JPH05248008A - All weather type building method - Google Patents
All weather type building methodInfo
- Publication number
- JPH05248008A JPH05248008A JP4845292A JP4845292A JPH05248008A JP H05248008 A JPH05248008 A JP H05248008A JP 4845292 A JP4845292 A JP 4845292A JP 4845292 A JP4845292 A JP 4845292A JP H05248008 A JPH05248008 A JP H05248008A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- storey
- driving
- construction
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、建物の最上階をはじ
めに構築し、これを順次上昇させながら建築を進めるこ
とにより全天候型の作業環境を保持して建物各階を下か
ら順に上方へと構築する建築工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention constructs the top floor of a building first, and then gradually raises it to proceed with the construction to maintain an all-weather working environment and construct each floor of the building from bottom to top. Concerning the construction method to do.
【0002】[0002]
【従来の技術】従来一般の建物の建築工法は、地上1階
から、同2階、3階と順次1フロアーずつ積み重ねる形
に躯体工事、仕上げ及び設備工事を進め、最上階は最後
に構築している。2. Description of the Related Art Conventionally, the construction method of a general building is such that the first floor, the second floor, and the third floor are sequentially stacked one by one, and the construction work, finishing and equipment work are carried out, and the top floor is constructed last. ing.
【0003】[0003]
【本発明が解決しようとする課題】従来の建築工法のよ
うに、建物の下階から上階へと順に構築を進めるやり方
では、特に躯体工事は常に天候条件による影響をもろに
受け、悪天候によって工事を中止せざるを得ない日々も
生ずる。同様に、仕上げ、設備工事も、外壁及びサッシ
ュガラスの施工がなされるまでは、天候条件による影響
を受けるほか、随所に高所作業も発生するから、工期が
長引き、作業場環境の悪さ、危険さの故に人員の確保も
難しい、と言う問題点があり、解決するべき課題になっ
ている。[Problems to be Solved by the Invention] In the method of proceeding the construction from the lower floor to the upper floor of the building in the same manner as in the conventional construction method, especially the skeleton construction is always affected by the weather condition and There will be days when the construction will have to be stopped. Similarly, finishing and facility work will be affected by weather conditions until the outer wall and sash glass are installed, and work at high places will occur everywhere, so the construction period will be prolonged, and the work environment will be poor and dangerous. Therefore, there is a problem that it is difficult to secure personnel, which is a problem to be solved.
【0004】[0004]
【課題を解決するための手段】上記従来技術の課題を解
決するための手段として、この発明に係る全天候型建築
工法は、図面に実施例を示したとおり、基準階1の構築
を完成した後、その上に本設柱2を建て、この本設柱2
を伝い登る駆動階3を構築し、その下面に天井走行型の
サークルクレーン4を設置する段階と、前記駆動階3を
前記基準階1から少なくとも1階分の階高よりも上方の
位置まで上昇させ、その位置に固定した上で前記サーク
ルクレーン4を使用して前記基準階1の上で基準階1か
ら数えて2階の床構造体51 を構築する。この床構造体
51 を基準階1からおよそ作業員の背丈相当の高さだけ
ハーフアップさせ、その位置で前記2階の床構造体51
を完成させ、前記基準階1の耐火被覆やダクト布設など
の仕上げ、設備工事を行い、さらに前記2階の床上で3
階の床構造体52を並行して構築する段階と、本設柱2
の継ぎ足しと駆動階3の上昇、及び前記2階の床構造体
51 を同2階の正規位置まで上昇させ、本設柱2へ取付
け固定する段階と、以下同様に、各階の床構造体52 …
を順次に次下階の床上で構築し、そのハーフアップと正
規位置までの上昇及び固定、並びに本設柱2の継ぎ足し
と駆動階3の上昇を繰り返し、最終的に前記駆動階3は
建物の最上階とすること、をそれぞれ特徴とする。As a means for solving the above-mentioned problems of the prior art, the all-weather construction method according to the present invention is, after the construction of the standard floor 1 is completed, as shown in the embodiments in the drawings. , The main pillar 2 is built on it, and the main pillar 2
Building a drive floor 3 that climbs up, and installing a ceiling traveling type circle crane 4 on the lower surface thereof, and raising the drive floor 3 from the reference floor 1 to a position above the floor height of at least one floor Then, the floor structure 5 1 on the second floor counting from the standard floor 1 on the standard floor 1 is constructed by using the circle crane 4 after fixing it at that position. This floor structure 5 1 is half-up from the standard floor 1 by a height approximately equivalent to the height of the worker, and at that position, the floor structure 5 1 on the second floor is located.
Completed, and finished the fire-resistant coating and duct installation on the standard floor 1 and installed equipment, and further 3 on the floor of the 2nd floor.
Building the floor structure 5 2 on the floor in parallel and the main pillar 2
And the rise of the driving floor 3, and the step of raising the floor structure 5 1 of the second floor to the normal position of the second floor and mounting and fixing it to the main pillar 2, and the like, the floor structure of each floor. 5 2 ...
Are sequentially built on the floor of the next lower floor, and the half-up, raising and fixing to the regular position, addition of the permanent pillar 2 and raising of the driving floor 3 are repeated, and finally the driving floor 3 is Each is characterized by being the top floor.
【0005】上記本発明の建築工法は、本設柱2を伝い
登り駆動階3を上昇させるジャッキ装置6が、基準階1
又は各階の床上で構築した各階の床構造体51 、52 の
ハーフアップ及び正規位置への上昇にも併用されること
も特徴とする。In the construction method of the present invention described above, the jack device 6 for climbing up the driving floor 3 along the main installation pillar 2 is the reference floor 1
Alternatively, it is characterized in that it is also used for half-up of the floor structures 5 1 , 5 2 on each floor constructed on the floor of each floor and ascent to the normal position.
【0006】[0006]
【作用】駆動階3は常に先行して上昇し、建築作業場の
屋根代用となるため、全天候型の作業環境が実現する。
ハーフアップ工法を採用しているので、各階の床構造工
事と耐火被覆、あるいはダクト工事などの先行仕上げ、
設備工事が、無足場で、高所作業なしで作業可能であ
る。ハーフアップ後は当階及び次上階の床構造体51 と
52 を重ね合わせ状態で合一に上昇させる(例えば図1
E参照)ので、時間の短縮が達成される。The driving floor 3 always rises in advance and serves as a roof substitute for a construction workshop, so that an all-weather working environment is realized.
Since the half-up construction method is adopted, the floor structure work and fireproof coating on each floor, or the preceding finish such as duct work,
It is possible to perform equipment work without scaffolding and without working at height. After the half-up, the floor structures 5 1 and 5 2 on the present floor and the next upper floor are integrally lifted in a state of being overlapped with each other (see, for example, FIG. 1).
(See E)), so a reduction in time is achieved.
