JPS55122916A - Method for building prestressed concrete-made pier foundation - Google Patents

Method for building prestressed concrete-made pier foundation

Info

Publication number
JPS55122916A
JPS55122916A JP3072679A JP3072679A JPS55122916A JP S55122916 A JPS55122916 A JP S55122916A JP 3072679 A JP3072679 A JP 3072679A JP 3072679 A JP3072679 A JP 3072679A JP S55122916 A JPS55122916 A JP S55122916A
Authority
JP
Japan
Prior art keywords
pier foundation
foundation
tension
footing
sheaths
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3072679A
Other languages
Japanese (ja)
Inventor
Ryohei Kurosawa
Hiroshi Terunuma
Fumiya Oosugi
Keizo Tanabe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurosawa Construction Co Ltd
Original Assignee
Kurosawa Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurosawa Construction Co Ltd filed Critical Kurosawa Construction Co Ltd
Priority to JP3072679A priority Critical patent/JPS55122916A/en
Publication of JPS55122916A publication Critical patent/JPS55122916A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE: To provide a method for building robust pier foundation wherein high resistance against upward vertical load and horizontal shearing force are obtained through prestress which is provided by passing tension member through pier foundation, thus preventing buildings from collapsing for lack of durability of foundation.
CONSTITUTION: While pushing steel pipe 1 in the ground, inner earth and sand are dug out to form pier foundation hole 10, into which cage-shaped rods 5 for foundation pile are inserted. In this case, cage-shaped rods are prefitted with sheaths 6 in the longitudinal direction. Then, tension member 7 after being inserted into the sheath 6 is fitted with anchor plate at its lower end and temporarily fixed at its upper end. Concrete is placed in the hole 10 to form pier foundation pole 3, on which footing 4 and surface pole 9 are built. After applying a given prestress through tension of the tension material 7 on the upper end of the footing 4, the end is fitted to the pressure supporting plate 16 and grout is poured in sheaths 6.
COPYRIGHT: (C)1980,JPO&Japio
JP3072679A 1979-03-16 1979-03-16 Method for building prestressed concrete-made pier foundation Pending JPS55122916A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3072679A JPS55122916A (en) 1979-03-16 1979-03-16 Method for building prestressed concrete-made pier foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3072679A JPS55122916A (en) 1979-03-16 1979-03-16 Method for building prestressed concrete-made pier foundation

Publications (1)

Publication Number Publication Date
JPS55122916A true JPS55122916A (en) 1980-09-22

Family

ID=12311652

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3072679A Pending JPS55122916A (en) 1979-03-16 1979-03-16 Method for building prestressed concrete-made pier foundation

Country Status (1)

Country Link
JP (1) JPS55122916A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5758724A (en) * 1980-09-27 1982-04-08 Takechi Koumushiyo:Kk In-situ prestressed concrete pile construction work
JPS59134228A (en) * 1983-01-20 1984-08-01 Ohbayashigumi Ltd Integration work of pile or continuous wall and footing
JPS6110622A (en) * 1984-06-26 1986-01-18 Hasegawa Komuten Co Ltd Method of constructing cast-in-place concrete pile
EP0793754A1 (en) * 1994-11-23 1997-09-10 Allan P.. Henderson Tensionless pier foundation
KR100899372B1 (en) 2007-07-13 2009-05-26 김정인 Connection method of micropile cap to existing concrete footing structure, reinforced method using same and structure thereof
US7618217B2 (en) 2003-12-15 2009-11-17 Henderson Allan P Post-tension pile anchor foundation and method therefor
CN102797263A (en) * 2012-08-27 2012-11-28 中国建筑第六工程局有限公司 Method for preparing replacement reducer single-pier composite foundation with reinforcing net sheets
CN104264667A (en) * 2014-09-10 2015-01-07 中建四局第六建筑工程有限公司 Construction method for pre-stress bamboo joint piles
CN104674833A (en) * 2015-03-24 2015-06-03 北京中水新能工程技术有限公司 Center entire-pressed infrastructure
ES2761655A1 (en) * 2018-11-19 2020-05-20 Nabrawind Tech Sl Foundation for a wind turbine tower (Machine-translation by Google Translate, not legally binding)
CN113863291A (en) * 2021-10-21 2021-12-31 中建三局集团有限公司 Novel construction method of unbonded prestressed poured uplift pile

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5758724A (en) * 1980-09-27 1982-04-08 Takechi Koumushiyo:Kk In-situ prestressed concrete pile construction work
JPS6319650B2 (en) * 1980-09-27 1988-04-23 Takechi Komusho Kk
JPS59134228A (en) * 1983-01-20 1984-08-01 Ohbayashigumi Ltd Integration work of pile or continuous wall and footing
JPH0243848B2 (en) * 1983-01-20 1990-10-01 Obayashi Constr Co Ltd
JPS6110622A (en) * 1984-06-26 1986-01-18 Hasegawa Komuten Co Ltd Method of constructing cast-in-place concrete pile
EP0793754A4 (en) * 1994-11-23 2000-01-12 Allan P Henderson Tensionless pier foundation
EP0793754A1 (en) * 1994-11-23 1997-09-10 Allan P.. Henderson Tensionless pier foundation
US7618217B2 (en) 2003-12-15 2009-11-17 Henderson Allan P Post-tension pile anchor foundation and method therefor
KR100899372B1 (en) 2007-07-13 2009-05-26 김정인 Connection method of micropile cap to existing concrete footing structure, reinforced method using same and structure thereof
CN102797263A (en) * 2012-08-27 2012-11-28 中国建筑第六工程局有限公司 Method for preparing replacement reducer single-pier composite foundation with reinforcing net sheets
CN104264667A (en) * 2014-09-10 2015-01-07 中建四局第六建筑工程有限公司 Construction method for pre-stress bamboo joint piles
CN104674833A (en) * 2015-03-24 2015-06-03 北京中水新能工程技术有限公司 Center entire-pressed infrastructure
ES2761655A1 (en) * 2018-11-19 2020-05-20 Nabrawind Tech Sl Foundation for a wind turbine tower (Machine-translation by Google Translate, not legally binding)
CN113863291A (en) * 2021-10-21 2021-12-31 中建三局集团有限公司 Novel construction method of unbonded prestressed poured uplift pile
CN113863291B (en) * 2021-10-21 2023-03-03 中建三局集团有限公司 Construction method of unbonded prestressed poured uplift pile

Similar Documents

Publication Publication Date Title
CA2036832C (en) Pinned foundation system
EP2698476B1 (en) Method for the construction of an offshore structure and foundation for an offshore structure
US4293242A (en) Piles
US5050356A (en) Immured foundation
JPS55122916A (en) Method for building prestressed concrete-made pier foundation
US7993079B2 (en) Device and method for a tower reinforcing foundation
US3992890A (en) Method of forming foundations
JPS6149029A (en) Underwater foundation fixer
JP3054635B2 (en) Construction method of attached structure
US4999966A (en) Method of forming an-before "immured"
CN210066763U (en) Foundation pit side wall structure reinforcing and supporting device
JPH0367168B2 (en)
RU2464381C2 (en) Prestressed shallow foundation
KR0138260Y1 (en) Rock anchor structure for transmission tower
JPH0355612B2 (en)
CN107642083A (en) Post-tensioned prestressing continuous underground wall structure and construction method with pull bar
RU2063497C1 (en) Method for erecting foundation
GB2289494A (en) Improvements in or relating to foundations
CN1087051C (en) Technology for constructing foundation of artificially composite ground piles
JP3099040B2 (en) Embankment culvert
RU2056478C1 (en) Method for reinforcing bases and foundations on sagging ground in hindered conditions
JPS56125528A (en) Construction of in-situ driven pile
JPS56111725A (en) Constructing method for strip footing by using existing concrete pile
RU2045627C1 (en) Wall of underground structure
JPS5648413A (en) Harbor structure such as quay wall on a cement blended foundation and construction method thereof