JPH0673781A - Construction of reinforced concrete structure - Google Patents

Construction of reinforced concrete structure

Info

Publication number
JPH0673781A
JPH0673781A JP24865092A JP24865092A JPH0673781A JP H0673781 A JPH0673781 A JP H0673781A JP 24865092 A JP24865092 A JP 24865092A JP 24865092 A JP24865092 A JP 24865092A JP H0673781 A JPH0673781 A JP H0673781A
Authority
JP
Japan
Prior art keywords
formwork
floor slab
work
reinforced concrete
concrete structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP24865092A
Other languages
Japanese (ja)
Other versions
JPH07103622B2 (en
Inventor
Mitsuo Nakamura
光男 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIYOISUTO KK
Original Assignee
JIYOISUTO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIYOISUTO KK filed Critical JIYOISUTO KK
Priority to JP4248650A priority Critical patent/JPH07103622B2/en
Publication of JPH0673781A publication Critical patent/JPH0673781A/en
Publication of JPH07103622B2 publication Critical patent/JPH07103622B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To extremely reduce the weight of floor and the whole building and also decrease the construction cost and period. CONSTITUTION:After piling work 1 and foundation work 2, reinforcing rods of columns are arranged and molding frames are assembled. And molding frames 4 of beams are supported by temporary struts 5. Thereafter, light floor slabs 6 are placed between the frames 4. Then steel rods 7 for beams are arranged and concrete is poured in the joints of the molding frames 4 and the light floor slabs 6 after arrangement of steel rods. After the concrete has cured, the molding frames 4 are removed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鉄筋コンクリート建造
物(以下、単にRC建造物という)の建築工法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a reinforced concrete building (hereinafter referred to simply as an RC building).

【0002】[0002]

【従来の技術】従来のRC建造物の建築工法は、杭打ち
工事、基礎工事、型枠工事、配筋工事、コンクリート打
設工事を順に施工するものであり、多階層の建造物の場
合は、型枠工事、配筋工事、コンクリート打設工事は下
階から順次行う順次積上げ方式で施工されている。
2. Description of the Related Art A conventional RC building construction method is to construct a pile, a foundation, a formwork, a bar, and a concrete in order. In the case of a multi-story building, The formwork, bar arrangement, and concrete placing work are carried out in a sequential stacking method, starting from the lower floor.

【0003】[0003]

【発明が解決しようとする課題】この従来のRC建造物
の建築工法では、建物の柱・外壁ばかりでなく、床・天
井もコンクリートで打設するものであるため、建物全体
の重量がきわめて大きくなり、それだけ、杭・基礎のボ
リューム・本数・径は大きいものを使用し、又柱・梁も
断面積・鉄筋量いずれも大きいものとなっていた。又、
下階からの順次積上げ方式であるので複数階を同時施工
できず、そのため工事コストが高くなり、工期も長くか
かっていた。
In this conventional construction method for RC buildings, not only the pillars and outer walls of the building but also the floor and ceiling are laid with concrete, so the weight of the entire building is extremely large. As a result, piles, foundations with large volume, number, and diameter were used, and columns and beams had large cross-sectional areas and reinforcing bar amounts. or,
Since it is a method of stacking sequentially from the lower floor, it is not possible to construct multiple floors at the same time, which increases construction costs and takes a long construction period.

【0004】本発明が解決しようとする課題は、従来の
RC建造物の建築工法の問題点を解消し、床及び建物全
体の重量をきわめて低いものにでき、しかも工事コスト
及び工期を低減できるという新しい構想のRC構造体の
建築工法を提供することにある。
The problem to be solved by the present invention is that the problems of the conventional construction method for RC buildings can be solved, the weight of the floor and the entire building can be made extremely low, and the construction cost and construction period can be reduced. It is to provide a construction method of a RC structure of a new concept.

