JPH0421869Y2 - - Google Patents

Info

Publication number
JPH0421869Y2
JPH0421869Y2 JP14028287U JP14028287U JPH0421869Y2 JP H0421869 Y2 JPH0421869 Y2 JP H0421869Y2 JP 14028287 U JP14028287 U JP 14028287U JP 14028287 U JP14028287 U JP 14028287U JP H0421869 Y2 JPH0421869 Y2 JP H0421869Y2
Authority
JP
Japan
Prior art keywords
steel sheet
water
sheet piles
swellable rubber
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14028287U
Other languages
Japanese (ja)
Other versions
JPS6447841U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP14028287U priority Critical patent/JPH0421869Y2/ja
Publication of JPS6447841U publication Critical patent/JPS6447841U/ja
Application granted granted Critical
Publication of JPH0421869Y2 publication Critical patent/JPH0421869Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) この考案は、建築物の地下工事における鋼矢板
を使用した山留壁において、建築物側の掘削後、
地下水が鋼矢板の継目部から漏れて掘削箇所内に
流入するのを防止する鋼矢板用止水装置に係るも
のである。
[Detailed explanation of the invention] (Industrial application field) This invention is used for retaining walls using steel sheet piles in underground construction of buildings, after excavation on the building side.
This invention relates to a water stop device for steel sheet piles that prevents groundwater from leaking from joints of steel sheet piles and flowing into excavated areas.

(従来の技術) 従来、この種の建築物の地下工事における鋼矢
板を使用した山留壁は、順次鋼矢板を継がせて地
中に打込んだだけであるため、その後、建築物側
の掘削を行うと、地下水が鋼矢板の継目部から漏
れて掘削箇所内に流水する。従つて、その水の排
出のために水中ポンプ等の使用が一般には行われ
ている。
(Conventional technology) Conventionally, retaining walls using steel sheet piles for underground construction of this type of building were simply connected one after another and driven into the ground. When excavation is carried out, groundwater leaks from the joints of the steel sheet piles and flows into the excavated area. Therefore, submersible pumps and the like are generally used to discharge the water.

また、海洋や河川の水中構造物の構築工事等に
おいては、海水や川水等の遮断を目的として鋼矢
板を二重に設置する等の点に問題があつた。
Furthermore, in the construction work of underwater structures in the ocean and rivers, problems have arisen in the installation of double steel sheet piles for the purpose of blocking seawater, river water, etc.

そのために、一部の業者では、鋼矢板の継目部
分にシール剤を塗布して施工を行つている。とこ
ろが、このシール方法では、シール剤の塗布を鋼
矢板の打込み作業の前に行うために、作業が複雑
である上に、すべての鋼矢板に塗布するために不
経済である等の点に問題がある。
For this reason, some contractors apply a sealant to the joints of steel sheet piles during construction. However, with this sealing method, the sealant is applied before driving the steel sheet piles, so the work is complicated, and it is uneconomical because it has to be applied to all the steel sheet piles. There is.

(問題点を解決するための手段) そこで、この考案は上記の問題点を解決するた
めに、鋼矢板1の打込みを行つて建築物側の掘削
後、その掘削箇所側において、隣接した鋼矢板
1,1の継目部2中の漏水する箇所に水膨潤性ゴ
ム材3を当てた後、両側押え材4,4の間に適当
間隔で介装した数個の伸長金具aによりその両側
押え材4,4を両側の水膨潤性ゴム材3,3に当
て、該水膨潤性ゴム材3を鋼矢板1,1の継目部
2に圧接させる。
(Means for solving the problem) Therefore, in order to solve the above problem, this invention is to drive the steel sheet pile 1 and, after excavating on the building side, to the adjacent steel sheet pile on the side of the excavated area. After applying the water-swellable rubber material 3 to the water leakage point in the joint 2 of 1, 1, it is held down by several extension fittings a inserted at appropriate intervals between the holding members 4, 4 on both sides. 4, 4 are applied to the water-swellable rubber materials 3, 3 on both sides, and the water-swellable rubber materials 3 are brought into pressure contact with the joint portion 2 of the steel sheet piles 1, 1.

