JPH0492006A - Setting temporary bridge of hanging structure - Google Patents

Setting temporary bridge of hanging structure

Info

Publication number
JPH0492006A
JPH0492006A JP20755690A JP20755690A JPH0492006A JP H0492006 A JPH0492006 A JP H0492006A JP 20755690 A JP20755690 A JP 20755690A JP 20755690 A JP20755690 A JP 20755690A JP H0492006 A JPH0492006 A JP H0492006A
Authority
JP
Japan
Prior art keywords
towers
temporary
cables
tower
span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP20755690A
Other languages
Japanese (ja)
Inventor
Akinobu Kishi
明信 岸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP20755690A priority Critical patent/JPH0492006A/en
Publication of JPH0492006A publication Critical patent/JPH0492006A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To obtain long spans by a method in which a module having temporary towers is provided on both or one side of existing road and three- dimensional crossings are hung down by cables(skew supporters) attached to the tower to form an over bridge. CONSTITUTION:Towers 1 are set on the three-dimensional crossings of modular approach parts M1, M2,..., and back stay cables 2 are attached to the approach side. The three-dimensional crossings 3 are hung down from the towers 1 by stain cables 4. The towers 1 are set on one side or both sides to make the span longer, and the support span is adjusted by the height of the tower 1. The cables 14 are used for sliding of beams from the towers 1 and connected with pins 15 to prevent the transmission of bending moment. The temporary bridge of long span can thus be set in a short time.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、−時的に道路を横断して輸送路或いは、通行
路を確保するために構築される仮橋の設置方法に関する
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for installing a temporary bridge that is constructed to secure a transportation route or a traffic route by occasionally crossing a road.

〔従来の技術] 既設道路の通行を阻害するため、作業区域の設定を行な
い、交通規制を行なうことにより対処し。
[Prior art] In order to obstruct traffic on existing roads, work areas are set up and traffic regulations are implemented.

ていた、工事が長期に継続される場合には、永久構造物
とし7での固定橋を設置、或いは、別ルートの道路を建
設していた。
If the construction work was to continue for a long time, a fixed bridge would be installed as a permanent structure, or a separate road route would be constructed.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

従来の方法では、通行が阻害され交通渋滞が起こり、ク
レームの原因となる。又、別ルー[を確保するため、新
しい道路を建設するため、工事を着工するまで長期の準
備期間を要す。
Traditional methods obstruct traffic and cause traffic congestion, which can lead to complaints. Additionally, in order to secure a separate route, a new road will be constructed, which will require a long preparation period before construction can begin.

仮橋を設置する場合でも、その設置・解体に一般橋梁工
事の同程度の大規模な規制が必要となると同時に、多大
な費用が発生する。
Even when a temporary bridge is installed, its installation and dismantling require the same large-scale regulations as for general bridge construction, and at the same time, large costs are incurred.

又、従来の仮橋では、小スパンに制限されていた。Furthermore, conventional temporary bridges are limited to small spans.

〔課題を解決するための手段〕[Means to solve the problem]

立体交差部を適当な長さ(15m〜20m)に分割した
モジュールの脚に伸縮機構を設けることにより、輸送可
能な寸法とする0位置決めは、モジュールに駆動装置を
設けて自走式にするが、トレーラ−等の台車にモジュー
ルを搭載し、所定の位置まで運ぶ方式のいづれかとする
Zero positioning is achieved by providing a telescopic mechanism on the legs of a module that divides an overpass into appropriate lengths (15m to 20m) to make it transportable. The module is mounted on a trolley such as a trailer and transported to a predetermined location.

立体交差部は、短期間に安全に設置できるよう、両側モ
ジュールに搭載された面材パネルを張り出す張り出し2
架設丁法を採用スる。
Overhangs 2 are used to overhang the facing panels mounted on the modules on both sides of the grade-separated intersections so that they can be installed safely in a short period of time.
Adopt the construction method.

立体交差部を長スパン化及び軽量化するため、立体交差
部を吊構造とする。
In order to make the intersection longer and lighter, the intersection will have a suspended structure.

[作 用] 仮橋設備を吊構造とし、梁構するに際し5で吊橋或は斜
張橋の架設工法を適用することにより、仮橋の支間長を
長大化すると共に、架設の簡略化を実現できる。
[Function] By making the temporary bridge equipment a suspended structure and applying the construction method of suspension bridges or cable-stayed bridges in step 5 when constructing the beams, the span length of the temporary bridge can be increased and the construction can be simplified. can.

〔実施例〕〔Example〕

仮橋は、第1図、第2図で示す欅に、モジュールM 1
. M t〜7化したアプローチ部の立体交差部側に簡
易に設置ごきるタワー1を設置(図では、可倒式として
いるが、組立方式も可)し、アプローチ側にバックステ
ーケーブル2を取付け、立体交差部3は1.タワーlよ
りステーケーブル4により品り構造とする。
The temporary bridge has module M1 on the keyaki shown in Figures 1 and 2.
.. Install tower 1, which can be easily installed, on the side of the grade-separated intersection of the Mt~7 approach section (in the figure, it is shown as a collapsible type, but an assembled method is also possible), and backstay cable 2 is installed on the approach side. , the overpass 3 is 1. The structure is made up of stay cables 4 from tower l.

第1図は両側にタワー・1を設置した場合、第2図は片
側に設置した場合で、両側に設置した力が長スパン化で
きる。また、タワーの高さを#J!1節づる事により支
間長を調整できる。
Figure 1 shows the case where the tower 1 is installed on both sides, and Figure 2 shows the case where it is installed on one side, and the force installed on both sides can be extended over a long span. Also, set the height of the tower to #J! The span length can be adjusted by twisting one knot.

千ジ1−ル部は、運転部11、駆動輪12を備えた自走
式或いは、トレーラ等搬走台申により所定値iにセット
される。
The 1,000-wheel unit is set to a predetermined value i by a self-propelled vehicle equipped with a driving unit 11 and drive wheels 12 or a transport platform such as a trailer.

桁13の送り出L2に関し5ては、タワーlより々−プ
ル14を利用し2桁1(1べらセで(第3図)架設する
。桁とおしは、ピン15結合とし2、曲げモーメントの
伝達は行なわない。
Regarding the sending out L2 of the girder 13, the two girders 1 (1 spring (Fig. 3)) are erected using the vertical pull 14 from the tower l.The girder and the girder are connected with pins 15. No transmission will take place.

第4回、第5図に塔(タワー)の架設方法を示す。短時
間に架設を行なうため、第4図ごはタワー1をモジュー
ルMにビン結合6さセジャッキ5により押し上げて直ケ
さセる。第5図では直方体ブロック7を、積み重ねる方
法で、圧mにたいしては、メタルタッチにより引張りに
は引張ボルト8を作用さゼ抵抗させる(第6図)、なお
、16は引張ボルト用はかま構造である。
Part 4, Figure 5 shows how to construct a tower. In order to carry out erection in a short time, as shown in FIG. 4, the tower 1 is directly mounted on the module M by pushing it up using a jack 5 through a bottle coupling 6. In Fig. 5, the rectangular parallelepiped blocks 7 are stacked, and the tension bolt 8 is applied to resist the pressure m by metal touch (Fig. 6). Note that 16 is a hook structure for the tension bolt. .

第7図はう一プル4の定着構造を示したもので、桁のウ
ェブ面10に2個の平行にすき間を明けた定着ブロック
9を設置しておき、ケーブル4を桁の外側から着脱をi
iJ能にする。
Figure 7 shows another fixing structure for the pull 4. Two fixing blocks 9 with a gap are installed in parallel on the web surface 10 of the girder, and the cable 4 can be attached and detached from the outside of the girder. i
Make it into iJ Noh.

なお、17はケーブル4の端部に固着したソゲットであ
る。
Note that 17 is a soget fixed to the end of the cable 4.

〔発明の効果〕〔Effect of the invention〕

本発明による吊り構造仮橋設置方法は、既設の道路・鉄
道を横断(オーバーブリ゛ンジ)する仮設の立体交差部
を構築するに当り、既存道路等の両側或いは片側に仮設
タワーを有するモジュールを設置し、仮設タワーに取付
けられたケーブル(斜支柱)により、立体交差部を吊り
下げ支持することにより、次の効果を有する。
The suspension structure temporary bridge installation method according to the present invention, when constructing a temporary grade-separated intersection that crosses (overbridges) an existing road or railway, installs a module having temporary towers on both sides or one side of the existing road, etc. The following effects can be achieved by suspending and supporting the grade-separated intersection using cables (diagonal struts) installed and attached to the temporary tower.

(1)短時間で長径間の仮橋を設置する事ができ、短丈
間から長点間まである程度自由度がある。
(1) Long span temporary bridges can be installed in a short time, and there is a certain degree of freedom from short lengths to long spans.

(2)また、設置において長時間の交通規制が不要であ
り、高さ制限がない場所では、非常に効果的である。
(2) Furthermore, the installation does not require long-term traffic control, and is very effective in locations where there are no height restrictions.

(3)立体交差部を吊構造としたことにより、長スパン
化及び軽量化が可能である。
(3) By using a suspension structure for the overpass, it is possible to lengthen the span and reduce the weight.

【図面の簡単な説明】[Brief explanation of drawings]

第1図(a)は本発明の第1実施例を示す全体側面図、
第1図働)は走行時のモジュールを示す側面図、第2図
は第2実施fNl(1本タワー)の全体t111面図、
。 第3回は桁送り出し方法の説明図、第4回は夕・ノー架
設方法(ビン方式)の説明図、第5図はタワー架設方法
(ブロック方式)の説明図、第6図(a)はブロック方
式における結合方法を示す斜視図、第6図(b)は引張
ボルトによる結合部分の拡大回、第7図はケーブル定着
構造の斜視図である。
FIG. 1(a) is an overall side view showing a first embodiment of the present invention;
Figure 1 (work) is a side view showing the module during running, Figure 2 is an overall t111 side view of the second implementation fNl (one tower),
. Part 3 is an explanatory diagram of the girder feeding method, Part 4 is an explanatory diagram of the evening/no erection method (bin method), Figure 5 is an explanatory diagram of the tower erection method (block method), and Figure 6 (a) is an explanatory diagram of the tower erection method (block method). FIG. 6(b) is an enlarged view of a connecting portion using a tension bolt, and FIG. 7 is a perspective view of a cable fixing structure.

Claims (1)

【特許請求の範囲】[Claims] 既設の道路・鉄道を、横断(オーバーブリッジ)する仮
設の立体交差部を、構築するに当り、既存道路等の両側
或いは、片側に仮設タワーを有するモジュールを設置し
、仮設タワーに取付けられたケーブル(斜支材)により
、立体交差部を、吊り下げ支持することを特徴とする吊
り構造仮橋設置方法。
When constructing a temporary grade crossing that crosses (overbridges) existing roads and railways, modules with temporary towers are installed on both sides or one side of the existing road, etc., and cables attached to the temporary towers are installed. A suspension structure temporary bridge installation method characterized by suspending and supporting an elevated intersection using (diagonal supports).
JP20755690A 1990-08-07 1990-08-07 Setting temporary bridge of hanging structure Pending JPH0492006A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20755690A JPH0492006A (en) 1990-08-07 1990-08-07 Setting temporary bridge of hanging structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20755690A JPH0492006A (en) 1990-08-07 1990-08-07 Setting temporary bridge of hanging structure

Publications (1)

Publication Number Publication Date
JPH0492006A true JPH0492006A (en) 1992-03-25

Family

ID=16541695

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20755690A Pending JPH0492006A (en) 1990-08-07 1990-08-07 Setting temporary bridge of hanging structure

Country Status (1)

Country Link
JP (1) JPH0492006A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006065041A1 (en) * 2004-12-13 2006-06-22 Leton Bridge Co., Ltd Temporary bridge of a cable-stayed girder bridge type with a long span
KR100660104B1 (en) * 2004-09-21 2006-12-26 (주)리튼브릿지 Long-distance-pier temporary bridge using stayed cable
JP2016108873A (en) * 2014-12-03 2016-06-20 財團法人國家實驗研究院National Applied Research Laboratories Lightweight simple bridge and building method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100660104B1 (en) * 2004-09-21 2006-12-26 (주)리튼브릿지 Long-distance-pier temporary bridge using stayed cable
WO2006065041A1 (en) * 2004-12-13 2006-06-22 Leton Bridge Co., Ltd Temporary bridge of a cable-stayed girder bridge type with a long span
JP2016108873A (en) * 2014-12-03 2016-06-20 財團法人國家實驗研究院National Applied Research Laboratories Lightweight simple bridge and building method thereof

Similar Documents

Publication Publication Date Title
CN101418543B (en) Self-anchored rope-suspension bridge inclined drawing construction method
JP2003193430A (en) Construction method of composite truss bridge
JPH06341110A (en) Skeleton structure type bridge and method of installation construction thereof
CN108505405B (en) Combined construction structure of suspension type monorail and highway bridge
JP3440422B2 (en) Bridge construction method and bridge construction device
JP2008025195A (en) Construction method of cable-stayed bridge
JP2000096819A (en) Temporary construction method of working scaffold for pedestrian bridge, overhead line beam and the like
JP2010031607A (en) Construction method for grade separation
CN105464007B (en) A kind of folding plane girder in longitudinal direction and its application process
JPH0492006A (en) Setting temporary bridge of hanging structure
JP2004183433A (en) Box girder bridge structure and its construction method
CN110528342A (en) Suspension type combines track
CN212895958U (en) Lower hanging movable bridge floor crane
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN205591115U (en) Suspension type catwalk veil installing the system
CN211815605U (en) Construction device for pile column type pier tie beam and capping beam
CN212315371U (en) Cable installation lifting device for cable-stayed bridge
JP3349463B2 (en) How to install additional girder
WO2020075511A1 (en) Mobile scaffold installation method
CN108252170B (en) Level crossing bridge applied to level crossing at road center
CN113957755A (en) Medium-low speed magnetic levitation traffic combined U-shaped beam structure
CN108221527B (en) Level crossing bridge applied to left-turning road in road center
CN112160246A (en) Method for mounting combined beam
JP2911011B2 (en) Construction method of non-stiffened suspension pipe bridge
CN111472285A (en) Method for mounting main bridge variable-section continuous steel truss girder by using cable crane