JPH047779B2 - - Google Patents

Info

Publication number
JPH047779B2
JPH047779B2 JP61033644A JP3364486A JPH047779B2 JP H047779 B2 JPH047779 B2 JP H047779B2 JP 61033644 A JP61033644 A JP 61033644A JP 3364486 A JP3364486 A JP 3364486A JP H047779 B2 JPH047779 B2 JP H047779B2
Authority
JP
Japan
Prior art keywords
water
frame
anchor
ground
anchor member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP61033644A
Other languages
Japanese (ja)
Other versions
JPS62194326A (en
Inventor
Fumio Kinoshita
Akyoshi Nojiri
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP61033644A priority Critical patent/JPS62194326A/en
Publication of JPS62194326A publication Critical patent/JPS62194326A/en
Publication of JPH047779B2 publication Critical patent/JPH047779B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は大深度の施工が可能な地下構造物の
構築方法に関するもので、軟弱地盤の市街地等で
も適用できるようにしたものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for constructing an underground structure that can be constructed at great depths, and is designed to be applicable even in urban areas with soft ground.

〔従来の技術〕[Conventional technology]

従来、施工深度が大きい場合や地下水位が高く
ヒービング、ボイリング等の恐れがある場合の地
下躯体の構築方法としては、例えば圧搾空気を用
いたニユーマチツクケーソン工法が利用されてい
る。その場合、下端の耐圧盤外周に刃口を設けた
構造物躯体を地上で順次構築するとともに、地下
水圧に対抗させるために圧気した耐圧盤下の作業
室で人力等による掘削を行ない、躯体を順次沈設
して行く方法が採られている。
Conventionally, as a method for constructing an underground framework when the construction depth is large or when the underground water level is high and there is a risk of heaving, boiling, etc., for example, the pneumatic caisson construction method using compressed air has been used. In that case, a structure frame with a cutting edge on the outer periphery of the pressure plate at the lower end is constructed one after another on the ground, and excavation is carried out manually in a work room under the pressure plate, which is pressurized to counter groundwater pressure. The method used is to deposit them in stages.

このようなケーソンによる地下構造物の施工で
は躯体を所定の深度まで鉛直に精度良く沈設する
ことが要求される。しかし、躯体週面と地盤との
摩擦力等によつて沈下し難くなつたり、ボイリン
グやヒービング等の発生により施工が困難となる
恐れがある。また、沈下を促すため載荷したり、
ニユーマチツクケーソンの場合は一時的に圧気圧
を低下させる方法等もあるが、沈下のコントロー
ルが難しい。
Construction of such underground structures using caisson requires that the frame be vertically and precisely sunk to a predetermined depth. However, there is a risk that it may become difficult to sink due to frictional forces between the frame surface and the ground, and construction may become difficult due to occurrence of boiling, heaving, etc. In addition, loading to encourage subsidence,
In the case of pneumatic caissons, there are methods to temporarily lower the pressure, but it is difficult to control the sinking.

また、オープンケーソン工法の場合、通常水中
掘削等により地下水圧に対処させることができる
が、大きな被水圧がある場合はヒービング、ボイ
リングが発生し、周辺地盤にも沈下等の影響を及
ぼす恐れがある。さらにオープンケーソン工法で
は各階のスラブが後施工となり、工程上影響が出
るといつた問題がある。
In addition, in the case of the open caisson construction method, underground water pressure can usually be dealt with by underwater excavation, etc., but if there is large water pressure, heaving and boiling may occur, which may also affect the surrounding ground, such as subsidence. . Furthermore, with the open caisson construction method, the slabs for each floor must be constructed later, which has the problem of affecting the construction process.