(作用) 鋼矢板1,1の継目部2の隙間が水膨潤性ゴム
材3に密封されて地下水が鋼矢板1,1の継目部
2よりその建築物側の掘削箇所A内に流入するの
を防止される。
(Function) The gap between the joint 2 of the steel sheet piles 1 and 1 is sealed with the water-swellable rubber material 3, and groundwater is prevented from flowing into the excavation point A on the building side from the joint 2 of the steel sheet piles 1 and 1. will be prevented.

また、地下水が鋼矢板1,1の継目部2の隙間
を通つて水膨潤性ゴム材3に当ると、その水膨潤
性ゴム材3が膨張し、鋼矢板1,1の継目部2へ
の圧接度を増して該継目部2における地下水の掘
削箇所A内への流入防止作用を助長する。
In addition, when groundwater hits the water-swellable rubber material 3 through the gap between the joint 2 of the steel sheet piles 1, 1, the water-swellable rubber material 3 expands, and the water swells at the joint 2 of the steel sheet piles 1, 1. The degree of pressure contact is increased to help prevent groundwater from flowing into the excavated area A at the joint 2.

(実施例) 図面に示すこの考案の一実施例についてその構
造を説明すれば、1は鋼矢板で、開放側が拡開す
る溝形鋼の両側縁外側にフツク状溝金5を形成し
て成る。2は隣接した鋼矢板1,1の継目部、3
はその継目部2の外側全体にわたして形に当て
る縦長帯状の水膨潤性ゴム材、4は木片、角パイ
プ、型鋼等の押え材である。
(Embodiment) To explain the structure of one embodiment of this invention shown in the drawings, 1 is a steel sheet pile, and hook-shaped grooves 5 are formed on the outside of both side edges of a channel steel whose open side widens. . 2 is a joint between adjacent steel sheet piles 1, 1, 3
numeral 4 is a water-swellable rubber material in the form of a vertically long strip that is applied to the entire outside of the joint portion 2, and 4 is a holding material such as a piece of wood, a square pipe, or a molded steel.

aは伸長金具を示し、はそのターンバツクル
で、パイプの中間部に数個のスパナ係合部7を並
設し、両端部は小径にしぼり加工しその両側小径
部内に左右反対方向の雌ねじ81,82をそれぞれ
設けてターンバツクルを形成する。は押え座
金で、前方片(以下鋼矢板1に対して掘削箇所A
側を前方と称する。)が長いコ形金10の前方片
外側の先端縁に形受金11を斜め前外側へ向け
連設してその先端部に釘孔12を穿ち、コ形金1
0の内側面中央部には中央片に通孔13を穿つた
コ形取付金14を固定して成る。151,152
左右反対方向の雄ねじを設けたボルトで、それぞ
れ両側の取付金14の通孔13に挿通して基端の
四角形頭16を取付金14内に廻らないように係
合する。そして、ボルト151,152をそれぞれ
ターンバツクルの雌ねじ81,82に螺通して伸
長金具aを構成する。
A indicates an extension fitting, and 6 is a turnbuckle thereof.Several spanner engaging parts 7 are arranged in parallel in the middle part of the pipe, both ends are narrowed to a small diameter, and female screws 8 in left and right opposite directions are inserted in the small diameter parts on both sides. 1 and 8 2 are respectively provided to form the turnbuckle 6 . 9 is a presser washer, and the front piece (hereinafter, excavated location A for steel sheet pile 1)
The side is called the front. ) is long on the outer tip edge of the front piece of the U-shaped metal piece 10, a shaped support piece 11 is connected diagonally forward and outward, and a nail hole 12 is drilled in the tip of the metal piece 11.
A U-shaped fitting 14 having a through hole 13 in the center piece is fixed to the center of the inner surface of the 0. 15 1 and 15 2 are bolts with male threads in opposite left and right directions, and are inserted into the through holes 13 of the mounting brackets 14 on both sides, respectively, and engaged with the square heads 16 at the base end so as not to turn inside the mounting brackets 14. . Then, the bolts 15 1 and 15 2 are threaded through the female threads 8 1 and 8 2 of the turnbuckle 5 , respectively, to form the extension fitting a.

