JPS59134228A - Integration work of pile or continuous wall and footing - Google Patents

Integration work of pile or continuous wall and footing

Info

Publication number
JPS59134228A
JPS59134228A JP671283A JP671283A JPS59134228A JP S59134228 A JPS59134228 A JP S59134228A JP 671283 A JP671283 A JP 671283A JP 671283 A JP671283 A JP 671283A JP S59134228 A JPS59134228 A JP S59134228A
Authority
JP
Japan
Prior art keywords
footing
pile
steel material
construction method
continuous wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP671283A
Other languages
Japanese (ja)
Other versions
JPH0243848B2 (en
Inventor
Isao Aihara
相原 功
Toyoyuki Okajima
豊行 岡島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohbayashi Gumi Ltd
Obayashi Gumi Ltd
Original Assignee
Ohbayashi Gumi Ltd
Obayashi Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohbayashi Gumi Ltd, Obayashi Gumi Ltd filed Critical Ohbayashi Gumi Ltd
Priority to JP671283A priority Critical patent/JPS59134228A/en
Publication of JPS59134228A publication Critical patent/JPS59134228A/en
Publication of JPH0243848B2 publication Critical patent/JPH0243848B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To prevent the reduction of prestress by a method in which the end of a steel material is projected from a footing, the steel material is tensed by using a fixing tool to introduce prestress force into the steel material, and a pile or continuous wall and the footing are integrated. CONSTITUTION:A PC pile 14 in which plural PC steel materials 10 are buried in a tense state in concrete is driven into the ground 16, the upper end 26 of the PC pile 14 is cut off so slightly project the pile head 18 to the ground surface, and the steel material 10 is left as an upper end exposure 28 without being cut off. Concrete is placed to form a footing 24, and the upper end of the steel material 10 is slightly projected upwards by forming a recessed fixing portion 30 on the upper end of the footing 24. A fixing tool 32 is inserted into the fixing portion 30, the steel material 10 is tensed to introduce prestress force between the pile head 18 and the footing 24, and thereby the PC pile 14 and the footing 24 are integrated.

Description

【発明の詳細な説明】 この発明は、杭または連壁とフーチングとの一体化工法
に関し、より具体的には、プレストレス1〜コンクリー
ト(以下PCと略称り°る)用鋼材を埋設したPC杭、
場所打ち杭あるいは地中連続壁とコンクリートの打設に
J:り形成されるフーチングとの一体化工法に関するも
のである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an integrated construction method of piles or continuous walls and footings, and more specifically, prestressing concrete (PC) in which steel materials for concrete (hereinafter abbreviated as PC) are embedded. stake,
This relates to a construction method that integrates cast-in-place piles or underground continuous walls with footings formed during concrete pouring.

従来、例えば予めPC用鋼材を緊張状態でコンクリート
中に埋設し、コンクリート製杭にブレストレスカを導入
したいわゆるP’C杭とフーチングとを一体化する工法
においては、地中に打ち込んだPC杭の杭上端をPC鋼
材と一緒にカットオフし、地上に杭頭部を若干露出させ
た状態でフーチングとの接合を行なっていた。
Conventionally, for example, in the construction method of integrating the so-called P'C pile and footing, in which prestressing steel was buried in concrete under tension and a bracing stress was introduced into the concrete pile, The upper end of the pile was cut off along with the PC steel material, and the pile head was slightly exposed above the ground before being joined to the footing.

しかしながら、このように杭上端をカットオフすれば、
杭頭部のプレストレスが減少し、フーチ〕/グとの接合
部近傍はPC杭にならないという問題点があった。
However, if you cut off the top end of the pile like this,
There was a problem in that the prestress at the pile head decreased and the area near the joint with the footch did not become a PC pile.

このため、第1図あるいは第2図に示すような、プレス
トレスの減少した部分を補強する工法が提供されている
For this reason, a method of reinforcing a portion where prestress has decreased, as shown in FIG. 1 or 2, has been proposed.

寸なわら、第1図に示す工法では、PC鋼材10とコン
クリート12とからなるPC杭14を所定の深さまで地
中16に打ち込み、杭頭部18を若干地上に突出した状
態までカットオフした後、該PC杭14の外周に所定の
深さの孔部20を掘削し、この孔部20内に補強用鉄筋
22の一部を挿入した状態で建て込み、孔部20および
中埋めコンクリート部21のコンクリート打設を行なっ
た後、フーチング24をコンクリートで仕上げて一体化
するものである。
However, in the construction method shown in Fig. 1, a PC pile 14 made of PC steel 10 and concrete 12 is driven into the ground 16 to a predetermined depth, and the pile head 18 is cut off to a point where it slightly protrudes above the ground. After that, a hole 20 of a predetermined depth is excavated around the outer periphery of the PC pile 14, and a part of the reinforcing reinforcing bar 22 is inserted into this hole 20, and the pile is built, and the hole 20 and the concrete filling part are After pouring concrete 21, the footing 24 is finished with concrete and integrated.

また、第2図に示す工法は、PC杭14の打ち込み、杭
頭部18のカットオフまでの工程は、上記工法と同様で
あるが−1この後にP’C抗14の内部の孔部20に補
強用鉄筋22を一部挿入した状態で建て込み、中3里め
コンクリート部21のコンクリート打設を行なった後、
フーチング24をコンクリートで仕上げて一体化するも
のである。
In addition, in the construction method shown in FIG. 2, the steps from driving the PC pile 14 to cutting off the pile head 18 are similar to the construction method described above. After constructing the building with reinforcing reinforcing bars 22 partially inserted, and pouring concrete for the middle 3rd concrete section 21,
The footing 24 is finished with concrete and integrated.

しかしながら、このような工法においても、PC杭とフ
ーチング24の接合状態は、ある程度補強されるものの
、杭頭部18におけるプレストレスの減少分を回復する
ものではなく、根本的な問題点の解消はなされていない
という問題があった。
However, even with this construction method, although the joint state between the PC pile and the footing 24 is reinforced to some extent, it does not recover the reduced prestress at the pile head 18, and the fundamental problem cannot be solved. The problem was that it had not been done.

また、上述のようにPC杭14の外周部や内部に孔部2
0を掘削することや、補強用鉄筋22を建て込むことは
、工期を短縮する上での障害となり、コストアップにも
なるという欠点を有するものであった。
In addition, as described above, there are holes 2 on the outer periphery and inside of the PC pile 14.
Excavation of 0 and installation of reinforcing reinforcing bars 22 have the drawbacks of being an obstacle to shortening the construction period and increasing costs.

この発明は、上述したような従来工法の欠点に着目し、
これを解消すべくなされたものであり、その目的とする
ところは、補強用の部材や掘削作業を追加することなく
施工できる経済的有利性を有し、且つPC杭の頭部をカ
ッ1〜オフした場合でもプレストレスの減少を回復でき
るとともに、PC杭や地中連続壁とフーチングとの接合
状態を強化できる抗または連壁とフーチングとの一体化
工法を提供するところにある。
This invention focuses on the drawbacks of the conventional method as described above,
It was developed to solve this problem, and its purpose is to have an economical advantage in that it can be constructed without adding reinforcement members or excavation work, and to cut the head of the PC pile from 1 to 1 To provide a construction method for integrating a column or a continuous wall and a footing, which can recover the decrease in prestress even when the prestress is turned off, and can strengthen the joint state between the footing and the PC pile or underground continuous wall.

上記目的を達成するため、この発明は抗または連壁とフ
ーチングとの一体化工法において、プレストレストコン
クリート用鋼材の上端露出部にコンクリート打設により
フーチングを形成するとともに、前記調料の端部をフー
チングより若干突出さぜ、定着具を用いて前記M拐を緊
張させプレストレス力を導入し、杭または連続壁とフー
チングとを一体化するようにしてなるという特徴を有す
るものである。
In order to achieve the above object, the present invention uses a construction method that integrates a wall or a continuous wall with a footing, in which a footing is formed by pouring concrete into the exposed upper end of a steel material for prestressed concrete, and the end of the preparation is removed from the footing. The footing is characterized in that the footing is slightly protruded, and a fixing tool is used to tension the M-wall and introduce a prestress force, thereby integrating the pile or the continuous wall and the footing.

以下にこの発明の好適な実施例を添付図面を参照して説
明する。
Preferred embodiments of the present invention will be described below with reference to the accompanying drawings.

なお、以下の説明においては、上記した従来の施工法と
同−若しくは相当する部分については、同一符号を付す
ものである。
In the following description, parts that are the same as or correspond to the conventional construction method described above are given the same reference numerals.

第3図から第6図は、この発明に係る杭または連壁とフ
ーチングとの一体化工法の一実施例を示すものである。
FIGS. 3 to 6 show an embodiment of the method of integrating a pile or a continuous wall and a footing according to the present invention.

同図に示す一体化工法は、PC杭とフーチングとの一体
化について適用した場合を示すもので、先ずPC用鋼材
10を複数本コンクリート12中に緊張した状態で埋設
したPC杭を、所定の深さまで地中16に打ち込み、地
上に露出したPC杭14の上端部26をカットオフし、
抗頭部18を若干地上に突出した状態となすことは、従
来工法と同様である(第3図、第4図参照)。
The integrated construction method shown in the figure shows the case where a PC pile and a footing are integrated. First, a PC pile, in which a plurality of PC steel materials 10 are buried under tension in concrete 12, is placed in a predetermined position. Drive it into the ground 16 to a depth, cut off the upper end 26 of the PC pile 14 exposed above the ground,
The state in which the counter head 18 is slightly protruded above the ground is similar to the conventional construction method (see FIGS. 3 and 4).

そして、同図に示すフーチングと杭との一体化工法にお
いては、上述した従来工法に対し以下に述べるような特
徴点を有するものである。
The method of integrating footings and piles shown in the figure has the following features compared to the conventional method described above.

すなわち、上記PC杭14の上端部26をカットオフす
る際に、上記PC用鋼材10はカットしないで、第4図
に示すようにそのまま上端露出部28として残しておぎ
、この部分にコンクリートを打設してフーチング24を
形成するとともに、PC用鋼材10の上端部をフーチン
グ24の上端に、凹状の定着部30を形成することで若
干′上方に突出した状態になす事である(第5図参照)
That is, when cutting off the upper end part 26 of the PC pile 14, the PC steel material 10 is not cut, but is left as it is as the upper end exposed part 28 as shown in FIG. 4, and concrete is poured into this part. At the same time, the upper end of the PC steel material 10 is made to protrude slightly upward by forming a concave fixing part 30 at the upper end of the footing 24 (see Fig. 5). )
.

この場合、予め上記PC用鋼材10の上端に、後述する
定着具32と合致する、ネジを周設した状態でコンクリ
ート12内に埋設しておくことで、定着作業を容易にな
すことができ望ましいところである。
In this case, it is preferable to bury the PC steel material 10 in advance in the concrete 12 with a screw that matches the fixing tool 32, which will be described later, installed at the upper end of the steel material 10 to facilitate the fixing work. By the way.

また、前もって形成すべきフーチング24の厚み、PC
Cl2O地中16への埋設長および突出させる杭頭部1
8長等を計算し、PCCl2O上端に所定の長さだけP
C用鋼材10の上端露出部28を形成した状態で施工J
ることも可能であり、このようになすことで上述したカ
ットオフ作業も不要となり、経済的にも有利となる。
Also, the thickness of the footing 24 to be formed in advance, PC
Cl2O burial length in the ground 16 and protruding pile head 1
8 length, etc., and add a predetermined length of P to the upper end of PCCl2O.
Construction J with the upper end exposed portion 28 of the steel material 10 for C formed
It is also possible to do this, and by doing so, the above-mentioned cut-off operation is not required, which is also economically advantageous.

この後に、上記定着部30内に定着具32を挿入し、上
記PC用鋼材10を緊張することで、杭頭部18とフー
チング24との間にプレストレスノ〕を導入することで
、PCCl2Oフーチング24とを一体化するものであ
る(第6図参照)。
After that, by inserting the fixing tool 32 into the fixing part 30 and tensioning the PC steel material 10, a pre-stress hole is introduced between the pile head 18 and the footing 24, thereby forming the PCCl2O footing. 24 (see Figure 6).

このPC用鋼材10に緊張力を導入するに当たっては、
上記フーチング24の打設コンクリートが完全に固化す
る前に行なうことも可能であり、要すれば、上記上端露
出部28に、鋼管製等のシースを被せておき、打設コン
クリートの同化後において行なうこともまた可能である
In introducing tension to this PC steel material 10,
It is also possible to carry out this process before the poured concrete of the footing 24 is completely solidified, or if necessary, cover the exposed upper end portion 28 with a sheath made of steel pipe or the like and carry out this process after the poured concrete has assimilated. It is also possible.

さて、上記のような構成でフーチング24とPCCl2
O一体化する工法においては、上述した従来工法のよう
にPCCl2O上端部26をカットオフして杭頭部18
のプレストレスが減少しても、再びPC用鋼材10を緊
張することでプレストレスの回復がなされるとともに、
PCCl2Oフーチング24の接合部にもプレストレス
が導入された状態で接合されるため、従来の補強用鉄筋
22よりもはるかに強固に接合され、カットオフに伴う
問題点は根本的に解消することができる。
Now, with the above configuration, the footing 24 and PCCl2
In the O integration method, the pile head 18 is cut off by cutting off the PCCl2O upper end 26 as in the conventional method described above.
Even if the prestress decreases, the prestress is recovered by tensioning the PC steel material 10 again, and
Since the joints of the PCCl2O footings 24 are also joined with prestress introduced, the joints are much stronger than the conventional reinforcing bars 22, and the problems associated with cut-off can be fundamentally solved. can.

また、上述したような作用効果を発揮させるための構成
は、定着部30の形成、および定着具32の追加等比較
的簡単なものであり、工期の短縮、コメ1〜ダウン等の
経済的有利さをも有するものである。
In addition, the configuration for achieving the above-mentioned effects is relatively simple, such as forming the fixing part 30 and adding the fixing tool 32, and has economical advantages such as shortening the construction period and reducing rice production. It also has the characteristics of

第7図はこの発明の第2の実施例を示すものであり、そ
の特徴点についてのみ説明すると、上記第1の実施例が
予め埋設されていたpc&lil材1゜を、PCCl2
O上端部26をカットオフづることで上端露出部28と
したのに対し、この実施例では、」−記PCwI月10
の外周に、一端がデッドアンカー36として埋設された
、比較的短尺な連結PC用鋼材33を、他端側が上記露
出部28となるようにシ旧ノだどころにある。
FIG. 7 shows a second embodiment of the present invention, and to explain only its features, the first embodiment described above replaces 1° of PC&lil material buried in advance with PCCl2.
The upper end portion 26 is cut off to form the upper end exposed portion 28, whereas in this embodiment, the upper end portion 26 is cut off.
A relatively short steel material 33 for a connecting PC, one end of which is buried as a dead anchor 36, is placed in the outer periphery of the board so that the other end becomes the exposed portion 28.

このような構成のPC抗を地中16に、その杭頭部18
が若干露出した状態までノ]ち込み、その上部フーチン
グ24を形成し、連結PC用鋼材33に定着具32を用
いて緊張しプレストレスを導入することで、上述した作
用効果を奏することができる。
A PC shaft with such a configuration is installed underground 16, and its pile head 18
The above-mentioned effects can be achieved by lowering the steel material 33 to a slightly exposed state, forming the upper footing 24, and applying prestress to the connecting PC steel material 33 by tensioning it using the fixing tool 32. .

第8図は、この発明の第3の実施例を示すものであり、
その特徴点についてのみ説明すると、上記第、1および
第2の実施例がいずれも既存のPCCl2O地中16に
打ち込み杭とするものであったのに対し、この実施例で
は杭を構築現場に縦孔を掘削し、この縦孔内にコンクリ
−1〜を打設して形成するいわゆる場所打ち抗34に適
用したものである。
FIG. 8 shows a third embodiment of the invention,
To explain only its characteristic points, while the above-mentioned 1st, 1st and 2nd embodiments all used piles driven into the existing PCCl2O underground 16, this embodiment uses piles vertically at the construction site. This is applied to a so-called cast-in-place shaft 34 which is formed by excavating a hole and pouring concrete into the vertical hole.

同図に承りように、この実施例においては上記1) C
用鋼材10を、杭頭部18がら予め突出した状態で配置
しておき、上記上端露出部28となすものであり、その
他の点は上記第1の実施例と同様な工程でフーチング部
24との一体化がなされる。
As shown in the figure, in this embodiment, the above 1) C
The steel material 10 is placed in advance so as to protrude from the pile head 18, and is formed into the upper end exposed portion 28, and the footing portion 24 and the footing portion 24 are otherwise formed in the same process as in the first embodiment. will be integrated.

また第9図は、この発明の第4の実施例を示すものであ
る。
Further, FIG. 9 shows a fourth embodiment of the present invention.

同図に示す一体化工法は、フーチングと地中連続壁35
とを一体化する場合について適用したものであり、その
特徴とする点についてのみ説明すると、地中連続壁35
内に予め埋設されているPC用鋼材10の下端部をデッ
ドアンカー36として埋め殺した状態となずものである
The integrated construction method shown in the figure consists of a footing and an underground continuous wall 35.
This is applied to the case where the underground continuous wall 35
This is similar to the state in which the lower end of the PC steel material 10 that has been buried in advance is buried as a dead anchor 36.

このように予めPC用鋼材10の下端部をデッドアンカ
ー36となした場合においても、上述した実施例で説明
した作用効果を発揮し得ることはいうまでもない。
It goes without saying that even in the case where the lower end of the steel material 10 for PC is made into the dead anchor 36 in advance, the effects described in the above-mentioned embodiments can be exhibited.

以上のように、この発明はPC杭−1場所打ち抗あるい
は地中連続壁とフーチングと一体化する工法においてP
C用鋼材の上端露出部にコンクリートを打設してフーチ
ングを形成するとともに、前記PC用鋼材の端部を前記
フーチング上端より若干突出させ定着部を形成し、この
定着部内で定着具を用いて前記PC用鋼材を緊張せしめ
プレストレスを導入し、前記PC,場所打ち杭あるいは
地中連続壁ど前記フーチングとを一体化するようにして
なるものであり、PC杭のカットオノに伴うプレストレ
スの減少を回復できるとともに、これらとフーチングの
接合とを強固にならしめることかできる。
As described above, this invention provides a method for integrating PC piles with one cast-in-place pile or with an underground continuous wall and footing.
A footing is formed by pouring concrete onto the exposed upper end of the C steel material, and a fixing part is formed by slightly protruding the end of the PC steel material from the upper end of the footing, and a fixing tool is used within this fixing part. The steel material for the PC is tensed and prestress is introduced, and the PC, cast-in-place pile, or continuous underground wall or footing is integrated with the footing, and the prestress due to the cut-on of the PC pile is reduced. It is possible to recover these and to strengthen the joint between them and the footing.

【図面の簡単な説明】[Brief explanation of drawings]

第1図および第2図は、従来工法により形成されたプレ
ストレストコンクリート杭とフーチングとを示すそれぞ
れの断面図である。 第3図から第6図は、この発明に係るプレストレストコ
ンクリート杭とフーチングとの一体化工法の一実施例を
示す各工程の断面図であり、施工は順次第3図から第6
図の順に行なわれる。 第7図はこの発明の第2の実施例を示すもので、同図(
a )は断面図、同図(b)は杭の上面図である。 第8図は、この発明を場所打ち杭とフーチングとの一体
化に適用した第3の実施例を示す断面図である。 第9図は、この発明を地中連続壁とのフーチングの一体
化に適用した第4の実施例を示す断面図である。 10・・・・・・・・・・・・・・・PC用鋼材12・
・・・・・・・・・・・・・・コンクリート14・・・
・・・・・・・・・・・・PC抗16・・・・・・・・
・・・・・・・地中18・・・・・・・・・・・・・・
・杭頭部20・・・・・・・・・・・・・・・孔部22
・・・・・・・・・・・・・・・補強用鉄筋24・・・
・・・・・・・・・・i・フーチング26・・・・・・
・・・・・・・・・上端部28・・・・・・・・・・・
・・・・上端露出部30・・・・・・・・・・・・・・
・定着部32・・・・・・・・・・・・・・・定着具3
5・・・・・・・・・・・・・・・地中連続壁36・・
・・・・・・・・・・・・・デッドアンカー特許出願人
       株式会社 大 林 組代 理 人   
      弁理士 −色健輔第 11ふ′1 ’、:;2図 第7図 第9図
FIG. 1 and FIG. 2 are cross-sectional views showing a prestressed concrete pile and a footing formed by a conventional method. Figures 3 to 6 are cross-sectional views of each process showing an embodiment of the method of integrating prestressed concrete piles and footings according to the present invention.
This is done in the order shown. FIG. 7 shows a second embodiment of the present invention.
Figure a) is a cross-sectional view, and figure (b) is a top view of the pile. FIG. 8 is a sectional view showing a third embodiment in which the present invention is applied to the integration of a cast-in-place pile and a footing. FIG. 9 is a sectional view showing a fourth embodiment in which the present invention is applied to the integration of a footing with an underground continuous wall. 10... Steel materials for PC 12.
・・・・・・・・・・・・・・・Concrete 14...
・・・・・・・・・・・・PC anti-16・・・・・・・・・
・・・・・・Underground 18・・・・・・・・・・・・・・・
・Pile head 20・・・・・・・・・・・・ Hole 22
・・・・・・・・・・・・Reinforcement reinforcing bar 24...
・・・・・・・・・・i・Footing 26・・・・・・
......Top end portion 28...
...Top exposed portion 30...
・Fixing part 32...Fixing tool 3
5・・・・・・・・・・・・Underground continuous wall 36...
・・・・・・・・・・・・Dead Anchor Patent Applicant Obayashi Co., Ltd. Representative Person
Patent Attorney - Kensuke Shiro No. 11F'1':;2 Figure 7 Figure 9

Claims (1)

【特許請求の範囲】 (1)プレスi・レストコンクリート用鋼材を埋設した
プレストレストコンクリート杭 、場所打ち杭あるいは
地中連続壁とフーチングとを一体化する工法において、
該プレストレストコンクリート用鋼材の上端露出部にコ
ンクリートを打設して該フーチングを形成するとともに
該鋼材の端部を該フーチング上端より若干突出させ定着
部を形成し、該定着部内で定着具を用い該鋼材を緊張せ
しめプレストレスカを導入し、該プレストレストコンク
リート杭、場所打ち杭あるいは抗咳地中連続壁と該フー
チングとを一体化するようにしてなることを特徴とする
杭または連壁とフーチングとの一体化工法。 (2、特許請求の範囲第1項記載の工法において、前記
上端露出部を前記プレストレスI−コンクリー1〜杭の
上端部をカットオフして形成することを特徴とJる杭ま
た連壁とフーチングとの一体化工法。 (3)特許請求の範囲第1項記載の工法において、既存
のプレストレストコンクリート杭の上端部近傍に下方の
一部が埋設された連結プレス1〜レスト用鋼材を設は前
記上端露出部となすことを特徴とづる杭または連壁とフ
ーチングとの一体化工法。 (4)特許請求の範囲第1項記載の工法において、前記
プレストレストコンクリ−]・用鋼材の上端部を予め前
記プレストレストコンクリート杭、場所打ち抗あるいは
地中連続壁の上端より上方に突出した状態に配設し、前
記上端露出部となすことを特徴とする杭または連壁とフ
ーチングとの一体化工法。
[Scope of Claims] (1) In a construction method that integrates a prestressed concrete pile with embedded steel material for press i-rest concrete, a cast-in-place pile, or an underground continuous wall and a footing,
The footing is formed by pouring concrete onto the exposed upper end of the steel material for prestressed concrete, the end of the steel material is slightly protruded from the upper end of the footing to form a fixing section, and a fixing tool is used within the fixing section to form the footing. A combination of a pile or continuous wall and a footing, characterized in that the steel material is tensed and a prestressing force is introduced, and the footing is integrated with the prestressed concrete pile, cast-in-place pile, or anti-cough underground continuous wall. Integrated construction method. (2. The construction method according to claim 1, wherein the upper end exposed portion is formed by cutting off the upper end of the prestressed concrete 1 to pile. An integrated construction method with a footing. (3) In the construction method described in claim 1, a connecting press 1 whose lower part is buried near the upper end of an existing prestressed concrete pile to a steel material for rest are installed. A method of integrating a footing with a pile or a continuous wall in which the upper end is exposed. (4) In the construction method according to claim 1, the upper end of the prestressed concrete/steel material is A construction method for integrating a pile or a continuous wall with a footing, characterized in that the prestressed concrete pile, cast-in-place shaft, or continuous underground wall is arranged in a state that projects upward from the upper end thereof to form the upper end exposed part.
JP671283A 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing Granted JPS59134228A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP671283A JPS59134228A (en) 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP671283A JPS59134228A (en) 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing

Publications (2)

Publication Number Publication Date
JPS59134228A true JPS59134228A (en) 1984-08-01
JPH0243848B2 JPH0243848B2 (en) 1990-10-01

Family

ID=11645888

Family Applications (1)

Application Number Title Priority Date Filing Date
JP671283A Granted JPS59134228A (en) 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing

Country Status (1)

Country Link
JP (1) JPS59134228A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63233122A (en) * 1987-03-18 1988-09-28 Maeda Seikan Kk Combined structure of hollow concrete pile and footing having improved axial holding and horizontal deforming function
JPS6431138U (en) * 1987-08-18 1989-02-27
KR100444555B1 (en) * 2001-05-22 2004-08-18 주식회사 한가람 Reinforced Method of Head in a Prestressed Spun High Strength Concrete Pile
CN102493470A (en) * 2011-11-16 2012-06-13 中铁三局集团有限公司 Foundation treatment method for simulating rigidly enlarged foundation
JP5727652B1 (en) * 2014-06-23 2015-06-03 黒沢建設株式会社 Pile head seismic isolation structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55122916A (en) * 1979-03-16 1980-09-22 Kurosawa Kensetsu Kk Method for building prestressed concrete-made pier foundation

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55122916A (en) * 1979-03-16 1980-09-22 Kurosawa Kensetsu Kk Method for building prestressed concrete-made pier foundation

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63233122A (en) * 1987-03-18 1988-09-28 Maeda Seikan Kk Combined structure of hollow concrete pile and footing having improved axial holding and horizontal deforming function
JPS6431138U (en) * 1987-08-18 1989-02-27
KR100444555B1 (en) * 2001-05-22 2004-08-18 주식회사 한가람 Reinforced Method of Head in a Prestressed Spun High Strength Concrete Pile
CN102493470A (en) * 2011-11-16 2012-06-13 中铁三局集团有限公司 Foundation treatment method for simulating rigidly enlarged foundation
JP5727652B1 (en) * 2014-06-23 2015-06-03 黒沢建設株式会社 Pile head seismic isolation structure

Also Published As

Publication number Publication date
JPH0243848B2 (en) 1990-10-01

Similar Documents

Publication Publication Date Title
JP2007154413A (en) Soldier pile type earth retaining anchor type retaining wall and its construction method
JP2543667B2 (en) Rainwater storage tank
JPS59134228A (en) Integration work of pile or continuous wall and footing
JPH11222861A (en) Execution of retaining wall to existing banking and retaining wall executed by the same
JPH08177059A (en) Footing block, and integrated method for constructing continuous footing employing footing block
JPS61191715A (en) Method of building underground continuous wall in pile support building having underground floor and cast-in-place concrete pile
JPS59192145A (en) Fixing of iron pillar
JP2579120B2 (en) garage
JPS63280153A (en) Underground inverted lining method
JPH08199565A (en) Pile head joint construction of cast-in-place concrete pile
JP2555838B2 (en) Independent panel mountain retaining method
JPH11181807A (en) Construction method for underground story
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JPH10131300A (en) Execution method for building by preceding erection of steel frame
JPS6135359B2 (en)
JPH04185816A (en) Construction of beam in underground wall
JP2520364B2 (en) Construction method of underground structure
JP2000303465A (en) Method for retaining earth by low strength underground wall
JPS6140812B2 (en)
JP2000291146A (en) Joint structure of pile head and column, and construction method therefor
JPS58199925A (en) Construction of underground wall and underground foundation pile with brace
JPH0447021A (en) Construction method for sheathing guide pile
JP2555837B2 (en) Construction method of underground structure by upside down construction method
JPS59224723A (en) Breaking and cutting of concrete
JPS63184620A (en) Water-proofing work for underground outer wall