また、このような問題点を解決する工法とし
て、出願人は、地上で構築した構造物躯体上にジ
ヤツキを配置し、躯体下を掘削するとともにアー
スアンカーに反力をとつて躯体を地中に押込んで
沈設する方法について既に出願を行なつている
(特願昭60−243679号)。同工法によれば沈下速度
の制御、傾斜の修正をしながら沈設でき、またア
ースアンカーを建物の浮力対策にも転用すること
ができる。
In addition, as a construction method to solve these problems, the applicant places jacks on the frame of a structure built on the ground, excavates under the frame, and uses a reaction force on the earth anchor to lower the frame into the ground. An application has already been filed regarding the method of pushing and sinking (Japanese Patent Application No. 243679/1982). This construction method allows the building to be lowered while controlling the sinking speed and correcting the slope, and also allows the earth anchor to be used as a measure against building buoyancy.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

躯体内に沈設荷重として、清水または泥水を満
たし、水中掘削しながら躯体の沈設を行なう場
合、所定深さまで沈設が完了した後、内部の清水
または泥水を排出する。ところで、浮力対策用の
本設アースアンカーのアンカー部材頭部を躯体の
底版に定着させる場合、先に躯体内部の清水また
は泥水を排出しなければならないが、そのために
はデイープウエル等で地下水位を低下させる等の
手段が必要となる。しかし、地下水を汲み上げは
周囲の地盤に影響を与えるため、できるだけ少な
くしなければならない。
When the structure is filled with fresh water or muddy water as a submerged load and the structure is sunk while excavating underwater, the fresh water or muddy water inside is discharged after the structure has been sunk to a predetermined depth. By the way, when fixing the anchor member head of the main earth anchor for buoyancy countermeasures to the bottom plate of the structure, it is necessary to first drain the fresh water or muddy water inside the structure, but in order to do this, the underground water level must be lowered with a deep well etc. It is necessary to take measures such as lowering the temperature. However, pumping up groundwater has an impact on the surrounding ground, so it must be minimized as much as possible.

この発明は上述のような問題点を解決すること
を目的としたものである。
This invention aims to solve the above-mentioned problems.

〔問題点を解決するための手段〕[Means for solving problems]

この発明の工法では地上で構築した躯体内に清
水または泥水を満たして浮力に抵抗させながら、
底版下を掘削して順次沈設して行く。浮力対策用
の本設アースアンカーは底版を構成するスラブ複
数箇所に配置することとし、また必要に応じ躯体
の壁部分を貫通するアースアンカーに反力をとつ
てジヤツキ等により沈下速度、傾斜等を修正しな
がら沈設して行く。
In the construction method of this invention, the framework built on the ground is filled with fresh water or muddy water to resist buoyancy.
The area will be excavated below the bottom slab and deposited in stages. Ground anchors for buoyancy countermeasures will be placed at multiple locations on the slab that makes up the bottom slab, and if necessary, the earth anchors penetrating the walls of the building structure will be used to absorb reaction force and reduce the sinking speed, inclination, etc. by means of jacking, etc. It will be installed while being corrected.

各スラブ中央部の本設アースアンカーについて
は躯体が所定深さまで沈設したら、清水または泥
水を満たしたまま、躯体の底版より該アースアン
カーのアンカー部材を貫通させたパイプを水上ま
で立上げ、該パイプ上部でアンカー部材を仮定着
させ、浮力に対抗できるようにする。その後、躯
体内部の清水または泥水を排除し、アンカー部材
の底版への定着作業を行ない、不要部分は切断す
るなどする。
For the permanent earth anchors in the center of each slab, once the structure has been sunk to a predetermined depth, a pipe with the anchor member of the earth anchor penetrated from the bottom of the structure is raised above the water while it is filled with fresh water or muddy water. An anchor member is temporarily attached at the top to counteract buoyancy. After that, clean water or muddy water inside the frame is removed, the anchor member is fixed to the bottom plate, and unnecessary parts are cut off.

〔実施例〕〔Example〕

次に、図示した実施例について説明する。 Next, the illustrated embodiment will be described.

第1図にはこの発明の工程におけるアースアン
カー5による躯体1の仮定着時の様子を示したも
のである。なお図中、左半分は仮定着後、デイー
プウエル14により躯体1部分の地下水位を低下
させ、内部の清水または泥水8を排出した状態で
ある。
FIG. 1 shows a state in which a frame 1 is tentatively attached by earth anchors 5 in the process of the present invention. In addition, the left half of the figure shows a state in which after temporary landing, the groundwater level in one part of the frame was lowered by the deep well 14, and the fresh water or muddy water 8 inside was discharged.

沈設位置の周囲にはあらかじめ土留および止水
を兼ねた地中連続壁13が構築され、下端に刃口
3を有し、地上で順次構築される躯体1を底版2
下の掘削を行ないながら徐々に沈設して行く。躯
体1の内部には沈設荷重として清水または泥水8
が満たされており、また底版2を含めたスラブに
は浮力対策用のアースアンカー5のアンカー部材
(PCストランド7)を貫通させる貫通孔4形成し
てある。
An underground continuous wall 13 that serves as earth retaining and water stop is constructed in advance around the submerged position, and has a cutting edge 3 at the lower end, and a bottom plate 2 is used to connect the frame 1 that will be built sequentially on the ground.
The site will be gradually submerged while excavating the area below. Inside the frame 1, there is fresh water or muddy water 8 as a submerged load.
The slab including the bottom plate 2 is provided with a through hole 4 through which an anchor member (PC strand 7) of an earth anchor 5 for buoyancy countermeasures is passed.

躯体1を所定深さまで沈設したら、底版2下に
は水中コンクリート12を打設し、底版2上には
アースアンカー5のPCストランド7に被せるよ
うにして鋼管等のパイプ9を水面上まで立上げ
る。この状態で、一旦PCストランド7の上端部
をパイプ9上端に仮定着させる。これにより、躯
体1は内部の清水または泥水8排出しても浮力に
抵抗させることができる。
After the frame 1 has been sunk to a predetermined depth, underwater concrete 12 is placed under the bottom slab 2, and a pipe 9 such as a steel pipe is raised above the water surface so as to cover the PC strand 7 of the earth anchor 5 on the bottom slab 2. . In this state, the upper end of the PC strand 7 is temporarily attached to the upper end of the pipe 9. Thereby, the frame 1 can resist buoyancy even if fresh water or muddy water 8 is discharged from inside.

また、図中15は後述のようにして、早期に底
版2のアースアンカー用貫通孔4からの地下水を
侵入を防止するための止水装置であり、躯体1の
内部の清水または泥水8を排出するとともに、止
水装置15を作用させて躯体1内部の水を排除し
た状態で、PCストランド7を底版2の上部位置
に定着することができる。なお、止水装置15は
特に、デイープウエル14等により地下水位を下
げても不透水層bの下からアースアンカー5に沿
つて上がつてくる被圧地下水の侵入を防止するの
に効果が大きい。
In addition, 15 in the figure is a water stop device to prevent groundwater from entering from the earth anchor through hole 4 of the bottom plate 2 at an early stage, as will be described later. At the same time, the PC strand 7 can be fixed at the upper position of the bottom plate 2 while the water stop device 15 is activated to eliminate water inside the frame 1. Note that the water stop device 15 is particularly effective in preventing the intrusion of pressurized groundwater rising from below the impermeable layer b along the earth anchor 5 even if the groundwater level is lowered by the deep well 14 or the like. .

第2図a,bは止水装置15の構造の一例を示
したもので、シース16内に複数本のPCストラ
ンド7を通したアースアンカー5の途中にシース
16より太径のパイプからなるパツカー収納部1
7を取り付け、このパツカー収納部17にPCス
トランド7をドーナツ状に取り巻く袋体からなる
止水パツカー18を装着してある。止水パツカー
18はゴムびき布あるいはゴム、プラスチツク等
からなり、下部には地上からグラウト材を送り込
むためのグラウトチユーブ21、上部にはエアー
抜きチユーブが取り付けてあり、空気圧または水
圧により作動させて仮止水でき、本止水を行なう
時には止水パツカー18をグラウト注入により膨
らませて、PCストランド7に密着させる。また
PCストランド7間の間〓については、あらかじ
め止水区間の上下にゴムあるいはプラスチツク、
金属等の止水用スペーサー19の取り付け、間に
シリコンゴム等の充填材20を詰めておくことに
より、膨らんだ止水パツカー18に押圧されて、
地下水の侵入が防止される。なお、止水スペーサ
ーの構造や、止水パツカー18と接触する個数は
地下水圧の大きさによつて換える。軽微なときは
星型スペーサーを少なくとも一個止水パツカー1
8と接触させればよい。
Figures 2a and 2b show an example of the structure of the water stop device 15, in which a sheath 16 has a plurality of PC strands 7 passed through the earth anchor 5, and a pipe with a diameter larger than the sheath 16 is inserted in the middle of the earth anchor 5. Storage part 1
7 is attached, and a waterproof packer 18 consisting of a bag surrounding the PC strand 7 in a donut shape is attached to the packer storage part 17. The water stopper 18 is made of rubber-lined cloth, rubber, plastic, etc., and has a grout tube 21 at the bottom for feeding grout material from the ground, and an air vent tube at the top, which is operated by air or water pressure to temporarily release the water. Water can be stopped, and when performing the actual water stopping, the water stopping packer 18 is inflated by grout injection and brought into close contact with the PC strand 7. Also
For the space between 7 PC strands, place rubber or plastic on the top and bottom of the water stop section in advance.
By attaching a water stop spacer 19 made of metal or the like and filling the space with a filler 20 such as silicone rubber, the spacer is pressed by the swollen water stop spacer 18.
Groundwater intrusion is prevented. The structure of the water stop spacer and the number of spacers that come into contact with the water stop spacer 18 are changed depending on the magnitude of the groundwater pressure. If it is minor, use at least one star-shaped spacer water stopper 1
8 should be brought into contact with it.

〔発明の効果〕〔Effect of the invention〕

この発明の工法では沈設した躯体内部に沈設荷
重としての清水または泥水を満たしたまま、躯体
底版よりパイプを水上まで立上げ、底版のスラブ
に定着させる本設アースアンカーを一旦水上でパ
イプ上端に仮定着させた後、清水または泥水を排
出してアースアンカーの本定着を行なうので、全
施工期間にわたつて安定した状態で施工でき、デ
イープウエル等による地下水位の低下も少なくて
済むため周辺地盤に悪影響を及ぼす心配も少な
い。
In the construction method of this invention, the pipe is raised above the water from the bottom plate of the structure while the inside of the submerged structure is filled with fresh water or muddy water as a submerged load, and the permanent earth anchor, which is fixed to the slab of the bottom plate, is temporarily attached to the top end of the pipe above the water. After the ground anchor is installed, clear water or muddy water is discharged to perform the final fixation of the earth anchor, so construction can be carried out in a stable state over the entire construction period, and there is less lowering of the groundwater level due to deep wells, etc., so it does not affect the surrounding ground. There is little worry about negative effects.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の一実施例を示す断面図、第
2図a,bはそれぞれ止水装置の縦断面図、横断
面図である。 1……躯体、2……底版、3……刃口、4……
貫通孔、5……アースアンカー、6……定着部、
7……PCストランド、8……清水または泥水、
9……パイプ、10……仮定着部、12……水中
コンクリート、13……地中連続壁、14……デ
イープウエル、15……止水装置、16……シー
ス、17……パツカー収納部、18……止水パツ
カー、19……止水用スペーサー、20……充填
材、21……グラウトチユーブ、22……エアー
抜きチユーブ、a……地下水位、b……不透水
層。
FIG. 1 is a sectional view showing an embodiment of the present invention, and FIGS. 2a and 2b are a vertical sectional view and a horizontal sectional view, respectively, of a water stop device. 1...Main body, 2...Bottom plate, 3...Blade mouth, 4...
Through hole, 5...Earth anchor, 6...Fixing part,
7...PC strand, 8...Clear water or muddy water,
9... Pipe, 10... Temporary attachment part, 12... Underwater concrete, 13... Underground continuous wall, 14... Deep well, 15... Water stop device, 16... Sheath, 17... Police car storage section , 18... Water stop packer, 19... Water stop spacer, 20... Filler, 21... Grout tube, 22... Air vent tube, a... Groundwater level, b... Impermeable layer.

Claims (1)

【特許請求の範囲】[Claims] 1 地上で構築した躯体内に清水または泥水を満
たして浮力に対抗させながら、底版下を掘削して
順次沈設して行く地下構造物の構築方法におい
て、所定深さまで沈設したら、躯体の底版よりア
ースアンカーのアンカー部材を貫通させたパイプ
を水上まで立上げ、該パイプ上部でアンカー部材
を仮定着させて躯体内部の清水または泥水を排除
した後、底版へのアンカー部材の定着を行なうこ
とを特徴とする地下構造物の構築方法。
1. In this method of constructing underground structures, the structure constructed above ground is filled with fresh water or muddy water to counteract buoyancy, while the bottom slab is excavated and the structure is sunk one after another.When the structure is sunk to a predetermined depth, it is grounded from the bottom slab of the skeleton. A pipe passing through the anchor member of the anchor is raised above water, the anchor member is temporarily attached to the upper part of the pipe, fresh water or muddy water inside the frame is removed, and then the anchor member is fixed to the bottom plate. How to construct an underground structure.
JP61033644A 1986-02-18 1986-02-18 Construction of underground structure Granted JPS62194326A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61033644A JPS62194326A (en) 1986-02-18 1986-02-18 Construction of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61033644A JPS62194326A (en) 1986-02-18 1986-02-18 Construction of underground structure

Publications (2)

Publication Number Publication Date
JPS62194326A JPS62194326A (en) 1987-08-26
JPH047779B2 true JPH047779B2 (en) 1992-02-13

Family

ID=12392154

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61033644A Granted JPS62194326A (en) 1986-02-18 1986-02-18 Construction of underground structure

Country Status (1)

Country Link
JP (1) JPS62194326A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0258639A (en) * 1988-05-11 1990-02-27 Toda Constr Co Ltd Correction for tilt and unequal sinking of structure
JPH04125399A (en) * 1990-09-13 1992-04-24 Ohbayashi Corp Underground type storage tank structure

Also Published As

Publication number Publication date
JPS62194326A (en) 1987-08-26

Similar Documents

Publication Publication Date Title
WO2017139828A1 (en) Improved caisson emplacement system and method
US6220789B1 (en) Integrated excavation shoring building foundation method
KR100360462B1 (en) Method to construct a structure on soft soil and the structure thereof
JPH06146305A (en) Underwater foundation and installation method thereof
CN216194845U (en) Pebble covering layer steel sheet pile cofferdam system
JPH047779B2 (en)
JP2726611B2 (en) How to set up an open caisson
JP2876076B2 (en) Underground structure construction method
JPS598833A (en) Settling work of caisson in foundation work
JP2718241B2 (en) Foundation construction method on soft submarine ground
JPS62107115A (en) Method for sink laying underground sructural body
JP2821934B2 (en) Underground structure construction method
CN111485555A (en) Foundation pit supporting system
JPH0439536B2 (en)
JP2838324B2 (en) Shaft bottom water stoppage method
JPS62233333A (en) Water stopper for earth anchor
CN205557573U (en) Underground structure
JP2003041586A (en) Method for suppressing deformation quantity of earth retaining wall
JPH0562170B2 (en)
JP2784314B2 (en) How to set up an open caisson
JP2874906B2 (en) Shaft construction method
JPH10102477A (en) Method for improving confined ground right under existing structure and water sealing device for use in the method
JPH116164A (en) Construction method for underground structure
JPS6018769B2 (en) Construction method of underground structure
JP3614587B2 (en) How to install a shaft in the groundwater under pressure