JPH04368566A - Foundational construction and form for pile foundation - Google Patents

Foundational construction and form for pile foundation

Info

Publication number
JPH04368566A
JPH04368566A JP14631691A JP14631691A JPH04368566A JP H04368566 A JPH04368566 A JP H04368566A JP 14631691 A JP14631691 A JP 14631691A JP 14631691 A JP14631691 A JP 14631691A JP H04368566 A JPH04368566 A JP H04368566A
Authority
JP
Japan
Prior art keywords
formwork
concrete
pile
foundation
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP14631691A
Other languages
Japanese (ja)
Other versions
JP2520524B2 (en
Inventor
Takayuki Ito
伊 藤 高 行
Tomio Katono
上遠野 登美男
Shigenobu Kato
加 藤 重 信
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ando Kensetsu Co Ltd
Original Assignee
Ando Kensetsu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ando Kensetsu Co Ltd filed Critical Ando Kensetsu Co Ltd
Priority to JP3146316A priority Critical patent/JP2520524B2/en
Publication of JPH04368566A publication Critical patent/JPH04368566A/en
Application granted granted Critical
Publication of JP2520524B2 publication Critical patent/JP2520524B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE:To construct a pile foundation footing and an underground beam for a building structure or the like in an efficient manner. CONSTITUTION:A circular form 2 is set up so as to make a pile head part come to a central position and fixed and held on leveling concrete. In addition, each edge 2a of the circular form 2 is fixed to side ends of two adjacent forms 1 and 1 with nails 3 for connection, and a foundational concrete form is solidly assembled and foundation concrete is placed in these forms 1 and 2.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は基礎構築方法及び杭基礎
用型枠に係り、特に建築構造物等の円形の杭基礎コンク
リートを連結するように地中梁を施工する基礎構築方法
と円形杭基礎コンクリート打設用の杭基礎用型枠に関す
る。
[Field of Industrial Application] The present invention relates to a foundation construction method and formwork for pile foundations, and in particular to a foundation construction method for constructing underground beams to connect circular pile foundation concrete for building structures, etc., and circular pile foundations. Concerning formwork for pile foundations for pouring foundation concrete.

【0002】0002

【従来の技術】一般に大規模な建築構造物の基礎には周
辺地盤の状況や建築物の形状重量を考慮し、杭基礎構造
が採用されることが多い。そして各設計、施工条件から
適切な杭種類や杭寸法、配置が決定されるようになって
いる。また、上部構造の荷重はフーチング等を介して各
杭に分配伝達されるが、このとき、杭頭を連結する地中
梁構造を主構造材とし、この地中梁間に捨コンを打設し
てスラブ構造とする構造が多くとられる。この地中梁構
造によれば建物の重量の軽量化が図れるという利点があ
る。ところで、このように杭頭を連結して地中梁を施工
する場合、杭頭に作用する外力を考慮して、その寸法構
造を決定する必要がある。このとき杭頭作用力は杭頭の
固定条件により異なるが、固定構造では一般に地中梁を
介して鉛直支持力V、杭頭曲げモーメントM、水平剪断
力Hが坑基礎フーチングに作用し、この作用力に対して
杭基礎フーチングの構造、寸法が決定される。図5はこ
の種の杭基礎と各杭基礎を地中梁で連結した基礎構造の
例を示した斜視図である。同図において、一部のみが示
されているが、平面形状がほぼ正方形の直方体形状の杭
基礎フーチング20が杭21の配置間隔と一致するよう
に構築されている。さらにこの杭基礎フーチング20よ
り高い梁せいの地中梁Gが杭基礎フーチング20と一体
となるように連結されている。このとき地中梁Gの梁せ
いは上部構造の重量等により決定され、フーチング高さ
より大きくなる場合が多い。図6は杭基礎フーチング2
0と地中梁G部分とを一体的に打設するように組立られ
た型枠23を示したものである。これらの型枠23は、
コンクリート打設面を形成してコンクリート側圧を受け
るせき板24、24…と、型枠形状が変形するのを防止
するためにせき板24を保持固定する端太材25、25
…とから構成されている。せき板24には一般にコンパ
ネと呼ばれる合板やメタルフォームと呼ばれる鋼製型枠
が使用され、端太材25には角鋼管や木材が利用され、
各端太材25は所定位置でフォームタイ26、26…に
よりせき板24に固定されるようになっている。また、
対向するせき板24はセパレータ27により固定保持さ
れ、所定の構造物仕上寸法が確保される。
2. Description of the Related Art Generally, pile foundation structures are often adopted for the foundations of large-scale building structures, taking into consideration the surrounding ground conditions and the shape and weight of the building. Appropriate pile types, pile dimensions, and placement are then determined based on each design and construction condition. In addition, the load of the superstructure is distributed and transmitted to each pile via footings, etc., but at this time, the underground beam structure that connects the pile heads is the main structural material, and waste concrete is poured between the underground beams. A slab structure is often used. This underground beam structure has the advantage of reducing the weight of the building. By the way, when constructing an underground beam by connecting pile heads in this way, it is necessary to determine its dimensional structure in consideration of the external force acting on the pile heads. At this time, the force acting on the pile cap varies depending on the fixing conditions of the pile cap, but in a fixed structure, generally, the vertical support force V, the pile cap bending moment M, and the horizontal shearing force H act on the foundation footing through underground beams. The structure and dimensions of the pile foundation footing are determined based on the acting force. FIG. 5 is a perspective view showing an example of a foundation structure in which this type of pile foundation and each pile foundation are connected by underground beams. Although only a portion is shown in the figure, a pile foundation footing 20 in the shape of a rectangular parallelepiped with a substantially square planar shape is constructed so as to match the arrangement spacing of the piles 21. Furthermore, an underground beam G having a higher beam height than the pile foundation footing 20 is connected to the pile foundation footing 20 so as to be integrated with the pile foundation footing 20. At this time, the beam height of the underground beam G is determined by the weight of the superstructure, etc., and is often larger than the footing height. Figure 6 shows pile foundation footing 2.
This figure shows the formwork 23 assembled to integrally cast the G part 0 and the underground beam G part. These formworks 23 are
Weir plates 24, 24, which form concrete pouring surfaces and receive concrete lateral pressure, and thick timbers 25, 25, which hold and fix the weir plates 24 to prevent the shape of the formwork from deforming.
It is composed of... The weir plate 24 is generally made of plywood called a control panel or a steel formwork called a metal form, and the end pieces 25 are made of square steel pipes or wood.
Each end piece 25 is fixed to the weir plate 24 at a predetermined position by form ties 26, 26, . . . . Also,
The opposing weir plates 24 are fixedly held by separators 27 to ensure a predetermined finished structure dimension.

【0003】0003

【発明が解決しようとする課題】しかしながら、上述の
杭基礎フーチングの型枠では形状が複雑でメタルフォー
ムのような定尺材が利用できないので、コンパネを加工
して杭基礎フーチングの寸法に合わせて各型枠を製作し
なければならず、多数の杭が打設されている基礎等では
地中梁と杭基礎とを一体的に施工するのが煩雑である。 また、図7に示したようにせき板が直線を構成している
ので、コンクリート側圧がせき板に等分布荷重として作
用し、せき板のほぼ中央位置で最大曲げモーメントが生
じ、その部分のせき板の撓みが最大となる。そして端太
材による補強が不十分だと硬化前のコンクリートの圧力
でせき板が外方にはらみ出し、型枠が崩壊してしまうと
いうおそれがある。さらに、平板型枠の組合せによる四
角いフーチングは、設計強度が必要とするものより、多
くのコンクリートと鉄筋とを必要としていた。
[Problem to be Solved by the Invention] However, the formwork for the pile foundation footing described above has a complicated shape, and regular length materials such as metal foam cannot be used, so the control panels are processed to match the dimensions of the pile foundation footing. Each type of formwork must be manufactured, and in the case of a foundation where a large number of piles are driven, it is complicated to construct the underground beam and the pile foundation in one piece. In addition, since the weir plate forms a straight line as shown in Figure 7, the concrete side pressure acts on the weir plate as a uniformly distributed load, and the maximum bending moment occurs at approximately the center of the weir plate, causing the weir in that area to The deflection of the plate is maximum. If the reinforcement with timbers is insufficient, the pressure of the unhardened concrete will cause the weir plates to bulge outward, and there is a risk that the formwork will collapse. In addition, the square footing with the combination of flat plate formwork required more concrete and rebar than the design strength required.

【0004】0004

【課題を解決するための手段】上記目的を達成するため
に、本発明は杭頭部が中心位置となるように円弧状型枠
を配置して捨てコンクリート上に固定保持するとともに
、上記円弧状型枠の縁部を隣接する型枠の側端部に連結
し基礎コンクリート用型枠を組立て、型枠内に基礎コン
クリートを打設するようにしたことを特徴とするもので
ある。
[Means for Solving the Problems] In order to achieve the above object, the present invention arranges an arc-shaped formwork so that the pile head is at the center position and fixes it on the concrete, and This method is characterized in that the edge of the formwork is connected to the side end of an adjacent formwork to assemble a formwork for foundation concrete, and the foundation concrete is poured into the formwork.

【0005】また、上述の基礎構築に使用する杭基礎用
型枠として薄板材を所定曲げ半径で湾曲して円弧状とし
、縁部に連結用の帯板状リブを形成したことを特徴とす
るものである。
[0005] Furthermore, as the formwork for the pile foundation used in the above-mentioned foundation construction, a thin plate material is bent at a predetermined bending radius to form an arc shape, and a strip-like rib for connection is formed at the edge. It is something.

【0006】[0006]

【作用】本発明によれば、杭頭部が中心位置となるよう
に円弧状型枠を配置して捨てコンクリート上に固定保持
するとともに、上記円弧状型枠の縁部を隣接する型枠の
側端部に連結し基礎コンクリート用型枠を組立て、型枠
内に基礎コンクリートを打設するようにしたので、杭基
礎部分の型枠を簡単に組立てることができるとともに、
作用するコンクリート側圧が型枠の円周方向引張力に変
換され、型枠の局部的なはらみ出しを防止し、設計が期
待する円弧状のフーチングを構築できる。
[Operation] According to the present invention, the arcuate formwork is arranged so that the pile head is at the center position and is fixedly held on the concrete, and the edge of the arcuate formwork is connected to the adjacent formwork. The formwork for the foundation concrete is assembled by connecting it to the side end, and the foundation concrete is poured into the formwork, so the formwork for the pile foundation part can be easily assembled.
The applied concrete lateral pressure is converted into a tensile force in the circumferential direction of the formwork, preventing local protrusion of the formwork and creating the arc-shaped footing expected by the design.

【0007】また、上述の基礎構築に使用する杭基礎用
型枠として薄板材を所定曲げ半径で湾曲して円弧状とし
、縁部に連結用の帯板状リブを形成したので、簡単な構
造で強固な型枠とすることができるとともに、隣接する
型枠と簡単かつ確実に連結できる。
[0007] Furthermore, as the formwork for the pile foundation used in the above-mentioned foundation construction, a thin plate material is bent into an arc shape with a predetermined bending radius, and strip-like ribs for connection are formed at the edges, resulting in a simple structure. Not only can the formwork be made strong, but it can also be easily and reliably connected to adjacent formworks.

【0008】[0008]

【実施例】以下本発明による基礎構築方法の一実施例を
添付図面を参照して説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the foundation construction method according to the present invention will be described below with reference to the accompanying drawings.

【0009】図1において、符号1は地中梁Gの型枠を
示しており、この型枠1は予め打設された捨てコンクリ
ート面上の墨打ちマークに従って長手方向に配置され、
図示しない杭頭部近傍において所定間隔をあけて配置さ
れている。さらに地中梁Gの各型枠1の端部には薄鋼板
からなる杭基礎用型枠2、2が円弧状に湾曲された状態
で取着されている。本実施例ではこの型枠2は厚さ0.
8mmの着色防錆鋼板を用いて、直径1.2mの円弧の
一部を形成するように湾曲されており、端部には幅10
cmの連結用のリブ2aが折り返すようにして一体的に
形成されている。このリブ2aを地中梁部の型枠1の端
部にあてがい、さらに内側から釘3、3…により地中梁
型枠1の端部に固定し、一体的な基礎コンクリート用の
型枠を組立てる。ところで、この杭基礎フーチング4の
ほぼ中心部には図2に示したように杭5が配置されてお
り、この杭5の杭頭処理を設計仕様に基づいて行う。ま
た、この杭頭処理された鉄筋部分と地中梁の鉄筋との接
合部に図示しない補強鉄筋を配置し、地中梁Gからの作
用力を確実に杭頭に伝達できるようにする。
In FIG. 1, reference numeral 1 indicates a formwork for an underground beam G, and this formwork 1 is arranged in the longitudinal direction according to the marking marks on the surface of the sacrificial concrete placed in advance.
They are arranged at predetermined intervals near the pile head (not shown). Further, pile foundation forms 2, 2 made of thin steel plates are attached to the ends of each form 1 of the underground beam G in a curved arc shape. In this embodiment, the formwork 2 has a thickness of 0.
It is made of 8mm colored rust-proof steel plate and is curved to form part of a circular arc with a diameter of 1.2m, with a width of 10mm at the end.
A connecting rib 2a of cm is integrally formed so as to be folded back. This rib 2a is applied to the end of the formwork 1 of the underground beam section, and further fixed to the end of the underground beam formwork 1 from the inside with nails 3, 3... to form an integral formwork for foundation concrete. Assemble. Incidentally, a pile 5 is arranged approximately at the center of the pile foundation footing 4 as shown in FIG. 2, and the pile head treatment of the pile 5 is performed based on design specifications. In addition, reinforcing reinforcing bars (not shown) are arranged at the joints between the reinforcing bars treated with the pile caps and the reinforcing bars of the underground beams, so that the acting force from the underground beams G can be reliably transmitted to the pile caps.

【0010】また、地中梁型枠1のせき板を保持固定す
るために図示しない端太材が所定間隔で配置されている
が、フーチングの円形型枠部分には全く端太材は配置さ
れていない。ここでこの型枠内にコンクリートポンプ等
の図示しないコンクリート供給装置からコンクリートを
供給し、所定手順により順次打設する。このとき型枠1
、2内のまだ固まらないコンクリートの側圧は図2に示
したように円周方向に均等に作用する。したがってこの
コンクリート側圧はせき板に対して曲げモーメントを発
生させずに円周方向の引張力に変換される。この円周方
向引張力は鋼板の許容引張強度に比し大変小さく、型枠
2の半径方向の変形はほとんど生じない。そのためこの
円形型枠2部分は補強用の端太材を全く必要としないこ
とがわかる。
[0010]Although thick timbers (not shown) are placed at predetermined intervals to hold and fix the sheathing plates of the underground beam formwork 1, no thick timbers are placed in the circular formwork portion of the footing. Not yet. Here, concrete is supplied into the formwork from a concrete supply device (not shown) such as a concrete pump, and concrete is sequentially poured according to a predetermined procedure. At this time, formwork 1
, 2, the lateral pressure of the unhardened concrete acts uniformly in the circumferential direction as shown in FIG. Therefore, this concrete lateral pressure is converted into a tensile force in the circumferential direction without generating a bending moment on the weir. This circumferential tensile force is very small compared to the allowable tensile strength of the steel plate, and almost no radial deformation of the formwork 2 occurs. Therefore, it can be seen that this circular formwork 2 portion does not require any reinforcement material.

【0011】図3は上述の円形型枠を使用して地中梁G
と杭基礎フーチング4とを一体的に構築した一例を示し
たものである。なお、円形の型枠2の上部の梁は別の梁
用の型枠を連結して所定の打継ぎ処理を行って構築した
ものである。
FIG. 3 shows an underground beam G using the above-mentioned circular formwork.
This figure shows an example in which the pile foundation footing 4 and the pile foundation footing 4 are integrally constructed. Note that the upper beam of the circular formwork 2 is constructed by connecting formworks for other beams and performing a predetermined joining process.

【0012】以上に述べた円形型枠2は予め円弧状に形
成された型枠を連結したものであるが、端部にリブ2a
の屈曲された平板状のせき板を型枠セット時に所定の形
状に湾曲させ、コンクリート側圧により型枠形状が円形
となるようにしても良い。このような場合には樹脂製の
せき板を使用してもよい。いずれの場合にも他の杭基礎
部分に容易に転用することができる。
The circular formwork 2 described above is formed by connecting formworks formed in an arc shape in advance, and has ribs 2a at the ends.
The bent flat plate-like weir plate may be bent into a predetermined shape when setting the formwork, and the shape of the formwork may be made circular by concrete side pressure. In such cases, resin weir plates may be used. In either case, it can be easily diverted to other pile foundation parts.

【0013】図4は上述の実施例の変形例として円弧状
の型枠を平板状の型枠と組合わせた型枠の組立て例を示
したものである。同図(a)は円柱状の独立基礎フーチ
ングを構築するためのものであり、同図(b)は複数の
杭に対する小判型フーチングを構築する例を示したもの
である。この場合は直線状型枠部分には所定の補強用の
端太材を配置することが好ましい。同図(c)は矩形フ
ーチングの隅角部に円弧状型枠を適用した例を示してお
り、この円弧状の型枠により型枠端部の仕舞を簡単化す
ることができる。
FIG. 4 shows an assembly example of a formwork in which an arc-shaped formwork is combined with a flat formwork as a modification of the above-described embodiment. Figure (a) shows an example for constructing a cylindrical independent foundation footing, and figure (b) shows an example of constructing an oval-shaped footing for a plurality of piles. In this case, it is preferable to arrange a predetermined reinforcing end piece in the linear formwork portion. The figure (c) shows an example in which an arcuate formwork is applied to the corner portion of a rectangular footing, and this arcuate formwork makes it possible to simplify the closing of the ends of the formwork.

【0014】[0014]

【発明の効果】以上の説明から明らかなように、本発明
によれば杭頭部が中心位置となるように複数の円弧状型
枠を固定保持するとともに、上記円弧状型枠の縁部を隣
接する型枠の側端部に連結し基礎コンクリート用型枠を
組立て、型枠内に基礎コンクリートを打設するようにし
たので、杭基礎部分の型枠を簡単に組立てることができ
るとともに、効率良くコンクリート打設することができ
、また、上述の基礎構築に使用する杭基礎用型枠として
薄板材を所定曲げ半径で湾曲して円弧状とし、縁部に連
結用の帯板状リブを形成したので、安価で簡単な構造の
型枠をとすることができ、また設計が期待する円弧状の
フーチングを構築できる等の効果を奏する。
As is clear from the above description, according to the present invention, a plurality of arcuate formworks are fixedly held so that the pile head is at the center position, and the edges of the arcuate formworks are The formwork for the foundation concrete is assembled by connecting it to the side ends of the adjacent formwork, and the foundation concrete is poured into the formwork. This makes it possible to easily assemble the formwork for the pile foundation part, and improves efficiency. Concrete can be placed easily, and as a formwork for the pile foundation used in the above-mentioned foundation construction, thin plate material is bent into an arc shape with a predetermined bending radius, and strip-like ribs for connection are formed at the edges. Therefore, it is possible to use a formwork with an inexpensive and simple structure, and it is also possible to construct an arcuate footing as expected by the design.

【図面の簡単な説明】[Brief explanation of drawings]

【図1】本発明による基礎構築方法の一実施例の態様を
示した組立概念図。
FIG. 1 is an assembly conceptual diagram showing an embodiment of the foundation construction method according to the present invention.

【図2】本発明による基礎構築時のコンクリート側圧分
布説明図。
FIG. 2 is an explanatory diagram of concrete lateral pressure distribution during foundation construction according to the present invention.

【図3】本発明の型枠により構築された地中梁の一部を
示した斜視図。
FIG. 3 is a perspective view showing a part of an underground beam constructed using the formwork of the present invention.

【図4】本発明による円弧状型枠の変形例を示した平面
図。
FIG. 4 is a plan view showing a modified example of the arc-shaped formwork according to the present invention.

【図5】従来の型枠により構築された地中梁の一部を示
した斜視図。
FIG. 5 is a perspective view showing a part of an underground beam constructed using conventional formwork.

【図6】従来の型枠の一例を示した概略平面図。FIG. 6 is a schematic plan view showing an example of a conventional formwork.

【図7】従来の型枠による基礎構築時のコンクリート側
圧分布説明図。
FIG. 7 is an explanatory diagram of concrete lateral pressure distribution during foundation construction using conventional formwork.

