JPH0524577A - Ship building dock - Google Patents
Ship building dockInfo
- Publication number
- JPH0524577A JPH0524577A JP18254991A JP18254991A JPH0524577A JP H0524577 A JPH0524577 A JP H0524577A JP 18254991 A JP18254991 A JP 18254991A JP 18254991 A JP18254991 A JP 18254991A JP H0524577 A JPH0524577 A JP H0524577A
- Authority
- JP
- Japan
- Prior art keywords
- dock
- ship
- construction
- opening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、船舶建造ドック、より
詳しくは新造船,修繕船, 海洋構造物等を同時期に効率
よく建造できるようにした船舶建造ドックに関するもの
である。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a shipbuilding dock, and more particularly to a shipbuilding dock capable of efficiently building new ships, repair ships, marine structures and the like at the same time.
【0002】[0002]
【従来の技術】船舶を建造する場合には船台と建造ドッ
クとが利用されるが、特に大型船の場合には後者の建造
ドックが用いられる。この建造ドックにも一端にのみ開
閉ゲートを有するもの、又はその中間に中間ゲートを有
するもの、更には両端に開閉ゲートを有するものなど各
種の建造ドックが提案実施されている。2. Description of the Related Art A sill and a construction dock are used for building a ship, and the latter construction dock is used especially for a large ship. Various construction docks such as one having an opening / closing gate only at one end, one having an intermediate gate in the middle, and one having opening / closing gates at both ends have also been proposed and implemented.
【0003】そしてこのような建造ドックを用いて船舶
を建造する場合、船首部, 貨物艙部(船体の中央部),
及び船尾部に分けた分割建造が一般的に行なわれている
が、建造効率を向上させるために、長い工期を必要とす
る船尾部 (機関室部) が船首部や貨物艙部より先行して
建造されている。一方、修繕船の保守点検作業は比較的
工期が短かいという性格を有しており、更に石油掘削等
に用いられる海上作業台等の海洋構造物は幅広の構造物
で、通常の幅のドック内に収容することができず、かつ
工期が長くなるため特別の建造ドックとする必要があっ
た。When a ship is constructed using such a construction dock, the bow, the cargo hold (the center of the hull),
In general, split construction is performed by dividing into the stern and the stern, but in order to improve the construction efficiency, the stern (engine room), which requires a long construction period, precedes the bow and cargo hold. It is built. On the other hand, the maintenance and inspection work of repair ships has the characteristic that the construction period is relatively short.Furthermore, offshore structures such as offshore work tables used for oil drilling are wide structures and docks of normal width. Since it could not be housed inside and the construction period was long, it was necessary to use a special construction dock.
【0004】[0004]
【発明が解決しようとする課題】前記したように、従来
の船舶建造, 修繕船の保守点検, 海洋構造物建造時にお
ける工期等の特殊性から夫々専用のドックを用いていた
ためにドックの使用効率が悪いものとなっていた。As described above, due to the peculiarities of the conventional ship construction, maintenance and inspection of repair ships, construction period at the time of construction of offshore structures, etc. Was bad.
【0005】[0005]
【課題を解決するための手段】本発明は、前記したよう
な従来の問題点を解決するためになされたものであっ
て、一端部に第1の開閉ゲートを設けるとともに中間部
に複数の中間ゲートを配置した細長ドックの他端に前記
細長ドックより幅広のポケットドックを連接し、該ポケ
ットドックの他端に第2の開閉ゲートを設けた船舶建造
ドックを提供するものである。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, in which a first opening / closing gate is provided at one end and a plurality of intermediate portions are provided at an intermediate portion. Provided is a shipbuilding dock in which a pocket dock having a width wider than that of the slender dock is connected to the other end of the slender dock in which the gate is arranged, and a second opening / closing gate is provided at the other end of the pocket dock.
【0006】そして、細長ドックでは主として修繕船の
保守点検や、新造船の貨物艙部が建造され、ポケットド
ックでは海洋構造物や新造船の場合に船尾部が建造され
る。これによって多目的建造ドックとして利用可能とな
る。The slender dock is mainly used for maintenance and inspection of repair ships and the cargo hold of new ships is built, and the pocket dock is built for the stern of offshore structures and new ships. This allows it to be used as a multipurpose construction dock.
【0007】[0007]
【実 施 例】以下、第1図及び第2図に基づき本発明
による船舶建造用ドックの一実施例を説明する。第1図
において1は細長ドックで、この細長ドック1の一端に
は第1の開閉ゲート2が設けられ、他端にはこの細長ド
ック1より幅広のポケットドック3が連接されている。
そしてこの細長ドック1内には中間ゲート4及び5が配
置されるようになっている。[Embodiment] An embodiment of the ship building dock according to the present invention will be described below with reference to FIGS. 1 and 2. In FIG. 1, reference numeral 1 denotes a slender dock, a first opening / closing gate 2 is provided at one end of the slender dock 1, and a pocket dock 3 wider than the slender dock 1 is connected to the other end.
The intermediate gates 4 and 5 are arranged in the elongated dock 1.
【0008】更に又第2図にも示されるように細長ドッ
ク1とポケットドック3との接続部にも中間ゲート6が
配置されるようになっている。そしてポケットドック3
の他端には幅広の第2の開閉ゲート7が配置されるよう
になっている。前記船舶建造ドックにおいて、今、修繕
船工事と船舶建造を同時に行なう場合には、先ず中間ゲ
ート4, 5を配置して修繕ドック8と貨物艙建造ドック
9を形成させ、この貨物艙建造ドック9内で貨物艙ブロ
ックMを、又ポケットドック3内で船尾部ブロックAを
先行建造するとともに、第1の開閉ゲート2を開放して
修繕ドック8内に修繕船Sを入渠させ、工事後この第1
の開閉ゲート2から出渠させる。このとき、ポケットド
ック3と細長ドック1とは連結され、一体ドック10とし
て形成され、ここに先行の建造船舶が収容されているこ
とになる。Further, as shown in FIG. 2, an intermediate gate 6 is also arranged at the connecting portion between the elongated dock 1 and the pocket dock 3. And pocket dock 3
A wide second opening / closing gate 7 is arranged at the other end of the. In the ship building dock, when repair ship construction and ship building are performed at the same time, first, the intermediate gates 4 and 5 are arranged to form the repair dock 8 and the cargo hold dock 9, and the cargo hold dock 9 is formed. The cargo hold block M and the stern block A in the pocket dock 3 are pre-built inside, and the first opening / closing gate 2 is opened to dock the repair ship S in the repair dock 8, and after the construction, 1
From the open / close gate 2 of the dock. At this time, the pocket dock 3 and the slender dock 1 are connected to each other to form an integrated dock 10 in which the preceding construction ship is accommodated.
【0009】そしてこの先行建造船舶が第2の開閉ゲー
ト7を開放して出渠した後、中間ゲート5を開放して貨
物艙ブロックMと船尾部ブロックAを矢印Bで示すよう
に一体ドック10へ移動させて接続するとともに船首部ブ
ロックFを接続建造して新造船Nを建造する。一方、海
洋構造物と新造船を建造するときは第2図に示すように
ポケットドック3と細長ドック1との間に中間ゲート6
を配置してポケットドック3内で海洋構造物Hを建造し
て第2の開閉ゲート7を開放して出渠する。そしてこの
とき貨物艙ブロックMは貨物艙建造ドック9で、又船尾
部ブロックAは一体ドック10で先行建造され、次いで開
放ゲート5を開放して貨物艙ブロックMが一体ドック10
内に移送されて接続された後、船首部ブロックFが接続
建造される。Then, after this pre-built ship opens the second open / close gate 7 and docks, the intermediate gate 5 is opened and the cargo hold block M and the stern block A are integrated into the dock 10 as indicated by arrow B. The new ship N is constructed by connecting and constructing the bow block F while moving to and connecting. On the other hand, when constructing an offshore structure and a new ship, an intermediate gate 6 is provided between the pocket dock 3 and the elongated dock 1 as shown in FIG.