【0005】[0005]

【課題を解決するための手段】かかる課題を解決した本
発明の要旨は、 1) 杭打ちと基礎工事の後、柱の配筋・型枠組立を行
い、梁型の型枠を仮設用支柱等の部材で支持させながら
組立て、梁の型枠組立て後に軽量床版を型枠間に架設
し、又梁筋の配筋を行い、配筋後型枠及び軽量床版の接
合部にコンクリートを流し込み、コンクリート硬化後型
枠を撤去することを特徴とする鉄筋コンクリート構造体
の建築工法 2) 軽量床版が、版外周フレームに複数の強度部材を
架設し、その上下面に耐火ボードを張り、しかも版外周
フレームと上下の耐火ボードとによって囲まれる内部空
間に硬質発泡樹脂を充填させて構成された1記載の鉄筋
コンクリート構造体の建築工法 3) 軽量床版の強度部材が断面長方形状の長尺の筒体
内に硬質発泡樹脂を充填した部材である2記載の鉄筋コ
ンクリート構造体の建築工法にある。
[Means for Solving the Problems] The gist of the present invention, which has solved the above problems, is as follows: 1) After piling and foundation work, arranging the columns and assembling the formwork to form a beam-type formwork post for temporary installation. Assembling while supporting it with other members such as, and after assembling the beam formwork, laying the lightweight floor slab between the forms, and also arranging the beam reinforcement, and after the reinforcement, concrete is attached to the joint between the formwork and the lightweight floor slab. Construction method of reinforced concrete structure characterized by pouring and removing the formwork after concrete hardening 2) Lightweight floor slab has multiple strength members erected on the plate outer frame, and fireproof boards are laid on the top and bottom of the frame. Construction method of the reinforced concrete structure according to 1, which is configured by filling a hard foamed resin into an internal space surrounded by the plate outer peripheral frame and the upper and lower fireproof boards 3) The strength member of the lightweight floor slab has a long rectangular shape in cross section. Hard foam resin in the cylinder In Hama the construction methods of the reinforced concrete structure wherein a member.

【0006】[0006]

【作用】本発明では、杭打ちと基礎工事の後に、柱及び
梁の型枠と配筋を行う。梁の型枠は仮設用支柱等の部材
で支持させる。梁の型枠組立後に軽量床版を架設し、型
枠及び軽量床版との接合部にコンクリートを流し込んで
一体化させる。従って、床天井をコンクリートの打設す
る従来の工法のものに比べ、床天井の重量は大巾に軽量
化され、その分柱・配筋・基礎・杭の強度負担がなく、
小型・寸法・本数を少なくできる。又、コンクリート打
設する前に重量床版が架設されるので、この床版を使っ
て上階の型枠支持及びコンクリート打設工事・垂直パネ
ル取付工事等の作業が行え、工事作業性がよくなり、し
かも二〜三階の複数階を並行に同時に施工でき、工期を
大略半分程に短縮できる。
In the present invention, the pillar and beam formwork and bar arrangement are performed after pile driving and foundation work. The beam formwork is supported by members such as temporary columns. After assembling the beam formwork, a lightweight floor slab is installed, and concrete is poured into the joint between the formwork and the lightweight floor slab to be integrated. Therefore, the weight of the floor ceiling is significantly reduced compared to the conventional construction method of placing the floor ceiling with concrete, and there is no burden of strength on the pillars, reinforcements, foundations, and piles.
Small size, size and number can be reduced. Also, since a heavy floor slab is erected before concrete is placed, this floor slab can be used to perform work such as formwork support for the upper floor and concrete placement work / vertical panel installation work, and workability is good. Moreover, multiple floors (2nd to 3rd floor) can be installed at the same time in parallel, and the construction period can be shortened to about half.

【0007】[0007]

【実施例】以下、本発明の実施例を図面に基づいて説明
する。図1は実施例の施工手順を示す説明図、図2は実
施例の型枠組立工事を示す説明図、図3は軽量床版架設
工事を示す説明図、図4は梁筋の配筋工事を示す説明
図、図5はコンクリート打設工事を示す説明図、図6は
型枠取り外し状態を示す説明図、図7は実施例の軽量床
版を示す一部切欠斜視図、図8は図7のA−A線からの
断面図、図9は構築後の建造物の構造を示す縦断面図で
ある。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is an explanatory view showing a construction procedure of the embodiment, FIG. 2 is an explanatory view showing a formwork assembling work of the embodiment, FIG. 3 is an explanatory view showing a lightweight floor slab erection work, and FIG. 4 is a beam reinforcement work. FIG. 5, FIG. 5 is an explanatory view showing concrete pouring work, FIG. 6 is an explanatory view showing a form removing state, FIG. 7 is a partially cutaway perspective view showing a lightweight floor slab of an embodiment, and FIG. 7 is a sectional view taken along the line AA, and FIG. 9 is a longitudinal sectional view showing the structure of the building after construction.

