JPH04258492A - Shield excavator - Google Patents
Shield excavatorInfo
- Publication number
- JPH04258492A JPH04258492A JP3040749A JP4074991A JPH04258492A JP H04258492 A JPH04258492 A JP H04258492A JP 3040749 A JP3040749 A JP 3040749A JP 4074991 A JP4074991 A JP 4074991A JP H04258492 A JPH04258492 A JP H04258492A
- Authority
- JP
- Japan
- Prior art keywords
- shield
- lining
- cylinder
- passage
- pathway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009412 basement excavation Methods 0.000 claims description 16
- 239000003795 chemical substances by application Substances 0.000 claims description 10
- 239000004576 sand Substances 0.000 claims description 10
- 238000003756 stirring Methods 0.000 claims description 4
- 239000002689 soil Substances 0.000 abstract description 6
- 238000000034 method Methods 0.000 abstract description 2
- 230000037361 pathway Effects 0.000 abstract 5
- 239000004848 polyfunctional curative Substances 0.000 abstract 2
- 239000000463 material Substances 0.000 description 9
- 238000002347 injection Methods 0.000 description 5
- 239000007924 injection Substances 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- 238000007796 conventional method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 238000005192 partition Methods 0.000 description 2
- 238000004078 waterproofing Methods 0.000 description 2
- 238000009499 grossing Methods 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【0001】0001
【産業上の利用分野】本発明は、掘進と同時にセグメン
トによる一次覆工の外側に外面覆工を施工するシールド
掘進機に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a shield excavator that constructs an external lining on the outside of a primary lining made of segments while excavating.
【0002】0002
【従来の技術】従来、セグメントにより一次覆工を形成
させる型式のシールド掘進機は、円筒状をしたシールド
筒の前端部に掘削機構を設けるとともに、後端部内をセ
グメント組立部となし、該セグメント組立部内でセグメ
ントを円筒状に組み立てて、先に施工されている一次覆
工を延長し、これに反力を取ってシールド掘進機全体を
推進用の油圧ジャッキにより押し出すことにより、延長
された一次覆工を後方に押し出して掘進するようにして
いる。そして、その後に一次覆工とトンネル地山面間に
できる空隙に裏込材を充填している。[Prior Art] Conventionally, a shield excavator of the type in which a primary lining is formed by segments is provided with an excavation mechanism at the front end of a cylindrical shield tube, and a segment assembly section within the rear end. The segments are assembled into a cylindrical shape in the assembly section, the previously constructed primary lining is extended, and the reaction force is taken to push out the entire shield excavator using a hydraulic jack for propulsion. The lining is pushed backwards and excavation is carried out. Then, the gap created between the primary lining and the tunnel ground surface is filled with backfilling material.
【0003】また多くの場合は、セグメントによる一次
覆工の内側に現場打コンクリートによる二次覆工を施し
ている。この二次覆工の目的は、主に防水、防錆、防振
、その他、覆工内面の平滑化(仕上工)等であった。In many cases, a secondary lining made of cast-in-place concrete is provided inside the primary lining made of segments. The purpose of this secondary lining was mainly waterproofing, rust prevention, anti-vibration, and smoothing the inner surface of the lining (finishing).
【0004】0004
【発明が解決しようとする課題】上述の如き従来の装置
を使用したシールド工法は、下記の如く問題点があった
。 (1)シールドトンネルの完成時には、一般的に
は二次覆工の機能は外圧を受ける応力部材ではなく、平
滑で止水効果及び防錆効果があれば厚さを必要としない
が、現場打コンクリートの施工性から、最低数十cm程
度以上の厚みを持っている。[Problems to be Solved by the Invention] The shield construction method using the conventional equipment as described above has the following problems. (1) When a shield tunnel is completed, the function of the secondary lining is generally that it is not a stressed member that receives external pressure, but does not need to be thick as long as it is smooth and has water-stopping and rust-preventing effects. Due to the workability of concrete, it should be at least several tens of centimeters thick.
【0005】従って、二次覆工の厚さを確保するために
余分な断面をシールド掘進機により掘削しなければなら
ない。[0005] Therefore, in order to ensure the thickness of the secondary lining, an extra cross section must be excavated using a shield excavator.
【0006】(2)応力部材ではない二次覆工の厚さだ
け一次覆工の断面が大きくなるため、一次覆工セグメン
トの設計が過大となる。(2) Since the cross section of the primary lining increases by the thickness of the secondary lining, which is not a stress member, the design of the primary lining segment becomes excessive.
【0007】(3)シールドトンネルでは、狭い坑内で
一次、二次覆工を平行して行うことが難しいことから、
一次覆工完了後、、その内面に型枠を組み、二次覆工を
施工するため、非常に長い工期を必要としている。(3) In shield tunnels, it is difficult to perform primary and secondary lining in parallel in a narrow tunnel;
After the primary lining is completed, formwork is erected on the inner surface and the secondary lining is constructed, which requires a very long construction period.
【0008】(4)一方、二次覆工を省略して一次覆工
のみで完成断面とするシールドトンネルもあるが、止水
、防錆が完全ではなく、坑内に弊害が現れる場合がある
。(4) On the other hand, there are shield tunnels in which the secondary lining is omitted and the cross section is completed with only the primary lining, but this is not completely watertight and rust-proof, and may cause problems inside the tunnel.
【0009】(5)防水及び応力増強のために一次覆工
外面の空隙を大きくし、裏込材層を厚くしようとすると
、掘削後、裏込材充填前に地山が崩壊し易くなり、周囲
の地山にゆるみが生じて地盤沈下が起こり易くなる。(5) If an attempt is made to increase the voids on the outer surface of the primary lining and thicken the backfill material layer for waterproofing and stress reinforcement, the ground will tend to collapse after excavation and before filling with the backfill material. The surrounding ground becomes loose, making it easier for ground subsidence to occur.
【0010】本発明はこれらの問題にかんがみ、二次覆
工を要することなく、安全性の高い覆工を掘進と同時に
短時間で経済的に施工することのできるシールド掘進機
の提供を目的としてなされたものである。[0010] In view of these problems, the present invention aims to provide a shield excavator that can construct a highly safe lining in a short time and economically at the same time as excavation, without requiring a secondary lining. It has been done.
【0011】[0011]
【課題を達成するための手段】上述の如き従来の問題を
解決し、所期の目的を達成するための本発明の特徴は、
円筒状をしたシールド筒の先端部に掘削チャンバーを設
け、該掘削チャンバーの前部に回転カッターヘッドを設
け、かつ、シールド筒後端部内にセグメント組立部を設
け、該セグメント組立部にて組み立てられたセグメント
による一次覆工に反力を取って掘進すると同時に一次覆
工を後方に押し出すようにしてなるシールド掘進機にお
いて、前記シールド筒の内側に間隔を隔てて二重円筒状
に内筒を固定し、該内筒と前記シールド筒間に前後に連
通開口した掘削土砂通路を設け、該掘削土砂通路内に強
制撹拌送り機構を設けるとともに、該通路の中間位置に
硬化剤注入路を連通させ、かつ、前記円筒の後端部内を
セグメント組立部としたことにある。[Means for Accomplishing the Problems] The features of the present invention for solving the above-mentioned conventional problems and achieving the intended purpose are as follows:
An excavation chamber is provided at the tip of the cylindrical shield tube, a rotary cutter head is provided at the front of the excavation chamber, a segment assembly section is provided at the rear end of the shield tube, and the segment assembly section is used to assemble the shield tube. In a shield excavator that excavates by taking a reaction force to the primary lining made of segments and simultaneously pushes the primary lining backward, an inner cylinder is fixed in a double cylindrical shape at a spaced interval inside the shield cylinder. providing an excavated earth and sand passage that communicates with each other in the front and back between the inner cylinder and the shield cylinder, a forced stirring feeding mechanism in the excavated earth and sand passage, and a curing agent injection passage communicating with the intermediate position of the passage; Further, the rear end portion of the cylinder is provided with a segment assembly portion.
【0012】0012
【作用】本発明のシールド掘進機は、円筒の内側にセグ
メントを組み立てて一次覆工を延長させる。そして、そ
の一次覆工に反力を取ってシールド掘進機を前進させる
。このとき、シールド筒の前端部においてカッターヘッ
ドにより掘削された土砂は、その一部が内筒とシールド
筒間の掘削土砂通路内にのり込み、強制撹拌送り機構に
撹拌されながらシールド筒の後端側に送られる。この通
路の途中において硬化剤注入路から硬化剤が注入され、
撹拌されつつシールド筒後端に送り出される。 シー
ルド筒後端では、シールド筒の前進によって一次覆工の
外面とトンネル地山面との間に空隙ができるが、掘進と
同時にこの空隙内に前述した掘削土砂と硬化剤とが混練
された裏込材が充填され、経時的に硬化し、地山及び一
次覆工と一体化した外側覆工が形成される。[Operation] The shield excavator of the present invention extends the primary lining by assembling segments inside the cylinder. Then, the shield excavator moves forward by taking reaction force from the primary lining. At this time, a portion of the earth and sand excavated by the cutter head at the front end of the shield cylinder enters the excavated earth and sand passage between the inner cylinder and the shield cylinder, and is stirred by the forced stirring and feeding mechanism at the rear end of the shield cylinder. Sent to the side. A hardening agent is injected from the hardening agent injection path in the middle of this passage,
It is sent to the rear end of the shield cylinder while being stirred. At the rear end of the shield tube, as the shield tube moves forward, a gap is created between the outer surface of the primary lining and the surface of the tunnel ground. The material is filled and hardened over time to form an outer lining that is integrated with the earth and the primary lining.
【0013】[0013]
【実施例】次に本発明の実施例を図面について説明する
。Embodiments Next, embodiments of the present invention will be described with reference to the drawings.
【0014】図において、10はシールド筒であり、そ
の内側には同心配置に間隔を隔てて内筒11が固定され
ている。内筒11の前端部には隔壁11aを隔てて、そ
の前方側が掘削部となっており、その前部にカッターヘ
ッド12が軸13を中心に回転駆動されるように設置さ
れている。In the figure, reference numeral 10 denotes a shield cylinder, and inner cylinders 11 are fixed at intervals in a concentric arrangement inside the shield cylinder. At the front end of the inner cylinder 11, with a partition wall 11a in between, the front side thereof is an excavation part, and a cutter head 12 is installed in the front part so as to be driven to rotate around a shaft 13.
【0015】内筒11の後端部内は、セグメント組立部
14となっており、その前方側に推進用ジャッキ15が
設置され、このジャッキにより、セグメント組立部14
内でセグメント16を円筒状に組み立てて延長した一部
覆工17に反力を取ってシールド掘進機全体を推進させ
るようにしている。図において、14aはテールシール
である。Inside the rear end of the inner cylinder 11 is a segment assembly section 14, and a propulsion jack 15 is installed on the front side of the segment assembly section 14.
Inside, the segments 16 are assembled into a cylindrical shape and the extended partial lining 17 absorbs a reaction force to propel the entire shield excavator. In the figure, 14a is a tail seal.
【0016】シールド筒10と内筒11間は、両端部間
を多数の放射状の連結リブ18,19にて連結し、両筒
10,11間の円筒状の空隙を掘削土砂通路20として
いる。この通路20内には、強制撹拌送り機構としてリ
ボンスクリュー21が回転自在に収容されている。リボ
ンスクリュー21は、その内周面にリング23が固着さ
れ、そのリング22に設けたラック状のギャー23に駆
動モーター24によって回転されるピニオン25を噛合
させて回転駆動させるようになっている。The shield cylinder 10 and the inner cylinder 11 are connected at both ends by a large number of radial connecting ribs 18 and 19, and the cylindrical gap between the cylinders 10 and 11 is used as an excavation earth passage 20. A ribbon screw 21 is rotatably housed in this passage 20 as a forced stirring feeding mechanism. A ring 23 is fixed to the inner peripheral surface of the ribbon screw 21, and a pinion 25 rotated by a drive motor 24 is engaged with a rack-shaped gear 23 provided on the ring 22, thereby driving the ribbon screw 21 to rotate.
【0017】通路20の中間部には円筒11を貫通させ
た硬化剤注入路26,26……が連通されている。[0017] A curing agent injection path 26, 26, .
【0018】次に上記の如く構成されるシールド掘進機
による掘進行程について説明する。Next, the excavation process by the shield excavator constructed as described above will be explained.
【0019】シールド掘進機の掘進を停止させた状態で
推進用ジャッキ15を縮め、その後方のセグメント組立
部14にてセグメント16を円筒状に組み立てて、先に
施工してある一次覆工17を延長させる。然る後、推進
用ジャッキ15を伸し、一次覆工17に反力を取ってシ
ールド掘進機全体を掘進させる。With the shield excavator stopped digging, the propulsion jack 15 is retracted, and the segments 16 are assembled into a cylindrical shape in the segment assembly section 14 behind it, and the primary lining 17 that has been constructed earlier is retracted. extend it. Thereafter, the propulsion jack 15 is extended, and the primary lining 17 takes up a reaction force to cause the entire shield excavator to dig.
【0020】このとき、掘削部ではカッターヘッド12
にて掘削された土砂の一部が掘削土砂通路20内に入り
込み、リボンスクリュー21の駆動によって強制的に撹
拌されつつ後方に移動される。その移動の途中において
、硬化剤注入路26,26……より硬化剤が注入され、
これが混合撹拌され、混練状態の裏込材27となって後
方に送り出される。At this time, the cutter head 12
A part of the excavated earth and sand enters the excavated earth and sand passage 20, and is moved rearward while being forcibly stirred by the drive of the ribbon screw 21. During the movement, the curing agent is injected from the curing agent injection paths 26, 26...
This is mixed and stirred to become the backfilling material 27 in a kneaded state and sent to the rear.
【0021】このようにしてシールド掘進機の掘進に伴
って後方に形成される裏込用空隙に、掘削土砂に硬化剤
が添加されて混練された裏込材27が圧入され、これが
経時的に硬化して地山及び一次覆工と一体化した外側覆
工29が成形される。In this way, the backfilling material 27, which is mixed with a hardening agent added to the excavated soil, is press-fitted into the backfilling gap formed at the rear as the shield excavator excavates, and this An outer lining 29 that is hardened and integrated with the earth and the primary lining is formed.
【0022】なお上述の実施例では、シールド筒と内筒
間の空隙全体を掘削土砂通路20としているが、この他
、シールド筒10の内面に前端が掘削部に開口した円筒
状の複数の掘削土砂通路を設け、各通路内に強制送り用
のスクリューを収容してもよい。In the above-described embodiment, the entire gap between the shield tube and the inner tube is used as the excavated earth and sand passage 20, but in addition to this, there are a plurality of cylindrical excavations on the inner surface of the shield tube 10, the front end of which opens into the excavation part. Earth and sand passages may be provided and a forced feeding screw may be accommodated in each passage.
【0023】[0023]
【発明の効果】上述したように本発明のシールド掘進機
では、シールド筒の内側に間隔を隔てて内筒を設け、そ
の内筒内にてセグメント組立部を設けたことにより、一
次覆工外に厚みの大きい外面覆工用の裏込空間が形成さ
れ、その裏込空間に掘進と同時に掘削土の一部と硬化剤
とを混練した裏込材を圧入するようにしたことにより、
肉厚の大きい強固な外側覆工が形成されることとなって
、一次覆工の内面への二次覆工が不要になり、覆工作業
が著しく簡略化され、工期も短縮されることとなったも
のである。[Effects of the Invention] As described above, in the shield excavator of the present invention, the inner cylinder is provided at intervals inside the shield cylinder, and the segment assembly portion is provided within the inner cylinder. A thick backfilling space for the external lining is formed in the backfilling space, and a backfilling material made by mixing part of the excavated soil and a hardening agent is press-fitted into the backfilling space at the same time as excavation is being carried out.
A strong outer lining with a large wall thickness is formed, making it unnecessary to apply a secondary lining to the inner surface of the primary lining, significantly simplifying the lining work and shortening the construction period. It has become.
【0024】また、セグメントにより一次覆工の内面が
そのままトンネルの仕上内面となすことが可能なため、
二次覆工を予定した一次覆工に比べて径が小さくてよく
、このためセグメントの設計に余裕をもたせることがで
きるとともに、テールシールも大型のものを使用する必
要がなくなる。[0024] Furthermore, since the inner surface of the primary lining can be used as the finished inner surface of the tunnel due to the segments,
The diameter of the secondary lining can be smaller than that of the planned primary lining, which allows more leeway in segment design and eliminates the need for large tail seals.
【0025】更に現場打による二次覆工の代わりに、セ
グメントにより一次覆工を型枠とした外側覆工が成形さ
れることとなるため、覆工全体の厚さを応力のみのため
に必要な厚さに近いものとすることがてきるため、従来
に比べてトンネル掘削断面を小さくでき、経済性が高い
。Furthermore, instead of a secondary lining cast on-site, an outer lining is formed using the primary lining as a formwork using segments, so the thickness of the entire lining is reduced only to the stress. Since the thickness can be made close to that of the conventional method, the tunnel excavation cross section can be made smaller than that of the conventional method, making it highly economical.
【0026】更にまた、掘進に伴って大きな外面覆工用
の空間が形成されるが、該空間が形成されると同時に裏
込材が加圧されて充填されるため、トンネル地山面のゆ
るみや出水を防止しつつ安全な施工ができる。Furthermore, a large space for external lining is formed as the excavation progresses, but at the same time as this space is formed, the lining material is pressurized and filled, which prevents loosening of the tunnel ground surface. Safe construction can be performed while preventing water leakage.
【図1】本発明のシールド掘進機の一例の断面図である
。FIG. 1 is a sectional view of an example of a shield tunneling machine according to the present invention.
【図2】図1中のA−A線断面図である。FIG. 2 is a sectional view taken along line AA in FIG. 1.
10 シールド筒 11 内筒 11a 隔壁 12 カッターヘッド 13 軸 14 セグメント組立部 14a テールシール 15 ジャッキ 16 セグメント 17 一次覆工 18,19 連結リブ 20 通路 21 リボンスクリュー 22 リング 23 ギャー 24 駆動モーター 25 ピニオン 26 硬化剤注入通路 27 裏込材 29 外側覆工 10 Shield tube 11 Inner cylinder 11a Partition wall 12 Cutter head 13 axis 14 Segment assembly department 14a Tail seal 15 Jack 16 Segment 17 Primary lining 18, 19 Connecting rib 20 Passage 21 Ribbon screw 22 Ring 23 Gyaa 24 Drive motor 25 Pinion 26 Hardening agent injection passage 27 Backfill material 29 Outside lining
Claims (1)
削チャンバーを設け、該掘削チャンバーの前部に回転カ
ッターヘッドを設け、かつ、シールド筒後端部内にセグ
メント組立部を設け、該セグメント組立部にて組み立て
られたセグメントによる一次覆工に反力を取って掘進す
ると同時に一次覆工を後方に押し出すようにしてなるシ
ールド掘進機において、前記シールド筒の内側に間隔を
隔てて二重円筒状に内筒を固定し、該内筒と前記シール
ド筒間に前後に連通開口した掘削土砂通路を設け、該掘
削土砂通路内に強制撹拌送り機構を設けるとともに、該
通路の中間位置に硬化剤注入路を連通させ、かつ、前記
円筒の後端部内をセグメント組立部としたことを特徴と
してなるシールド掘進機。1. An excavation chamber is provided at the tip of a cylindrical shield tube, a rotary cutter head is provided at the front of the excavation chamber, a segment assembly is provided in the rear end of the shield tube, and the segment assembly is provided. In a shield excavator that excavates by taking a reaction force to the primary lining made of segments assembled in the section, and at the same time pushes out the primary lining backward, a double cylindrical structure is installed at a distance inside the shield tube. An inner cylinder is fixed to the inner cylinder, an excavated earth and sand passage is provided between the inner cylinder and the shield cylinder, which communicates with each other in the front and back, a forced stirring and feeding mechanism is provided in the excavated earth and sand passage, and a hardening agent is injected at an intermediate position of the passage. 1. A shield excavator characterized in that a passage is communicated with the cylinder, and a segment assembly section is formed inside the rear end of the cylinder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3040749A JPH04258492A (en) | 1991-02-14 | 1991-02-14 | Shield excavator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3040749A JPH04258492A (en) | 1991-02-14 | 1991-02-14 | Shield excavator |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH04258492A true JPH04258492A (en) | 1992-09-14 |
Family
ID=12589284
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3040749A Pending JPH04258492A (en) | 1991-02-14 | 1991-02-14 | Shield excavator |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH04258492A (en) |
-
1991
- 1991-02-14 JP JP3040749A patent/JPH04258492A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5221160A (en) | Subterranean connecting method for construction of shield tunnel and connecting apparatus therefor | |
JP4461410B2 (en) | Tunnel excavator | |
JP3890528B2 (en) | Tunnel construction method | |
JPH04258492A (en) | Shield excavator | |
EP0393187B1 (en) | Method and apparatus for connecting halves of shield tunnel under ground | |
JP3651970B2 (en) | Start / arrival method of branch shield machine and lining structure used therefor | |
JPH04258495A (en) | Lining work of shield tunnel | |
JPH0548840B2 (en) | ||
JPH0369439B2 (en) | ||
JPH0423994Y2 (en) | ||
JPS6347499A (en) | Method of tunnel joining construction in shield excavation | |
JPH02229395A (en) | Ground improving method utilizing shield excavator | |
JPH0369438B2 (en) | ||
JP2712685B2 (en) | Shield machine | |
JPH0462299A (en) | Larger section tunnel and construction method thereof | |
JPH0525998B2 (en) | ||
JP2003049596A (en) | Method of constructing tunnel having widened section | |
JP2712686B2 (en) | Shield machine | |
JPH0814235B2 (en) | Shield method | |
JP2004068377A (en) | Tunnel boring machine and tunnel construction method | |
JP4762641B2 (en) | Tunnel excavator | |
JPH04250294A (en) | Lining method of shield tunnel and device thereof | |
JPH06100056B2 (en) | Shield construction method | |
JPH06341296A (en) | Shield construction method | |
JPH04238997A (en) | Ring shaped lining device of peripheral surface of planned tunnel |