JPH0461943B2 - - Google Patents

Info

Publication number
JPH0461943B2
JPH0461943B2 JP3406087A JP3406087A JPH0461943B2 JP H0461943 B2 JPH0461943 B2 JP H0461943B2 JP 3406087 A JP3406087 A JP 3406087A JP 3406087 A JP3406087 A JP 3406087A JP H0461943 B2 JPH0461943 B2 JP H0461943B2
Authority
JP
Japan
Prior art keywords
floor
external
working
internal
floors
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3406087A
Other languages
Japanese (ja)
Other versions
JPS63201260A (en
Inventor
Eiichi Oonishi
Shoji Ootaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP3406087A priority Critical patent/JPS63201260A/en
Publication of JPS63201260A publication Critical patent/JPS63201260A/en
Publication of JPH0461943B2 publication Critical patent/JPH0461943B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、中・高層建築物の自動上昇式水平足
場に関するものである。
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a self-rising horizontal scaffold for medium- and high-rise buildings.

「従来の技術と発明が解決しようとする問題点」 従来、市街地等における中・高層建築物では、
固定式水平足場又はスカイハンガー等による外
部・内部足場が用いられているが、この種の足場
は、膨大な仮設資材、労務力、揚重費等を必要と
し、しかも、組み払い時の危険、落下物の危険等
の欠点がある。
``Problems to be solved by conventional technology and inventions'' Conventionally, in medium and high-rise buildings in urban areas,
External/internal scaffolding such as fixed horizontal scaffolding or skyhangers is used, but this type of scaffolding requires a huge amount of temporary materials, labor, lifting costs, etc., and is also dangerous when demolishing. There are drawbacks such as the danger of falling objects.

ところで、建物構築工法の1つに、足場兼用型
枠による工法がある(特公昭52−13645号公報)。
この工法は、鉄骨建方完了後、その鉄骨構造体の
最上部からワイヤロープを垂設し、該ワイヤロー
プに揚重機械を介して足場兼用型枠を懸吊させ、
最下階から上階へと順次に移動させて各階毎に鉄
骨本締めを行い、最上階の鉄骨本締め完了後、足
場兼用型枠上面を利用して最上階の床版を打設
し、以下、順次に下降させて同様にして各階のコ
ンクリート床版を打設するものである。
By the way, one of the building construction methods is a construction method using formwork that also serves as scaffolding (Japanese Patent Publication No. 13645/1983).
This construction method involves hanging a wire rope from the top of the steel structure after the steel frame has been erected, and suspending a formwork that also serves as a scaffold from the wire rope via a lifting machine.
The steel frame was finally tightened on each floor by moving from the bottom floor to the upper floor, and after the steel frame on the top floor was finally tightened, the floor slabs for the top floor were poured using the top of the formwork that also served as scaffolding. Thereafter, the concrete slabs for each floor are placed in the same way by lowering the concrete slabs one after another.

しかし、この足場兼用型枠による場合でも、結
局は上記外部足場を要し、また、コンクリートの
打設を最上階から下方へと進行させねばならない
という制約を受け、作業手順に不便を来たす欠点
がある。
However, even when this formwork is used as a scaffold, the above-mentioned external scaffolding is ultimately required, and there is a restriction that concrete pouring must proceed from the top floor downwards, which causes inconvenience to the work procedure. be.

そこで、本発明は、専用の外部・内部足場にお
いて、昇降手段及び落下物阻止手段を講じて、上
述の各種の欠点を除去しようとするものである。
Therefore, the present invention aims to eliminate the above-mentioned various drawbacks by providing elevating means and falling object prevention means in dedicated external and internal scaffolds.

「問題点を解決するための手段」 本発明は、建方された鉄骨構造体の外側に外部
作業床を、内側の所要各所に内部作業床をそれぞ
れ配し、鉄骨構造体の上部適所からそれらの作業
床に対応させてそれぞれロツドを垂設し、これら
のロツドに各作業床をクライミングジヤツキを以
て昇降自在に懸吊させ、また、各作業床に落下物
阻止手段を講じて成る。
``Means for Solving the Problems'' The present invention provides an external working floor on the outside of the erected steel structure, and an internal working floor at various locations inside the erected steel structure. Rods are vertically provided corresponding to the respective working floors, each working floor is suspended from these rods so as to be able to be raised and lowered using a climbing jack, and each working floor is provided with means for preventing falling objects.

「作用」 如上の構成であるから、外部作業床及び内部作
業床は、クライミングジヤツキを働かせて下層階
から上層階へと次々に上昇させ、各階にて鉄骨本
締め、その他の所要作業に供する。また、工事中
の上方からの落下物は、各作業床に装備させた落
下物阻止手段により阻止する。
``Function'' Because of the above structure, the external and internal working floors are raised one after another from the lower floors to the upper floors using climbing jacks, and each floor is used for final tightening of the steel frame and other necessary work. . Falling objects from above during construction will be prevented by falling object prevention means installed on each work floor.

「実施例」 図面は、本発明の実施例を示している。"Example" The drawings illustrate embodiments of the invention.

図において、1は、鉄骨建方された鉄骨構造
体、2は、該鉄骨構造体に用いた本発明に係る自
動上昇式水平足場である。
In the figure, 1 is a steel frame structure erected, and 2 is an automatically rising horizontal scaffolding according to the present invention used for the steel frame structure.

鉄骨構造体1は、多数の鉄骨柱11…と、鉄骨
大梁12…と、鉄骨小梁13…とを建方して成
る。
The steel structure 1 is constructed by erecting a large number of steel columns 11, large steel beams 12, and small steel beams 13.

自動上昇式水平足場2は、上記鉄骨構造体1の
外周に、これを一巡させて外部作業床21を配
し、また、その鉄骨構造体の内側の所要各所に、
すなわち、所要の鉄骨大梁12…に沿えて、複数
の内部作業床22…を配し、これらの内部作業床
には、端部に出入自在なスライド作業床23…を
装備させ、鉄骨構造体の上部適所にて、それらの
作業床に対応させて、固定用治具24…を以て複
数のロツド25…を垂設し、これらのロツドに外
部作業床21及び内部作業床22…をクライミン
グジヤツキ26…を以て昇降自在に懸吊させ、そ
れらの外部作業床21及び内部作業床22…に落
下物阻止手段27…を講じて成る。
The self-elevating horizontal scaffolding 2 has an external work floor 21 arranged around the outer periphery of the steel structure 1, and also has an external work floor 21 arranged at various locations inside the steel structure.
That is, a plurality of internal working floors 22 are arranged along the required steel girders 12, and these internal working floors are equipped with sliding working floors 23 that can be freely moved in and out at the ends of the steel frame structures. A plurality of rods 25 are hung vertically using fixing jigs 24 in correspondence with the working floors at the upper part, and climbing jacks 26 are attached to these rods to attach the external working floor 21 and the internal working floor 22. . . . It is suspended so as to be able to rise and fall freely, and falling object prevention means 27 are provided on the outer working floor 21 and the inner working floor 22 .

外部作業床21、内部作業床22…及びスライ
ド作業床23…には、それぞれ所要の手すり21
1,221…,231を設け、クライミングジヤ
ツキ26…は、第5図に示すように、外部作業床
21と内部作業床22…との適所にヨーク261
…を固定して、該ヨークに装着している。
The external work floor 21, the internal work floor 22... and the slide work floor 23... each have the required handrails 21.
As shown in FIG.
... is fixed and attached to the yoke.

スライド作業床23…は、第6図乃至第10図
に示すように、フレーム232…と手すり231
…とに複数のローラ233…と案内板234…を
設けて、これらを内部作業床22…のフレーム2
22…と手すり221…とに出入可動に装着して
いる。図中、235は、筋違である。
As shown in FIGS. 6 to 10, the sliding work floor 23... has frames 232... and handrails 231.
A plurality of rollers 233... and guide plates 234... are provided in the frame 2 of the internal work floor 22...
22... and the handrail 221... so as to be movable in and out. In the figure, 235 is a brace.

落下物阻止手段27…は、外部作業床21にお
いて、背面で、適宜に複数の支柱212…を起立
させて、これらの支柱の先端から傾斜する外部落
下物養生ネツト271(又はシート)を突設し
て、これを外部作業床全体に一巡させ、かつ、支
柱の先端から2階相当分の外部養生シート272
(又はネツト)を垂設して、これを外部作業床全
体に一巡させている。また、内部作業床22…に
おいて、背面に、複数の支柱223…を起立させ
て、対応する鉄骨大梁12,12にある内部作業
床22,22の支柱相互間に、伸縮自在な内部落
下物養生ネツト273…(又はシート)を張り渡
している。
The falling object prevention means 27... is constructed by appropriately erecting a plurality of columns 212 on the back side of the external work floor 21, and protruding external falling object protection nets 271 (or sheets) inclined from the tips of these columns. Then, wrap this around the entire external work floor, and extend the external curing sheet 272 from the tip of the pillar to the area equivalent to the second floor.
(or a net) is installed vertically and runs around the entire external work floor. In addition, a plurality of columns 223 are erected on the back side of the internal working floors 22, and a flexible internal fallen object protection is provided between the columns of the internal working floors 22, 22 on the corresponding steel girders 12, 12. Net 273... (or sheet) is being stretched.

如上の構成であるから、外部作業床21、内部
作業床22…及びスライド作業床23…は、クラ
イミングジヤツキ26…を働かせることにより下
層階から上層階へと順次上昇させることができ、
これと共に、落下物阻止手段27…も連動上昇さ
せることができる。この際、内部落下物養生ネツ
ト273…は、鉄骨小梁13…を越えるにあたつ
て開閉させればよく、また、スライド作業床23
…は、鉄骨大梁12…を越えるにあたつて一旦引
き込ませ、越えて後、再び進出させればよい。
With the above configuration, the external working floor 21, internal working floor 22... and sliding working floor 23... can be raised sequentially from the lower floor to the upper floor by operating the climbing jacks 26...
At the same time, the falling object prevention means 27 can also be raised in conjunction with this. At this time, the internal fallen object curing nets 273... should be opened and closed when going over the steel beams 13..., and the sliding work floor 23...
When crossing the steel frame girder 12..., it may be pulled in once, and after crossing it, it may be advanced again.

これにより、各階にて鉄骨本締め、その他の所
要の作業を行う。
As a result, steel frame tightening and other necessary work will be carried out on each floor.

その後は、床デツキプレートの敷設、床配筋、
床コンクリートの打設、カーテンウオールの設置
等を順次に行う。
After that, the installation of floor deck plates, floor reinforcement,
Concrete flooring and curtain wall installation will be carried out in sequence.

「発明の効果」 本発明によれば、一層の外部作業床及び内部作
業床、したがつて、水平足場を逐次上方へと移動
させながら作業を追行でき、水平足場についての
膨大な仮設資材、労務力、揚重費等が不要とな
り、組み払い時の危険、落下物の危険等を無くす
ことができる。また、コンクリートの打設等を下
層階から上方へと進行させることができ、作業手
順に不便を来たさず、工期を短縮でき、コストを
低減できる。
"Effects of the Invention" According to the present invention, the work can be carried out by sequentially moving the external working floor and the internal working floor, and therefore the horizontal scaffolding upwards, and a huge amount of temporary materials for the horizontal scaffolding can be used. There is no need for labor, lifting costs, etc., and it is possible to eliminate dangers during assembly and dangers from falling objects. In addition, concrete pouring can proceed upward from the lower floors, so there is no inconvenience in the work procedure, the construction period can be shortened, and costs can be reduced.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は、本発明の実施例で、第1図は、平面
図、第2図は、正面図、第3図は、縦断側面図、
第4図は、要部の拡大平面図、第5図は、要部の
拡大側面図、第6図は、要部の拡大平面図、第7
図は、同拡大正面図、第8図は、第7図−線
の断面図、第9図、第10図は、それぞれ更に拡
大した部分断面図である。 1……鉄骨構造体、2……自動上昇式水平足
場、11……鉄骨柱、12……鉄骨大梁、13…
…鉄骨小梁、21……外部作業床、22……内部
作業床、23……スライド作業床、24……固定
用治具、25……ロツド、26……クライミング
ジヤツキ、27……落下物阻止手段、271……
外部落下物養生ネツト、272……外部養生シー
ト、273……内部落下物養生ネツト。
The drawings show embodiments of the present invention; FIG. 1 is a plan view, FIG. 2 is a front view, and FIG. 3 is a longitudinal side view.
Fig. 4 is an enlarged plan view of the main part, Fig. 5 is an enlarged side view of the main part, Fig. 6 is an enlarged plan view of the main part, and Fig. 7 is an enlarged plan view of the main part.
8 is a sectional view taken along the line of FIG. 7, and FIGS. 9 and 10 are further enlarged partial sectional views. 1...Steel frame structure, 2...Automatically rising horizontal scaffolding, 11...Steel frame column, 12...Steel frame girder, 13...
...Steel frame beam, 21...External work floor, 22...Internal work floor, 23...Sliding work floor, 24...Fixing jig, 25...Rod, 26...Climbing jack, 27...Falling Object prevention means, 271...
External falling object curing net, 272... External curing sheet, 273... Internal falling object curing net.

Claims (1)

【特許請求の範囲】[Claims] 1 建方された鉄骨構造体の外側に外部作業床
を、内側の所要各所に内部作業床をそれぞれ配
し、鉄骨構造体の上部適所からそれらの作業床に
対応させてそれぞれロツドを垂設し、これらのロ
ツドに各作業床をクライミングジヤツキを以て昇
降自在に懸吊させ、また、各作業床に落下物阻止
手段を講じたことを特徴とする自動上昇式水平足
場。
1. Arrange external working floors on the outside of the erected steel structure, and internal working floors at various locations inside the erected steel structure, and hang rods corresponding to these working floors from appropriate places on the top of the steel structure. , an automatically rising type horizontal scaffold characterized in that each work floor is suspended from these rods using climbing jacks so that they can be raised and lowered freely, and each work floor is provided with means for preventing falling objects.
JP3406087A 1987-02-16 1987-02-16 Automatic rising type horizontal scaffold Granted JPS63201260A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3406087A JPS63201260A (en) 1987-02-16 1987-02-16 Automatic rising type horizontal scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3406087A JPS63201260A (en) 1987-02-16 1987-02-16 Automatic rising type horizontal scaffold

Publications (2)

Publication Number Publication Date
JPS63201260A JPS63201260A (en) 1988-08-19
JPH0461943B2 true JPH0461943B2 (en) 1992-10-02

Family

ID=12403729

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3406087A Granted JPS63201260A (en) 1987-02-16 1987-02-16 Automatic rising type horizontal scaffold

Country Status (1)

Country Link
JP (1) JPS63201260A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008133900A (en) * 2006-11-28 2008-06-12 Fujitsu Access Ltd Screw-fastening structure

Also Published As

Publication number Publication date
JPS63201260A (en) 1988-08-19

Similar Documents

Publication Publication Date Title
US9611663B2 (en) Self-lifting concrete form adapted to accommodate horizontal reinforcing steel
CN1028556C (en) Building construction system
KR20210066799A (en) How to erect multi-storey structures and facades
JPH09317183A (en) Construction method of building
US3818084A (en) Method and apparatus for the construction of multi-storey buildings
US3156071A (en) Building structure
JP2957328B2 (en) Peripheral holding self-elevating construction method
CN211923466U (en) Elevator shaft regularization operation platform
JPH0461943B2 (en)
JP2874576B2 (en) Moving scaffold for retaining wall construction
CN216276830U (en) Super high-rise core tube formwork lowering construction device
CN212836618U (en) A integral operation platform in capital for prefabricated stand concrete placement
JPH09296610A (en) Outside curing unit
JP2876991B2 (en) Steel frame method for high-rise buildings
CA2624702A1 (en) Overhead beam assembly
SU1110884A1 (en) Suspended scaffolding
JP2023004557A (en) Building demolition method
JP3008054B2 (en) Horizontal material temporary fixing device
JP3018947B2 (en) Construction method of reinforced concrete building with balcony
JPH04309651A (en) Construction method for stairs
RU3952U1 (en) SLIDING FORMWORK FOR ESTABLISHING WALLS AND FLOORS
JP2551488B2 (en) Lifting method by crane and lifting jig
SU1196477A1 (en) Suspension mobile scaffold
JPH0714007U (en) Curing net for construction work
JPH0776914A (en) Hanging-down construction method of steel stairs