【0008】図中、S1は杭打工事、S2は基礎工事、
3は鉄骨、4は梁型の型枠、5は仮設用支柱、6は軽量
床版、7は梁筋、8は軽量床版6の端面から突出させた
アンカー筋、9は軽量床版6を支持するサポート、10
は軽量床版6の外周枠、11は軽量床版6の上面・下面
に取付けられる耐火ボード、12は軽量床版6の外周枠
10間に架設される断面矩形状の中空筐体、13は軽量
床版6内に充填された硬質発泡樹脂、14は中空筐体1
2内に充填された硬質発泡樹脂、15は建造物、16は
建造物15の外壁、17は建造物15の鉄筋補強コンク
リート梁部分である。
In the figure, S1 is pile driving work, S2 is foundation work,
3 is a steel frame, 4 is a beam form, 5 is a temporary support column, 6 is a lightweight floor slab, 7 is a beam reinforcement, 8 is an anchor reinforcement protruding from the end face of the lightweight floor slab 6, 9 is a lightweight floor slab 6 Supports to support 10
Is a peripheral frame of the lightweight floor slab 6, 11 is a refractory board attached to the upper and lower surfaces of the lightweight floor slab 6, 12 is a hollow housing having a rectangular cross-section that is erected between the peripheral frames 10 of the lightweight floor slab 6, and 13 is Hard foam resin filled in the lightweight floor slab 6, 14 is a hollow housing 1
2 is a hard foam resin filled in, 15 is a building, 16 is an outer wall of the building 15, and 17 is a reinforced concrete beam portion of the building 15.

【0009】又図1中、S1は杭打工事、S2は基礎工
事、S3は型枠工事、S4は軽量床版架設工事、S5は
配筋工事、S6はコンクリート打設工事、S7は型枠取
り外し工事である。
In FIG. 1, S1 is pile driving work, S2 is foundation work, S3 is formwork work, S4 is lightweight floor slab construction work, S5 is reinforcement work, S6 is concrete placement work, and S7 is formwork. Removal work.

【0010】本実施例では、まず従来通り、杭打工事S
1、基礎工事S2を行う。これに使用する杭の本数・径
・ボリュームとも後述するように、従来のものに比べて
小さくて少ないもので済む。
In this embodiment, first, as in the conventional method, the pile driving work S
1. Perform foundation work S2. As will be described later, the number, diameter, and volume of the piles used for this are smaller and smaller than conventional ones.

【0011】次に、柱の配筋・柱の型枠の組立て及び梁
部分となる型枠4の組立てを行う。梁部分となる型枠の
組立てが終わると、型枠4内に梁筋を配筋し、又軽量床
版6の端面から突出させたアンカー筋8を型枠4の空間
内に進入させた状態とする。その後、型枠4及びこれに
続く軽量床版6の端面に囲まれる空間にコンクリートを
流し込む。流し込んでコンクリート硬化後に型枠4及び
仮設用支柱5,サポート9を撤去し、躯体工事が完了す
る。この建造物の躯体完了時の構造を図9に示してい
る。5階500坪の延面積のRC構造物の床版部分はコ
ンクリートで建造すると59トン程の重量となる所、本
実施例の軽量床版6を使うことで82トンと大略1/7
の重量で済む。
Next, the reinforcement of the columns, the assembling of the form of the column, and the assembling of the form 4 as the beam portion are performed. When the assembling of the formwork which becomes the beam part is completed, the beam reinforcement is arranged in the formwork 4, and the anchor reinforcement 8 protruding from the end face of the lightweight floor slab 6 is allowed to enter the space of the formwork 4. And Then, concrete is poured into the space surrounded by the end faces of the formwork 4 and the lighter floor slab 6 that follows it. After pouring and hardening the concrete, the formwork 4, the temporary support columns 5 and the support 9 are removed, and the skeleton work is completed. FIG. 9 shows the structure of the building when the frame is completed. The floor slab portion of the RC structure having an extended area of 500 tsubo on the 5th floor will weigh about 59 tons when constructed with concrete. By using the lightweight floor slab 6 of this embodiment, 82 tons, which is approximately 1/7.
The weight of