, The offshore structure H is built in the pocket dock 3, the second opening / closing gate 7 is opened, and the ship is docked. Then, at this time, the cargo hold block M is pre-built at the cargo hold construction dock 9, and the stern block A is pre-built at the integrated dock 10, and then the opening gate 5 is opened to open the cargo hold block M at the integrated dock 10.
After being transferred in and connected, the bow block F is connected and constructed.
【0010】この間、修繕ドック8内では工期の短かい
修繕船Sの工事がなされている。そして第1の開閉ゲー
ト2及び中間ゲート4を開放して修繕船S及び新造船N
が出渠されるのである。During this time, a repair ship S having a short construction period is being constructed in the repair dock 8. Then, the first opening / closing gate 2 and the intermediate gate 4 are opened, and the repair ship S and the new ship N are opened.
Will be unwound.
【0011】[0011]
【発明の効果】以上の説明から明らかなように、本発明
による船舶建造ドックは、一端部に第1の開閉ゲートを
設けるとともに中間部に複数の中間ゲートを配置した細
長ドックの他端に、前記細長ドックより幅広のポケット
ドックを連接し、該ポケットドックの他端に第2の開閉
ゲートを設けて構成されている。As is apparent from the above description, the shipbuilding dock according to the present invention is provided with the first opening / closing gate at one end and at the other end of the elongated dock having a plurality of intermediate gates arranged in the middle. A pocket dock wider than the elongated dock is connected to the pocket dock, and a second opening / closing gate is provided at the other end of the pocket dock.
【0012】従って、工期の異なる新造船, 修繕船及び
海洋構造物の建造等に利用できる。即ち、多目的建造ド
ックとして利用できるためドックの効率的な活用を計る
ことができるという効果がある。Therefore, it can be used for construction of new ships, repair ships and offshore structures having different construction periods. That is, since it can be used as a multipurpose construction dock, there is an effect that the dock can be efficiently utilized.
【図1】修繕船の工事と新造船を建造する場合の説明図
である。FIG. 1 is an explanatory diagram for the construction of a repair ship and the construction of a new ship.
【図2】修繕船の工事と新造船及び海洋構造物を建造す
る場合の説明図である。FIG. 2 is an explanatory diagram for construction of a repair ship and construction of a new ship and an offshore structure.
【符号の説明】 1 細長ドック 2 第1の開閉ゲート 3 ポケ
ットドック 4, 5, 6 中間ゲート 7 第2の開閉ゲート
8 修繕ドック 9 貨物艙建造ドック 10 一体ドック。[Explanation of symbols] 1 elongated dock 2 first opening / closing gate 3 pocket docks 4, 5, 6 intermediate gate 7 second opening / closing gate
8 Repair dock 9 Cargo barge dock 10 Integrated dock.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 小俣 和夫 千葉県市原市八幡海岸通1番地 三井造船 株式会社千葉事業所内 (72)発明者 金子 健一 千葉県市原市八幡海岸通1番地 三井造船 株式会社千葉事業所内 (72)発明者 鈴木 雅美 千葉県市原市八幡海岸通1番地 三井造船 株式会社千葉事業所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Kazuo Omata No. 1 Yawata Kaigan Dori, Ichihara City, Chiba Prefecture Mitsui Shipbuilding Co., Ltd. (72) Kenichi Kaneko No. 1 Hachiman Kaido Dori, Ichihara City, Chiba Prefecture Mitsui Shipbuilding Co., Ltd. Chiba Works (72) Inventor Masami Suzuki 1st Hachiman Kaigan Dori, Ichihara City, Chiba Mitsui Engineering & Shipbuilding Co., Ltd. Chiba Works
Claims (1)
に中間部に複数の中間ゲートを配置した細長ドックの他
端に、前記細長ドックより幅広のポケットドックを連接
し、該ポケットドックの他端に第2の開閉ゲートを設け
たことを特徴とする船舶建造ドック。Claim: What is claimed is: 1. A pocket dock wider than the elongated dock is connected to the other end of an elongated dock having a first opening / closing gate at one end and a plurality of intermediate gates arranged at the middle. A ship building dock, wherein a second opening / closing gate is provided at the other end of the pocket dock.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18254991A JPH0524577A (en) | 1991-07-23 | 1991-07-23 | Ship building dock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18254991A JPH0524577A (en) | 1991-07-23 | 1991-07-23 | Ship building dock |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0524577A true JPH0524577A (en) | 1993-02-02 |
Family
ID=16120229
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18254991A Pending JPH0524577A (en) | 1991-07-23 | 1991-07-23 | Ship building dock |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0524577A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100796410B1 (en) * | 2006-12-29 | 2008-01-21 | 현대중공업 주식회사 | Inundation method using tandem construction method |
WO2008082076A1 (en) * | 2006-12-29 | 2008-07-10 | Hyundai Heavy Industries Co., Ltd. | Inundation method used in tandem shipbuilding process |
KR100952910B1 (en) * | 2007-08-31 | 2010-04-16 | 삼성중공업 주식회사 | Floating gate dock and vessel construction method thereof |
CN101920766A (en) * | 2010-05-14 | 2010-12-22 | 蓬莱中柏京鲁船业有限公司 | Shipbuilding method |
-
1991
- 1991-07-23 JP JP18254991A patent/JPH0524577A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100796410B1 (en) * | 2006-12-29 | 2008-01-21 | 현대중공업 주식회사 | Inundation method using tandem construction method |
WO2008082076A1 (en) * | 2006-12-29 | 2008-07-10 | Hyundai Heavy Industries Co., Ltd. | Inundation method used in tandem shipbuilding process |
JP2009517290A (en) * | 2006-12-29 | 2009-04-30 | ヒュンダイ ヘビー インダストリーズ カンパニー リミテッド | Inundation method applied to tandem construction method |
JP4759620B2 (en) * | 2006-12-29 | 2011-08-31 | ヒュンダイ ヘビー インダストリーズ カンパニー リミテッド | Inundation method applied to tandem construction method |
KR100952910B1 (en) * | 2007-08-31 | 2010-04-16 | 삼성중공업 주식회사 | Floating gate dock and vessel construction method thereof |
CN101920766A (en) * | 2010-05-14 | 2010-12-22 | 蓬莱中柏京鲁船业有限公司 | Shipbuilding method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2228792A1 (en) | Icebreaking method and icebreaker | |
JPH0524577A (en) | Ship building dock | |
GB1503079A (en) | Ships hull | |
US3955523A (en) | Method of continuously building ships | |
WO2002049256A3 (en) | Methods and system for time sharing on cruise ships | |
GB1254960A (en) | Improvements in or relating to boat assemblies | |
US6698370B1 (en) | Hydrodynamic and supportive structure for gated ship stern | |
US3919960A (en) | Converted ship and method of converting | |
Martin | Horse and cargo handling on Medieval Mediterranean ships | |
JPS6331890A (en) | Building method for docking work facility utilizing used ship | |
JPS5336895A (en) | Method of floating and connecting hull of ship | |
KR800000463B1 (en) | Consecutive method of hull construction | |
JPS62160373A (en) | Waste ship utilizing type indoor factory forming method | |
JPH1129090A (en) | Accommodation space shape of ship | |
Casson | New evidence for Greek merchantmen | |
Minchinton | Richard Champion, Nicholas Pocock, and the Carolina Trade | |
US3185206A (en) | Device for stowing hatch covers on ships | |
GB1138691A (en) | Improvements in or relating to the deck structure of ships with very wide hatches | |
SU1576418A1 (en) | Method of reconstruction of pontoon floating dock | |
US20020096100A1 (en) | Articulated tug barge | |
Fukushima | Factors contributing to marine casualties | |
Belak | The KBXM Ship Hull Structure | |
JPS61220989A (en) | Super-shallow draft ship building method of utilizing existing ship | |
Brocket et al. | Shipping in The Great Lakes | |
DE2642868A1 (en) | Streamlined hull for catamaran - has symmetrical profiles tapering into keels without centre board to reduce wash |