17は伸長金具aの止め釘、Aは建築物の地下
工事の掘削箇所を示す。
Reference numeral 17 indicates a peg of an extension fitting a, and A indicates an excavation location for underground construction of a building.

次にその作用を説明する。第2図に示すよう
に、鋼矢板1を交互に前後反対方向に向け、順次
隣接する鋼矢板1,1の溝金5,5を引掛けて鋼
矢板1,1を継ぎながら鋼矢板1を地中に所要深
さまで打込んでゆく。その後、鋼矢板1より前方
部を掘削して建築物の地下工事の掘削箇所Aを形
成する。
Next, its effect will be explained. As shown in Fig. 2, the steel sheet piles 1 are alternately turned in front and back opposite directions, and the grooves 5, 5 of the adjacent steel sheet piles 1, 1 are successively hooked to connect the steel sheet piles 1, 1. It is driven into the ground to the required depth. Thereafter, a portion in front of the steel sheet pile 1 is excavated to form an excavated location A for underground construction of the building.

次いで、鋼矢板1,1の継目部2中の漏水する
箇所において、第2図に示すように両側の鋼矢板
1,1の継目部2の前方隅部に水膨潤性ゴム材3
を形に当て、該水膨潤性ゴム材3を押え材4に
よつて上記前方隅部に押圧し、後方鋼矢板1の溝
金5の前面とそれに隣接している前方鋼矢板1の
側面とにわたして接触させる。そこで、適当箇所
において、伸長金具aの両側の押え座金の受金
11をそれぞれ両側の押え材4の前方内側隅部に
係合させて押え座金を押え材4,4に当て
た後、両側において止め釘17を押え座金の釘
孔12に挿通して押え材4に打込む。
Next, at the location where water leaks in the joint 2 of the steel sheet piles 1, 1, a water-swellable rubber material 3 is placed at the front corner of the joint 2 of the steel sheet piles 1, 1 on both sides, as shown in FIG.
The water-swellable rubber material 3 is pressed against the front corner using the presser material 4, and the front surface of the gutter 5 of the rear steel sheet pile 1 and the side surface of the front steel sheet pile 1 adjacent thereto. Hand it over to touch it. Therefore, at appropriate locations, the receivers 11 of the presser washers 9 on both sides of the extension fitting a were engaged with the front inner corners of the pressers 4 on both sides, and the presser washers 9 were applied to the pressers 4, 4. After that, the pegs 17 are inserted into the nail holes 12 of the presser washer 9 on both sides and driven into the presser member 4.

その後、スパナをターンバツクルの係合部7
に嵌合してターンバツクルを一方へ回転させる
と、該ターンバツクルの左右反対方向の雌ねじ
1,82とボルト151,152との螺合によつて
伸長金具aが伸長し、その押え座金により
押え材4,4を外側へ押送つて水膨潤性ゴム材
3,3を継目部2,2に圧接させる。
Then, use the wrench to connect the engaging part 7 of the turnbuckle 6 .
When the turnbuckle 6 is rotated in one direction, the extension fitting a is extended by the screw engagement of the bolts 15 1 and 15 2 with the internal threads 8 1 and 8 2 of the turnbuckle 6 in opposite left and right directions. The pressers 4, 4 are pushed outward by the presser washers 9 , 9 , and the water-swellable rubber materials 3, 3 are brought into pressure contact with the joint portions 2, 2.

従つて、鋼矢板1,1の継目部2の隙間を水膨
潤性ゴム材3により密封するから、地下水が鋼矢
板1,1の継目部2より掘削箇所A内に流入する
のを防止される。
Therefore, since the gap between the joint 2 of the steel sheet piles 1 and 1 is sealed with the water-swellable rubber material 3, groundwater is prevented from flowing into the excavated location A through the joint 2 of the steel sheet piles 1 and 1. .

また、地下水が鋼矢板1,1の継目部2の隙間
を通つて水膨潤性ゴム材3に当ると、該水膨潤性
ゴム材3が膨張し、鋼矢板1,1の継目部2およ
び押え材4への圧接度を増してその継目部2にお
ける地下水の止水作用を助長する。
Further, when groundwater hits the water-swellable rubber material 3 through the gap between the joint 2 of the steel sheet piles 1, 1, the water-swellable rubber material 3 expands, and the joint 2 of the steel sheet piles 1, 1 and the presser foot are expanded. By increasing the degree of pressure contact with the material 4, the water-stop action of groundwater at the joint portion 2 is promoted.

なお、上記水膨潤性ゴム材3は表面を粗面とな
したものの方が好ましい。
Note that it is preferable that the water-swellable rubber material 3 has a rough surface.

一方、上記のターンバツクル、ボルト151
152、押え座金より成る伸長金具aと押え材
4とを一体に連結した構成になしてもよい。
On the other hand, the turnbuckle 6 , the bolt 151 ,
15 2 , the elongated metal fitting a consisting of the presser washer 9 and the presser member 4 may be integrally connected.

(考案の効果) この考案の鋼矢板用止水装置は、下記のような
顕著な効果を有する。
(Effects of the invention) The water stop device for steel sheet piles of this invention has the following remarkable effects.

(1) 鋼矢板を打込んでその建築物側を掘削した
後、該掘削箇所側において鋼矢板の継目部に水
膨潤性ゴム材を当て、それを伸長金具および押
え材により押圧して鋼矢板の継目部からの漏水
を防止するから、その施工が簡単で容易的確に
行うことができる。
(1) After driving steel sheet piles and excavating the building side, apply a water-swellable rubber material to the joints of the steel sheet piles on the excavated side, and press it with an extension fitting and holding material to remove the steel sheet piles. Since it prevents water from leaking from the joints, the construction is simple and can be carried out easily and accurately.

(2) 鋼矢板の継目箇所中で漏水する箇所だけに水
膨潤性ゴム材を当てて施工するから、その施工
箇所が少なくて資材および手数を節減して経済
的である。
(2) Since the water-swellable rubber material is applied only to the joints of steel sheet piles where water leaks, the number of construction points is small, which saves on materials and labor, making it economical.

(3) 伸長金具により両側の押え材を介して両側の
水膨潤性ゴム材を同時に鋼矢板の継目部に押圧
するから、その操作が簡単で、着脱を迅速にな
し得て作業上便利である。
(3) Since the water-swellable rubber material on both sides is simultaneously pressed against the seam of the steel sheet piles using the extension fittings via the holding members on both sides, the operation is easy and the attachment/detachment can be done quickly, making it convenient for work. .

(4) 水膨潤性ゴム材を使用するから、鋼矢板の継
目部の隙間を通つた地下水が水膨潤性ゴム材に
当ると、該水膨潤性ゴム材が膨張して鋼矢板の
継目部への圧接度を増し、その継目部における
地下水の止水作用を助長する。
(4) Since a water-swellable rubber material is used, when groundwater that has passed through the gap between the joints of steel sheet piles hits the water-swellable rubber material, the water-swellable rubber material expands and flows into the joints of the steel sheet piles. This increases the degree of pressure contact between the seams and facilitates the water-stopping effect of groundwater at the joints.

(5) 構造は簡単で、容易安価に製作できる。(5) The structure is simple and can be manufactured easily and inexpensively.

【図面の簡単な説明】[Brief explanation of the drawing]

第1部はこの考案の一実施例に係る鋼矢板使用
の山留壁の一部の正面図、第2図は拡大平面図、
第3図はその伸長金具の拡大正面図、第4図は平
断面図、第5図は第3図のI−I線断面図であ
る。 a……伸長金具、1……鋼矢板、2……継目
部、3……水膨潤性ゴム材、4……押え材。
Part 1 is a front view of a portion of a retaining wall using steel sheet piles according to an embodiment of this invention, and Figure 2 is an enlarged plan view.
3 is an enlarged front view of the elongated metal fitting, FIG. 4 is a plan sectional view, and FIG. 5 is a sectional view taken along the line I--I in FIG. 3. a... Extension metal fitting, 1... Steel sheet pile, 2... Joint portion, 3... Water-swellable rubber material, 4... Holding material.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 鋼矢板を使用した山留壁の掘削箇所側におい
て、隣接した鋼矢板の継目部に水膨潤性ゴム材を
当てた後、両側押え材の間に適当間隔で介装した
数個の伸長金具によりその両側押え材を両側の上
記水膨潤性ゴム材に当て、該水膨潤性ゴム材を上
記鋼矢板の継目部に圧接させてなる鋼矢板用止水
装置。
At the excavation site side of a retaining wall using steel sheet piles, after applying water-swellable rubber material to the joint between adjacent steel sheet piles, use several extension fittings interposed at appropriate intervals between the retaining materials on both sides. A water stop device for steel sheet piles, in which the pressers on both sides are applied to the water-swellable rubber materials on both sides, and the water-swellable rubber materials are brought into pressure contact with the joints of the steel sheet piles.
JP14028287U 1987-09-14 1987-09-14 Expired JPH0421869Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14028287U JPH0421869Y2 (en) 1987-09-14 1987-09-14

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14028287U JPH0421869Y2 (en) 1987-09-14 1987-09-14

Publications (2)

Publication Number Publication Date
JPS6447841U JPS6447841U (en) 1989-03-24
JPH0421869Y2 true JPH0421869Y2 (en) 1992-05-19

Family

ID=31404311

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14028287U Expired JPH0421869Y2 (en) 1987-09-14 1987-09-14

Country Status (1)

Country Link
JP (1) JPH0421869Y2 (en)

Also Published As

Publication number Publication date
JPS6447841U (en) 1989-03-24

Similar Documents

Publication Publication Date Title
US7900418B2 (en) Method for post-installation in-situ barrier creation
CN106703084A (en) Waterproofing treatment method and system of construction joint structure of plane and elevation structure junction areas of basement
JP2001348862A (en) Cut-off structure for steel sheet pile joint part, impervious revetment structure and construction method
US4970835A (en) Wall anchoring device and method of installation
JPH0421869Y2 (en)
US2239989A (en) Sealing means for use in grouting vertical seams in sea walls or the like
JPH0813719A (en) Horizontal drain for drainage of building and its installing structure
JPH02296914A (en) Construction method for row of steel pipe pile
JPH1046762A (en) Drain discharge gutter material and floor of outdoor corridor with drain discharge gutter
JP2003020640A (en) Steel pipe column soil retaining wall, method of constructing the retaining wall, and water cut-off member used for the method
JP6776683B2 (en) Gap water stop structure, gap water stop method and member with tubular body
JP2767023B2 (en) Device for removing infiltrated groundwater in thermal storage tanks
CN216515750U (en) Combined device for accurately fixing water stop of box culvert by adopting U-shaped clamp
CN1083518C (en) Quick leak-blocking technology by pouring and filling of polyurethane
JP3003786U (en) Internal water stop band
RU215958U1 (en) REPAIR WATER SPIN FOR COLD JOINTS
JPH0324526B2 (en)
JP3002697B2 (en) External waterproof sheet laying method for continuous underground wall
JP2807587B2 (en) Water sheet for steel sheet pile and ground excavation method
KR200201192Y1 (en) Rubber packing
JP2001026937A (en) Manhole joint and its connecting work method
JPS5841229Y2 (en) Steel plate for earth retaining
JP2801379B2 (en) Underground wall spring treatment structure
JP2004197399A (en) Cutoff joint device in steel pipe column earth retaining wall
JP3253055B2 (en) Water stop device at reaching part in shield method