【0012】[0012]

【発明の効果】以上の様に、本発明によれば、コンクリ
ート構造体の床部分を軽量床版に使用するものであるか
ら、RC構造体の重量が大巾に軽減し、それに伴って他
の構造躯体の寸法・ボリュームも小さくできてRC構造
物の重量を大巾に軽量化できる。又、型枠に架設する軽
量床版が次の作業の足場として使用でき、施工作業が迅
速にできる。又、コンクリートの硬化する1カ月程の期
間を待たずに作業できるものであるから工期が大巾に短
縮できる。
As described above, according to the present invention, since the floor portion of the concrete structure is used for the lightweight floor slab, the weight of the RC structure is greatly reduced, and other factors are accompanied. The size and volume of the structural body can be reduced, and the weight of the RC structure can be greatly reduced. Also, the lightweight floor slab installed on the formwork can be used as a scaffold for the next work, and the construction work can be speeded up. Further, since the work can be done without waiting for about one month for the concrete to harden, the construction period can be greatly shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例の施工手順を示す説明図であ
る。
FIG. 1 is an explanatory view showing a construction procedure of an embodiment of the present invention.

【図2】実施例の型枠組立工事を示す説明図である。FIG. 2 is an explanatory view showing a formwork assembling work of the embodiment.

【図3】実施例の軽量床版架設工事を示す説明図であ
る。
FIG. 3 is an explanatory diagram showing a construction work for constructing a lightweight floor slab according to an embodiment.

【図4】実施例の配筋工事を示す説明図である。FIG. 4 is an explanatory diagram showing a reinforcement work of the embodiment.

【図5】実施例の梁筋の配筋工事を示す説明図である。[Fig. 5] Fig. 5 is an explanatory view showing a reinforcing bar construction work of the embodiment.

【図6】実施例のコンクリート打設工事を示す説明図で
ある。
FIG. 6 is an explanatory diagram showing concrete placing work according to the embodiment.

【図7】実施例の軽量床版を示す一部切欠斜視図であ
る。
FIG. 7 is a partially cutaway perspective view showing a lightweight floor slab of an embodiment.

【図8】図7のA−A線からの断面図である。8 is a sectional view taken along the line AA of FIG.

【図9】構築後の建造物の構造を示す縦断面図である。FIG. 9 is a vertical sectional view showing the structure of a building after construction.

【符号の説明】[Explanation of symbols]

S1 杭打工事 S2 基礎工事 3 鉄骨 4 型枠 5 仮設用支柱 6 軽量床版 7 梁筋 8 アンカー筋 9 サポート 10 外周枠 11 耐火ボード 12 中空筐体 13 硬質発泡樹脂 14 硬質発泡樹脂 15 建造物 16 外壁 17 梁部分 S1 Piling work S2 Foundation work 3 Steel frame 4 Formwork 5 Temporary support column 6 Lightweight floor slab 7 Beam reinforcement 8 Anchor reinforcement 9 Support 10 Outer frame 11 Fireproof board 12 Hollow housing 13 Hard foam resin 14 Hard foam resin 15 Building 16 Outer wall 17 Beam part