【0007】ジャッキ装置6の併用により、ジャッキ総
数の低減が可能である。By using the jack device 6 together, the total number of jacks can be reduced.
【0008】[0008]
【実施例】次に、図示した本発明の実施例を説明する。
図1A〜Gに示した第1実施例において、まず図1Aは
基準階1の構築を完成した後に、その上に本設柱2を建
て、この本設柱2を伝い登る駆動階3を基準階1の上で
構築し、その下面には天井走行型のサークルクレーン4
を設置し、しかる後に駆動階3を基準階1からある程度
上昇させた段階を示している。本発明で云う基準階1と
は、通常は地上1階を意味するが、場合によっては地下
の最下階又は地上に予め構築されたスーパーメガトラス
などの場合もある。従って、以下に説明する地上部分の
建築と並行して、基準階又はその下の云わば地下構造な
どの建築も認められるのが一般的であることを了解され
たい。駆動階3は、爾後は常に建築作業場の屋根代用と
されるので、それなりの雨養生が行なわれている。場合
によっては駆動階3において、建物外周部位に外部養生
膜を吊下げることも行なわれる。駆動階3はまた、以後
の建物各階の建築に必要な工事事務所と組立て工場を兼
ねたスカイファクトリーとしても構成される。本発明で
いう天井走行型のサークルクレーン4とは、例えば特願
平2−152467号、及び特願平2−152468号
明細書及び図面に記載した、ブームが水平旋回と水平伸
縮又は移動をし、同ブームに取付けたリフトによって躯
体部分や設備、仕上げユニットの運搬及び組立てに使用
可能なクレーンである。このサークルクレーン4の設置
は、基準階1の上で駆動階3の構築を完成した後に、作
業員の背丈相当の高さだけハーフアップさせて行なわれ
る。その後、駆動階3は、基準階1から1階上の床構造
体51 の構築を前提として、少なくとも1階分の階高よ
りも少し上方の位置(例えば基準階1の床上4〜5m程
度)に上昇させ、その位置において一旦本設柱2へ固定
してあずけられる。EXAMPLE An example of the present invention shown in the drawings will be described below.
In the first embodiment shown in FIGS. 1A to 1G, first, in FIG. 1A, after the construction of the reference floor 1 is completed, the main installation pillar 2 is built on the reference floor 1, and the drive floor 3 that climbs along the main installation pillar 2 is used as a reference. It is built on the 1st floor and the lower surface of it is an overhead traveling type circle crane 4.
Is installed, and thereafter the driving floor 3 is raised to some extent from the reference floor 1. The standard floor 1 referred to in the present invention usually means the first floor above the ground, but in some cases, it may be the lowest floor underground or a super mega truss pre-built on the ground. Therefore, it should be understood that, in parallel with the construction of the above-mentioned ground portion, the construction of the standard floor or the so-called underground structure below it is generally accepted. Since the driving floor 3 is always used as a roof substitute for a construction workshop after that, it is subjected to some rain curing. In some cases, on the driving floor 3, an outer curing film may be hung on the outer periphery of the building. The driving floor 3 is also configured as a sky factory that doubles as a construction office and an assembly factory necessary for the subsequent construction of each floor of the building. The overhead traveling type circle crane 4 referred to in the present invention refers to, for example, Japanese Patent Application No. 2-152467 and Japanese Patent Application No. 2-152468 specification and drawings, in which the boom horizontally swings and horizontally expands or contracts or moves. A crane that can be used for transporting and assembling frame parts, equipment, and finishing units by means of a lift attached to the boom. The circle crane 4 is installed by half-up by a height corresponding to the height of the worker after the construction of the drive floor 3 is completed on the reference floor 1. After that, the driving floor 3 is located at a position slightly above the floor height of at least one floor (for example, about 4 to 5 m above the floor of the reference floor 1) on the assumption that the floor structure 5 1 above the reference floor 1 is constructed. ), And temporarily fixed to the main pillar 2 at that position and placed.
【0009】図1Bは駆動階3のサークルクレーン4を
使用して、基準階1の床上で、基準階1から数えて2階
の床構造体51 を構築している段階を示している。床が
鉄骨造の場合の柱、梁、床の構造例を図2Aに示した。
角鋼管による本設柱2の四方にH形鋼による鉄骨梁10
を架け、その上にデッキプレート11を敷きスラブコン
クリートを打設することによって構築される。床のPC
化を図る場合には、鉄骨梁10の上にPC床版が敷き込
まれる。FIG. 1B shows a stage in which a circle crane 4 on the drive floor 3 is used to build a floor structure 5 1 on the second floor, counting from the standard floor 1, on the floor on the standard floor 1. FIG. 2A shows a structural example of columns, beams, and floors when the floor is a steel frame structure.
Steel beams 10 made of H-shaped steel on all sides of the main pillar 2 made of square steel pipe
Is constructed, and the deck plate 11 is laid on it, and the slab concrete is cast. Floor pc
In order to realize the above, a PC floor slab is laid on the steel beam 10.
【0010】図1Cは前記のようにして組立てた2階の
床構造体51 を、駆動階3から吊下げたケーブル(又は
吊りロッドなど)7で吊り、駆動階3の上昇と共に作業
員の背丈相当の高さまでハーフアップさせた段階を示し
ている。床構造体51 が上述した鉄骨造である場合に
は、この段階でデッキプレート11の上にスラブコンク
リートを打設して床が完成される。In FIG. 1C, the floor structure 5 1 on the second floor assembled as described above is hung by a cable (or a suspension rod or the like) 7 hung from the drive floor 3, and as the drive floor 3 rises The figure shows the half height up to the height. When the floor structure 5 1 has the above-mentioned steel frame structure, the floor is completed by placing slab concrete on the deck plate 11 at this stage.
【0011】図1Dは図1Cと同じハーフアップの段階
において、基準階1については耐火被覆、ダクト工事な
どを行ない、2階の床構造体51 の上ではサークルクレ
ーン4を使用して3階の床構造体52 の構築を行なって
いる状況を示している。この段階で本設柱2の継ぎ足し
も行なわれる。本設柱2の継ぎ足しは、図示を省略した
が、駆動階3の上にクレーンを設置し、又は本設柱2の
上端に同本設柱を伝い登るセルフクライミングのタワー
クレーンを設置して行なう。この段階での鉄骨造の柱、
梁、床の構造例を示したのが図2Bである。なお、本設
柱2は、上部へ継ぎ足すので、2層又は3層を1節とし
た長い柱単体の使用が出来、継手数の低減と鉄骨工事費
の節約が図られる。FIG. 1D shows that at the same half-up stage as in FIG. 1C, fireproof coating and duct work are performed on the standard floor 1, and on the floor structure 5 1 on the second floor, the circle crane 4 is used on the third floor. 2 shows a situation in which the floor structure 5 2 is being constructed. At this stage, the main pillar 2 is also replenished. Although not shown in the drawings, the extension of the main installation pillar 2 is performed by installing a crane on the drive floor 3 or by installing a self-climbing tower crane that climbs up the main installation pillar 2 at the upper end of the main installation pillar 2. .. Steel frame pillars at this stage,
FIG. 2B shows an example of the structure of beams and floors. In addition, since the main installation column 2 is added to the upper part, it is possible to use a long column alone having two or three layers as one node, which can reduce the number of joints and save the steel frame construction cost.
【0012】図1Eは駆動階3の上昇により、既に構築
を完成した2階の床構造体51 をその上に構築した3階
の床構造体52 と共に2階の正規位置まで上昇させ、同
2階の床構造体51 は本設柱2へ取付け固定した段階を
示している。従って、二つの床構造体51 ,52 の上昇
に要する時間の短縮ができる。このときの上昇システム
を表したのが図2C,Dである。即ち、本設柱2を中心
に四方に配置された鉄骨梁10には本設柱2を中心に対
角方向に略正方形の上昇枠8を組み、該上昇枠8におけ
る各辺の略中点位置にケーブル7(ジャッキアップの場
合にはジャッキ)を結合した構造で上昇が行なわれる。FIG. 1E shows that, by raising the driving floor 3, the second-floor floor structure 5 1 which has already been constructed is raised to the normal position on the second floor together with the third-floor floor structure 5 2 constructed on it. The floor structure 5 1 on the second floor shows the stage where it is attached and fixed to the main installation column 2. Therefore, the time required to raise the two floor structures 5 1 and 5 2 can be shortened. The ascending system at this time is shown in FIGS. 2C and 2D. That is, ascending frames 8 each having a substantially square shape are installed diagonally around the main installation columns 2 on the steel beams 10 arranged in four directions around the main installation columns 2. The ascending operation is performed by a structure in which a cable 7 (a jack in case of jacking up) is connected to the position.
【0013】図1Fは2階の床構造体51 を残し、既に
構築されている3階の床構造体52をハーフアップさせ
た段階を示している。図1Gは前記ハーフアップの段階
のまま、3階の床構造体52 が鉄骨造であるときにはそ
のスラブコンクリートの打設を行ない、2階の床構造体
51 については耐火被覆、ダクト工事などを行ない、2
階の外壁9や天井8の取付けなどを並行して行なってい
る状況を示している。また、3階の床構造体52 の上で
は、必要なら4階の床構造体の構築を行なうなど、以下
は前記図1D〜Gの工程を繰り返して建物の建築が進め
られる。そして、最終的に駆動階3は建物天端に到達
し、そのまま建物の最上階として利用される。床構造体
がPC化されている場合もほぼ同様な工程で建築が進め
られる。FIG. 1F shows a stage in which the floor structure 5 1 on the second floor is left and the floor structure 5 2 on the third floor, which has already been constructed, is half-up. Fig. 1G shows that the slab concrete is placed when the floor structure 5 2 on the third floor is made of steel while the half-up stage is being used, and the floor structure 5 1 on the second floor is fireproof coated, ducted, etc. 2
This shows a situation in which the outer wall 9 and the ceiling 8 of the floor are attached in parallel. Also, on the third floor of the floor structure 5 2, including performing a construction of the fourth order of the floor structure if necessary, following the construction of the building it is advanced by repeating the process of FIG 1D~G. Finally, the driving floor 3 reaches the top of the building and is used as it is as the top floor of the building. Even if the floor structure is made of PC, the construction proceeds in almost the same process.
【0014】[0014]
【第2の実施例】図3A〜Jに示した第2の実施例は、
先行する駆動階3を上昇させる(押し上げる)ジャッキ
装置6を、各階の床構造体51 ,52 の上昇(引き上
げ)にも併用することを特徴としている。即ち、基準階
1の上で構築した駆動階3を本設柱2に沿って上昇(ハ
ーフアップ)させ、駆動階3の下面に天井走行型のサー
クルクレーン4を設置する。次に前記の天井走行型サー
クルクレーン4を使用して基準階1の上で2階の床構造
体51 の構築を行なう(図3B)。その構築が完成する
か完成の以前に並行して、駆動階3の下側に本設柱2を
伝い登るジャッキ装置6を設置する。そして、該ジャッ
キ装置6によって駆動階3を少なくとも1階分の階高よ
りも少し上方の位置まで上昇(押し上げ)させる(図3
C)。ちなみに図3Aに示した駆動階3のハーフアップ
は、例えば本設柱2の上部にリフトアップジャッキを設
置するなど暫定的な上昇手段を採用して行なう。[Second Embodiment] The second embodiment shown in FIGS.
It is characterized in that the jack device 6 for raising (pushing up) the preceding drive floor 3 is also used for raising (pulling up) the floor structures 5 1 , 5 2 on each floor. That is, the drive floor 3 constructed on the reference floor 1 is raised (half-up) along the main installation pillar 2, and the overhead traveling type circle crane 4 is installed on the lower surface of the drive floor 3. Next, the above-mentioned overhead traveling type circle crane 4 is used to construct the floor structure 5 1 on the second floor above the standard floor 1 (FIG. 3B). When the construction is completed or before the construction is completed, a jack device 6 that climbs along the main installation pillar 2 is installed below the drive floor 3. Then, the driving device 3 is raised (pushed up) to a position slightly above the floor height of at least one floor by the jack device 6 (FIG. 3).
C). By the way, the half-up of the drive floor 3 shown in FIG. 3A is performed by adopting a temporary raising means such as installing a lift-up jack on the upper portion of the main pillar 2.
【0015】上述のようにして2階の床構造体51 を基
準階1の上で構築を完成すると、駆動階3の支持を本設
柱2へ盛り替えた上で、前記ジャッキ装置6を下降さ
せ、該ジャッキ装置6により2階の床構造体51 を引き
上げてハーフアップさせる(図3D)。このハーフアッ
プの状態で、必要ならば2階のスラブコンクリート打設
を行ない(図3F)、あるいは基準階1の耐火被覆、ダ
クト工事を行ない、2階の床構造体51 の下側に天井工
事及び天井内の先行仕上げ工事などが無足場で行なわれ
る。さらに同2階の床構造体51 の床上では、駆動階3
のサークルクレーン4を使用して3階の床構造体52 の
構築が各々並行して行なわれる(図3F)。また、本設
柱2の継ぎ足しも行なわれる。When the construction of the floor structure 5 1 on the second floor is completed on the reference floor 1 as described above, the support of the drive floor 3 is re-placed on the main pillar 2, and then the jack device 6 is installed. It is lowered, and the floor device 5 1 on the second floor is pulled up by the jack device 6 to be half-up (FIG. 3D). In this half-up condition, if necessary, slab concrete is laid on the second floor (Fig. 3F), or fireproof coating on the standard floor 1 and duct work are performed, and the ceiling is placed below the floor structure 5 1 on the second floor. Construction and pre-finishing work in the ceiling will be carried out without any scaffolding. Furthermore, on the floor of the floor structure 5 1 on the second floor, the driving floor 3
The floor structure 5 2 on the third floor is constructed in parallel using the circle crane 4 of FIG. 3 (FIG. 3F). In addition, the main pillar 2 is also replenished.
【0016】この後、2階及び3階の床構造体51 、5
2 を本設柱2へあずけておき、ジャッキ装置6を使用し
て駆動階3の上昇(押し上げ)が行なわれる(図3
G)。次には駆動階3を本設柱2へあずけてから、同じ
ジャッキ装置6を使用して2階及び3階の床構造体51
と52 が重なり合った状態のまま合一に2階の正規位置
まで引き上げて上昇される(図3H)。2階の床構造体
51 を正規位置において本設柱2へ取付け固定したあ
と、3階の床構造体52 のみがジャッキ装置6でハーフ
アップされる(図3I)。以後3階の床構造体52 にス
ラブコンクリートの打設(図3J)を行なうなど、図3
F〜Iの工程を繰り返して建物の建築が進められ、最終
的に駆動階3は建物の最上階に使用される。After this, the floor structures 5 1 , 5 on the second and third floors
2 is placed on the main pillar 2, and the jack 3 is used to raise (push up) the driving floor 3 (Fig. 3).
G). Next, after the driving floor 3 is placed on the main pillar 2, the same jack device 6 is used, and the floor structures 5 1 on the 2nd and 3rd floors are used.
And 5 2 are overlapped with each other and are raised up to the normal position on the second floor (Fig. 3H). After the floor structure 5 1 on the second floor is attached and fixed to the main pillar 2 in the regular position, only the floor structure 5 2 on the third floor is half-upped by the jack device 6 (FIG. 3I). Thereafter the third floor of the floor structure 5 2 etc. perform pouring of concrete slab (Fig. 3J), 3
The construction of the building is advanced by repeating the steps F to I, and finally the driving floor 3 is used as the top floor of the building.
【0017】[0017]
【第3の実施例】図4A〜Fに示した第3実施例は、床
構造体を鉄骨梁とPC床版で構築する場合のものであ
る。基準階1の上で駆動階3を構築し、これをハーフア
ップさせた(図4A,B)後にサークルクレーン4を設
置し、本設柱2の継ぎ足しを行ない(図4B)、駆動階
3の下側に本設柱2を伝い登るジャッキ装置6を設置
し、該ジャッキ装置6を使用して駆動階3を基準階1の
床から少なくとも1階分の階高よりも少し上方の位置ま
で押し上げて上昇させる(図4C)。この段階で、駆動
階3の下面のサークルクレーン4を使用して2階の床構
造体51 を2階の正規位置に構築をする(図4D)。並
行して本設柱2の継ぎ足しを行ない(図4E)、その後
ジャッキ装置6による駆動階3の上昇を2階の階高より
も少し上方位置まで行なう。以下図4C〜Fの各工程を
くり返して建物の建築を進め、最終的に駆動階3は建物
の最上階に使用する。[Third Embodiment] A third embodiment shown in FIGS. 4A to 4F is a case where a floor structure is constructed with steel beams and a PC floor slab. After constructing the drive floor 3 on the standard floor 1, half-up it (Figs. 4A and 4B), install the circle crane 4, and add the permanent pillar 2 (Fig. 4B). A jack device 6 that climbs along the main pillar 2 is installed on the lower side, and the driving device 3 is pushed up from the floor of the reference floor 1 to a position slightly above the floor height of at least one floor by using the jack device 6. To raise (Fig. 4C). At this stage, the floor structure 5 1 on the second floor is constructed in the regular position on the second floor using the circle crane 4 on the lower surface of the drive floor 3 (FIG. 4D). In parallel with this, the main installation columns 2 are replenished (FIG. 4E), and thereafter the driving floor 3 is raised by the jack device 6 to a position slightly above the floor height of the second floor. The steps of FIGS. 4C to 4F are repeated below to proceed with building construction, and finally the driving floor 3 is used as the top floor of the building.
【0018】[0018]
【本発明が奏する効果】本発明に係る全天候型建築工法
によれば、駆動階3が常に建築作業場の屋根代用となっ
て全天候型の作業環境が実現するので、天候条件(風
雨)に左右されない施工を進められ、作業能率の向上と
工期の短縮が図られ、安全性の向上も図れる。According to the all-weather construction method of the present invention, since the drive floor 3 is always used as a roof substitute for a construction workshop to realize an all-weather working environment, it is not affected by weather conditions (wind and rain). Construction can be advanced, work efficiency can be improved, construction period can be shortened, and safety can be improved.
【0019】また、ハーフアップ工法を採用しているた
め、下階の耐火被覆工事、ダクト工事、天井工事などを
無足場で行なえ、コストダウンと安全作業の確保及び工
期の短縮を達成できる。Further, since the half-up construction method is adopted, it is possible to perform fireproof coating work, duct work, ceiling work and the like on the lower floor without a scaffold, and it is possible to achieve cost reduction, secure safety work, and shorten the construction period.
【図1】A〜Gは本発明工法の第1実施例を工程順に示
した立面図である。1A to 1G are elevation views showing a first embodiment of the method of the present invention in the order of steps.
【図2】A,Bは床構造体の斜視図、C,Dは床構造体
の上昇のための手段を示した斜視図と平面図である。2A and 2B are a perspective view of a floor structure, and C and D are a perspective view and a plan view showing a means for raising the floor structure.
【図3】A〜Jは本発明工法の第2実施例を工程順に示
した立面図である。3A to 3J are elevation views showing a second embodiment of the method of the present invention in the order of steps.
【図4】A〜Fは本発明工法の第3実施例を工程順に示
した立面図である。4A to 4F are elevation views showing a third embodiment of the method of the present invention in the order of steps.
1 基準階 2 本設柱 3 駆動階 4 サークルクレーン 51 2階の床構造体 52 3階の床構造体 6 ジャッキ装置1 Standard floor 2 Main installation column 3 Drive floor 4 Circle crane 5 1 2nd floor floor structure 5 2 3rd floor floor structure 6 Jacking device
─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───
【手続補正書】[Procedure amendment]
【提出日】平成4年12月21日[Submission date] December 21, 1992
【手続補正1】[Procedure Amendment 1]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0008[Correction target item name] 0008
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0008】[0008]
【実施例】次に、図示した本発明の実施例を説明する。
図1A〜D及び図2A〜Cに示した第1実施例におい
て、まず図1Aは基準階1の構築を完成した後に、その
上に本設柱2を建て、この本設柱2を伝い登る駆動階3
を基準階1の上で構築し、その下面には天井走行型のサ
ークルクレーン4を設置し、しかる後に駆動階3を基準
階1からある程度上昇させた段階を示している。本発明
で云う基準階1とは、通常は地上1階を意味するが、場
合によっては地下の最下階又は地上に予め構築されたス
ーパーメガトラスなどの場合もある。従って、以下に説
明する地上部分の建築と並行して、基準階又はその下の
云わば地下構造などの建築も認められるのが一般的であ
ることを了解されたい。駆動階3は、爾後は常に建築作
業場の屋根代用とされるので、それなりの雨養生が行な
われている。場合によっては駆動階3において、建物外
周部位に外部養生膜を吊下げることも行なわれる。駆動
階3はまた、以後の建物各階の建築に必要な工事事務所
と組立て工場を兼ねたスカイファクトリーとしても構成
される。本発明でいう天井走行型のサークルクレーン4
とは、例えば特願平2−152467号、及び特願平2
−152468号明細書及び図面に記載した、ブームが
水平旋回と水平伸縮又は移動をし、同ブームに取付けた
リフトによって躯体部分や設備、仕上げユニットの運搬
及び組立てに使用可能なクレーンである。このサークル
クレーン4の設置は、基準階1の上で駆動階3の構築を
完成した後に、作業員の背丈相当の高さだけハーフアッ
プさせて行なわれる。その後、駆動階3は、基準階1か
ら1階上の床構造体51 の構築を前提として、少なくと
も1階分の階高よりも少し上方の位置(例えば基準階1
の床上4〜5m程度)に上昇させ、その位置において一
旦本設柱2へ固定してあずけられる。EXAMPLE An example of the present invention shown in the drawings will be described below.
In the first embodiment shown in FIGS. 1A to 1D and 2A to 2C , first, in FIG. 1A, after the construction of the standard floor 1 is completed, a permanent pillar 2 is built on the basic floor 1, and the main pillar 2 is climbed. Driving floor 3
Is constructed on the standard floor 1, a ceiling traveling type circle crane 4 is installed on the lower surface of the standard floor 1, and then the drive floor 3 is elevated to some extent from the standard floor 1. The standard floor 1 referred to in the present invention usually means the first floor above the ground, but in some cases, it may be the lowest floor underground or a super mega truss pre-built on the ground. Therefore, it should be understood that, in parallel with the construction of the above-mentioned ground portion, the construction of the standard floor or the so-called underground structure below it is generally accepted. Since the driving floor 3 is always used as a roof substitute for a construction workshop after that, it is subjected to some rain curing. In some cases, on the driving floor 3, an outer curing film may be hung on the outer periphery of the building. The driving floor 3 is also configured as a sky factory that doubles as a construction office and an assembly factory necessary for the subsequent construction of each floor of the building. Overhead traveling type circle crane 4 according to the present invention
For example, Japanese Patent Application No. 2-152467 and Japanese Patent Application No. 2-2
This is a crane described in the specification and the drawings, in which a boom horizontally swings and horizontally expands or contracts or moves, and can be used for transporting and assembling a skeleton part, equipment, and finishing unit by a lift attached to the boom. The circle crane 4 is installed by half-up by a height corresponding to the height of the worker after the construction of the drive floor 3 is completed on the reference floor 1. Then, drive floor 3, assuming constructed from standard floor 1 1 upstairs floor structure 5 1, slightly above the position than story height of at least 1 Kaibun (e.g. standard floor 1
4 to 5 m above the floor), and once fixed to the main pillar 2 at that position, it can be enjoyed.
【手続補正2】[Procedure Amendment 2]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0009[Correction target item name] 0009
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0009】図1Bは駆動階3のサークルクレーン4を
使用して、基準階1の床上で、基準階1から数えて2階
の床構造体51 を構築している段階を示している。床が
鉄骨造の場合の柱、梁、床の構造例を図3Aに示した。
角鋼管による本設柱2の四方にH形鋼による鉄骨梁10
を架け、その上にデッキプレート11を敷きスラブコン
クリートを打設することによって構築される。床のPC
化を図る場合には、鉄骨梁10の上にPC床版が敷き込
まれる。FIG. 1B shows a stage in which a circle crane 4 on the drive floor 3 is used to build a floor structure 5 1 on the second floor, counting from the standard floor 1, on the floor on the standard floor 1. An example of the structure of columns, beams, and floors when the floor is a steel frame is shown in FIG. 3A .
Steel beams 10 made of H-shaped steel on all sides of the main pillar 2 made of square steel pipe
Is constructed, and the deck plate 11 is laid on it, and the slab concrete is cast. Floor pc
In order to realize the above, a PC floor slab is laid on the steel beam 10.
【手続補正3】[Procedure 3]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0011[Correction target item name] 0011
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0011】図1Dは図1Cと同じハーフアップの段階
において、基準階1については耐火被覆、ダクト工事な
どを行ない、2階の床構造体51 の上ではサークルクレ
ーン4を使用して3階の床構造体52 の構築を行なって
いる状況を示している。この段階で本設柱2の継ぎ足し
も行なわれる。本設柱2の継ぎ足しは、図示を省略した
が、駆動階3の上にクレーンを設置し、又は本設柱2の
上端に同本設柱を伝い登るセルフクライミングのタワー
クレーンを設置して行なう。この段階での鉄骨造の柱、
梁、床の構造例を示したのが図3Bである。なお、本設
柱2は、上部へ継ぎ足すので、2層又は3層を1節とし
た長い柱単体の使用が出来、継手数の低減と鉄骨工事費
の節約が図られる。FIG. 1D shows that at the same half-up stage as in FIG. 1C, fireproof coating and duct work are performed on the standard floor 1, and on the floor structure 5 1 on the second floor, the circle crane 4 is used on the third floor. 2 shows a situation in which the floor structure 5 2 is being constructed. At this stage, the main pillar 2 is also replenished. Although not shown in the drawings, the extension of the main installation pillar 2 is performed by installing a crane on the drive floor 3 or by installing a self-climbing tower crane that climbs up the main installation pillar 2 at the upper end of the main installation pillar 2. .. Steel frame pillars at this stage,
FIG. 3B shows an example of the structure of beams and floors. In addition, since the main installation column 2 is added to the upper part, it is possible to use a long column alone having two or three layers as one node, which can reduce the number of joints and save the steel frame construction cost.
【手続補正4】[Procedure amendment 4]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0012[Correction target item name] 0012
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0012】図2Aは駆動階3の上昇により、既に構築
を完成した2階の床構造体51 をその上に構築した3階
の床構造体52 と共に2階の正規位置まで上昇させ、同
2階の床構造体51 は本設柱2へ取付け固定した段階を
示している。従って、二つの床構造体51 ,52 の上昇
に要する時間の短縮ができる。このときの上昇システム
を表したのが図4A,Bである。即ち、本設柱2を中心
に四方に配置された鉄骨梁10には本設柱2を中心に対
角方向に略正方形の上昇枠8を組み、該上昇枠8におけ
る各辺の略中点位置にケーブル7(ジャッキアップの場
合にはジャッキ)を結合した構造で上昇が行なわれる。FIG . 2A shows that the floor structure 5 1 of the second floor, which has already been constructed, is moved up to the normal position of the second floor together with the floor structure 5 2 of the third floor constructed on it by raising the driving floor 3 . The floor structure 5 1 on the second floor shows the stage where it is attached and fixed to the main installation column 2. Therefore, the time required to raise the two floor structures 5 1 and 5 2 can be shortened. FIGS. 4A and 4B show the lifting system at this time. That is, ascending frames 8 each having a substantially square shape are installed diagonally around the main installation columns 2 on the steel beams 10 arranged in four directions around the main installation columns 2. The ascending operation is performed by a structure in which a cable 7 (a jack in case of jacking up) is connected to the position.
【手続補正5】[Procedure Amendment 5]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0013[Correction target item name] 0013
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0013】図2Bは2階の床構造体51 を残し、既に
構築されている3階の床構造体52をハーフアップさせ
た段階を示している。図2Cは前記ハーフアップの段階
のまま、3階の床構造体52 が鉄骨造であるときにはそ
のスラブコンクリートの打設を行ない、2階の床構造体
51 については耐火被覆、ダクト工事などを行ない、2
階の外壁9や天井8の取付けなどを並行して行なってい
る状況を示している。また、3階の床構造体52 の上で
は、必要なら4階の床構造体の構築を行なうなど、以下
は前記図1D及び図2A〜Cの工程を繰り返して建物の
建築が進められる。そして、最終的に駆動階3は建物天
端に到達し、そのまま建物の最上階として利用される。
床構造体がPC化されている場合もほぼ同様な工程で建
築が進められる。FIG . 2B shows a stage in which the floor structure 5 1 on the second floor is left and the floor structure 5 2 on the third floor which has already been constructed is half-upped. FIG. 2C shows that, when the floor structure 5 2 on the third floor is a steel frame structure, the slab concrete is placed in the half-up stage, and the floor structure 5 1 on the second floor is fireproof coated or ducted. 2
This shows a situation in which the outer wall 9 and the ceiling 8 of the floor are attached in parallel. Also, on the third floor of the floor structure 5 2, including performing a construction of the fourth order of the floor structure if necessary, following the construction of the building it is advanced by repeating FIG. 1D and 2A~C steps. Finally, the driving floor 3 reaches the top of the building and is used as it is as the top floor of the building.
Even if the floor structure is made of PC, the construction proceeds in almost the same process.
【手続補正6】[Procedure correction 6]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0014[Correction target item name] 0014
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0014】[0014]
【第2の実施例】図5A〜F及び図6A〜Dに示した第
2の実施例は、先行する駆動階3を上昇させる(押し上
げる)ジャッキ装置6を、各階の床構造体51 ,52 の
上昇(引き上げ)にも併用することを特徴としている。
即ち、基準階1の上で構築した駆動階3を本設柱2に沿
って上昇(ハーフアップ)させ、駆動階3の下面に天井
走行型のサークルクレーン4を設置する。次に前記の天
井走行型サークルクレーン4を使用して基準階1の上で
2階の床構造体51 の構築を行なう(図5B)。その構
築が完成するか完成の以前に並行して、駆動階3の下側
に本設柱2を伝い登るジャッキ装置6を設置する。そし
て、該ジャッキ装置6によって駆動階3を少なくとも1
階分の階高よりも少し上方の位置まで上昇(押し上げ)
させる(図5C)。ちなみに図5Aに示した駆動階3の
ハーフアップは、例えば本設柱2の上部にリフトアップ
ジャッキを設置するなど暫定的な上昇手段を採用して行
なう。Second Embodiment In the second embodiment shown in FIGS. 5A to 5F and 6A to 6D, the jack device 6 for raising (pushing up) the preceding drive floor 3 is installed in the floor structure 5 1 of each floor. 5 to 2 rise (pulling) is characterized by in combination.
That is, the drive floor 3 constructed on the reference floor 1 is raised (half-up) along the main installation pillar 2, and the overhead traveling type circle crane 4 is installed on the lower surface of the drive floor 3. Next, the above-mentioned overhead traveling type circle crane 4 is used to construct the floor structure 5 1 on the second floor above the standard floor 1 ( FIG. 5B ). When the construction is completed or before the construction is completed, a jack device 6 that climbs along the main installation pillar 2 is installed below the drive floor 3. Then, at least one drive floor 3 is set by the jack device 6.
Raise to a position slightly higher than the floor height (up)
( Fig. 5C ). Incidentally, the half-up of the drive floor 3 shown in FIG. 5A is performed by adopting a temporary raising means such as installing a lift-up jack on the upper part of the main installation column 2.
【手続補正7】[Procedure Amendment 7]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0015[Correction target item name] 0015
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0015】上述のようにして2階の床構造体51 を基
準階1の上で構築を完成すると、駆動階3の支持を本設
柱2へ盛り替えた上で、前記ジャッキ装置6を下降さ
せ、該ジャッキ装置6により2階の床構造体51 を引き
上げてハーフアップさせる(図5D)。このハーフアッ
プの状態で、必要ならば2階のスラブコンクリート打設
を行ない(図5F)、あるいは基準階1の耐火被覆、ダ
クト工事を行ない、2階の床構造体51 の下側に天井工
事及び天井内の先行仕上げ工事などが無足場で行なわれ
る。さらに同2階の床構造体51 の床上では、駆動階3
のサークルクレーン4を使用して3階の床構造体52 の
構築が各々並行して行なわれる(図5F)。また、本設
柱2の継ぎ足しも行なわれる。When the construction of the floor structure 5 1 on the second floor is completed on the reference floor 1 as described above, the support of the drive floor 3 is re-placed on the main pillar 2, and then the jack device 6 is installed. It is lowered, and the floor structure 5 1 on the second floor is pulled up by the jack device 6 to half-up ( FIG. 5D ). In this half-up state, if necessary, slab concrete is placed on the second floor ( Fig. 5F ), or fireproof coating and duct work on the standard floor 1 are performed, and the ceiling is placed below the floor structure 5 1 on the second floor. Construction and pre-finishing work in the ceiling will be carried out without any scaffolding. Furthermore, on the floor of the floor structure 5 1 on the second floor, the driving floor 3
The floor structures 5 2 on the third floor are constructed in parallel using the circle crane 4 of FIG. 5 ( FIG. 5F ). In addition, the main pillar 2 is also replenished.
【手続補正8】[Procedure Amendment 8]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0016[Correction target item name] 0016
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0016】この後、2階及び3階の床構造体51 、5
2 を本設柱2へあずけておき、ジャッキ装置6を使用し
て駆動階3の上昇(押し上げ)が行なわれる(図6
A)。次には駆動階3を本設柱2へあずけてから、同じ
ジャッキ装置6を使用して2階及び3階の床構造体51
と52 が重なり合った状態のまま合一に2階の正規位置
まで引き上げて上昇される(図6B)。2階の床構造体
51 を正規位置において本設柱2へ取付け固定したあ
と、3階の床構造体52 のみがジャッキ装置6でハーフ
アップされる(図6C)。以後3階の床構造体52 にス
ラブコンクリートの打設(図6D)を行なうなど、図5
F及び図6A〜Cの工程を繰り返して建物の建築が進め
られ、最終的に駆動階3は建物の最上階に使用される。After this, the floor structures 5 1 , 5 on the second and third floors
2 is placed in the main installation pillar 2, and the driving floor 3 is raised (pushed up) using the jack device 6 ( Fig. 6 ) .
A ). Next, after the driving floor 3 is placed on the main pillar 2, the same jack device 6 is used, and the floor structures 5 1 on the 2nd and 3rd floors are used.
And 5 2 are overlapped with each other and are raised up to the normal position on the second floor ( Fig. 6B ). After the floor structure 5 1 on the second floor is attached and fixed to the main pillar 2 in the regular position, only the floor structure 5 2 on the third floor is half-upped by the jack device 6 ( FIG. 6C ). The subsequent third floor of the floor structure 5 2 etc. perform pouring of concrete slab (Fig. 6D), 5
The construction of the building is advanced by repeating the steps of F and FIGS. 6A to 6C , and finally the driving floor 3 is used as the top floor of the building.
【手続補正9】[Procedure Amendment 9]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0017[Correction target item name] 0017
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0017】[0017]
【第3の実施例】図7A〜Fに示した第3実施例は、床
構造体を鉄骨梁とPC床版で構築する場合のものであ
る。基準階1の上で駆動階3を構築し、これをハーフア
ップさせた(図7A,B)後にサークルクレーン4を設
置し、本設柱2の継ぎ足しを行ない(図7B)、駆動階
3の下側に本設柱2を伝い登るジャッキ装置6を設置
し、該ジャッキ装置6を使用して駆動階3を基準階1の
床から少なくとも1階分の階高よりも少し上方の位置ま
で押し上げて上昇させる(図7C)。この段階で、駆動
階3の下面のサークルクレーン4を使用して2階の床構
造体51 を2階の正規位置に構築をする(図7D)。並
行して本設柱2の継ぎ足しを行ない(図7E)、その後
ジャッキ装置6による駆動階3の上昇を2階の階高より
も少し上方位置まで行なう。以下図7C〜Fの各工程を
くり返して建物の建築を進め、最終的に駆動階3は建物
の最上階に使用する。[Third Embodiment] A third embodiment shown in FIGS. 7A to 7F is for constructing a floor structure with steel beams and a PC floor slab. After constructing the drive floor 3 on the standard floor 1, half-up the drive floor 3 ( Figs. 7A and 7B ), install the circle crane 4 and add the permanent pillars 2 ( Fig. 7B ) . A jack device 6 that climbs along the main pillar 2 is installed on the lower side, and the driving device 3 is pushed up from the floor of the reference floor 1 to a position slightly above the floor height of at least one floor by using the jack device 6. To raise ( Fig. 7C ). At this stage, the floor structure 5 1 on the second floor is constructed at the regular position on the second floor using the circle crane 4 on the lower surface of the driving floor 3 ( FIG. 7D ). In parallel, the permanent columns 2 are replenished ( FIG. 7E ), and then the driving floor 3 is raised by the jack device 6 to a position slightly above the floor height of the second floor. 7C to F are repeated to build the building, and finally the driving floor 3 is used as the top floor of the building.
【手続補正10】[Procedure Amendment 10]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】図面の簡単な説明[Name of item to be corrected] Brief description of the drawing
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【図面の簡単な説明】[Brief description of drawings]
【図1】A〜Dは本発明工法の第1実施例を工程順に示
した立面図である。[1] A~D is an elevational view showing a first embodiment of the present inventive method in order of steps.
【図2】A〜Cは本発明工法の第1実施例を工程順に示
した立面図である。 2A to 2C show the first embodiment of the method of the present invention in process order.
FIG.
【図3】A,Bは床構造体の斜視図である。 3A and 3B are perspective views of a floor structure.
【図4】A,Bは床構造体の上昇のための手段を示した
斜視図と平面図である。 4A and B show means for raising the floor structure
It is a perspective view and a top view.
【図5】A〜Fは本発明工法の第2実施例を工程順に示5A to 5F show a second embodiment of the method of the present invention in process order.
した立面図である。FIG.
【図6】A〜Dは本発明工法の第2実施例を工程順に示6A to 6D show a second embodiment of the method of the present invention in process order.
した立面図である。FIG.
【図7】A〜Fは本発明工法の第3実施例を工程順に示7A to 7F show a third embodiment of the method of the present invention in process order.
した立面図である。FIG.
【符号の説明】 1 基準階 2 本設柱 3 駆動階 4 サークルクレーン 51 2階の床構造体 52 3階の床構造体 6 ジャッキ装置[Explanation of symbols] 1 Standard floor 2 Main installation pillar 3 Drive floor 4 Circle crane 5 1 2nd floor floor structure 5 2 3rd floor floor structure 6 Jacking device
【手続補正11】[Procedure Amendment 11]
【補正対象書類名】図面[Document name to be corrected] Drawing
【補正対象項目名】全図[Correction target item name] All drawings
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【図1】 [Figure 1]
【図2】 [Fig. 2]
【図5】 [Figure 5]
【図6】 [Figure 6]
【図3】 [Figure 3]
【図4】 [Figure 4]
【図7】 [Figure 7]
───────────────────────────────────────────────────── フロントページの続き (72)発明者 森田 哲哉 大阪市中央区本町四丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 小倉 清志 大阪市中央区本町四丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 向井 久夫 大阪市中央区本町四丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 長谷川 保善 大阪市中央区本町四丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 佐藤 光弘 大阪市中央区本町四丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 長谷部 斎 大阪市中央区本町四丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 岩佐 義輝 東京都江東区南砂二丁目5番14号 株式会 社竹中工務店技術研究所内 (72)発明者 室 英治 東京都江東区南砂二丁目5番14号 株式会 社竹中工務店技術研究所内 (72)発明者 萩原 忠治 東京都江東区南砂二丁目5番14号 株式会 社竹中工務店技術研究所内 (72)発明者 西村 博之 東京都江東区南砂二丁目5番14号 株式会 社竹中工務店技術研究所内 (72)発明者 木林 浩 東京都江東区南砂二丁目5番14号 株式会 社竹中工務店技術研究所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Tetsuya Morita 4-1-1-13 Honmachi, Chuo-ku, Osaka Stock company Takenaka Corporation Osaka Main Store (72) Inventor Kiyoshi Ogura 4-1-1 Honmachi, Chuo-ku, Osaka No. 13 Stock Company Takenaka Corporation Osaka Main Store (72) Inventor Hisao Mukai 4-1-1 Honmachi, Chuo-ku, Osaka City Stock Company Takenaka Corporation Osaka Main Store (72) Inventor Hasegawa Hozen Osaka City Chuo-ku Honcho 4-1-13-1 Takenaka Corporation, Osaka Main Store (72) Inventor Mitsuhiro Sato 4-1-1, Honmachi, Chuo-ku, Osaka Incorporated Takenaka Corporation Osaka Main Store (72) Inventor Hasebe Sai Osaka Takenaka Kogyo Co., Ltd. 4-1-1 Hommachi, Chuo-ku, Osaka (72) Inventor Yoshiteru Iwasa 2-5-14 Minamisuna Koto-ku, Tokyo Takenaka Co., Ltd. Institute of Technology (72) Inventor Eiji 2-5-14 Minamisuna, Koto-ku, Tokyo Stocks company Takenaka Corporation Technical Research Institute (72) Inventor Tadaharu Hagiwara 2-5-14, Minamisuna, Koto-ku, Tokyo Stock Association Takenaka Corporation Technical Research Institute (72) Inventor Hiroyuki Nishimura 2-5-14 Minamisuna, Koto-ku, Tokyo Stock Corporation Takenaka Engineering Research Institute (72) Inventor Hiroshi Kibayashi 2-5 Minamisuna, Koto-ku, Tokyo No. 14 Stock Company Takenaka Corporation Technical Research Institute
Claims (2)
建て、この本設柱を伝い登る駆動階を構築し、その下面
に天井走行型のサークルクレーンを設置する段階と、 前記駆動階を前記基準階から少なくとも1階分の階高よ
りも上方の位置まで上昇させ、その位置に固定した上で
前記サークルクレーンを使用して前記基準階の上で基準
階から数えて2階の床構造体を構築し、この床構造体を
基準階からおよそ作業員の背丈相当の高さだけハーフア
ップさせ、その位置で前記2階の床構造体を完成させ、
前記基準階の耐火被覆やダクト布設などの仕上げ、設備
工事を行い、さらに前記2階の床上で3階の床構造体を
構築する段階と、 本設柱の継ぎ足しと駆動階の上昇、及び前記2階の床構
造体を同2階の正規位置まで上昇させ、本設柱へ取付け
固定する段階と、 以下同様に、各階の床構造体を順次に次下階の床上で構
築し、そのハーフアップと正規位置までの上昇及び固
定、並びに本設柱の継ぎ足しと駆動階の上昇を繰り返
し、最終的に前記駆動階は建物の最上階とすること、を
それぞれ特徴とする、全天候型建築工法。1. A step of, after completing the construction of a standard floor, constructing a permanent pillar on it, constructing a drive floor that climbs up the primary pillar, and installing an overhead traveling type circle crane on the lower surface thereof. The driving floor is raised from the reference floor to a position above the floor height of at least one floor, fixed at that position, and the circle crane is used to count 2 above the reference floor from the reference floor. Build a floor structure of the floor, half up the floor structure by about the height equivalent to the height of the worker from the reference floor, and complete the floor structure of the second floor at that position,
Finishing fireproof coating and ducting on the standard floor, performing facility work, and further constructing a floor structure on the third floor on the floor on the second floor, adding a permanent pillar and raising the driving floor, and The steps of raising the floor structure of the second floor to the normal position of the second floor and attaching and fixing it to the main pillar, and the same way as below, constructing the floor structure of each floor sequentially on the floor of the next lower floor, An all-weather construction method characterized by repeating up-movement, raising and fixing to a regular position, replenishing main columns and raising the driving floor, and finally making the driving floor the top floor of the building.
ッキ装置は、基準階又は各階床の上で構築した各階の床
構造体のハーフアップ及び正規位置への上昇に併用され
ることを特徴とする、請求項1に記載した全天候型建築
工法。2. A jack device for climbing up a driving floor by climbing up a main pillar is used for half-up of a floor structure of each floor constructed on a standard floor or each floor and raising to a normal position. The all-weather construction method according to claim 1, characterized in that
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP04048452A JP3079326B2 (en) | 1992-03-05 | 1992-03-05 | All-weather construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP04048452A JP3079326B2 (en) | 1992-03-05 | 1992-03-05 | All-weather construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH05248008A true JPH05248008A (en) | 1993-09-24 |
JP3079326B2 JP3079326B2 (en) | 2000-08-21 |
Family
ID=12803746
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP04048452A Expired - Lifetime JP3079326B2 (en) | 1992-03-05 | 1992-03-05 | All-weather construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3079326B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008214932A (en) * | 2007-03-02 | 2008-09-18 | Takenaka Komuten Co Ltd | Construction method for building |
-
1992
- 1992-03-05 JP JP04048452A patent/JP3079326B2/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008214932A (en) * | 2007-03-02 | 2008-09-18 | Takenaka Komuten Co Ltd | Construction method for building |
Also Published As
Publication number | Publication date |
---|---|
JP3079326B2 (en) | 2000-08-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1059483C (en) | Construction of stair and stair case and units of stair | |
JP3079324B2 (en) | Construction method of high-rise building | |
JPH05248008A (en) | All weather type building method | |
TW202227706A (en) | Multi-story building having prefabricated stair and elevator modules | |
JP3040309B2 (en) | Construction method of multi-layer suspension structure | |
JP3079323B2 (en) | Core precedence construction method for high-rise buildings | |
JP3115942B2 (en) | Building construction method | |
JP3241896B2 (en) | Steel frame stair hang down method | |
JP7500408B2 (en) | Pre-construction method for interior stairs of buildings | |
JP3355374B2 (en) | Driving-floor ascending construction method | |
JP2785112B2 (en) | All-weather construction method for high-rise buildings | |
JP3049584B2 (en) | All-weather construction method | |
JP3439545B2 (en) | Construction method of multi-story parking lot | |
JP2793052B2 (en) | Building construction method | |
JP2024000601A (en) | Construction method of building | |
JPH0781323B2 (en) | Building construction method | |
JPH0518132A (en) | Jack-up type construction method for steel structure such as tower type stereoscopic parking lot | |
JPH04231529A (en) | Method for constructing main frames of high-rise building | |
JP2946372B2 (en) | Construction method of structure | |
CN118601133A (en) | Construction method for layered lifting and high-altitude assembly of steel structure corridor | |
JP3236052B2 (en) | Unit type building and construction method | |
JPH05340001A (en) | Constructing method and device for building | |
JPH05187068A (en) | Construction method of building | |
JPH11125014A (en) | Construction method of building | |
JPH04155034A (en) | Execution method for small scale building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080623 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080623 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 9 Free format text: PAYMENT UNTIL: 20090623 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100623 Year of fee payment: 10 |