JPH0489938A - Liftup device installing method for truss lifting construction method and truss joining method - Google Patents
Liftup device installing method for truss lifting construction method and truss joining methodInfo
- Publication number
- JPH0489938A JPH0489938A JP20249290A JP20249290A JPH0489938A JP H0489938 A JPH0489938 A JP H0489938A JP 20249290 A JP20249290 A JP 20249290A JP 20249290 A JP20249290 A JP 20249290A JP H0489938 A JPH0489938 A JP H0489938A
- Authority
- JP
- Japan
- Prior art keywords
- truss
- joining
- bracket
- attached
- temporary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 21
- 238000010276 construction Methods 0.000 title abstract description 11
- 238000009434 installation Methods 0.000 claims description 5
- 239000000463 material Substances 0.000 description 21
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 239000004035 construction material Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000004026 adhesive bonding Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【発明の詳細な説明】
[産業上の利用分野]
本発明は、例んば張弦梁やトラス梁等の架構材を吊り上
げて建物の柱や耐力壁等の支持構造体に一体的に接合す
るリフトアップ工法における吊上装置の取付方法および
架構材の接合方法に関する。[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a lift that lifts a structural member such as a stringed beam or a truss beam and integrally connects it to a supporting structure such as a building column or load-bearing wall. The present invention relates to a method for attaching a lifting device and a method for joining frame members in the up construction method.
[従来の技術1
従来、この種のり7ト7ツプエ法において、架構材の吊
り上げ箇所に仮設の支柱等を設置し、これに吊上装置を
取り付けて、架構材のリフトアップを行っていた。[Prior art 1] Conventionally, in this type of gluing method, a temporary support or the like was installed at the point where the frame member was to be lifted, and a lifting device was attached to this to lift up the frame member.
しかしながら、上記り7トア7プエ法は、gi設支柱の
設置に多大の費用と時間を要し、施工が複雑かつ大がか
りなものとなってしまう等の問題点があった。However, the above-mentioned 7 tor 7 pue method requires a great deal of cost and time to install the GI support, and has problems such as making the construction complicated and large-scale.
[発明が解決しようとする課題1
本発明は、上記従来の問題点を解決するためになされた
もので、その目的とするところは、仮設材使用量を極力
少なくすることにより、工期と費用の低減を図ることの
できる架構材のリフトアップ工法における吊上装置の取
付方法および架構材の接合方法を提供するものである。[Problem to be solved by the invention 1 The present invention has been made to solve the above-mentioned conventional problems, and its purpose is to reduce the construction period and cost by minimizing the amount of temporary construction materials used. The present invention provides a method for attaching a lifting device and a method for joining frame members in a lift-up construction method for frame members, which can reduce the amount of damage.
[課題を解決するための手段1
本発明の架構材のり7トアツプエ法における吊上装置の
取付方法は、梁等の架構材を吊り上げて建物の柱や耐力
壁等の支持構造体に一体的に接合するり7トアツプエ法
において、上記架構材の接合端部にブラケットを側方に
張り出すように取り付けると共に、該ブラケットに吊ワ
イヤーやロッド等の引張材を取り付け、一方、上記支持
構造体の接合端部にもブラケットを側方に張り出すよう
に取り付けて、その上に吊上用ジャッキ等の吊上手段を
設置し、該吊上手段により引張材を引き上げるようにし
たことを特徴とする。[Means for Solving the Problems 1] The method for attaching a lifting device in the frame material glue 7-to-pue method of the present invention is to lift a frame material such as a beam and integrally attach it to a supporting structure such as a building column or load-bearing wall. In the joining method, a bracket is attached to the joint end of the above-mentioned frame member so as to project laterally, and a tension member such as a hanging wire or rod is attached to the bracket, while the above-mentioned support structure is joined. The present invention is characterized in that a bracket is also attached to the end so as to project laterally, a lifting means such as a lifting jack is installed on the bracket, and the tension member is pulled up by the lifting means.
また、本発明の架構材のり7トアツプエ法における架構
材の接合方法は、梁等の架構材を吊り上げて建物の柱や
耐力壁等の支持構造体に一体的に接合するリフトアップ
工法において、上記架構材と支持構造体の接合端部に仮
プレートを取り付けて、本設プレートの取り付け完了ま
で仮接合することを特徴とする。上記仮プレートのボル
ト穴はルーズホールとし、また、上記架構材と支持構造
体の接合端部のボルト穴を予め正規の位置にあけ、本設
プレートのボルト穴は上記正規位置のボルト穴に現場突
き合わせてあける。In addition, the method for joining frame members using the 7-to-pue method for bonding frame members of the present invention is the above-mentioned lift-up method in which a frame member such as a beam is lifted up and integrally joined to a supporting structure such as a building column or load-bearing wall. A temporary plate is attached to the joint end of the frame member and the support structure, and the temporary joint is continued until the installation of the permanent plate is completed. The bolt holes in the above temporary plate should be loose holes, and the bolt holes at the joint end of the above frame material and supporting structure should be pre-drilled in the correct positions, and the bolt holes in the permanent plate should be made into the bolt holes in the above normal positions. Butt them together and open them.
[実施例]
以下、本発明の一実施例について図面を参照しながら説
明する。[Example] Hereinafter, an example of the present invention will be described with reference to the drawings.
第1図において、1は支持構造体であって、柱や耐力壁
等のように屋根等の架設構造体の荷重を支える支持躯体
である。該支持構造体1上には受け)ラス2が設置され
ている。該受はトラス2は、主として2本の傾斜材2a
と、屋根を受ける頂梁材2bとから構成されている。2
本の傾斜材2aの下端部は、上記支持構造体1の上端部
にビン接合により回転自在に枢着されていると共に、上
記頂梁材21)の両端部も、各傾斜材2aの頂部にビン
接合により回転自在に枢着されていて、全体として三角
形に組んだトラ入構造を成している。In FIG. 1, reference numeral 1 denotes a support structure, which is a support framework such as columns and load-bearing walls that supports the load of an erected structure such as a roof. A support lath 2 is installed on the support structure 1. The bridge truss 2 mainly consists of two inclined members 2a.
and a top beam member 2b that receives the roof. 2
The lower end of the book slant member 2a is rotatably pivoted to the upper end of the support structure 1 by means of a bottle joint, and both ends of the top beam member 21) are also attached to the top of each slant member 2a. It is rotatably connected by a pin joint, and has a triangular truss structure as a whole.
上記支持構造体1111の接合端部、すなわち受はトラ
ス2の頂梁材2bの接合端部は、第2図に示すように、
H型鋼のウェブ部を段状に切欠いて、その中矢切矢部に
仮プレー)2cを一体的に取り付け、該仮プレー)2e
に接合用ボルト穴2c’ をあけると共に、上下の7ラ
ンノ部に接合用ボルト穴2b’ をあけておく。As shown in FIG.
The web portion of the H-shaped steel is notched in steps, and a temporary play) 2c is integrally attached to the middle arrow cut portion, and the temporary play) 2e is cut out.
At the same time, drill bolt holes 2c' for joining, and make bolt holes 2b' for joining at the upper and lower 7 run sections.
尚、本実施例における上記受はトラス2は、架構材とし
ての張弦梁3を接合する部材として機能するので、−本
発明における支持構造体1と同じ概念に含まれる。Incidentally, since the truss 2 in this embodiment functions as a member for joining the stringed beam 3 as a frame member, it is included in the same concept as the support structure 1 in the present invention.
再び、第1図において、3は張弦梁であって、上記支持
構造体1の開の地El:設置された仮設台4tで、主と
してアーチ状の大梁材3aと張弦材3bと補助材3cを
地組みして構成される。この際、屋根下地材も取り付け
る。該大梁材3aは、後述するようにリフトアップ後、
上記受はトラス2の頂梁材2bの内端部に接合固定され
て、全体としてアーチ状の屋根を構成するようになって
いる。Again, in FIG. 1, reference numeral 3 is a stringed beam, and on the open ground El of the support structure 1: a temporary stand 4t installed, the arch-shaped girder 3a, the stretched stringed material 3b, and the auxiliary material 3c are assembled into the ground. It is composed of At this time, the roof underlayment will also be installed. After the girder material 3a is lifted up as described later,
The bridge is fixedly connected to the inner end of the top beam member 2b of the truss 2, thereby forming an arch-shaped roof as a whole.
(第8図参照)
また、上記張弦材3bは、上記大梁材3aの両端部に接
続して、これを弓形に張っている。さらに、上記補助材
3cは、上記大梁材3aと張弦材3bとの開に介在して
、該張弦梁3を補強している。(See FIG. 8) The string members 3b are connected to both ends of the girder member 3a, and are stretched in an arcuate shape. Furthermore, the auxiliary material 3c is interposed between the girder material 3a and the stringed material 3b to reinforce the stringed beam 3.
上記張弦梁3の接合端部、すなわち大梁材3aの端部も
、第2図に示すように、H型鋼のウェブ部を段状に切欠
いて、その中大切矢部に仮プレー)3dを一体的に取り
付け、該仮プレー)3dに接合用ボルト穴3d’ をあ
けると大に、上下の7ランノ部に接合用ボルト穴3a’
をあけておく。The joint end of the above-mentioned stringed beam 3, that is, the end of the girder material 3a, is also made by cutting out the web part of the H-shaped steel in a step shape, and integrally attaching a temporary plate (3d) to the center arrow part, as shown in Fig. 2. When the bolt hole 3d' for connection is made in 3d (for installation and temporary play), the bolt hole 3a' for connection is made in the upper and lower 7 run sections.
Leave it open.
尚、この張弦梁3の組立ては、上記支持構造体1や受は
トラス2の構築と並行して行ってもよい。Incidentally, the assembly of the stringed beam 3 may be performed in parallel with the construction of the support structure 1 and the truss 2.
張弦梁3の組立てが完了すると、第3図に示すように、
その両端部に吊ワイヤーやロッド等の弓張材5を取り付
け、該引張材5の上部を上記受はトラス2の内端上部に
取り付けた吊上用ツヤ7キ6に取り付けて、吊り上げる
。尚、上記仮設台4は適宜撤去しておく。When the assembly of the stringed beam 3 is completed, as shown in Fig. 3,
A bow tension member 5 such as a hanging wire or rod is attached to both ends of the tension member 5, and the upper part of the tension member 5 is attached to a lifting shear 7 attached to the upper inner end of the truss 2 to lift it up. Incidentally, the temporary stand 4 is removed as appropriate.
第4図および第5図は上記引張材5および吊上用ジヤツ
キ6を拡大して詳細に示すもので、上記張弦梁3の大梁
材3aの先端7ランノ下部に1ラケント7を側方に張り
畠すように取り付け、このブラケット7に上記引張材5
の下端部を取り付けるようになっている。従って、引張
材5は、張弦梁3の大梁材3aおよび受はトラス2の頂
梁材2bを避けるようにして、該頂梁材2bの先端7ラ
ンノ部上に側方に張り出すように取り付けたブラケット
8上の吊上用ジャッキ6に取り付けられる。4 and 5 show enlarged details of the tensile member 5 and the lifting jack 6, in which a racket 7 is stretched laterally at the bottom of the end 7 run of the girder 3a of the strung beam 3. Attach the tension member 5 to this bracket 7.
It is designed to attach the lower end of the. Therefore, the tension member 5 is attached to the main beam member 3a of the stringed beam 3 and the bridge member so as to avoid the top beam member 2b of the truss 2, and to project laterally over the tip 7 run portion of the top beam member 2b. It is attached to the lifting jack 6 on the bracket 8.
上記リフトアップ作業に際しては、wJ3図に示すよう
に、上記受はトラス2の外端部と基盤9との開にバック
ステー10を張設して、吊上げ時の受はトラス2の変位
を制御してバランスをとるようになっている。During the lift-up work, as shown in Fig. wJ3, the backstay 10 is stretched between the outer end of the truss 2 and the base 9, and the support controls the displacement of the truss 2 during lifting. It's designed to balance things out.