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 杭打ちと基礎工事の後、柱の配筋・型枠
組立を行い、梁型の型枠を仮設用支柱等の部材で支持さ
せながら組立て、梁の型枠組立て後に軽量床版を型枠間
に架設し、又梁筋の配筋を行い、配筋後型枠及び軽量床
版の接合部にコンクリートを流し込み、コンクリート硬
化後型枠を撤去することを特徴とする鉄筋コンクリート
構造体の建築工法。
1. After pile driving and foundation work, pillar reinforcement and formwork assembly are performed, the beam formwork is assembled while being supported by a member such as a temporary support column, and the beam floor is assembled after the beam formwork assembly. Reinforced concrete structure characterized in that the slab is installed between the formwork, beam reinforcement is performed, concrete is poured into the joint between the formwork and lightweight floor slab after reinforcement, and the formwork is removed after the concrete is hardened. Body construction method.
【請求項2】 軽量床版が、版外周フレームに複数の強
度部材を架設し、その上下面に耐火ボードを張り、しか
も版外周フレームと上下の耐火ボードとによって囲まれ
る内部空間に硬質発泡樹脂を充填させて構成された請求
項1記載の鉄筋コンクリート構造体の建築工法。
2. A lightweight floor slab, wherein a plurality of strength members are erected on a plate outer peripheral frame, fireproof boards are attached to upper and lower surfaces thereof, and hard foam resin is provided in an internal space surrounded by the plate outer peripheral frame and the upper and lower fire resistant boards. The method for constructing a reinforced concrete structure according to claim 1, wherein the method is a method for constructing a reinforced concrete structure.
【請求項3】 軽量床版の強度部材が断面長方形状の長
尺の筒体内に硬質発泡樹脂を充填した部材である請求項
2記載の鉄筋コンクリート構造体の建築工法。
3. The method for constructing a reinforced concrete structure according to claim 2, wherein the strength member of the lightweight floor slab is a member in which a long foam having a rectangular cross section is filled with hard foam resin.
JP4248650A 1992-08-24 1992-08-24 Construction method of reinforced concrete structure Expired - Fee Related JPH07103622B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4248650A JPH07103622B2 (en) 1992-08-24 1992-08-24 Construction method of reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4248650A JPH07103622B2 (en) 1992-08-24 1992-08-24 Construction method of reinforced concrete structure

Publications (2)

Publication Number Publication Date
JPH0673781A true JPH0673781A (en) 1994-03-15
JPH07103622B2 JPH07103622B2 (en) 1995-11-08

Family

ID=17181285

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4248650A Expired - Fee Related JPH07103622B2 (en) 1992-08-24 1992-08-24 Construction method of reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPH07103622B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006057615A1 (en) * 2004-11-25 2006-06-01 Roger Ericsson A building element and a building structure comprising the building element

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS615463U (en) * 1984-06-15 1986-01-13 株式会社 富士電機総合研究所 Ultrasonic flaw detector
JPH03161643A (en) * 1989-11-20 1991-07-11 Tokyu Constr Co Ltd Prestress partial half pca plate and its slab structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS615463U (en) * 1984-06-15 1986-01-13 株式会社 富士電機総合研究所 Ultrasonic flaw detector
JPH03161643A (en) * 1989-11-20 1991-07-11 Tokyu Constr Co Ltd Prestress partial half pca plate and its slab structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006057615A1 (en) * 2004-11-25 2006-06-01 Roger Ericsson A building element and a building structure comprising the building element

Also Published As

Publication number Publication date
JPH07103622B2 (en) 1995-11-08

Similar Documents

Publication Publication Date Title
JP2915897B1 (en) Building construction method
JP3069753B2 (en) Construction method of framed reinforced concrete structure
JPH0673781A (en) Construction of reinforced concrete structure
JP2769937B2 (en) Steel tube concrete column in underground reverse driving method
JP3116767B2 (en) Existing building seismic isolation structuring method
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH084196A (en) Panel for building
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH0673780A (en) Construction of steel framed reinforced concrete structure
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JPH06136821A (en) Construction method for steel frame reinforced concrete structure
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JPS61196035A (en) Construction of concrete building
JPH0893137A (en) Precast post serving as form and construction method therefor
JP2578671B2 (en) Column and beam construction method
JP2023022563A (en) Concrete wall construction method
JPS62182329A (en) Construction of concrete structure
JP3312945B2 (en) Construction method of concrete structure
JP2001032376A (en) Floor slab frame and construction method for skeleton
JPH0621469B2 (en) Multi-story building frame construction method
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPS63165634A (en) Construction of wall type building
JPH1122106A (en) Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member
JPH04149365A (en) Construction method of beam

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees