JPH04309651A - Construction method for stairs - Google Patents

Construction method for stairs

Info

Publication number
JPH04309651A
JPH04309651A JP3103915A JP10391591A JPH04309651A JP H04309651 A JPH04309651 A JP H04309651A JP 3103915 A JP3103915 A JP 3103915A JP 10391591 A JP10391591 A JP 10391591A JP H04309651 A JPH04309651 A JP H04309651A
Authority
JP
Japan
Prior art keywords
landing
temporary
staircase
support
stairs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3103915A
Other languages
Japanese (ja)
Other versions
JP2611882B2 (en
Inventor
Toshio Tamakoshi
玉越 敏男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP3103915A priority Critical patent/JP2611882B2/en
Publication of JPH04309651A publication Critical patent/JPH04309651A/en
Application granted granted Critical
Publication of JP2611882B2 publication Critical patent/JP2611882B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

PURPOSE:To provide so that the stairs do not become the neck in the process progress of an RC structure by removing the complicated frame work construction for stair floor parts and that the staircase can be made use of as a passage for work from before concrete laying when the stairs are built in an RC- structure building. CONSTITUTION:A supporting device is arranged in the condition without hindrance in passage on a landing 1, and a temporary landing B is installed on this supporting device A, and besides S-structure stairs are laid between the supporting devices A and A installed on the upper and lower landings 1,1. In this condition, the staircase is made use of as a passage for work and a framework D is laid on the temporary landing B, and the arrangement of bars and the concrete placing are performed to buid a landing 1 of RC structure.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は、RC造(鉄筋コンクリ
ート造)建物における階段の施工方法に関し、詳しくは
、踊り場をコンクリートの現場打ちによるRC造とし、
段床をS造とした階段の施工方法に関するものである。
[Industrial Application Field] The present invention relates to a method for constructing stairs in an RC (reinforced concrete) building, and more specifically, the landing is made of RC construction using cast-in-place concrete;
This invention relates to a method of constructing a staircase with an S-shaped step floor.

【0002】0002

【従来の技術】従来、コンクリートの現場打ちによるR
C造建物における階段室は、その四周壁、踊り場、段床
の全てがRC造とされていた。
[Prior art] Conventionally, R by pouring concrete on-site
The stairwell in the C building had all four walls, landings, and steps made of reinforced concrete.

【0003】そして、踊り場及び段床より成るRC造階
段が、支保工として、多数のパイプサポートを林立させ
て、これらのパイサポートで鋼管製の大曳き及び根太を
支持させると共に、根太上に踊り場用型枠及び段床用型
枠を設置し、それらの上に配筋及びコンクリート打設を
行うといった方法により施工されていたため、次のよう
な欠点があった。
[0003] An RC staircase consisting of a landing and a stair floor is constructed using a large number of pipe supports as shoring, and these pipe supports support the steel pipe trusses and joists. Construction was carried out by installing concrete formwork and berm formwork, and then placing reinforcement and concrete on top of them, which had the following drawbacks.

【0004】■狭い空間の中で、段床の傾斜に合わせた
複雑な型枠工事、配筋工事、支保工を行わなければなら
ず、これが工程進渉のネックとなっていた。■段床部分
に支保工としてのパイプサポートが林立しているため、
作業員の通行が困難であり、コンクリートが硬化し、型
枠及び支保工を撤去するまで階段室を作業用の通路とし
て利用できなかった。
[0004] In a narrow space, complicated form work, reinforcing work, and shoring work had to be carried out to match the slope of the berm, and this was a bottleneck in the progress of the project. ■Because there are a lot of pipe supports as shoring on the stepped floor,
Passage for workers was difficult, and the staircase could not be used as a work passage until the concrete had hardened and the formwork and shoring had been removed.

【0005】[0005]

【発明が解決しようとする課題】本発明は、上記の点に
留意してなされたものであって、その目的とするところ
は、段床部分のための複雑な型枠工事をなくして、階段
がRC造建物の工程進渉のネックとならないようにする
と共に、階段室をコンクリート打設前の時点から作業用
の通路(資材等の運搬が可能な広さを有する通路)とし
て利用できるようにすることにある。
SUMMARY OF THE INVENTION The present invention has been made with the above-mentioned points in mind, and its purpose is to eliminate the complicated formwork work for the stepped floor part and to improve the construction of stairs. In addition to ensuring that this does not become a bottleneck in the progress of the RC building construction process, the stairwell can be used as a work passageway (a passageway wide enough to transport materials, etc.) even before concrete is poured. It's about doing.

【0006】[0006]

【課題を解決するための手段】上記の目的を達成するた
めに、第1発明では、踊り場に支保装置を通行に支障の
ない配置状態に設置し、該支保装置の上に仮設踊り場を
設置し且つ上下の踊り場に設置された支保装置間にはS
造階段を架設し、しかる後、前記仮設踊り場の上に敷設
された踊り場用型枠の上に配筋及びコンクリート打設を
行って踊り場をRC造、段床をS造とする階段を構築し
ている。
[Means for Solving the Problems] In order to achieve the above object, in the first invention, a supporting device is installed on the landing in a position that does not hinder traffic, and a temporary landing is installed on the supporting device. In addition, there is an S between the supporting devices installed on the upper and lower landings.
After constructing the artificial staircase, reinforcing and pouring concrete were carried out on the landing formwork laid on top of the temporary landing to construct a staircase in which the landing was made of RC construction and the step floor was made of S construction. ing.

【0007】第2発明は、前記支保装置が踊り場に立設
される支柱部分とその上端に装着される支持金物とから
成り、前記支持金物が仮設踊り場を支持するための高さ
調節可能な第1支持部とS造階段を支持するための第2
支持部とを備え、作業の進行に伴って、仮設踊り場の高
さを、構築される踊り場の上面と略同一のレベルから構
築される踊り場の下面と略同一のレベルへと変更するよ
うにしたことを特徴としている。
[0007] In a second aspect of the present invention, the supporting device comprises a pillar part erected on the landing and a supporting metal part attached to the upper end of the pillar part, and the supporting metal part is a height-adjustable part for supporting the temporary landing. 1 support part and the 2nd part for supporting the S-shaped stairs.
As the work progresses, the height of the temporary landing is changed from approximately the same level as the top of the landing to be constructed to approximately the same level as the bottom of the landing. It is characterized by

【0008】前記支柱部分としては、パイプサポートや
単管を組んで構成してもよいが、後述する理由により、
枠組足場用のたて枠を使用することが望ましい。
[0008] The support portion may be constructed by assembling a pipe support or a single pipe, but for the reasons described below,
It is preferable to use frame scaffolding frames.

【0009】[0009]

【作用】上記の構成によれば、通行に支障のない配置状
態に設置された支保装置の上に仮設踊り場が設置され、
上下の踊り場に設置された支保装置間にS造階段が架設
されるため、段床部分にパイプサポートが林立せず、下
方の踊り場からS造階段及び仮設踊り場へと通行するこ
とが可能であり、コンクリート打設前から階段室を作業
用の通路として利用できる。
[Operation] According to the above configuration, a temporary landing is installed on the supporting device installed in a position that does not hinder traffic,
Since the S-frame stairs are constructed between the supporting devices installed on the upper and lower landings, there are no pipe supports standing on the step floor, and it is possible to pass from the lower landing to the S-frame stairs and temporary landing. , the staircase can be used as a work passage even before concrete is poured.

【0010】殊に、第2発明の構成によれば、コンクリ
ート打設前の階段室を作業用の通路として利用する時点
では、仮設踊り場の高さを、構築される踊り場の上面と
略同一のレベルに設定しておけるため、S造階段から仮
設踊り場、仮設踊り場からS造階段へと歩行する際、不
自然な段差がなく、作業用通路として利用する際の安全
性を向上することができる。
In particular, according to the configuration of the second invention, when the staircase before concrete pouring is used as a work passage, the height of the temporary landing is set to be approximately the same as the top surface of the landing to be constructed. Since it can be set at the same level, there is no unnatural step difference when walking from the S-frame stairs to the temporary landing, or from the temporary landing to the S-frame stairs, improving safety when used as a work passage. .

【0011】[0011]

【実施例】図1はコンクリートの現場打ちによるRC造
建物における折返し型の階段を示す。この階段は、踊り
場(図示の実施例では、各階の踊り場と中間の踊り場)
1をRC造とし、段床2をS造としたもので、次の方法
により施工されたものである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows a folded staircase in an RC building made of cast-in-place concrete. This staircase consists of a landing (in the example shown, a landing on each floor and an intermediate landing).
1 is made of RC construction, and tiered floor 2 is made of S construction, and was constructed using the following method.

【0012】即ち、図2〜図4に示すように、先行して
構築された踊り場1の上に、支柱部分3とその上端に装
着される支持金物4A,4Bとから成る支保装置Aを通
行に支障のない配置状態に設置する。
That is, as shown in FIGS. 2 to 4, a support device A consisting of a support section 3 and support hardware 4A, 4B attached to the upper end of the support device A is mounted on the landing 1 constructed in advance. Install it in an arrangement that does not cause any problems.

【0013】尚、前記支柱部分3としては、パイプサポ
ートや単管で組み立てたものであってもよいが、この実
施例では、組立及び解体を容易に行えるようにするため
に、図示の通り、枠組足場用のたて枠を使用し、該たて
枠を平面視略コ字状に配置すると共に、隣接するたて枠
同士を直交クランプや平行クランプで連結することによ
って前記支柱部分3を構成している。前記仮設踊り場B
は、踊り場1と略同等な面積を有する1枚物のパネルで
あって、この実施例では、アルミ製のグレーチングによ
って前記仮設踊り場Bを構成している。
The support section 3 may be constructed of a pipe support or a single tube, but in this embodiment, in order to facilitate assembly and disassembly, as shown in the figure, The support portion 3 is constructed by using vertical frames for a framework scaffold, arranging the vertical frames in a substantially U-shape in plan view, and connecting adjacent vertical frames with orthogonal clamps or parallel clamps. are doing. Said temporary landing B
is a single panel having approximately the same area as the landing 1, and in this embodiment, the temporary landing B is constituted by an aluminum grating.

【0014】次に、前記支保装置Aの上に仮設踊り場B
を設置し且つ上下の踊り場1,1に設置された支保装置
A,A間にS造階段Cを架設する。
Next, a temporary landing B is placed on the supporting device A.
, and an S-shaped staircase C is constructed between the supporting devices A and A installed on the upper and lower landings 1 and 1.

【0015】この状態では、下方の踊り場1からS造階
段S及び仮設踊り場Bへと通行することが可能であり、
コンクリート打設前から階段室が作業用の通路として利
用される。
In this state, it is possible to pass from the lower landing 1 to the S-frame stairs S and the temporary landing B,
The staircase will be used as a work passage even before concrete is poured.

【0016】しかる後、前記仮設踊り場Bの上に、合板
製の踊り場用型枠Dを敷設し、その上に配筋及びコンク
リートE打設を行ってRC造の踊り場1を構築し、前記
階段を構築するのである。
[0016] Thereafter, a landing form D made of plywood is laid on the temporary landing B, reinforcement is placed on top of the landing form D, and concrete E is poured to construct the RC landing 1. The goal is to build.

【0017】ところで、仮に、前記仮設踊り場Bが、構
築される踊り場1の下面と略同一のレベル(即ち、踊り
場下面よりも型枠の厚さ分低い位置)に固定的に設置さ
れているすると、コンクリート打設前に、階段室を作業
用通路として利用した際、仮設踊り場Bが本設の踊り場
の上面よりも低い位置にあるため、階段としての段差が
仮設踊り場Bの位置で不規則になる。
By the way, suppose that the temporary landing B is fixedly installed at approximately the same level as the lower surface of the landing 1 to be constructed (that is, at a position lower than the lower surface of the landing by the thickness of the formwork). , When the staircase room was used as a work passage before concrete pouring, the temporary landing B was located lower than the top of the permanent landing, so the steps as a staircase were irregular at the position of the temporary landing B. Become.

【0018】従って、例えば、適当な厚さのある仮設的
な台を仮設踊り場B上に敷設する等して段差が規則的と
なるようにしないと、歩行時の安全確保上、問題がある
が、この点についても、次の工夫が施されている。
Therefore, unless the steps are made regular by, for example, laying a temporary platform with an appropriate thickness on the temporary landing B, there will be a problem in ensuring safety when walking. , Regarding this point as well, the following measures have been taken.

【0019】即ち、前記支持金物4A,4Bのうち、S
造階段Cを支持する側の支持金物4Aは、図5に示すよ
うに、基板5上に、支柱部分3の上端部(たて枠の縦杆
上端部)3aに嵌合する鞘管6を立設すると共に、仮設
踊り場Bを支持するための高さ調節可能な第1支持部7
aと、S造階段Cを支持するための第2支持部7bとを
設けて成る一対の金物8,8を、水平な角形鋼管9によ
って連結すると共に、前記角形鋼管9の中間部にも2個
の第2支持部7b,7bを設けて構成してある。第1支
持部7aはねじ式ジャッキ機構を備えており、且つ、上
端には、仮設踊り場Bとして使用されるグレーチングの
格子と係合する上向きコ字状の爪部が設けられている。 また、第2支持部7bは上向きに開口した階段幅方向と
平行な溝状に形成されている。
That is, of the supporting hardware 4A, 4B, S
As shown in FIG. 5, the supporting hardware 4A on the side that supports the built staircase C has a sheath pipe 6 on the base plate 5 that fits into the upper end portion 3a of the column portion 3 (the upper end portion of the vertical rod of the vertical frame). A first support part 7 that is erected and whose height is adjustable for supporting the temporary landing B
a and a second support part 7b for supporting the S-shaped stairs C are connected by a horizontal square steel pipe 9, and a second support part 7b is connected to the middle part of the square steel pipe 9. The second support portions 7b, 7b are provided. The first support portion 7a is equipped with a screw type jack mechanism, and is provided with an upwardly U-shaped claw portion that engages with a grating of a grating used as a temporary landing B at its upper end. Further, the second support portion 7b is formed in the shape of a groove that opens upward and is parallel to the width direction of the stairs.

【0020】他方の支持金物4Bは、前記支持金物4A
から角形鋼管9と第2支持部7bを取り除いた如き構造
であって、基板5上に、支柱部分3の上端部3aに嵌合
する鞘管を立設すると共に、仮設踊り場Bを支持するた
めの高さ調節可能な第1支持部7aを設けて構成してあ
る。
[0020] The other supporting hardware 4B is similar to the supporting hardware 4A.
The structure is such that the square steel pipe 9 and the second support part 7b are removed from the original structure, and a sheath pipe that fits into the upper end 3a of the support column 3 is erected on the base plate 5, and also for supporting the temporary landing B. A first support portion 7a whose height is adjustable is provided.

【0021】そして、図6〜図8に示すように、S造階
段Cの上下両端側に設けられている鋼製プレート10,
10を、前記支持金物4A,4Aの第2支持部7b,7
bに支持させると共に、第1支持部7aのジャッキ機構
を伸長させた状態で、当該第1支持部7aに仮設踊り場
Bを支持させる。
As shown in FIGS. 6 to 8, steel plates 10,
10, the second support parts 7b, 7 of the support hardware 4A, 4A
b, and in a state where the jack mechanism of the first support part 7a is extended, the temporary landing B is supported by the first support part 7a.

【0022】この状態では、仮設踊り場Bが構築される
踊り場の上面と略同一のレベルに位置し、階段としての
段差が仮設踊り場Bの位置で不規則にならない。また、
仮設踊り場B用のグレーチングが第1支持部7aの爪部
と係合し、水平方向での位置ずれが阻止されている。
In this state, the temporary landing B is located at approximately the same level as the top surface of the landing to be constructed, and the steps of the stairs do not become irregular at the position of the temporary landing B. Also,
The grating for the temporary landing B engages with the claw portion of the first support portion 7a to prevent displacement in the horizontal direction.

【0023】従って、コンクリート打設前に、階段室を
作業用通路として利用する際、歩行を安全に行うことが
できる。
[0023] Therefore, when using the staircase as a work passage before concrete pouring, walking can be done safely.

【0024】踊り場のコンクリートを打設するにあたっ
ては、図9に示すように、前記ジャッキ機構を縮小して
第1支持部7aの位置を下げ、仮設踊り場Bを、構築さ
れる踊り場の下面と略同一のレベル(この実施例では、
前記踊り場用型枠Dが合板製で、コンクリート硬化後、
撤去されるため、構築される踊り場の下面よりも型枠D
の厚さ分低い位置である。)に変更する。
When pouring concrete for the landing, as shown in FIG. 9, the jack mechanism is scaled down to lower the position of the first support part 7a, and a temporary landing B is formed approximately on the lower surface of the landing to be constructed. the same level (in this example,
The landing formwork D is made of plywood, and after concrete hardens,
Because it will be removed, the formwork D is lower than the bottom of the landing that will be constructed.
It is at a lower position by the thickness of . ).

【0025】この状態で、仮設踊り場Bの上に前記型枠
Dを敷設し、型枠D上に配筋を行うと共に、前記プレー
ト10にアンカーボルト11を取り付ける。
In this state, the form D is laid on the temporary landing B, reinforcement is arranged on the form D, and the anchor bolts 11 are attached to the plate 10.

【0026】しかる後、型枠D上にコンクリートEを打
設し、図10に示すように、踊り場1を構築するのであ
る。
Thereafter, concrete E is placed on the formwork D, and the landing 1 is constructed as shown in FIG.

【0027】尚、型枠Dは、仮設踊り場Bのレベルを下
げる前に、敷設しておいてもよい。また、図示の実施例
では、アンカーボルト11をプレート10に挿通してナ
ット12で抜け止めするように構成されているが、プレ
ート10に直接ネジ孔を形成するか、ナットを溶接して
おき、これにアンカーボルト11をねじ込み固着するよ
うにしてもよい。
Note that the formwork D may be laid before lowering the level of the temporary landing B. Further, in the illustrated embodiment, the anchor bolt 11 is inserted into the plate 10 and is secured with a nut 12. The anchor bolt 11 may be screwed into this and fixed.

【0028】前記S造階段Cとしては、厚鋼板製のもの
でもよく、薄鋼板製のものであってもよい。また、前記
S造階段Cとしては、予め、工場生産されたものを用い
てもよいが、この実施例では、ノックダウン方式とされ
ている。
The S-shaped staircase C may be made of a thick steel plate or a thin steel plate. Further, as the S-shaped stairs C, those manufactured in advance in a factory may be used, but in this embodiment, they are of a knock-down type.

【0029】具体的には、工場生産された薄鋼板製の中
空状ささら桁13と薄鋼板製の段床構成部品2a,2b
と前記プレート10とを建築現場の敷地内に搬入し、現
地で、複数個の段床構成部品2a,2b同士をビス等で
連結して前記段床2を構成すると共に、当該段床2の両
端部を両側のささら桁13にビス等で連結し、さらに前
記プレート10をささら桁13にビス等で連結すること
によって構成されている。また、図示の実施例では、コ
ンクリート打設後においても、S造階段Cをアンカーボ
ルト11に連結できるように、プレート10をナット1
2で締め付けた後、最上段の段床構成部品2aを次の段
の段床構成部品2aやささら桁13にビス等で連結する
ように構成されている。
Specifically, the hollow stringers 13 made of thin steel plates and the step bed components 2a and 2b made of thin steel plates are manufactured in a factory.
and the plate 10 are carried into the premises of a construction site, and at the site, the plurality of tiered floor components 2a and 2b are connected with each other with screws etc. to form the tiered floor 2, and the tiered floor 2 is constructed. It is constructed by connecting both ends to the stringers 13 on both sides with screws or the like, and further connecting the plate 10 to the stringers 13 with screws or the like. In addition, in the illustrated embodiment, the plate 10 is attached to the nut 1 so that the S-frame staircase C can be connected to the anchor bolt 11 even after concrete is poured.
2, the uppermost tiered floor component 2a is connected to the next tiered tiered floor component 2a and stringers 13 with screws or the like.

【0030】図1中の14は踊り場1を支持するRC造
の壁、15はささら桁13にビス等で固着された手摺り
支柱、16は手摺りを示す。階段の幅方向両側に位置す
る壁は、乾式工法による耐火壁(例えば、ALC板を使
用した耐火壁や、軽鉄下地を組み、これに珪酸カルシウ
ム板を貼着した耐火壁)とされているが、コンクリート
の現場打ちによるRC造の壁としてもよい。
In FIG. 1, reference numeral 14 indicates an RC wall that supports the landing 1, reference numeral 15 indicates a handrail post fixed to the stringer 13 with screws, etc., and reference numeral 16 indicates a handrail. The walls located on both sides of the staircase in the width direction are fireproof walls constructed using dry construction methods (for example, fireproof walls using ALC boards, or fireproof walls constructed with a light iron base and affixed with calcium silicate boards). However, it may also be an RC wall made of cast-in-place concrete.

【0031】図11と図12は本発明の他の実施例を示
す。この実施例は、各S造階段Cの下端側(又は上端側
)にのみ、踊り場1の全幅にわたる長さのプレート10
を設ける一方、上端側(又は下端側)には左右のささら
桁13間にわたる長さの下向き開口のチャンネル材10
aを設け、図12に示すように、支持金物4Aの第2支
持部7bに支持されたプレート10に、別のS造階段C
のチャンネル材10aが嵌合して支持されるように構成
した点に特徴がある。尚、チャンネル材10aはプレー
ト10に嵌合させた状態で、溶接等の手段により当該プ
レート10に固着される。その他の構成は、先の実施例
と同じである。
FIGS. 11 and 12 show another embodiment of the invention. In this embodiment, a plate 10 having a length spanning the entire width of the landing 1 is provided only on the lower end side (or upper end side) of each S-shaped staircase C.
On the other hand, on the upper end side (or lower end side), a channel material 10 with a downward opening extending between the left and right stringers 13 is provided.
a, and as shown in FIG. 12, another S-shaped staircase C
A feature is that the channel material 10a is fitted and supported. Note that the channel material 10a is fixed to the plate 10 by means such as welding while being fitted into the plate 10. The other configurations are the same as in the previous embodiment.

【0032】[0032]

【発明の効果】以上の通り、本発明によれば、段床部分
のための複雑な型枠工事がなくなり、階段がRC造建物
の工程進渉のネックとならないようにすることができ、
しかも階段室をコンクリート打設前の時点から作業用の
通路として利用できる効果がある。請求項2によれば、
上記の効果に加えて、S造階段から仮設踊り場、仮設踊
り場からS造階段へと歩行する際、不自然な段差がなく
、作業用通路として利用する際の安全性を向上すること
ができるという効果がある。
[Effects of the Invention] As described above, according to the present invention, it is possible to eliminate the complicated formwork work for the stepped floor portion, and to prevent the stairs from becoming a bottleneck in the progress of the construction of an RC building.
Moreover, the staircase can be used as a work passage even before concrete is poured. According to claim 2,
In addition to the above effects, there are no unnatural steps when walking from the S-frame stairs to the temporary landing, and from the temporary landing to the S-frame stairs, improving safety when used as a work passage. effective.

