JPH0443129B2 - - Google Patents

Info

Publication number
JPH0443129B2
JPH0443129B2 JP5679986A JP5679986A JPH0443129B2 JP H0443129 B2 JPH0443129 B2 JP H0443129B2 JP 5679986 A JP5679986 A JP 5679986A JP 5679986 A JP5679986 A JP 5679986A JP H0443129 B2 JPH0443129 B2 JP H0443129B2
Authority
JP
Japan
Prior art keywords
reinforcing bars
columns
reinforced concrete
beam reinforcing
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP5679986A
Other languages
Japanese (ja)
Other versions
JPS62215741A (en
Inventor
Shachio Masuzawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP5679986A priority Critical patent/JPS62215741A/en
Publication of JPS62215741A publication Critical patent/JPS62215741A/en
Publication of JPH0443129B2 publication Critical patent/JPH0443129B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】 (技術分野) 本発明は、梁鉄筋挿通用の穴を有する複数のプ
レキヤスト鉄筋コンクリート柱を用いる鉄筋コン
クリート構造物の構築方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (Technical Field) The present invention relates to a method for constructing a reinforced concrete structure using a plurality of precast reinforced concrete columns having holes for inserting beam reinforcing bars.

(従来技術) プレキヤスト鉄筋コンクリート構造物の構築方
法の1つとして、梁鉄筋を有する柱をプレキヤス
ト鉄筋コンクリート製とし、該柱を作業現場にお
いて所定の位置に設置し、次いで該柱に予め設け
られた前記梁鉄筋を隣の柱に予め設けられた梁鉄
筋と所定の長さを有する梁鉄筋で接合し、その後
柱間の梁部分にコンクリートを打設する構築方法
がある。しかし、この構築方法では、梁鉄筋がプ
レキヤスト鉄筋コンクリートに予め設けられてい
るため、柱の運搬時前記梁鉄筋が邪魔になり、運
搬時の作業性が悪く、また施工現場での梁鉄筋の
接合箇所が多く、組立作業が複雑になる。
(Prior Art) As one method for constructing a precast reinforced concrete structure, a column having beam reinforcement is made of precast reinforced concrete, the column is installed at a predetermined position at a work site, and then the beam installed in advance on the column is There is a construction method in which the reinforcing bars are connected to the beam reinforcing bars of a predetermined length on the adjacent columns, and then concrete is poured into the beams between the columns. However, in this construction method, since the beam reinforcing bars are pre-installed on the precast reinforced concrete, the beam reinforcing bars get in the way when transporting the columns, making it difficult to transport the columns, and the joints of the beam reinforcing bars at the construction site are difficult to handle. There are many parts, which complicates assembly work.

プレキヤスト鉄筋コンクリート構造物の構築方
法の他の1つとして、たとえば特公昭51−36924
号公報に記載されているように、水平方向に貫通
する複数の穴を有する柱と、該柱の前記穴に整合
される穴を有する梁とをプレキヤスト鉄筋コンク
リート製とし、作業現場において柱および梁の各
穴を整合させ、整合された各穴に緊張用鋼材を挿
通し、次いで該緊張材の端部を梁に締付固定して
柱と梁とを緊張定着により相互に接合固定する方
法がある。しかし、この構築方法では、柱および
梁の各穴を整合させる作業が面到であり、また柱
と梁の接合を完了するまで梁を吊下げた状態に維
持しなければならないため、組立時の作業性が悪
い。
As another method for constructing precast reinforced concrete structures, for example,
As described in the publication, a column having a plurality of holes penetrating in the horizontal direction and a beam having holes aligned with the holes of the column are made of precast reinforced concrete, and the columns and beams are made of precast reinforced concrete at the work site. There is a method of aligning each hole, inserting a tensioning steel material into each aligned hole, and then tightening and fixing the ends of the tensioning material to the beam, thereby joining and fixing the column and beam to each other by tension fixing. . However, with this construction method, it is difficult to align each hole in the columns and beams, and the beams must be kept suspended until the columns and beams are joined, making it difficult to assemble the beams. Poor workability.

(発明の目的) 本発明は、運搬作業および組立作業が容易で、
作業性の良いプレキヤスト鉄筋コンクリート柱を
用いる鉄筋コンクリート構造物の構築方法を提供
することを目的とする。
(Object of the invention) The present invention is easy to transport and assemble;
The purpose of this invention is to provide a method for constructing a reinforced concrete structure using precast reinforced concrete columns with good workability.

(発明の構成) 本発明は、水平方向へ貫通する梁鉄筋挿通用穴
を有する複数のプレキヤスト鉄筋コンクリート柱
を用いる鉄筋コンクリート構造物の構築方法であ
つて、作業現場において前記各柱の前記穴に梁鉄
筋を挿通し、次いで該梁鉄筋の端部を相互に接合
し、その後前記柱間の梁部分にコンクリートを打
設して梁を形成することを特徴とする。
(Structure of the Invention) The present invention is a method for constructing a reinforced concrete structure using a plurality of precast reinforced concrete columns having horizontally penetrating holes for inserting beam reinforcing bars, and in which beam reinforcing bars are inserted into the holes of each column at a work site. are inserted, then the ends of the beam reinforcing bars are joined to each other, and then concrete is poured into the beam portion between the columns to form a beam.

(発明の作用効果) 本発明は、梁鉄筋を施工現場において柱の穴に
挿入すればよく、プレキヤスト鉄筋コンクリート
柱に梁鉄筋を予め設ける必要がない。このため、
本発明によれば、梁鉄筋が運搬作業および組立作
業の邪魔になることがなく、運搬作業および組立
作業が容易になり、これらの作業性が向上する。
(Operations and Effects of the Invention) According to the present invention, the beam reinforcing bars may be inserted into the holes of the columns at the construction site, and there is no need to provide the beam reinforcing bars in the precast reinforced concrete columns in advance. For this reason,
According to the present invention, the beam reinforcing bars do not get in the way of transportation work and assembly work, making the transport work and assembly work easier, and the workability of these works is improved.

また、本発明では、梁鉄筋を柱の穴に挿通させ
た後、梁鉄筋を相互に接合するだけでよく、しか
も柱を所定の位置に設置した後は該柱および梁鉄
筋を吊下げている必要がない。このため、本発明
によれば、組立作業がより容易になり、その作業
性がより向上する。
Furthermore, in the present invention, it is only necessary to insert the beam reinforcing bars into the holes of the columns and then connect the beam reinforcing bars to each other, and after the columns are installed in a predetermined position, the columns and the beam reinforcing bars are suspended. There's no need. Therefore, according to the present invention, the assembly work becomes easier and the workability is further improved.

各穴への梁鉄筋の挿入は、柱を所定の位置に設
置した後または設置する前のいずれであつてもよ
い。各梁鉄筋の接合位置は、接合部に加わるせん
断力が最も小さい梁中央部とすることが好まし
い。各梁鉄筋は、梁部に打設されたコンクリート
の一部が穴に挿入することにより、そのコンクリ
ートにより柱に定着されるが、穴にグラウト材を
柱入して該グラフト材により柱に定着させること
が好ましい。
The beam reinforcing bars may be inserted into each hole either after or before the columns are installed in position. The joint position of each beam reinforcing bar is preferably at the center of the beam where the shear force applied to the joint is the smallest. Each beam reinforcing bar is fixed to the column by inserting a part of the concrete poured into the beam into the hole, but by putting grout material into the hole and fixing it to the column by the graft material. It is preferable to let

(実施例) 以下、図面に示す本発明の実施例について説明
する。
(Example) Hereinafter, an example of the present invention shown in the drawings will be described.

なお、第2図、第3図、第4図、第5図、第7
図および第8図では、各鉄筋およびシース管の配
置状態を示すべく、実際にはコンクリート内に埋
没して現われない各鉄筋およびシース管をも実線
で示す。
In addition, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 7
In the figures and FIG. 8, in order to show the arrangement of each reinforcing bar and sheath pipe, each reinforcing bar and sheath pipe that are actually buried in concrete and do not appear are also shown by solid lines.

第1図〜第3図に示す、本発明で用いるプレキ
ヤスト鉄筋コンクリート柱10は、上下方向へ伸
びる複数の縦鉄筋12と、該縦鉄筋12を相互に
連結する複数の連結鉄筋14と、柱と梁の接合部
すなわち図示の例では柱の上端部に配置された複
数のシース管16とをコンクリート18内に備え
る。縦鉄筋12は、柱10から上方へ突出してい
る。
A precast reinforced concrete column 10 used in the present invention, shown in FIGS. 1 to 3, includes a plurality of vertical reinforcing bars 12 extending in the vertical direction, a plurality of connecting reinforcing bars 14 that interconnect the longitudinal reinforcing bars 12, and a column and a beam. In the illustrated example, a plurality of sheath pipes 16 are disposed in the joint portion of the column, that is, at the upper end of the column, and are provided in the concrete 18. The vertical reinforcing bars 12 protrude upward from the columns 10.

シース管16は、上下方向および水平方向へ間
隔をおいて格子状に交差して配置されており、ま
た外表面および内表面に複数の凹凸を備え、外表
面の凹凸によりコンクリート18に堅固に固定さ
れている。また、シース管16の長さ寸法はシー
ス管16の長て方向における柱10の厚さ寸法と
同じであり、これにより各シース管16は梁鉄筋
挿入用の水平方向へ伸びる穴20を規定する。穴
20は、コンクリート18に直接形成してもよ
い。
The sheath pipes 16 are arranged to intersect in a grid pattern at intervals in the vertical and horizontal directions, and have a plurality of irregularities on the outer and inner surfaces, and are firmly fixed to the concrete 18 due to the irregularities on the outer surface. has been done. Further, the length dimension of the sheath tube 16 is the same as the thickness dimension of the column 10 in the longitudinal direction of the sheath tube 16, so that each sheath tube 16 defines a hole 20 extending in the horizontal direction for inserting the beam reinforcement. . Holes 20 may be formed directly in concrete 18.

なお、第1図に示す柱10は、構造物の一階分
の高さ寸法を有するものであるが、第10図に示
すように構造物の二階分の高さ寸法さらにはそれ
以上の高さ寸法を有する柱10′であつてもよい。
この柱10′の場合、シース管16は、一階部分
および二階部分の各梁と柱との接合箇所にそれぞ
れ配置される。
Note that the pillar 10 shown in FIG. 1 has a height of one floor of a structure, but as shown in FIG. The pillar 10' may have a dimension of 10.
In the case of this column 10', the sheath pipes 16 are arranged at the joints between each beam and the column in the first floor portion and the second floor portion.

このような構造の複数の柱10を用いる鉄筋コ
ンクリート構造物の構築方法は、先ず施工現場に
おいて一階分の各柱10の穴20に第4図〜第6
図に示すように梁主筋すなわり梁鉄筋22を挿通
した後、柱10を所定の位置に設置する。なお、
柱10を所定の位置に設置した後に梁鉄筋22を
穴20に挿通させてもよいが、穴20に梁鉄筋2
2を挿入した後、柱10を所定の箇所に設置すれ
ば、作業能率が向上する。
A method for constructing a reinforced concrete structure using a plurality of columns 10 having such a structure is to first fill the holes 20 of each column 10 for one floor at the construction site as shown in FIGS. 4 to 6.
As shown in the figure, after inserting the main beam reinforcing bars 22, the columns 10 are installed at predetermined positions. In addition,
The beam reinforcing bars 22 may be inserted into the holes 20 after the pillars 10 are installed at predetermined positions.
If the pillar 10 is installed at a predetermined location after inserting the pillar 2, the work efficiency will be improved.

次いで、第6図に示すように各梁鉄筋の端部を
隣りの柱10の穴20に挿通された梁鉄筋22の
端部と溶接、ねじ継手等の接合手段により相互に
接合した後、第7図および第8図に示すように各
穴20にグラウト材24を注入し、梁鉄筋22を
柱10に定着させ、さらに第6図、第7図および
第8図に示すように梁鉄筋にせん断補強筋26を
配置する。グラフト材24の注入と、せん断補強
筋26の配置は、いずれを先に行つてもよい。
Next, as shown in FIG. 6, the end of each beam reinforcing bar is joined to the end of the beam reinforcing bar 22 inserted through the hole 20 of the adjacent column 10 by a joining means such as welding or screw joint. As shown in FIGS. 7 and 8, grouting material 24 is injected into each hole 20, and the beam reinforcing bars 22 are fixed to the columns 10, and as shown in FIGS. Shear reinforcing bars 26 are placed. Either injection of the graft material 24 or placement of the shear reinforcing bars 26 may be performed first.

その後柱10間の梁部分に型枠を配置し、該型
枠により規定される空間にコンクリート18を打
設し、該コンクリートを凝結させて梁30をまた
は梁30と床とを形成することにより一階分の構
造物を構築する。
After that, a formwork is placed in the beam part between the columns 10, concrete 18 is placed in the space defined by the formwork, and the concrete is solidified to form the beam 30 or the beam 30 and the floor. Build a one-story structure.

上記の工程を各階毎に行うことにより、第9図
に示すようなコンクリート構造物32を構築する
ことができる。構造物32の各柱10は、符号3
4で示す位置において上下に隣り合う柱と相互に
接合されている。なお、第10図に示す柱10′
を用いるときは、第11図に示すように、柱と梁
との各接合箇所のシース管16に梁鉄筋22を挿
入することにより、一回で二階分の構造物を構築
してもよい。
By performing the above steps for each floor, a concrete structure 32 as shown in FIG. 9 can be constructed. Each column 10 of the structure 32 is designated by the reference numeral 3
It is mutually joined to vertically adjacent columns at the position indicated by 4. Note that the pillar 10' shown in FIG.
When using, as shown in FIG. 11, a two-story structure may be constructed at one time by inserting beam reinforcing bars 22 into the sheath pipe 16 at each joint between a column and a beam.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明で用いる柱の一実施例を示す正
面図、第2図は第1図の柱の一部を拡大して示す
縦断面図、第3図は第2図の3−3線に沿つて得
た断面図、第4図は柱に梁鉄筋を挿通した状態を
示す第2図と同じ位置の縦断面図、第5図は第4
図の5−5線に沿つて得た断面図、第6図は梁鉄
筋を総合に接合した状態を示す正面図、第7図は
せん断補強筋を配置し、梁鉄筋をグラウト材によ
り柱に定着した状態を示す第2図と同じ位置の縦
断面図、第8図は第7図の8−8線に沿つて得た
断面図、第9図は構築した構造物の一部を示す断
面図、第10図は柱の他の実施例を示す正面図、
第11図は第10図の柱を用いるときの構築方法
の説明図である。 10,10′:柱、20:梁鉄筋挿通用の穴、
22:梁鉄筋、24:グラウト材、30:梁。
Fig. 1 is a front view showing one embodiment of the pillar used in the present invention, Fig. 2 is a vertical cross-sectional view showing a part of the pillar in Fig. 1 enlarged, and Fig. 3 is 3-3 in Fig. 2. Figure 4 is a cross-sectional view taken along the line, Figure 4 is a vertical cross-sectional view at the same position as Figure 2, showing the beam reinforcing bars inserted into the column, and Figure 5 is the same position as Figure 4.
Figure 6 is a cross-sectional view taken along line 5-5 in the figure, Figure 6 is a front view showing the state in which the beam reinforcing bars are joined together, and Figure 7 is a front view showing the state in which the beam reinforcing bars are connected together. A vertical cross-sectional view taken at the same position as Fig. 2 showing the established state, Fig. 8 is a cross-sectional view taken along line 8-8 in Fig. 7, and Fig. 9 is a cross-sectional view showing a part of the constructed structure. Figure 10 is a front view showing another embodiment of the pillar,
FIG. 11 is an explanatory diagram of a construction method when using the pillars shown in FIG. 10. 10, 10': Column, 20: Hole for inserting beam reinforcement,
22: Beam reinforcing bar, 24: Grout material, 30: Beam.

Claims (1)

【特許請求の範囲】 1 水平方向へ貫通する梁鉄筋挿通用穴を有する
複数のプレキヤスト鉄筋コンクリート柱を用いる
鉄筋コンクリート構造物の構築方法であつて、作
業現場において前記各柱の前記穴に梁鉄筋を挿通
し、次いで該梁鉄筋の端部を相互に接合し、その
後前記柱間の梁部分にコンクリートを打設して梁
を形成することを含む、鉄筋コンクリート構造物
の構築方法。 2 前記梁鉄筋を前記梁部分の中央部において相
互に接合する、特許請求の範囲第1項に記載の鉄
筋コンクリートの構築方法。 3 前記梁鉄筋を前記柱に挿通した後、前記柱を
所定の位置に設置する、特許請求の範囲第1項に
記載の鉄筋コンクリート構造物の構築方法。
[Scope of Claims] 1. A method for constructing a reinforced concrete structure using a plurality of precast reinforced concrete columns having horizontally penetrating holes for inserting beam reinforcing bars, the method comprising inserting beam reinforcing bars into the holes of each of the columns at a work site. and then joining the ends of the beam reinforcing bars to each other, and then pouring concrete into the beam portion between the columns to form a beam. 2. The reinforced concrete construction method according to claim 1, wherein the beam reinforcing bars are mutually joined at the center of the beam portion. 3. The method for constructing a reinforced concrete structure according to claim 1, wherein the pillar is installed at a predetermined position after the beam reinforcing steel is inserted into the pillar.
JP5679986A 1986-03-17 1986-03-17 Construction of reinforced concrete structure Granted JPS62215741A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5679986A JPS62215741A (en) 1986-03-17 1986-03-17 Construction of reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5679986A JPS62215741A (en) 1986-03-17 1986-03-17 Construction of reinforced concrete structure

Publications (2)

Publication Number Publication Date
JPS62215741A JPS62215741A (en) 1987-09-22
JPH0443129B2 true JPH0443129B2 (en) 1992-07-15

Family

ID=13037447

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5679986A Granted JPS62215741A (en) 1986-03-17 1986-03-17 Construction of reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPS62215741A (en)

Also Published As

Publication number Publication date
JPS62215741A (en) 1987-09-22

Similar Documents

Publication Publication Date Title
JPH0518003A (en) Joining method of steel pipe concrete column and half-precast reinforced concrete column
JPH11100854A (en) Building and foundation structure therefor
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
JP3752999B2 (en) Upper and lower integrated bridge and its construction method
JP3424842B2 (en) Joining method of steel reinforced concrete columns in precast method
JPH10219831A (en) Joined building construction between reinforced concrete column and steel frame beam and its joined part structure, and precast reinforced concrete column
JP2880027B2 (en) Joint structure between steel pipe column and reinforced concrete slab
JPH0443129B2 (en)
JP2004052276A (en) Joining structure of column and beam
JP2864906B2 (en) Precast wall joining method
JP2656175B2 (en) Column-beam joint structure
JPH07292857A (en) Pc member with irregular-shaped steel pipe for joint, and connecting method thereof
JPH101956A (en) Underground construction method for building
JPH02221535A (en) Connecting structure for pillar and beam
JPH06316964A (en) Method for constructing joint of precast reinforced concrete column and beam
JP3072534B2 (en) Precast beam member and method of constructing the beam
JPH04185816A (en) Construction of beam in underground wall
JP2558695Y2 (en) Column / beam joint structure
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP2001115464A (en) Joining structure of pile to column
JP2677189B2 (en) Steel beam for joining reinforced concrete columns
JP2984626B2 (en) PC pillar construction method and its PC pillar
JP2914205B2 (en) Installation method of handrail wall or lumbar wall
JPH0216826B2 (en)
JPH0649897A (en) Joining method for beam and pillar and precast concrete pillar applied to above method