JPH042247Y2 - - Google Patents

Info

Publication number
JPH042247Y2
JPH042247Y2 JP6514785U JP6514785U JPH042247Y2 JP H042247 Y2 JPH042247 Y2 JP H042247Y2 JP 6514785 U JP6514785 U JP 6514785U JP 6514785 U JP6514785 U JP 6514785U JP H042247 Y2 JPH042247 Y2 JP H042247Y2
Authority
JP
Japan
Prior art keywords
girder
connecting member
steel frame
face
mesh
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP6514785U
Other languages
Japanese (ja)
Other versions
JPS61181418U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP6514785U priority Critical patent/JPH042247Y2/ja
Publication of JPS61181418U publication Critical patent/JPS61181418U/ja
Application granted granted Critical
Publication of JPH042247Y2 publication Critical patent/JPH042247Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) 本考案は大梁の梁鉄骨に仮止めできるプレキヤ
ストコンクリート小梁(以下PC小梁という)に
関する。
[Detailed description of the invention] (Field of industrial application) The present invention relates to a precast concrete beam (hereinafter referred to as a PC beam) that can be temporarily fixed to the beam steel frame of a girder.

(従来の技術) 一般に、大梁および小梁を現場打ちコンクリー
トで施工する例が多い。しかしながら現場打ちに
よる施工法は配筋工事や型枠工事がすべて現場長
期化する難点がある。この不都合を除去するため
小梁にPC小梁を用いて施工する例がある。
(Prior art) Generally, there are many cases in which large beams and small beams are constructed using cast-in-place concrete. However, the cast-in-place construction method has the disadvantage that all reinforcement work and formwork work take a long time on site. In order to eliminate this inconvenience, there are examples of construction using PC beams for the small beams.

(考案が解決しようとする問題点) PC小梁を建築現場でクレーンで吊り上げて大
梁にセツトする際、PC小梁を予め支持するため
のサポートを必要とし、サポートを設置するスラ
ブは施工完了しなければ使用できないため、スラ
ブの施工法が制約される問題がある。
(Problem that the invention aims to solve) When lifting a PC beam with a crane at a construction site and setting it on a girder, a support is required to support the PC beam in advance, and the slab on which the support is installed is not completed. Since it cannot be used without it, there is a problem that the construction method of the slab is restricted.

本考案の目的は、上記の問題点を解決すると共
に大梁との一体性を強化することにある。
The purpose of the present invention is to solve the above problems and to strengthen the integrity with the girder.

(問題点を解決するための手段) 本考案のPC小梁1は大梁4と接合すべき端面
にL形鋼からなる結合部材2が設けてあり、この
結合部材は大梁の梁鉄骨5に仮止め可能である。
PC小梁1の上記端面1aはPC小梁の製作時に、
型枠を兼用するメツシユ7で覆つている。
(Means for Solving the Problem) The PC beam 1 of the present invention has a connecting member 2 made of L-shaped steel on the end face to be connected to the girder 4, and this connecting member is temporarily attached to the beam steel frame 5 of the girder. Can be stopped.
The above end face 1a of the PC beam 1 is
It is covered with mesh 7 which also serves as a formwork.

(作用) PC小梁1を建築現場に運び、クレーンで吊り
上げて大梁4の所定位置に仮止めする際、結合部
材2を大梁の梁鉄骨5に当接してPC小梁を仮保
持する。この仮保持した状態で大梁およびスラブ
のコンクリートを打設し、大梁と小梁とを一体化
する。
(Function) When the PC beam 1 is transported to a construction site, lifted by a crane, and temporarily fixed at a predetermined position on the large beam 4, the connecting member 2 is brought into contact with the beam steel frame 5 of the large beam to temporarily hold the PC beam. In this temporarily held state, concrete is poured for the girder and slab to integrate the girder and the small beam.

(実施例) 以下本考案の実施例について図面を参照して説
明する。PC小梁1の接合部端面1aにL形鋼か
らなる結合部材2が設けてあり、この結合部材は
アンカー筋3によりPC小梁に固定してある。結
合部材の一片の水平部2aは、小梁端面1aに突
出状態になつていおり、小梁の上端部と同一平面
を形成している。水平部2aは大梁4の梁鉄骨5
の上側フランジ5aに掛止め、小梁端部を梁鉄骨
に仮止め可能である。水平部2aにはこれをフラ
ンジ5aにボルト6で固定するためにボルト孔2
bがあけてある。結合部材2の他片の垂直部には
等間隔に配設した3本のアンカー筋3が溶接して
あり、アンカー筋の他端部はそれぞれPC小梁1
の下端筋7に固着してある。さらにPC小梁1の
端面1aは結合部材2で覆われた部分以外の面は
メツシユ8で覆ってある。このメツシユはPC小
梁1の製作時に梁端面用型枠として使用したもの
である。
(Example) Examples of the present invention will be described below with reference to the drawings. A connecting member 2 made of L-shaped steel is provided on the joint end face 1a of the PC beam 1, and this connecting member is fixed to the PC beam by anchor bars 3. The horizontal portion 2a of one piece of the coupling member projects from the end face 1a of the beam and forms the same plane as the upper end of the beam. The horizontal part 2a is the beam steel frame 5 of the girder 4
It can be latched onto the upper flange 5a of the beam, and the end of the small beam can be temporarily secured to the beam steel frame. A bolt hole 2 is provided in the horizontal part 2a to fix it to the flange 5a with a bolt 6.
b is open. Three anchor bars 3 arranged at equal intervals are welded to the vertical part of the other piece of the connecting member 2, and the other ends of the anchor bars are each connected to a PC beam 1.
It is fixed to the lower end reinforcement 7 of. Further, the end face 1a of the PC beam 1 is covered with a mesh 8 except for the part covered with the connecting member 2. This mesh was used as a formwork for the beam end when manufacturing the PC beam 1.

次にPC小梁1の施工法について説明する。 Next, the construction method of the PC beam 1 will be explained.

大梁の梁鉄骨5を仮設した後、PC小梁1をク
レーンで吊り上げ、梁端部の結合部材2の水平部
2aを鉄骨のフランジ5aに掛止め、ボルト孔2
aをフランジの所定位置に設けてあるボルト孔に
合わせ、ボルト6とナツト9とによつてPC小梁
の位置を固定する。その後大梁の鉄筋10,11
と小梁1の鉄筋7aを配筋し、型枠工事をし、大
梁およびスラブのコンクリートを打設する。
After temporarily installing the beam steel frame 5 of the main beam, lift the PC beam 1 with a crane, hook the horizontal part 2a of the connecting member 2 at the beam end to the flange 5a of the steel frame, and attach the bolt hole 2
Align a with the bolt hole provided at a predetermined position on the flange, and fix the position of the PC beam with bolts 6 and nuts 9. After that, reinforcing bars 10 and 11 of the girder
Then, the reinforcing bars 7a of the small beam 1 are arranged, the formwork is constructed, and the concrete of the girder and slab is poured.

小梁は、上例ではスターラツプ12が梁上面よ
り突出しているハーフ小梁を用いているが、ハー
フ梁に限定されない。結合部材2はボルトに代え
て溶接によりフランジ5aに固着してもよい。
In the above example, a half beam in which the stirrup 12 protrudes from the upper surface of the beam is used as the beam, but the invention is not limited to a half beam. The connecting member 2 may be fixed to the flange 5a by welding instead of bolts.

(考案の効果) 大梁の鉄骨と同時にPC小梁を仮止めできるた
め、工期が大幅に短縮でき、サポートが不要とな
り、スラブの施工法の制限を受けず、そして結合
部材とメツシユとにより小梁と大梁との一体化が
強化される。
(Effects of the idea) Since the PC beams can be temporarily fixed at the same time as the steel frame of the large beam, the construction period can be significantly shortened, no supports are required, there are no restrictions on slab construction methods, and the connecting members and mesh The integration between the main beam and the main beam is strengthened.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は要部の断面図、第2図は第1図の一部
切欠右側面図、第3図は施工状態を示す断面図、
第4図は梁鉄骨とPC小梁との位置関係を示す平
面図である。 1……PC小梁、1a……接合部端面、2……
結合部材、4……大梁、5……梁鉄骨、8……メ
ツシユ。
Figure 1 is a sectional view of the main part, Figure 2 is a partially cutaway right side view of Figure 1, and Figure 3 is a sectional view showing the construction state.
Figure 4 is a plan view showing the positional relationship between the beam steel and the PC beams. 1... PC beam, 1a... joint end surface, 2...
Connecting member, 4... girder, 5... beam steel frame, 8... mesh.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 大梁と接合すべき接合部端面に、L形鋼からな
り大梁の梁鉄骨に仮止め可能の結合部材と、上記
端面を覆う型枠兼用のメツシユとをそれぞれ設け
てあることを特徴とするPC小梁。
A small PC characterized in that the end face of the joint to be joined to the girder is provided with a connecting member made of L-shaped steel and capable of being temporarily fixed to the beam steel frame of the girder, and a mesh that also serves as a formwork to cover the end face. Beam.
JP6514785U 1985-05-02 1985-05-02 Expired JPH042247Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6514785U JPH042247Y2 (en) 1985-05-02 1985-05-02

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6514785U JPH042247Y2 (en) 1985-05-02 1985-05-02

Publications (2)

Publication Number Publication Date
JPS61181418U JPS61181418U (en) 1986-11-12
JPH042247Y2 true JPH042247Y2 (en) 1992-01-27

Family

ID=30596880

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6514785U Expired JPH042247Y2 (en) 1985-05-02 1985-05-02

Country Status (1)

Country Link
JP (1) JPH042247Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2523891Y2 (en) * 1989-07-04 1997-01-29 大成建設株式会社 Connection structure between girders and steel beams

Also Published As

Publication number Publication date
JPS61181418U (en) 1986-11-12

Similar Documents

Publication Publication Date Title
JPH042247Y2 (en)
JPH0343282Y2 (en)
JP3008051B2 (en) Reinforced preassembly with formwork and reinforced preassembly method with formwork
JP2972955B2 (en) Column and beam joining method and its structure
JP2759361B2 (en) Pillar support members for building reinforced concrete buildings
JPS5925931Y2 (en) Composite girder using π-shaped steel
JPH0612617U (en) Superstructure of steel reinforced concrete beams
JPH0642184A (en) Construction of skeleton using half precast floor board
JPS5926001Y2 (en) Precast beam and girder joint structure
JPH06341167A (en) Working method for concrete structure
JP3001674B2 (en) Half precast slab plate reverse construction method
JP2600411Y2 (en) Column-beam joint structure
JPH0432901B2 (en)
JPH0128992Y2 (en)
JPS6328756Y2 (en)
JPS6343281Y2 (en)
JPH0711202Y2 (en) Joint structure of columns and beams in precast reinforced concrete structures
JPH0355619Y2 (en)
JPS6035638Y2 (en) panel foundation
JP2759360B2 (en) Construction method of reinforced concrete building
JPS6375231A (en) Building housing
JPH0765368B2 (en) Precast concrete half flat slab
JPH0296035A (en) Connecting structure for beam and girder
JPH0528815U (en) Precast steel reinforced concrete columns
JPS63125743A (en) Construction of building