【符号の説明】[Explanation of symbols]

1  地中梁型枠 2  杭基礎用型枠 4  杭基礎フーチグ 5  杭 1 Underground beam formwork 2 Formwork for pile foundation 4 Pile foundation footig 5 Pile

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】杭頭部が中心位置となるように円弧状型枠
を配置して捨てコンクリート上に固定保持するとともに
、上記円弧状型枠の縁部を隣接する型枠の側端部に連結
し基礎コンクリート用型枠を組立て、型枠内に基礎コン
クリートを打設するようにしたことを特徴とする基礎構
築方法。
Claim 1: An arc-shaped formwork is arranged so that the pile head is in the center position and fixedly held on the concrete, and the edge of the arc-shaped formwork is attached to the side end of the adjacent formwork. A foundation construction method characterized by assembling connected formwork for foundation concrete, and pouring foundation concrete into the formwork.
【請求項2】薄板材を所定曲げ半径で湾曲して円弧状と
し、縁部に連結用の帯板状リブを形成したことを特徴と
する杭基礎用型枠。
2. A formwork for a pile foundation, characterized in that a thin plate material is curved at a predetermined bending radius to form an arc shape, and a strip-shaped rib for connection is formed at the edge.
JP3146316A 1991-06-18 1991-06-18 Pile foundation footing construction method and pile foundation footing curved formwork Expired - Fee Related JP2520524B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3146316A JP2520524B2 (en) 1991-06-18 1991-06-18 Pile foundation footing construction method and pile foundation footing curved formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3146316A JP2520524B2 (en) 1991-06-18 1991-06-18 Pile foundation footing construction method and pile foundation footing curved formwork

Publications (2)

Publication Number Publication Date
JPH04368566A true JPH04368566A (en) 1992-12-21
JP2520524B2 JP2520524B2 (en) 1996-07-31

Family

ID=15404917

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3146316A Expired - Fee Related JP2520524B2 (en) 1991-06-18 1991-06-18 Pile foundation footing construction method and pile foundation footing curved formwork

Country Status (1)

Country Link
JP (1) JP2520524B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11377865B2 (en) 2016-03-10 2022-07-05 Lonza Ltd Customizable facility

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS456177Y1 (en) * 1965-12-11 1970-03-27
JPS4520033Y1 (en) * 1967-03-07 1970-08-12
JPS4530527Y1 (en) * 1967-04-24 1970-11-24

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS456177Y1 (en) * 1965-12-11 1970-03-27
JPS4520033Y1 (en) * 1967-03-07 1970-08-12
JPS4530527Y1 (en) * 1967-04-24 1970-11-24

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11377865B2 (en) 2016-03-10 2022-07-05 Lonza Ltd Customizable facility

Also Published As

Publication number Publication date
JP2520524B2 (en) 1996-07-31

Similar Documents

Publication Publication Date Title
JP4284056B2 (en) Non-embedded column base construction method and non-embedded column base structure
KR20210003315A (en) Column form system using deckplate form
JP3200813B2 (en) Beam formwork structure and its forming method
JP2915897B1 (en) Building construction method
JP3763575B2 (en) Underground beam construction frame and underground beam construction method using the same
JP3752999B2 (en) Upper and lower integrated bridge and its construction method
JPH04368566A (en) Foundational construction and form for pile foundation
JPH0519384Y2 (en)
JP3039295B2 (en) Manufacturing method of prefabricated member of mixed structure
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP2017082548A (en) Concrete foundation joint member and pile structure
JPH10311041A (en) Column base foundation of precast concrete column
JPH08100464A (en) Joint structure and work execution method for structure using it
JP2003034997A (en) Earthquake-resistant steel plate wall and its construction method
JP3194729B2 (en) Reinforced concrete structure, method of constructing reinforced concrete structure, and reinforcing bar restraint
KR100761741B1 (en) Bridge footing system for accelerated bridge construction and construction method of bridge with the same system
JP7137978B2 (en) Plate-shaped member for pillar
JP2000248678A (en) Shear reinforcing member, half-pc member, and method for constructing floor slab and wall using the same
KR102280901B1 (en) Combined structure for half section slab and girder
JPH0447737B2 (en)
JPH1122106A (en) Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member
JP2006193985A (en) Concrete construction joint method
JP4421053B2 (en) Foundation structure
JPH044091Y2 (en)
JPH05230839A (en) Anchoring part structure of pile head part

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090517

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100517

Year of fee payment: 14

LAPS Cancellation because of no payment of annual fees