張弦梁3を所定の接合位置にり7トアツプしたら、第6
図に示すように、上記仮プレー)2c、3a同士をボル
トにより仮#C会する。この場合、第2図に示すように
、ボルト穴2c′、3d′ を大きくして数を少なくす
ると共に、ルーズホールとして、迅速かつ強力な接合が
出来るようにする。After placing the stringed beam 3 at the specified joint position and pulling it up 7 times, the 6th
As shown in the figure, the above provisional play) 2c and 3a make a provisional #C meeting with each other using bolts. In this case, as shown in FIG. 2, the bolt holes 2c' and 3d' are enlarged to reduce the number of bolt holes, and are used as loose holes to enable quick and strong joining.
仮接合が完了したら、吊上用ジャッキ6を撤去し、本接
合を行う。After the temporary bonding is completed, the lifting jack 6 is removed and the final bonding is performed.
本接合は、第7図に示すように、H型鋼から成る上記頂
梁材2bと大梁材3aの7ランノ部分を本設プレート1
1により上下から挟んでボルトにより締め付け固定して
、第8図に示すように、張弦梁による大架構建物を構築
する。As shown in Fig. 7, the main joining is to connect the 7 run portions of the top beam material 2b and main beam material 3a made of H-shaped steel to the main plate 1.
1, sandwich it from above and below and tighten and fix it with bolts to construct a large frame building made of stringed beams, as shown in FIG.
この際、第2図に示すように、上記頂梁材2bと大梁材
3aの7ランノ部分にはボルト穴2b’3a’ を予め
正規の位置にあけておき、本設プレート11のボルト穴
は現場突き合わせであけるようにする。At this time, as shown in FIG. 2, bolt holes 2b'3a' are pre-drilled at the proper positions in the 7-run portions of the top beam material 2b and main beam material 3a, and the bolt holes in the main plate 11 are It will be possible to open it at the site.
尚、引張材支持部材の取り付け位置としては、上記仮プ
レート3dの下側であってもよい。Note that the tensile material support member may be attached below the temporary plate 3d.
[発明の効果]
])’/7)7ノブエ法における仮設資材の使用量を低
減することにより、工費および工期の低減を図ることが
できる。[Effects of the Invention] ])'/7) 7 By reducing the amount of temporary construction materials used in the Nobue method, it is possible to reduce construction costs and construction period.
2)本設部材を使用することで、す7トアツプ設備の簡
素化ならびに取付作業の簡略化による全体の省力化が可
能となる。2) By using the main components, it is possible to simplify the top-up equipment and to simplify the installation work, thereby saving overall labor.
3)為所作業量が減るため安全性が向上する。3) Safety is improved because the amount of labor required is reduced.
4)仮接合部材を使用することにより、次のような効果
が期待できる。4) By using the temporary bonding member, the following effects can be expected.
a、鉄骨部材間のボルト接合時に、無理な力を加える事
なく接合が可能である。a. When bolting steel members together, it is possible to do so without applying excessive force.
60本締め作業に余分な労力や位置補正のための過大な
外力を必要としない。There is no need for extra labor or excessive external force for position correction for 60 bolts tightening work.
C9接合部位に歪みや不適当な応力が生じないので、接
合部の信頼性が高まる。The reliability of the joint is increased because there is no distortion or undue stress at the C9 joint.
第1図は架構材の地組み状態を示す施工図、第2図は接
合部の拡大斜視図、第3図は架構材のす7トアツプ状態
の竜王図、第4図は吊上%置の取り付け状態を示す正面
図、第5図はその側面図、第6図は仮プレートによるV
i接合状態の拡大斜視図、第7図は本接合状態を示す側
面図、第8図は架構材の接合完了状態を示す施工図であ
る。
1・・・支持構造体、2・・・受けトラス、2a・・・
傾斜材、2a′ ・・・ブラケット、2b・・・頂梁材
、2b’ボルト穴、2c・・・仮プレート、2e′・・
・ボルト穴、3・・・張弦梁、3a・・・大梁材、3a
’・・・ボルト穴、3b・・・張弦材、3c・・・補助
材、3d・・・仮プレート、3d′・・・ボルト穴、4
・・・仮設台、5−・・引張材、6・・・吊上用ジャッ
キ、7,8・−・ブラケット、9・・・基盤、10・−
・バックステー、11・・・本設プレート。Figure 1 is a construction drawing showing the state of the frame members being assembled into the ground, Figure 2 is an enlarged perspective view of the joints, Figure 3 is a diagram of the frame members in their fully up state, and Figure 4 is the lifting percentage. A front view showing the installation state, Fig. 5 is a side view, and Fig. 6 is a V with a temporary plate.
FIG. 7 is an enlarged perspective view of the i-joined state, FIG. 7 is a side view showing the fully joined state, and FIG. 8 is a construction drawing showing the completed state of joining of the frame members. DESCRIPTION OF SYMBOLS 1... Support structure, 2... Support truss, 2a...
Inclined material, 2a'...bracket, 2b...top beam material, 2b' bolt hole, 2c...temporary plate, 2e'...
・Bolt hole, 3... String beam, 3a... Girder material, 3a
'... Bolt hole, 3b... String material, 3c... Auxiliary material, 3d... Temporary plate, 3d'... Bolt hole, 4
...Temporary stand, 5--Tension material, 6--Hoisting jack, 7, 8--Bracket, 9--Base, 10--
・Backstay, 11...Permanent plate.
Claims (1)
持構造体に一体的に接合するリフトアップ工法において
、上記架構材の接合端部にブラケットを側方に張り出す
ように取り付けると共に、該ブラケットに吊ワイヤーや
ロッド等の引張材を取り付け、一方、上記支持構造体の
接合端部にもブラケットを側方に張り出すように取り付
けて、その上に吊上用ジャッキ等の吊上手段を設置し、
該吊上手段により引張材を引き上げるようにしたことを
特徴とする吊上装置の取付方法。 2、梁等の架構材を吊り上げて建物の柱や耐力壁等の支
持構造体に一体的に接合するリフトアップ工法において
、上記架構材と支持構造体の接合端部に仮プレートを取
り付けて、本設プレートの取り付け完了まで仮接合する
ことを特徴とする架構材の接合方法。 3、上記仮プレートのボルト穴をルーズホールとするこ
とを特徴とする請求項2に記載の架構材の接合方法。 4、上記架構材と支持構造体の接合端部のボルト穴を予
め正規の位置にあけ、本設プレートのボルト穴は上記正
規位置のボルト穴に現場突き合わせてあけることを特徴
とする請求項2または3に記載の架構材の接合方法。[Claims] 1. In a lift-up method in which a frame member such as a beam is lifted up and integrally joined to a supporting structure such as a building column or a load-bearing wall, a bracket is placed laterally at the joint end of the frame member. At the same time, a tension member such as a hanging wire or rod is attached to the bracket, and on the other hand, a bracket is also attached to the joint end of the support structure so as to extend sideways, and a tension member such as a hanging wire or rod is attached to the bracket. Install lifting means such as a lifting jack,
A method for installing a lifting device, characterized in that the tension member is pulled up by the lifting means. 2. In the lift-up method, in which a frame member such as a beam is lifted up and integrally joined to a supporting structure such as a building column or load-bearing wall, a temporary plate is attached to the joint end of the frame member and support structure, A method for joining frame members characterized by temporary joining until the installation of the permanent plates is completed. 3. The method for joining frame members according to claim 2, wherein the bolt holes of the temporary plate are made loose holes. 4. Bolt holes at the joining end of the frame member and the support structure are pre-drilled at regular positions, and the bolt holes in the main plate are drilled on-site to match the bolt holes at the regular positions. Or the method for joining frame members according to 3.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20249290A JP2882541B2 (en) | 1990-08-01 | 1990-08-01 | A method of mounting a lifting device and a method of joining frame members in a frame material lift-up method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20249290A JP2882541B2 (en) | 1990-08-01 | 1990-08-01 | A method of mounting a lifting device and a method of joining frame members in a frame material lift-up method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0489938A true JPH0489938A (en) | 1992-03-24 |
JP2882541B2 JP2882541B2 (en) | 1999-04-12 |
Family
ID=16458395
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP20249290A Expired - Fee Related JP2882541B2 (en) | 1990-08-01 | 1990-08-01 | A method of mounting a lifting device and a method of joining frame members in a frame material lift-up method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2882541B2 (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102953553A (en) * | 2012-11-14 | 2013-03-06 | 中冶天工集团有限公司 | Method for mounting large-span pipe truss by using boom luffing mechanism |
JP2014118749A (en) * | 2012-12-17 | 2014-06-30 | Shimizu Corp | Aerial photovoltaic power generation system |
CN105332515A (en) * | 2015-10-29 | 2016-02-17 | 中冶建工集团有限公司 | Erection method of large-span truss structure in limited space |
JP2016151090A (en) * | 2015-02-16 | 2016-08-22 | 株式会社大林組 | Horizontally installed structure |
CN108625530A (en) * | 2018-06-26 | 2018-10-09 | 上海天华建筑设计有限公司 | Tension string beam structure and its construction method |
CN113513174A (en) * | 2021-04-27 | 2021-10-19 | 北京建工集团有限责任公司 | Inverse installation method for steel truss hanging type structure |
JP2022054133A (en) * | 2020-09-25 | 2022-04-06 | 三菱重工業株式会社 | Method for erecting bridge between building ridges |
-
1990
- 1990-08-01 JP JP20249290A patent/JP2882541B2/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102953553A (en) * | 2012-11-14 | 2013-03-06 | 中冶天工集团有限公司 | Method for mounting large-span pipe truss by using boom luffing mechanism |
JP2014118749A (en) * | 2012-12-17 | 2014-06-30 | Shimizu Corp | Aerial photovoltaic power generation system |
JP2016151090A (en) * | 2015-02-16 | 2016-08-22 | 株式会社大林組 | Horizontally installed structure |
CN105332515A (en) * | 2015-10-29 | 2016-02-17 | 中冶建工集团有限公司 | Erection method of large-span truss structure in limited space |
CN108625530A (en) * | 2018-06-26 | 2018-10-09 | 上海天华建筑设计有限公司 | Tension string beam structure and its construction method |
CN108625530B (en) * | 2018-06-26 | 2024-01-19 | 上海天华建筑设计有限公司 | Beam string structure and construction method thereof |
JP2022054133A (en) * | 2020-09-25 | 2022-04-06 | 三菱重工業株式会社 | Method for erecting bridge between building ridges |
CN113513174A (en) * | 2021-04-27 | 2021-10-19 | 北京建工集团有限责任公司 | Inverse installation method for steel truss hanging type structure |
Also Published As
Publication number | Publication date |
---|---|
JP2882541B2 (en) | 1999-04-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210658011U (en) | Steel truss arch bridge installation system | |
JP4279189B2 (en) | Temporary strut and its construction method | |
JPH0489938A (en) | Liftup device installing method for truss lifting construction method and truss joining method | |
JPH0757972B2 (en) | Truss structure | |
KR100707726B1 (en) | B-cable long span using principle of a bow and constructing method thereof | |
US5150556A (en) | Chord truss roof structure | |
KR200407667Y1 (en) | B-cable long span using principle of a bow | |
JP4471468B2 (en) | How to install structural members | |
JPH08134847A (en) | Erection method of steel-pipe arch | |
JP2946074B2 (en) | Large roof erection method | |
JPH01322064A (en) | Scaffold erection method for construction work performing temporary general grounding using scaffolding steel pipe | |
JP2761792B2 (en) | Construction method of large space building | |
JP2683415B2 (en) | Cable-stayed bridge | |
JPH08184122A (en) | Construction of roof | |
JPH06240874A (en) | Construction of truss beam for long span | |
JP2634999B2 (en) | Dismantling method of branch line tower | |
CN116025095B (en) | Cable-beam composite long-span cable-support arch shell and construction method thereof | |
CN221216811U (en) | Prefabricated box girder protection lifting appliance | |
JP3103294B2 (en) | Pillar steel frame, jig used for the connection, and steel frame connection method | |
JPS5952044A (en) | Construction of structure | |
WO1990013715A1 (en) | Lift arch building system | |
JPH04176931A (en) | Distance controlling system for lift up method for stretch chord beam | |
CN211256673U (en) | Steel truss installation attached construction platform | |
JP2691262B2 (en) | Facility method of arch form support | |
JP2691261B2 (en) | Facility method of arch form support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090205 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100205 Year of fee payment: 11 |
|
LAPS | Cancellation because of no payment of annual fees |