JPH0477087B2 - - Google Patents
Info
- Publication number
- JPH0477087B2 JPH0477087B2 JP1152576A JP15257689A JPH0477087B2 JP H0477087 B2 JPH0477087 B2 JP H0477087B2 JP 1152576 A JP1152576 A JP 1152576A JP 15257689 A JP15257689 A JP 15257689A JP H0477087 B2 JPH0477087 B2 JP H0477087B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- cross
- reinforcing bar
- underground continuous
- partition plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000005192 partition Methods 0.000 claims description 17
- 230000003014 reinforcing effect Effects 0.000 claims description 14
- 239000004575 stone Substances 0.000 claims description 10
- 238000010276 construction Methods 0.000 claims description 9
- 238000009412 basement excavation Methods 0.000 claims description 7
- 239000000463 material Substances 0.000 claims description 4
- 230000002265 prevention Effects 0.000 claims description 4
- 239000000945 filler Substances 0.000 claims description 3
- 238000000638 solvent extraction Methods 0.000 claims 1
- 238000000034 method Methods 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 3
- 229910000278 bentonite Inorganic materials 0.000 description 3
- 239000000440 bentonite Substances 0.000 description 3
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000004140 cleaning Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 125000006850 spacer group Chemical group 0.000 description 2
- 229920001875 Ebonite Polymers 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000002440 industrial waste Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、地中連続壁の施工法に関する。[Detailed description of the invention] [Industrial application field] The present invention relates to a method of constructing an underground continuous wall.
地中連続壁は従来、仮土留壁及び止水壁として
使用されることが多かつたが、最近の傾向として
本体構造物に採用されることも多く、それに伴つ
て、超深度化、超壁厚化が進み規模も急速に大型
化してきている。
In the past, underground continuous walls were often used as temporary soil retaining walls and water-stop walls, but as a recent trend, they are often used in main structures, and along with this, super-deep walls and super-walls are being used. It is becoming thicker and rapidly increasing in size.
このような本体構造物に採用される地中連続壁
では、設計上の要請及び施工上における他の構造
物との取り合い等から、深さ方向に断面形状(壁
厚)を変化させる構造が有効な場合も多い。 For underground continuous walls used in such main structures, it is effective to have a structure in which the cross-sectional shape (wall thickness) changes in the depth direction due to design requirements and coordination with other structures during construction. There are many cases.
従来は、第19図に示すように、上下同一断面
の地中連続壁20を施工し、コンクリート硬化後
内部掘削に伴つて不要部分21を斫り撤去し、上
部の断面径が縮小する地中連続壁20′を得てい
た。 Conventionally, as shown in Fig. 19, an underground continuous wall 20 with the same cross-section at the top and bottom is constructed, and after the concrete has hardened, the unnecessary part 21 is removed as the internal excavation is carried out to create an underground wall with a reduced cross-sectional diameter at the top. A continuous wall 20' was obtained.
前記従来の方法では変断面地中連続壁を施工す
るのでは、不要部分21にもコンクリートを打設
しなければならず、この不要部分21の硬化した
コンクリートを大量に斫り取る作業が多くの時間
と労力を費やし、斫り取つたコンクリートの塊を
産業廃棄物として処分しなければならず非常に面
倒である。
When constructing an underground continuous wall with a variable cross-section using the conventional method, concrete must also be poured in unnecessary parts 21, and a lot of work is required to scoop out a large amount of hardened concrete in unnecessary parts 21. It is very troublesome as it takes time and effort to dispose of the scooped-up concrete lumps as industrial waste.
本発明の目的は前記従来例の不都合を解消し、
変断面の地中連続壁を簡単かつ安価に施工できる
地中連続壁の施工法を提供することにある。 The purpose of the present invention is to eliminate the disadvantages of the conventional example,
An object of the present invention is to provide a construction method for an underground continuous wall that can easily and inexpensively construct an underground continuous wall with a variable cross section.
本発明は前記目的を達成するため、掘削、スラ
イム処理が完了後、断面径が同一の掘削溝内に、
上部をコンクリート流出防止仕切板で縦方向に仕
切つて断面径が縮小する鉄筋篭を挿入し、該鉄筋
篭内にトレミー管を建て込んで、鉄筋篭下部の非
縮小変断面部では通常通り全断面にコンクリート
を打設し、上部の縮小変断面部では仕切板外側に
押さえ用の充填物を介在させてコンクリートを天
端まで打設することを要旨とするものである。
In order to achieve the above-mentioned object, the present invention has the following objectives: After the completion of excavation and slime treatment, in an excavated trench with the same cross-sectional diameter,
A reinforcing bar cage with a reduced cross-sectional diameter is inserted by dividing the upper part vertically with a partition plate to prevent concrete spillage, and a tremie pipe is built into the reinforcing bar cage, so that the entire cross section of the lower part of the reinforcing bar cage is not reduced as usual. The gist of the project is to pour concrete to the top of the partition, and in the reduced section at the top, filler is placed on the outside of the partition plate for holding down, and the concrete is poured all the way to the top.
本発明によれば、コンクリートは上部の断面径
が縮小する鉄筋篭にしたがつて打設すればよく、
従来のように不要部分にもコンクリートを打設す
る必要がないので、この不要部分のコンクリート
を大量に斫り取ることや斫り取つたコンクリート
を処分する手間がなくなる。
According to the present invention, concrete can be poured in accordance with the reinforcing bar cage whose cross-sectional diameter at the top is reduced;
Unlike the conventional method, there is no need to pour concrete into unnecessary areas, so there is no need to scoop up a large amount of concrete from unnecessary areas or to dispose of the concrete that has been scooped out.
以下、図面について本発明の実施例を詳細に説
明する。
Embodiments of the present invention will be described in detail below with reference to the drawings.
第1図〜第8図は本発明の地中連続壁の施工法
の1実施例を示す各工程の正面図、第9図、第1
0図は第7図、第8図の工程における側面図で、
図中1は先行エレメント、2は砕石、3は先行エ
レメント端の継手筋を保護するカバープレートで
ある。 Figures 1 to 8 are front views of each process showing one embodiment of the underground wall construction method of the present invention, Figures 9 and 1.
Figure 0 is a side view of the process in Figures 7 and 8.
In the figure, 1 is a leading element, 2 is crushed stone, and 3 is a cover plate that protects the joint muscle at the end of the leading element.
第1図に示すように、クローラクレーン等のベ
ースマシン4から吊り下げた掘削機5(エレクト
ロミル)で後行エレメント用の断面径が同一の掘
削溝6を掘削する。孔内は孔壁の崩壊防止用のベ
ントナイト溶液7を充填する。 As shown in FIG. 1, an excavation machine 5 (electro mill) suspended from a base machine 4 such as a crawler crane excavates an excavation groove 6 having the same cross-sectional diameter for a trailing element. The inside of the hole is filled with a bentonite solution 7 for preventing collapse of the hole wall.
次いで第2図に示すように、先行エレメント1
の仕切鋼板を清掃するように清掃機8をカバープ
レート3内に吊り下ろし、継手部の清掃を行う。 Then, as shown in FIG.
The cleaning machine 8 is lowered into the cover plate 3 so as to clean the partition steel plate, and the joint portion is cleaned.
第3図に示すようにカバープレート3を撤去
し、第4図に示すように掘削機5等でのスライム
処理及びベントナイト溶液7を良液に置換する。 As shown in FIG. 3, the cover plate 3 is removed, and as shown in FIG. 4, the slime is treated with an excavator 5 or the like and the bentonite solution 7 is replaced with a good solution.
以上は従来例と同じであるが、第5図に示すよ
うに本発明はこのようにして得た掘削溝6内に独
自の鉄筋篭9を吊り下ろす。 The above is the same as the conventional example, but as shown in FIG. 5, the present invention suspends a unique reinforcing bar cage 9 into the excavated groove 6 thus obtained.
第11図、第12図はこの鉄筋篭9の一例を示
すもので、下部9aは非縮小変断面部であるが、
上部9bをコンクリート流出防止仕切板10で縦
方向に仕切つて断面径が縮小するものとした。 FIG. 11 and FIG. 12 show an example of this reinforcing bar basket 9, and the lower part 9a is a non-reduced cross-sectional part,
The upper part 9b is vertically partitioned by a concrete outflow prevention partition plate 10 to reduce the cross-sectional diameter.
このコンクリート流出防止仕切板10は鉄板、
木板でもよいが、本実施例では第17図、第18
図に示すようにアングル材16で枠を形成し、こ
の枠にエキスパンドメタルによる金網10aを取
付け、さらにその一面に土木シート10bをキヤ
ンバス状に張設してドライビツト17で周囲を止
めて形成する。図中18は、枠端部に設ける硬質
ゴム板である。 This concrete spill prevention partition plate 10 is a steel plate,
Although a wooden board may be used, in this example, the wooden board shown in Figs.
As shown in the figure, a frame is formed from angle material 16, a wire mesh 10a made of expanded metal is attached to this frame, and a civil engineering sheet 10b is stretched over one side of the frame in a canvas shape, and the surrounding area is fixed with dry bits 17 to form the frame. In the figure, 18 is a hard rubber plate provided at the end of the frame.
なお、該仕切板10は、非縮小変断面部である
下部9aから縮小変断面部である上部9bへと変
化する下部9aの上端までも水平に仕切るように
してもよい。 Note that the partition plate 10 may also horizontally partition the upper end of the lower part 9a, which changes from the lower part 9a, which is a non-reduced cross-section part, to the upper part 9b, which is a reduced cross-section part.
このように鉄筋篭9は上部9bが仕切板10で
縦方向に仕切られて断面径が縮小するものである
が、該仕切板10の外側にもラチス状に補強筋1
1が組まれ、外形状の幅は上下で変わらないよう
にして、掘削溝6内へのセツトの容易性を確保し
た。図中12は、掘削溝6の孔壁とのクリアラン
スをとるためのスペーサーである。 In this way, the upper part 9b of the reinforcing bar cage 9 is partitioned in the vertical direction by the partition plate 10 so that the cross-sectional diameter is reduced, but there are also reinforcing bars 1 in a lattice shape on the outside of the partition plate 10.
1 is assembled, and the width of the outer shape is made the same on the top and bottom to ensure ease of setting into the excavated groove 6. In the figure, reference numeral 12 denotes a spacer for ensuring clearance with the hole wall of the excavated groove 6.
第6図に示すように該鉄筋篭9内にトレミー管
13を建て込み、第7図、第9図に示すように鉄
筋篭9の下部9aの非縮小変断面部では通常通り
全断面にコンクリート14を打設する。 As shown in FIG. 6, a tremie pipe 13 is built into the reinforcing bar cage 9, and as shown in FIG. 7 and FIG. 14.
第13図〜第16図はこのようなコンクリート
14の打設状態を示す各工程の縦断側面図であ
る。 FIG. 13 to FIG. 16 are longitudinal sectional side views of each step showing the state of placing concrete 14 as described above.
断面変化点Lから上では、第8図、第10図に
示すように、コンクリート14を先行して打設
し、前記仕切板10の外側に押さえ用の充填物と
して砕石15を500mm以内の遅れで投入する。こ
のようにして、コンクリート14の打設に並行し
てコンクリート圧とのバランスを保つため砕石1
5を投入し、地中連続壁の天端までコンクリート
14を打設する。 Above the cross-sectional change point L, as shown in FIGS. 8 and 10, concrete 14 is placed in advance, and crushed stone 15 is placed as a holding filler on the outside of the partition plate 10 with a delay of within 500 mm. Insert it. In this way, in parallel with the pouring of concrete 14, crushed stone 1 is used to maintain a balance with the concrete pressure.
5 and pour concrete 14 up to the top of the underground continuous wall.
さらに、地中連続壁天端AからGLまでの範囲
は全断面に砕石15を投入して施工を完了する。 Furthermore, crushed stone 15 is added to the entire section of the underground continuous wall from the top A to GL to complete the construction.
また、砕石15については、地中連続壁の完了
後、内部掘削の時に撤去して変断面の地中連続壁
を完成させる。 Moreover, the crushed stone 15 is removed at the time of internal excavation after completion of the underground continuous wall to complete the underground continuous wall with a variable cross section.
なお、以上の実施例は断面変化点Lは一個のも
のについて述べたが、複数の断面変化を有するも
のについても本発明は対応が可能であり、また、
仕切板10の外側の押さえ用の充填物としては、
砕石によらず、土砂、ゴムパツカー(水封入)、
函体、鉄骨支保工などの使用も考えられる。 Although the above embodiments have been described with respect to one cross-sectional change point L, the present invention is also applicable to cases with multiple cross-sectional changes, and
As the filling material for holding down the outside of the partition plate 10,
Regardless of crushed stone, earth and sand, rubber packer (filled with water),
The use of boxes, steel supports, etc. may also be considered.
以上述べたように本発明の地中連続壁の施工法
は、上部の断面径が縮小する変断面の地中連続壁
を施工するのに、従来のように不要部分にもコン
クリートを打設するようなことはなく、簡単かつ
安価に施工でき、工期の短縮も図れるものであ
る。
As described above, the method for constructing an underground continuous wall of the present invention is to construct an underground continuous wall with a variable cross section in which the cross-sectional diameter of the upper part is reduced, without pouring concrete into unnecessary parts as in the conventional method. This is not the case, and it can be constructed easily and inexpensively, and the construction period can be shortened.
第1図〜第8図は本発明の地中連続壁の施工法
の1実施例を示す各工程の正面図、第9図、第1
0図は第7図、第8図の工程における側面図、第
11図は本発明で使用する鉄筋篭の側面図、第1
2図は同上要部の側面図、第13図〜第16図は
コンクリートの打設状態を示す側面図、第17図
は仕切板部分の横断平面図、第18図は同上正面
図、第19図は従来例を示す説明図である。
1……先行エレメント、2……砕石、3……カ
バープレート、4……ベースマシン、5……掘削
機、6……掘削溝、7……ベントナイト溶液、8
……清掃機、9……鉄筋篭、9a……下部、9b
……上部、10……仕切板、10a……金網、1
0b……土木シート、11……補強筋、12……
スペーサー、13……トレミー管、14……コン
クリート、15……砕石、16……アングル材、
17……ドライビツト、18……ゴム板、20,
20′……地中連続壁、21……不要部分。
Figures 1 to 8 are front views of each process showing one embodiment of the underground wall construction method of the present invention, Figures 9 and 1.
Figure 0 is a side view of the steps in Figures 7 and 8, Figure 11 is a side view of the reinforcing bar basket used in the present invention, and Figure 1
Figure 2 is a side view of the main part of the same as above, Figures 13 to 16 are side views showing the state of concrete placement, Figure 17 is a cross-sectional plan view of the partition plate part, Figure 18 is a front view of the same as above, Figure 19 The figure is an explanatory diagram showing a conventional example. 1... Leading element, 2... Crushed stone, 3... Cover plate, 4... Base machine, 5... Excavator, 6... Excavation groove, 7... Bentonite solution, 8
... Cleaning machine, 9 ... Reinforced cage, 9a ... Lower part, 9b
... Upper part, 10 ... Partition plate, 10a ... Wire mesh, 1
0b... Civil engineering sheet, 11... Reinforcement bar, 12...
spacer, 13... tremie pipe, 14... concrete, 15... crushed stone, 16... angle material,
17...Drybit, 18...Rubber plate, 20,
20'...Underground continuous wall, 21...Unnecessary part.
Claims (1)
一の掘削溝内に、上部をコンクリート流出防止仕
切板で縦方向に仕切つて断面径が縮小するものと
した鉄筋篭を挿入し、該鉄筋篭内にトレミー管を
建て込んで、鉄筋篭下部の非縮小変断面部では通
常通り全断面にコンクリートを打設し、上部の縮
小変断面部では仕切板外側に押さえ用の充填物を
介在させてコンクリートを天端まで打設すること
を特徴とする地中連続壁の施工法。 2 押さえ用の充填物は砕石であり、鉄筋篭上部
の縮小変断面部では先行してコンクリートを打設
しながら、この砕石を投入していく請求項第1項
記載の地中連続壁の施工法。 3 コンクリート流出防止仕切板は、金網と土木
シートで構成する請求項第1項記載の地中連続壁
の施工法。[Scope of Claims] 1. After the excavation and slime treatment are completed, a reinforcing bar cage whose cross-sectional diameter is reduced by vertically partitioning the upper part with a concrete outflow prevention partition plate is inserted into the excavated trench with the same cross-sectional diameter. Then, a tremie pipe is built inside the reinforcing bar cage, and concrete is poured over the entire cross section of the non-reduced cross section at the bottom of the reinforcing bar cage as usual, and filler is placed on the outside of the partition plate in the upper reduced cross section. An underground continuous wall construction method characterized by pouring concrete all the way to the top with objects in between. 2. Construction of an underground continuous wall according to claim 1, wherein the filling material for holding down is crushed stone, and this crushed stone is poured in while concrete is being poured in advance in the reduced cross-sectional area of the upper part of the reinforcing bar cage. Law. 3. The construction method for an underground continuous wall according to claim 1, wherein the concrete outflow prevention partition plate is composed of a wire mesh and a civil engineering sheet.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15257689A JPH0317314A (en) | 1989-06-15 | 1989-06-15 | Execution of underground continuous wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15257689A JPH0317314A (en) | 1989-06-15 | 1989-06-15 | Execution of underground continuous wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0317314A JPH0317314A (en) | 1991-01-25 |
JPH0477087B2 true JPH0477087B2 (en) | 1992-12-07 |
Family
ID=15543493
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP15257689A Granted JPH0317314A (en) | 1989-06-15 | 1989-06-15 | Execution of underground continuous wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0317314A (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0720413U (en) * | 1993-09-17 | 1995-04-11 | 川崎重工業株式会社 | Non-rotating bolt |
KR101475206B1 (en) | 2013-01-25 | 2014-12-22 | 삼성중공업 주식회사 | Trolley |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5420051A (en) * | 1977-07-15 | 1979-02-15 | Nippon Kokan Tsugite Kk | Surface coating method of pipe joints |
JPS61216929A (en) * | 1985-03-19 | 1986-09-26 | Kumagai Gumi Ltd | Slope formwork |
-
1989
- 1989-06-15 JP JP15257689A patent/JPH0317314A/en active Granted
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5420051A (en) * | 1977-07-15 | 1979-02-15 | Nippon Kokan Tsugite Kk | Surface coating method of pipe joints |
JPS61216929A (en) * | 1985-03-19 | 1986-09-26 | Kumagai Gumi Ltd | Slope formwork |
Also Published As
Publication number | Publication date |
---|---|
JPH0317314A (en) | 1991-01-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102959157B (en) | Build method and the assembly of partition wall | |
JPS5991214A (en) | Head treatment work of on-site pile | |
CN107119695A (en) | A kind of operation support body and construction method for cancelling outer wall of basement backfill | |
JPS62288218A (en) | Settlement caisson | |
CN105155421B (en) | Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water | |
CN207812482U (en) | A kind of stone masonry vertical retaining wall structure ecological reconstruction structure | |
JPH0477087B2 (en) | ||
JPH08209686A (en) | Pile head processing tool and pile head processing construction method for cast-in-place pile | |
JP2010281038A (en) | Earth retaining method | |
JP3674439B2 (en) | Composite type underground continuous wall and construction method of the same wall | |
CN205557573U (en) | Underground structure | |
JPH03206211A (en) | Drain material, soft ground improving structure using drain material and foundation pillar using the same structure | |
JPS6248011B2 (en) | ||
JP2663087B2 (en) | How to build underground structures | |
CN218148385U (en) | Precast concrete foundation ditch bank protection | |
JPS6149452B2 (en) | ||
JPH03122317A (en) | Concrete pile for hollow place and driving method thereof | |
JP2004332368A (en) | Construction method of concrete foundation | |
JP4576768B2 (en) | Composite type underground continuous wall and construction method of the same wall | |
JP2022108444A (en) | Reinforcement method for existing bank | |
JPH0657958B2 (en) | Reverse floor construction method | |
JPH06108459A (en) | Construction of underground continuous wall | |
JPS59177422A (en) | Construction work of underground continuous wall using disposable formwork | |
JP2524579B2 (en) | Reinforcement method of existing retaining wall under water surface | |
JP2506978Y2 (en) | Synthetic retaining wall |