【図面の簡単な説明】[Brief explanation of drawings]

【図1】踊り場をRC造とし、段床をS造とした階段の
縦断側面図である。
FIG. 1 is a longitudinal sectional side view of a staircase in which the landing is made of RC construction and the step floor is made of S construction.

【図2】階段の施工方法を示す斜視図である。FIG. 2 is a perspective view showing a method of constructing stairs.

【図3】階段の施工方法を示す縦断側面図である。FIG. 3 is a longitudinal side view showing a method of constructing stairs.

【図4】階段の施工方法を示す平面図である。FIG. 4 is a plan view showing a method of constructing stairs.

【図5】上記の施工方法に使用される支持金物の一例を
示す斜視図である。
FIG. 5 is a perspective view showing an example of a supporting hardware used in the above construction method.

【図6】S造階段の下端側を上記支持金物に取り付けた
状態を示す要部の縦断側面図である。
FIG. 6 is a longitudinal cross-sectional side view of the main part showing the lower end side of the S-shaped staircase attached to the supporting hardware.

【図7】S造階段の上端側を上記支持金物に取り付けた
状態を示す要部の縦断側面図である。
FIG. 7 is a vertical sectional side view of the main part showing the upper end side of the S-shaped staircase attached to the supporting hardware.

【図8】仮設踊り場を支持金物に取り付けた状態を示す
要部の縦断側面図である。
FIG. 8 is a longitudinal cross-sectional side view of the main part showing the state in which the temporary landing is attached to the supporting hardware.

【図9】仮設踊り場を下降し、該仮設踊り場上に踊り場
用型枠を敷設した状態を示す要部の縦断側面図である。
FIG. 9 is a longitudinal sectional side view of the main part showing a state in which the temporary landing has been lowered and the landing formwork has been laid on the temporary landing.

【図10】踊り場のコンクリートが硬化した状態を示す
要部の縦断側面図である。
FIG. 10 is a longitudinal cross-sectional side view of the main part showing a state in which the concrete of the landing has hardened.

【図11】本発明の他の実施例を説明するための要部の
概略平面図である。
FIG. 11 is a schematic plan view of main parts for explaining another embodiment of the present invention.

【図12】図11に示したS造階段の下端側を支持金物
に取り付けた状態を示す要部の縦断側面図である。
12 is a longitudinal sectional side view of the main part showing the lower end side of the S-shaped staircase shown in FIG. 11 attached to a supporting metal fitting.

【符号の説明】[Explanation of symbols]

A  支保装置 B  仮設踊り場 C  S造階段 A. Shoring device B Temporary landing C S-built stairs

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】  踊り場に支保装置を通行に支障のない
配置状態に設置し、該支保装置の上に仮設踊り場を設置
し且つ上下の踊り場に設置された支保装置間にはS造階
段を架設し、しかる後、前記仮設踊り場の上に敷設され
た踊り場用型枠の上に配筋及びコンクリート打設を行っ
て踊り場をRC造、段床をS造とする階段を構築するこ
とを特徴とする階段の施工方法。
Claim 1: A supporting device is installed on the landing in a position that does not hinder traffic, a temporary landing is installed on top of the supporting device, and an S-shaped staircase is constructed between the supporting devices installed on the upper and lower landings. Then, after that, reinforcing and pouring concrete are performed on the landing formwork laid on the temporary landing to construct a staircase in which the landing is made of RC construction and the step floor is made of S construction. How to construct stairs.
【請求項2】  前記支保装置が踊り場に立設される支
柱部分とその上端に装着される支持金物とから成り、前
記支持金物が仮設踊り場を支持するための高さ調節可能
な第1支持部とS造階段を支持するための第2支持部と
を備え、作業の進行に伴って、仮設踊り場の高さを、構
築される踊り場の上面と略同一のレベルから構築される
踊り場の下面と略同一のレベルへと変更するようにした
ことを特徴とする請求項1に記載の階段の施工方法。
2. The support device comprises a support section that stands upright on the landing and a support hardware attached to the upper end of the support, and the support hardware is a height-adjustable first support part for supporting the temporary landing. and a second support part for supporting the S-shaped staircase, and as the work progresses, the height of the temporary landing can be adjusted from approximately the same level as the top of the landing to be constructed to the bottom of the landing to be constructed. 2. The method of constructing stairs according to claim 1, wherein the steps are changed to substantially the same level.
【請求項3】  前記支柱部分として、枠組足場用のた
て枠を使用する請求項1に記載の階段の施工方法。
3. The method for constructing stairs according to claim 1, wherein a vertical frame for a scaffolding is used as the support portion.
JP3103915A 1991-04-08 1991-04-08 Construction method of stairs Expired - Fee Related JP2611882B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3103915A JP2611882B2 (en) 1991-04-08 1991-04-08 Construction method of stairs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3103915A JP2611882B2 (en) 1991-04-08 1991-04-08 Construction method of stairs

Publications (2)

Publication Number Publication Date
JPH04309651A true JPH04309651A (en) 1992-11-02
JP2611882B2 JP2611882B2 (en) 1997-05-21

Family

ID=14366725

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3103915A Expired - Fee Related JP2611882B2 (en) 1991-04-08 1991-04-08 Construction method of stairs

Country Status (1)

Country Link
JP (1) JP2611882B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002364139A (en) * 2001-06-12 2002-12-18 Yokomori Mfg Co Ltd Steel stair mounting hardware, mounting device and mounting method
KR100762421B1 (en) * 2006-06-05 2007-10-02 주식회사 포스코 Support system of steel stair preceding construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002364139A (en) * 2001-06-12 2002-12-18 Yokomori Mfg Co Ltd Steel stair mounting hardware, mounting device and mounting method
JP4650757B2 (en) * 2001-06-12 2011-03-16 株式会社横森製作所 Steel frame mounting hardware, steel frame mounting structure and mounting method
KR100762421B1 (en) * 2006-06-05 2007-10-02 주식회사 포스코 Support system of steel stair preceding construction method

Also Published As

Publication number Publication date
JP2611882B2 (en) 1997-05-21

Similar Documents

Publication Publication Date Title
US5839239A (en) Apparatus and method for building construction
US4036466A (en) Flying deck-type concrete form installation
US20060260238A1 (en) Refinement to the construction systems for structures in reinforced concrete or some other material of high-precision intergral modular forms
TW200809061A (en) Stairway for use on building sites
US3927518A (en) Site assembled multi-story stair
US3994113A (en) Stairs and railing system for multi-floored buildings and method of constructing same
JP2611882B2 (en) Construction method of stairs
US4050203A (en) Stairs and railing system for multi-floored buildings and method of constructing same
JPS61290164A (en) Method and apparatus for supporting beam and slab
EP1181423B1 (en) Inner stairs for building and method of constructing it
RU2043470C1 (en) Method for erecting monolithic elements of a building, preferentially floor, and concrete form to implement it
JPS5836142B2 (en) Method and device for installing supports for stair construction
KR20010092469A (en) Method of forming concrete floors
JPH0681463A (en) Building method for stair
KR100247608B1 (en) Concrete form with a scaffolding
JPH0145301Y2 (en)
JP3087196B2 (en) How to build stairs
RU2087650C1 (en) House-building combine
JPS637654Y2 (en)
JP3115908B2 (en) How to build steel stairs
JP2649057B2 (en) How to build stairs in buildings
JPH09268756A (en) Temporary stair with stair landing and multistage construction method in shaft of temporary stair with stair landing
KR100473612B1 (en) Form system and frame construction method using the same
JP2016204982A (en) Temporary staircase scaffold
JPH0461943B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees