JPH0521533Y2 - - Google Patents

Info

Publication number
JPH0521533Y2
JPH0521533Y2 JP16614788U JP16614788U JPH0521533Y2 JP H0521533 Y2 JPH0521533 Y2 JP H0521533Y2 JP 16614788 U JP16614788 U JP 16614788U JP 16614788 U JP16614788 U JP 16614788U JP H0521533 Y2 JPH0521533 Y2 JP H0521533Y2
Authority
JP
Japan
Prior art keywords
hole
reinforcing material
fixing
shaft
collar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP16614788U
Other languages
Japanese (ja)
Other versions
JPH0289030U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP16614788U priority Critical patent/JPH0521533Y2/ja
Publication of JPH0289030U publication Critical patent/JPH0289030U/ja
Application granted granted Critical
Publication of JPH0521533Y2 publication Critical patent/JPH0521533Y2/ja
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) 本考案は、地盤補強型基礎の形成において、基
礎躯体から地山に貫入する補強材を地山に確実に
定着させるための手段に関する。
[Detailed Description of the Invention] (Industrial Application Field) The present invention relates to a means for reliably fixing reinforcing material penetrating into the ground from the foundation frame to the ground in the formation of a ground-reinforced foundation.

(従来の技術) 躯体体積を増加させることなく支持力を増強す
る基礎の構築方法として、立坑から地山内に穿孔
し、孔内に異形棒鋼等の補強材を定着させた後、
この補強材の基端を立坑内に打設する基礎の躯体
に一体化する地盤補強型基礎が知られている(特
開昭62−25611号)。
(Prior technology) As a method for constructing a foundation that increases the supporting capacity without increasing the volume of the building frame, a hole is drilled into the ground from a vertical shaft, and a reinforcing material such as a deformed steel bar is fixed in the hole.
A ground-reinforced foundation is known in which the base end of this reinforcing material is integrated into the frame of the foundation that is cast into the shaft (Japanese Patent Laid-Open No. 62-25611).

この場合に、穿孔した孔部への補強材の定着方
法として、第8図に示すようにテープなどで排気
パイプ20と注入パイプ21を固定した補強材1
を孔口2から孔部3へ挿入し、注入パイプ21か
ら定着材(グラウト材)4を注入しつつ、孔部3
の空気を排気パイプ20で抜く方法がある。この
場合には、注入した定着材4が孔口2から立坑の
中へ流出しないよう、補強材1の基端に取り付け
た布製のパツカー22により孔口2を閉塞する。
In this case, as a method of fixing the reinforcing material to the drilled hole, as shown in FIG.
is inserted into the hole 3 from the hole 2, and while injecting the fixing material (grout material) 4 from the injection pipe 21,
There is a method of removing the air using the exhaust pipe 20. In this case, the hole 2 is closed with a cloth packer 22 attached to the base end of the reinforcing material 1 so that the injected fixing material 4 does not flow out from the hole 2 into the shaft.

(考案の課題) しかしながら、この定着方法にあつては定着後
も孔部3に排気パイプ20や注入パイプ21など
の異物が残留するので、その分補強材1の定着材
4に対する付着力や、定着材4と一体化した後の
補強材1の剛性が低下するという問題があつた。
また、注入パイプ21の径が小さいために定着材
4の注入に時間がかかり、定着材4に流動性の高
い高価な材料を使う必要があつた。
(Problem for the invention) However, in this fixing method, foreign substances such as the exhaust pipe 20 and the injection pipe 21 remain in the hole 3 even after fixing, so the adhesion force of the reinforcing material 1 to the fixing material 4 is reduced accordingly. There was a problem in that the stiffness of the reinforcing material 1 after being integrated with the fixing material 4 was reduced.
Furthermore, since the diameter of the injection pipe 21 is small, it takes time to inject the fixing material 4, and it is necessary to use an expensive material with high fluidity for the fixing material 4.

これに対して、孔部3に先に定着材4を注入
し、その後に補強材1を挿入するならば、このよ
うな問題は発生せず、より好ましい結果が得られ
るが、その場合でも定着材4による補強材1の定
着がパツカー22より奥側でしか行われないた
め、後で打設される基礎の躯体コンクリートと定
着材4との継目が、補強材1の応力が最も集中す
る位置に来てしまうという、構造的な問題があつ
た。
On the other hand, if the fixing material 4 is injected into the hole 3 first and the reinforcing material 1 is inserted after that, this problem will not occur and a more favorable result will be obtained, but even in that case, the fixing material 4 Since the reinforcement material 1 is anchored by the reinforcement material 4 only on the back side of the reinforcement material 22, the joint between the foundation concrete that will be poured later and the anchorage material 4 is the location where the stress of the reinforcement material 1 is most concentrated. There was a structural problem that caused the problem to occur.

本考案は、以上の問題点に鑑みてなされたもの
で、穿孔孔口に配置するパツカーの改良を通じ
て、補強材の地山への定着を強固にするととも
に、定着材と躯体コンクリートとの継目を躯体内
部に構成することを目的とする。
The present invention was developed in view of the above problems, and by improving the fixing car placed at the hole opening, it is possible to firmly fix the reinforcing material to the ground, and also to improve the joint between the fixing material and the concrete structure. The purpose is to configure it inside the building frame.

(課題を達成するための手段) 本考案は、立坑から地山内に穿孔した孔口の内
側に嵌合して一部を立坑内に突出する短管と、定
着材を注入した穿孔孔部に挿入定着させる補強材
の基端近くに固着して、前記短管の内側に挿入さ
れるつば状部材とを備える。
(Means for achieving the objective) This device comprises a short pipe which fits into the inside of the mouth of a hole drilled into the ground from a vertical shaft with a portion of it protruding into the shaft, and a flange-shaped member which is fixed near the base end of a reinforcing material to be inserted and fixed into the drilled hole into which an anchoring material has been injected and which is inserted into the inside of the short pipe.

(作用) 短管を孔口に嵌合し、立坑内に突出する短管開
口部から定着材を孔部に注入した後に、つば状部
材を固着した補強材を孔部に挿入すると、補強材
の侵入体積分の余剰定着材が孔部から短管開口部
を通つて外側へ溢れ出ると同時に、孔部に残る定
着材が孔部の隅々に行き渡り、つば状部材が短管
の内側に侵入する時点では、つば状部材の裏側は
定着材が隙間なく充填された状態となる。
(Function) After fitting the short pipe into the hole and injecting the fixing material into the hole from the short pipe opening protruding into the shaft, inserting the reinforcing material to which the collar-shaped member is fixed into the hole, the reinforcing material At the same time, the surplus fixing material corresponding to the intrusion volume overflows from the hole to the outside through the short pipe opening, and at the same time, the fixing material remaining in the hole spreads to every corner of the hole, and the collar-like member is pushed inside the short pipe. At the time of entry, the back side of the brim member is filled with the fixing material without any gaps.

また、補強材の挿入完了時につば状部材が短管
の立坑への突出部の内側に位置するように、予め
補強材へのつば状部材の固着位置を設定しておく
ことにより、定着材と後で立坑に打設される躯体
コンクリートとの継目は躯体内側に包含される。
In addition, by setting the fixing position of the collar-like member to the reinforcing material in advance so that the collar-like member is located inside the protruding part of the short pipe into the shaft when the reinforcing material is inserted, the anchoring material and The joint with the concrete frame that will be poured into the shaft later is included inside the frame.

(実施例) 第1図〜第7図に本考案の実施例を示す。(Example) Embodiments of the present invention are shown in FIGS. 1 to 7.

第1図はパツカーの構成を示すもので、1は異
形棒鋼による補強材であり、パツカーはこの補強
材1の基端寄りに固着するつば状部材5と、つば
状部材5を挿入する短管(鋼管)6とで構成され
る。
Fig. 1 shows the structure of the packer. 1 is a reinforcing member made of deformed steel bar, and the packer includes a collar-like member 5 fixed to the proximal end of the reinforcing member 1, and a short tube into which the collar-like member 5 is inserted. (Steel pipe) 6.

短管6の外径は第2図に示すように、立坑9か
ら地山7に穿孔された孔部3の孔口2に嵌合する
大きさとし、短管6の中間部の外周には孔口2へ
の侵入位置を位置決めする円環状のストツパ8を
形成する。一方、つば状部材5の外径はこの短管
6の内径より僅かに小さくする。なお、補強材1
を孔部3の奥まで挿入した時に、つば状部材5が
孔口2の外側の短管6の内側に位置するよう、補
強材1の先端からつば状部材5の固着位置までの
距離は孔部3の深さより若干大きく設定される。
As shown in FIG. 2, the outer diameter of the short pipe 6 is large enough to fit into the opening 2 of the hole 3 drilled from the shaft 9 into the ground 7, and a hole is provided on the outer periphery of the intermediate part of the short pipe 6. An annular stopper 8 is formed to determine the entry position into the mouth 2. On the other hand, the outer diameter of the collar-like member 5 is made slightly smaller than the inner diameter of the short tube 6. In addition, reinforcing material 1
The distance from the tip of the reinforcing material 1 to the fixed position of the collar-like member 5 is set so that the collar-like member 5 is located inside the short tube 6 outside the hole opening 2 when the collar-like member 5 is inserted deep into the hole 3. The depth is set slightly larger than the depth of section 3.

次に作用を説明する。 Next, the action will be explained.

立坑9からの穿孔作業により第2図のように地
山7に孔部3を形成したら、第3図に示すように
短管6をストツパ8が孔口2に接するまで孔口2
の内側に挿入する。次に第4図に示すように、注
入ホース10を短管6の開口部から孔部3に挿入
して定着材4を注入する。注入作業はホース10
を孔部3から引き抜きながら行うが、この時点で
は孔部3に補強材1が挿入されていないので、注
入作業は大径のホース10を使用する短時間で行
うことができる。このため、定着材4は流動性の
低いものでも良い。
After the hole 3 is formed in the ground 7 as shown in FIG. 2 by drilling from the shaft 9, the short pipe 6 is inserted into the hole 2 until the stopper 8 comes into contact with the hole 2, as shown in FIG.
Insert it inside. Next, as shown in FIG. 4, the injection hose 10 is inserted into the hole 3 through the opening of the short tube 6, and the fixing material 4 is injected. Hose 10 for injection work
The reinforcing material 1 is not inserted into the hole 3 at this point, so the injection work can be carried out in a short time using the large diameter hose 10. Therefore, the fixing material 4 may have low fluidity.

第5図に示すような状態で定着材4の注入が完
了したら、第6図に示すように短管6の開口部か
ら補強材1を孔部3に挿入する。補強材1に押し
除けられた定着材4は、短管6の開口部から立坑
9内に溢れ出る一方、孔部3内に残つていた空隙
を隙間なく充填する。このようにして、やがてつ
ば状部材5が短管6に侵入すると、定着材4は短
管6とつば状部材5の隙間からのみ流出すること
になるので、この流出によりつば状部材5の裏側
の隅々まで定着材4が充填されたことを確認しつ
つ、補強材1を第7図のように孔部3いつぱいに
押し込めば、作業は完了する。
When the injection of the fixing material 4 is completed in the state shown in FIG. 5, the reinforcing material 1 is inserted into the hole 3 from the opening of the short tube 6 as shown in FIG. The fixing material 4 pushed away by the reinforcing material 1 overflows into the shaft 9 from the opening of the short pipe 6, and fills the gap remaining in the hole 3 without leaving a gap. In this way, when the collar-shaped member 5 eventually enters the short tube 6, the fixing material 4 will flow out only from the gap between the short tube 6 and the collar-shaped member 5. The work is completed by pushing the reinforcing material 1 into the hole 3 to the fullest as shown in FIG. 7, while making sure that the fixing material 4 is filled to every corner.

以上のようにして、つば状部材5と短管6から
なるパツカーを用いて孔部3に定着させた補強材
1は、孔部3内に異物の残留がなく、定着材4が
隙間なく行き渡つているので、付着力、剛性とも
十分で、優れた地盤補強効果を発揮する。
As described above, the reinforcing material 1 is fixed in the hole 3 using the packer made of the brim member 5 and the short tube 6, so that no foreign matter remains in the hole 3 and the fixing material 4 is spread without any gaps. Because it is attached, it has sufficient adhesion and rigidity, and exhibits an excellent ground reinforcement effect.

また、立坑9に躯体コンクリートを打設する際
に定着材4とコントリートとの継目となるつば状
部材5は孔口2より立坑9側に位置しているの
で、これらの継目は躯体の内部に包含され、応力
の集中する補強材1と躯体との境目に来ることは
ない。このため、継目が構造上の弱点とならず、
好ましい形で基礎の施工を行うことができる。
In addition, when pouring concrete into the shaft 9, the collar-like member 5 that forms the joint between the anchoring material 4 and the concrete is located on the side of the shaft 9 from the hole opening 2, so these joints are connected to the inside of the shaft. , and does not come to the boundary between the reinforcing material 1 and the frame where stress is concentrated. Therefore, joints do not become structural weaknesses,
The foundation can be constructed in a desirable manner.

(考案の効果) 以上のように、本考案は穿孔孔口の内側に嵌合
して一部を立坑内に突出する短管と、補強材の基
端近くに固着して短管の内側に挿入されるつば状
部材とでパツカーを構成したので、定着材を注入
した穿孔孔部にこのパツカーを用いつつ補強材を
挿入することにより孔内に異物や空隙が残らず、
補強材を容易かつ強固に地山に定着させることが
できる。
(Effects of the invention) As described above, the present invention consists of a short pipe that fits inside the borehole opening and partially protrudes into the shaft, and a short pipe that is fixed near the base end of the reinforcing material and extends inside the short pipe. Since the packer is made up of the brim-shaped member to be inserted, by using this packer and inserting the reinforcing material into the hole where the fixing material has been injected, no foreign matter or voids will remain in the hole.
The reinforcing material can be easily and firmly fixed to the ground.

また、定着部材と立坑に打設する基礎の躯体コ
ンクリートとの継目となるつば状部材を、立坑の
内側に突出する短管の内側に位置させることによ
り、基礎完成時には継目が躯体内部に包含され、
継目が構造上の弱点となるのを防止することがで
きる。
In addition, by locating the collar-shaped member that forms the joint between the anchoring member and the foundation concrete concrete cast in the shaft inside the short pipe that protrudes inside the shaft, the joint will be contained within the framework when the foundation is completed. ,
Seams can be prevented from becoming structural weaknesses.

このため、本考案は簡易な構造でありながら、
地盤補強型の基礎の形成において優れた効果を発
揮する。
Therefore, although the present invention has a simple structure,
Demonstrates excellent effectiveness in forming ground-reinforced foundations.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案の実施例を示す穿孔孔口処理用
パツカーの斜視図、第2図〜第7図は同パツカー
を用いた補強材定着作業の様子を順を追つて示し
た穿孔孔部の縦断図である。また、第8図は従来
例を示す定着状態の補強材の側面図である。 1……補強材、2……孔口、3……孔部、4…
…定着材、5……つば状部材、6……短管、7…
…地山、9……立坑。
Fig. 1 is a perspective view of a packer for processing a perforated hole according to an embodiment of the present invention, and Figs. 2 to 7 show a perforated hole section showing the reinforcing material fixing work using the same packer in order. FIG. Moreover, FIG. 8 is a side view of a reinforcing material in a fixed state showing a conventional example. 1... Reinforcement material, 2... Hole opening, 3... Hole portion, 4...
...Fixing material, 5...Brim member, 6...Short tube, 7...
...ground, 9...shaft.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 立坑から地山内へ穿孔した孔口の内側に嵌合し
て一部を孔外に突出する短管と、定着材を注入し
た穿孔孔部に挿入定着させる補強材の基端近くに
固着して、前記短管の内側に挿入されるつば状部
材からなる穿孔孔口処理用パツカー。
A short pipe that fits inside the hole drilled into the ground from the shaft and partially protrudes outside the hole, and a reinforcing material that is inserted into the hole into which fixing material is injected and fixed near the base end. , a puncher for processing a perforated hole, which comprises a collar-like member inserted inside the short pipe;
JP16614788U 1988-12-22 1988-12-22 Expired - Lifetime JPH0521533Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16614788U JPH0521533Y2 (en) 1988-12-22 1988-12-22

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16614788U JPH0521533Y2 (en) 1988-12-22 1988-12-22

Publications (2)

Publication Number Publication Date
JPH0289030U JPH0289030U (en) 1990-07-13
JPH0521533Y2 true JPH0521533Y2 (en) 1993-06-02

Family

ID=31453274

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16614788U Expired - Lifetime JPH0521533Y2 (en) 1988-12-22 1988-12-22

Country Status (1)

Country Link
JP (1) JPH0521533Y2 (en)

Also Published As

Publication number Publication date
JPH0289030U (en) 1990-07-13

Similar Documents

Publication Publication Date Title
JP5202708B2 (en) Steel pipe pile and pile foundation method using the steel pipe pile
JPH0521533Y2 (en)
JP2823369B2 (en) Flexible pipe and its construction method
JP2885077B2 (en) Connection pile method of ready-made concrete pile
JP2790038B2 (en) Reinforcement method of existing pile foundation building
JPH09324422A (en) Cast-in-place compound pile and building method therefor
JP3172694B2 (en) Embedding method of straight pillar in reverse hitting method
JP3776330B2 (en) Seismic walls of existing buildings and construction methods
JPS59192145A (en) Fixing of iron pillar
JP2003055985A (en) Connecting method of column to pile
JPS59134228A (en) Integration work of pile or continuous wall and footing
JPH108482A (en) Joined structure between construction center column and pile and posteriorly constructing method for construction center column
JP2627540B2 (en) Additional structure of concrete skeleton
JPH03250114A (en) Construction method of cast-in-place concrete pile
JPH10102600A (en) Execution method for post-execution anchor and grout cap
JPH1162247A (en) Construction method for building skeleton utilizing existing foundation slab
JPH038922A (en) Executing method for hollow foundation pile and pile head filling-in stuff
JPH0328416A (en) Construction method to build up pile
JPH0351467Y2 (en)
JPH06280271A (en) Cast-in-place steel pipe concrete pile-column construction and construction method thereof
JPH08199565A (en) Pile head joint construction of cast-in-place concrete pile
JPH09328759A (en) Join method of column and pile
JP2567990B2 (en) Reverse construction method for underground construction
JP2001355232A (en) Water stop method for joint section on steel pipe sheet pile
JP2000291146A (en) Joint structure of pile head and column, and construction method therefor