JPH06240874A - Construction of truss beam for long span - Google Patents

Construction of truss beam for long span

Info

Publication number
JPH06240874A
JPH06240874A JP5493593A JP5493593A JPH06240874A JP H06240874 A JPH06240874 A JP H06240874A JP 5493593 A JP5493593 A JP 5493593A JP 5493593 A JP5493593 A JP 5493593A JP H06240874 A JPH06240874 A JP H06240874A
Authority
JP
Japan
Prior art keywords
truss beam
diagonal
temporary
chord member
lower chord
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5493593A
Other languages
Japanese (ja)
Other versions
JP3247749B2 (en
Inventor
Kazumi Yamane
一三 山根
Teruo Sasaki
照夫 佐々木
Masahito Matsukawa
正仁 松川
Hiroyuki Yamamoto
裕行 山本
Kazuo Fukazawa
和夫 深沢
Takao Yamaoka
隆夫 山岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP05493593A priority Critical patent/JP3247749B2/en
Publication of JPH06240874A publication Critical patent/JPH06240874A/en
Application granted granted Critical
Publication of JP3247749B2 publication Critical patent/JP3247749B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To make it possible to achieve the shortening of construction period and cost down to a large extent by removing temporary stages at the early time when a truss beam for a long span for supporting an upper load is constructed. CONSTITUTION:Under the state, wherein weight is supported with temporary stages D which are uprighly provided on the floor surface beneath a truss-beam erecting position, the on-site welding of the joint part of an upper chord member 1 and a lower chord member 2 and the main tightening of high-tension bolts 8 of erection pieces 6 at the joint part of a longitudinal member 3 and a diagonal member 4 are performed. After the temporary stages D are removed, the on-site welding at the joint part of the longitudinal member 3 and the diagonal member 4 is performed. The on-site welding of the joint part of the lower chord member 2 is also performed. A temporary suspending diagonal member 10 is provided from the top part of a post. At the time when the lower chord member 2 is supported with the suspending diagonal member 10, the temporary stages D are removed. Thereafter, on-site welding of the joint part of the longitudinal member 3 and the diagonal member 4 can be performed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、上部構造体等による上
部の荷重を支持するための長大スパンのトラス梁を構築
する方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a long-span truss beam for supporting an upper load by an upper structure or the like.

【0002】[0002]

【従来の技術】例えば、高層部を支持するためのメガス
トラクチャーを構成するトラス梁のように、高層部(上
部構造体)等による上部の大きな荷重を支持するための
長大スパンのトラス梁は、スパンは勿論、梁成も大き
く、重量は極めて大きい。そのため、このような上部の
大荷重を支持する長大スパンのトラス梁を構築するにあ
たっては、トラス梁を幾つかのピースに分割して現地に
搬入し、トラス梁架設位置の下方の床面に立設した仮設
ステージにピース毎に吊り上げ、仮設ステージでそれら
の重量を支持した状態で、各継手部の現場溶接を行って
一体化するのが普通である。具体的には、先ず、上弦
材、下弦材、斜材、縦材の継手部におけるエレクション
ピースの高力ボルトを仮締めして、建方の調整を行い、
前記高力ボルトを本締めした後、全ての継手部を最終的
に溶接して、上部構造体等の荷重に耐え得る状態に接合
し、しかる後、仮設ステージを撤去している。
2. Description of the Related Art For example, a truss beam having a long span for supporting a large load in the upper portion due to a high-rise portion (upper structure), such as a truss beam forming a megastructure for supporting a high-rise portion, The span is of course large and the beam is large, and the weight is extremely large. Therefore, when constructing a long-span truss beam that supports such a large load on the upper part, the truss beam is divided into several pieces and loaded into the field, and the truss beam is erected on the floor below the truss beam installation position. It is usual to suspend each piece on an established temporary stage, and in the state where the weight is supported by the temporary stage, on-site welding of each joint is performed to integrate them. Specifically, first, temporarily tighten the high-strength bolt of the erection piece at the joint part of the upper chord member, the lower chord member, the diagonal member, and the vertical member to adjust the erection.
After the high-strength bolts are fully tightened, all joints are finally welded and joined so as to withstand the load of the upper structure and the like, and then the temporary stage is removed.

【0003】[0003]

【発明が解決しようとする課題】上記の従来例では、長
大スパンのトラス梁における全ての継手部を最終的に現
場溶接して、上部構造体等の荷重に耐え得る状態となる
まで、仮設ステージで支持しているため、仮設ステージ
が長期間にわたって存置されることになり、このことが
トラス梁下方の低層部の施工工期に大きく影響を与え、
しかも、仮設ステージのリース料が膨大なものとなり、
工期、コストの両面で問題があった。本発明は、上記の
点に留意してなされたものであって、その目的とすると
ころは、早期に仮設ステージを撤去できて、大幅な工期
短縮とコストダウンが可能となる長大スパンのトラス梁
の構築方法を提供することにある。
In the above-mentioned conventional example, all the joints in the truss beam having a long span are finally field-welded until the load of the upper structure or the like can be endured. Since it is supported by, the temporary stage will remain for a long period of time, which greatly affects the construction period of the low-rise part below the truss beam,
Moreover, the leasing fee for the temporary stage becomes huge,
There were problems in terms of construction period and cost. The present invention has been made with the above points in mind, and the purpose thereof is to make it possible to remove a temporary stage at an early stage, greatly shorten the construction period, and reduce the cost. It is to provide a construction method of.

【0004】[0004]

【課題を解決するための手段】上記の目的を達成するた
めに本発明が講じた技術的手段は次のとおりである。即
ち、第1発明による長大スパンのトラス梁の構築方法
は、トラス梁架設位置の下方の床面に立設した仮設ステ
ージで重量を支持した状態で、上弦材および下弦材の継
手部の現場溶接と、縦材および斜材の継手部におけるエ
レクションピースの高力ボルトを本締めを行い、前記仮
設ステージを撤去した後、縦材および斜材の継手部の現
場溶接を行うことを特徴としている。第2発明による長
大スパンのトラス梁の構築方法は、トラス梁架設位置の
下方の床面に立設した仮設ステージで重量を支持した状
態で、下弦材の継手部の現場溶接を行い、且つ、柱頂部
から仮設の吊り斜材を設けて、当該吊り斜材で前記下弦
材を支持し、前記仮設ステージを撤去した後、上弦材の
継手部の現場溶接、縦材および斜材の継手部の現場溶接
を行うことを特徴としている。
The technical means taken by the present invention to achieve the above object are as follows. That is, the method for constructing a long-span truss beam according to the first aspect of the present invention is to perform on-site welding of the joint portion of the upper chord member and the lower chord member while supporting the weight on the temporary stage that is erected on the floor below the truss beam installation position. In addition, the high-strength bolt of the erection piece at the joint portion of the vertical member and the diagonal member is finally tightened, the temporary stage is removed, and then the joint portion of the vertical member and the diagonal member is welded on site. A method of constructing a long-span truss beam according to a second aspect of the invention is to perform on-site welding of a joint portion of a lower chord member while supporting a weight on a temporary stage erected on a floor surface below a truss beam installation position, and Providing a temporary hanging diagonal from the top of the pillar, supporting the lower chord with the hanging diagonal, removing the temporary stage, then field welding of the joint of the upper chord, vertical and diagonal joints It is characterized by performing on-site welding.

【0005】[0005]

【作用】第1発明の構成によれば、縦材および斜材の継
手部については、最終的な溶接を行う前に、つまり、エ
レクションピースの高力ボルトを本締めした時点で、仮
設ステージを撤去するため、縦材および斜材の継手部の
現場溶接に必要な日数だけ早期に仮設ステージが撤去さ
れることになる。第2発明の構成によれば、下弦材の現
場溶接が完了し且つ仮設の吊り斜材で前記下弦材を支持
した時点で、仮設ステージを撤去できるので、より早期
に仮設ステージが撤去されることになる。
According to the structure of the first aspect of the present invention, for the joint portion of the vertical member and the diagonal member, the temporary stage is set before the final welding, that is, when the high-strength bolt of the erection piece is fully tightened. Because of the removal, the temporary stage will be removed as early as the number of days required for in-situ welding of the vertical and diagonal joints. According to the configuration of the second invention, the temporary stage can be removed at a time when the in-situ welding of the lower chord member is completed and the lower chord member is supported by the temporary hanging diagonal member, so that the temporary stage can be removed earlier. become.

【0006】[0006]

【実施例】先ず、第1発明の実施例を図面に基づいて説
明する。図1において、Aはメガストラクチャーを構成
する長大スパンのトラス梁であり、高層部Bの荷重を支
持している。Cはメガストラクチャーを構成する柱を示
す。
DESCRIPTION OF THE PREFERRED EMBODIMENTS First, an embodiment of the first invention will be described with reference to the drawings. In FIG. 1, A is a long-span truss beam that constitutes a megastructure, and supports the load of the high-rise portion B. C indicates the pillars that make up the megastructure.

【0007】トラス梁Aは、図2に示すように、柱C,
C間にわたる上弦材1および下弦材2と、それらの間に
設けられた多数の縦材3および斜材4によって構成され
ている。図2において、5は柱Cの側面に突設したブラ
ケットであり、下弦材2の端部を支持し、補強してい
る。aは縦材3の継手部、bは斜材4の継手部を示し、
これらの継手部a,bは、図3〜図5に示すように、エ
レクションピース6の両側を接合用プレレート7で挟持
した状態で、それらを貫通する複数の高力ボルト8で締
付け連結し、さらに、最終的には、現場溶接Wを行って
一体化するように構成されている。
As shown in FIG. 2, the truss beam A has pillars C,
It is composed of an upper chord member 1 and a lower chord member 2 extending between C, and a large number of vertical members 3 and diagonal members 4 provided therebetween. In FIG. 2, 5 is a bracket projecting from the side surface of the pillar C, which supports and reinforces the end of the lower chord member 2. a is a joint portion of the vertical member 3, b is a joint portion of the diagonal member 4,
These joint parts a and b are, as shown in FIGS. 3 to 5, clamped and connected by a plurality of high-strength bolts 8 penetrating them in a state where both sides of the erection piece 6 are sandwiched by the joining prerate 7. Furthermore, finally, it is configured to perform on-site welding W and integrate them.

【0008】尚、均一な太さの縦材3の継手部cは、斜
材4の継手部bと同じ構造となっているため、図示説明
を省略する。図2に示すdは上弦材1の端部の継手部、
eは下弦材2の端部の継手部である。これらの継手部
d,eは、前記継手部a,bと実質的に同じ構造であ
り、エレクションピース6の両側を接合用プレレート7
で挟持した状態で、それらを貫通する複数の高力ボルト
8で締付け連結し、最終的には、現場溶接Wを行って一
体化するように構成されている。図示しないが、上弦材
1および下弦材2のスパン中央側の継手部も同じ構造で
ある。
Since the joint portion c of the vertical member 3 having a uniform thickness has the same structure as the joint portion b of the diagonal member 4, its illustration is omitted. 2 is a joint portion at the end of the upper chord member 1,
e is a joint portion at the end of the lower chord member 2. These joint portions d and e have substantially the same structure as the joint portions a and b, and both sides of the erection piece 6 are joined to each other by the joining pre-plate 7.
In the state of being sandwiched by, the plurality of high-strength bolts 8 penetrating them are tightened and connected, and finally, on-site welding W is performed to integrate them. Although not shown, the joint portions of the upper chord member 1 and the lower chord member 2 on the center side of the span also have the same structure.

【0009】次に、上記のトラス梁Aの構築方法を図6
に基づいて説明する。先ず、図6の(イ)に示すよう
に、トラス梁架設位置(仮想線で示す)の下方の床面9
に、トラス梁架設位置までの高さをもつ仮設ステージD
を立設する。一方、トラス梁Aは、複数のピースに分割
して現地に搬入し、タワークレーン等を使用してピース
毎に仮設ステージDに吊り上げる。
Next, a method of constructing the truss beam A described above will be described with reference to FIG.
It will be described based on. First, as shown in FIG. 6A, the floor surface 9 below the truss beam installation position (shown in phantom).
The temporary stage D with the height up to the truss beam installation position
To stand. On the other hand, the truss beam A is divided into a plurality of pieces, carried into the site, and hoisted on a temporary stage D for each piece using a tower crane or the like.

【0010】そして、仮設ステージDで重量を支持した
状態で、上弦材1および下弦材2の継手部の現場溶接W
と、縦材3および斜材4の継手部におけるエレクション
ピース6の高力ボルト8の本締めを行う。より具体的に
説明すると、上弦材1および下弦材2の継手部における
エレクションピース6の高力ボルト8、縦材3および斜
材4の継手部におけるエレクションピース6の高力ボル
ト8を夫々仮締めし、建方の調整を行った後、全ての高
力ボルト8を本締めし、しかる後、上弦材1および下弦
材2の継手部だけを溶接するのである。
Then, with the weight being supported by the temporary stage D, on-site welding W of the joint portion of the upper chord member 1 and the lower chord member 2 is performed.
Then, the high-strength bolt 8 of the erection piece 6 at the joint portion of the vertical member 3 and the diagonal member 4 is fully tightened. More specifically, the high-strength bolts 8 of the erection piece 6 at the joints of the upper chord member 1 and the lower chord member 2 and the high-strength bolts 8 of the erection piece 6 at the joints of the vertical member 3 and the diagonal member 4 are temporarily tightened, respectively. Then, after adjusting the erection, all the high-strength bolts 8 are fully tightened, and then only the joint portions of the upper chord member 1 and the lower chord member 2 are welded.

【0011】この状態においては、トラス梁Aは、全て
の継手部の最終的な溶接が済んでいないので、予め設計
されている上部からの荷重(高層部Bの荷重)にまで耐
えることができないことは当然であるが、最も力のかか
る上弦材1および下弦材2については最終的な溶接まで
完了しているので、縦材3および斜材4の継手部におけ
るエレクションピース6や高力ボルト8の数を適当に設
定することにより、トラス梁A自体の重量には十分に耐
えることができる。
In this state, the truss beam A cannot withstand the pre-designed load from the upper portion (the load of the high-rise portion B) because the final welding of all joints has not been completed. Needless to say, since the upper chord member 1 and the lower chord member 2 having the highest force are completely welded, the erection piece 6 and the high-strength bolt 8 at the joint portion of the vertical member 3 and the diagonal member 4 are completed. By properly setting the number of the truss beams A, it is possible to sufficiently bear the weight of the truss beam A itself.

【0012】従って、第1発明では、上弦材1および下
弦材2の継手部の現場溶接Wと、縦材3および斜材4の
継手部におけるエレクションピース6の高力ボルト8の
本締めが完了した時点で、図6の(ロ)に示すように、
全ての仮設ステージDを撤去し、トラス梁Aの下方の低
層部の躯体工事や仕上げ工事を進めるのである。同図の
Pは、縦材3および斜材4のエレクションピースによる
接続点を示している。
Therefore, according to the first aspect of the invention, the on-site welding W of the joint portion of the upper chord member 1 and the lower chord member 2 and the final fastening of the high-strength bolt 8 of the erection piece 6 at the joint portion of the vertical member 3 and the diagonal member 4 are completed. At that time, as shown in (b) of FIG.
All the temporary stages D will be removed, and the skeleton construction and finishing work of the lower part of the truss beam A will proceed. P in the figure shows the connection point of the vertical member 3 and the diagonal member 4 by the erection piece.

【0013】そして、仮設ステージDの撤去後、適当な
時点で、縦材3および斜材4の継手部についても最終的
な現場溶接Wを行ってトラス梁Aの構築を完了し、しか
る後、図6の(ハ)に示すように、トラス梁Aの上部に
高層部Bを構築して行くのである。
Then, after the temporary stage D is removed, at the appropriate time, final joint welding W is also performed on the joint portion of the vertical member 3 and the diagonal member 4 to complete the construction of the truss beam A, and thereafter, As shown in (c) of FIG. 6, the high-rise part B is built on the upper part of the truss beam A.

【0014】上記の構成によれば、仮設ステージDを早
期に撤去できるため、工期の短縮とコストダウンが可能
である。因みに、上弦材1の溶接個所が3個所、下弦材
2が3個所、縦材3が6個所、斜材4が8個所で、全個
所の最終的な溶接完了まで約40日かかるトラス梁をモ
デルにして考えると、上記の方法によれば、仮設ステー
ジDの存置期間は約20日となり、大幅な工期短縮とコ
ストダウンが可能である。
According to the above construction, the temporary stage D can be removed early, so that the construction period can be shortened and the cost can be reduced. By the way, there are 3 welding points for the upper chord, 1 for the lower chord, 3 for the vertical chord, 6 for the vertical chord, and 8 for the diagonal timber. It takes about 40 days to complete the final welding of the truss beam. When considered as a model, according to the above method, the temporary stage D can be stored for about 20 days, which can significantly reduce the construction period and reduce the cost.

【0015】次に、第2発明の実施例を図7以降の図面
に基づいて説明する。図7〜図9において、10は柱Cの
頂部から下弦材2にわたって設けた仮設の吊り斜材であ
る。この吊り斜材10は、下弦材2にかかる上弦材1、縦
材3、斜材4の重量をその張力で支持すると共に、下弦
材2の撓みを抑制するためのものである。トラス梁Aの
その他の構成は、図1〜図5で説明した構成と同じであ
るため、図示説明を省略する。
Next, an embodiment of the second invention will be described with reference to the drawings starting from FIG. 7 to 9, 10 is a temporary hanging diagonal member provided from the top of the pillar C to the lower chord member 2. This hanging diagonal member 10 supports the weight of the upper chord member 1, the vertical member 3, and the diagonal member 4 applied to the lower chord member 2 by its tension and suppresses the bending of the lower chord member 2. The other configuration of the truss beam A is the same as the configuration described with reference to FIGS.

【0016】トラス梁Aを構築するにあたっては、図1
0の(イ)に示すように、トラス梁架設位置(仮想線で
示す)の下方の床面9に仮設ステージDを立設し、図1
0の(ロ)に示すように、仮設ステージDで重量を支持
した状態で、下弦材2の継手部の現場溶接Wを行い、且
つ、柱C,Cの頂部から仮設の吊り斜材10,10を設け
て、当該吊り斜材10,10で前記下弦材2を支持する。こ
の時点では、上弦材1の継手部、縦材3の継手部、斜材
4の継手部は、いずれも、エレクションピース6の高力
ボルト8の本締めまで完了しているが、現場溶接による
最終的な接続はなされていない。
In constructing the truss beam A, as shown in FIG.
As shown in (a) of 0, the temporary stage D is erected on the floor surface 9 below the truss beam installation position (shown by a virtual line).
As shown in (b) of 0, in the state where the weight is supported on the temporary stage D, on-site welding W of the joint portion of the lower chord member 2 is performed, and the temporary suspension diagonal member 10 is provided from the tops of the columns C, C. 10 is provided and the lower chord member 2 is supported by the suspension diagonal members 10 and 10. At this point, the joint portion of the upper chord member 1, the joint portion of the vertical member 3, and the joint portion of the diagonal member 4 have all been completed up to the final tightening of the high-strength bolt 8 of the erection piece 6, but by field welding. No final connection has been made.

【0017】この状態で、前記仮設ステージDを撤去
し、トラス梁Aの下方の低層部の躯体工事や仕上げ工事
を進めるのである。そして、仮設ステージD撤去後の適
当な時期に、上弦材1の継手部の現場溶接W、縦材3お
よび縦材4の継手部の現場溶接Wを行ってトラス梁Aの
構築を完了し、しかる後、図10の(ハ)に示すよう
に、トラス梁Aの上部に高層部Bを構築して行くのであ
る。
In this state, the temporary stage D is removed, and the skeleton work and finishing work of the lower part of the truss beam A are proceeded. Then, at an appropriate time after the removal of the temporary stage D, the on-site welding W of the joint portion of the upper chord member 1 and the on-site welding W of the joint portions of the vertical members 3 and 4 are performed to complete the construction of the truss beam A, Then, as shown in FIG. 10C, the high-rise part B is constructed on the upper part of the truss beam A.

【0018】上記の構成によれば、下弦材2の現場溶接
が完了し、吊り斜材10を設置した時点で、仮設ステージ
Dを撤去できるため、第1発明の場合よりも一層、早期
に仮設ステージDを撤去できることになる。
According to the above construction, since the temporary stage D can be removed at the time when the in-situ welding of the lower chord member 2 is completed and the hanging diagonal member 10 is installed, the temporary stage D can be installed even earlier than in the case of the first invention. You will be able to remove Stage D.

【0019】尚、トラス梁Aは、第1発明の実施例と同
じように、複数のピースに分割して現地に搬入され、タ
ワークレーン等を使用してピース毎に仮設ステージDに
吊り上げられる。また、上弦材1、下弦材2、縦材3、
斜材4の継手部の構造は、第1発明の実施例と同じであ
る。吊り斜材10による下弦材2の支持形態は、図7〜図
10に示した実施例の他、種々の変更が可能である。例
えば、図11に示すように、下弦材2のスパン中央近傍
を吊り斜材10で支持するようにしてもよく、図12に示
すように、下弦材2の下方にスペーサー11を介在させた
状態で、吊り斜材10で支持するようにしてもよい。殊
に、後者によれば、吊り斜材10の角度が急になるため、
トラス梁Aのスパン中央での撓み抑制がより効果的に行
われることになる。
As in the first embodiment of the invention, the truss beam A is divided into a plurality of pieces and carried in to the site, and is lifted on a temporary stage D for each piece using a tower crane or the like. Also, the upper chord member 1, the lower chord member 2, the vertical chord member 3,
The structure of the joint portion of the diagonal member 4 is the same as that of the first embodiment. The supporting form of the lower chord member 2 by the hanging diagonal member 10 can be variously modified in addition to the embodiment shown in FIGS. For example, as shown in FIG. 11, a suspension diagonal member 10 may be supported near the center of the span of the lower chord member 2, and as shown in FIG. 12, a spacer 11 is interposed below the lower chord member 2. Then, the suspension diagonal member 10 may be used for supporting. Especially, according to the latter, since the angle of the suspended diagonal member 10 becomes steep,
The flexure suppression at the center of the span of the truss beam A is more effectively performed.

【0020】[0020]

【発明の効果】本発明は、上記の構成よりなり、仮設ス
テージを早期に撤去できるので、大幅な工期短縮とコス
トダウンが可能となる効果がある。
According to the present invention, which has the above-mentioned structure, and the temporary stage can be removed early, there is an effect that the construction period can be greatly shortened and the cost can be reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】高層部を支持するための長大スパンのトラス梁
を含む建物の軸組図である。
FIG. 1 is a frame diagram of a building including long span truss beams for supporting high rises.

【図2】トラス梁の要部の概略側面図である。FIG. 2 is a schematic side view of a main part of a truss beam.

【図3】縦材の継手部の側面図である。FIG. 3 is a side view of a joint portion of a vertical member.

【図4】斜材の継手部の断面図である。FIG. 4 is a cross-sectional view of a joint portion of a diagonal member.

【図5】斜材の継手部の側面図である。FIG. 5 is a side view of a joint portion of a diagonal member.

【図6】第1発明による長大スパンのトラス梁の構築方
法の説明図である。
FIG. 6 is an explanatory diagram of a method of constructing a long-span truss beam according to the first invention.

【図7】トラス梁の要部の概略側面図である。FIG. 7 is a schematic side view of a main part of a truss beam.

【図8】トラス梁の要部の平面図である。FIG. 8 is a plan view of a main part of a truss beam.

【図9】トラス梁の要部の斜視図である。FIG. 9 is a perspective view of a main part of a truss beam.

【図10】第2発明による長大スパンのトラス梁の構築
方法の説明図である。
FIG. 10 is an explanatory diagram of a method of constructing a long-span truss beam according to the second invention.

【図11】第2発明の他の実施例の説明図である。FIG. 11 is an explanatory diagram of another embodiment of the second invention.

【図12】第2発明の他の実施例の説明図である。 〔図面の簡単な説明〕 A…トラス梁、C…柱、D…仮設ステージ、1…上弦
材、2…下弦材、3…縦材、4…斜材、6…エレクショ
ンピース、8…高力ボルト、10…吊り斜材。
FIG. 12 is an explanatory diagram of another embodiment of the second invention. [Brief Description of Drawings] A ... Truss beam, C ... Pillar, D ... Temporary stage, 1 ... Upper chord member, 2 ... Lower chord member, 3 ... Vertical member, 4 ... Oblique member, 6 ... Erection piece, 8 ... High strength Bolts, 10 ... Hanging diagonals.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 山本 裕行 大阪市中央区本町4丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 深沢 和夫 大阪市中央区本町4丁目1番13号 株式会 社竹中工務店大阪本店内 (72)発明者 山岡 隆夫 大阪市中央区本町4丁目1番13号 株式会 社竹中工務店大阪本店内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Hiroyuki Yamamoto 4-1-1-13 Honmachi, Chuo-ku, Osaka City Takenaka Corporation Osaka Main Store (72) Inventor Kazuo Fukasawa 4-1-1 Honmachi, Chuo-ku, Osaka No. 13 Stock Company Takenaka Corporation Osaka Main Store (72) Inventor Takao Yamaoka 4-1-1 Hommachi, Chuo-ku, Osaka City Stock Company Takenaka Corporation Osaka Main Store

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 上部の荷重を支持するための長大スパン
のトラス梁を構築する方法であって、トラス梁架設位置
の下方の床面に立設した仮設ステージで重量を支持した
状態で、上弦材および下弦材の継手部の現場溶接と、縦
材および斜材の継手部におけるエレクションピースの高
力ボルトを本締めを行い、前記仮設ステージを撤去した
後、縦材および斜材の継手部の現場溶接を行うことを特
徴とする長大スパンのトラス梁の構築方法。
1. A method of constructing a long-span truss beam for supporting a load on an upper portion thereof, wherein the upper chord is supported by a temporary stage erected on a floor surface below a position where the truss beam is erected. Welding the joints of wood and lower chords, and tightening the high-strength bolts of the erection piece in the joints of vertical and diagonal members, and removing the temporary stage. A method for constructing a long-span truss beam characterized by performing on-site welding.
【請求項2】 上部の荷重を支持するための長大スパン
のトラス梁を構築する方法であって、トラス梁架設位置
の下方の床面に立設した仮設ステージで重量を支持した
状態で、下弦材の継手部の現場溶接を行い、且つ、柱頂
部から仮設の吊り斜材を設けて、当該吊り斜材で前記下
弦材を支持し、前記仮設ステージを撤去した後、上弦材
の継手部の現場溶接、縦材および斜材の継手部の現場溶
接を行うことを特徴とする長大スパンのトラス梁の構築
方法。
2. A method for constructing a long-span truss beam for supporting a load on an upper portion thereof, wherein the lower chord is supported by a temporary stage erected on a floor surface below the truss beam erection position while supporting the weight. Performing on-site welding of the joint part of the material, and providing a temporary hanging diagonal member from the top of the pillar, supporting the lower chord member with the hanging diagonal member, removing the temporary stage, and then the joint part of the upper chord member. A method for constructing a long-span truss beam, which is characterized by performing on-site welding and on-site welding of joints of vertical members and diagonal members.
JP05493593A 1993-02-19 1993-02-19 Construction method of long span truss beams Expired - Fee Related JP3247749B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP05493593A JP3247749B2 (en) 1993-02-19 1993-02-19 Construction method of long span truss beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP05493593A JP3247749B2 (en) 1993-02-19 1993-02-19 Construction method of long span truss beams

Publications (2)

Publication Number Publication Date
JPH06240874A true JPH06240874A (en) 1994-08-30
JP3247749B2 JP3247749B2 (en) 2002-01-21

Family

ID=12984497

Family Applications (1)

Application Number Title Priority Date Filing Date
JP05493593A Expired - Fee Related JP3247749B2 (en) 1993-02-19 1993-02-19 Construction method of long span truss beams

Country Status (1)

Country Link
JP (1) JP3247749B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10159344A (en) * 1996-11-29 1998-06-16 Takenaka Komuten Co Ltd Building method of multi-layered structure provided with a plurality of super beam
JP2016108816A (en) * 2014-12-05 2016-06-20 名古屋菱重興産株式会社 Frame with truss beam
JP2018123635A (en) * 2017-02-03 2018-08-09 株式会社竹中工務店 Building structure
CN112482719A (en) * 2020-11-16 2021-03-12 北京市机械施工集团有限公司 Multifunctional operation platform for large-span truss and construction method thereof
CN114134990A (en) * 2021-12-09 2022-03-04 上海市机械施工集团有限公司 Installation and uninstallation method of large-span overhanging corridor

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10159344A (en) * 1996-11-29 1998-06-16 Takenaka Komuten Co Ltd Building method of multi-layered structure provided with a plurality of super beam
JP2016108816A (en) * 2014-12-05 2016-06-20 名古屋菱重興産株式会社 Frame with truss beam
JP2018123635A (en) * 2017-02-03 2018-08-09 株式会社竹中工務店 Building structure
CN112482719A (en) * 2020-11-16 2021-03-12 北京市机械施工集团有限公司 Multifunctional operation platform for large-span truss and construction method thereof
CN114134990A (en) * 2021-12-09 2022-03-04 上海市机械施工集团有限公司 Installation and uninstallation method of large-span overhanging corridor

Also Published As

Publication number Publication date
JP3247749B2 (en) 2002-01-21

Similar Documents

Publication Publication Date Title
US5063718A (en) Curtain wall for a building
CN112695952B (en) Building roof truss support structure and construction method
JPH06240874A (en) Construction of truss beam for long span
US5150556A (en) Chord truss roof structure
JPH10159344A (en) Building method of multi-layered structure provided with a plurality of super beam
JP2882541B2 (en) A method of mounting a lifting device and a method of joining frame members in a frame material lift-up method
JPH01315541A (en) Roof truss
JP2000129958A (en) Tower-like structural body
US4442640A (en) Method of converting a roof frame and frame elements for performing this method
CN219045208U (en) Steel structure connecting piece based on steel structure building support
JP3103294B2 (en) Pillar steel frame, jig used for the connection, and steel frame connection method
JPH08113982A (en) Device for joining column and beam of steel framed building
JPH09328816A (en) Y-form column and anchor plate in hexagonal building structure
JP2761792B2 (en) Construction method of large space building
JPH08120771A (en) Method for constructing steel trussed construction
JPH08218640A (en) Nonbracekt type column-beam joining method for steelwork structure
JP2660953B2 (en) Construction method
JPH02282572A (en) Erection method for precast concrete pillar
JP2668616B2 (en) Steel frame construction method
JPH0533606Y2 (en)
JPH05340002A (en) Construction method for steel construction building with large outrigger girder
JPH0213623Y2 (en)
JPH06287998A (en) Constructing method for preliminary assembling of reinforced concrete composite beam
JP3027550U (en) Frame structure of a two-story wooden building that is strong against earthquakes
JP2506464B2 (en) Fence for roofing of industrialized houses

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081102

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 8

Free format text: PAYMENT UNTIL: 20091102

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 9

Free format text: PAYMENT UNTIL: 20101102

LAPS Cancellation because of no payment of annual fees