間29、打設空間310等の該鋼
管体の内部の空間を仕切る形で設け、前記鋼管体内部の
前記遮蔽蓋より柱2側の空間に、主軸51、スタッド3
2等の柱2と梁3との連結手段を、該鋼管体と前記コン
クリート材とを繋ぐ形で設けて構成したので、柱2が梁
3を一体に支持することが出来る。従って、柱2のコン
クリート材を打設構築するに先立ち、鋼管体を該柱2に
支持させる形で配設しておけば、該鋼管体内部の空間の
遮蔽蓋部分まで柱2のコンクリート材が進入充填される
形で、前記柱2と梁3との連結手段が該柱2のコンクリ
ート材中に定着されることが出来る。これにより、梁3
は、柱2にコンクリート材を打設構築すると同時に、連
結手段を介して該柱2に連結する形で確実に柱2側に接
合支持されるので、梁3を柱2に簡単且つ適格に接合す
ることが出来、故に柱・梁構造を接合構築する為の施工
効率が極めて秀れている。しかも、梁3を構成している
鋼管体の内部の空間は遮蔽手段により、その連結手段が
配設されていない側の空間が該梁3中に空隙部分として
残されるので、当該空間に制振ダンパ等の設備材を予め
設置しておく形で、ここを有効利用することが出来る。
従って、梁3に鋼管等の鋼材を用いて、該梁3を鉄筋コ
ンクリート等のコンクリート材からなる柱2と効率的に
接合した柱・梁構造を構築して、当該柱とを梁接合する
際の煩雑な作業手間を極僅に抑え乍ら、鉄筋コンクリー
ト柱と鋼材梁の両者の長所を活かした複合構造体を構造
物1に提供することが、短期間の施工工期で簡単に出来
る。また、前記鋼管体は、前記隣接する柱2、2を接続
する形で直列に並ぶ複数の鋼管31等の分割管体を、そ
の側端面31c等の接続部を介して隣接する分割管体の
双方に跨る形で被嵌したジョイント鋼管33等の接続用
管体を介して一体に接続して構成されると、接続用管体
は複数の分割管体を、その接続部を相互に付き合わせた
形で接続することが出来る。従って、分割管体の接続部
を任意な位置に設定しておくことにより、梁3を柱2、
2間に懸架する際に、最も施工し易く且つ構造的に負担
の少ない有利な梁構造を得ることが出来る。また、鋼管
体を分割管体に分割しておくことにより、その搬送及び
保管等の取扱が極めて容易になり、一層施工の効率化が
図られる。
As described above, according to the present invention,
Pillars 2 and 2 made of concrete material such as the adjacent frame 21
In a pillar / beam structure in which a beam 3 is suspended between
Is a structural steel pipe 30 having a shape for connecting the adjacent columns 2 and 2.
And the like, and a shielding lid such as an inner lid 35 is provided near both ends inside the steel pipe so as to partition the space inside the steel pipe such as the space 29 and the casting space 310. Inside the body, in the space on the column 2 side of the shield lid, the main shaft 51, the stud 3
Since the connecting means for connecting the column 2 and the beam 3 such as 2 is provided by connecting the steel pipe body and the concrete material, the column 2 can integrally support the beam 3. Therefore, if the steel pipe is arranged so as to be supported by the pillar 2 before the concrete material of the pillar 2 is cast and constructed, the concrete material of the pillar 2 will be extended to the shielding lid part of the space inside the steel pipe. The connecting means of the pillar 2 and the beam 3 can be fixed in the concrete material of the pillar 2 in the form of intrusion filling. This makes the beam 3
Since the concrete material is cast and constructed on the pillar 2, it is surely joined and supported to the pillar 2 side by being connected to the pillar 2 through the connecting means, so that the beam 3 is easily and properly joined to the pillar 2. Therefore, the construction efficiency for joining and constructing the pillar / beam structure is extremely excellent. Moreover, since the space inside the steel tube that constitutes the beam 3 is left as a void portion in the beam 3 by the shielding means, the space on the side where the connecting means is not arranged is left in the space, so that the vibration is suppressed in the space. This can be effectively used by installing equipment such as dampers in advance.
Therefore, when a steel material such as a steel pipe is used for the beam 3 and the beam 3 is efficiently joined to the pillar 2 made of a concrete material such as reinforced concrete, a column / beam structure is constructed, and when the beam is joined to the pillar 3. It is possible to provide the structure 1 with a composite structure utilizing the advantages of both the reinforced concrete column and the steel beam to the structure 1 easily with a short construction period, while keeping the complicated work time to a minimum. Moreover, the said steel pipe body WHEREIN: The division pipe body of several steel pipes 31 etc. which are located in a line in the form which connects the said adjacent pillars 2 and 2 is connected through the connection part of the side end surface 31c etc. When configured to be integrally connected through a connecting pipe body such as a joint steel pipe 33 which is fitted so as to straddle both sides, the connecting pipe body makes a plurality of divided pipe bodies, but abuts the connecting portions with each other. It can be connected in a closed shape. Therefore, by setting the connecting portion of the split pipe body at an arbitrary position, the beam 3 is connected to the pillar 2,
When suspended between two, it is possible to obtain an advantageous beam structure that is the most easy to construct and has the least structural burden. Further, by dividing the steel pipe body into the divided pipe bodies, handling such as transportation and storage becomes extremely easy, and the efficiency of construction can be further improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明による柱・梁構造の一実施例を示す断側
面図である。
FIG. 1 is a sectional side view showing an embodiment of a pillar / beam structure according to the present invention.

【図2】図1に示す柱・梁構造における柱・梁接合部分
の拡大図である。
FIG. 2 is an enlarged view of a column / beam joint portion in the column / beam structure shown in FIG.

【図3】図1のIII、III矢視断面図である。3 is a sectional view taken along the line III and III in FIG.

【図4】図1のIV、IV矢視断面図である。FIG. 4 is a sectional view taken along the line IV and IV in FIG.

【図5】図1に示す柱・梁構造の施工手順を示す一連の
側面図である。
5 is a series of side views showing a construction procedure of the pillar / beam structure shown in FIG. 1. FIG.

【図6】図1に示す柱・梁構造の施工手順を示す一連の
側面図である。
6 is a series of side views showing a construction procedure of the pillar / beam structure shown in FIG. 1. FIG.

【図7】図1に示す柱・梁構造の施工手順を示す一連の
側面図である。
FIG. 7 is a series of side views showing a construction procedure of the pillar / beam structure shown in FIG.

【符号の説明】[Explanation of symbols]

2……柱 21……コンクリート材(躯体) 3……梁 30……鋼管体(構造鋼管) 35……遮蔽蓋(内蓋) 29……鋼管体内部の空間(打設空間) 310……鋼管体内部の空間(空間) 32……連結手段(スタッド) 51……連結手段(主筋) 31……分割管体(鋼管) 31c……接続部(側端面) 33……ジョイント鋼管 2 ... Pillar 21 ... Concrete material (frame) 3 ... Beam 30 ... Steel tube (structural steel tube) 35 ... Shielding lid (inner lid) 29 ... Space inside steel tube (placing space) 310 ... Space inside the steel pipe (space) 32 ...... Connection means (stud) 51 ...... Connection means (main bar) 31 ...... Split pipe body (steel pipe) 31c ...... Connection part (side end surface) 33 ...... Joint steel pipe

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】隣接するコンクリート材からなる柱間に梁
を懸架した形の柱・梁構造において、 前記梁は、前記隣接する柱を接続する形の鋼材からなる
鋼管体を有し、 前記鋼管体内部の両端部近傍に遮蔽蓋を、該鋼管体の内
部の空間を仕切る形で設け、 前記鋼管体内部の前記遮蔽蓋より柱側の空間に、柱と梁
との連結手段を、該鋼管体と前記コンクリート材とを繋
ぐ形で設けて構成した、柱・梁構造。
1. A pillar / beam structure in which a beam is suspended between pillars made of adjacent concrete materials, wherein the beam has a steel pipe body made of a steel material for connecting the adjacent pillars, Shielding lids are provided in the vicinity of both ends inside the body so as to partition the space inside the steel pipe body, and in the space on the column side of the shielding lid inside the steel pipe body, connecting means between columns and beams, the steel pipe A pillar / beam structure constructed by connecting the body and the concrete material.
【請求項2】前記鋼管体は、前記隣接する柱を接続する
形で直列に並ぶ複数の分割管体を、その接続部を介して
隣接する分割管体の双方に跨る形で被嵌した接続用管体
を介して一体に接続して構成される、請求項1記載の柱
・梁構造。
2. The steel pipe body is a connection in which a plurality of divided pipe bodies arranged in series so as to connect the adjacent pillars are fitted in a manner of straddling both of the adjacent divided pipe bodies through their connecting portions. The pillar / beam structure according to claim 1, wherein the pillar / beam structure is integrally connected through a pipe body.
JP14651192A 1992-05-12 1992-05-12 Pole-beam structure Pending JPH05311735A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14651192A JPH05311735A (en) 1992-05-12 1992-05-12 Pole-beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14651192A JPH05311735A (en) 1992-05-12 1992-05-12 Pole-beam structure

Publications (1)

Publication Number Publication Date
JPH05311735A true JPH05311735A (en) 1993-11-22

Family

ID=15409294

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14651192A Pending JPH05311735A (en) 1992-05-12 1992-05-12 Pole-beam structure

Country Status (1)

Country Link
JP (1) JPH05311735A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018003451A (en) * 2016-07-01 2018-01-11 株式会社アーク Earthquake-proof foundation for assembly house

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018003451A (en) * 2016-07-01 2018-01-11 株式会社アーク Earthquake-proof foundation for assembly house

Similar Documents

Publication Publication Date Title
KR101663132B1 (en) Self-supporting type column structure
JP2522714B2 (en) Construction method of building frame
JPH05311747A (en) Pole-beam structure
JPH0518003A (en) Joining method of steel pipe concrete column and half-precast reinforced concrete column
JPH04261934A (en) Building frame construction method using form member made of pre-cast concrete
JPH05311735A (en) Pole-beam structure
JP3836920B2 (en) Construction method of pier overhang
JPH0434161A (en) Centrifugally molded hollow pc concrete column and column construction method
JPH05311748A (en) Connecting execution method of pole and beam
JPH11229495A (en) Composite-structure building
JP2643641B2 (en) Building method using PC members
JPS6043547A (en) Mold frame and reinforcement iron integral assembling and constructing method
JPH0893137A (en) Precast post serving as form and construction method therefor
JPH01203537A (en) Src precast beam and junction structure of column and beam
JP2635872B2 (en) How to build a composite structure
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP3700129B2 (en) Joint structure of composite structure and construction method thereof
JPH08232366A (en) High damping building and construction method therefor
JP2984626B2 (en) PC pillar construction method and its PC pillar
JP2972956B2 (en) Column and beam joining method and its structure
JPH0673781A (en) Construction of reinforced concrete structure
JPH0448136B2 (en)
JPH03290543A (en) Frame body of structure consisting of precast steel pipe column and precast steel beam or prestressed steel beam, joint structure with pc steel pipe column and pc steel beam or ps steel beam, and pc steel pipe column and ps steel beam